Wearing planks, untreated timber plank running strips. Structural planks, creosote treated timber planks placed longitudinally.

Similar documents
~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

BRIDGES ARE relatively expensive but often are

Safe & Sound Bridge Terminology

US 51 Ohio River Bridge Engineering and Environmental Study

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

Report on Sanctuary/Chancel Crawl Space Inspection. St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove. Project No.

Informational Workshop Public Meeting Kanawha Falls Bridge Project

REHABILITATION PACKAGE 1-a

How To Check For Scour At A Bridge

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

Page & Turnbull imagining change in historic environments through design, research, and technology

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

Alberta Transportation Bridge Inspection & Maintenance System (Web 2005) Bridge. Bridge Inspection. Assistant Name Assistant Class

Failing Coastal Wood Infrastructure on the Great Lakes

Chapter 3 Pre-Installation, Foundations and Piers

EAST LYME HIGH SCHOOL

2015 ODOT Bridge Design Conference May 12, DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

CITY OF TRAIL MEMORANDUM

Building Condition Assessment: North Howard Street Baltimore, Maryland

The unit costs are based on the trend line of the 3 low bids for the average quantity.

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Open House Public Meeting for the Thurmond Bridge Rehabilitation Project State Project: State Project S310-25/ Federal Project: BR-0252(001)D

Structural Failures Cost Lives and Time

OVERVIEW OF TMH19: DRAFT STANDARD FOR THE VISUAL ASSESSMENT OF ROAD STRUCTURES

SECTION 3 ONM & J STRUCTURAL ANALYSIS

1,045 m length of the Deh Cho Bridge

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges

FORM DESIGN. easy to work with, and generally available.

6 RETROFITTING POST & PIER HOUSES

Residential Deck Safety, Construction, and Repair

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

Overhang Bracket Loading. Deck Issues: Design Perspective

Architectural Inspection Site Structures

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

Evaluation and Field Load Testing of Timber Railroad Bridge

3.1 Historical Considerations

Ross River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

Mark Cramer Inspection Services, Inc.

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Report to INFRASTRUCTURE SERVICES Committee for noting

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

Handling, Erection and Bracing of Wood Trusses

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS

Quality Control and Quality Assurance Guide

Historic Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301)

March 19, Ms. Jean McDonald CAP Management th Street, Suite 1010 Denver, Colorado 80202

PONTIS BRIDGE INSPECTION FIELD MANUAL FOR OKLAHOMA BRIDGES OKLAHOMA DEPARTMENT OF TRANSPORTATION BRIDGE DIVISION

COMMONLY USED RESIDENTIAL BUILDING CODES

Residential Foundations and Basements

Residential Decks. Planning and Development Services Department

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

Basic Requirements for Residential Plan Review _

Emergency Spillways (Sediment basins)

Building Condition Assessment: West Lexington Street Baltimore, Maryland

Building Construction. Lightweight construction. Conventional Construction

EPR Exempt Flood Risk Activities: descriptions and conditions

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

Unit Price Averages Reports

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA

INSTALLATION. General. Important Note. Design. Transport

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

(1) Minami Nagamachi and Naka Nagamachi viaducts between Shiraishi Zao and Sendai Stations on the Tohoku Shinkansen line

WSDOT Bridge Elements

Commercial Roof Inspection Form

Bridge Rehabilitation Alternatives

Public Information & Public Scoping Meeting

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

DESCRIPTION OF WORK:

Fifteen years experience of design, production and assembling of prestressed Bridge decks in Timber

Bridge Type Selection

How To Write An Analysis System For Bridge Test

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

What is Seismic Retrofitting?

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

Chaudière Crossing Bridge Rehabilitation

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA

Emergency repair of Bridge B421

A0 SHEET 1 OF LOCUST STREET FRANKFORT, KANSAS FRANKFORT, KANSAS ROOF REPAIR OF THE 400 LOCUST STREET

STANDARD OPEN PATIO COVER

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

City of Shelbyville Site Inspection Checklist

Section A Roof Truss

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

CHAPTER 4 FIELD INSPECTION, DATA COLLECTING, REPORT WRITING AND REPORT REVIEW

Superform Products Ltd.

