Cheong Gye Cheon Restoration Project



Similar documents
Cheong Gye Cheon Restoration Project - a revolution in Seoul -

Environmental Engineering, University of Seoul, Jennong-dong, Dongdaemun-gu, Seoul, Korea.

Proposed General Plan Update Goals, Policies, and Implementation Actions

Los Angeles Union Station, CA Sustainable Neighborhood Assessment. April 22-23, 2014

National Disaster Management Institute

Stormwater Control Measures for Tokyo

VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY

Contents Small- to Mid-Size River Development Projects. Recent issues. 1.1 The rivers of Tokyo. Small- to Mid-Size River Development Projects

FOUR RIVERS RESTORATION PROJECT

Florida Avenue Multimodal Transportation Study. June 19, 2013

Earthquake Disaster Recovery Plan in TMG

THE FOUR RIVERS RESTORATION PROJECT AND ITS IMPLICATIONS TO THE CHAO PHRAYA RIVER

Corridor Goals and Objectives

"Description of the urban and architectural development conceptual design of the historical city centre of Gorzow Wlkp. R3DC4T

A Developer s Guide: Watershed-Wise Development

Downtown Tampa Transportation Vision

Toronto s Wet Weather Flow Master Plan

Rural Road Safety Policy in Korea: Lesson Learned

How To Build A River Restoration Project In North Korea

Sustainable Features. High-performance HVAC. High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements

Introduction to the Envision Sustainability Rating System

RESTORATION OF URBAN WATERWAYS AS A GREEN INFRA

Goals & Objectives. Chapter 9. Transportation

Making San Francisco a Water Sensitive City. Sarah Minick SFPUC Urban Watershed Management Program June 2009

VANDERBILT COMPARISON

Significant investment and improvement of infrastructure and transport networks, delivered at no cost and no risk

4 Alternatives and Design Evolution

OVERVIEW PROJECT SUMMARY

Protected Bicycle Lanes in NYC

Congestion Pricing Experiences in Singapore. Dr Kian-Keong Chin Chief Engineer, Transportation Land Transport Authority Singapore

Arkansas River Corridor Vision & Master Plan

General Obligation Bond Projects FYE

Damage to Sewage Treatment Systems caused by the Great East Japan Earthquake and the Government s Response

Copenhagen, Denmark - Trends in Public Perception

Traffic Information in NYC

Muddy River Restoration Project Project Description

City of Jakarta (Tanggerang) Total Greater Jakarta (Jabotabek) Area width

Bolton s Flood Risk Management Strategy

Tropical Storm Allison

Guiding Principles. McCauley Area Focused Urban Design Plan. 1 Connect: Chinatown and Little Italy with downtown and surrounding areas

Guildford Station Regeneration

The Mersey Gateway Project

How To Plan A Buffer Zone

Draft Non Transportation Performance Measures Including Related Qualitative Assessment of Example Sections

THE FOUR RIVERS RESTORATION PROJECT

Roads Task Force - Technical Note 10 What is the capacity of the road network for private motorised traffic and how has this changed over time?

Sector Design Concepts

Light Rail Transit in Phoenix

Managing the Transit Network A Primer on Key Concepts


Project Rankings. Fiscal Year Capital Improvement Plan

Comprehensive Flood Control Measures

Chicago Climate Action Plan Update

Permeable Pavers. calstone.com. Permeable Interlocking Concrete Pavements (PICP s)

River Management 2013 Colorado Flood

Measuring the Street:

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO.

Center for Sustainable Business Growth

Fast Track A Successful Redevelopment: The Palm Beach Outlets Story

Findings and Recommendations. June 2015

The New Master Plan aims to reverse the trend of declining population of Lisbon, creating conditions to attract more people.

Estimation of Travel Demand and Network Simulators to Evaluate Traffic Management Schemes in Disaster

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011

Transportation Alternatives

Caring for. our. harbour

4.5. ECOCITY Trnava. Concepts for ECOCITY model settlements. Figure ECOCITY Trnava site analysis

THE SOUNDSCAPE APPROACH. Pilot study in Bristol

Application for Planning Permission. Town and Country Planning Act 1990

WELCOME.

Maryland Invests $845 Million in New Highway and Bridge Projects

Flood Mitigation and Management in Bangkok Metropolitan Area

Presented by Dani Wise Johnson Vanasse Hangen Brustlin, Inc.

