TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Size: px
Start display at page:

Download "TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE"

Transcription

1 TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

2 TECHNICAL SPECIFICATION PART PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL General Approval of Methods Construction Marking Handling Tolerances PRECAST CONCRETE PIPES General Materials Joints Payment PRECAST CONCRETE BEAMS General Dimensions and Tolerance Payment PRECAST PRESTRESSED CONCRETE BEAMS General Approval of Methods Handling of Beams Dimensions and Tolerance Construction Payment PRECAST CONCRETE PILES General Materials Casting Marking of Poles Handling of Piles Stacking of Piles Measurement Payment MISCELLANEOUS PRECAST CONCRETE General Payment 8-11 UNOPS-Afghanistan PART 8-1

3 8100: precast concrete construction general 8101 General a) The Contractor shall construct and erect precast concrete units, in accordance with this Part where and as shown on the Drawings or directed. b) The units may be supplied by a manufacturer or may be manufactured by the Contractor at an approved location. For units, such as precast concrete pipes, which are not detailed on the Drawings, the Contractor shall also submit for approval all details of the individual units, including proposed reinforcement and location of lifting points as hereinafter specified. c) Repairing of damaged units will not be approved except where such damage and repair will not impair the strength or the appearance of the units after installation Approval of Methods Thirty days before commencing manufacture of all precast concrete units the Contractor shall submit for approval all details of the methods to be used in manufacture, handling, transport, storage and erection of the units Construction a) Except as otherwise provided in this Part, all units shall be constructed and created in accordance with the applicable requirements of Parts 6 and 7. b) The maximum size of aggregate for all precast concrete shall generally be 20 mm, except for concrete pipes where the maximum size of aggregate shall be 10 mm. c) The classes of concrete used to manufacture precast concrete units shall be in accordance with Clause 6.2 of this Specification d) All units shall be cast in individual forms and may be cured by steam curing in accordance with Clause e) Where the use of immersion type vibrators is not practicable the Contractor shall consolidate thin precast concrete slabs and units on a vibrating table or by another approved method Marking a) Immediately on removal of forms, each unit shall be clearly marked with the date of casting, the estimated mass and the identification number directed by the Engineer. Temporary identification and date of casting markings shall be scratched into the top surface of beams near an end immediately after screeding off. b) The marking shall be made by an approved indelible marking material using letters approximately 75 mm high. c) Care shall be taken to ensure the marking on outside facing bridge beams is made on the inner face Handling a) At all times, especially during transportation, all precast concrete units shall be supported as in their final positions. Other methods of support may be approved if the Engineer considers that the units will not be damaged in any way by the proposed method of support. b) All units shall be lifted only at the lifting points shown on the Drawings. Where lifting devices have not been detailed the Contractor shall submit, for approval, complete calculations and details of his proposed lifting devices. UNOPS-Afghanistan PART 8-2

4 c) All units shall be adequately braced and supported during erection to ensure proper alignment and safety. Such bracing or support shall be maintained until adequate permanent connections have been made. Special care shall be taken not to damage the flanges of beams. d) Temporary supports for members shall be timber bearers at least 150 mm wide and 100 mm thick, placed on a firm foundation and supporting the members over their full width. The ground or space between the bearers supporting the members shall be carefully cleared and levelled to prevent the member being accidentally supported other than on the bearers. e) No precast unit manufactured away from the site shall be delivered to the site without the approval of the Engineer, nor shall a unit be transported from the place of manufacture prior to the completion of the specified curing Tolerances For the purposes of this Clause the following definitions or interpretations apply: i. Tolerance means the permitted variation from a stated dimension or shape, excluding any deliberate shortening of dimension to provide clearance. ii. Length and Width refer, as the case requires to : the longer and shorter sides of a rectangular precast unit; any side of a unit which is not rectangular; the overall length and width at any location of any unit. iii. iv. Straightness and Flatness mean the tolerance distance of any part of an edge or surface from the nearest point of a straight line joining the ends of the edge or of the surface in any direction. Twist means the rotation of one end relative to the other end. v. Warp means the maximum permissible tolerance distance of any point on a surface from any of the four planes through three of the four corners of a rectangular surface. These corners, if the surface is not rectangular, being those points on the surface which are the corners of a rectangle having the greatest possible area and generally, but not necessarily wholly, within the actual surface of the unit. vi. Squareness means the maximum permissible tolerance distance by which a shorter side may deviate from a straight line through the corner and perpendicular to the longer side. any error in the straightness of the adjacent sides being ignored for the purposes of this definition; and where the included angle between the surfaces or sides is intended to be other than a right angle, the check line being varied accordingly. The dimensions of all finished precast concrete units shall be within the following limits at the time of placement of the units in the structure, unless otherwise specified herein or shown on the Drawings: UNOPS-Afghanistan PART 8-3

