1 DATA CENTER Two Phase Approach Located at the State Defense Building July 17, 2015 Compiled by: Office of Facilities and Property Management 800 SW Jackson, Suite 600 Topeka, Kansas i

2 I. Programming Committee Jim Clark Executive Branch CIO and OITS Director Secretary, Mark J. McGivern Cliff Flowers Frank Burnam Christine Simons George Steele Donna Shelite Jay Coverdale Jennifer Busch Loren Westerdale Nathan Ensz Travis Combes Bill Kelly Director, Office of Facilities and Property Management Deputy Director, Facilities Maintenance Office of Facilities and Property Management Deputy Director, Design, Construction & Compliance Office of Facilities and Property Management Deputy Director, Building Services and Grounds Office of Facilities and Property Management Deputy Director, Engineering Office of Facilities and Property Management Chief of Staff Office of Information and Technology Services Director, Telecommunications Group Office of Information and Technology Services Project Manager, Innovation Group Office of Information and Technology Services Director, Information Services Office of Information and Technology Services Project Manager, Innovation Group Office of Information and Technology Services Cloud Services Group Office of Information and Technology Services Telecommunications Group Office of Information and Technology Services ii

3 Table of Contents I. Programming Committee... ii II. Program for the Proposed Data Center... 1 A. Introduction... 1 B. Existing Conditions... 1 C. Applicable Codes... 1 D. General Considerations State Defense Building Parking Data Center General Requirement... 3 E. Data Center Phase F. Data Center Phase Room Renovation Data Center Cooling Fire Suppression Electrical Underground Fuel Storage Tanks... 6 III. Project Schedule and Other Attached Documents... 7 A. Schedules Schedule SDB Data Center Schedule... 7 B. Other Attached Documents Data Center Servers Floor Plan Space Layout... 7 IV. Project Budget... 8 A. Cost Estimate Phase B. Cost Estimate Phase iii

4 II. Program for the Proposed Data Center A. Introduction The is actively pursuing the relocation of the existing Data Centers in various State Office Building to a centralized location. B. Existing Conditions The Capitol Complex is served by various data centers in State Office Buildings in the Capital Complex. The State of Kansas is interested in moving the Office of Information Services (OITS) Data Center from the Landon State Office Building to the State Defense Building, located at 2722 SW Topeka, Blvd., Topeka, Kansas. The State Defense Building approximately 55,098 gross square feet with 28,423 square feet on the lower level and 26,675 square feet on the upper level. Other Data Centers have sprung up around the campus in Curtis, Docking, Eisenhower and other small agencies. The infrastructure for these centers is weak, as some do not have features like redundancy, proper cooling systems, size of electrical services, size of backup power, age, and disaster protection. It has been observed some have been used improperly for storage. This project is an effort to consolidate the data center function of various agencies in a properly supported, designed, and secured location. C. Applicable Codes The consultants shall evaluate the building for code compliance. The following code summary is included as a reference only. International Building Code (IBC), 2012 Edition. a. Chapter 11, Accessibility, is deleted. See Item M below. b. Additionally, The Life Safety Code (NFPA 101) will also be applicable for Occupancies described in Item I. and J below. International Building Fire Code (IFC), 2012 Edition International Residential Code (IRC), 2012 Edition International Existing Building Code (IEBC), 2012 Edition International Mechanical Code (IMC), 2012 Edition International Plumbing Code (IPC), 2012 Edition International Fuel Gas Code (IFGC), 2012 Edition 1

5 International Energy Conservation Code (IECC), 2012 Edition or ASHRAE The codes and standards referenced in the Referenced Standards Chapters in the IBC, IFC, IRC, IMC, IPC, IFGC and IECC shall be applicable except for NFPA codes noted in Item I and J below. The NFPA editions noted in Items I. and J. shall be applicable. National Fire Protection Association (NFPA), National Fire Codes and Standards for occupancies other than Healthcare occupancies described in Item J.: NFPA Edition Portable Fire Extinguishers NFPA 13, 13D and 13R 2013 Edition - Installation of Sprinkler Systems NFPA Edition Installation of Standpipe and Hose Systems NFPA Edition Testing Fire Sprinkler Systems NFPA Edition National Electric Code (NEC) NFPA Edition National Fire Alarm Code NFPA Edition Life Safety Code only applicable to adult and boarding care homes per KSFM K.A.R NFPA Edition Emergency and Standby Power Systems Kansas Fire Prevention Code (This code combines many different documents including Kansas Statutes Annotated (K.S.A.) and Kansas Administrative Regulations (K.A.R.)). A list of pertinent statutes and regulations can be found at the Kansas State Fire Marshal website at K.S.A et. Seq ADA Standards for Accessible Design (2010 ADA Standards) Kansas State Boiler Code (K.S.A et seq) available through the Office of the State Fire Marshal (OSFM) at D. General Considerations 1. State Defense Building The Adjutant General is planning to vacate space in the State Defense Building and relocate its operations to Joint Base Forbes Field. The current State Defense Building was built in 1977 and half buried in the ground to protect it from most disasters. The building has two floors with an elevator. The building has two raised floor areas - conference and meeting rooms. The heating and air conditioning has recently been refurbished. The facility is currently served by 750 kva electrical service. Westar Electric reports the peak usage for the service was 300 kw. The lowest usage was in December with 184 kw. The average usage is approximately 250 kw. 2

