Work Breakdown Structure Element Dictionary Construction
|
|
|
- Elvin Clarke
- 9 years ago
- Views:
Transcription
1 Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor and execution of a construction contract. The lead office develops these project parameters as project baseline documents in the early stages of. The baseline documents serve to help manage the project s development. Advertisement CON Advertisement is the public announcement, as required by law, which invites bids for construction work to be performed. Advertising Memo CON The Bureau of Management shall prepare the Advertising Memo and send it to the Bureau of Services Procurement by FAX or no later than the Friday before the scheduled advertisement date. BidX Posting CON The Bureau of Services Procurement shall post the project within BidX, the Department's electronic bidding process program, to allow for the submission of bids. Goals CON The EEO Special Provisions, DBE, SBE or ESBE Goals shall be included as part of the Special Provisions within the Advertising Package. Notification of Approval to Advertise CON The Project Manager and Bureau of Services Procurement shall be notified upon receiving the approval to Advertise. Local Paper Advertisement CON The Bureau of Services Procurement shall post the advertisement for construction bids within the local newspapers. Addenda CON Addenda are contract revisions or responses to a Contractor's inquiry issued after advertisement and before the opening of bids. BidX Posting of Addenda CON The Capital Program Support - Program Systems Management shall post the project addenda within BidX, the Department's electronic bidding process program, to allow bidders to electronically acknowledge the posted addenda. Contractor Addenda Acknowledgement CON The Bidder shall acknowledge all addenda posted through the Department's electronic bidding process program before the opening of bids. The Department will not accept the bid if the Bidder has not acknowledged all addenda posted. Revision 2 Pg 1 of 8 Released: 02/2016
2 Bids CON Bids are the submissions by contractors that outline each contractor's proposed cost for completing the advertised work. Bids also include the process by which the Department manages the submission of bids for advertised work from an individual, firm, or corporation. Certified Bids CON After bids are received on an individual project, the Bureau of Services Procurement certifies the individual bid prices that make up each contractor s total bid. The Office of Information Technology group then loads this information onto the Mainframe Computer. Once this has been completed, Management produces a Line Item Profile Report for that project for use in the bid analysis if needed. Management also files a hard copy into the Master Line Item Profile files. Bid Tabulation CON The Bureau of Services Procurement shall organize and tabulate the bids so that they are ranked by cost and can be compared across bid items. Bid Analysis CON The Department reviews bids for conformity with the Contract and compares bids on the basis of the correctly determined summation. The Department makes the total bid amount for all bids available. Pre-Bid Meeting Minutes CON The Regional Engineer or designee will record, transcribe and complete the meeting minutes for distribution within ten (10) working days of the meeting to all attendees. The Project Manager will review a draft of the minutes prior to distribution to ensure that the information presented was properly understood. Awarded Contract CON The contract is awarded to the lowest bidder. The Project Manager sends the award memo to the Bureau of Services Procurement announcing the selected Contractor. FHWA Certification CON FHWA certification shall be obtained on contracts with Federal-Aid funding awarded by the State. AD-12 to Execute Contract CON The AD-12 is the Department Action Slip authorizing the execution of the contract. Award Web Posting CON The Bureau of Services Procurement shall post on the Department's website the results of the bid selection process. Revision 2 Pg 2 of 8 Released: 02/2016
3 Performance and Payment Bonds CON A performance bond and a payment bond shall be provided to the Department within 15 days of the date of Award or Conditional Award. Ensure that the penal sum of the bond is equal to at least the Total Contract Price less the bid price for Performance and Payment bond. With the bond, provide a certification authorizing the attorney-in-fact to commit the Surety and a true and correct statement of the Surety s financial condition. Submit the broker s fees, the certified rate schedule, and the report of execution for the bond to the Resident Engineer. Contractor Award Notification CON The Bureau of Services Procurement shall notify the selected Contractor of the Department's selection. Signed Contract CON Within 14 days of the date of Award or Conditional Award, the Bidder shall properly and duly sign the Contract. Notice To Proceed CON Notice to Proceed is a Department document that authorizes the contractor to start construction activities. Operations CON 5.2 Operations includes the physical construction of work done in the performance of the Contract within the Project Limits. Pre- Meeting Minutes Pre- ITS Meeting Minutes CON The Pre- Meeting is the meeting between the Department, the winning Contractor and other key stakeholders that provides a project overview and establishes initial project contacts. CON The Pre- ITS Meeting is for projects that include installation of ITS facilities. Attendees include the winning Contractor, the Sub-Contractor for ITS work, Bureau of ITS Engineering, Bureau of Traffic Operations, Regional and other key stakeholders. Daily/Weekly Reports CON The Resident Engineer has the responsibility for ensuring that the Daily Report Form (DC-3b) and weekly Progress Report Form (DC-24), or Resident Engineer's Bi-Weekly Progress Report (DC-156) is completed using the Automated Estimate System (ACES) as per procedure. Monthly Progress Estimates CON The Resident Engineer is responsible for completing Monthly Progress Estimates within the Automated Estimate System (ACES) that track progress of the Contractor and subcontractors. Revision 2 Pg 3 of 8 Released: 02/2016
