1 Contract Issues 1
2 Two Alternative Contract Strategies Contract issues discussion Strength - Weakness 2
3 If you like challenges, try an interface 3
4 Why EPC contract Single point responsibility for safety, progress, quality and warranties Potential for reduced execution time Potential for reduced investment costs Few contractual interfaces Multi discipline execution and coordination 4
5 EPC alternatives Main alternative EPC Contracts: FIDIC, NTK/NF and NS 8407 FIDIC: «no» tradition in Major Norwegian Industry Companies NTK/NF: used extensively by Major Norwegian Industry Companies in Norway and abroad, onand offshore (Statoil, Hydro, Norske skog, etc.) NS 8407: used by JBV, Statsbygg, SVV and construction generally in Norway. FIDIC: Fédération Internationale Des Ingénieurs-Conseils NTK/NF: Norsk totalkontrakt/norsk fabrikasjonskontrakt NS: Norsk standard 5
6 NS : NS : NS 401 A. 1969: NS : NS : NS 3431 (totalentreprise (EPC)) 2004 :NS : NS 8406 («enklere variant» av NS 8405) 2008: NS 8405 (mindre revisjon) 2011: NS 8407 (totalentreprise (EPC)) Merk: NS 3431 og NS 8407 er totalentrepriser, øvrige NS er byggherrestyrte kontrakter. 6
7 NTK/NF 1974: Norsk Hydro contract for Ethylene Plant, Rafnes 1977: Norsk Hydro Model Contract 1983: North Sea Offshore Lump Sum Construction Contract (MVL (=Norsk industri) and NIFO) 1987: Norsk Fabrikasjonskontrakt 1987 (NF 87) 1992: NF : Norsk Totalkontrakt 2000 (NTK 2000) 2005: NF : NTK : NF : NTK 07 Note: NTK is EPC («design-build»); NF is PC («design-bid-build») 7
8 NTK/NF vs NS NTK07/NF07 Structured with Attachments. Used by major Norwegian industry companies domestically and abroad. Good experience. More Owner friendly than NS 8407, e.g. NO preclusion regarding changes. NS 8407 Layer-on-layer principle («mountain» of contradictory pages). Not used by major Norwegian industry companies. Not Owner friendly, e.g. preclusion regarding changes. Conclusion: FB will use NTK07 modified; NS 8407 is too risky. 8
9 The Approved Contract Strategy 9
10 The Appoved Contract Strategy 10
11 Requirements on our Contractors High safety standard Documented excellent safety record at previous projects Bidders to describe in detail how to obtain top class safety standard at FB sites Ability to perform the work according to agreed quality, schedule and cost Experienced and competent organization Ability to cooperate with client Construction close to tracks in operation 11
12 Requirements on Ourselves High Quality ITT s and Contacts High Quality Geotechnical Baseline Report (GBR) Fair sharing of risk Fair and clear compensation mechanisms Walk-to-Talk Role model on safety issues Keep our sheet clean (e.g. no delay on approvals of drawings, etc.) We keep what you promise Make the Contractors good Enable the Contractors to excel 12
13 Main Follo Line Contracts Oslo S D&B Tunnel TBM Ski EPC Oslo S EPC D&B EPC TBM EPC Ski Substructure (~ 2 mrd. NOK) Substructure (~1 mrd. NOK) Substructure (~ 7 mrd. NOK) Substructure (~ 2 mrd. NOK) + Railway Systems (~ 0,5 mrd. NOK) + Railway Systems (~ 1,2 mrd. NOK) + Railway Systems (~ 0,7 mrd. NOK) Signal (Oslo S GS extension) (~ 0,4 mrd. NOK) EPC Signal (Thales) (~ 0,5 mrd. NOK) 13
14 Clean interface to Main EPC s & Enhancement of Owner organisation Type of Scope Oslo S Langhus-Ski Oslo - Ski Clean Interface to Main EPC s Preparatory Work Demolition Technical Scope Demolish: Borgen Garasjen Presenningtørka Fyrhus Locate and relocate cables Prep. Work for track and rail tech. Modify part of Skeidarbygget Demolish Omformerhall Locate and relocate Cables Extend Cable bridge Establish power supply to Åsland for 4 TBM and segment prefab. Rig Areas, adit tunnels Rig area Oslo S Rig area Langhus Rig area Åsland Adit tunnel Åsland Prep. Work Sydhavna (soil transp.) Enhancement of Owner Organisation Project Service Agreement (PSA) Technical resources Technical resources Technical resources 14