5 Table 8-1 Dimensions Tolerances I. Members others than flat panels: 3 Cross-section, overall dimensionsless than 600 mm, but less than 1600 mm, but less than 1500 mm, not less than 1500 mm. 3 Cross-section, dimension of parts such as webs, ribs and flanges less than 1500 mm, not less than 1500 mm. c) Length, critical dimensions of abutting members. 3 Length, non-critical less than 6 m; not less than 6 m. e) Twist. ±3 mm ±6 mm +10 mm, - 6 mm ±6 mm +10 mm,- 6 mm +0, - 6 mm ±length/1000 ±6 mm 10 mm/m width per 3 m of length Table 8-2 II. All units: a) Straightness of edges and flatness of surfaces. b) Warp less than 5 m diagonal not less than 5 m diagonal c) Squareness of corners - less than 2 m, on shorter side; not less than 2 m, less than 4 m, not less than 4 m. d) Holes or openings and the like, diameter or side dimensions. e) Location of holes or openings f) Grooves, width and depth. g) Position of individual connecting bolts, both holes, projecting metal or other devices in any associated group (e.g. the joint of two precast units). h) Longitudinal locations of any such groups (mentioned in item (g) ) Length/ mm 10 mm 3 mm 5 mm 6 mm ±3 mm ±7 mm 2 mm Within 3 mm of their true positions in the group in which they are cast. Within 6 mm of its true position in the unit in which it is cast, if the tolerance does not adversely affect the proper assembly of the whole structure. UNOPS-Afghanistan PART 8-4

6 8200: Precast Concrete Pipes 8201 General a) The Contractor shall manufacture precast concrete pipes for pipe culverts in accordance with this Clause and the applicable provisions of Parts 6 and 7. b) Concrete pipe shall be constructed in accordance with Clause Materials a) Concrete pipes shall be 300 mm, 600 mm, 815 mm and 1700 mm inside diameter and shall conform to the requirements of AASHTO M242M. b) For each diameter of pipe, classes shall differentiate between pipes of different strength designation. c) The strength designation of the pipe shall be the D-load to produce a 0.30 mm crack when tested by the three-edge bearing method of loading all in accordance with AASHTO T280M. The D-load strength is quoted as Kilo Newtons per linear metre (KN/m), and minimum required strengths and classes are. Table 8-3 Diameter mm Class II I II I II III I D-load kn/m d) Pipes to be tested for strength shall be selected at random by the Engineer. At least one pipe for each diameter and class of pipe shall be tested to failure by the Contractor in the presence of the Engineer, and the material cost of this pipe shall be paid for by the Employer. Otherwise, the cost of all equipment and labour required to carry all testing of pipes shall be included in the rates for construction of pipe culvert in Clause e) Minimum clear cover to reinforcement shall be 30 mm. f) Reinforcement shall comply with clause Joints a) In general, concrete pipes shall be manufactured with male and female ends. Joints in concrete pipes shall be of the bell and spigot type. b) All joints shall be capable of transferring the required shear across the joint. The Contractor shall furnish to the Engineer a certificate of compliance that the pipes conform to this requirement. UNOPS-Afghanistan PART 8-5