4 Working Drawings CON Working Drawings are technical plans on a construction project that are prepared by the Contractor to illustrate items not included within the Contract Documents. Working Drawings shall include methods of construction, material designations, design calculations, catalogue cuts, illustrations, schedules, performance charts, brochures, and other information necessary to construct the work as specified in the Contract. Changes CON The Department has the right to make changes to the Work at any time, including altering the Contract, altering the requirements of an Item, increasing or decreasing the quantities of any Item, or deleting any Item. Such changes neither invalidate the Contract, nor release the Surety. The Contractor agrees to perform the work as changed. Changed Field Conditions CON Changed Field Conditions includes contractual changes based on existing field conditions. Design Changes CON Design changes are made based on field observations that may be requested by Regional Engineering forces, the Resident Engineer, or the Contractor. Value Engineering Requests CON Value Engineering Requests include a proposal or concept submitted by the Contractor in accordance with Subsection of the Contract Specifications for changing the plans, the specifications, or other requirements of the contract. Orders CON Orders include any change of scope, design or specifications that the Department, Regional Engineer, Field Manager, or Resident Engineer may request of the Contractor. Field Orders CON Field Orders are direction given to a Contractor to proceed with work. Change Orders CON Change Orders are written orders from the Department provided to the Contractor that modifies the Contract. Utility Change Orders CON Utility Change Orders are Master Agreement Change Orders that are submitted to Project Management for execution. The Project Manager assures the Master Agreement Change Order is complete, transmitting the Change Order through the chain of command for approval and execution, and distributing the executed document to the Utility Owner. Resolution of Disputes and Claims CON Resolution of disputes and claims is composed of the following four steps: Step 1 - Review by the Resident Engineer/Project Manager; Step 2 - Review by the Regional Dispute Board; Step 3 - Review by the Department Claims Committee; Step 4 - Nonbinding Mediation. Revision 2 Pg 4 of 8 Released: 02/2016
5 Design Communications Report CON The Design Communications Report is established for the project in Concept Development and receives continual updates throughout the remainder of the project s development, through the, to document coordination efforts completed for the project, and the guidance and decisions associated with those efforts. Traffic Interference Notices CON The Contractor has to provide the Resident Engineer notice for traffic interference. There are a few different types of notice: The Contractor has to provide a 28 day, 14 day and 7 day notice for all traffic changes - usually meaning a major traffic stage. There would be such a notice for the first time traffic was interfered with, for each stage change, and for the final traffic pattern. With the 28 day notice, the Division of Community and Constituent Relations contacts local stakeholders (municipalities) and gives them notification. At 14 days, messages are placed on Portable Changeable Message Signs. With each notice received by the Contractor, the Resident Engineer - passes the information along to Traffic Operations and the Traffic Interference Coordinator (TIC) to disseminate the information to Senior Management. Additionally, the Contractor has to provide weekly and daily notices for lane closures. On a project basis, this may involve a permanent closure with a detour, but on a daily basis may also involve a right lane closure for a portion of a highway. The Contractor gives the Resident Engineer a weekly notice and a daily confirmation of what they're doing - that info gets sent to Traffic Operations and the TIC, so they know who's out on the road and how they're interfering with traffic at any time. Approved Annual Financial Plan (Major Projects) Environmental Permit Notifications CON An Approved Annual Financial Plan (Major Projects) includes the updated and FHWA approved Project Financial Plans for Major Projects, as required by FHWA regulations. In accordance with FHWA regulations, a Financial Plan must be completed for a project that is estimated to cost $100,000,000 or more. CON A Notice of is sent by the Office of Environmental Solutions to the environmental permitting agencies. Revision 2 Pg 5 of 8 Released: 02/2016
