Remodel Projects. Photos by Marvin Dodge

Size: px
Start display at page:

Download "Remodel Projects. Photos by Marvin Dodge"

Transcription

1 Remodel Projects Photos by Marvin Dodge

2 Lucy Phillips Classroom Building Highlights: All new heating and air conditioning systems ducts, air handler, VAV boxes, pumps, etc. All new electrical/data wiring, panels and service Addition of fire sprinkler system throughout building Virtually complete gutting of the building with all new wall/room construction 12 new all-purpose classrooms 2 new UEN broadcast classrooms and 1 new conference room New and expanded testing center with 125 desks Enhanced computer testing with 30 laptop computers complete with lock-down browser

3 Lucy Phillips Classroom Building Highlights, Cont: All classrooms fully enhanced with computer, DVD, projector, 5 point surround sound, and Elmo All new furniture with casters designed to accommodate arranging classrooms for various teaching methods and preferences 4 additional faculty offices Expanded Information Technology Office space with enhanced security options 2 nd Floor entrance/exit on the building s East side Modern datacenter with raised floor, state-of-the-art Liebert cooling system, data cabinets, and space for future expansion New energy efficient exterior window systems New exterior doors with electronic security locks Anticipated opening date for classes beginning January 4, 2011

4 Lucy Phillips 1 st Floor South Wall Demolition

5 Lucy Phillips 1 st Floor- can you say conduit-new UEN rooms

6 Lucy Phillips 1 st Floor-Final heating and cooling ducts

7 Lucy Phillips 1 st Floor-Framing new testing center entrance

8 Lucy Phillips 1 st Floor-Looking through windows into new testing center

9 Lucy Phillips 1 st Floor-New testing center-125 seat capacity

10 Lucy Phillips 1 st Floor-New testing center main entrance and reception area

11 Lucy Phillips 2 nd Floor-Classroom wall construction

12 Lucy Phillips 2 nd Floor-North classroom framing

13 Lucy Phillips 3 rd Floor-Ceiling grid being installed (classroom)

14 Lucy Phillips 3 rd Floor-Classroom ceiling grid and lighting

15 Lucy Phillips 3 rd Floor-Datacenter new cabinets

16 Lucy Phillips 3 rd Floor-Datacenter-new Liebert cooling system

17 Lucy Phillips 3 rd Floor-hallway ceiling grid and mechanical system

18 Lucy Phillips 3 rd Floor-installation of light fixtures (classroom)

19 Lucy Phillips 3 rd Floor-IT Offices-open space with new exterior windows and sprinklers

20 Lucy Phillips 3 rd Floor-Main Hallway

21 Lucy Phillips 3 rd Floor-Move in day! New datacenter-server cabinets

22 Lucy Phillips 3 rd Floor-Move in day! New datacenter

23 Lucy Phillips Mechanical Room-New air handler

24 Lucy Phillips New ductwork and heat-cool units

25 Lucy Phillips New energy efficient exterior windows (north side)

26 Lucy Phillips New energy efficient exterior windows (south side)

27 Lucy Phillips New main entrance doors

28 Lucy Phillips New mechanical systems and fire sprinklers

29 Richfield Nursing and Business Remodel highlights: New registration/student services offices in the Administration building Expanded and remodeled nursing classroom/lab facilities with new counters, sinks, bathroom, observation room, and nurse s station Addition of new nursing classroom Consolidation of nursing offices in the Washburn building Creation of science lab including gas, air, water, electric and data at each student station Creation of lab storage area to include a cadaver for anatomy classes

30 Richfield Nursing and Business Remodel highlights, continued: Remodeled business classrooms including carpet, desks, chairs, and teaching stations Created business conference room for professional student training/presentations New offices for business faculty Replaced carpeting in all remodeled areas Yet to be completed a new student lounge/game room space including offices for student leaders and support staff

31 SCR-Business classroom remodel

32 SCR-Faculty office remodel

33 SCR-New biology and chemistry lab

34 SCR-New biology and chemistry lab

35 SCR-New biology and chemistry lab

36 SCR-New biology and chemistry lab

37 SCR-New biology and chemistry lab

38 SCR-New biology and chemistry lab

39 SCR-New nursing classroom lab

40 SCR-New nursing classroom lab

41 SCR-New registration and student services offices

42 SCR-Nursing classroom remodel

43 SCR-Nursing lab space

44 SCR-Nursing lab space

H107 Video Conference Room

H107 Video Conference Room Capacity: 20 persons White Board (1) Document Camera (1) Door (1) Network connections possible Layout: Seminar style with chairs and tables (moveable) Podium (1) Media Cart (1) Windows (4) Meets all ADA