7 c) pipes shall be interchangeable, except for special end sections Payment Payment for precast concrete pipes will be made in accordance with Clause : Precast Concrete Beams 8301 General The Contractor shall furnish and erect precast reinforced concrete beams for bridges to the lines, grades and dimensions shown on the Drawings or directed by the Engineer Dimensions and Tolerances a) The dimensions and shape of precast concrete beams shown on the Drawings shall apply to the beams as close as practicable to 28 days after casting and the beams shall be supported at the positions specified for stacking. b) The dimensions and profile of the forms shall be so constructed to include the upward deviation in the vertical plane, or camber, required as shown on the Drawings. The Contractor shall submit, for approval, details of how he proposes to introduce the camber, and construction of the forms shall not commence without such approval by the Engineer. c) Except where otherwise required by Clause 8.5, tolerances for precast concrete beams shall be in accordance with Clause Payment a) Payment for furnishing and erecting precast reinforced concrete beams will be made at the rate per cubic metre of concrete in the finished beam bid therefore in the priced Bill of Quantities (Item 8.04). b) The rate shall include the entire cost of all labour, equipment and materials required to manufacture and erect the precast beams in their final positions, except that separate payment will be made for reinforcement and miscellaneous metal work in the beams, in accordance with Clauses 7.7 and 12.3 respectively. 8400: Precast Prestressed Concrete Beams 8401 General a) The Contractor shall furnish and erect precast prestressed concrete beams for bridges to the lines, grades and dimensions shown on the Drawings or directed by the Engineer. The beams shall be cast as shown on the Drawings. b) Prestressing of precast beams shall be in accordance with Part Approval of Methods The Contractor shall, at least 30 days before commencement of manufacture of the precast beams: i. Submit to the Engineer for approval full details of his method of forming, placing and curing of the beams and his handling, transporting, stressing, grouting and erection methods. Once approved, the Contractor shall not vary his methods without the written approval or direction of the Engineer; and UNOPS-Afghanistan PART 8-6

8 ii. Submit to the Engineer for approval shop Drawings and details of all metalwork, prestressing tendon anchorages to be embedded in the beams, schedules of locations of material and marks by which individual items can be identified Handling of Beams a) Prestressed concrete beams shall be fully stressed or stressed to the extent shown on the Drawings and all stressed tendons shall have been grouted for 7 days before lifting or handling of the beam unless the moving of the beams off their casting beds before grouting stressed tendons is approved. If such approval is given each ungrouted tendon shall be adequately marked for possible slip and should any slip or damage occur, the tendon shall be replaced and/or re-stressed as directed. b) Completed beams shall not be stacked on top of each other and no superimposed load shall be placed on a member without prior approval Dimensions and Tolerance a) The dimensions and shape of prestressed concrete beams shown on the Drawings shall apply to the beams at the time of their completion when under self weight alone. b) Except where shown otherwise on the Drawings or approved, the dimensions and profile of the forms shall compensate for deformations caused by prestressing so that the dimensions and profile of the completed members shall conform to the Drawings. The Contractor shall submit, for approval, details of the magnitude of these deformations and how he proposes to allow for them. Construction of the forms shall not commence without such approval. c) Except where otherwise required by this subclause, tolerances for prestressed concrete beams shall be in accordance with Clause 8.1. d) Variation in the overall length and length centre to centre of bearings shall be accurate to within 7 mm or ±0.05 per cent of the length, whichever is the greater. e) Sagging profiles in a vertical plane will generally not be permitted but upward deviation (hog) from the required profile of up to 0.1 per cent of the span length will be approved. f) The deviation of a member from straightness in a horizontal plane (bow) shall not exceed 7 mm or ±0.05 per cent of the length of the member, whichever is greater. g) Location of ducts and sheathing shall be accurate to ±4 mm. h) Cover to ducts and sheathing shall be not less than 50 mm Construction a) Sheathing for all ducts shall be placed accurately in the formwork in the position shown on the Drawings and shall be adequately tied and held against movement during concreting. The sheathing shall be fixed so as to ensure the alignment as well as the position of ducts at joints is accurate. All joints in the sheathing shall be mortar tight. Sheathing shall be stiffened during concreting by means of an internal stiffener of equal or greater diameter than the final tendons. Immediately after the whole of the concrete has been placed in a precast concrete beam, all duct internal stiffeners shall be pulled back and forth for about 300 mm to ensure they are perfectly free inside the sheathing. b) All anchorage plates for prestressing tendons shall be accurately positioned square to the line of action of the tendons and held firmly during concreting. Should any mortar adhere to the exposed faces of the anchorages, it shall be removed. UNOPS-Afghanistan PART 8-7

