Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way
|
|
|
- Christiana King
- 9 years ago
- Views:
Transcription
1 Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org
2 HILLSBOROUGH COUNTY Office of the County Administrator ADMINISTRATIVE DIRECTIVE #CS-04 SUBJECT: EFFECTIVE DATE: UTILITY COORDINATION PROCEDURES FOR HILLSBOROUGH COUNTY CONSTRUCTION PROJECTS WITHIN COUNTY RIGHTS-OF-WAY EXPIRATION DATE: SUPERSEDES: PURPOSE: The Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way contains the approved coordination procedures and guidelines to accomplish necessary actions related to County construction projects. When implemented properly, these procedures and guidelines will ensure early advanced planning actions and establish working relationships between County departments, designers, and utility agencies and other rights-of-way users. DIRECTIVE: The Hillsborough County Public Works Department, with assistance from the Public Utilities Department, and the Parks, Recreation and Conservation Department, shall update the manual for Utility Coordination Procedures for Hillsborough County Construction Projects Within County Rights-of-Way. This manual establishes utility coordination procedures for the planning/pre-design, design, rights-of-way determination and acquisition, bidding, and construction phases for County projects. Utilizing these procedures will result in clarity in bids and commitments between the County, contractors, and utility agencies concerning inter-related construction work schedules. The County Administrator approves and adopts these Utility Coordination Procedures for Hillsborough County Construction as the County s guide for all Hillsborough County Departments and Organizations. The Public Works Department is authorized to distribute the Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-way manual and any future revisions. RESPONSIBILITY: Public Works Department APPROVED: Michael S. Merrill County Administrator Date October 2015 Page i
3 PREFACE This manual: Describes in detail applicable procedures intended to provide the earliest liaison on a routine basis to ensure that all parties potentially affected by County Capital Improvement Program (CIP) projects share the same knowledge about these projects. These procedures are to be followed for all County Construction projects inside the Rights-of-Way, including accelerated or fast track projects. Provides advanced planning actions necessary to promote exchange of technical data, which can affect choices of alternate schemes that may benefit public users. Establishes design practices that facilitate development of a cohesive working relationship between Designers and Utility Agency Owner(s) (UAO), which allows for custom features and design considerations, and helps ensure that all known utility issues are addressed and utilities are relocated properly prior to and during construction. Establishes procedures for Preliminary Design and Engineering (PD&E) design, funding, rightsof-way determination and acquisition, bidding, and construction phases. These procedures are intended to result in clarity of bids and commitments between contractors and UAO concerning working schedules. These procedures are in place to clarify the responsibilities of each party and ensure proper communication, cooperation, and coordination, which is crucial to minimization of utility conflicts and delay claims for Hillsborough County Projects. Minimization of such claims can result in cost savings. These procedures are intended to be utilized by all Hillsborough County Departments that are designing and constructing CIP projects within County Rights-of-Way. Although various County Departments may have CIP project delivery processes that vary from those contained in this document, or similarly, some portions of these procedures may not apply to a particular project, the overarching intent is for each Department to initiate and maintain effective procedures for coordinating the work being done by the County and the UAO for the duration of all CIP projects within County Rights-of-Way. Users of these procedures must be familiar with the Utility Accommodation Guide, which defines the policies and standards of Hillsborough County for accommodation of private and public projects as well as the permitting procedure for maintenance work within the County s public right-of-way; the glossary of terms contained at the end of these procedures will also contribute to understanding the purpose and intent of this manual. Each individual department is responsible for working with and providing information to all UAO s. As material specifications, technical criteria and County polices change to meet new needs and changing technology, it will become necessary to revise and update this manual. The County s procedure for making revisions which includes issuing technical bulletins, accepting public comments, and requesting design exceptions can be previewed on the County s website at under Services/Publications. In addition, you can submit comments and suggestions for changes to the manual using the online Comment on PUD / PW Technical Publications form located on the County s website. October 2015 Page ii
4 TABLE OF CONTENTS SECTION 1.0 STANDARD PROCEDURES PRELIMINARY DESIGN AND ENGINEERING (PD&E) PHASE DESIGN PHASE PERCENT TO 60 PERCENT DESIGN PHASE PERCENT TO 90 PERCENT DESIGN PHASE PERCENT TO 100 PERCENT DESIGN PHASE PERCENT DESIGN PHASE POST DESIGN SERVICES (IF APPLICABLE) RIGHTS-OF-WAY DETERMINATION AND ACQUISITION BIDDING PHASE CONSTRUCTION PHASE SECTION 2.0 ACCELERATED PROJECT PROCEDURES ACCELERATED PROJECT DIRECTIVE ACCELERATED PROJECT PROCEDURES APPENDICES APPENDIX A: APPENDIX B: GLOSSARY UTILITY CONFLICT MATRIX October 2015 Page iii
5 SECTION 1.0 STANDARD PROCEDURES 1.1 PRELIMINARY DESIGN AND ENGINEERING (PD&E) PHASE NOTE: Not all projects include a PD&E study unless Public Utilities Department (PUD) funds will be requested which will require the study. If a PD&E study is not included, begin with Section 1.2 Design Phase, of these procedures. If the PD&E study phase includes preparation of 30% design plans, refer to the procedures described in Sections 1.3 and At the inception of a Capital Improvement Plan (CIP) project, the requesting Department Project Manager shall prepare a scope of services for a PD&E study and 30% plans (if applicable) for the project, which shall include County utility relocation requirements when applicable The scope of services shall contain well defined utility coordination tasks, and will reference the Utility Coordination Procedures Manual The scope of services for project design shall ensure that the Designer is responsible for all utility coordination. This includes locating existing utilities by subsurface utility engineering (SUE) or other acceptable methods, if deemed necessary. The scope shall also require that the Designer consider the location of all utilities and attempt to design around utilities when possible. The Designer shall not attempt any such design, however, that would adversely affect the overall design of County utilities When the Designer identifies potential utilities conflicts, the Designer shall verify the conflict by means of horizontal and vertical locates, including SUE as necessary. a) The Designer shall identify, if possible, any conflicts and improvements that will impact the cost and schedule of the project, such as public or private utility costs that may be reimbursable by the County (ex. overhead to underground relocations of private utilities) and any additional rights-of-way or easement costs The Designer s responsibility is for the benefit of the County and not for the benefit of any third party. While the County is encouraging cooperation between public and private interests, the private Utility Agency Owners (UAOs) are to remain responsible for their own utility facilities, including but not limited to rights-of-way and/or easement acquisition, design, re-design, removal, relocation, upgrading, and new facilities, including all associated costs At the inception of a project, Designer shall involve all known affected UAOs. The needs of the County and all known affected public or private UAOs shall be identified for County construction projects added to the capital improvement program The first communication to the UAO is a formal advanced notification from the Designer. This notification will request public and private Utility Agencies to furnish all appropriate planning information pertaining to the described project, including asbuilt drawings If a utility responds via or submits a letter of either, NO CONFLICT stating that the UAO has facilities within the project limits but will require no relocation or adjustment or NO FACILITIES stating that they have no facilities in the area and do not plan on having facilities in the area to the Designer, the County may not provide further notification to said UAO unless a plan change presents a need that was not previously addressed. However, it is recommended that updated plans or meeting notices be transmitted as needed Projects that might impact PUD assets, shall incorporate the following procedures: October 2015 Page 1-1
6 The Project Manager shall provide PUD with a copy of the project scope, preliminary design report, any relevant geotechnical reports, all current construction drawings and/or base maps, and any preliminary estimates of probable cost of construction. Upon receipt, WRS will evaluate same and determine whether the proposed project will adversely affect the security, stability, or operational efficiency of existing assets in the project vicinity. If it is determined that the PUD assets will be compromised in any way, a written response will be prepared outlining the needed changes (realignment, removal, replacement, or upgrade) to PUD assets and the probable additional cost to the County The Project Manager shall be responsible for collaborating with PUD design staff and incorporating any recommended changes into the project design. The Project Manager may enter into a separate design agreement with PUD to prepare the appropriate drawings or utilize any other design resources at his disposal Funding for the redesign of PUD assets as the result of a project initiated by Public Works Department (PWD), shall be provided by the initiating department. Funding for the construction and implementation of proposed changes shall be by mutual consent in accordance with past agreements between PWD and PUD, and shall include the following provisions: a) PUD will establish a separate utility relocation fund to provide money for the construction or relocation of affected PUD assets. b) Monies to be used for projects constructed under the work order contracts process may only be released by authorized WRS signature. Monies to be used for projects constructed under the competitive bid process, shall be transferred via an administrative budget amendment c) The release of any monies from the relocation fund shall be contingent upon PUD concurrence of project priority, review and approval of the proposed relocation budget, review and approval of all associated construction drawings, receipt of required permits from all regulating agencies, agreement to provide signed and sealed record drawings at the end of the project, and the commitment to provide full time inspection for all PUD assets installed under the aforementioned agreement. d) Incidental utility relocations (structure offsets, line replacement or relocations of less than or equal to 60 linear feet, etc), shall be the financial responsibility of the PWD. No money will be transferred out of the PUD utility relocation fund for any expenditures of less than $5, At this point in the process, the County may consider a Joint Project Agreement (JPA) with one or more UAOs. If the JPA process is preferred, then a formal agreement signed by the Board of County Commissioners will ultimately be required Unreasonable Interference by a Public or Private Utility: If the requesting County Department determines that any public or private UAO is unreasonably interfering with the proposed County project, the County Department Project Manager will provide proper notification of such to the private utility, pursuant to Section and Section 404, Florida Statutes. The formal notification of the finding of interference must be provided per the requirements in this Statute, at a minimum. 1.2 DESIGN PHASE General Design and Inception to 30 Percent Design Phase (NOTE: The PD&E Phase may include October 2015 Page 1-2
7 30% design plans. If so, the procedures described in Sections and 1.3 shall apply to the PD&E phase) To monitor projects, copies of all correspondence between the Designer and every affected UAO shall be sent to the Project Manager. In addition, the Designer is required to furnish copies of the minutes of all meetings to those attending and to the County Project Manager The Designer shall ensure that all UAOs located within the construction limits are involved at the inception of design by sending a letter or describing the project. This notification shall include the design completion date, and anticipated project construction start date, along with two sets of plans if sent by mail: one to send back with existing utilities plotted, and one for the affected entity to keep on file. The letter of notification must include the following information: A description of the Designer s requested procedure for delineating existing facilities providing disposition of utilities and resolving utility conflicts. For example, which process will be used to mark-up existing facilities and relocations during the design process. Standard color coding for marked plans are as follows: a) RED Relocation/Removal b) GREEN Facilities to Remain c) BROWN New Installations d) BLUE Adjustments A statement that attendance at meetings and cooperation of the known utilities is encouraged and expected; A statement that the private UAO is ultimately responsible for any conflicts in design by its own organization which result in uncovered or unresolved conflicts; A statement that any UAO that has no facilities within the limits of the proposed construction, or which determines that its facilities are not impacted by the proposed construction, will furnish a letter of NO FACILITIES or NO CONFLICT to the Department Project Manager. When the Department Project Manager receives a letter of NO FACILITIES or NO CONFLICT, the County may not provide further notification to the utility unless a plan change occurs that may impact said utility. However, it is recommended that the Designer continue to transmit updated plans or meeting notices as needed. Be advised that the NO CONFLICT document is one of permit submittal requirement All design submittals involving the PUD, will be routed to the PUD Utility Coordination Team for logging and tracking, unless the Project has been transferred to the PUD Project Management Section and notification of the change in contact information has been provided to the Designer. The PWD will ensure that all designs prepared on behalf of the County Water Resource Services Department are in accordance with the Hillsborough County Water, Wastewater, and Reclaimed Water Technical Manual Design plans will be submitted to the PUD design team for review at 30, 60, 90, and 100 percent phases, unless approved otherwise by the project management teams of both departments Design plans for projects designated as accelerated or fast tracked projects will be submitted to the PUD for review at a minimum of two submittals, unless PUD facilities relocation is necessary, then additional reviews may be necessary as agreed upon by the Project Manager and PUD A notice that the UAO will have 20 working days to review each plan submittal, unless otherwise approved. For more complex projects the review period may be negotiated. October 2015 Page 1-3
