SAFE WORK METHOD STATEMENT SP003 Formwork and Concreting Part 1

Similar documents
WORKPLACE INDUCTION FOR CONSTRUCTION WORKPLACES INFORMATION SHEET 1

Contractor s Safe Working Agreement

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

Risk Assessment Tool (example only)

WHS Contractor Management Procedure

Job safety analysis Installing wall frames and roof trusses on-site

For ease of reference the clauses are arranged in 12 sections as follows:-

Tremline Pty Ltd trading as The Hills Bark Blower

Excavation & Trenching Procedure

SPECIFIC SAFETY OBLIGATIONS FOR CONTRACTORS ENGAGED WITH THE CITY OF BUNBURY.

SITE SPECIFIC FALL PROTECTION PLAN

WHS Contractor Management Procedure

7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

WHS CONTRACTOR MANAGEMENT PROCEDURE

A: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION

GHD EPCM Standard operating procedure Working at height May 2013 v1

WHS CONTRACTOR MANAGEMENT PROCEDURE

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

foot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.

Fall Protection Plan for Residential Roofing Construction. Tim Graboski Roofing, Inc.

Working at a height of two metres or more while carrying out general work activities or construction works

Traffic Management Issue 1.0 Revision: v2 October 2014

Jersey Safety Council. End Users Scaffolding Seminar

NORTHWEST AIRCONDITIONING SERVICE P/LFill = Green 204 SAFE WORK PROCEDURE Workplace: Page: 1 of 6 TASK / OPERATION: Air Conditioner Installation

Guidance Note GN049. Using portable ladders safely. WorkSafe Tasmania Department of Justice. Introduction and purpose

Managing the risk of falls while working on roofs in housing construction

WHS CONTRACTOR MANAGEMENT PROCEDURE

SITE CONTRACTOR PROCEDURES

Risk Assessment: An introduction

SAFETY SIGNAGE PROCEDURE

Generic Risk Assessment: Working on Roofs (FMRA 0006)

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard

Demolition Works Measures for Public Safety

Safe Work Method Statement

Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, , , , and1926.

WHS record keeping requirements

SAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399

Contractor Safety Management

Asbestos licensing and notification guide for applicants

RESIDENTIAL ROOF TRUSS INSTALLATION PROCEDURES

Chapter 3: Fall Protection/ Scaffolding Safety

Procedure. Working at Heights. 1. Purpose. 2. Scope. 3. Definitions. 4. Planning QUT risk check Work at Height permit

TEMPORARY TRAFFIC MANAGEMENT Operate as a Traffic Controller (TC) for low volume and Level 1 roads

PART 3: RIGHTS AND RESPONSIBILITIES

WORKING IN CONFINED SPACES GUIDELINES

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY

Activity Hazard Analysis (AHA)

Lifting Equipment - Work equipment for lifting or lowering loads and includes its attachments used for anchoring, fixing or supporting it.

Event Management Guidelines. Month Event Management Guidelines (Month, 2011)

WORK AT HEIGHT. STFC Safety Code No 9. Rev. 1.4, Issued April, 2015

Unit Title: Unit purpose and aim

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Asbestos removal and licensing

Construction and Civil Work Management

Procedure. Work Health and Safety General construction. Document number: PRO Description Process Owner Approved for issue. Rev no.

The Guide to Safer Scaffolds

OH&S Management Systems Audit Checklist (NAT, E3)

Programme-Based Engagement (ProBE) for Fall From Heights. Statistics

RZ Guardrail System Installation Manual

The Use and Application of the Benchmarking Assessment Tool for the Recovery and Recycling of Used Lead Acid Batteries in India

Trenching and Excavation Safety

Conditions of accreditation as an assessor for high risk work classes

ASBESTOS REMOVAL LICENCE ASBESTOS NOTIFICATIONS

Walking/Work Surfaces Fall Protection Program

WORK HEALTH AND SAFETY PUBLIC COURSES 2015 COURSE DATES AND FEES

SCAFFOLDING PRODUCT TECHNICAL GUIDE. Scaffold Couplers General Technical and Application Manual. Genuine Safety. Outstanding Service.

CONTRACTOR S MANAGEMENT PROCEDURE

Fall Protection Susan Harwood Grant Training Program 2013 Wood Frame Construction

Title: Plant and Equipment Management Procedure

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

Work Health and Safety Management Plan

The Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting

Traffic Management Scheme

SQF SYSTEMS PRACTICE TEST / OCTOBER, 2012 American Food Safety Services Division, Technical and Business Services, LLC

Safety Systems Review Facilities Management Guidance and specification Version

Pollution Incident Response Management Plan (PIRMP)

Unit Title: Unit purpose and aim

Page & Turnbull imagining change in historic environments through design, research, and technology

Policy Number: 054 Work Health and Safety July 2015

City of Belmont Contractor Induction Program

SCAFFOLDING AUGUST making a difference ERECTING, ALTERING AND DISMANTLING PART 1: PREFABRICATED STEEL MODULAR SCAFFOLDING

BCIT. CNST 1100 Construction Safety Officer Training. Lesson Plan

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

MANAGING RISKS OF PLANT IN THE WORKPLACE

Report on Sanctuary/Chancel Crawl Space Inspection. St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove. Project No.