Post and Beam Construction

Virginia Approach Spans

J. David Rogers Natural Hazards Mitigation Center University of Missouri-Rolla

BROWNSVILLE STRUCTURES STUDY. July Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania

INDIANA DEPARTMENT OF TRANSPORTATION BRIDGE INSPECTION PROGRAM CODING GUIDE

Transcription:

BRIDGE INSPECTION BRIDGE NO./NAME 62 039: Cariboo River FSR (0.75 KM) Inspection Date: September 10 th 2012 Inspected By: D. Chen, J. Rupar Gilliatt Year Built: 1976 Number of Spans: 3 Span Lengths: Superstructure Type: Span 1 15,900 mm Span 2 31,400 mm Span 3 31,100 mm Simply supported Acrow 300 Series Panel Bridge: Span 1: 3 double single non reinforced panels 2 triple single non reinforced panels Span 2: 10 triple single reinforced panels Span 3: 10 triple single reinforced panels The deck ties are supported by longitudinal stringers which bear on transverse transoms that are bolted to the bottom chord of the Acrow panels. Deck: Deck Structural: Curb: Substructure: Wearing planks, untreated timber plank running strips. Structural planks, creosote treated timber planks placed longitudinally. Creosote treated transverse timber ties. Timber curbs and risers. Abutments: Steel I girder cap beam bearing on steel pipe piles. Creosote treated timber breast wall and wing walls supported by steel pipe soldier piles. Piers: Creosote treated timber piers. Each pier comprises timber corbels on top of two timber caps, each cap is supported by 6 timber piles. The two sets of piles are connected by log cross bracing and are protected by timber sheathing planks and a dolphin pile at the upstream end. P:\20112891\01_2012_Proxy_Insp\Engineering\12.00_Inspections\Updated Summary Report\62-039.doc

BRIDGE INSPECTION GENERAL BRIDGE CONDITION: Superstructure Condition: Substructure Condition: Deck Condition: Load Posting: Date for the Next Close Proximity Inspection: No sign noted. 2013 Projected Replacement Date: 2017 BRIDGE INSPECTION SUMMARY/ RECOMMENDATIONS: Although the bridge appears to be in fair condition, we observed signs (e.g. loose panel pins) that suggest that the Acrow Panel superstructure is nearing the end of its service life. Since Acrow Panel Bridges typically have a service life of approximately 25 years and are intended to be used as temporary bridges, we recommend that the Ministry replace the bridge (including substructure) within the next 5 years. As an interim measure, we recommend annual close proximity inspections if the bridge is part of an active haul route. INSPECTION NOTES: Approaches: The approaches are generally in good condition. Bridge ahead signs are missing from both approaches. Loose gravel was noted on the approaches. The concrete approach barriers are slightly misaligned. Debris is accumulating against the concrete barriers. Minor vegetation overgrowth adjacent to the approaches. Delineators are present at all 4 corners. The Wells end delineators are slightly loose and the Likely end upstream delineator is damaged. Deck: The deck is generally in fair condition. The majority of curb rail sections are loose. Insect decay noted in a number of sections. Longitudinal checks in the curb rail with pockets of rot. A few risers have rub damage; some are broken. Minor wear in the running planks. Longitudinal checks and a number of pockets of rot noted in the running planks. Coring identified rot in the bottom half of the structural planks, with the initial signs of rot noted at interface between the structural planks and the ties. Debris accumulation on bridge deck. P:\20112891\01_2012_Proxy_Insp\Engineering\12.00_Inspections\Updated Summary Report\62-039.doc