15 Questions? Follobanen Langhus Ski og Ski hensetting Informasjonsmøte 24. oktober
Collaboration between Brazil and Norway in the field of oil and gas research and technology and exchange of human resources(bn21)
Collaboration between Brazil and Norway in the field of oil and gas research and technology and exchange of human resources(bn21) Director general Marit Engebretsen NHO, 23 January 2014 Brazil 25 November
The Follo Line Project
The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the
Agenda. Det norske always moving forward Ivar Aasen project learning points Field development what will it take? Observations
Agenda Det norske always moving forward Ivar Aasen project learning points Field development what will it take? Observations DET NORSKE Concentrated in two core areas Utsira High Greater Alvheim area GREATER
PROJECT ESTIMATION & CONTROL
PROJECT ESTIMATION & CONTROL Jean-François REITER VP Project Estimation & Control INVESTOR DAY, PARIS, FRANCE - October 22, 2004 E.P.C. LUMP SUM CONTRACTS Technip guarantees to its client: The price of
Geoff Schmitt FRICS FInstCES FCIArb. Mission Statement. Major Projects. Potential Target Locations. Paper Summary
Geoff Schmitt FRICS FInstCES FCIArb Dispute Resolution Consultant Expert Witness Overseas civil engineering projects CONTRACTING IN THE GLOBAL MARKET PLACE Geoffrey SCHMITT, United Kingdom Over 40 years
Songa Offshore SE Q2 2009. July 31, 2009
Songa Offshore SE Q2 2009 July 31, 2009 Highlights Q2 Move to Cyprus registered on May 11, headquarters moved to Limassol from same day Finalised SPS for Songa Dee, estimated cost increased to USD 65 mln
How To Write New Government Construction Contracts
HUSSEY FRASER SOLICITORS 1. Objectives of new contracts 2. How objectives are to be achieved Risk Transfer Procedural / Information Burden 3. Termination Provisions 4. Collateral Warranties 5. Conclusion
Oslo Børs VPS Holding ASA 1st Quarter 2011
Oslo Børs VPS Holding ASA 1st Quarter 2011 28 April 2011 Overview First quarter highlights Increased market activity compared to last quarter Operating revenues: NOK 243.0 million (246.1) Operating profit
MILJØPAKKEN: Greener Trondheim Partnership for sustainable transport
MILJØPAKKEN: Greener Trondheim Partnership for sustainable transport 13th March 2013 Henning Lervåg Head of Miljøpakken 10 concrete, verifiable goals 1. Minimum 20 % reduction in CO 2 emissions from transport
Project and site organization of a NATM tunnel project on the example of the Koralm tunnel. Hanns Wagner OBB Austrian Federal Railways
Project and site organization of a NATM tunnel project on the example of the Koralm tunnel Hanns Wagner OBB Austrian Federal Railways Requirements for a successful application of NATM Design, which considers
New contract for jacket to the Johan Sverdrup Process Platform. 8 October 2015 Sverre Myklebust, Executive Vice President, Jackets
New contract for jacket to the Johan Sverdrup Process 8 October 2015 Sverre Myklebust, Executive Vice President, Jackets Kvaerner involvement in Johan Sverdrup so far: 1 PLATFORM TOPSIDE: Scope: EPC delivery
TBMs for Norwegian Hydropower projects. Sindre Log The Robbins Company