6 Updated Risk Register CON A Risk Register is a tool that the Project Risk Manager and Project Risk Team Members can use to address and document project risks throughout the project life cycle. It is a living document that includes a comprehensive listing of risks and the manner in which they are being addressed. It is updated throughout the life of the project whenever new risks are identified or response action plans are modified. Quality Management CON 5.3 Quality Management encompasses deliverables associated with the development and implementation of quality management plans, and identifies actions that must be taken to obtain a project s quality assurance certification. Quality management plans may take the form of plans that are part of a consulting firm s prequalification requirements, or may be projectspecific plans that are prepared for more complex projects. Contractor Evaluations CON Contractor Evaluation is performed by the Resident Engineer on a yearly basis. It provides an objective, consistent method for measuring consultant performance. Inspections CON Inspections include the interim completion, substantial completion, final completion and final acceptance inspections. Inspections shall be conducted at their respective project completion milestones and conducted by the appropriate inspection body. Substantial Completion Inspection CON Substantial Completion Inspection is the review and inspection of the entire project by the Field Manager and Resident Engineer after receipt of the Contractor's notice of Substantial Completion. Final Acceptance Inspection CON Final Acceptance Inspection is the review and inspection of the work that required corrective actions as identified during the Corrective Action Inspection. Communications CON 5.4 Communications encompasses deliverables associated with communicating project information to internal and external project stakeholders, such as public officials, the general public, outside agencies, internal management, subject matter experts, and project consultants. Public Outreach Meeting Minutes CON Internal Core Group coordination meetings and external local officials and agency coordination meetings may be necessary during. Revision 2 Pg 6 of 8 Released: 02/2016
7 Project Briefing Meeting Minutes CON Project briefings may be held if necessary during the at the start of a new construction stage if significant traffic stages/traffic impacts are planned. A project briefing would be held with the Department s Senior Management to provide an executive summary of the planned traffic detours, control, and construction staging. The main purpose of the briefing is to inform Senior Management on the upcoming traffic stage, to provide an update on the current status of community reaction, and to present the community involvement activities planned during construction. Completion CON 5.5 Completion includes the series of action items that shall be performed to obtain final approvals and achieve project closeout. FHWA Required Documents CON There are several required documents that must be sent to FHWA, which include: Original LB-96 Material Certification; Original fully executed Final Order without attachments but with the final cost sharing distribution (DC-17/174); Original DC-123 Contractor's Final Certification of Compliance; Copy of the final Certification of Cost; Copy of the AD-12 Department of Action Slip (Accepting the Project); Form FA-8 - Contractor's Statement of Materials and Labor; and written confirmation that the Final Inspection Deficiencies noted by the FHWA have been corrected, if applicable. Traffic Regulation Orders CON The Traffic Regulation Order (TRO) is a legal order, which allows us to regulate the speed, movement and parking of vehicles and regulate pedestrian movement, which are enforceable by law. As-Built Plans CON As-built plans are a set of drawings that represent the actual built environment upon completion of the project, which also lists the quantities and contract items. As-Built Summary (DC-104) CON The As-Built Summary (DC-104), completed by the Resident Engineer, lists the as-built quantities to assist in preparation of the as-built plans. The As-Built Summary also lists the original Contract Quantities to be compared to the as-built quantities. Certification of Completion (DC- 20) CON The Certification of Completion (DC-20) is the form prepared by the Regional office at the request of the Resident Engineer that certifies to the Contractor that the project is contractually complete. Revision 2 Pg 7 of 8 Released: 02/2016
8 Designer Final Invoice CON The Project Manager requests the consultant designer submit a Final Invoice to close out the PE phase of work. Inspection Consultant Final Invoice CON The Bureau of Regional Engineering requests the inspection consultant to submit their Final Invoice for construction inspection services. Final Audit CON All claims filed and force account work are subject to audit at any time following the filing, whether or not part of a suit pending in the courts of this State pursuant to N.J.S.A. 59:13-1, et seq. The audit may begin after the Department has given 15-day notice to the Contractor, subcontractor, or supplier. If an audit is to be commenced more than 60 days after Acceptance, the Department will provide the Contractor with reasonable notice of the time when such audit is to begin. Revision 2 Pg 8 of 8 Released: 02/2016
CONTRACT ADMINISTRATION. Procedures
CONTRACT ADMINISTRATION Procedures Check the Capital Project Delivery web site to ensure this is the current version. Index Section Page Introduction 1 Contract Administration Final Design PS&E / Advertising
ADVERTISING, SALE & AWARD
ADVERTISING, SALE & AWARD PRIMARY ROLES & RESPONSIBILITIES PRIMARY TASK ODOT LPA DEVELOP BID PROPOSAL If project estimate exceeds $500,000, submit engineer estimate to LPA Coordinator to obtain DBE goal.