BRIDGE INSPECTION Abutments: The abutments are generally in good condition. Debris accumulation on the cap beams at both abutments. Minor mill scale on the cap beams. The ballast walls at both abutments are sound. Minor erosion at the base of the Wells end abutment. The wing walls at both abutments are sound. The Wells end upstream wing wall has a saturated plank with the initial signs of rot. Deterioration does not affect the integrity or performance of the wall. Observed displaced lock blocks at base of Likely abutment. Embankment appears stable. The embankments are protected by log breakwaters. Piers: Pier 1 Pier 1 is generally in fair condition. Debris accumulating on the bearing plates. Debris accumulating on the cap beam. Wide vertical end splits at the downstream end of both the Likely and Wells end caps; no rot was found. Pier tie back cables sagging. The piles are sound; a 6 mm wide check was noted at the top of the Wells end Pile 5. Coring of the top of Piles 1 and 5 at the Wells end identified no rot. Coring of the top of Piles 1 and 5 at the Likely end identified no rot. Sway bracing dead man piles at the Likely abutment are collecting water. A 1500 mm section of heartwood rot noted in the top of the dolphin pile. The upstream log bracing has heartwood rot, 60 mm of shell remains. We do not believe this significantly affects the capacity of the bridge. A log breakwater extends from the embankment to the upstream end of the pier, to prevent debris collecting between pier and abutment. Pier 2 Pier 2 is generally in fair condition. Debris accumulating on the bearing plates. Debris accumulating on the cap beam. Wide vertical end splits were noted at the downstream end of both the Likely and Wells end caps. Moss growth along the mid check on top of the downstream end timber corbel, no rot noted. Likely End Cap Beam: Coring identified rot localized to the downstream end split, with 100 mm of shell. No rot was found below the spilt. The rot is in the end of the cap with no signs of crushing noted; hence we do not believe it significantly affects the capacity of the cap. Cored between Piles 2 and 3, no rot was found. Wells End Cap Beam: Coring the downstream end split identified no rot. Coring the cap beam between Piles 1 and 2, identified saturated wood with initial signs of rot near centre of the cap. The decay is not in the bearing area of the cap; hence we believe it does not significantly affect the capacity of the cap. Tie back cables are sagging. P:\20112891\01_2012_Proxy_Insp\Engineering\12.00_Inspections\Updated Summary Report\62-039.doc

BRIDGE INSPECTION The piles are sound. Coring the top of Pile 1 at the Wells end identified no rot. Coring the top of Pile 5 and at the mid height of Pile 3 at the Likely end, identified no rot. Two broken dolphin piles were noted. The upstream sheathing planks are broken. A log jam was noted at the upstream end of the pier. Girders: Typical Condition: Localized loss of paint and minor surface corrosion on all members, no measurable section loss. Localized damage on corners of a number of truss elements. A few bolts connecting the transom to the bottom chord of the panels are missing. We do not believe this affects the capacity of the bridge. A number of panel pins along the centre panels are missing safety clips; some pins are displaced and are held in place by adjacent pins. First and last bays between transoms in each span have two X shaped lateral braces. Remaining bays have chevron shaped lateral bracing. Span 1: Span 2: 4 small isolated cracks noted on the top bracing frame elements of the upstream and downstream panels; minor impact damage to interior end post at Wells end upstream corner. The minor defects noted should not have significant effect on the capacity of the bridge. 3 bottom chord reinforcing connection bolts missing in downstream panel 9. We do not believe this significantly affects the capacity of the bridge. Span 3: A minor isolated crack was noted on the end bracing frame of the upstream end panel above Pier 2. Minor mechanical damage to bottom chord reinforcing in upstream panel 9. Impact damage to end post at Likely end downstream corner. The minor defects noted should not have significant effect on the capacity of the bridge. P:\20112891\01_2012_Proxy_Insp\Engineering\12.00_Inspections\Updated Summary Report\62-039.doc