TBMs for Norwegian Hydropower projects Sindre Log The Robbins Company Who am I? Sindre Log M.Sc. Civil engineering, NTNU Specializations in tunneling, geology and Project management Working out of Oslo,
Oslo Børs Holding ASA first quarter 2005
Oslo Børs Holding ASA first quarter 25 First quarter in brief: Operating revenues: NOK 79. (71.) million Operating profit: NOK 37. (29.1) million Earnings for the period: NOK 34.9 (21.5) million Earnings
Aker Solutions Splits Into Two Companies
Fornebu, April 30, 2014 Øyvind Eriksen, Executive Chairman 2014 Aker Solutions Boosting Value Through Two New Companies New Aker Solutions Swifter realization of synergies, operational excellence and organic
How To Know How Many Major Transport Accidents In Norway
Major transport accidents in Norway: assessing long-term frequency and priorities for prevention Rune Elvik, Institute of Transport Economics, Oslo, Norway Problems to be discussed How many major transport
Shtokman Development AG
Shtokman Development AG Integrated Development of the Shtokman Gas- Condensate Field. Phase 1 SDAG Standard EPC Contract. Main Principles. EPC Contracts What is an EPC contract? - Contract for Engineering,
Norwegian electromobility policy for 2020
Norwegian electromobility policy for 2020 Per-André Torper Norwegian Ministry of Transport and Communications Oslo, June 11 th 2015 Sold cars in May 2015 1. Volkswagen Golf 1 323 2. Tesla Model S 346 3.
BOUNDARY DAM CCS CROSSES THE FINISH LINE. October 2014
Bellona Europa [email protected] Rue d Egmont 15 +32 (0)2 648 31 22 1000 Brussels www.bellona.org BOUNDARY DAM CCS CROSSES THE FINISH LINE October 2014 Canadians can be proud of the Boundary Dam CCS facility,
NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS
NAS 13 NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS CONTENTS Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT
Data Centres that never, never, ever go down
Data Centres that never, never, ever go down Investing in Norwegian Data Centres 13 February 2013 J. Byrne Murphy - Chairman DigiPlex Group of Companies My Topics Today Investing In Norwegian Data Centres
The Technology Challenge. Agenda - The Technology Challenge
The Technology Challenge British and Norwegian Oil and Gas Industry Collaboration Conference R. Rasmus Sunde Executive Vice President London, October 26, 2005 Agenda - The Technology Challenge Overall
GENCO HOLDING COMPANY LIMITED (GHCL) PROFORMA PC-II
GENCO HOLDING COMPANY LIMITED (GHCL) PROFORMA PC-II HIRING OF CONSULTANTS FOR EIAs, PC-1 & BIDDING DOCUMENTS FOR COAL FIRED POWER PLANT 2X660 MW (Gross) AT LAKHRA, AND FEASIBILITY OF 1x660 MW (Gross) AT
Linear Schedules for Tunnel Projects
Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear
Preferred partner. Investor Day 2015. London, March 17, 2015 Luis Araujo, CEO Svein Stoknes, CFO
Investor Day 2015 London, March 17, 2015 Luis Araujo, CEO Svein Stoknes, CFO 2015 Aker Solutions Slide 1 March 17, 2015 Investor Day 2015 Forward-Looking Statements and Copyright This Presentation includes
The Norwegian Model: Evolution, performance and benefits
The Norwegian Model: Evolution, performance and benefits Ola Borten Moe Minister of Petroleum and Energy Olje- og energidepartementet regjeringen.no/oed Our largest industry Norwegian Oil and Gas Activities
The Norwegian Experience
The Norwegian Experience Jerusalem, January 23 rd 2012 www.agr.com 1 About the presenters Eivind Reiten Chairman AGR CEO Hydro from 2001 to 2009 Minister of Oil & Energy from 1989 to 1990 Minister of Fishery
Background. When the Government Is the Landlord. 1 Norway's oil and gas reserves are all offshore.