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

CWSRF Project Descriptions and Examples for Green Project Reserve

Ardessie Hydro Electric Project

Turn the Tide promote green, inclusive and sustainable urban mobility

Guangzhou, China's ecological future city

Vermont Economic Resiliency Initiative (VERI) Community Forum Barre City & Barre Town

esign interloc SUMMER 2014 PICP Residential Rebates Increasing Job Site Efficiency Preventing Bans on Charity Car Washes

If You Build It : The Impact of Street Improvements on Commercial Office Space

SECTION 2 CORRIDOR A

Recommendations for future developments

Penticton Creek May 4, 2015 Council Meeting

AUTHORIZED OFFICIAL. Title: Director, Western District - NYSOPRHP

Best Practice of Flood Hazard Map in Japan

4.4 ECOCITY Tampere - Vuores

12MAP-21, a funding and authorization bill to govern U.S. federal surface MONITORING IMPLEMENTATION AND PERFORMANCE

A NOTE ON THIS SUMMARY

Sustainable urban mobility: visions beyond Europe. Brest. Udo Mbeche, UN-Habitat

For more information, visit: rethinkingstreets.com

Sustainable city development through smart urban planning

Why build the Silvertown Tunnel?

ORANGE COUNTY TRANSPORTATION AUTHORITY. Final Long-Range Transportation Plan - Destination Attachment A

HARRIS TEETER AT LADY S ISLAND CITY OF BEAUFORT DRB CONCEPTUAL PROJECT NARRATIVE Submittal Date: September 2, 2015 Meeting Date: September 10, 2015

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

Shannon Corner Service Centre, Burlington Road, New Malden, KT3 4NP

First Transit Contra Flow Lane in Downtown San Francisco

THE RUSKIN COMMUNITY PLAN

Package Treatment Plant Policy and Procedure

Transcription:

Cheong Gye Cheon Restoration Project - a revolution in Seoul Director of The water Quality Management Division Kie-Wook Kwon Seoul Metropolitan Government

Before After

Content 1. Introduction Seoul and Cheong Gye Cheon 2. Cheong Gye Cheon 2002 3. The Restoration Project Background Outline Challenges Progress 4. Cheong Gye Cheon 2006 5. Final Remarks

I. Introduction - Seoul and Cheong Gye Cheon

Seoul & Cheong-Gye Cheon Area : 600 km 2 Population : 10 million Location Cheong-Gye Cheon - length: 13.7 km - width: 20~85 m

Old map of Seoul

Early 20C

Problem: sanitation

Solution: covering

Covering work (1958~1977)

Cheonggye Highway (1967~1971)

Highway in 1990s

II. Cheong Gye Cheon 2002

Cheong Gye Cheon Area Building: over 6,000 over 100,000 small shops Nation s biggest commercial area

Declining old CBD CBD redevelopment stopped where the Cheonggye Expressway started Population and employment reduced Population: 40,000 Employment: 80,000 in 10 years Business headquarters moved to Gangnam (new sub-center) Industries in CBD lost competitiveness

Safety problem Over all C, partially D or E

Safety problem Only small cars were allowed from 1997 Maintenance cost soared: JPN 5,000,000,000 ( 94~ 99)

III. The Restoration Project - Background - Outline - Challenges - Progress

Decision to restore: July 2002

III. The Restoration Project - Background - Outline - Challenges - Progress

Site location Total length: 5.84 km Restoration of upper reaches of CGC on a long term basis Divided into 3 sections to reduce the construction schedule Section 1 (L=2.04km) Section 2 (L=2.1km) Section 3 (L=1.7km)

Demolition Covered structure and highway: 5.4 km Waste (concrete+asphalt): 872,400ton (96% recycled) Step 1 Step 2 Step 3

Demolition - Dust and noise control was vital

River design Design Criteria Secure the stream capacity for 200 years frequency rainfall (118mm/hr) Access to Water: Install sidewalks along the lower level of the bank HWL (200yrs)

Flow Section Basic design secure flood capacity for 200 years frequency rainfall introduce lower terrace to enhance easy access to water