BRIDGE INSPECTION LIST OF MAINTENANCE ITEMS TO BE COMPLETED: Items Description Priority 1. Replace curb rail. High 2. Reinstall displaced panel pins and install missing safety clips as required. Medium 3. Replace missing panel reinforcing connection bolts in span 2 panel 9. Medium 4. Install missing transom bolts. Medium 5. Replace damaged sheathing planks on pier 2 Medium 6. Replace running planks as required. Medium 7. Install bridge ahead signs at both approaches. Medium 8. Schedule the structural planks and ties for replacement. Medium 9. Remove road spill from deck. Low 10. Brush approaches. Low MONITOR DURING FUTURE INSPECTIONS: Monitor the decay of the cap beams at both piers. Prepared by: Reviewed by: Jamie Rupar Gilliatt M.Eng., EIT. Project Engineer David Chen, P.Eng. Project Manager Attached: 1. CBR Report 2. Annotated Photo Sheets P:\20112891\01_2012_Proxy_Insp\Engineering\12.00_Inspections\Updated Summary Report\62-039.doc

BRIDGE INSPECTION NOTES: Directional & Numbering Conventions Used: Girders and piles are numbered from upstream to downstream. Left end or right end is determined facing downstream (except for delineators). Spans and piers are numbered from the left end when facing downstream. Projected Replacement Date: The projected date for the bridge replacement is based on the remaining service life of the bridge. We estimate the remaining service life as the greater of: For Glulam Girder Bridges: 1. Original design life, typically 50 years. 2. If a bridge is nearing the end of its estimated service life but is still in fair condition, we recommend that the Ministry assume a remaining service life of five years. For Steel and Concrete Bridges: 1. Original design life, typically 60 years. 2. If a bridge is nearing the end of its estimated service life but is still in fair condition, we recommend that the Ministry assume a remaining service life of ten years. Condition Ratings: Excellent: : : Poor: New or almost new condition and properly installed Structurally sound, in good repair with minimal wear Structurally functional, shows moderate wear or preliminary indications of deterioration Structurally unsound, items typically in need of repair or replacement Maintenance Priority (Typical Usage): High: Critical items that need to be addressed to protect safety of users (curbs, structural decks, delineators, major structural repairs, etc.); schedule work immediately. Medium: Items that maintain the service life of the bridge (wearing planks, deck joints, etc.) Low: Items that will extend the service life of the structure or general maintenance. Cost Estimate: The cost estimate for individual maintenance items, shown in the CBR report, reflects the cost of materials and labour for completing a task; it does not include any costs associated with mobilization, demobilization, engineering or contract administration. P:\20112891\01_2012_Proxy_Insp\Engineering\12.00_Inspections\Updated Summary Report\62-039.doc

BC Ministry of Forests and Range Permanent Bridge Inspection Report Page 1 of 5 Date Printed: 2013/03/27 User Id: BCEID\WRILEY1 Database: PROD Report Id: CBR001A Structure #: 62-039 Site #: 62-039 Road Name: CARIBOO RIVER Inspection Date: 2012/09/10 KM: Project File ID #: 0.75 User km: 0.00 Crossing Name: Cariboo R Next Inspection Date: 2014/09/03 6142 Br. 01 Forest District: Central Cariboo Forest District Deck Type: Timber - Untreated Running Surface: Timber Planks Superstructure Steel Truss/Bailey/Acrow Abutments (Left/Right): Pile -Permanent Materials Total Length (metres): 78.4 # Spans: 3 Span Length(s) (metres): 15.9, 31.4, 31.1 UTM Zone: Inspector Name: 10 UTM Easting: 605087 UTM Northing: 5842026 D. Chen, J. Rupar Year Built: 1976 Access: ABUTMENTS Bearings Bracing Ballast Wall Corrosion Protection Caps or Sills Fill Piles or Posts Riprap Wing Wall APPROACHES Alignment Bridge Ahead Signs Missing Brushing Required Delineator Missing Left Delineator Missing Right Fender Condition Road Surface DECK Span 1 2 Yes 0 0 The ballast walls at both abutments are sound. Minor erosion at the base of the Wells end abutment. Minor mill scale on the cap beams. Debris accumulation on the cap beams at both abutments. Observed displaced lock blocks at base of Likely abutment. Embankment appears stable. Steel pipe piles. The embankments are protected by log breakwaters. The wing walls at both abutments are sound. The Wells end upstream wing wall has a saturated plank with the initial signs of rot. Deterioration does not affect the integrity or performance of the wall. Minor vegetation overgrowth adjacent to the approaches. Likely end: narrow delineator, split. Wells end: narrow delineator slightly loose. Likely end: narrow delineator. Wells end: narrow delineator slightly loose. The concrete approach barriers are slightly misaligned. Debris is accumulating against the concrete barriers. Loose gravel was noted on the approaches. Corporate Bridge Register (CBR)