More information

Board Seminar Facilities. School Year 2012-2013. Submitted by Joseph L. Lisa-Director of Facilities

Board Seminar Facilities. School Year 2012-2013. Submitted by Joseph L. Lisa-Director of Facilities Board Seminar Facilities School Year 2012-2013 Submitted by Joseph L. Lisa-Director of Facilities High School Installed new fence for Pre-K activities by weight room. Installed new rails and side walks

More information

Arizona Health Care Association DISASTER PLANNING AND EMERGENCY MANAGEMENT GUIDE POST INCIDENT DAMAGE ASSESSMENT CHECKLIST

Arizona Health Care Association DISASTER PLANNING AND EMERGENCY MANAGEMENT GUIDE POST INCIDENT DAMAGE ASSESSMENT CHECKLIST It is essential to perform a Basic Damage Assessment (BDA) following an adverse event to help ensure the safety of building occupants as well as prevent additional losses from occurring. This checklist

More information

Repair Project for April 7, 2009

Repair Project for April 7, 2009 Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades

More information

Quality Assurance Calendar Maintenance Responsible Party Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Quality Assurance Calendar Maintenance Responsible Party Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Generator fire up Generator 1 hour load test Generator 4 hour load test Fire extinguisher integrity checks Fire extinguisher certification Fire drills Fire door integrity Fire signage lighting Fire alarm

More information

Angelo State University Construction Report

Angelo State University Construction Report May 12, 2009 Angelo State University Construction Report Modular buildings will temporarily house ASU staff during the Hardeman renovation starting this fall. Prepared for: John Russell, Director of Planning

More information

Damage Charge Lists. FLOORING Replace Repair Carpet per square foot (Mohwak heat carpet tile)

Damage Charge Lists. FLOORING Replace Repair Carpet per square foot (Mohwak heat carpet tile) American River Courtyard Charge List Damage Charge Lists LIVING ROOM FURNITURE Replace Repair Coffee Table $164.00 Sectional sofa corner section $457.00 Sectional sofa two seat section $525.00 Sectional

More information

Bond Priorities. Repairs and Maintenance. School Safety. Capacity

Bond Priorities. Repairs and Maintenance. School Safety. Capacity Replace old windows, boilers, heating and air conditioning system. Improve accessibility for disabled persons. Keyless entry lock systems, redesign of school entrance, and wireless access throughout building.

More information

BUILDING NAMING RIGHTS

BUILDING NAMING RIGHTS NEW HEALTH SCIENCE BUILDING Davis Applied Technology College METHODSTUDIO INC. BUILDING NAMING RIGHTS NAMING RIGHTS OPPORTUNITIES Building Areas $500,000 Building Naming Right $100,000 LEED Gold Sponsorship

More information

Part 2 Definitions for this Policy 2.1. ADA / TAS the Americans with Disabilities Act / Texas Accessibility Standards.

Part 2 Definitions for this Policy 2.1. ADA / TAS the Americans with Disabilities Act / Texas Accessibility Standards. Office of Space Management Page 1 of 6 Part 1 Purpose 1.1. This policy establishes space allocation and space use guidelines for UTSA entities occupying space in UTSA-owned and UTSA-leased facilities.

More information

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are: When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory

More information

Electrical. This section applies to the design and installation of building power distribution systems.

Electrical. This section applies to the design and installation of building power distribution systems. Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions

More information

Academic Learning and Teaching Center Classrooms

Academic Learning and Teaching Center Classrooms Academic Learning and Teaching Center Classrooms Lobby Capacity: 157 Video wall Furniture can be removed or reconfigured for after-hours (after 5PM) events Classroom 1.101 Capacity: 30 (2) TV s located

More information

MARQUETTE UNIVERSITY: McCabe Hall

MARQUETTE UNIVERSITY: McCabe Hall MARQUETTE UNIVERSITY: McCabe Hall THE SITE Newly acquired by Marquette, the vintage 1920 s building is located on the northeast corner of Wisconsin and 17th Streets. The urban setting offers immediate

More information

Building Condition Assessment Report

Building Condition Assessment Report C2 - Nurses Resident (aka Administration) Building Condition Assessment Report Asset Address Address Construction Year Size (Gross Floor Area) Asset Type Floors Above Ground Inspection Date C2 - Nurses