9 c) Concrete shall not be placed until all formwork, block outs, installations of sheathing, grout points or vents, anchorage plates for prestressing tendons, reinforcement, embedded metalwork and any other fittings shown on the Drawings or required by the Specification have been approved by the Engineer. Placing of concrete shall be performed only in the presence of the Engineer. d) The parts of the top surface upon which the concrete deck is to be placed shall be suitably roughened to the extent shown on the Drawings by compressed air nail hammering or other approved means. Care shall be taken to protect corners from damage or disfiguration Payment a) Payment for furnishing and erecting precast prestressed concrete beams will be made at the rate per cum. bid therefore in the priced Bill of Quantities. b) The rates shall include the entire cost of all labour, equipment and material required to manufacture the precast beams and to erect the prestressed concrete beams in their final positions, except that separate payment will be made for supply and installation of prestressing materials and prestressing, reinforcement and miscellaneous metalwork in the beams, in accordance with Clause 10.3, 7.7 and 12.3 respectively. Pay Item Unit 84/1 Payment for furnishing and erecting precast prestressed concrete beams Cum 8500: Precast Concrete Piles 8501 General The Contractor shall construct precast reinforced concrete piles in accordance with this clause as shown on the Drawings or directed by the Engineer. b) Piles shall be manufactured to the lengths and cross sectional dimensions to conform to the toe levels shown on the Drawings or directed by the Engineer and in accordance with Part Materials a) Concrete in precast concrete piles shall comply with Parts 6 and 7 of this Specification. b) Pile shoes and splice plates shall be manufactured from mild steel plates welded to reinforcement and cast into the head or toe of the pile as shown on the Drawings or directed by the Engineer. c) Piling shall be in accordance with Part 11 of this Specification Casting a) Piles shall be cast on a horizontal platform in box moulds as approved by the Engineer. Fillets shall be fixed to the formwork to provide all chamfers as shown on the Drawings. b) The placement of concrete in each pile shall be completed in one continuous operation and no interruption to the placement will be permitted. c) Lifting holes shall be cast into the piles in the positions shown on the Drawings. UNOPS-Afghanistan PART 8-8