BC Ministry of Forests and Range Permanent Bridge Inspection Report Page 2 of 5 Date Printed: 2013/03/27 User Id: BCEID\WRILEY1 Database: PROD Report Id: CBR001A Structure #: 62-039 Site #: 62-039 Road Name: CARIBOO RIVER Inspection Date: 2012/09/10 Curb Rail/Blocks/Posts Deck to Girder Bolts Hand Rails/Walkouts Nails Overall Deck Condition Running Planks Sub Deck Ties Span 2 Curb Rail/Blocks/Posts Deck to Girder Bolts Hand Rails/Walkouts Nails Overall Deck Condition Running Planks Sub Deck Ties Span 3 Curb Rail/Blocks/Posts Deck to Girder Bolts Hand Rails/Walkouts Nails Overall Deck Condition Running Planks Sub Deck Poor Poor Poor The majority of curb rail sections are loose. Insect decay noted in a number of sections. Longitudinal checks in the curb rail with pockets of rot. A few risers have rub damage; some are broken. Debris accumulation on bridge deck. Minor wear in the running planks. Longitudinal checks and a number of pockets of rot noted in the running planks. Coring identified rot in the bottom half of the structural planks, with the initial signs of rot noted at interface with the ties. Coring identified the initial signs of rot at interface with structural plank. The majority of curb rail sections are loose. Insect decay noted in a number of sections. Longitudinal checks in the curb rail with pockets of rot. A few risers have rub damage; some are broken. Debris accumulation on bridge deck. Minor wear in the running planks. Longitudinal checks and a number of pockets of rot noted in the running planks. Coring identified rot in the bottom half of the structural planks, with the initial signs of rot noted at interface with the ties. Coring identified the initial signs of rot at interface with structural plank. The majority of curb rail sections are loose. Insect decay noted in a number of sections. Longitudinal checks in the curb rail with pockets of rot. A few risers have rub damage; some are broken. Debris accumulation on bridge deck. Minor wear in the running planks. Longitudinal checks and a number of pockets of rot noted in the running planks. Coring identified rot in the bottom half of the structural planks, with the initial signs of rot noted at interface with the ties. Corporate Bridge Register (CBR)

BC Ministry of Forests and Range Permanent Bridge Inspection Report Page 3 of 5 Date Printed: 2013/03/27 User Id: BCEID\WRILEY1 Database: PROD Report Id: CBR001A Structure #: 62-039 Site #: 62-039 Road Name: CARIBOO RIVER Inspection Date: 2012/09/10 Ties PIERS Pier 1 Bearings Bracing or Sheathing Caps Cribs Dolphins Overall Piles or Posts Riprap Wall Pier 2 Bearings Bracing or Sheathing Caps Cribs Dolphins Overall Piles or Posts Riprap Wall SUPERSTRUCTURE Span 1 Bracing Girders Coring identified the initial signs of rot at interface with structural plank. Debris accumulating on the bearing plates. Bracing: fair, upstream log bracing has heartwood rot, 60 mm of shell remains. Sheathing: good. Longitudinal cable sway braces are sagging. See additional note for more details A 1500 mm section of heartwood rot was noted in the top of the dolphin pile. See additional notes for more details. Pier tie back dead man piles at the Likely abutment are collecting water. A log breakwater extends from the embankment to the upstream end of the pier. Debris accumulating on the bearing plates. Bracing: good. Sheathing: poor, upstream sheathing planks broken. Tie back cables are sagging. See additional notes for more details. A log jam was noted at the upstream end of the pier. Two broken dolphin piles were noted. See additional notes for more details. First and last bays between transoms have two X shaped lateral braces. Remaining bays have chevron shaped lateral bracing. 4 small isolated cracks noted on the top bracing frame elements of the upstream and downstream panels; minor impact damage to interior end post at Wells end upstream corner. The minor defect noted should not have significant effect on the capacity of the bridge. Localized loss of paint and minor surface corrosion on all members, no measurable section loss. Localized damage on corners of a number of truss elements. A few bolts connecting the transom to the bottom chord of the panels are missing. We do not believe this affects the capacity of the bridge. Corporate Bridge Register (CBR)