More information

Room# 111. Room# 112. One wooden door Auto door closer Draft on bottom. 1 wooden door Auto door closer. One plexiglass window with metal frame

Room# 111. Room# 112. One wooden door Auto door closer Draft on bottom. 1 wooden door Auto door closer. One plexiglass window with metal frame Building Name: College of Natural and Applied Sciences (CNAS) Floor: 1 st floor Auditor: Jessecca Craig Date: 11/13/12 104 105 111 112 113 121 124 Exterior Wall Penetration on E wall, needs sealing Two

More information

1/9/2015 P:\130217-03\Project Management\Program\Ripon Space Program - 7 January 2015.xlsx

1/9/2015 P:\130217-03\Project Management\Program\Ripon Space Program - 7 January 2015.xlsx MIDDLE SCHOOL Administration Office Principal's Office 200 1 200 Desk, conference table for 4-6 Conference Room 250 1 250 Conference table for 12 Open Office Area 250 1 250 2 Workstations Mail / copier

More information

SUMMARY REPORT THE BOTTOM LINE. Electrical. Report Number: 1860. Inspection Date: Saturday, February XX, XXXX

SUMMARY REPORT THE BOTTOM LINE. Electrical. Report Number: 1860. Inspection Date: Saturday, February XX, XXXX SUMMARY REPORT Report Number: 1860 Inspection Date: Saturday, February XX, XXXX Property Address: XX XXXXX XXX Toronto, ON XXX XZX Client Name: Xxxx Xxxxxxxxxxxxx Prepared by: Andrew Marioselva BSc,CHI

More information

Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School

Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School Introduction Background The Duke School of Nursing building offers a new three-story state of the art facility that has helped strengthen the quality and integrity of the School of Nursing at Duke. The

More information

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011 Facility Services Section Page Recharge Services, Maintenance and Construction PURPOSE 1 of 6 The purpose of this policy is to set forth standards for chargeable services for maintenance and construction

More information

B. Policies & Procedures Governing Humanities Conference Rooms

B. Policies & Procedures Governing Humanities Conference Rooms HUMANITIES CONFERENCE ROOMS A. Protocol for the Divisional-Assigned Conference Rooms B. Policies & Procedures Governing Humanities Conference Rooms C. Room Descriptions D. Detailed Reservation Instructions

More information

Schedule B to By-law 33-2009

Schedule B to By-law 33-2009 Amended by By-law 8-2016 Note: This consolidation is prepared for convenience only. For accurate reference the original by-laws should be reviewed. Floor Area Calculation Floor area shall: Schedule B to

More information

New Hanover County Schools Middle School Educational Specifications Media Center. Overview. Spatial Relationships

New Hanover County Schools Middle School Educational Specifications Media Center. Overview. Spatial Relationships Overview The will serve as the information hub of the school. The library and media program has as its major goal the physical and intellectual access to materials within and outside the physical facility.

More information

Champaign Public Library Meeting Room F.A.Q.

Champaign Public Library Meeting Room F.A.Q. Champaign Public Library Meeting Room F.A.Q. Most-Frequently-Asked Questions Can I book a room for two or three days in a row? Yes. The library allows up to three reservations per group at a time. (This

More information

Items in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes.

Items in red were complete 2-22-10. Items in green were complete on 8-2-11. Lined out items are Life Safety Codes. Office of Safe and Orderly Schools Facility Safety Assessment Dennis Meador, School Facilities Supervisor Mark Hobson, School Facilities Supervisor Division of School Building September 18 19, 2007 Items

More information

LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -

LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE - The original section of this building was constructed in 1941. The exterior walls are built of good quality stone. In the early 1980 s a similar addition was added to the north elevation. The exterior

More information

Designing a Facility: Making It a Place Where Every Student Succeeds

Designing a Facility: Making It a Place Where Every Student Succeeds American Association of School Librarians 12th National Conference and Exhibition October 6-9, 2005 Pittsburgh, Pennsylvania Designing a Facility: Making It a Place Where Every Student Succeeds Gail Formanack

More information

HOMEOWNER S PERMIT GUIDE

HOMEOWNER S PERMIT GUIDE HOMEOWNER S PERMIT GUIDE WHEN IS A PERMIT REQUIRED? Department of Development and Permits 306 Cedar Road, City Hall 2 nd Floor P.O. Box 15225 Chesapeake, VA 23328 Phone: (757) 382-6018 Fax: (757) 382-8448

More information

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Printed On: 2003/04/03 St Patrick CES, 7932 Study [03.3-050 Plumbing Piping Systems] Study condition, remaining service