Getting Connected with the Colorado Department of Transportation (CDOT)
Getting Connected with the Colorado Department of Transportation (CDOT) INTRODUCTION Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges State government agency with funding
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Document A101 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the in the year (In words, indicate day, month and year.)
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
Chapter 10 - Contract Completion
Chapter 10 - Contract Completion Construction Manual 1-1000 General This Chapter contains guidelines that are followed on projects inspected and administered by the Department and its construction engineering
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
Ocoee, FL July 01, 2016 Advertisement No. 1
BID SOLICITATION NOTICE Turnpike FLORIDA DEPARTMENT OF TRANSPORTATION CONSTRUCTION AND MAINTENANCE PROGRAMS Ocoee, FL July 01, 2016 Advertisement No. 1 All bids must be completed using Expedite Bid software
Purchases from $750 $1,500 requires 3 Verbal Quotes. Purchases from $1,501 $24,999 requires 3 Written Quotes
Introduction A Guide for Contractors and Suppliers The Purchasing Office should be your first point of contact with the County. Our role is to bring together users and suppliers to ensure that the County
15-213. Procurement practices of school districts and charter schools; definitions
ARIZONA AUTHORITY 15-213. Procurement practices of school districts and charter schools; definitions A. The state board of education shall adopt rules prescribing procurement practices for all school districts
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
PROJECT MANAGEMENT BASICS
PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the
ORDINANCE NO.------- THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:
ORDINANCE NO.------- An ordinance authorizing the award of one design-build contract for the decommissioning, disablement, demolition and removal of Scattergood Generating Station Unit 3 pursuant to a
Project Management Procedures
1201 Main Street, Suite 1600 Columbia, South Carolina 29201 Project Management Procedures Start Up The grant becomes effective upon return of one copy of the grant award executed by the Chief Executive
Handbook No. 7460.8 REV 2 CHAPTER 6. SEALED BIDS
CHAPTER 6. SEALED BIDS Handbook No. 7460.8 REV 2 6.1 General For all PHA contracting requirements above the small purchase threshold, competitive procurements are conducted by inviting sealed bids or by
CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS
CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS 48-01.2-01. Definitions. In this chapter, unless the context otherwise requires: 1. "Agency construction management" means a public improvement delivery
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
DENVER URBAN RENEWAL AUTHORITY GUIDELINES FOR UTILIZATION OF SMALL BUSINESS ENTERPRISES IN URBAN REDEVELOPMENT PROJECTS.
DENVER URBAN RENEWAL AUTHORITY GUIDELINES FOR UTILIZATION OF SMALL BUSINESS ENTERPRISES IN Policy Statement URBAN REDEVELOPMENT PROJECTS November 2014 The Denver Urban Renewal Authority ("DURA") has determined
CHAPTER 7 PUBLIC PURCHASES, PURCHASE OF LAND OR STRUCTURES AND INVENTORY OF FIXED ASSETS
7-1 CHAPTER 7 PUBLIC PURCHASES, PURCHASE OF LAND OR STRUCTURES AND INVENTORY OF FIXED ASSETS The "Public Purchasing Law" applies to every expenditure of public funds by a governmental body, unless specifically
How To Get Construction Procurement Services
Construction Procurement William C. Charvat, AIA, CSI Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 The procurement of construction services brings together the team
University Of New Hampshire Transportation Services. Disadvantaged Business Enterprises
University Of New Hampshire Transportation Services Disadvantaged Business Enterprises Table of Contents Program Objectives/Procedures Statement..3 Non Discrimination Clause.4 Record Keeping Requirements...4
ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects
Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT CONSTRUCTION AUDIT PROGRAM
GENERAL: Some of the Districts largest capital expenditures are from new construction, facility upgrades, and renovations. A single project can run into the millions of dollars, involving engineering,
TABLE OF CONTENTS. Prefacej... 1
TABLE OF CONTENTS Prefacej... 1 How Can I Receive Copies Of Solicitations?j... 2 Bidder s List... 2 Vendor Registration System... 2 Public Notice/Advertisement... 3 Posting... 3 Internet... 3 Pre-Bid Conferences...