Regional Details: Norway In this appendix, we describe the methods the government uses to obtain revenues from oil and gas production in Norway. We present quantitative estimates of revenues as well as
Det norske a new large independent. Odd Ragnar Heum, Det norske oljeselskap ASA
Det norske a new large independent Odd Ragnar Heum, Det norske oljeselskap ASA A new large independent Who we are... How we will operate A fully fledged O&G company Among the largest European Independents
Forsikring av offshoreprosjekter Foreleser: Harry Nilsen, Norsk Hydro
Forsikring av offshoreprosjekter Foreleser: Harry Nilsen, Norsk Hydro Ettertrykk er kun tillatt etter avtale med foreleser og Tekna Hydro Oil & Energy Erfaringer vedr. utviklingen av forsikringspremier
SKAGEN Vekst. Status as of 30-11-05
SKAGEN Vekst Status as of 30-11-05 Why SKAGEN Vekst? Balanced portfolio adapted to Norwegian investors Better geographic spread than pure Norwegian fund Better industry balance than a Norwegian fund =
The Transformation of the Norwegian Maritime Industry to a Global Maritime Knowledge Hub
The Transformation of the Norwegian Maritime Industry to a Global Maritime Knowledge Hub Professor BI Norwegian Business School Oslo, Norway OECD Workshop on the Future of Shipbuilding Paris, November
Norwegian Research Centre for Offshore Wind Technology
Norwegian Research Centre for Offshore Wind Technology John Olav Giæver Tande Manager NOWITECH Senior Research Scientist SINTEF Energy Research [email protected] 1 Preface The Research Council of Norway
Status og utsikter for norsk sokkel
Status og utsikter for norsk sokkel Marknadskreftene rår «Oljetrykket» Seminar i regi av DNB og Næringsforeningen i Stavanger-regionen Stavanger, 2. mars 214 Klaus Mohn, professor of petroleum economics
JUA Underwriting Agency Pty Ltd
JUA Underwriting Agency Pty Ltd Engineers & Architects Professional Indemnity Proposal Form Please answer every question fully, incomplete answers will not be accepted, and may result in a delay in terms
Delivering Engineering Services to UK Infrastructure through our branded businesses nationwide
Delivering Engineering Services to UK Infrastructure through our branded businesses nationwide Renew provides multidisciplinary engineering services to maintain and develop UK infrastructure focused in
ERTMS - National implementation plan
ERTMS Page: 2 av 9 ERTMS - National implementation plan 00E First release 09.07.2013 KLY SKEI KJENSV Revision Reason for issue Date Created by Contr. by Appr. by Title: ERTMS - National implementation
Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa
Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Contents Features of Project Finance Challenges posed by Project Finance Risk assessment
Electric vehicles or use of hydrogen in the Norwegian transport sector in 2050?
Electric vehicles or use of hydrogen in the Norwegian transport sector in 2050? Klaus Skytte DTU Management Engineering Energy Economics and Regulation [email protected] TOP NEST workshop - WP2 NIFU, Oslo, 2
Gharbeya Water and Wastewater Company - Background
Gharbeya Water and Wastewater Company - Background The Gharbeya company is located in the Delta Population: 4,170,000 Water coverage: 90% Water accounts: 730,000 Wastewater coverage: 35% Wastewater accounts:
SINTEF Energy Research
SINTEF Energy Research We develop solutions for the great challenges of our time. We are an internationally leading research and knowledge institute. We create business opportunities and values for the
Licensing system in Norway. Steinar Njå Norwegian Petroleum Directorate
Licensing system in Norway Steinar Njå Norwegian Petroleum Directorate Licensing system in Norway Discretionary system The Government invites companies to apply for exclusive rights to petroleum activities
PhD project description The use of TBM in future Norwegian infrastructure projects
NTNU - The Norwegian University of Science and Technology PhD project description The use of TBM in future Norwegian infrastructure projects PhD candidate: Øyvind Dammyr Main supervisor: Professor Bjørn
Third quarter results 2015
1 Third quarter results 2015 30 October 2015 Peter A. Ruzicka, President & CEO Improved performance in the third quarter 2.3% organic growth 1 15% EBIT (adj.) 2 growth in BCG 57% increase in EPS 2 1 Reported
Rail Contractors Liability Insurance