More information

OWASSO. Conference Center

OWASSO. Conference Center OWASSO Conference Center The primary purpose of Tulsa Tech s Owasso Conference Center is to provide students in our hospitality programs with workplace experience. We also encourage the use of the facility

More information

Asbestos Procedures. Asbestos Products

Asbestos Procedures. Asbestos Products Asbestos Procedures Asbestos Products Where is asbestos known to be located on The Evergreen State College? Please see Appendix A for a list of known asbestos containing materials located on the Olympia

More information

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

D Sample Notices to Property Owners, Sample Affidavits, and Other Material D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully

More information

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal. 2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other

More information

Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016

Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Year Opened 2003 Current Square Footage 391,000 Site Acreage 86.22 cherokeetrail.cherrycreekschools.org $279,200 Asphalt and concrete

More information

Aurora Mall. Aurora (Denver), Colorado

Aurora Mall. Aurora (Denver), Colorado is the largest superregional mall in the city of Aurora, and it s only getting bigger and better. The mall is currently undergoing a significant interior and exterior renovation, scheduled for completion

More information

BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207

BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207 BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207 SELF EVALUATION CHECKLIST FOR RESIDENTIAL AND MULTI-FAMILY DWELLING INSPECTIONS The attached checklist

More information

New York, Dean. Price 182,500

New York, Dean. Price 182,500 New York, Dean Semi detached family home Three bedrooms Lounge Separate dining room Modern fitted kitchen Bathroom plus separate W.C. Gas central heating/ double glazed Drive plus garage Gardens front

More information

Report Index PROPERTY DESCRIPTION 1 ELECTRICAL SYSTEM 2 COMMON INTERIOR AREAS 3 INTERIOR ROOMS 6 KITCHEN 8 BATHROOMS 10

Report Index PROPERTY DESCRIPTION 1 ELECTRICAL SYSTEM 2 COMMON INTERIOR AREAS 3 INTERIOR ROOMS 6 KITCHEN 8 BATHROOMS 10 Report Index PROPERTY DESCRIPTION 1 ELECTRICAL SYSTEM 2 COMMON INTERIOR AREAS 3 INTERIOR ROOMS 6 KITCHEN 8 BATHROOMS 10 PROPERTY DESCRIPTION PROPERTY INSPECTED: INSPECTION ADDRESS: 4722 Baltimore Avenue

More information

Borough President and City Council Capital Funding Requests FY 2009

Borough President and City Council Capital Funding Requests FY 2009 Borough President and City Council Capital Funding Requests FY 2009 CIP Number Phase* Request $ Classroom Development GR-0928061514 DCE $1,088,000 Expansion of Campus Security Systems GR-0504070756 DCE

More information

Building Condition Assessment Report

Building Condition Assessment Report Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.

More information

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 0 Overlea High School - Facility Summary Facility Opened: Auditorium Addition: Activity Room Addition: School Rated Capacity

More information

HOUSING QUALITY STANDARDS (HQS)

HOUSING QUALITY STANDARDS (HQS) HOUSING QUALITY STANDARDS (HQS) HQS INSPECTIONS Part II Site Inspections 24 CFR 982.401 & 405 1si Rev. 4-20-06 General Conditions All doors and windows accessible to the outside, must have a workable lock.

More information

STAFF ORIENTATION March 2013

STAFF ORIENTATION March 2013 STAFF ORIENTATION March 2013 Los Angeles County Office of Education (LACOE) Business Services, Controller s Office Facilities and Construction LOS ANGELES COUNTY HIGH SCHOOL FOR THE ARTS (LACHSA) STAFF

More information

May 5, 2010. Client Client Address. Re: Inspection Address, Chicago, Illinois. Dear Mr. Client,

May 5, 2010. Client Client Address. Re: Inspection Address, Chicago, Illinois. Dear Mr. Client, PROPERTY INSPECTION PROFESSIONALS May 5, 2010 Client Client Address Re: Inspection Address, Chicago, Illinois Dear Mr. Client, On May 4, 2010, Tomacor completed a property inspection of the above referenced

More information

SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY

SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY Construction Criteria The unit costs for (Wet) space types are based on the construction quality and design features in the following table. This

More information

Quick Reference Guide: A Guide to Some Frequently Requested Services

Quick Reference Guide: A Guide to Some Frequently Requested Services Facilities and Property Management Post Office Box 751 503-725-3738 tel Portland, Oregon 97207-0751 503-725-4329 fax www.pdx.edu/facilities Quick Reference Guide: A Guide to Some Frequently Requested Services