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES

OSHA Scaffold Standard for Construction. 29 CFR 1926 Subpart L

POTENTIAL HEALTH & SAFETY HAZARDS

Engineering for Stability in Bridge Construction: A New Manual and Training Course by FHWA/NHI

Revision: 5. Category: Contract Management CONTENTS

POLICY ON OCCUPATIONAL HEALTH AND SAFETY RISK MANAGEMENT

PARTICIPANT HANDBOOK

THE METALITH PERIMETER SECURITY SYSTEM INSTALLATION INSTRUCTIONS. Attention

Transcription:

SAE WORK METHOD STATEMENT SP003 ormwork and Concreting Part 1 Company Details Company Name: Auzcon Pty td ABN: 431 4488 6359 Contact Name; Barney Geldenhuys, Project Manager, mob 0450 117 955 Address: 86 Campbell Parade, Beachmere, QD 4510 Project details Project: Contract No MBRC003349 for MoretonBay Regional Council Area: Margate Parade, Margate Job Address: Job Description: Activity: Margate Parade, Margate Construction of a vertical seawall and Boardwalk Concrete ormwork Relevant workers must be consulted in the development, approval and communication of this SWMS SWMS Approved by: Page 1 of 14 Name; Signature: Job Title: Date: Name: Signature: Date: Personnel responsible for monitoring and managing activity: Overall Risk Rating After Controls atal Moderate A PERSONS INVOVED IN TASK MUST HAVE THIS SWMS COMMUNICATED TO THEM PRIOR TO WORK COMMENCING High ow Regular inspections and observations will be conducted by Barney Geldenhuys to ensure SWMS is being complied with. Daily Tool Box Talks will be undertaken to identify, control and communicate additional site hazards. Work must cease immediately if incident or near miss occurs. SWMS must be amended in consultation with relevant persons. Amendments must be approved by Barney Geldenhuys and communicated to all affected workers before work resumes. SWMS must be made available for inspection or review as required by WHS legislation. Record of SWMS must be kept as required by WHS legislation (until job is complete or for 2 years if involved in a notifiable incident). Authorised by: B.Geldenhuys Page 1- Version. 1

Personal Protective Equipment oot Protection Hearing Protection High Visibility Head Protection Eye Protection Hand Protection Protective Clothing General: Safety footwear (rubber boots), gloves, protective clothing (long sleeve shirts and long trousers or overalls). Ensure all PPE meets relevant Australian Standards. Inspect, and replace PPE as needed. Provide UV sun protection where required, (broad brimmed hat, UV rated clothing, SP 30+ sunscreen, tinted safety glasses with adequate UV protection). Where required: Hearing protection, high visibility shirt or vest, hard hat. Safety Notes ormwork is the surface, supports and framing used to withstand the loads imposed by the forms and the concrete and any bracing added to ensure stability. Main hazards include: - formwork collapse (before, during and after placement of concrete) - falling s - noise/dust - manual handling Authorised by: B.Geldenhuys Page 2- Version. 1

Task Breakdown Possible Safety or Environmental Hazards RB Control Measures to Reduce risk RA Responsible Officer NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Design Specifications egislation breach Designers must: - ully describe all features of design - Provide SWMS for installation and stripping - Define load areas - define acceptance criteria - Provide for field adjustment - Describe location of weep, vibrator and clean-out holes and inspection openings - Detail sequence of concrete placement, including any slopes, direction of pour and time between pours - Describe strength, stability and stiffness of system - Detail foundation materials - Detail surface type (filling, compaction, drainage) - Allow for loads during construction (such as workers, materials, wind, false decks, rain, water runoff) reduce fall risks where practicable Certification of design must be provided by a competent person Engineer All formwork materials (timber/plywood, prefab modules aluminum, steel or plastic) must meet quality testing criteria as defined in AS 3610. All exposed rebar ends must contain end-caps. Ensure: - Correct size for bar - itted correctly - Regular inspections are undertaken to check condition of end caps and to ensure no caps are missing Note: End-caps to NOT provide adequate protection against impalement. Safe systems of work must be in place to prevent persons falling onto rebar ends (capped or not). Examples include guardrails, screens, edge protection of scaffolds, barriers and exclusion zones. Authorised by: B.Geldenhuys Page 3- Version. 1

Task Breakdown Possible Safety or Environmental Hazards RB Control Measures to Reduce risk RA Responsible Officer NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Preparation egislation breach Project documentation must be available on site and include (at least): - designs specifications - drawings - loading calculations - plans/elevations - general arrangements - maximum point loadings - component types and spacings - methods of securing structure and components - formply size - minimum stripping times - edge protection - back propping where required - any variations from design and subsequent certification of variations - safe load bearings - timeframes between pours and pour rates Engineer Site Supervisor Personnel requirements egislation breach Competency Based Training: Should include: - site induction - nature of hazards and emergency plans - requirements of AS3610 - Operation of plant/equipment as required - PPE (use, maintenance, storage) - Specific SWMS Site supervisor Risk Control Consider: - edge protection and netting to prevent falling s - fit for purpose work platforms/scaffolding - traffic management - mechanical lifting - adequate lighting - certificate of competencies where required Authorised by: B.Geldenhuys Page 4- Version. 1 Site Supervisor