10 8504 Marking of Piles a) Each pile shall be clearly marked within 600 mm from the pile head. The date, identification number required by the Engineer and the overall length of the pile shall be marked. The marking shall be in indelible paint which is not injurious to the concrete and the letters shall be at least 75 mm high. b) Commencing at 5 m from the toe, and thereafter at 1 m intervals up to the head, each pile shall be marked by a lightly scribed line across the full width of one face of the pile, and square to its length. The distance of each such line from the toe shall be lightly scribed Handling of Piles a) Piles shall have reached a concrete compressive strength of at least 25 MPa prior to removal from the casting bed. b) All piles shall only be lifted at the lifting holes provided as shown on the Drawings, unless otherwise approved by the Engineer. c) The Contractor shall ensure that piles are not subjected to high impact loads during the handling operations Stacking of Piles a) For the stacking of piles heavy, sill logs shall be well embedded into the ground and flattened on the top surface to give a bearing width of not less than 200 m with a minimum clearance above the ground of 150 mm. b) Sill logs shall be positioned as shown on the Drawings or directed by the Engineer. c) Piles shall be stacked on top of each other for up to 5 layers, providing that the ground foundations are deemed suitable by the Engineer. d) When layering piles for stacking, each layer shall be separated by timber bearers 150 mm wide by 100 mm high. The bearers shall be centrally placed above the sill logs Measurement Measurement for payment for constructing precast concrete piles will be made of the volume of concrete in the driven piles below the underside of the pile caps as shown on the Drawings or directed by the Engineer Payment a) Payment for constructing precast concrete piles will be made at the rate per cubic metre bid therefore in the priced Bill of Quantities (Item 8.07/1). This rate shall include the entire cost of all labour, equipment and materials required except that separate payment will be made for reinforcement. b) Payment for Furnishing precast concrete piles will be made at the rate per linear metre of piles driven and accepted (Items 8.07/2) which rate shall include the cost of pile shoes and splice plates. c) Payment for reinforcement in concrete piles shall be in accordance with Clause 7.7. Pay Item Unit 85/1 constructing precast concrete piles Cum 85/2 Furnishings, placing and driving of pre-cast concrete piles Linear-m UNOPS-Afghanistan PART 8-9

11 8600: Miscellaneous Precast Concrete 8601 General The Contractor shall furnish and install miscellaneous precast concrete not specifically shown on the Drawings, but as directed by the Engineer Payment Payment for furnishing and installing miscellaneous precast concrete will be made at the rate per cubic metre bid therefore in the priced Bill of Quantities. Payment for metalwork embedded in the concrete will be made in accordance with Clause Installation, materials, shuttering included except reinforcement. Pay Item Unit 86/1 Furnishing and Installing Pre-cast reinforce concrete Cum 86/2 Furnishing and Installing Pre-cast plain concrete Cum UNOPS-Afghanistan PART 8-10

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Design and Construction of Cantilevered Reinforced Concrete Structures

Design and Construction of Cantilevered Reinforced Concrete Structures Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures

More information

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

AISI CHEMICAL COMPOSITION LIMITS: Nonresulphurized Carbon Steels

AISI CHEMICAL COMPOSITION LIMITS: Nonresulphurized Carbon Steels AISI CHEMICAL COMPOSITION LIMITS: Nonresulphurized Carbon Steels AISI No. 1008 1010 1012 1015 1016 1017 1018 1019 1020 1021 1022 1023 1024 10 1026 1027 1029 10 1035 1036 1037 1038 1039 10 1041 1042 1043

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab, DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

Chapter. Restoration of Damaged Structures

Chapter. Restoration of Damaged Structures 5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

Detailing of Reinforcment in Concrete Structures

Detailing of Reinforcment in Concrete Structures Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For

More information

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE Community Development Permit Services SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE PROJECT NAME PROJECT ADDRESS PERMIT NUMBER CITY RECEIVED STAMP AND INITIALS Instructions: BEFORE

More information

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges 7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience

More information

FORM DESIGN. easy to work with, and generally available.

FORM DESIGN. easy to work with, and generally available. Forms play a major role in concrete construction. They give the plastic concrete its shape and hold it until it hardens. Forms protect the concrete, assist in curing it, and support any reinforcing rods

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.

Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug. P-5 The P-5 is hot forged from carbon steel. The formed head provis spherical seating that the Lifting Eye engages, while a disc-shaped foot is embedd in the concrete. Due to its being a forged part, the

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

SECTION 02612 NONREINFORCED CONCRETE SEWER PIPE

SECTION 02612 NONREINFORCED CONCRETE SEWER PIPE SECTION 02612 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Furnishing and installing nonreinforced concrete sewer pipe. Provide concrete sewer pipe less than 12 inches in diameter, and in other sizes

More information

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span formwork formwork Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span has grown to become one of the major players in the scaffolding and