More information

Waterleaf Space Optimization Study

Waterleaf Space Optimization Study Waterleaf Space Optimization Study Board of Trustees Meeting June 25, 2015 Option 1 Convert to Classroom Space Existing Dining Room Existing Conditions Kitchen & Dining Room Classroom Conversion Option

More information

Estimating Database Checklist

Estimating Database Checklist Estimating Database Checklist If you are creating a new estimating database for projects, the following list offers a thorough listing of Main and Sub Categories. You can also use it as a checklist to

More information

Print Shop/Mail Room

Print Shop/Mail Room Chapter XVIII Print Shop/Mail Room Page 110 CHAPTER XVIII Print Shop/Mail Room ARCHITECTURAL/STRUCTURAL A. BUILDING EXTERIOR 1.0 EXTERIOR WALLS The exterior walls are comprised of stone veneer. There were

More information

University of Northern Iowa Facilities Services

University of Northern Iowa Facilities Services University of Northern Iowa Facilities Services February 2013 Page 1 Table of Contents: 3 General Service Information 3 Maintenance Services 4 Non-Maintenance Services 5 Area Maintenance Program 6 Carpentry

More information

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL?

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? 1. BASIC FACTS: The current Abington High School building is 111,831

More information

School Board Proposed Capital Improvements Program. Fiscal Years 2014-2023

School Board Proposed Capital Improvements Program. Fiscal Years 2014-2023 School Board Proposed Capital Improvements Program Fiscal Years 2014-2023 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-6 Capital Projects Description Pages 7-14 SCHOOL BOARD PROPOSED CAPITAL

More information

OFFICE SPACE SUBLEASE 1105 Berkshire Boulevard / The TRAVELERS BUILDING Wyomissing, PA 19610. Rare Wyomissing Sublease 4,926 SF AVAILABLE NOW

OFFICE SPACE SUBLEASE 1105 Berkshire Boulevard / The TRAVELERS BUILDING Wyomissing, PA 19610. Rare Wyomissing Sublease 4,926 SF AVAILABLE NOW SPACE SUBLEASE 1105 Berkshire Boulevard / The TRAVELERS BUILDING Rare Wyomissing Sublease 4,926 SF AVAILABLE NOW Full Service Lease, all-in for only $16.50 / SF! Glass on three sides, huge conference room

More information

Facility Assessment for. 11801 East Main Street, Huntley, IL

Facility Assessment for. 11801 East Main Street, Huntley, IL Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested

More information

TURN-KEY LAB SPACE AVAILABLE

TURN-KEY LAB SPACE AVAILABLE TURN-KEY LAB SPACE AVAILABLE 910 CLOPPER ROAD LOCATION... Tech Park 270 910 Clopper Road BUILDING... 180,650 rentable square feet TURN-KEY LAB/OFFICE SPACE AVAILABLE Second Floor 9,800 SF 14,644 SF (can

More information

NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1

NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 DISCLAIMER : The New York State Office of Parks, Recreation and

More information

PUBLIC NOTICE State of Kansas. Request for Proposal Leased Office Space

PUBLIC NOTICE State of Kansas. Request for Proposal Leased Office Space PUBLIC NOTICE State of Kansas Request for Proposal Leased Office Space The Kansas Department of Credit Unions is accepting written proposals for approximately 2,250 square feet of renovated or new office

More information

IRISH ACCOMMODATION SERVICE AWARDS

IRISH ACCOMMODATION SERVICE AWARDS IRISH ACCOMMODATION SERVICE AWARDS CHECKLIST Property Name: Category: 3* hotel 4* hotel 5* hotel Boutique hotel B&B Hospital Nursing Home Colleges / Schools Irish Accommodation Service Awards IASI Accommodation

More information

PROPERTY INSPECTION REPORT

PROPERTY INSPECTION REPORT Whisper Computer Solutions, Inc. P.O. Box 690502 San Antonio, TX 78269-0502 Phone: (210)681-6325 Fax: (210)681-6325 Email: support@whispersolutions.com PROPERTY INSPECTION REPORT Prepared For: Concerning:,

More information

3rd Annual Design Drafting Contest

3rd Annual Design Drafting Contest 3rd Annual Design Drafting Contest YTI Career Institute 3 rd Annual Design Drafting Contest The purpose of this contest is to encourage excellence in effort and discipline, and to give recognition to outstanding