8 In addition to PUD proposed utility relocations, the Project Manager is responsible for coordinating and incorporating any new work as proposed into the design plans PERCENT TO 60 PERCENT DESIGN PHASE At 30 percent design, the Designer shall ensure that all known existing utilities are drawn on the plan and profile sheets and cross-section sheets plotted based on the ground utility survey and the returned, marked-up plans from the UAOs The Designer shall hold a utility coordination meeting within 30 calendar days following the 30 percent design acceptance for the purpose of ensuring that all known UAOs are informed of project status. The Project Manager shall attend each of the utility coordination meetings, and shall be involved with the resolution of any conflicts At the utility coordination meeting, the Designer shall, at a minimum, perform the following: Confirm that two sets of plans and the utility conflict matrix have been furnished to each UAO so that each utility may begin its designs Describe the project to aid the UAO in understanding the project parameters Ensure that the UAO confirm their existing utility locations as plotted on the plans Identify obvious conflicts and possible major utility relocations as noted on the utility conflict matrix Describe and discuss with all parties the possible locations of alignments, corridors, and the type of installations involved Inform all other affected utilities of the County s utility alignments and locations, if known. The locations of County-owned utilities shall be provided by the Designer, to all involved utilities as soon as the final alignment is selected and approved by PUD The Designer shall review information obtained from each known UAO within the project limits and shall attempt to minimize utility relocations and adjustments during the design The Designer must determine whether adequate Rights-of-Way exist to accommodate all existing and proposed utilities (See Rights of-way Determination and Acquisition Phase) The project shall not progress until all items on the applicable design review checklist have been addressed and verified by the Project Manager The Designer shall utilize a Utility Conflict Matrix (See Appendix) provided by the County throughout the design process. The initial utility conflict matrix shall identify all conflicts between existing utilities and design features. As the design progresses and utility relocation plans are prepared by the UAOs, the utility conflict matrix shall be utilized to identify and resolve conflicts between existing and proposed utilities and design features. The Utility Conflict Matrix will be updated and distributed during each design phase. At the conclusion of the design, all conflicts identified by the Utility Conflict Matrix (APPENDIX B) shall be resolved PERCENT TO 90 PERCENT DESIGN PHASE At 60 percent design, the Designer shall confirm that all known existing utilities are shown on the drainage structure sheets, cross-section sheets, plan and profile sheets, lighting plans and signalization plans (when applicable) The Designer shall further evaluate all potential conflicts by field investigation, both October 2015 Page 1-4
9 horizontally and vertically utilizing Subsurface Utility Engineering (SUE) This identification process shall include all necessary coordination between the UAOs, surveyors and the Designer in an attempt to identify possible conflicts. If any such conflicts are discovered, the Designer shall request completion of a design by the affected UAO, with a non-conflicting adjustment indicated on the design plans The Designer shall inform the affected utility that if the UAO fails to accomplish this design, the County will resolve the conflict. The cost of this resolution shall be the responsibility of the affected UAO, and the UAO shall reimburse the County for any expenses incurred, as described in Standard Procedures, Section 1.1.5, Unreasonable Interference by a Public or Private Utility, of this document Within 30 calendar days following the 60 percent design acceptance, the Designer shall hold a utility coordination meeting. The Project Manager shall attend each of the utility coordination meetings, and shall be involved with the resolution of any conflicts The 60 percent design utility coordination meeting shall ensure that all entities are up to date on the project and have received the following: Two sets of plans, which shall include all appropriate plan sets, including but not limited to signalization plans and the County s proposed utility plans (if applicable); draft Utility Relocation Schedule (URS) and updated Utility Conflict Matrix Instructions to the UAO to mark up one set of plans showing their designs for relocations, adjustments, new installations, and existing utilities to remain, and prepare a draft URS. These mark-ups are to be returned to the Designer within 20 working days, unless otherwise approved, for more complex projects the review period may be negotiated. Color coding for marked plans area as follows: a) RED Relocation/Removal b) GREEN Facilities to Remain c) BROWN New Installations d) BLUE Adjustments The Designer must ensure that all existing and proposed utilities are shown on the appropriate sheets, including but not limited to drainage structure sheets and cross-section sheets. Plan and profile sheets may only show existing facilities for more complex projects The proposed alignment of relocated private utilities (horizontal and vertical) will be shown on the plan and profile sheets of the utility adjustment plans. For small less complex projects, these proposed alignments may be on the roadway plan and profile sheets, if approved by the Project Manager. PUD utility relocation design must be shown on separate sheets and shall meet Hillsborough County Water, Wastewater, and Reclaimed Water Technical Manual Based on information obtained from the UAOs at 60 percent design, the Designer shall: Compile the utility adjustment plans Work jointly in an attempt to resolve potential conflicts Make its best efforts to identify any utility conflicts between agencies designs (which will include but not be limited to applicable signalization designs, the County s proposed utility designs when applicable, and maintenance of traffic designs) The Engineer of Record (EOR) will prepare a draft Project Construction Phasing Plan or (Traffic Control Plan; based on County Engineer approval) which will be provided to the UAOs along with the 60% Plans. The UAOs will then either conform their October 2015 Page 1-5