More information

INSTALLATION. General. Important Note. Design. Transport

INSTALLATION. General. Important Note. Design. Transport General The roof trusses you are about to install have been manufactured to precise engineering standards. To ensure that the trusses perform as designed, it is essential that they be handled, erected

More information

SECTION 02845 GUARDRAILS

SECTION 02845 GUARDRAILS SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein

More information

PRE INSTALLATION MANUAL

PRE INSTALLATION MANUAL REINFORCED CONCRETE PIPE PRE INSTALLATION INSPECTION & REPAIR MANUAL Kentucky Transportation Cabinet Kentucky Department of Highways Division of Materials 1227 Wilkinson Boulevard Frankfort, KY 40601 (502)

More information

POST AND FRAME STRUCTURES (Pole Barns)

POST AND FRAME STRUCTURES (Pole Barns) POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:

More information

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow. 9.2 One-way Slabs This section covers the following topics. Introduction Analysis and Design 9.2.1 Introduction Slabs are an important structural component where prestressing is applied. With increase

More information

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14 Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

Installation Instructions

Installation Instructions Installation Instructions 1. Position the unit onto bridging packers. These keep the unit away from any water sitting inside the frame. 2. Centralise the unit within the frame and pack the edges with appropriate

More information

Technical Notes 3B - Brick Masonry Section Properties May 1993

Technical Notes 3B - Brick Masonry Section Properties May 1993 Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

SECTION 7: C - STRUCTURAL ENGINEERS SPECIFICATIONS

SECTION 7: C - STRUCTURAL ENGINEERS SPECIFICATIONS SECTION 7: C - STRUCTURAL ENGINEERS SPECIFICATIONS SITE C SHOPPING CENTRE, KHAYELITSHA PROJECT NO 2369 Project Specification Refer all queries to: John Meiring Tel: +27 21 425 0065 REVISION P01 E-mail:

More information

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS SERIES NG 400 SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS Contents Clause Title Page NG 401 Performance Criteria for Safety Fences and Safety Barriers 2 NG 402 Components for Safety Fences

More information

9.3 Two-way Slabs (Part I)

9.3 Two-way Slabs (Part I) 9.3 Two-way Slabs (Part I) This section covers the following topics. Introduction Analysis and Design Features in Modeling and Analysis Distribution of Moments to Strips 9.3.1 Introduction The slabs are

More information

(B) Reinforcing and Tie Bars shall conform to the requirements of Mn/DOT 3301 unless otherwise shown on the Contract Drawings.

(B) Reinforcing and Tie Bars shall conform to the requirements of Mn/DOT 3301 unless otherwise shown on the Contract Drawings. S-1 (2301) FABRICATION AND PLACEMENT OF PRECAST CONCRETE PAVEMENT PANELS This work consists of furnishing and installing reinforced precast concrete highway pavement slabs as shown on the Plans and in

More information

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,

More information

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE 86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,

More information

Code of Standard Practice for Timber Frame Structures

Code of Standard Practice for Timber Frame Structures TFEC 2-2013 Code of Standard Practice for Timber Frame Structures August 2013 Preface This Code is intended to represent a reasonable consensus of what constitutes ordinary and acceptable practice within

More information

Overhang Bracket Loading. Deck Issues: Design Perspective

Overhang Bracket Loading. Deck Issues: Design Perspective Deck Issues: Design Perspective Overhang Bracket Loading Deck overhangs and screed rails are generally supported on cantilever brackets during the deck pour These brackets produce an overturning couple

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

1.2 Advantages and Types of Prestressing

1.2 Advantages and Types of Prestressing 1.2 Advantages and Types of Prestressing This section covers the following topics. Definitions Advantages of Prestressing Limitations of Prestressing Types of Prestressing 1.2.1 Definitions The terms commonly

More information

APPENDIX K PIPE INSPECTION

APPENDIX K PIPE INSPECTION APPENDIX K PIPE INSPECTION **Virginia Test Method 123** Post Installation Inspection of Buried Storm Drain Pipe and Pipe Culverts June 25, 2010 SCOPE For all roadway projects that are constructed by private