Procedure Manual. Title: Small Disadvantaged Business Program. A6Hx2-6.36 Page: Page 1 of 5. Policy Number: 6Hx2-6.36
Page 1 of 5 I. Small Disadvantaged Business (SDB) Overall Participation. Broward College has established goals to assist the College in increasing overall SDB participation. The commodity/service classifications
Ocoee, FL May 13, 2016 Advertisement No. 1
BID SOLICITATION NOTICE Turnpike FLORIDA DEPARTMENT OF TRANSPORTATION CONSTRUCTION AND MAINTENANCE PROGRAMS Ocoee, FL May 13, 2016 Advertisement No. 1 All bids must be completed using Expedite Bid software
COUNTY OF DUTCHESS OFFICE OF CENTRAL AND INFORMATION SERVICES DIVISION OF CENTRAL SERVICES 27 HIGH STREET POUGHKEEPSIE, NEW YORK 12601 (845) 486-3670
COUNTY OF DUTCHESS OFFICE OF CENTRAL AND INFORMATION SERVICES DIVISION OF CENTRAL SERVICES 27 HIGH STREET POUGHKEEPSIE, NEW YORK 12601 (845) 486-3670 The Division of Central Services has developed this
LOCAL AGENCY CONTRACT ADMINISTRATION CHECKLIST
LOCAL AGENCY CONTRACT ADMINISTRATION CHECKLIST The following checklist has been developed to ensure that all required aspects of a project approved for Federal funding have been addressed and a responsible
Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.
The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most
July 5, 2016 FAILURE TO RETURN THIS BID ADDENDUM IN ACCORDANCE WITH INSTRUCTIONS MAY SUBJECT YOUR BID TO REJECTION ON THE AFFECTED ITEM(S):
STATE OF NORTH CAROLINA DEPARTMENT OF ADMINISTRATION OFFICE OF FISCAL MANAGEMENT IMPORTANT BID ADDENDUM July 5, 2016 FAILURE TO RETURN THIS BID ADDENDUM IN ACCORDANCE WITH INSTRUCTIONS MAY SUBJECT YOUR
MEDICAL CAPTIVE INSURANCE COMPANY PROCUREMENT POLICIES AND PROCEDURES
MEDICAL CAPTIVE INSURANCE COMPANY PROCUREMENT POLICIES AND PROCEDURES GOVERNMENT OF THE DISTRICT OF COLUMBIA OFFICE OF RISK MANAGEMENT 441 Fourth Street, NW Suite 800 South Washington, DC 20001 Phone:
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically
ITS Change Management Guidelines
ITS Change Management Guidelines Revision 3.0 Original drafted March 5, 2002 Revision 3.1 Version Update November 28, 2011 Revision 3.2 Version Updated February 24, 2012 Revision 3.3 Current Version Updated
Bureau of Recreation and Conservation (BRC) Administrative Policy/Grant Guidelines
COMMONWEALTH OF PENNSYLVANIA Department of Conservation and Natural Resources Bureau of Recreation and Conservation (BRC) Administrative Policy/Grant Guidelines SUBJECT: Development Project Management
Request for Proposal/Invitation for Bid Guidelines
Request for Proposal/Invitation for Bid Guidelines 1.0 Purpose These guidelines outline the preparation and evaluation of an Invitation for Bid (IFB)/Request for Proposal (RFP). The guidelines are effective
Replacement of Heat System Components
STATEMENT OF WORK FOR Replacement of Heat System Components At Warehouse Takoraudantie 4 08/17/2013 REV 8-24-13 Project 2013-021 Page 1 of 6 1.0 INTRODUCTION 1.1 Overview: The U.S. Embassy Helsinki has
TABLE OF CONTENTS. Purchasing and Contracts Division... 1. Purchasing Policies and Procedures... 1. The Competitive Process... 2
TABLE OF CONTENTS Title Page Purchasing and Contracts Division... 1 Purchasing Policies and Procedures... 1 The Competitive Process... 2 Vendor Participation... 2 Vendor Database... 2 Web Site Information...
Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way
Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org HILLSBOROUGH COUNTY Office of the County
Facilitating Local Hiring on Transportation Projects: A Recommendation for the Surface Transportation Authorization. Overview
Facilitating Local Hiring on Transportation Projects: A Recommendation for the Surface Transportation Authorization Prepared by: Center for Community Change, Gamaliel Foundation, Green for All, Partnership
Nebraska Public Schools: Statutes Related to the Construction of Improvements to Real Property
Nebraska Public Schools: Statutes Related to the Construction of Improvements to Real Property 73-101. Public lettings; how conducted. Whenever the State of Nebraska, or any department or any agency thereof,
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
INDOT Professional Services Contract Administration Manual Vers. 1/9/15
INDOT Professional Services Contract Administration Manual Vers. 1/9/15 Table of Contents Chapter 1 Consultant Contracting General... 1 Introduction... 1 1.1.1 Determination of Need... 1 1.1.2 Initiation
Welcome to the City of Chicago. Department of Procurement Services. Rahm Emanuel, Mayor Jamie Rhee, Chief Procurement Officer
Welcome to the Bid & Bond Room Rahm Emanuel, Mayor Jamie Rhee, Chief Procurement Officer The remains committed to the growth and development of small, minority and women-owned business enterprises and
Request for Expression of Interest (EOI) Contract Assembly & Management System (s) (CAMS)
Request for Expression of Interest (EOI) Contract Assembly & Management System (s) (CAMS) 1. Introduction: The Washington Metropolitan Area Transit Authority (METRO) seeks industry information about commercial
Policy Number: 3-804 Policy Name: Professional Services and Construction Services Procurement
Page 1 3-804 Professional Services and Construction A. Project Delivery Methods 1. A university may procure design services, construction and construction services, as applicable, under any of the following
HOW TO DO BUSINESS WITH THE STATE OF ALASKA
State of Alaska Department of Administration Division of General Services HOW TO DO BUSINESS WITH THE STATE OF ALASKA REVISED AUGUST 2013 PREPARED BY THE DIVISION OF GENERAL SERVICES, PURCHASING SECTION:
Construction Contract Administration Guide
Construction Contract Administration Guide Version 1.0 August 2014 Construction Contract Administration Guide ISSUE AND REVISION RECORD Version / Revision Date Sections / Pages Comments 1.0 August 2014
CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
NEW JERSEY ADMINISTRATIVE CODE Copyright 2015 by the New Jersey Office of Administrative Law
Page 1 NEW JERSEY ADMINISTRATIVE CODE Copyright 2015 by the New Jersey Office of Administrative Law *** This file includes all Regulations adopted and published through the *** *** New Jersey Register,
IEC Electronics Terms and Conditions
IEC Electronics Terms and Conditions 1. General: This Purchase Order is placed subject to these terms and conditions including those within the Purchase Order. The terms of any proposal referred to in
HOW TO DO BUSINESS WITH THE CITY OF WICHITA KANSAS FINANCE DEPARTMENT PURCHASING
HOW TO DO BUSINESS WITH THE CITY OF WICHITA KANSAS FINANCE DEPARTMENT PURCHASING We appreciate your interest in doing business with the City of Wichita. We want to assure you of our interest in seeing
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal
a. Proposals shall be submitted in a sealed envelope and addressed as follows:
1 CITY OF ATCHISON REQUEST FOR QUALIFICATIONS & PROPOSAL HVAC SERVICES JANUARY 1, 2014 THROUGH DECEMBER 31, 2014 DUE: DECEMBER 10, 2013 10:00 A.M. The City of Atchison (City) invites interested and qualified
AGREEMENT BETWEEN THE CITY OF BEVERLY HILLS AND VENDOR TBD FOR PURCHASE AND INSTALLATION OF AUTOMATED LICENSE PLATE RECOGNITION SYSTEMS