More information

6 FAM 1700 SPACE ALLOCATION AND RELATED SERVICES

6 FAM 1700 SPACE ALLOCATION AND RELATED SERVICES 6 FAM 1700 SPACE ALLOCATION AND RELATED SERVICES 6 FAM 1710 OFFICE SPACE ASSIGNMENT AND UTILIZATION, DESIGN AND CONSTRUCTION (CT:GS-174; 05-29-2013) (Office of Origin: A/OPR/RPM) 6 FAM 1711 GENERAL PROVISIONS:

More information

AGENDA. BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room

AGENDA. BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room AGENDA BUILDING AND GROUNDS COMMITTEE MEETING April 21, 2015 6:30 PM School Board Room 1. Call to order at 6:30 p.m. 2. Review of Three Year Life Safety Recommendations from EGM Architects 3. Review of

More information

The College of Southern Maryland respectfully submits the following responses regarding the project cited above:

The College of Southern Maryland respectfully submits the following responses regarding the project cited above: The College of Southern Maryland respectfully submits the following responses regarding the project cited above: 1. Will this room be treated as a data center required to meet all NFPA, and International

More information

Borges Construction Company A limited liability Corporation Page1 of 1

Borges Construction Company A limited liability Corporation Page1 of 1 Page1 of 1 The following is a quote to remodel the master bathroom at your home: Materials Labor Demolition 1 Dumpster $ 225.00 $ - 2 Remove existing carpet $ - $ 50.00 3 Remove existing tile $ - $ 80.00

More information

Facilities Operations Customer Service Standards WORK ORDER PRIORITIES

Facilities Operations Customer Service Standards WORK ORDER PRIORITIES Facilities Operations Customer Service Standards WORK ORDER PRIORITIES In order to provide fair and consistent maintenance service to all University faculty, staff and students, a work priority system

More information

Executive Flight Office & Hangar

Executive Flight Office & Hangar ONE CAMPBELL PARKWAY, EAST WENATCHEE, WASHINGTON 98802 Exceptional value for world class 64,305 sq. ft. hangar facility in Eastern Washington ONE CAMPBELL PARKWAY, EAST WENATCHEE, WASHINGTON 98802 THE

More information

How To Design An Hvac Design For A Stick Built Home

How To Design An Hvac Design For A Stick Built Home LEGALETT HVAC DESIGN FEE SCHEDULE (revised April 17, 2012) Background In the past Legalett has simply supplied warm floors for comfortable living. However, 2012 Building Code changes in Ontario make it

More information

Addition and Renovation Northview Elementary School Design Development Manual

Addition and Renovation Northview Elementary School Design Development Manual PERU ELEMENTARY SCHOOL DISTRICT 124 Peru, La Salle County, Illinois Addition and Renovation Northview Elementary School Design Development Manual Healy Bender Project No. 10-3113-145 Tab 3 Sheet 3-1.00

More information

COMPREHENSIVE PROPERTY INSPECTIONS

COMPREHENSIVE PROPERTY INSPECTIONS COMPREHENSIVE PROPERTY INSPECTIONS Thank you for selecting CPI for your Deficiency Observation. A full home inspection was not performed on this property at the buyers request. This inspection is a limited

More information

Description of Project Statewide Student Data Warehouse

Description of Project Statewide Student Data Warehouse Description of Project Statewide Student Data Warehouse The Department of Education (DE) uses Rebuild Iowa Infrastructure Fund funding to support critical components of Iowa s Statewide Longitudinal Data

More information

KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS

KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS This guideline is intended to provide the homeowner/contractor with the

More information

Schedule B to By-law 33-2009 Part A Fees Payable for Permits

Schedule B to By-law 33-2009 Part A Fees Payable for Permits Floor Area Calculation Floor area shall: Part A Fees Payable for Permits (Effective January 1, 2015) a) be calculated by measuring to the outer face of exterior walls and to the centre of party walls or

More information

Use of Meeting Rooms. Goodnow Library Policy Manual Policy #4-7

Use of Meeting Rooms. Goodnow Library Policy Manual Policy #4-7 Use of Meeting Rooms When not needed by the Library or the Town, the Goodnow Library Meeting Rooms are available to local groups and organizations for educational, cultural, philanthropic or civic uses.