More information

Chapter. Earthquake Damage: Types, Process, Categories

Chapter. Earthquake Damage: Types, Process, Categories 3 Chapter Earthquake Damage: Types, Process, Categories Earthquakes leave behind a trail of damage and destruction. People s lives are affected by the loss of loved ones, destruction of property, economic

More information

Optimum proportions for the design of suspension bridge

Optimum proportions for the design of suspension bridge Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering

More information

COMMONLY USED RESIDENTIAL BUILDING CODES

COMMONLY USED RESIDENTIAL BUILDING CODES COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section

More information

INSTRUCTIONS FOR USE

INSTRUCTIONS FOR USE 2/2013 ANCHOR BOLTS INSTRUCTIONS FOR USE - Threaded rebars ATP, AHP, AJP - Threaded high strength steel bolts ALP-L, ALP-P, AMP ATP AHP ALP-L ALP-P AMP Eurocode design according to EN1993-1-8 (2005) &

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,

More information

Timber Decks. Technical Note. March 2007

Timber Decks. Technical Note. March 2007 Timber Decks Technical Note. March 2007 This Technical Note contains general information for residential timber decks and floor frame structures for veranda s, patios etc which are exposed to the weather.

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

CONTENTS. Page KERBS ETHEKWINI PRODUCTS ETHEKWINI PRODUCTS WATER CHANNELS WATER CHANNELS / GRILL BLOCKS / CHANNEL DRAIN COVERS

CONTENTS. Page KERBS ETHEKWINI PRODUCTS ETHEKWINI PRODUCTS WATER CHANNELS WATER CHANNELS / GRILL BLOCKS / CHANNEL DRAIN COVERS CONTENTS KERBS ETHEKWINI PRODUCTS ETHEKWINI PRODUCTS WATER CHANNELS WATER CHANNELS / GRILL BLOCKS / CHANNEL DRAIN COVERS STADIUM SEATING / ETHEKWINI & TELKOM SPEC PRODUCTS PRECAST PANELS DURBAN BEACHFRONT

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally

More information

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)

More information

6 RETROFITTING POST & PIER HOUSES

6 RETROFITTING POST & PIER HOUSES Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This

More information

Operations and Instruction Manual Might Swivel - Part # 310273 Concrete and Steel Anchorage Connector ANSI Z359.1 10,000 lbs / 44kn

Operations and Instruction Manual Might Swivel - Part # 310273 Concrete and Steel Anchorage Connector ANSI Z359.1 10,000 lbs / 44kn Safety.. Operations and Instruction Manual Might Swivel - Part # 310273 Concrete and Steel Anchorage Connector ANSI Z359.1 10,000 lbs / 44kn Description: Technical: Zinc plated forged heat treated steel,

More information

8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS

8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS 8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS MARICA DELLA BELLA and DIEGO CIAN Precompressi Centro Nord S.p.A., Italy SUMMARY: Secondary roofing elements, complementary to the

More information

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/2011. 7. Stud Welding

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/2011. 7. Stud Welding 7. Stud Welding 7.1 Scope Section 7 contains general requirements for welding steel studs to steel (see 7.2.7 and 1.2.2 for approved steels). In addition, it stipulates specific requirements for the following:

More information

No allowance will be made for classification of different types of material encountered.

No allowance will be made for classification of different types of material encountered. PROJECT : Repair/ Maintenance of Flood Control and Drainage Structures Along Butuan City Cagayan de Oro City Iligan City Road LOCATION : San Antonio, Jasaan, Misamis Oriental SUBJECT : General Notes and

More information

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE Multi-storey Precast Concrete Framed Structures Kim S. Elliott BTech, PhD, CEng, MICE Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE WI LEY Blackwell Contents Preface Notation Precast Concepts, History

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

Structural Failures Cost Lives and Time

Structural Failures Cost Lives and Time Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one

More information

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...