AGREEMENT BETWEEN THE CITY OF BEVERLY HILLS AND VENDOR TBD FOR PURCHASE AND INSTALLATION OF AUTOMATED LICENSE PLATE RECOGNITION SYSTEMS NAME OF CONTRACTOR: RESPONSIBLE PRINCIPAL OF CONTRACTOR:, Vendor
Anglo American Procurement Solutions Site
Anglo American Procurement Solutions Site Event Terms and Conditions Anglo American Procurement Solutions Site Event Terms and Conditions Event Terms and Conditions 3 1. Defined terms 3 2. Interpretation
How To Get A Job Done
CUMBERLAND COUNTY COMMUNITY DEVELOPMENT (CCCD) HOUSING REHABILITATION PROGRAM PO DRAWER 1829 707 EXECUTIVE PLACE FAYETTEVILLE, NC 28302-1829 CONTRACTOR QUALIFICATIONS: REHABILITATION CONTRACTOR'S HANDBOOK
Construction Change Orders
Construction Change Orders Michael E. Purdy Contracts Manager University of Washington (206) 221-4235 [email protected] 1 Agenda Tools to Prevent Change Orders 4 Elements of Change Orders Authorization
Contractor s Guide. April 2016
Contractor s Guide April 2016 The Minnesota Housing Finance Agency does not discriminate on the basis of race, color, creed, national origin, sex, religion, marital status, status with regard to public
CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE
CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE STATE OF IDAHO DEPARTMENT OF ADMINISTRATION DIVISION OF PURCHASING REVISED 01 01 14 Table of Contents I. Purpose... 1 II. Overview of Contract Management and
VDOT Prequalification. Suzanne Lucas Construction Division
VDOT Prequalification Suzanne Lucas Construction Division VDOT Prequalification for Highway Contractors in the Commonwealth of Virginia 2 What is Prequalification? AASHTO defines a prequalification system
NOTICE TO POTENTIAL BIDDERS
NOTICE TO POTENTIAL BIDDERS Downloading the Plans, Specifications and other Bid Documents will NOT place you on the City s List of Plan Holders. This is important because only those on the City s List
DEMO Version. Owner and Contractor OCNMP103
Page 1 of 12 AGREEMENT made as of the in the year of (In words, indicate day, month and year) day of BETWEEN the Owner: (Name, address and other information) DEMO Version and the Contractor: (Name, address
STATEWIDE SB/DVBE ADVOCATE TOOLKIT. Chapter V
STATEWIDE SB/DVBE ADVOCATE TOOLKIT Small Business Program Chapter V February 2012 CHAPTER V SMALL BUSINESS PROGRAM CALIFORNIA BUSINESSES AND THE SMALL BUSINESS PROGRAM Thriving California small businesses
PROCUREMENT STANDARD OPERATING PROCEDURES (SOP)
PROCUREMENT STANDARD OPERATING PROCEDURES (SOP) TABLE OF CONTENTS 1. RESPONSIBILITY 1.1 Responsibility for Acquisition 1.2 Responsibility for Procurement Planning 2. REQUISITION 2.1 Requisitions for Supplies,
Project Management On-line Guide
Project Management On-line Guide Project Life Cycle Processes Flowchart Department Policy Memorandum Project Management Policy To support the Project Management Initiative, respond to Policy Agreement
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
USING THE ROAD MAINTENANCE AGREEMENT TEMPLATE
USING THE ROAD MAINTENANCE AGREEMENT TEMPLATE The Ministry of Government Relations has created a draft Road Maintenance Agreement template for municipalities and industry to use cooperatively. The primary
Request for Proposal
Request for Proposal Design, Build, Lease Rooftop Solar PV System RFP# 14-2015 Calabogie Community Rink, 574 Mill Street, Calabogie, Ontario Proposal Closing Date: September 25, 2015; 2:00 PM Local Time
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Section 000 Organization of an Engineering District (Construction)
Table of Contents 1. General Policies and Provisions... 000-1 2. District Executive... 000-2 3. Assistant District Executive Design... 000-3 4. Assistant District Executive Maintenance... 000-4 5. Assistant
RURAL UTILITIES SERVICE
Rural Development United States Department of Agriculture RURAL UTILITIES SERVICE RUS Bulletin 1738-2 Rural Broadband Access Loan and Loan Guarantee Advance and Construction Procedures Guide Page 1 According