10 relocation to the proposed phasing plan or inform the EOR, within two weeks of receipt of the Phasing Plan, why it cannot conform, which will potentially require the EOR to revise the phasing plan. The construction phasing plans will coincide with the UAOs URS Phases I, II, III, IV and Prior to Construction Coordinate as many utility meetings that are necessary to resolve all conflicts Regardless of the Designer s responsibility to make its best efforts to identify potential utility conflicts, each private utility is responsible for any conflicts attributable to its design PERCENT TO 100 PERCENT DESIGN PHASE At 90 percent design, the Designer shall confirm that the utility adjustment plans are 100 percent complete. The Designer will transmit to each UAO two complete sets of construction plans In addition to preparing utility adjustment plans, each UAO shall also be required to submit four completed original URSs as described in the Utility Accommodation Guide and Rights-of-Way Use Procedures Manual Each UAO shall adequately determine the number of days required to perform the necessary work When possible, UAOs shall complete the adjustment/relocation of facilities prior to issuance of the construction contract Notice to Proceed If a UAO is unable to complete adjustment/relocation of its facilities before issuance of Notice to Proceed, the Project Manager shall evaluate the time requested by the affected utility and determine the feasibility of providing the requested time during the duration of the contract. The Project Manager shall also determine whether special provisions to the technical specifications are required to accommodate the proposed utility relocation Each UAO shall also be required to submit a Right-of-Way use permit application. Refer to the Utility Accommodation Guide and Rights-of-Way Use Procedures Manual for permit requirements and maintenance of traffic (MOT) submittal requirements For major roadway or intersection projects, the Designer shall hold a Final Design utility coordination meeting within 18 calendar days following the 90 percent design acceptance. The Project Manager shall attend each of the utility coordination meetings, and shall be involved with the resolution of any conflicts. This meeting is to discuss and (if approved by the Project Manager) accept the anticipated URS and determine whether special provisions to the contract documents are needed to accommodate utility construction PERCENT DESIGN PHASE At 100 percent design, the Designer shall ensure that all utility conflicts have been resolved The Designer shall consult the Project Manager to ensure that construction scheduling and technical specifications have been addressed Additional utility coordination meetings shall be held as required to resolve utility conflicts. The Project Manager shall attend each of the utility coordination meetings, and shall be involved with the resolution of any conflicts An original signed and approved URS shall be sent to the UAO by the Designer or Project Manager. October 2015 Page 1-6
11 1.6.5 UAOs are to be notified that the URS may be revised during the bid or construction phases. During the final design, bid, and construction phases, URSs may be negotiated between the UAO, Contractor, and County. The Project Manager has final approval If at any time the project schedule is changed from the schedule that was provided to the UAOs, the Project Manager shall inform the UAO of the change The Designer shall review the project construction phasing plan that includes all of the proposed utilities relocation and proposed new utilities to ensure all relocations have been scheduled Once the advanced relocation work has been scheduled the Designer will monitor and track all advanced relocation efforts prior to construction. Status reports to the County will be required biweekly. 1.7 POST DESIGN SERVICES (IF APPLICABLE) The Designer shall hold a follow up utility meeting with all of the UAOs if there is a greater than six month delay between final plans and the County s advertisement date The Designer shall forward a copy of the approved URS to all involved UAOs for an additional review and the UAO is to initial and date the approved URS if still accurate. 1.8 RIGHTS-OF-WAY DETERMINATION AND ACQUISITION The Designer is to determine whether existing Rights-of-Way are sufficient to accommodate all utilities. This will be accomplished as early as possible prior to or during the design phase In the event that the proposed Rights-of-Way are determined to be inadequate to accommodate all utility facilities, the Designer shall notify the Project Manager, and furnish, the Project Manager with proposals and alternatives The appropriate Department will determine which proposal or alternative will be accepted or course of action to be taken. The County Real Estate Department, Acquisition Section, the County Attorney s Office (eminent domain attorney) and the PWD court engineer will also be involved in making this determination Upon request, the appropriate Department shall furnish Rights-of-Way plans (if available) to the UAOs Upon Project Manager approval of the URS, the UAOs shall be informed of ongoing Rights-ofway acquisitions to allow for pre-construction relocations At times during Right-of-Way Acquisition Process, the project design may be revised based on agreements with property owners. If revisions occur, the revised sheets of the final plans shall be submitted to the UAOs. The Designer and Project Manager must consider the effect of all utilities prior to making these changes Upon completion of the Rights-of-Way Acquisition and prior to the bidding phase, the Project Manager shall schedule a meeting with the involved UAOs and companies to inform them of the progress and schedule of the project. The Designer shall prepare detailed meeting minutes and submit them to the Project Manager for review prior to distribution. If any changes have occurred to either the roadway design or to the disposition of the utilities since the completion of final design, the Designer shall revise the utility adjustment plans as necessary and obtain revised URS October 2015 Page 1-7
12 from the respective public and/or private UAOs and/or companies. If no changes to the disposition of the utilities have occurred since final design, the Designer shall obtain written confirmation form each public and private utility agency and company that its relocation design and relocation schedule are current. 1.9 BIDDING PHASE The County shall keep the UAOs informed of the progress and schedule of the project on a monthly basis through Greater Tampa Utility Group (GTUG) meetings The County will invite all affected UAOs involved to the pre-bid meeting to address questions related to relocation plans and schedules If questions arise by prospective bidders during the bidding phase that relate to a UAO relocation plans or relocation schedule, the Project Manager will request that the UAO provide information to the County so that the question(s) can be given to the bidders in the form of a bid addendum Once a bidder is awarded a project, the Project Manager will provide written notification of the scheduled project start date and the Notice to Proceed date to all affected UAOs at the preconstruction meeting CONSTRUCTION PHASE Once the construction contract is awarded, the Department Project Manager will conduct a preconstruction/partnering meeting. All affected Utility Agencies involved shall be invited to the pre-construction meeting. Before or during this meeting, Utility Agencies may propose adjustments to their proposed construction schedules to coincide with the contractor s proposed schedule. The contractor and the County must agree to said proposed schedule adjustments, provided the adjustments have no impact on the Project s schedule and result in no additional cost to the County. If accepted, the adjusted schedule(s) will become part of the contract and the construction schedule. An approved signed copy of the schedule shall be given to the UAO by the Project Manager The Project Manager, in conjunction with the contractor, shall properly coordinate and schedule with all of the UAOs to prevent delays to the project Following Notice to Proceed, the Project Manager and the contractor shall schedule an initial progress meeting. Each UAO involved in the project shall be invited to this meeting to discuss each Utility Agencies construction schedule At that meeting, specific times, dates, and meeting frequency shall be set by the Project Manager for future meetings. Meeting frequency shall depend upon the complexity of the project These meetings shall continue until the Project Manager, Contractor, and the affected UAO agree that the meetings are no longer warranted Prior to the start of any work a Temporary Traffic Control and Rights-of-Way Use Permit must be submitted by the UAOs for approval. The permit submittal is to be signed by the Project Manager If the contractor or a UAO requests a construction schedule revision, the requesting party shall notify the Project Manager. The Project Manager shall notify all affected parties, and a meeting October 2015 Page 1-8
