Report to INFRASTRUCTURE SERVICES Committee for noting

Size: px
Start display at page:

Download "Report to INFRASTRUCTURE SERVICES Committee for noting"

Transcription

1 Subject: Prepared by: Capital Works Programme 2015/16 Tairāwhiti Roads Alexios Kavallaris (Capital Manager - Tairāwhiti Roads) Meeting Date: 22 October 2015 Report to INFRASTRUCTURE SERVICES Committee for noting SUMMARY The purpose of this report is to inform the Committee of three resilience projects (1-3) and three heavy productive motor vehicle bridge strengthening projects (4-6): 1) Anaura Bay Road (Nuhiti) rock revetment 2) Southern Seawall Repair, Beach Road, Tokomaru Bay 3) Mata Road Realignment R.P ) Horoeka and Te Pahi bridges deck strengthening 5) Gaddum s bridge strengthening 6) Mata (Huiarua) bridge deck replacement A Powerpoint presentation of the projects will be provided at the meeting. RECOMMENDATIONS That the Committee 1. receives the report. Alexios Kavallaris Capital Manager Tairāwhiti Roads Barry Vryenhoek Operations Group Manager Keywords: Tairāwhiti Roads, land transport, capital projects A Page 1 of 6

2 1. BACKGROUND Six capital projects have been approved for funding in the financial year. are: These 1.1 Anaura Bay Road (Nuhiti) Rock Revetment The works are to partially construct two rock revetments with buttress fill behind whilst beginning earthworks for a future road realignment of approximately 220m length of the Anaura Bay Road. This was a high priority as it was a commitment to the residents and landowners affected by consistent road closures. The seaward slope is being undermined by erosion from the action of the sea, which has resulted in the regression of the slope and a reduced road formation width. The damage is a result of a combination of factors including tides, current and wave action from the ocean as well as the mobilisation of the slip upslope of the road. The future road realignment is intended to cut the road further inland into more stable material and take weight off the top of the slope. The revetments to be constructed on the seaward side of the buttress fill are intended to reinforce the toe of the slope. This is expected to protect the toe from further erosion and help stabilise the existing slips. The future placement of topsoil, grass seeding and planting of the slopes below the new road will provide additional stability. Works include clearing the site of vegetation, stripping of topsoil, excavation of loose slip material at the toe and on the face of the seaward slope, some excavation for the construction of the new road with the excavated material being placed as buttress fill on the beach against the seaward slope and the partial construction of the rock revetments. The works are for Stage 1 of the four stage construction sequence. This stage is for the construction of approximately one quarter of the rock revetments and a portion of the earthworks relating to cutting in the road realignment along with buttress fill behind the rock revetments. Fill for the buttress is to be gained from the road cutting. Estimated Total Cost for Stage 1: $250,000 Preliminary design drawings completed Community consultation in progress Resource consent in progress Archaeological report in progress Mangatuna quarry consenting yet to begin Detailed design and contract documentation currently in progress Will proceed to construction open tendering by February 2015 Anticipated construction period for Stage 1 is 3-4 months A Page 2 of 6

3 Current status Community consultation in progress Resource consent in progress 1.2 Mata Road Realignment R.P This section of road has been slumping/subsiding for many years. Additional to this there is a large volume of heavy traffic and poor road width and visibility. There have been many requests from the public, local councillors, landowners and road users to improve this section of road. Currently the road can be restricted to one way only. Road users are unable to see oncoming traffic and the use of radio to communicate is the only way to negotiate this section of road safely. Not everyone has a radio. Option 1 - Carry out road alignment which would benefit the visibility of the road. Option 2 - Stay with the existing road alignment and widen the roadway, carry out sight benching and remove vegetation to improve sight visibility. With both options there will still be ongoing issues with the stability of this site. A neighbouring landowner has agreed to Council gaining access and utilising his land to enable improvement works. Estimated Total Cost: $250,000 Investigation phase in order to produce an options report and agree on the engineer s preferred option. Apply for resource consent with Council and progress consultation with stakeholder for the option that needs land acquisition. Preliminary and detailed design. Contract documentation and tender process. Progressing with investigation to produce options report due by 21 November Southern Seawall Repair, Beach Road, Tokomaru Bay The concrete seawall alongside Beach Road, Tokomaru Bay, has been damaged. There is a large hole in the wall that is causing backfill to be lost from behind the wall. This has been covered by a steel plate as a temporary measure but a more permanent solution is required. The scope of the permanent work is to remove the temporary plate and repair the concrete wall. This includes: Dewatering and protecting the repair area from the ocean. Removing the temporary plate and fixings. Excavating the material from in front of the wall down to bedrock. Removing all loose material from the damaged area and preparing the exposed concrete and reinforcement. Drilling and epoxying MateenBar reinforcing into the walls and base of the damaged area. A Page 3 of 6