CITY OF MESA, ARIZONA ENGINEERING DEPARTMENT REQUEST FOR QUALIFICATIONS
CITY OF MESA, ARIZONA ENGINEERING DEPARTMENT REQUEST FOR QUALIFICATIONS On-Call Consultant List for Mechanical Engineering Services TABLE OF CONTENTS REQUEST FOR QUALIFICATIONS PAGE NO. SECTION I PROJECT
Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015
Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 For PROJECT : Renovation and Repair of Atlanta Jewish Academy
Request for Proposals (RFP) Communications Services RFP #CS-PY 15-I September 17, 2015
Request for Proposals (RFP) Communications Services September 17, 2015 PURPOSE Opportunity Inc. of Hampton Roads (OppInc.) seeks a communications consultant (the Consultant) to provide Communications Services
TITLE 11. DEPARTMENT OF BANKING AND INSURANCE - DIVISION OF INSURANCE CHAPTER 2. INSURANCE GROUP SUBCHAPTER 33. WORKERS' COMPENSATION SELF-INSURANCE
TITLE 11. DEPARTMENT OF BANKING AND INSURANCE - DIVISION OF INSURANCE CHAPTER 2. INSURANCE GROUP SUBCHAPTER 33. WORKERS' COMPENSATION SELF-INSURANCE 11:2-33.1 Purpose and scope (a) This subchapter sets
ITS specification Handover and commissioning process (ITS-10-01)
ITS specification Handover and commissioning process (ITS-10-01) NZ Transport Agency Effective from September 2011 Copyright information This publication is copyright NZ Transport Agency (NZTA). Material
Procedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14
Procedures for Tenders and Contracts October 2014 Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Huon Valley Council Procedures for Tenders and Contracts October 2014
INVITATION TO BID FOR FC-7314 ANNUAL CONTRACT FOR SMALL WATER METER INSTALLATIONS
INVITATION TO BID FOR FC-7314 ANNUAL CONTRACT FOR SMALL WATER METER INSTALLATIONS City of Atlanta Jo Ann J. Macrina, PE Commissioner Department of Watershed Management Adam L. Smith, Esq., CPPO, CPPB,
RESOLUTION NO. 15-2012
RESOLUTION NO. 15-2012 APPROVING THE GUIDELINES FOR THE ESTABLISHMENT OF NEGATIVE LIST OF SURETY AND/OR INSURANCE COMPANIES WHEREAS, pursuant to Section 63 of RA 9184 and its IRR, it is the Government
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,
Purchasing and Contracts Request for Proposal Procedure
Purchasing and Contracts Request for Proposal Procedure F.P.02.PR.3 Request for Proposal Procedures..2 F.P.02.PR.3.1 Commitment to Supplier Diversity...2 F.P.02.PR.3.2 Process Overview... 2 F.P.02.PR.3.3
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES This Master Agreement made this 11 day of December, 2012, by and between the St. Lucie County School Board (hereinafter referred to as the School Board
Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of
TM Document A101 2007 Instructions Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum GENERAL INFORMATION Purpose. AIA Document A101 2007 is intended
CHAPTER 5 SMALL PURCHASES
PIM 98-033 CHAPTER 5 SMALL PURCHASES In this Chapter look for... 5. General 5.1 Competitive Requirements 5.2 Charge Cards for Small Purchases (Deleted) 5.3 Single Quotation 5.4 Deleted 5.5 Deleted 5.6
The University of North Carolina Plan to Increase Utilization of Historically Underutilized Businesses in Construction Projects
The University of North Carolina Plan to Increase Utilization of Historically Underutilized Businesses in Construction Projects May 2002 1 of 15 The University of North Carolina Office of The President
Bay. Region Design- US-10. June 13, 2014
REQUEST FOR QUALIFICATIONS MICHIGAN DEPARTMENT OF TRANSPORTATION Bay Region Design- Build Project US-10 over I-75 Job Numbers: 122868 Control Section: 09034 Original Issue June 13, 2014 TABLE OF CONTENTS
2.3.9 Construction Procurement
2.3 Management of the Project 2.3.9 Construction Procurement 2.3.9 Canadian Handbook of Practice for Architects Introduction Obtaining Bids Open Competitive Bids (or Public Tender Call) Invited Competitive