13 shall be held by the Project Manager to determine what effects the revisions will have on the County, contractor, or UAOs If any construction schedule revision request results in delays to the project, the UAO and the contractor shall negotiate with the County for said delays, and shall compensate the County, if appropriate, before the Project Manager will agree to process a change order permitting the proposed schedule revision. The contractor shall review revisions and is responsible for verifying the location of existing utilities For projects that involve the Hillsborough County PWD and the PUD, the Hillsborough County PUD shall perform the actual utility relocation construction as part of its construction contract, when applicable This shall not include Construction Engineering Inspection (CEI) for County utility relocation construction. PUD is responsible for CEI (cost and actual onsite effort) of its utility relocation construction This does not supersede the PWD s overall CEI of the construction project, but allows the PUD to directly oversee quality control and specification compliance of the relocation of its lines Any contractual issues will be coordinated with the PWD s Project Manager Change orders and Allowance Authorization Release (AAR s) will be agreed upon by the PUD CEI personnel and the PWD Contractor, and submitted to PWD for processing The PUD CEI personnel will monitor quantities for payment and submit them to the PWD Project Manager weekly Pipeline locations as determined by PUD will not be adjusted without PWD approval Construction record drawings per the Hillsborough County Water, Wastewater, and Reclaimed Water Technical Manual will be provided to PUD at the conclusion of the construction project. October 2015 Page 1-9
14 SECTION 2.0 ACCELERATED PROJECT PROCEDURES 2.1 ACCELERATED PROJECT DIRECTIVE By written directive from a Department Director (or higher-level official), the County may deem a project to be accelerated or fast tracked. Examples of justification for project acceleration include, but are not limited to, the following: Safety considerations; A public commitment by the Board of County Commissioners; Pending expiration of project funds such as grants In some cases, a project s accelerated or fast-tracked status may be rescinded, such as when additional Rights-of-Way are required. 2.2 ACCELERATED PROJECT PROCEDURES All of the procedures outlined in this document for PD&E, Design, Rights-of-Way determination and acquisition, Bidding and Construction phases shall still apply for accelerated or fast-tracked projects, except that stated timelines may be accelerated. Reasonable time schedules will need to be set during the PD&E phase, and any aspect of the existing process that can be accelerated shall be implemented as quickly as possible. October 2015 Page 2-1
15 APPENDIX A: GLOSSARY October 2015 Appendix A
16 CIP: Capital Improvement Project GLOSSARY Department: The County department that initiates a project and which is responsible for project management from inception to completion. Designer: the designer that provides engineering services for the Department or, when applicable, the Consultant chosen to design the project. EOR: Engineer of Record PD&E: Preliminary Design & Engineering Project Manager: County designee in responsible charge of managing and processing the project from start to finish and, ensuring adherence to the Scope of Services. All correspondence (questions, problems, or concerns pertaining to the project) shall be addressed, or copied, to the Project Manager. Public Utilities Department (PUD): County department responsible for constructing, maintaining and operating all county water, wastewater and reclaimed water systems. SUE: Subsurface Utility Engineering Utility Agency Owner (UAO): Public or private utility agency or company, or designee, that will research and furnish all pertinent, proposed and existing utility information to the Designer. Utility Conflict Matrix: Comprehensive list of potential utility conflicts with the proposed improvements. Utility Coordinator: Consultant designee that is responsible for the performance of all utility coordination procedures contained in the Consultant s scope of services. Utility Design Consultant: Consultant chosen to design proposed County utilities and/or any relocations or adjustments needed for the complete design of a project (if different than the Designer) Utility Relocation Schedule (URS): Detailed schedule of all utility relocations, removals and new facilities to be constructed by the UAO. Include construction phasing and number of calendar days to complete the work. URS must be signed by the Utility Design Consultant (EOR) and the County Project Manager. October 2015 Appendix A-1
17 APPENDIX B: UTILITY CONFLICT MATRIX October 2015 Appendix B
18 October 2015 Appendix B-1
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
REQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS Engineering Design Services for the Preliminary (Design) Engineering 1. Imlay City Road Imlay City Road at Wilder Road (signal modernization), Lapeer Township 2. Imlay City Road Imlay
ENGINEERING AGREEMENT
ENGINEERING AGREEMENT STATE OF LOUISIANA PARISH OF JEFFERSON This Agreement is made and entered into on this day of, 200 by and between the Parish of Jefferson, State of Louisiana, acting herein by and
TABLE OF CONTENTS. Purchasing and Contracts Division... 1. Purchasing Policies and Procedures... 1. The Competitive Process... 2
TABLE OF CONTENTS Title Page Purchasing and Contracts Division... 1 Purchasing Policies and Procedures... 1 The Competitive Process... 2 Vendor Participation... 2 Vendor Database... 2 Web Site Information...
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT
ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive
SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES PROJECT DEVELOPMENT AND ENVIRONMENTAL STUDY AND DESIGN
I-95 (SR 9) from I-10 to Georgia State Line- Managed Lane Study FIN No:435576-1-12-01 Federal Project #: TBD Duval and Nassau Counties, Florida SCOPE OF SERVICES FOR CONSULTING ENGINEERING SERVICES PROJECT
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
City of Powell Request for Proposals for a Total Compensation Survey
City of Powell Request for Proposals for a Total Compensation Survey Section I The City of Powell is soliciting proposals from qualified consulting firms, experienced in the development of a job evaluation
CP#64 / Environmental Monitoring Services
CP#64 / Environmental Monitoring Services Issuing Authority: Acting Commissioner Basil Seggos Date Issued: November 4, 2015 New York State Department of Environmental Conservation DEC Policy Latest Date
San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM
ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes
AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR
DB-BIM Contract No. 5890 07/14 Project No. 02-3210 AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR 1 DB-BIM Contract
Request for Proposal For: CQ5 Java Developer. ABA Information Systems April 11, 2013. Table of Contents
Request for Proposal For: CQ5 Java Developer ABA Information Systems April 11, 2013 Table of Contents Bid Timetable [2] 1.0 General Information [3] 2.0 Proposal Requirements [6] 3.0 Criteria for Selection
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Document A101 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the in the year (In words, indicate day, month and year.)