Task Breakdown Possible Safety or Environmental Hazards RB Control Measures to Reduce risk RA Responsible Officer NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. - PPE and housekeeping ormwork Erection egislation breach All framing must be carried out so that it complies with on site design documentation and any manufacturers' requirements. Inspect all formwork components to ensure acceptable condition as per AS3610. Traditional oundation: - ensure stable base - ensure base plates are provided under props and standards - ensure suitable sole boards are provided Note: Base plates and sole boards may not be required if competent persons deems them unnecessary. All Note: If apped planks are used, they must be secured against uplifting and slipping. Pre-pour Inspection egislation breach Inspection should be undertaken by qualified person to ensure: - safe work practices were/are followed - system complies with requirement of design and project documentation - is adequately braced - is strippable - has adequate connections - correct spacing of frames, props and timbers; - correct joist and bearer sizes; - acceptable jack extensions; Site supervisor Concretor Authorised by: B.Geldenhuys Page 5- Version. 1

Task Breakdown Possible Safety or Environmental Hazards RB Control Measures to Reduce risk RA Responsible Officer NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. - adequate bracing to ensure stability. The engineer should supply an inspection certificate to verify the structural integrity of the support structure and formwork system During Concrete Pour egislation breach Ensure: - continuous supervision of the formwork assembly and concrete placement - Communication between the supervising personnel and the placing crews. - Monitor indicators if installed - if any failure, undue settlement or distortion of the formwork develops, work should cease and - the affected formwork assembly or component strengthened or replaced - concrete is placed and compacted in a manner that ensures specified quality of surface finish All Dismantling ormwork (Stripping) Concrete should be inspected prior to dismantle: Check for unacceptable: - warping - twisting - cracks - blowholes - deviations as per AS3610 Site Supervisor egislation breach - Authorised by: B.Geldenhuys Page 6- Version. 1

Task Breakdown Possible Safety or Environmental Hazards RB Control Measures to Reduce risk RA Responsible Officer NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Emergency Plan egislation breach M Must include (at least): - rescue procedures - evacuation points - roles/responsibilities - communication procedures - first aid - use and location of fire protection equipment M All References: Work Health and Safety Act 2011 and Work Health and Safety Regulations 2011 Queensland ormwork Code of Practice Australian Standard - AS3610-1995 ormwork for Concrete Australian Standard AS3600 Concrete Structures Australian Standard - AS1379 Specifications of supply of concrete NSW Code of Practice for ormwork Authorised by: B.Geldenhuys Page 7- Version. 1

SAE WORK METHOD STATEMENT Part 2 ormal Training, icenses required for workers undertaking this task: Example: - icense to Perform High Risk Work (operating certain plant, equipment) - TAE or other recognized training organization Duties of workers undertaking this task: Example: (Name): Operator (Name: Clean-up crew (Name): Supervisor etc Training in the following safe work procedures/ SWMS / training modules is required: (All workers to be trained in relevant procedures.) Site-specific inductions Training in this SWMS Nature of hazards / risks Emergency procedures Details of Supervisory Arrangements for workers undertaking this task: Details of regulatory permits/licenses, Engineering Details/Certificates/WorkCover Approvals: Relevant egislation, Codes of Practice: Authorised by: B.Geldenhuys Page 8- Version. 1

Example: - Competent supervisors for job - Direct on-site supervision - Remote site communication systems/ schedule - Audits - Spot Checks, etc - Reporting systems Example: - ocal council permits - Building Approvals - EPA approvals/permits - Certain plant to be registered with The Regulator - PPE to comply with relevant Australian Standards Work Health and Safety Act 2011 and Work Health and Safety Regulations 2011 Queensland ormwork Code of Practice Australian Standard - AS3610-1995 ormwork for Concrete Australian Standard AS3600 Concrete Structures Australian Standard - AS1379 Specifications of supply of concrete NSW Code of Practice for ormwork Plant/Tools/Equipment: (ist plant and equipment to be used on the job.) Example: Electric jackhammer Maintenance Details for plant / equipment used on job (Include cranes, forklifts, electrical equipment etc.) As per manufacturer s recommendations. Electrical tested/tagged every 3 months. Authorised by: B.Geldenhuys Page 9- Version. 1

Part 3- SIGN O This SWMS has been developed in consultation and cooperation with workers and relevant Persons Conducting Business or Undertaking (PCBU). I have read the above SWMS and I understand its contents. I confirm that I have the skills and training, including relevant certification to conduct the task as described. I agree to comply with safety requirements within this SWMS including safe work instructions and Personal Protective Equipment described. Name Qualifications Signature Date Time PCBU Review No. 1 2 3 4 5 6 7 8 9 Name and initials Date Authorised by: B.Geldenhuys Page 10- Version. 1