4 Inserting and grouting seepage pipes. Placing concrete repair material. Placing rock rip-rap against the toe of the new repair. The scope of the permanent work is to repair this erosion. This includes: Dewatering and protecting the repair area from the ocean. Excavating the material from in front of the wall down to bedrock. Removing all loose material from the area and preparing the exposed concrete and reinforcement. Cutting the bedrock foundation to the correct profile. Drilling and epoxying MateenBar reinforcing into the existing concrete. Placing the concrete repair material. Backfilling behind the existing seawall. Placing rock rip-rap against the toe of the new repair. Estimated Total Cost: $300,000 Project will be staged as $150,000 is only available this financial year. Investigation of both buttress and seawall repair done. Detailed design and contract documentation completed by December Construction period from February to April Resources consent to be finalised once final design completed. 1.4 Horoeka and Te Pahi Bridges Deck Strengthening To carry out an assessment of two bridges on Waimata Road: Horoeka Bridge at RP 9.85 and Te Pahi Bridge at RP Both bridges previously assessed in 2006 giving >100% Class 1 (>44t gross weight). Reassessment of these bridges was considered necessary as new evaluation methods have since been introduced and also to determine their capacities to accommodate High Productivity Motor Vehicles loading. Estimated logging activities forecasting in tonnes is shown below: Accumulated volume Waimata Hokoroa 2016/ / / / / / /24 Tonnes 85, , , , , , ,000 1,327,496 Estimated Total Cost: $120,000 for both bridges A Page 4 of 6

5 Investigation assessment done. Benefit cost ratio, detailed design and construction drawings done. Construction estimate and contract documentation due by 16 October Open market tender by mid-november Construction estimate and contract documentation. 1.5 Gaddum s Bridge Strengthening Gaddum s Bridge is at 6678 Matawai Road and carries a single lane carriageway over the Motu River. The structure is a single span castellated steel bridge with timber deck founded on concrete abutments. The bridge is to be upgraded to allow tanker access. This involves strengthening the main girders primarily but also increasing support capacity to the central beam of the bridge. The timber deck will also be replaced with a new timber deck. Timber was deemed more appropriate than concrete as it will be lightweight and therefore will not put too much additional load onto the existing abutments. Scope of works includes: Access Traffic Management Demolition Steelwork Timberwork Barrier installation Corrosion protection Estimated Total Cost: $200,000 Investigation assessment done. Preliminary and detailed design done. Construction estimate and contract documentation done. Open market tender in progress, closing date for submission 23 October 2015 Open market tendering. 1.6 Mata (Huiarua) Bridge Deck Replacement The site of work is at the Mata (Huiarua) Bridge on Mata Road (Upper). This site is located 116km north of Gisborne, 35km west of Tokomaru Bay. Once the bridge is complete, Mata Road will be fully enabled for HPMV capability. A Page 5 of 6

6 This project involves replacing the existing deck on Mata (Huiarua) Bridge on all four spans in order to increase the carriageway width and improve the live load capacity to full HPMV. The work involves: Remove existing deck and guardrails. Shear stud installation. Precast concrete deck with in-situ infills. Joint installation. New galvanised steel protection barriers. Minor earthworks. Seismic steelwork retrofit. Paint beam top flange and seismic steelwork. Traffic management. Liaison with service authorities and local landowners. Estimated Total Cost: $500,000 Project was tendered in December Contract awarded on February Contract postponed allowing for Ernslaw One to reprogramme their operations due to potential bridge closure. Contract recommences on 26 October 2015 and estimated completion either before Xmas break or one week after Xmas holidays. Suspension period until 26 October A Page 6 of 6