Rail Contractors Liability Insurance (Please ensure that proposal is completed in full and is clear and legible) 1. Applicant Details Full Trading Name: (this should be name required in the policy) Address:
Goliat Barrier Management
Goliat Barrier Management ESRA Norge; March 25, 2015 www.eninorge.com Eni: Ole Rekdal Safetec: Helene Ness Hansen PL 229 Goliat Location and Partnership License awarded in 1997 Present licensees Eni Norge
Construction Services
Construction Services Construction Turning innovative ideas into delivered solutions At Golder Associates we strive to be the most respected global company providing consulting, design, and construction
Public Transport in the Oslo Region
Public Transport in the Oslo Region CEO Bernt Reitan Jenssen,, Ruter As Welcome to Ruter Office location at Jernbanetorget Jernbanetorget,, Central Station Square Ruter is Public Transport Authority in
EPIM LogisticsHub (ELH)
EPIM LogisticsHub (ELH) A common knowledgebase for tracking Cargo Carrying Units (CCUs) and equipment in the Norwegian Offshore Industry Dr. Thore Langeland Strategic Adviser, EPIM [email protected] +47 9095
PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA
PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA Table of content 1. INTRODUCTION... 2 1.1. Purpose of document... 2 1.2. Det norske oljeselskap... 2 1.3. HSE... 2 2. ABOUT THE IVAR AASEN FIELD... 2 2.1.
REPORT 1405. Bjørn G. Bergem, Arild Hervik and Oddmund Oterhals SUPPLIER EFFECTS ORMEN LANGE 2008-2012
REPORT 1405 Bjørn G. Bergem, Arild Hervik and Oddmund Oterhals SUPPLIER EFFECTS ORMEN LANGE 2008-2012 Bjørn G. Bergem, Arild Hervik and Oddmund Oterhals Supplier effects Ormen Lange 2008 2012 Report 1405
Company Overview. Chieti, May 7 th 2012
Chieti, May 7 th 2012 AGENDA 1 Toto Group Structure 2 Toto S.p.a. Costruzioni Generali: Overview 3 Business Interests 4 5 6 7 8 Toto s Strenght: Know How Toto s Technological Assets The Construction Business
Odfjell Drilling Ltd.
Odfjell Drilling Ltd. Report for the 3 rd quarter of 2015 This interim report is unaudited and has been prepared in accordance with IAS 34 Interim Financial Reporting. Key figures for the Group All figures
Third quarter results 2014
Third quarter results 2014 Highlights Third quarter 2014 High operational activity H6 rig upgrade completed ahead of time Cooperation with KBR for Sverdrup Study awarded for Subsea on a Stick Order backlog
The FIDIC Suite of Contracts
Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October
Role in the project (e.g. Prime Engineering Consultant or Contractor), and summary of professional Duties : Name Professional Duties Contract Awarded?
PROPOSAL FORM FOR SINGLE PROJECT PROFESSIONAL INDEMNITY NOTE: THIS IS A PROPOSAL FOR A CLAIMS MADE POLICY Note : Please provide any necessary explanations or additional details by attachment to this Proposal
Global Infrastruktur I AS
Kundeseminar, Felix konferansesenter 8. oktober 2015 2007 Etableringsår 2 928 Norske aksjonærer 2,8 mrd. NOK Markedsverdi av porteføljen 98 øre/aksje Totale utbetalinger 42 % Totalavkastning siden start
Mini-guide for. Foreign businesses and employees. in connection with assignments in Norway or on the Norwegian continental shelf
Mini-guide for Foreign businesses and employees in connection with assignments in Norway or on the Norwegian continental shelf Central Office - Foreign Tax Affairs (COFTA) January 2011 Foreign businesses
Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities
At Macau International Airport (RFQ-198) Section 6 Bill of Quantities Bill Nr. 1 Preliminaries Bill Nr. 1 PRELIMINARIES NOTES : (1) The work shall be done during day time and night time according to CAM/ADA
Sri Lanka Accounting Standard -LKAS 11. Construction Contracts
Sri Lanka Accounting Standard -LKAS 11 Construction Contracts -405- Sri Lanka Accounting Standard -LKAS 11 Construction Contracts Sri Lanka Accounting Standard LKAS 11 Construction Contracts is set out
Why is Insurance Paramount in the Construction Arena"
Why is Insurance Paramount in the Construction Arena" 4th EPMIF AN EIMS PRESENTATION Cas Hansa March 2009 Synopsis A A 'thumbnail' view of the scope of a typical Contractor's All Risks (projects works)
International Accounting Standard 11 Construction Contracts
International Accounting Standard 11 Construction Contracts Objective The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts.