6 The existing facility is equipped with a 1200 kva, 800 kw backup generator. The current Data Center space at the State Defense Building is a 20 ft. by 80 ft. addition to the existing building. The Adjutant General s office currently utilizes 750 SF of the addition for their data center. The remaining 680 SF of the existing data space is available for expansion. The data center has a gaseous suppression system covering the whole addition. They are using an APC hot aisle/ Cold aisle arrangement with 4 direct expansion APC cooling condensers outside to the east. The current data room will move out to the Joint Base Forbes Field over the course of the next couple of years. The current facility does not have an OITS connection to the OITS network. Currently the Kansas Highway Patrol is hosting some of their Data Center equipment at this facility. They are connected to the KANWIN Network through Cox Communications. The Cox Communication link is only 200 megabits. The OITS office relocation plan for the State Defense Building is for OITS to occupy approximately 22,000 square feet of office space. The planned move will be for OITS to move its personnel into the initially vacated space on the 1st floor of the State Defense Building. This space currently houses 105 people. Training and Shared spaces will be available to both OITS and the Adjutant General until the Adjutant General vacates the building. The Adjutant General is interested in keeping telecommunications separate and secure during joint occupancy with OITS. 2. Parking The facility has parking on four sides approximately 33 in front, 38 north of the building, 34 in the south lot, and 60 in the east lower lot. Existing parking around the facility will be utilized. 3. Data Center General Requirement The data center shall be configured for reliability and designed to resist tornadoes, flooding, by its locations-bombs, and other natural disasters. The facility shall have hardened walls for security. The facility shall be designed to withstand terroristic threats (Homeland Security), and catastrophic events (i.e. tornado, power outages, flood. etc.). The data center shall be provided with data room cooling, power protections systems, diesel engine driven generation equipment, fuel storage, cooling equipment, electrical switchgear, and redundant electrical service. The data room inside the building will be constructed out of the existing space, in the east side of the lower level, in the State Defense Building. The room is located in the lowest level of the building, in a block reinforced room, protecting it from explosions. The building security for walkin attack will be provided by electronic door security. The existing doors may need to be modified to move equipment into the building. Data Center doors need to be 42 wide and 80 tall. Door coming in from the loading dock needs to be raised to at least The concrete floors will need to be sealed. The room is currently being programmed to have standby power provided by On-Site generators. The power to the facility will provide redundancy for equipment failures. 3

7 A Tier I data center requires the following (Uptime Institute, LLC, Data Center Site Infrastructure Tier Standard: Topology, 2.4) 1. Single non-redundant distribution path serving the IT equipment. 2. Non-redundant capacity components. 3. Fault-tolerant site infrastructure with electrical power storage and distribution facilities guaranteeing % availability. This would allow minutes or hours per year. In phase 1, the existing data room equipment will be extended. In phase 2, the room in its final configuration will be approximately 2500 square feet. It is to include new UPS, PDUs, RPPs, and in-row cooling. Provide integral cable tray for IT Cabling and power wiring. The rooms will be configured as a Tier IV data center. A Tier IV data center requires the following (Uptime Institute, LLC, Data Center Site Infrastructure Tier Standard: Topology, 2.4) 1. Multiple independent distribution paths serving the IT equipment. 2. All IT equipment must be dual-powered and fully compatible with the topology of the site s architecture. 3. All cooling equipment is independently dual-powered, including chillers, and heating, ventilating and air conditioning (HVAC) System 4. Fault-tolerant site infrastructure with electrical power storage and distribution facilities guaranteeing % availability. This would allow minutes per year. The initial plan is to work with 20 racks to accommodate one leg of the cloud and some for networking equipment. The growth of the data center will be determined by funding, scheduling of the moves out of the other data centers. They currently have space needs for 74 racks. They have 100 racks planned in total. They are planning a 2 to 3 year transition. The cabling shall be integral to the racks. Racks should have built in cable trays. Adjustments to the ceiling, lighting, fire alarm, and existing convenience outlets might be necessary to accommodate the equipment. Nothing is planned in phase 1. A man trap double door security entrance will not be needed; if the outer exit door is sealed off. The set of doors between the hall and data center; dock and data center are to be key carded. Minor adjustments to openings may need to be completed to allow equipment to be moved into the space. Adjacent Space shall be provided for storage, secure storage, receiving and package breakdown. Existing space is available for receiving and package breakdown and will be shared with the Adjutant General while they occupy the facility. 4

8 E. Data Center Phase 1 In phase 1, the existing 680 SF of east data room will be utilized for the relocation of OITS equipment. Twenty (20) existing OITS racks will be moved into this existing space. The approximate load will be 130 kva. UPS, and cooling equipment will need to be purchased, and installed. The room is currently provided with a gaseous fire suppression system. Space will be prepared for 5 outside air conditioning condensing units and installation of 5 in-row cooling units. Existing electrical service will be expanded and used to serve this load. Phase 1 will also include the moving of 5 racks (34kVA) of equipment from the Department of Revenue into existing space to be prepared for connection. F. Data Center Phase 2 In Phase 2, the facility shall be equipped with redundant incoming power, redundant generating capacity, and redundant cooling. The Data Center shall be equipped with traditional or scalable UPS. The plan is to provide building support for a data center in the basement of the building. 1. Room Renovation The existing 2500 square feet of office space on the lower level of the east side of the existing building will be converted into a data room. The existing wall partitions, ceilings and lights will be removed, as necessary. The room will be sealed up for the fire suppression system. New man trap security doors will be added to this area. New general lighting will be added to the room. 2. Data Center Cooling At this point, the existing east data center will be operating on the 9 direct expansion cooling units. An option would be to add 18 more cooling/condenser units plus 2 units additional for some redundancy to the units (N+2). This option allows the continuation of using the direct expansion cooling systems. The direct expansion equipment could be changed out with two new chillers to the system each capable of handling the total load and the interior units converted or changed to chilled water system. Additional chilled water cooling units will be added to the new data center room. The existing direct expansion cooling units can be replaced one at a time in the existing data center to the new chilled water cooling units. Redundant chilled water pumps and piping will be added. Cooling for the data center shall also be 100% redundant. The cooling units shall be sized to cool 500 kw of computing power. It shall also be capable of being scalable as the data center is built out and still be able to operate properly. Condensing units shall be designed to resist terroristic threats, and catastrophic events (i.e. tornado, power outages, flood. etc.). Location for the needed circulation pumps, expansion tank, etc. will have to be determined. Space in the existing mechanical room may be available. 5