Project Management Procedures
1201 Main Street, Suite 1600 Columbia, South Carolina 29201 Project Management Procedures Start Up The grant becomes effective upon return of one copy of the grant award executed by the Chief Executive
LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL
LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...
CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE
CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE STATE OF IDAHO DEPARTMENT OF ADMINISTRATION DIVISION OF PURCHASING REVISED 01 01 14 Table of Contents I. Purpose... 1 II. Overview of Contract Management and
REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION
REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION
REQUEST FOR PROPOSALS
ROWAN COUNTY 130 West Innes Street Salisbury, NC 28144 Tel: (704) 216-8174 Email: [email protected] REQUEST FOR PROPOSALS FOR REPLACEMENT OF COMMERCIAL ROOFTOP AIR CONDITIONING UNIT Issued
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
maguilar\h:\agenda Items\2012\12-0917 CH Plumbing RFQ.doc\1-7
maguilar\h:\agenda Items\2012\12-0917 CH Plumbing RFQ.doc\1-7 maguilar\h:\agenda Items\2012\12-0917 CH Plumbing RFQ.doc\2-7 maguilar\h:\agenda Items\2012\12-0917 CH Plumbing RFQ.doc\3-7 maguilar\h:\agenda
Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY. Sacramento River Southport Early Implementation Project
Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY Sacramento River Southport Early Implementation Project TABLE OF CONTENTS Introduction... 1 Before the Acquisition Process
CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE. July 24, 2015 BY 11:00 A.M.
CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE July 24, 2015 BY 11:00 A.M. SUBMIT TO: Office of the City Clerk Lancaster City Hall 44933 Fern Avenue
REQUEST FOR QUALIFICATIONS. For ENGINEERING SERVICES
REQUEST FOR QUALIFICATIONS For ENGINEERING SERVICES For FY17/FY18 Fiscal Years Mecklenburg County Storm Water Services (MCSWS) Projects Mecklenburg County, North Carolina June 14, 2016 Submittal Deadline:
Design Development Agreement
Design Development Agreement June 2010 prepared by Larry Kirkland, PAN Council Member and The Law Office of Sarah Conley Disclaimer The Public Art Commission Agreement is made available as a service of
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL
P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL 1.0 Description. 1.1 This specification allows bidders the opportunity to include in their overall bid proposal, pricing for
LAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application
Applicant shall indicate that the required information has been provided or is not applicable to the project by placing the appropriate mark in the first column of this checklist. Missing or incomplete
Work Breakdown Structure Element Dictionary Construction
Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor
Description: Publication Date: 9/21/2015. Closing Date/Time: Open Until Contracted
Description: The New River Valley Regional Jail Authority (NRVRJA) values and appreciates the contributions and efforts of its employees. Toward this end, the NRVRJA is committed to providing a supportive,
Shawnee County ATTN: Bill Kroll 200 SE 7 th Street, Rm B-30 Topeka, KS 66603 Phone 785.251-4490 [email protected]
SECTION I Shawnee County is requesting qualifications/proposals for the renovation of 2600 SW East Circle Drive, Topeka, Kansas 66606 which will be utilized by the Shawnee County Health Agency per the
AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK
AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK MD ANDERSON AGREEMENT No. This Agreement is made as of, 20xx (the Effective Date ), by and between The Owner: M D Anderson Cancer Center c/o Sourcing
PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS
CHAPTER 11 - Project Continuity Contents Introduction... 2 Phase Hand-Offs... 3 Project Feedback... 9 Project Management Team Approach... 10 Page 1 of 15 Introduction A primary objective of all Project
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
Attachment 5 Electrical Engineering
A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
Section 7.13 INTERNAL REVENUE SERVICE REPORTING REQUIREMENTS
Section 7.13 INTERNAL REVENUE SERVICE REPORTING REQUIREMENTS Table of Contents PURPOSE...7-13-1 AUTHORITY...7-13-1 SCOPE...7-13-1 REFERENCES...7-13-1 TRAINING...7-13-1 FORMS...7-13-1 DEFINITIONS...7-13-2
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
CITY OF MESA, ARIZONA ENGINEERING DEPARTMENT REQUEST FOR QUALIFICATIONS
CITY OF MESA, ARIZONA ENGINEERING DEPARTMENT REQUEST FOR QUALIFICATIONS On-Call Consultant List for Mechanical Engineering Services TABLE OF CONTENTS REQUEST FOR QUALIFICATIONS PAGE NO. SECTION I PROJECT
Independent Third-Party Review Guidelines
Colorado Division of Water Resources Dam Safety Branch Independent Third-Party Review Guidelines Policy Memorandum No. 01-03 February 10, 2003 1.0 INTRODUCTION Colorado Statutes (C.R.S. 37-87-105) require
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES. Responsibilities of Construction Manager Scope of Construction Manager s Basic Services
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES Article I Article II Article III Article IV Article V Article VI Article VII Article VIII Article IX Responsibilities of Construction Manager Scope of Construction
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
DRINKING WATER SYSTEMS IMPROVEMENTS REVOLVING LOAN FUND PROGRAM FINAL REGULATIONS DRAFT AMENDMENT - JUNE 2016 PRESENTED TO THE BOARD FOR ADOPTION
DRINKING WATER SYSTEMS IMPROVEMENTS REVOLVING LOAN FUND PROGRAM FINAL REGULATIONS DRAFT AMENDMENT - JUNE 2016 PRESENTED TO THE BOARD FOR ADOPTION April 22, 2016 LOCAL GOVERNMENTS AND RURAL WATER SYSTEMS
NOTICE TO POTENTIAL BIDDERS
NOTICE TO POTENTIAL BIDDERS Downloading the Plans, Specifications and other Bid Documents will NOT place you on the City s List of Plan Holders. This is important because only those on the City s List
Request for Proposals For Financial Advisor Services
Request for Proposals For Financial Advisor Services Finance Department Contents Section I Introduction 2 Section II Description of Village 2 Section III Debt Financing Plans 3 Section IV Scope of Services