BC Ministry of Forests and Range Permanent Bridge Inspection Report Page 4 of 5 Date Printed: 2013/03/27 User Id: BCEID\WRILEY1 Database: PROD Report Id: CBR001A Structure #: 62-039 Site #: 62-039 Road Name: CARIBOO RIVER Inspection Date: 2012/09/10 Under Trussing Span 2 Bracing A number of panel pins along the centre panels are missing safety clips; some pins are displaced and are held in place by adjacent pins. First and last bays between transoms have two X shaped lateral braces. Remaining bays have chevron shaped lateral bracing. Girders 3 bottom chord reinforcing connection bolts missing in downstream panel 9. Localized loss of paint and minor surface corrosion on all members, no measurable section loss. Localized damage on corners of a number of truss elements. A few bolts connecting the transom to the bottom chord of the panels are missing. We do not believe this significantly affects the capacity of the bridge. Under Trussing Span 3 Bracing Girders Under Trussing A number of panel pins along the centre panels are missing safety clips; some pins are displaced and are held in place by adjacent pins. First and last bays between transoms have two X shaped lateral braces. Remaining bays have chevron shaped lateral bracing. A minor isolated crack was noted on the end bracing frame of the upstream end panel above Pier 2. Minor mechanical damage to bottom chord reinforcing in upstream panel 9. Impact damage to end post at Likely end downstream corner. The minor defect noted should not have significant effect on the capacity of the bridge. Localised loss of paint and minor surface corrosion on all members, no measurable section loss. Localized damage on corners of a number of truss elements. A few bolts connecting the transom to the bottom chord of the panels are missing. We do not believe this affects the capacity of the bridge. A number of panel pins along the centre panels are missing safety clips; some pins are displaced and are held in place by adjacent pins. CHANNEL Estimated Present Water Level Depth: Estimated High Water Level Clearance: 1.5 Estimated Present Water Level Width: 56.0 5.0 HAZARDS High Water: Comment: No Scour: No Ice: No Debris: No Aggradation: No Corporate Bridge Register (CBR)

BC Ministry of Forests and Range Permanent Bridge Inspection Report Page 5 of 5 Date Printed: 2013/03/27 User Id: BCEID\WRILEY1 Database: PROD Report Id: CBR001A Structure #: 62-039 Site #: 62-039 Road Name: CARIBOO RIVER Inspection Date: 2012/09/10 REPAIRS # Status Priority Estimate Description 1 Recommended High $9,500.00 Replace curb rail. 2 Recommended Medium $0.00 Reinstall displaced panel pins and install missing safety clips as required. Associated cost is unknown. 3 Recommended Medium $350.00 Replace missing panel reinforcing connection bolts in span 2 panel 9. 4 Recommended Medium $1,300.00 Install missing transom bolts. 5 Recommended Medium $1,600.00 Replace damaged sheathing planks on pier 2. 6 Recommended Medium $2,200.00 Replace running planks as required. 7 Recommended Medium $1,000.00 Install bridge ahead signs at both approaches. 8 Recommended Medium $28,000.00 Schedule the structural planks and ties for replacement. 9 Recommended Low $300.00 Debris accumulation from deck. 10 Recommended Low $600.00 Brush approaches. MONITORS # Description 1 Monitor the decay of the cap beams at both piers. Professional Inspection Required? No Regional Review Date: P. Eng Reviewer Name: GENERAL Replacement Date for full log haul traffic (year): 2017 Replacement Date for light vehicle traffic (year): 2017 Current Load Rating GVW (tonnes): 91 Design Load GVW (tonnes): 91 Design Vehicle Config.: L100 Inspector's Estimated Full Log Haul Replacement (year): 2017 Inspector's Comment: Although the bridge appears to be in fair condition, we observed signs (e.g. loose panel pins) that suggest that the Acrow Panel superstructure is nearing the end of its service life. Since Acrow Panel Bridges typically have a service life of approximately 25 years and are intended to be used as temporary bridges, we recommend that the Ministry replace the bridge (including substructure) within the next 5 years. As an interim measure, we recommend annual close proximity inspections if the bridge is part of an active haul route. PEng Reviewer's Comment: District Staff Comment: Corporate Bridge Register (CBR)