More information

APPENDIX E: CAPITAL NEEDS SUMMARY

APPENDIX E: CAPITAL NEEDS SUMMARY APPENDIX E: CAPITAL NEEDS SUMMARY Building A Foundation Hall Building to be replaced ARCHITECTURAL Roof Repair North Structural Wall Repair Flooring Repairs Ceiling Repairs Lighting Repairs Lighting Repairs

More information

Town of Sandwich Facilities Department Summary of Building Repairs from Prior 5 7 Years List Updated August 7, 2015

Town of Sandwich Facilities Department Summary of Building Repairs from Prior 5 7 Years List Updated August 7, 2015 Town of Sandwich Facilities Department Summary of Building Repairs from Prior 5 7 Years List Updated August 7, 2015 Town Hall Complete building restoration (state historic preservation award) High efficiency

More information

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT

ORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT 1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.3 Cabinets, Equipment 1.1.4 Portables 1.2 Fire / Life Safety 1.2.1 Corridor, Separation

More information

Lactation Spaces 16-Nov-15

Lactation Spaces 16-Nov-15 Lactation Spaces 16-Nov-15 CU Denver Business Building: (Andrew Rotz) 303-315-8071 Business School (UCD) 5001 Auraria (Denver) Campus Institute for Women's Studies and Services: 303-556-8441 AHEC Facilities

More information

A001.01. Project Description/Project Title and Data: Building Area: (sf) Addition 28,142 Renovation 14,302. Cost per Square Foot: +/- $106.

A001.01. Project Description/Project Title and Data: Building Area: (sf) Addition 28,142 Renovation 14,302. Cost per Square Foot: +/- $106. Project Description/Project Title and Data: KEVIN I. SULLIVAN CAMPUS CENTER ADDITION & RENOVATION Medaille College - Buffalo, NY Functioning as Medaille College's campus heart, The Kevin I Sullivan Campus

More information

Summit Series Single Section and Double Section Homes

Summit Series Single Section and Double Section Homes Single Section and Double Section Homes SM-01 All New 20 Wides Now Available! SM-08 Units shown with optional features SM-01-4814 42 Bedrooms 41 Bathrooms 648 Sq. Ft. SM-01-5214 42 Bedrooms 41 Bathrooms

More information

Appendices. College, University College, and Institute System. Space Guidelines Review APPENDIX G BEST PRACTICES EXAMPLES

Appendices. College, University College, and Institute System. Space Guidelines Review APPENDIX G BEST PRACTICES EXAMPLES University A. Computer/Language/Business Drop-In Computer Institution: The University College of the Cariboo Campus: Kamloops Campus Building: Old Main Room Number: 1429 Capacity: 15 Area Per Student Station:

More information

NORTH PENN HIGH SCHOOL RENOVATIONS

NORTH PENN HIGH SCHOOL RENOVATIONS NORTH PENN HIGH SCHOOL RENOVTIONS PRELIMINRY SCOPE, BUDGET & PHSING CONSIDERTIONS 401 EST HNCOCK STREET LNSDLE, P 19446 PREPRED BY BONNETT SSOCITES INCORPORTED 220 BLDWIN TOWER, 1510 CHESTER PIKE EDDYSTONE,

More information

FIRE EXTINGUISHER DORM #1 SYMPHONY

FIRE EXTINGUISHER DORM #1 SYMPHONY FIRE EXTINGUISHER DORM #1 SYMPHONY 101 ABC (Dry Chem) Basement (Downbeat Café Pool Tables) 102 ABC (Dry Chem) Hall Men s room (Downbeat Café) 103 ABC (Dry Chem) Hallway across chiller (Downbeat Café) 104

More information

Photo 1: This photograph shows drywall, joint compound, cove base mastic, carpet adhesive, and ceiling tile in store front No. 1.

Photo 1: This photograph shows drywall, joint compound, cove base mastic, carpet adhesive, and ceiling tile in store front No. 1. APPENDIX B PHOTOLOG Photo 1: This photograph shows drywall, joint compound, cove base mastic, carpet adhesive, and ceiling tile in store front No. 1. Photo 2: This photograph shows layered floor tile and

More information

Hotel Accessibility Pack

Hotel Accessibility Pack Hotel Accessibility Pack Thank you for considering the Hilton Dublin City. We are pleased to provide you with some information regarding our hotel that you may find useful when planning your visit to our

More information

Sim Center Mentor Simulation Floorplans and Center Layouts

Sim Center Mentor Simulation Floorplans and Center Layouts Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Reminders/Considerations for Simulation Center Development/Renovation AV plan! Plan early, be sure to include the people that will be responsible for maintaining