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement. 2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project

More information

Unit Price Averages Reports

Unit Price Averages Reports Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation

More information

Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road)

Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Bruce Highway (Cooroy to Curra) Section A (Cooroy southern interchange to Sankeys Road) Industry Briefing - 13 February 2013 Bruce Highway Upgrade (Cooroy to Curra) The Bruce Highway Upgrade (Cooroy to

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

The unit costs are based on the trend line of the 3 low bids for the average quantity.

The unit costs are based on the trend line of the 3 low bids for the average quantity. Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally

More information

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the

More information

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard

More information

CITY OF TRAIL MEMORANDUM

CITY OF TRAIL MEMORANDUM 0 C CITY OF TRAIL MEMORANDUM DATE: TO: FROM: SUBJECT: March 24, 2011 FILE NO. 5400-02 DAVID PEREHJJDOFF, CHIEF ADM1NTSTRATIVE OFFICER WARREN PROULX, ENGINEERING TECHMCIAN OLD TRAIL BRIDGE With the interest

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

EAST AYRSHIRE COUNCIL. CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME

EAST AYRSHIRE COUNCIL. CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME EAST AYRSHIRE COUNCIL CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME Report by the Depute Chief Executive/Executive Director of Neighbourhood Services PURPOSE OF REPORT 1 The

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Informational Workshop Public Meeting Kanawha Falls Bridge Project Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

Chaudière Crossing Bridge Rehabilitation

Chaudière Crossing Bridge Rehabilitation Chaudière Crossing Bridge Rehabilitation Douglas K. Lowry P. Eng., Armtec Infrastructure Incorporated David Delicate, P.Eng. Public Works and Government Services Canada (Retired) Prepared for presentation

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

Session 3: Guardrail Design and Sitespecific. Considerations

Session 3: Guardrail Design and Sitespecific. Considerations FHWA Roadway Departure Technology Transfer Roadside Safety Systems Installer Training : Guardrail Design and Sitespecific Installation Considerations 3-1 Course Topics Session 2 Testing Requirements and

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

REHABILITATION PACKAGE 1-a

REHABILITATION PACKAGE 1-a 1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened

More information

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS Chapter 11 Slope Stabiliza bilization and Stability of Cuts and Fills THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS are 1) to create space for the road template and driving surface; 2) to balance material

More information

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009. Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing

More information

King Post Wall Information

King Post Wall Information King Post Wall Information DAWSON-WAM specialise in the installation of piled retaining wall systems including steel sheet piling, concrete piled walls and king post walls. This document is our guide to

More information

Evaluating the Condition of Seawalls/Bulkheads

Evaluating the Condition of Seawalls/Bulkheads Volume 2 Evaluating the Condition of Seawalls/Bulkheads By: Coastal Systems International, Inc. Typical bulkhead under construction Seawalls and bulkheads (walls) provide shoreline stabilization for many

More information

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project. The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

DESIGN GUIDELINES FOR EARTH RETENTION

DESIGN GUIDELINES FOR EARTH RETENTION DESIGN GUIDELINES FOR EARTH RETENTION Strata Systems, Inc. 380 Dahlonega Rd., Suite 200 Cumming, GA 30040 USA www.geogrid.com TABLE OF CONTENTS MECHANICS OF RETAINING WALLS... 3 THE STRATAWEB SOLUTION...4

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

Interim Advice Note 105/08 Implementation of Construction (Design and Management) 2007 And the withdrawal of SD 10/05 and SD 11/05

Interim Advice Note 105/08 Implementation of Construction (Design and Management) 2007 And the withdrawal of SD 10/05 and SD 11/05 Interim Advice Note 105/08 Implementation of Construction (Design and Management) 2007 And the withdrawal of SD 10/05 and SD 11/05 IAN 105/08 1 of 7 Jan 2008 1. Introduction The Construction (Design and