Flooded in Aug 3, 2003 for intensity of 60mm/h, upstream near Cheong-Gye Plaza

Water supply Water supply plan Water from the Han river: 120,000 ton/day Underground water from subway stations: 22,000 ton/day Waterway plan Depth: average 40 cm Flow velocity: 0.24 m/sec Measures to prevent water loss Water quality: better than the 2nd grade BOD: 3mg/l or less SS: 25 mg/l or less DO: 5 mg/l or less Total N: 10 mg/l or less Total P: 1 mg/l or less

Pipe line system 3,500t 14,000t 78,700t 10,800t 13,000t Pumping station Han river Intake station 120,000t/day Total length of pipe line: 20.7km

Sewer system Design Criteria Combined sewer system for rainfall and wastewater Capacity : 3 times of estimated wastewater Combined Sewer System

Bridge design Number of bridges: 22 Design Criteria Minimize flow resistance Harmony with surrounding area - artistic landmark International concept design competition

Landscape design Concepts New green belt with waterfront: West to East Gradual transformation from urban landscape to natural environment Create ecological biotop and environment Thematic places: waterfall and fountains Upstream A History B Culture + Urban C Nature Downstream

Typical planting section Street Tree Street Tree Wall greening Marsh area

Lighting plan Design Concept Target areas : Start point, Gwang-Gyo, Supyo-gyo and Dongdaemun Appropriate degree of illumination based on fish and insect life. 3-Dimensional consideration

III. The Restoration Project - Background - Outline - Challenges - Progress

Challenge 1: Transport Cheonggye road & hwy Urban backbone corridor 170,000 vehicles/day Traffic disaster warned Media, interest group Traffic simulation Project delay

Solutions to transport Discourage driving cars in the city centre Leave cars at home one out of 10 days Improve traffic flow system One-way streets Improve public transport Bus-only lanes Downtown shuttle buses

Challenge 2: Neighboring merchants Business decline Access difficulty: traffic congestion Worse environment: noise & dust due to construction

Solutions to merchants Detailed survey on the markets and continuous interviews consultation offices at the markets regular meeting on the project Minimize inconvenience for business activity state-of-the-art technology provide parking space nearby

Solutions to merchants Stimulate business activity Reduce parking fee Improve parking system for loading & unloading Promote Cheong Gye Cheon stores Financial support and subsidies Low-interest loans Grants for the market remodeling Special arrangement for street vendors

III. The Restoration Project - Background - Outline - Challenges - Progress

Construction progress Started on 1 July 2003

Construction progress Stage 1: Scaffolding (July 2003)

Construction progress Stage 2: Highway demolition (Aug 2003)

Construction progress Stage 3: Covered road demolition (Jan 2004)

Construction progress Stage 4: Sewer, road & bridge construction (Sep 2004)

Construction progress Stage 5: Landscaping for the recovered area (May 2005)

First water supply 1 June 2005

Test running & Final touch June ~ September 2005

Grand opening 1 October 2005

IV. Cheong Gye Cheon 2006

Monitoring Monitor the changes due to the project from Jan 2003~May 2006 before, during and after the project Monitoring areas Land use Industry Environment Ecology Traffic Public opinion Ripple effect Changes

Traffic Changes Speed in CBD 15.5 13.6 km/hr (-12.3%) Morning peak: 17 km/hr Evening peak: 12 km/hr not very much worsened Car in/out flow 1.56M 1.27M (-18.6%) Public transport rider-ship Bus: + 6~10 % Subway: + 6~9 %

Environment Air No2: 69.7 46.0 ppb (-34%) PM10: 74.0 60.0 μg/m3 (-19%) Water quality BOD: 100~250 1~2 ppm Noise level reduced Heat island effect relieved Wind corrider created Changes

Cooling effect Changes Thermal image 27 July 2005 37o 28o 36o 36o Average 32.7oC Cheong Gye Cheon -3.6oC Average 36.3oC Nearby street

Environmental improvement Changes Public survey (Nov 2005) Air Water Noise V improved Improved Unchanged Odour Daylight Wind 0% 25% 50% 75% 100%

Ecology: Fishes Changes 4 25 species

Ecology: Birds Changes 6 36 species

Ecology: Insects Changes 15 192 species

V. Final Remarks

Most preferred destination

Most preferred destination

Future of Cheong Gye Cheon Identity as the 600 yr old Capital Harmony between preservation & development Economic vitality Pedestrian oriented street system

Further information http://english.seoul.go.kr/cheonggye/ Thank you for your attention!