9 3. Fire Suppression The existing fire sprinkler system will need to be removed and a new gaseous (FM200) fire suppression system will need to be installed. The room will need to be sealed for the system to function properly. A new gaseous fire suppression system will be added to the room. 4. Electrical The consultants shall evaluate and recommend the most cost effective design, and properly sizing utility-supplied, transformers, electrical service equipment, generators, and UPS equipment. The data center is programmed to require approximately 400 kw of load in order to support the desired IT equipment and associated computing equipment. The estimated power usage effectiveness (PUE) is a simple ratio of the total power entering the data center divided by the power used by the information technology equipment. The value of 1.8 is assumed for this data center, resulting in a total power usage of approximately 900 kw. If a power factor of.8 is assumed, the total power consumption of the data center will be approximately 1125 kva. A new redundant incoming power services shall be provided. A new 1125 kva transformer will be added to the facility. It will be connected to new electrical service equipment. The existing 750 kva transformer will have to be changed to an 1125 kva transformer to have the capacity to carry the whole load. This new transformer will need to be added to the new switchgear. Double ended switchgear will be added with tiebreaker between the new service from Westar and the existing service. Electrical switchgear shall be designed to have full redundancy with a main-tie-main configuration. The capacity shall be sufficient to carry the full load of the IT equipment, accessories, and cooling equipment. Utilize the existing 120/208 volt, 3 phase, 4 wire configuration. The switchgear shall be mounted internally and protected like the generators and data room from threats. Another UPS will need to be added to the system for the new room. A back up UPS will need to be added for the existing UPS equipment. Redundant uninterruptable power supplies (UPS) shall be provided for the IT Loads. This may be standalone units or scalable within the Data Center. Power Distribution units (PDU) will be provided in the data center. These PDUs shall be incorporated into the rack system that is provided as a part of the interior data center layout. 5. Underground Fuel Storage Tanks Existing fuel storage tanks for backup fuel for the generators will be used. 6

10 III. Project Schedule and Other Attached Documents A. Schedules 1. Schedule SDB Data Center Schedule B. Other Attached Documents 1. Data Center Servers 2. Floor Plan 3. Space Layout 7

11 IV. Project Budget A. Cost Estimate Phase 1 Data Center to Tier IV - Additional 103 kw Phase 1 - Finish 680 SF Data Center Space Units Costs Building renovation 0 SF $8.00 $0 Fire Protection (Stand Alone FM200) 0 SF $81.25 $0 Entrance Door 0 ea $3, $0 Hot Row Containment 680 SF $7.25 $4,930 Concrete Pad 400 SF $20.00 $8,000 Mechanical APC Cooling Units 4 units $45, $180,000 controls 680 ea $28.15 $19,142 Electrical UPS- 150 kw 1 ea $137, $137,500 PDUs kva ea 1 ea $35, $35,000 PDU Cables 680 SF $52.50 $35,700 Feeders 680 SF $ $106,216 Security -Cameras & Doors 680 SF $2.00 $1,360 Lighting 0 SF $1.00 $0 Miscellaneous 680 SF $0 Electrical Service Westar $0 Total $527,848 Supervision $0 Taxes 8% $42,228 Estimating Contingency 5% $26,392 Sub-Total $596,468 OH&P Prime 10% $59,647 Contingency 5% $29,823 Construction Total $685,938 Engineering Fee-9% 9% $61,734 DCC Fee (1.25%) 1.25% $8,574 Total $756,247 8

12 B. Cost Estimate Phase 2 Data Center to Tier IV - Additional 300 kw Phase 2 - Finish 2500 SF Data Center Space - Add redundancy Costs Building renovation 2500 SF $8.00 $20,000 Fire Protection (Stand Alone FM200) 2500 SF $81.25 $203,125 Demo Sprinklers 2500 SF $2.00 $5,000 Entrance Door 2 ea $3, $6,000 Hot Row Containment 2500 SF $7.25 $18,125 Concrete Pad 1600 SF $20.00 $32,000 Demo generator 1 ea $5, $5,000 Mechanical APC Cooling Units 18 units $45, $810,000 controls 1 ea $72, $72,500 Electrical 1200 kva Transformer 2 ea $5, $10,000 Main Switchgear - Main-Tie-Main 1 ea $220, $220, Amp 2 ea $10, $21,000 Generator-1200kW - 24 Day tank 1 ea $140, $140,000 Fuel Storage Tank 1 ea $10, $10,000 UPS- 500 kw kw ea. 4 ea $137, $550,000 Lightning Protection 1 ea $14, $14,500 PDUs kva ea 2 ea $35, $70,000 PDU Cables 2500 SF $52.50 $131,250 Feeders 2500 SF $ $390,500 Fire Alarm 2500 SF $7.00 $17,500 Security -Cameras & Doors 2500 SF $2.00 $5,000 Lighting 2500 SF $1.00 $2,500 Miscellaneous 2500 SF $0 Electrical Service Westar $100,000 Total $2,854,000 Supervision $0 Taxes 8% $228,320 Estimating Contingency 5% $142,700 Sub-Total $3,225,020 OH&P Prime 10% $322,502 Contingency 5% $161,251 Construction Total $3,708,773 Engineering Fee-9% 9% $333,790 DCC Fee (1.25%) 1.25% $46,360 Total $4,088,922 Alternates Raised Floor 2500 $1.95 $4,875 Raised Floor Grounding $32,825 9

13

14

15

16

17

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0. Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M

More information

AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ)

AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ) AT&T Internet Data Center Site Specification - Phoenix Area (Mesa, AZ) Site Biography Market Area: Phoenix, Mesa, Tempe, Chandler, Scottsdale, AZ Location: Mesa, AZ 85201 Address: 1301 University Blvd.

More information

AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL)

AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL) AT&T Internet Data Center Site Specification Chicago Area (Lisle, IL) Site Biography Market Area: Chicago, IL Location: Lisle, IL 60532 Address: 4513 Western Avenue CLLI,POP, NPA/NXX Code: LSLEILAA, EQLAILAA

More information

OPERATOR - FACILITY ADDRESS - DATE

OPERATOR - FACILITY ADDRESS - DATE . Facility Criteria (RFP).0 Location Characteristics Criteria Requirements 1 Ownership and Management: Please identify the owner(s) and managers of the property and indicate if there is on-site management.