More information

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

Handling, Erection and Bracing of Wood Trusses

Handling, Erection and Bracing of Wood Trusses Handling, Erection and Bracing of Wood Trusses Follow these guidelines for safe installation of Wood Trusses. These guidelines should not be considered to be the only method for erecting and bracing of

More information

Post and Beam Construction

Post and Beam Construction Post and Beam Construction A Presentation By the Canadian Wood Council Canadian Conseil Wood canadien Council du bois Early settlers introduced the concept of post and beam construction in North America

More information

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE A.Rito Proponte, Lda, Lisbon, Portugal J. Appleton A2P Consult, Lda, Lisbon, Portugal ABSTRACT: The Figueira da Foz Bridge includes a 405 m long cable stayed

More information

DMS - 7310 REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION AND PLANT QUALIFICATION

DMS - 7310 REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION AND PLANT QUALIFICATION DMS - 7310 REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION EFFECTIVE DATE: APRIL 2012 7310.1. Description. This specification will govern for the fabrication of machine-made

More information

Pro-Lift Steel Pile Foundation Repair

Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair System Pro-lift steel piles are designed for the stresses of Texas soils. They can have multiple steel walls, depending on the

More information

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Construction Specification for Concrete Curb and Concrete Curb and Gutter Engineering & Construction Services Division Standard Specifications for Road Works TS 3.50 April 2015 for Concrete Curb and Table of Contents TS 3.50.01 SCOPE... 3 TS 3.50.02 REFERENCES... 3 TS 3.50.03

More information

Guidelines for Earthquake Bracing Residential Water Heaters

Guidelines for Earthquake Bracing Residential Water Heaters Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the

More information

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Guidelines for Earthquake Bracing of Residential Water Heaters

Guidelines for Earthquake Bracing of Residential Water Heaters Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major

More information

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the

More information

PART 1 GENERAL 1.1 SECTION INCLUDES

PART 1 GENERAL 1.1 SECTION INCLUDES J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1 Chapter 5 Bridge Deck Slabs Bridge Engineering 1 Basic types of bridge decks In-situ reinforced concrete deck- (most common type) Pre-cast concrete deck (minimize the use of local labor) Open steel grid

More information

Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS

Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS 8.1.1 PURPOSE This procedure provides guidelines related to the implementation of quality control and quality assurance

More information

Chapter 6 ROOF-CEILING SYSTEMS

Chapter 6 ROOF-CEILING SYSTEMS Chapter 6 ROOF-CEILING SYSTEMS Woodframe roof-ceiling systems are the focus of this chapter. Cold-formed steel framing for a roof-ceiling system also is permitted by the IRC but will not be discussed;

More information

Bracing Webs in Trusses that have Dissimilar Configurations

Bracing Webs in Trusses that have Dissimilar Configurations Bracing Webs in Trusses that have Dissimilar Configurations Released April 25, 2006 Issue: Truss Design Drawings (TDD) that are prepared in accordance with ANSI/TPI 1, National Design Standard for Metal

More information

LEGACY REPORT. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council. *Corrected March 2014

LEGACY REPORT. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council. *Corrected March 2014 ICC-ES Legacy Report PFC-3700* Issued October 2003 www.icc-es.org (00) 423-57 (52) 99-0543 A Subsidiary of the International Code Council Legacy report on the 1997 Uniform Building Code and the 2000 International

More information

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P This material is duplicated in the Mechanical Principles module H2 and those

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

PART E SPECIFICATIONS

PART E SPECIFICATIONS PART E SPECIFICATIONS Page 1 of 5 PART E - SPECIFICATIONS GENERAL E1. APPLICABLE SPECIFICATIONS, STANDARD DETAILS AND DRAWINGS E1.1 The City of Winnipeg Works and Operations Division Standard Construction

More information

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width Modern Applied Science; Vol. 9, No. 6; 2015 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Numerical Analysis of the Moving Formwork Bracket Stress during Construction

More information