More information

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed. May 7,2015 KSANDER & ASSOCIATES CONSULTING PROFESSIONAL ENGINEERS 130 HUINTER STREET, UNIT 103, PETERBOROUGH, ONTARIO K9H2K8 TELEPHONE (705) 743-9221 FAX 743-0904 Ontario Region Conservation Authority

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

Alberta Transportation Bridge Inspection & Maintenance System (Web 2005) 00747-1 Bridge. Bridge Inspection. Assistant Name Assistant Class

Alberta Transportation Bridge Inspection & Maintenance System (Web 2005) 00747-1 Bridge. Bridge Inspection. Assistant Name Assistant Class Bridge File Number Year Built/Year Supstr 00747-1 Bridge 1964/1964 Bridge or Town Name SUNNYSLOPE Located Over Located On 582:04 C1 33.896 Water Body Cl./Year Navigabil. Cl./Year Legal Land Location KNEEHILLS

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

Rehabilitation of Locks on the Kentucky River

Rehabilitation of Locks on the Kentucky River Rehabilitation of Locks on the Kentucky River Joshua M. Repp, PE Bergmann Associates Presentation Overview River System History Evolution of Lock and Dams Structures Existing Condition of Structures Lock

More information

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee

More information

CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS

CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS Drew Monnier 1, P.Eng. (Presenting) Kimberly Yathon 2, B.Sc. CE (Presenting) Ruth Eden 1, M.Sc., P.Eng. Randy Fingas 1, P.Eng. Emile Shehata

More information

FINAL SECTION OF COASTAL PROTECTION RIVER DODDER PART 8 PROPOSALS London Bridge and New Bridge

FINAL SECTION OF COASTAL PROTECTION RIVER DODDER PART 8 PROPOSALS London Bridge and New Bridge FINAL SECTION OF COASTAL PROTECTION RIVER DODDER PART 8 PROPOSALS London Bridge and New Bridge Planning and Development Acts 2000-2006 Planning and Development Regulations 2001-2006, Part 8 March 2012

More information

A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES

A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES H. Turan DURGUNOGLU Ahmet SAHIN Onder AKCAKAL Zetas Zemin Teknolojisi A.S., TOKI-Housing Development Zetas Zemin Teknolojisi

More information

Virginia Approach Spans

Virginia Approach Spans Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel

More information

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE A.Rito Proponte, Lda, Lisbon, Portugal J. Appleton A2P Consult, Lda, Lisbon, Portugal ABSTRACT: The Figueira da Foz Bridge includes a 405 m long cable stayed

More information

SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN

SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN Introduction This Asset Management Plan (AMP) for Land Transport Network 2012 describes in detail how the District s land transport network will be managed

More information

US 51 Ohio River Bridge Engineering and Environmental Study

US 51 Ohio River Bridge Engineering and Environmental Study US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

How To Build A Luxury Apartment Complex In London

How To Build A Luxury Apartment Complex In London Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

OSU Extension FACT SHEET

OSU Extension FACT SHEET OHIO STATE UNIVERSITY EXTENSION! OSU Extension FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Shale Oil and Gas Development Fact Sheet Series A Landowner s Guide to Understanding

More information

Incident Management: Before and After Storm Events. Caroline Barford & Caroline Timlett Coastal Engineers

Incident Management: Before and After Storm Events. Caroline Barford & Caroline Timlett Coastal Engineers Incident Management: Before and After Storm Events Caroline Barford & Caroline Timlett Coastal Engineers Presentation Overview Overview of Area concerned Before & During Storm Events Coastal Flood Response

More information

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael

More information

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL Prepared for: Public Works and Government Services Canada Parliamentary Precinct Branch Prepared by: Halsall Associates 210 Gladstone

More information

Failing Coastal Wood Infrastructure on the Great Lakes

Failing Coastal Wood Infrastructure on the Great Lakes University of Wisconsin Sea Grant Institute Contact Gene Clark grclark@aqua.wisc.edu 715-392-3246 Failing Coastal Wood Infrastructure on the Great Lakes Gene Clark/UW Sea Grant Institute Introduction Many