More information

AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA)

AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA) AT&T Internet Data Center Site Specification San Diego Koll (San Diego, CA) Site Biography Market Area: San Diego, CA Location: San Diego, CA 92121 Address: 5732 Pacific Center Blvd CLLI,POP, NPA/NXX Code:

More information

N O W A V A I L A B L E

N O W A V A I L A B L E N O W A V A I L A B L E 5 0, 0 0 0 S F P O W E R E D S H E L L D A T A C E N T E R I I Data Center Park Catawba County, North Carolina S P E C I F I C A T I O N S Contact Doug Hollidge for more information

More information

AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA)

AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA) AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA) Site Biography Market Area: Washington, DC Area Location: Ashburn, VA 20147-6011 Address: All deliveries should be sent to

More information

100 Locust Avenue, Berkeley Heights, New Jersey P R O P E R T Y O F F E R I N G

100 Locust Avenue, Berkeley Heights, New Jersey P R O P E R T Y O F F E R I N G 100 Locust Avenue, Berkeley Heights, New Jersey P R O P E R T Y O F F E R I N G The Opportunity Jones Lang LaSalle, Inc. (the Broker ) is please to offer the fee simple interest in 100 Locust Avenue (the

More information

Scalable. Affordable. Flexible. Fast.

Scalable. Affordable. Flexible. Fast. Modular Data Center Solutions Scalable. Affordable. Flexible. Fast. Build the data center you need today with the flexibility to meet tomorrow s challenges The only constant in business is change. Fluctuations

More information

IBM Twin Data Center Complex Ehningen Peter John IBM BS peter.john@de.ibm.com. 2011 IBM Corporation

IBM Twin Data Center Complex Ehningen Peter John IBM BS peter.john@de.ibm.com. 2011 IBM Corporation IBM Twin Data Center Complex Ehningen Peter John IBM BS peter.john@de.ibm.com Overview Profile IBM owned facility 6447 m² IT-Space Infrastructure concurrent maintainable (Tier Level 3) Feed-ins of Power

More information

About Injazat. Enterprise Cloud Services. Premier Data Center. IT Outsourcing. Learning and Development Services. Enterprise Application Services

About Injazat. Enterprise Cloud Services. Premier Data Center. IT Outsourcing. Learning and Development Services. Enterprise Application Services About Injazat Injazat Data Systems is an industry-recognized market leader in the region for Information Technology Outsourcing, Cloud and Data Center Managed Services delivered from the region s 1st Tier

More information

Establishment of State s Second Data Center. Business Continuity and Disaster Recovery. North Carolina. Office of Information Technology Services

Establishment of State s Second Data Center. Business Continuity and Disaster Recovery. North Carolina. Office of Information Technology Services Establishment of State s Second Data Center North Carolina Office of Information Technology Services National Association of State Chief Information Officers 2008 Recognition Awards Nomination June 2,

More information

Introducing UNSW s R1 Data Centre

Introducing UNSW s R1 Data Centre Introducing UNSW s R1 Data Centre R1-DC Our New High Density Data Centre Right here Right now - Welcome to our newest UNSW Data Centre R1-DC R1 Location on UNSW Randwick campus. Keeping it in the family

More information

Subject: County of Los Angeles Data Center Space Requirement

Subject: County of Los Angeles Data Center Space Requirement Subject: County of Los Angeles Data Center Space Requirement The County of Los Angeles, Chief Executive Office, Real Estate Division (CEO-RED) is issuing this Property Search for the purchase of a vacant,

More information

19 Site Location, Design and Attributes. Site Location, Design and Attributes

19 Site Location, Design and Attributes. Site Location, Design and Attributes 1 Site Location, Design and Attributes The Primary Data Center shall be physically located on Oahu, Hawaii. 2 Site Location, Design and Attributes The Primary Data Center shall be located at least 1 mile

More information

NORTHERN VIRGINIA ONE (NoVa) DATA CENTER OVERVIEW

NORTHERN VIRGINIA ONE (NoVa) DATA CENTER OVERVIEW VAZATA 9651 Hornbaker Road Manassas, VA 20109 VAZATA.COM VAZATA's NoVa One data center located at 9651 Hornbaker Road in Manassas, Virginia is engineered from the ground up to deliver highly reliable and

More information

Electrical. This section applies to the design and installation of building power distribution systems.

Electrical. This section applies to the design and installation of building power distribution systems. Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions

More information

How To Visit An Internet Data Center

How To Visit An Internet Data Center AT&T Internet Data Center Site Specification Atlanta Area (Lithia Springs, GA) Site Biography Market Area: Atlanta and surrounding areas (Georgia, Alabama, Tennessee, Florida, North and South Carolina

More information

AT&T Internet Data Center Site Specification New York III (Secaucus, NJ)

AT&T Internet Data Center Site Specification New York III (Secaucus, NJ) AT&T Internet Data Center Site Specification New York III (Secaucus, NJ) Site Biography Market Area: New York City, New Jersey, Upstate NY and Lower Connecticut Location: Secaucus, NJ 07094 Address: 15

More information

Datacentre South London Data sheet

Datacentre South London Data sheet Datacentre South London Data sheet Data sheet Datacentre South London Find us With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our datacentre locations, Pulsant has the infrastructure

More information

APC APPLICATION NOTE #112

APC APPLICATION NOTE #112 #112 Best Practices for Deploying the InfraStruXure InRow SC By David Roden Abstract The InfraStruXure InRow SC (ACSC100 and ACSC101) is a self-contained air conditioner for server rooms and wiring closets.

More information

As close to perfection. development and production. Modular data center

As close to perfection. development and production. Modular data center As close to perfection development and production Modular data center August 2014 What is GreenMDC modular data center? Basically it is the modular design construction which is realized by the principle

More information

Data Centers, Information Technology and Low Current Services

Data Centers, Information Technology and Low Current Services Data Centers, Information Technology and Low Current Services 1 Data Centers and Low Current Services SDT offers a wide-ranging variety of professional services to Data Centres and Low Current operators.

More information

in other campus buildings and at remote campus locations. This outage would include Internet access at the main campus.

in other campus buildings and at remote campus locations. This outage would include Internet access at the main campus. DATA CENTER The current Campus Data Center is located within historic Founders Hall which is in a less-than ideal location for a variety of reasons, but is typical of an existing campus IT infrastructure

More information

Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design.

Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design. Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design. Equinix Telecity Kvastvägen 25-29 128 62 Sköndal Stockholm Sweden Tel: +46 (0) 8 799 3800 se.info@telecity.com www.telecitygroup.se

More information

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management. AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled

More information

Datacentre Reading East 2 Data sheet

Datacentre Reading East 2 Data sheet Datacentre Reading East 2 Data sheet Data sheet Datacentre Reading East 2 Find us With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our datacentre locations, Pulsant has the

More information

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management. AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled

More information

Data Center CH1. Elk Grove Village, IL

Data Center CH1. Elk Grove Village, IL Data Center CH1 Elk Grove Village, IL powerful/ efficient /reliable solutions > Data Center CH1 ABOUT DUPONT FABROS TECHOLOGY (DFT) DFT is a leading owner, developer, operator and manager of wholesale

More information

Technical specifications. Containerized data centre NTR CDC 40f+

Technical specifications. Containerized data centre NTR CDC 40f+ Technical specifications Containerized data centre NTR CDC 40f+ CONTENT 1 THE PURPOSE OF CDC... 3 2 BASIC PROPERTIES... 4 2.1 EXTERNAL DIMENSIONS... 4 2.2 INSTALLATION REQIREMENTS... 4 2.3 ELECTRICAL CONNECTION

More information

Data Centre Testing and Commissioning

Data Centre Testing and Commissioning Data Centre Testing and Commissioning What is Testing and Commissioning? Commissioning provides a systematic and rigorous set of tests tailored to suit the specific design. It is a process designed to

More information

POLK STATE COLLEGE CHILLER PLANT EVALUATION WINTER HAVEN, FLORIDA APRIL 2, 2014. C arastro & A ssociates, C&A# 5747

POLK STATE COLLEGE CHILLER PLANT EVALUATION WINTER HAVEN, FLORIDA APRIL 2, 2014. C arastro & A ssociates, C&A# 5747 POLK STATE COLLEGE WINTER HAVEN, FLORIDA CHILLER PLANT EVALUATION APRIL 2, 2014 C&A# 5747 C arastro & A ssociates, c o n s u l t i n g e n g i n e e r s inc. 2609 W. De Leon Street, Tampa, Florida 33609

More information

Data Center Presentation

Data Center Presentation Data Center Presentation The NetSource Datacenter. Agenda General Layout of Data Center Policies and Procedures Designed to Latest Standards High Performance High Reliability High Security Design Details

More information

Data Centre Barrie, Ontario

Data Centre Barrie, Ontario COGECO DATA SERVICES DATA CENTRE Data Centre Barrie, Ontario Cogeco Data Services offers flexible, secure, connected and fully managed ICT solutions at its Flagship Data Centre in Barrie, Ontario Data

More information

PUBLIC NOTICE State of Kansas. Request for Proposal Leased Office Space

PUBLIC NOTICE State of Kansas. Request for Proposal Leased Office Space PUBLIC NOTICE State of Kansas Request for Proposal Leased Office Space The Kansas Department of Credit Unions is accepting written proposals for approximately 2,250 square feet of renovated or new office

More information

Optimum Climate Control For Datacenter - Case Study. T. Prabu March 17 th 2009

Optimum Climate Control For Datacenter - Case Study. T. Prabu March 17 th 2009 Optimum Climate Control For Datacenter - Case Study T. Prabu March 17 th 2009 Agenda 2 About EDEC (Emerson) Facility Data Center Details Design Considerations & Challenges Layout Design CFD Analysis Of

More information

TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST

TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST In order to provide a comprehensive plan review in a timely manner, and to insure the design and installation of fire alarm systems

More information

Education Evolution: Scalable Server Rooms George Lantouris Client Relationship Manager (Education) May 2009

Education Evolution: Scalable Server Rooms George Lantouris Client Relationship Manager (Education) May 2009 Education Evolution: Scalable Server Rooms George Lantouris Client Relationship Manager (Education) May 2009 Agenda Overview - Network Critical Physical Infrastructure Cooling issues in the Server Room

More information

Building Description Project Description Estimated Cost Notes Total Deferred

Building Description Project Description Estimated Cost Notes Total Deferred Building Description Project Description Estimated Cost Notes Total Deferred Athletic Fields & Grounds Baseball dugouts 125,000 Surface level/inground? Relamp Baseball field 16,000 Relamp Softball field

More information

Recommendations for Measuring and Reporting Overall Data Center Efficiency

Recommendations for Measuring and Reporting Overall Data Center Efficiency Recommendations for Measuring and Reporting Overall Data Center Efficiency Version 2 Measuring PUE for Data Centers 17 May 2011 Table of Contents 1 Introduction... 1 1.1 Purpose Recommendations for Measuring

More information

Location. Central Business District. Ataturk Airport IFC. Sabiha Gökçen Airport

Location. Central Business District. Ataturk Airport IFC. Sabiha Gökçen Airport Welcome Zenium Istanbul One provides 12,000 square metres of high specification technical space across three purpose-built data centers. It is Turkey s first wholesale data center offering; the data halls

More information

Experience Matters...

Experience Matters... Experience Matters... Travelport Data Center offers confidence and space to meet your demanding IT needs Transwestern presents the Travelport Data Center in Denver, Colorado totaling 267,000 SF with 121,600

More information

ISOMEDIA COLOCATION WWW.ISOMEDIA.COM/COLOCATION

ISOMEDIA COLOCATION WWW.ISOMEDIA.COM/COLOCATION ISOMEDIA COLOCATION WWW.ISOMEDIA.COM/COLOCATION Your business needs a robust infrastructure that is secure, cost effective and reliable in order to remain competitive in today s market. ISOMEDIA s colocation

More information

Introduction to Datacenters & the Cloud

Introduction to Datacenters & the Cloud Introduction to Datacenters & the Cloud Datacenter Design Alex M. Hurd Clarkson Open Source Institute March 24, 2015 Alex M. Hurd (COSI) Introduction to Datacenters & the Cloud March 24, 2015 1 / 14 Overview

More information

Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers

Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers Prepared for the U.S. Department of Energy s Federal Energy Management Program Prepared By Lawrence Berkeley National

More information

COMMODITIZING THE DATA CENTER MARKET

COMMODITIZING THE DATA CENTER MARKET COMMODITIZING THE DATA CENTER MARKET Site Summary The building at 1360 Kifer Road has approximately 94,500 SF of server and support space and is currently divided into two independent data center areas.