Chapter 10. Acquisition of Real Property
Chapter 10 Acquisition of Real Property Chapter 10: Acquisition of Real Property Table of Contents Page Property Management & Disposition... 10-1 Acquisition as a National Objective... 10-2 Uniform Relocation
CDO WORKFORCE INVESTMENT BOARD. REPLACES CDO Workforce Investment Board Procurement Policy, dated 9/30/05
CDO WORKFORCE INVESTMENT BOARD POLICY #07-03: Local Procurement of Goods and Services DATE: November 14, 2007 APPLIES TO: Use of WIA Title I-B funds REPLACES CDO Workforce Investment Board Procurement
TROUP COUNTY COMPREHENSIVE HIGH SCHOOL
TROUP COUNTY BOARD OF EDUCATION REQUEST FOR SEALED COMPETITIVE PROPOSALS FOR CONSTRUCTION OF: RE-FLOORING TO: TROUP COUNTY COMPREHENSIVE HIGH SCHOOL LAGRANGE, GEORGIA TROUP COUNTY SCHOOL SYSTEM LAGRANGE,
1.001 University Board of Trustees Powers and Duties
1.001 University Board of Trustees Powers and Duties (1) Pursuant to Article IX, section 7(c), Florida Constitution, the Board of Governors shall establish the powers and duties of the board of trustees
The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:
The Role of Construction Managers FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: A. Notes on the use of FIDIC in the Middle East B. A Communication
MANAGING THE PROJECT RECORD
MANAGING THE PROJECT RECORD Project Record Filing System 2 Agency Submittals 2 Site Acquisition 3 Planning 3 Pre-Qualification of Bidders 3 Bidding 4 Construction 4 Inspection 4 Legal 5 Contracts 5 Accounting
How To Get A Job Done
CUMBERLAND COUNTY COMMUNITY DEVELOPMENT (CCCD) HOUSING REHABILITATION PROGRAM PO DRAWER 1829 707 EXECUTIVE PLACE FAYETTEVILLE, NC 28302-1829 CONTRACTOR QUALIFICATIONS: REHABILITATION CONTRACTOR'S HANDBOOK
Cleveland County Emergency Medical Services. PO Box 1210. Shelby, NC 28151 704-484-4984. Request for Proposal. For. Debt Collection Agency Services
Cleveland County Emergency Medical Services PO Box 1210 Shelby, NC 28151 704-484-4984 Request for Proposal For Debt Collection Agency Services Proposals Must Be Submitted by July 16, 2013 Issue Date: June
Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.
The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most
CAPITAL PLANNING, DESIGN AND CONSTRUCTION SECTION IV - FISCAL RESOURCES FOR CAMPUS DEVELOPMENT SECTIONS 9025-9040
9025 FISCAL RESOURCES FOR CAMPUS DEVELOPMENT The following paragraphs describe the process for obtaining and encumbering funding for capital outlay. The process for obtaining support funds for new space
PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
CHAPTER 5 - Construction Project Management Contents Introduction... 2 Construction Contract Management... 2 CEI Contracts... 3 Community Awareness Plan... 7 Alternative Contracting Methods... 8 Warranty
Texas Department of Transportation
Consultant Errors & Omissions Correction and Collection Procedures July 2014 July 2014 Consultant Errors & Omissions Correction and Collection Procedures 1.0 Consultant Contract Administration... 2 2.0
THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL
THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL OCTOBER, 2013 TABLE OF CONTENTS 1. CHECKLIST PAGE NO. 2. CHECKLIST DETAILS A. Design Path 3 B. Property Acquisition 6 C. Outside
STATE LIQUOR AUTHORITY: DIVISION OF ALCOHOLIC BEVERAGE CONTROL OVERSIGHT OF WHOLESALERS COMPLIANCE WITH THE ALCOHOLIC BEVERAGE CONTROL LAW
Alan G. Hevesi COMPTROLLER OFFICE OF THE NEW YORK STATE COMPTROLLER DIVISION OF STATE SERVICES Audit Objectives... 2 Audit Results Summary... 2 Background... 3 Audit Findings and Recommendations... 3 Oversight
UNIVERSITY HOSPITAL POLICY
UNIVERSITY HOSPITAL POLICY SUBJECT: PURCHASING SERVICES TITLE: PURCHASING PROCESS Responsible Executive: Executive Director, Supply Chain Management Responsible Office: Supply Chain Management CODING:
PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS
PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS CITY OF GREATER SUDBURY ENGINEERING SERVICES DIVISION JUNE 2005 TABLE OF CONTENTS Chapter 1 - Reference Procedure Manuals and Specifications - CAD Drawing Requirements
Food Service Management Companies Table of Contents
Food Service Management Companies Table of Contents Food Service Management Companies 22.1 Procedures for Competitive Bidding/Competitive Proposal 22.1 for a Food Service Management Company (FSMC) Procedures
REQUEST FOR PROPOSAL ON-SITE MEDICAL SERVICES CLINIC FOR THE CITY OF MISSOULA MISSOULA, MT
REQUEST FOR PROPOSAL ON-SITE MEDICAL SERVICES CLINIC FOR THE CITY OF MISSOULA MISSOULA, MT Submittals must be received by 5:00 p.m. (MDST) Tuesday, June 22, 2010. SECTION I: PURPOSE OF REQUEST A. The City
Florida s Turnpike Enterprise (FTE) Shop Drawing Review Process for Design Bid Build (Conventional) Projects
General: Florida s Turnpike Enterprise (FTE) Shop Drawing Review Process for Design Bid Build (Conventional) Projects The information outlined within this document, depicts a portion of Florida s Turnpike
GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
Clean Water Revolving Funds (SRF & SWQIF) Loan Application Instructions for Completing the Project Cost Worksheet
Clean Water Revolving Funds (SRF & SWQIF) Loan Application Instructions for Completing the Project Cost Worksheet 1. Entering Cost Figures To complete the Project Cost Worksheet, enter costs incurred to
To complete the process for a net metering interconnection, please follow the steps below:
We appreciate your interest in Pacific Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system to
Request for Proposals. SFY 2014 Section 604(b) Water Quality Planning Pass-Through Grant Program
Request for Proposals SFY 2014 Section 604(b) Water Quality Planning Pass-Through Grant Program State of New Jersey Department of Environmental Protection Water Resources Management Division of Water Monitoring
Covance Construction Management Staffing Plan Chandler, Arizona
INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according
Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting
Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003249 General Project Overview This work is located along Trunk Highway (TH) 23, for State Project (SP) 7305-124.