More information

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION -SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION -Unit number- 4420798 -Unit title- CONSTRUCTION TECHNOLOGY 2: SUBSTRUCTURE AND REMEDIAL WORKS -Superclass category-

More information

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3279 SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP Yuming DING 1, Bruce HAMERSLEY 2 SUMMARY Vancouver

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

EPR Exempt Flood Risk Activities: descriptions and conditions

EPR Exempt Flood Risk Activities: descriptions and conditions EPR Exempt Flood Risk Activities: descriptions and conditions Version 1 April 2016 We are the Environment Agency. We protect and improve the environment. Acting to reduce the impacts of a changing climate

More information

VEHICLE CROSSOVER INFORMATION PACK

VEHICLE CROSSOVER INFORMATION PACK VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)

More information

Purpose of the Local Liaison Committee

Purpose of the Local Liaison Committee Agenda 1. Welcome, introductions and purpose of the Local Liaison Committee 2. Introduction to the scheme 3. Progress update 4. Elect a chair for future meetings 5. Agree agenda and terms of reference

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12 If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need

More information

Lodge Grass Creek Add-on Project Overview

Lodge Grass Creek Add-on Project Overview Crow Tribal Water Rights Settlement Act of 2010 Rehabilitation and Improvement of the Crow Irrigation Project 189 Heritage Road Crow Agency, MT 59022 1 Lodge Grass 1 Headworks Project Description: The

More information

What is Seismic Retrofitting?

What is Seismic Retrofitting? What is Seismic Retrofitting? SEISMIC RETROFITTING A Seismic Retrofit provides existing structures with more resistance to seismic activity due to earthquakes. In buildings, this process typically includes

More information

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.

More information

Trenching and Excavation Safety

Trenching and Excavation Safety 1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking

More information

OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007

OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007 OTTAWA CIVIC CENTRE & NORTH SIDE STANDS at LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007 for CITY OF OTTAWA REAL PROPERTY ASSET MANAGEMENT prepared by ADJELEIAN ALLEN RUBELI LIMITED

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL INSPECTION PROCEDURE 88001 LLUR ON-SITE CONSTRUCTION PROGRAM APPLICABILITY: 2600, 2801 88001-01 INSPECTION OBJECTIVES 01.01 To determine by direct observation if on-site construction

More information

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions Peyman Amini Motlagh, Ali Pak Abstract Seismic retrofitting of important structures is essential in seismological

More information

CSXT Emergency Response for May 2010 Flood Repairs

CSXT Emergency Response for May 2010 Flood Repairs CSXT Emergency Response for May 2010 Flood Repairs 11 th Annual Geohazards Forum Chattanooga, Tennessee Christopher Ramsey, PE AMEC Project Overview Record rainfalls affecting greater Nashville. Some areas

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

Report of the Head of Service of Highways, Capital Development and Waste

Report of the Head of Service of Highways, Capital Development and Waste HCW/14/48 Public Rights of Way Committee 19 June 2014 Public Rights of Way Storm Damage Update Report of the Head of Service of Highways, Capital Development and Waste Please note that the following recommendation

More information

Sample Drawing Package for One and Two Family Dwelling Applications

Sample Drawing Package for One and Two Family Dwelling Applications Sample Drawing Package for One and Two Family Dwelling Applications For a full list of submission requirements, refer to the relevant checklist for your application found on our website: http://vancouver.ca/home-property-development/application-forms-and-checklists.aspx

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

COPYRIGHT. Dincel Construction System Pty Ltd

COPYRIGHT. Dincel Construction System Pty Ltd BASEMENT CONSTRUCTION Dincel Construction System Pty Ltd 101 Quarry Road ERSKINE PARK NSW 2759 PO Box 104, ST CLAIR NSW 2759 Phone: (612) 9670 1633 Fax: (612) 9670 6744 Email: construction@dincel.com.au

More information

Murrays Bay Wharf Investigation and Repairs - Options Assessment

Murrays Bay Wharf Investigation and Repairs - Options Assessment Report Murrays Bay Wharf Investigation and Repairs - Options Assessment Prepared for Auckland Council (Client) By Beca Ltd (Beca) 20 September 2013 Beca 2013 (unless Beca has expressly agreed otherwise

More information

Chapter. Restoration of Damaged Structures

Chapter. Restoration of Damaged Structures 5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.