Nettpartner Group. Company Presentation
Nettpartner Group Company Presentation Vision and Mission Nettpartner the company all others in the industry want to emulate! Nettpartner shall be a leading supplier of innovative solutions linked to the
Accounting & Finance 2 0 1 5 S A L A R Y G U I D E
Accounting & Finance AED (Gross monthly salaries excluding bonuses and education allowance, if applicable) Chief Financial Officer 75,000 55,000 90,000 Chief Accountant 18,000 14,000 22,000 Commercial
Engelsk. Norwegian Food and Allied Workers Union. Welcome to NNN
Norwegian Food and Allied Workers Union Engelsk Welcome to NNN As a member, your interests will be protected to the greatest degree possible, particularly in relation to pay and working conditions. In
How To Make Money From The Stock Market In Nok
SKAGEN Vekst Status as of 30-09-05 Why SKAGEN Vekst? Balanced portfolio adapted to Norwegian investors Better geographic spread than pure Norwegian fund Better industry balance than a Norwegian fund =
Task Order Manager. Project Planning, Engineering, Architecture service contract with experience in passenger rail or other modes, and
a) Offerors shall provide resumes for their Key Personnel, as identified below. The page count for each resume shall not exceed three (3) pages. Preferred professional qualifications of key personnel are
Application of IEC 61508 and IEC 61511 in the Norwegian Petroleum Industry
Application of IEC 61508 and IEC 61511 in the Norwegian Petroleum Industry Lars Bodsberg Research Director SINTEF, Trondheim, Norway [email protected] http://www.sintef.no/ 30 November 2005 Delft,
Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.
Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr. Civil Engineer Public Power Corporation, Greece Public Power Corporation
COWI TANZANIA LTD WELCOME TO OUR WORLD OF CONSULTANCY WITHIN ENGINEERING, ENVIRONMENT AND ECONOMICS
COWI TANZANIA LTD WELCOME TO OUR WORLD OF CONSULTANCY WITHIN ENGINEERING, ENVIRONMENT AND ECONOMICS COWI TANZANIA CORE SERVICE LINES Development assistance Urban and regional development Environmental
Risk Management and Insurance For U.S. Offshore Wind Projects. Jeff Kehne Sept. 14, 2011
Risk Management and Insurance For U.S. Offshore Wind Projects Jeff Kehne U.S. Offshore Wind Project Risk Profile Character and Incidence of Risks Change as Projects Progress Leasing and Permitting Owners
DNO ASA Corporate Presentation and Update
DNO ASA Corporate Presentation and Update Haakon Sandborg, CFO Swedbank Nordic Energy Summit 19 March 2015 Oslo, Norway DNO at a glance Norwegian oil and gas operator focused on the Middle East and North
Empirics of the Oslo Stock Exchange. Basic, descriptive, results.
Empirics of the Oslo Stock Exchange. Basic, descriptive, results. Bernt Arne Ødegaard University of Stavanger and Norges Bank Mar 2011 We give some basic empirical characteristics of the Oslo Stock Exchange
Construction Contracts
STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.
Applicability / Objective
By Rakesh Agarwal Applicability / Objective APPLICABILITY: applicable to all contracts entered into on or after 1-4-2003 and is mandatory in nature from that date. Based on AS 7 (Construction Contracts)
Hydroelectric Power Plant - Los Cóndores. Santiago, April 2014
Hydroelectric Power Plant - Los Cóndores Santiago, April 2014 Introduction Los Cóndores, a large hydro project of 150 MW with water flow regulation using the existing water reservoir of the Embalse Laguna