More information

Conference Room Reservation Policy Packet

Conference Room Reservation Policy Packet Conference Room Reservation Policy Packet Opening Our Doors to the Community 185 Oakes Street SW Grand Rapids, MI 49503 616.454.1751 Phone 616.454.6455 Fax www.grfoundation.org Policies and Procedures

More information

R. MICHAEL SHANAHAN CENTER FOR TEACHING AND LEARNING

R. MICHAEL SHANAHAN CENTER FOR TEACHING AND LEARNING R. MICHAEL SHANAHAN CENTER FOR TEACHING AND LEARNING The meeting rooms of Harvey Mudd College s (HMC) R. Michael Shanahan Center for Teaching and Learning are provided for use by HMC students, faculty,

More information

Nominal Life Expectancy for Building Components

Nominal Life Expectancy for Building Components Nominal Life Expectancy for Building Components Building System Page A. HVAC 2 B. Elevator/Escalator 6 C. Plumbing 7 D. Roofing 8 E. Electrical 10 F. Fire/Life/Safety/Security System 11 G. Interior Finishes

More information

Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com

Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com Crawford Inspection Services C.C.B. # 76914 www.crawfordinspections.com Portland Area PO Box 665 West Linn, OR 97068 Ph: (503) 650-6957 Salem Area 5434 River Rd. N; #192 Keizer, OR 97303 Ph: (503) 362-5809

More information

Water Leak 1: Intrusion Policy

Water Leak 1: Intrusion Policy Water Leak 1: Intrusion Policy {Non-Casualty) 1. Determine Source of Leak Roof Leak- 11 See roof leak" Pressured Pipe leak- 11 See pressured pipe leak" Water Intrusion- See 11 see Water Intrusion leak"

More information

New York State Office and Historic Homeownership Rehabilitation Tax Credit

New York State Office and Historic Homeownership Rehabilitation Tax Credit NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 DISCLAIMER : The New York State Office of Parks, Recreation and

More information

The schedule is based upon a five (5) day work week (Monday through Friday). Weekend service is only when requested.

The schedule is based upon a five (5) day work week (Monday through Friday). Weekend service is only when requested. Campus Custodial Service Standards The schedule is based upon a five (5) day work week (Monday through Friday). Weekend service is only when requested. Shifts Cleaning Hours 1 st 6:00 am 2:30 pm 2 nd 2:30

More information

Please note that exhibitor move out will not be permitted prior to 8:05 p.m and must be complete by 9:30pm.

Please note that exhibitor move out will not be permitted prior to 8:05 p.m and must be complete by 9:30pm. Logistics and Information The Manitoba Design Exchange 2011 will be held Thursday October 6, 2010 Victoria Inn Hotel and Convention Center Wellington Ballroom 1808 Wellington Avenue Winnipeg Manitoba The

More information

Required Certification Documentation. Contractor's installation certification for range hood fire suppression systems.

Required Certification Documentation. Contractor's installation certification for range hood fire suppression systems. OFFICE OF UNIVERSIT BUILDING OFFICIAL PROJECT/CONSTRUCTION MAGER: Sample Manager Required Aboveground only Required Certification Documentation Contractor s material and test certifications for both above

More information

November 3, 2015 Bond and District Additional Assistance Election Information

November 3, 2015 Bond and District Additional Assistance Election Information November 3, 2015 Bond and District Additional Assistance Election Information Proposition 432 - $22 million General Obligation Bond 150+ facility projects across all schools Building renovations and improvements

More information

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal

More information

Gramercy Place Condo Association, Inc.

Gramercy Place Condo Association, Inc. Gramercy Place Condo Association, Inc. UNIT MODIFICATION REQUEST Date of Application: Name of Owner (s): Telephone: (Home) (Cell) E-Mail: Anticipated start date: Anticipated ending date: Permission is

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information

The Carriage Homes at Woodland Pond Phase III & IV

The Carriage Homes at Woodland Pond Phase III & IV The Carriage Homes at Woodland Pond Phase III & IV Phase I & II (completed 2009) Phase III & IV (completed Summer 2012) The Carriage Homes are one of five distinctive condominium communities that comprise

More information

Inspection Report of 1895 Jamesport Circle PSL, Fl 33953 Prepared for Yen Ho

Inspection Report of 1895 Jamesport Circle PSL, Fl 33953 Prepared for Yen Ho Inspection Report of 1895 Jamesport Circle PSL, Fl 33953 Prepared for Yen Ho The State of Florida requires the builder to build in compliance with the Florida Building Code. Florida State Statutes 455

More information