More information

COASTAL DAMAGE INSPECTION SOUTHWEST VITI LEVU, FIJI AFTER CYCLONE SINA

COASTAL DAMAGE INSPECTION SOUTHWEST VITI LEVU, FIJI AFTER CYCLONE SINA COASTAL DAMAGE INSPECTION SOUTHWEST VITI LEVU, FIJI AFTER CYCLONE SINA Brendan J. Holden SOPAC Technical Secretariat July 1992 SOPAC Technical Report 148 Prepared for: South Pacific Applied Geoscience

More information

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012 FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012 Building and Housing has published technical guidance for foundation repairs and reconstruction for residential properties in green zone Foundation Technical

More information

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE Proceedings of the International Symposium on Engineering Lessons Learned from the 2011 Great East Japan Earthquake, March 1-4, 2012, Tokyo, Japan REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE

More information

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS UPDATED: 01/31/14 SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS Q. 1. What are the County s plans for Seminole Pratt Whitney Road between SR 80 (Southern Blvd) and the Bee Line

More information

Definition of Tower from the Bradley County Zoning Resolution

Definition of Tower from the Bradley County Zoning Resolution Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio

More information

Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over

Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over ewer utility crossing pedestrian bridge Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over the river at

More information

Engineering Policy 146. Severe Weather Management Plans

Engineering Policy 146. Severe Weather Management Plans Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...

More information

PRESTRESSED CONCRETE FLOORING BEAMS

PRESTRESSED CONCRETE FLOORING BEAMS PRESTRESSED CONCRETE FLOORING BEAMS TRIED & TRUSTED Introduction Established in 2001 TT Concrete Products Limited has become a prominent manufacturer of prestressed concrete flooring beams throughout the

More information

I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015

I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015 I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General

More information

3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH

3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH 3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH General Manager responsible: General Manager, Strategy and Planning Group, DDI: 941-8281 Officer responsible: Author: PURPOSE OF REPORT Programme

More information

Elevated Roads for Sri Lanka

Elevated Roads for Sri Lanka Elevated Roads for Sri Lanka M.T.R. Jayasinghe (Senior Professor, Structural Engineering, University of Moratuwa) Senior Professor M.T.R. Jayasinghe is a Professor of Structural Engineering, University

More information

Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES

Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES 1.0 Background An unopened road allowance as defined by the Municipal Act is a public highway that has not been opened and assumed for

More information

Traffic Management Plan

Traffic Management Plan China Civil Engineering Construction Corporation The Rarotonga Water Ring Mains Upgrade Project (Te Mato Vai) of the Cook Islands Traffic Management Plan Compilation: Chinese Civil Engineering Corporation

More information

FDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES

FDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES NAICS CODE Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway (includes 300, 320, 327, 330, 334, 336, 337, 338) Application of prime and tack coats, leveling surfaces and

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

SUBSIDIARY LEGISLATION 424.06 BUILDING (SAFETY) REGULATIONS

SUBSIDIARY LEGISLATION 424.06 BUILDING (SAFETY) REGULATIONS BUILDING (SAFETY) [S.L.424.06 1 SUBSIDIARY LEGISLATION 424.06 BUILDING (SAFETY) REGULATIONS 4th March, 1969 LEGAL NOTICE 96 of 1968. 1. The title of these regulations is the Building (Safety) Regulations.

More information

CONSTRUCTION SEQUENCE & PROGRAMME

CONSTRUCTION SEQUENCE & PROGRAMME CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone

More information

COST AND MAINTENANCE OF LIVING SHORELINES

COST AND MAINTENANCE OF LIVING SHORELINES COST AND MAINTENANCE OF LIVING SHORELINES Photo: C. Verlinde, University of Florida Sea Grant Extension Debbie L. DeVore South Florida Coastal Program Coordinator What are Living Shorelines? Shoreline

More information