More information

Tour of new eircom Data Centre Blanchardstown by Dervan Engineering Consultants 11 th March 2015

Tour of new eircom Data Centre Blanchardstown by Dervan Engineering Consultants 11 th March 2015 Tour of new eircom Data Centre Blanchardstown by Dervan Engineering Consultants 11 th March 2015 Presentation Outline Mechanical Overview Chillers and Pumps Pipework and Ancillaries In Row Cooling Units

More information

Calculating Total Power Requirements for Data Centers

Calculating Total Power Requirements for Data Centers Calculating Total Power Requirements for Data Centers By Richard Sawyer White Paper #3 Executive Summary Part of data center planning and design is to align the power and cooling requirements of the IT

More information

Product description NCC Data Center

Product description NCC Data Center Product description NCC Data Center Concept General As one of the largest actors in the Nordic construction industry, NCC Construction plays a leading role in shaping the future of our society. After building

More information

The College of Southern Maryland respectfully submits the following responses regarding the project cited above:

The College of Southern Maryland respectfully submits the following responses regarding the project cited above: The College of Southern Maryland respectfully submits the following responses regarding the project cited above: 1. Will this room be treated as a data center required to meet all NFPA, and International

More information

Data Center Industry Leaders Reach Agreement on Guiding Principles for Energy Efficiency Metrics

Data Center Industry Leaders Reach Agreement on Guiding Principles for Energy Efficiency Metrics On January 13, 2010, 7x24 Exchange Chairman Robert Cassiliano and Vice President David Schirmacher met in Washington, DC with representatives from the EPA, the DOE and 7 leading industry organizations

More information

IPSIP M series-m Modular Data Center

IPSIP M series-m Modular Data Center IPSIP M series-m Modular Data Center IPSIP MODULAR TECHNOLOGIES. 1 With the rapid development of cloud computing and mobile Internet businesses, the growth of IT density and energy consumption are bringing

More information

2014 Limited Plan Submittal Checklist

2014 Limited Plan Submittal Checklist City of Aurora Public Works Department WET AND DRY CHEMICAL HOOD SUPPRESSION SYSTEM 2014 Limited Plan Submittal Checklist Building Division 15151 E. Alameda Parkway, Ste 2400 Aurora, CO 80012 303-739-7420

More information

Iron Hill Corporate Center Newark, DE

Iron Hill Corporate Center Newark, DE Iron Hill Corporate Center Newark, DE Delaware s Premier Suburban Office Park Contact: John Kaczowka (302) 661-6709 or Brian Hopkins (302) 661-6712 Total Project Size 463,085 RSF Red Wing Built in 1988

More information

Datacentre South Gyle 1 Data sheet

Datacentre South Gyle 1 Data sheet Datacentre South Gyle 1 Data sheet Data sheet Datacentre South Gyle 1 Find us South Gyle Datacentre With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our datacentre locations,

More information

Data Operations Center Renovation

Data Operations Center Renovation Data Operations Center Renovation Frederick County s main Data Center is located at Winchester Hall and was originally designed to house five HP3000 computer systems and the support hardware needed for

More information

APPENDIX E: CAPITAL NEEDS SUMMARY

APPENDIX E: CAPITAL NEEDS SUMMARY APPENDIX E: CAPITAL NEEDS SUMMARY Building A Foundation Hall Building to be replaced ARCHITECTURAL Roof Repair North Structural Wall Repair Flooring Repairs Ceiling Repairs Lighting Repairs Lighting Repairs

More information

X-tier Data Facility. Prepared by X-tier SAE Corporation

X-tier Data Facility. Prepared by X-tier SAE Corporation X-tier Data Facility Company Profile X-tier Corporation X-tier is based in Leawood, Kansas. X-tier provides business agnostic, security hardened, custom and turnkey Cloudbased software systems, services,

More information

Best Practices for Wire-free Environmental Monitoring in the Data Center

Best Practices for Wire-free Environmental Monitoring in the Data Center White Paper Best Practices for Wire-free Environmental Monitoring in the Data Center April 2012 Introduction Monitoring for environmental threats in the data center is not a new concept. Since the beginning

More information

Data Center Consolidation Trends & Solutions. Bob Miller Vice President, Global Solutions Sales Emerson Network Power / Liebert

Data Center Consolidation Trends & Solutions. Bob Miller Vice President, Global Solutions Sales Emerson Network Power / Liebert Data Center Consolidation Trends & Solutions Bob Miller Vice President, Global Solutions Sales Emerson Network Power / Liebert Agenda Traditional Data Centers Drivers of a Changing Environment Alternate

More information

CHAPTER 9 FIRE PROTECTION SYSTEMS

CHAPTER 9 FIRE PROTECTION SYSTEMS CHAPTER 9 FIRE PROTECTION SYSTEMS SECTION 901 GENERAL 901.1 Scope. Provisions of this chapter shall govern the application, design, installation, testing and maintenance of automatic sprinklers, standpipes

More information

Building a Tier 4 Data Center on a Tier 1 Budget

Building a Tier 4 Data Center on a Tier 1 Budget Building a Tier 4 Data Center on a Tier 1 Budget A Walk Through of TIA-942 Peter P. Charland III, RCDD/NTS/WD, CET RTKL Associates Inc. March 27, 2008 BICSI South Central Region Meeting Denver, CO TIA-942

More information

Data Centre. Design and Project Management. from concept to completion

Data Centre. Design and Project Management. from concept to completion C O N S U L T I N G Data Centre Design and Project Management from concept to completion Computer rooms are the heart of most businesses today. Yet I see so many that have been patched together, are in

More information

Mechanical, Plumbing, and Fire Protection Conditions

Mechanical, Plumbing, and Fire Protection Conditions Mechanical, Plumbing, and Fire Protection Conditions Mechanical Conditions The mechanical systems within the building consist of a combination of the original 1926 systems and renovations that occurred

More information

LEVEL 3 DATA CENTER ASSESSMENT

LEVEL 3 DATA CENTER ASSESSMENT Nationwide Services Corporate Headquarters 410 Forest Street Marlborough, MA 01752 USA Tel: 800-342-5332 Fax: 508-303-0579 www.eecnet.com LEVEL 3 DATA CENTER ASSESSMENT Submitted by: Electronic Environments