BRIDGE INSPECTION REPORT BRIDGE INSPECTION PHOTOS Structure # Crossing Name Forest Service Road 62-039 Cariboo River Cariboo River User km CBR km 0.0 0.8 Figure 1-1: Upstream elevation. Figure 1-2: Downstream elevation. Figure 1-3: Looking towards Likely end. Figure 1-4: Looking towards Wells end. Figure 1-5: Looking upstream. Figure 1-6: Looking downstream. 62-039_Photos.xls Page 1 of 5

BRIDGE INSPECTION REPORT BRIDGE INSPECTION PHOTOS Structure # Crossing Name Forest Service Road 62-039 Cariboo River Cariboo River User km CBR km 0.0 0.8 Figure 1-7: Likely end abutment deck end. Figure 1-8: Wells end abutment deck end. Figure 1-9: Pocket of rot on curb rail, upstream shown. Figure 1-10: Typical deck condition. Figure 1-11: Pocket of rot in running strip. Figure 1-12: Typical panel condition, span 3 downstream shown. 62-039_Photos.xls Page 2 of 5

BRIDGE INSPECTION REPORT BRIDGE INSPECTION PHOTOS Structure # Crossing Name Forest Service Road 62-039 Cariboo River Cariboo River User km CBR km 0.0 0.8 Figure 1-13: Typical impact damage to bracing frame. Figure 1-14: Typical crack in span 1 bracing frame, upstream panel 4 shown. Figure 1-15: Typical impact damage to end post, Wells end upstream shown. Figure 1-16: Typical missing transom bolts, span 3 panel 1 shown. Figure 1-17: Typical missing reinforcing connection bolt in span 2 downstream panel 9. Figure 1-18: Typical peeling paint and minor surface corrosion of panel. 62-039_Photos.xls Page 3 of 5

BRIDGE INSPECTION REPORT BRIDGE INSPECTION PHOTOS Structure # Crossing Name Forest Service Road 62-039 Cariboo River Cariboo River User km CBR km 0.0 0.8 Figure 1-19: Minor damage to bottom chord reinforcing in span 3 panel 9 upstream. Figure 1-20: Typical protruding panel pin due to missing safety clip. Figure 1-21: Span 3 pier 2 upstream panel, crack in end post. Figure 1-22: Likely end abutment, note over turned lock blocks. Figure 1-23: Typical abutment bearing condition debris accumulation Likely end upstream shown. Figure 1-24: Pier 2 Likely end dead man piles, full of water. 62-039_Photos.xls Page 4 of 5

BRIDGE INSPECTION REPORT BRIDGE INSPECTION PHOTOS Structure # Crossing Name Forest Service Road 62-039 Cariboo River Cariboo River User km CBR km 0.0 0.8 Figure 1-25: Pier 1 Likely face. Figure 1-26: Pier 1 dolphin pile, heartwood rot. Figure 1-27: Typical loose cable sway brace, Pier 1 downstream shown. Figure 1-28: Pier 2 Wells end face, log jam and missing sheathing panels. Figure 1-29: Typical pier bearing condition, Pier 2 downstream shown, note debris accumulation. Figure 1-30: Typical end check in cap, Pier 2 likely end downstream shown. 62-039_Photos.xls Page 5 of 5