CITY OF AVENTURA COMMUNITY DEVELOPMENT DEPARTMENT 19200 W. Country Club Drive Aventura, Florida 33180 (305) 466-8940
DATE: CITY OF AVENTURA COMMUNITY DEVELOPMENT DEPARTMENT 19200 W. Country Club Drive Aventura, Florida 33180 (305) 466-8940 PUBLIC HEARING APPLICATION FOR CONDITIONAL USE APPROVAL City Code Section 31-73
Line Relocation Cost Allocation
Line Relocation Cost Allocation BUSINESS PRACTICE ATC will allow for the relocation of its transmission lines along with the associated structures and facilities at the request of interested third parties
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 1 This Chapter of the FERC Engineering Guidelines has been prepared under contract with R & H Thomas, Inc. JANUARY 1993 Chapter VII Construction
REQUEST FOR QUALIFICATIONS/ REQUEST FOR PROPOSAL. for CONSTRUCTION MANAGEMENT SERVICES. For CHAPEL OF PEACE AT RIVERSIDE CEMETERY. Project No.
REQUEST FOR QUALIFICATIONS/ REQUEST FOR PROPOSAL for CONSTRUCTION MANAGEMENT SERVICES For CHAPEL OF PEACE AT RIVERSIDE CEMETERY Project No. 08083 CITY OF ROCHESTER October 2009 TABLE OF CONTENTS GENERAL
CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
AWARD AND APPROVAL OF CONSTRUCTION CONTRACT CONTRACTOR: JOHNSON-PELTIER ELECTRICAL CONTRACTOR
THE PORT OF LOS ANGELES Executive Director's Report to the Board of Harbor Commissioners DATE: MAY 24, 2016 FROM: CONSTRUCTION RESOLUTION NO. AWARD AND APPROVAL OF CONSTRUCTION CONTRACT CONTRACTOR: JOHNSON-PELTIER
PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN
PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN FOR THE VILLAGE OF HUNTLEY, ILLINOIS 2015 Contents Introduction 1 Purpose 1 Officials Responsible for Implementation 2 Public Notice 2 Grievance Procedure
SITE PLAN APPROVAL PROCESS INTRODUCTION
SITE PLAN APPROVAL PROCESS INTRODUCTION File Manager System for Site Plan Approval Process Site Plan Control in the City of London The City of London utilizes site plan control to ensure high quality site
INTERNATIONAL STANDARD ON REVIEW ENGAGEMENTS 2410 REVIEW OF INTERIM FINANCIAL INFORMATION PERFORMED BY THE INDEPENDENT AUDITOR OF THE ENTITY CONTENTS
INTERNATIONAL STANDARD ON ENGAGEMENTS 2410 OF INTERIM FINANCIAL INFORMATION PERFORMED BY THE INDEPENDENT AUDITOR OF THE ENTITY (Effective for reviews of interim financial information for periods beginning
PARTICIPATION AGREEMENT For ELECTRONIC HEALTH RECORD TECHNICAL ASSISTANCE
PARTICIPATION AGREEMENT For ELECTRONIC HEALTH RECORD TECHNICAL ASSISTANCE THIS AGREEMENT, effective, 2011, is between ( Provider Organization ), on behalf of itself and its participating providers ( Providers
Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
CHAPTER 7 PUBLIC PURCHASES, PURCHASE OF LAND OR STRUCTURES AND INVENTORY OF FIXED ASSETS
7-1 CHAPTER 7 PUBLIC PURCHASES, PURCHASE OF LAND OR STRUCTURES AND INVENTORY OF FIXED ASSETS The "Public Purchasing Law" applies to every expenditure of public funds by a governmental body, unless specifically
Contract Administration
Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306
Reasons for Change Orders
T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E.
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. GENERAL PURPOSE Under direction, manages, oversees, evaluates,
North American Electric Reliability Corporation. Compliance Monitoring and Enforcement Program. December 19, 2008
116-390 Village Boulevard Princeton, New Jersey 08540-5721 North American Electric Reliability Corporation Compliance Monitoring and Enforcement Program December 19, 2008 APPENDIX 4C TO THE RULES OF PROCEDURE
Marion County Public Works
Marion County Public Works Federally Funded Transportation Program Title VI Annual Accomplishment Report Fiscal Year 2014/15 Marion County Public Works Department Introduction The Marion County Department
PRODUCER AGREEMENT. Hereinafter ("Producer"), in consideration of the mutual covenants and agreements herein contained, agree as follows:
PRODUCER AGREEMENT Hereinafter First Choice Insurance Intermediaries, Inc "FCII", a Florida company, having an office at 814 A1A North, Suite 206, Ponte Vedra Beach, FL 32082 and " Producer" having an
Statement of Guidance: Outsourcing All Regulated Entities
Statement of Guidance: Outsourcing All Regulated Entities 1. STATEMENT OF OBJECTIVES 1.1. 1.2. 1.3. 1.4. This Statement of Guidance ( Guidance ) is intended to provide guidance to regulated entities on