More information

SWAN POINT YACHT & COUNTRY CLUB

SWAN POINT YACHT & COUNTRY CLUB SWAN POINT YACHT & COUNTRY CLUB PROJECT INFORMATION: SCOPE OF WORK: INTERIOR ALTERATIONS ABBREVIATIONS: VICINITY MAP 33 East Charles Street PO Box 598 30-934-8078 PROPERTY MANAGER: DOTTIE HARPER BROOKFIELD

More information

MISSION CRITICAL FACILITIES DESIGN UPS BATTERY ROOM ENVIRONMENT CRITICAL DESIGN CONSIDERATIONS

MISSION CRITICAL FACILITIES DESIGN UPS BATTERY ROOM ENVIRONMENT CRITICAL DESIGN CONSIDERATIONS MISSION CRITICAL FACILITIES DESIGN UPS BATTERY ROOM ENVIRONMENT CRITICAL DESIGN CONSIDERATIONS Allen Wood Vice President Data Center Division Engineering Design Group INTRODUCTION It can be very effectively

More information

DATACENTER COLOCATION. Flexible, Secure and Connected

DATACENTER COLOCATION. Flexible, Secure and Connected DATACENTER COLOCATION Flexible, Secure and Connected Flexible Solutions for Your Requirements Contents Your Goals 2 Compound and Buildings 4 Security 6 Infrastructure 8 Free Choice 10 Good Reasons 12 Our

More information

EXAMPLE OF A DATA CENTRE BUILD

EXAMPLE OF A DATA CENTRE BUILD EXAMPLE OF A DATA CENTRE BUILD BT Harmondsworth Data Centre Hall 2 Upgrade Temperature Control have been involved in providing specialist to data centres for over 20 years, starting from providing specialist

More information

Required Certification Documentation. Contractor's installation certification for range hood fire suppression systems.

Required Certification Documentation. Contractor's installation certification for range hood fire suppression systems. OFFICE OF UNIVERSIT BUILDING OFFICIAL PROJECT/CONSTRUCTION MAGER: Sample Manager Required Aboveground only Required Certification Documentation Contractor s material and test certifications for both above

More information

Keyword: TIA 942, Tier level, Nuclear Data Center. Introduction

Keyword: TIA 942, Tier level, Nuclear Data Center. Introduction Nuclear Data Center International Standard Towards TSO Initiative Raja Murzaferi Raja Moktar, Mohd Fauzi Haris, Siti Nurbahyah Hamdan, Saaidi Ismail,Radhiah Jamaluddin, Nursuliza Samsudin. IT Center, Technical

More information

Data Center Technology: Physical Infrastructure

Data Center Technology: Physical Infrastructure Data Center Technology: Physical Infrastructure IT Trends Affecting New Technologies and Energy Efficiency Imperatives in the Data Center Hisham Elzahhar Regional Enterprise & System Manager, Schneider

More information

Best Practices for Wire-free Environmental Monitoring in the Data Center

Best Practices for Wire-free Environmental Monitoring in the Data Center White Paper 11800 Ridge Parkway Broomfiled, CO 80021 1-800-638-2638 http://www.42u.com sales@42u.com Best Practices for Wire-free Environmental Monitoring in the Data Center Introduction Monitoring for

More information

AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx)

AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx) AT&T Internet Data Center Site Specification Dallas Area (Allen, Tx) Site Biography Market Area: Dallas and Fort Worth Areas of Texas Location: Allen, Tx 75013 Address: 900 Ventura Drive CLLI, POP, NPA/NXX

More information

Contents Error! Bookmark not defined. Error! Bookmark not defined. Error! Bookmark not defined.

Contents Error! Bookmark not defined. Error! Bookmark not defined. Error! Bookmark not defined. We Do It Better. Contents Introduction...3 Service and Support...3 Data Center Details...4 Security...4 Location...4 Power...4 Humidification...5 AC...5 Cooling...6 Datacenter Features...6 SAS 70...6 PCI

More information

ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW OVERVIEW OF CODE REQUIREMENTS

ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW OVERVIEW OF CODE REQUIREMENTS ELECTRICAL EMERGENCY SYSTEM PLAN REVIEW What to Look for during Plan Review OVERVIEW OF CODE REQUIREMENTS First determine the type of emergency power system; is the system designed for Emergency or Legally

More information

The Pros and Cons of Modular Systems

The Pros and Cons of Modular Systems The Pros and Cons of Modular Systems Kevin Brown, Vice President Global Data Center Offer Schneider Electric Schneider Electric 1 Foundational BUSINESS OVERVIEW Rev 2 Desired characteristics of pre-fabricated

More information

DATA CENTRES UNDERSTANDING THE ISSUES TECHNICAL ARTICLE

DATA CENTRES UNDERSTANDING THE ISSUES TECHNICAL ARTICLE DATA CENTRES UNDERSTANDING THE ISSUES TECHNICAL ARTICLE Molex Premise Networks EXECUTIVE SUMMARY The term data centre usually conjures up an image of a high-tech IT environment, about the size of a football

More information

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Presented by: Liberty Engineering, LLP 1609 Connecticut Avenue

More information

High-density modular data center making cloud easier. Frank Zheng Huawei

High-density modular data center making cloud easier. Frank Zheng Huawei High-density modular data center making cloud easier Frank Zheng Huawei 2012-10-10 Content 1 2 3 4 Cloud s impact to data center Concerns of DC construction 4S DC making cloud easier Success stories Cloud?

More information

Print Shop/Mail Room

Print Shop/Mail Room Chapter XVIII Print Shop/Mail Room Page 110 CHAPTER XVIII Print Shop/Mail Room ARCHITECTURAL/STRUCTURAL A. BUILDING EXTERIOR 1.0 EXTERIOR WALLS The exterior walls are comprised of stone veneer. There were

More information

BUILDING SAFETY UNIT

BUILDING SAFETY UNIT POLICY Page 1 of 5 SUBMITTAL REQUIREMENTS FOR ONE AND TWO FAMILY DWELLINGS, ADDITIONS AND RENOVATIONS All submittals shall be site specific and designed to the provisions of the 2012 International Residential

More information

Wholesale Data Center Suites Available Now

Wholesale Data Center Suites Available Now Wholesale Data Center Suites Available Now FROM 2,500 to 100,000 Sq Ft A secure, fortified Mission Critical data center facility located in Innovation Park, Charlotte, NC Scalable data center suites available

More information

Tech Report 2: Electrical System Existing Conditions

Tech Report 2: Electrical System Existing Conditions , Tech Report 2: Electrical System Existing Conditions Oct 12, 2013 Yucheng Lu Lighting/Electrical AE Faculty Consultant: Dr. Shawn Good Executive Summary This report is a summary of my study about the

More information

Data Center Energy Profiler Questions Checklist

Data Center Energy Profiler Questions Checklist Data Center Energy Profiler Questions Checklist Step 1 Case Name Date Center Company State/Region County Floor Area Data Center Space Floor Area Non Data Center Space Floor Area Data Center Support Space

More information

Relative Sensitivity based Fire Detection Systems used in High Density Computer Rooms with In-Row Air Conditioning Units

Relative Sensitivity based Fire Detection Systems used in High Density Computer Rooms with In-Row Air Conditioning Units Relative Sensitivity based Fire Detection Systems used in High Density Computer Rooms with In-Row Air Conditioning Units By Suresh Soundararaj & David Admirand, PE Experts for Your Always Available Data

More information

BRUNS-PAK Presents MARK S. EVANKO, Principal

BRUNS-PAK Presents MARK S. EVANKO, Principal BRUNS-PAK Presents MARK S. EVANKO, Principal Data Centers of the Future and the Impact of High Density Computing on Facility Infrastructures - Trends, Air-Flow, Green/LEED, Cost, and Schedule Considerations

More information

EVT0002256 Services, Data Center Co-Location Updated Attachment A and B

EVT0002256 Services, Data Center Co-Location Updated Attachment A and B Attachment A Data Center Co-location Requirements 1. Scope This document defines KSDE s data center facilities requirements for reference in the Request for Proposal (RFP) for a Co-location Services Vendor

More information

Recommendations for Measuring and Reporting Overall Data Center Efficiency

Recommendations for Measuring and Reporting Overall Data Center Efficiency Recommendations for Measuring and Reporting Overall Data Center Efficiency Version 1 Measuring PUE at Dedicated Data Centers 15 July 2010 Table of Contents 1 Introduction... 1 1.1 Purpose Recommendations

More information

Data Centre Solutions energy efficient by design

Data Centre Solutions energy efficient by design Data Centre Solutions energy efficient by design Mobile & Modular Data Centre Solutions Agile, Scalable, High Performance Mobile and Modular DC solutions Flexible, scalable high performance mobile & modular

More information

AIA Provider: Colorado Green Building Guild Provider Number: 50111120. Speaker: Geoff Overland

AIA Provider: Colorado Green Building Guild Provider Number: 50111120. Speaker: Geoff Overland AIA Provider: Colorado Green Building Guild Provider Number: 50111120 Office Efficiency: Get Plugged In AIA Course Number: EW10.15.14 Speaker: Geoff Overland Credit(s) earned on completion of this course

More information

Doc Ref: 2015.06.01.002. 602.783.1112 baselayer.com 2015 BASELAYER TECHNOLOGY, LLC

Doc Ref: 2015.06.01.002. 602.783.1112 baselayer.com 2015 BASELAYER TECHNOLOGY, LLC TM 602.783.1112 baselayer.com 2015 BASELAYER TECHNOLOGY, LLC TM D400E Data Module (60Hz) The EDGE D400E is designed to meet high power density requirements for both the HPC and Web Scale environments while

More information

Data Center Solutions - The Containerized Evolution

Data Center Solutions - The Containerized Evolution Data Center Solutions - The Containerized Evolution Power IT Cooling 7 th Green Connected World Tsikogias Thanassis Data Centers Solutions Architect, IT Business Athens 2015 1 We are the global specialist

More information

Data Center Infrastructure & Managed Services Outline

Data Center Infrastructure & Managed Services Outline Data Center Infrastructure & Managed Services Outline The 360 Technology Center Solutions Data Center is located in Lombard, IL, USA. We are 20 minutes outside of downtown Chicago. The 360TCS staff consists

More information

High Density Data Centers Fraught with Peril. Richard A. Greco, Principal EYP Mission Critical Facilities, Inc.

High Density Data Centers Fraught with Peril. Richard A. Greco, Principal EYP Mission Critical Facilities, Inc. High Density Data Centers Fraught with Peril Richard A. Greco, Principal EYP Mission Critical Facilities, Inc. Microprocessors Trends Reprinted with the permission of The Uptime Institute from a white

More information

vcloud SERVICE Virtual Tech in partnership with Equinix - vcloud Service

vcloud SERVICE Virtual Tech in partnership with Equinix - vcloud Service vcloud SERVICES vcloud SERVICE Virtual Tech offers competitive pricing on vcloud hosted services at our world class Tier 4 data centre facility fully equipped with redundant power, cooling, internet connectivity

More information

Datacentre Maidenhead P1 Data sheet

Datacentre Maidenhead P1 Data sheet Datacentre Maidenhead P1 Data sheet Data sheet Datacentre Maidenhead P1 Find us With 10 datacentres, over 4,500 racks and a 10Gb resilient core network between our datacentre locations, Pulsant has the

More information

Electrical Systems. <Presenter>

Electrical Systems. <Presenter> Review Root Causes of Energy Inefficiency Roadmap to Maximize Energy Efficiency Best Practices Alternative Energy Sources Controls Take Aways Seek Professional Help. ENERGY INEFFICIENCY OF

More information

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management.

Our data centres have been awarded with ISO 27001:2005 standard for security management and ISO 9001:2008 standard for business quality management. AIMS is Malaysia and South East Asia s leading carrier neutral data centre operator and managed services provider. We provide international class data storage and ancillary services, augmented by an unrivaled

More information

The Different Types of Air Conditioning Equipment for IT Environments

The Different Types of Air Conditioning Equipment for IT Environments The Different Types of Air Conditioning Equipment for IT Environments By Tony Evans White Paper #59 Executive Summary Cooling equipment for an IT environment can be implemented in 10 basic configurations.

More information