Building Condition Assessment: North Howard Street Baltimore, Maryland
|
|
|
- Cynthia Bond
- 10 years ago
- Views:
Transcription
1 KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc Seton Drive, Baltimore, MD Phone: ( ) Fax: (410) Building Condition Assessment: Baltimore, Maryland May 7, 2012
2 EXCUTIVE SUMMARY The roof is leaking throughout. Water is entering through missing and damaged windows. Exterior walls require repointing. Exterior walls are structurally sound. There is no danger of failure of structural elements, but minor structural repairs are required. Opinion of Cost: Immediate Repairs $500 Structural Stabilization Repairs: $3,500 Building Envelope Repairs: $47,400 Total: $51,400 Prepared by Kennedy, Porter and Associates, Inc. Page 1
3 STRUCTURE DESCRIPTION The building is approximately 55 x 50, with five stories over a basement. It was reportedly constructed circa The building s structure consists of brick masonry exterior walls and wood framed floors and roof supported by steel beams, girders and columns. The front of the building is covered with decorative spandrel panels. The premises are currently vacant; its most recent uses include offices and retail stores. We have reviewed available information provided to us by Baltimore City about the building. This information was limited to tax records, historic fire insurance maps and land eligibility reports provided by CHAP. INSPECTION OBSERVATIONS Building 109 North Howard Street was inspected by the joint venture of EBA Engineering, Inc. and Kennedy, Porter and Associates, Inc. on May 3, Our inspection was visual in nature, and was limited to accessible structural elements. Façades were inspected from grade using binoculars. Roofs were accessible and were included in our inspection program. No finishes were removed and no probes were made to determine structural conditions. Figures 1 and 2 show general exterior conditions and photograph locations. Additional field notes are attached as an appendix. The structure is in overall fair to good condition. Observed deficiencies are summarized as follows: Roof Appurtenances Roof Framing The roof is generally flat, and is covered with a membrane roofing system. There are many penetrations through the roof for mechanical equipment. Access to the roof could not be obtained at the time of inspection. The roofing membrane has generally failed throughout. Active leaks were noted in all ceilings below. A large area of water damage from leakage was observed along the east wall. Additional area of water damage was noted throughout the ceiling area (see Photo 1). At these locations, wood plank roof sheathing has been damaged and will require replacement. Wood roof rafters have minor deterioration. Floor Framing Water damage continues down to all floor framings. Wood plank sub-floor damage was noted in these areas. The timber joist in these areas exhibits minor deterioration. The steel members in the water damaged areas exhibit surface corrosion with no significant section Prepared by Kennedy, Porter and Associates, Inc. Page 2
4 Foundations loss. Many areas of the steel framing are concealed by finishes, but no signs of distress, such as settlement or cracking were noted in these finishes (see Photos 1-13). No signs of differential settlement, bowing or cracking were observed in the masonry foundation walls (see Photos 15 and 16). Interior Bearing Walls Interior support members consists of steel beams and columns that appear to have no signs of distress or differential settlement (see Photos 3, 4, 6, and 7). North Elevation The north elevation raises 2 stories above an adjacent building. The third story façade common brick is covered with concrete plaster that exhibits a wide vertical crack at mid span (see Photo 17). The fourth floor façade is exposed common brick and appears to be in fair condition. South Elevation The south elevation raises 1 story above the adjacent building and consists of common brick that appears to be in fair condition with displayed graffiti (see Photo 18). East Elevation The east elevation consists of common brick. The brick is in poor condition with deteriorating grout throughout the entire surface. There are wide diagonal and vertical cracks located at the northeast corner between the lintel and sill areas of the northernmost windows (see Photos 21-24). The crack noted in the exterior surface at the second floor level (see Photo 24) can be seen in the interior face beneath the window sill (see Photo 25). West Elevation The west façade consists of a first floor recessed store front entrance below two large three story bay windows framed with decorative spandrel panels. There is a loose panel at the fourth floor level below the south window frame (see Photo 14). There is a missing exterior lintel panel at the south end of the buildings store front above the roll-up security door (see Photo 19). Water has penetrated through a damaged window frame and panel at the second floor level (see Photo 20). All window and door sashes, lintels, frames, and sills exhibit moderate to severe paint failure. Recommendations: Our recommendations below refer to structural elements of the building only. These are based on conditions observed at the time of our inspection. Our Engineer s Opinion of Probable Cost included with the repair recommendations is schematic in nature, consistent with the level of detail provided in our general repair recommendations. Immediate Repairs Prepared by Kennedy, Porter and Associates, Inc. Page 3
5 These repairs are required to be performed immediately on an emergency basis in order to prevent an imminent collapse or because the noted conditions pose a safety risk to the general public. - Re-fasten loose metal spandrel panel at front facade $500 Structural Stabilization Repairs These should be scheduled as soon as possible. These recommendations require action to prevent accelerated deterioration of the structure, or in order to prevent the development of dangerous conditions in the future. - Replace deteriorated areas of roof sheathing (+/- 200 SF) $2,000 - Replace deteriorated areas of sub-floor (+/-150 SF) $1,500 Building Envelope Repairs These repairs should be performed in order to maintain the building s longevity and ensure its continued usability, in part or in whole. - Replace entire roofing system $30,000 - Repoint east façade $15,000 - Repair three damaged windows $2,400 Total $51,400 Prepared by Kennedy, Porter and Associates, Inc. Page 4
6 14 19 Figure 1: 109 North Howard Street West Elevation Prepared by Kennedy, Porter and Associates, Inc. Page 5
7 Figure 2: 109 North Howard Street East Elevation Prepared by Kennedy, Porter and Associates, Inc. Page 6
8 Photo 1: Water Damage in Fifth Floor at East Wall Photo 2: Typical Damage in Fourth Floor Ceiling (West Wall Shown) Prepared by Kennedy, Porter and Associates, Inc. Page 7
9 Photo 3: Typical Condition Fourth Floor Photo 4: Typical Condition in First Floor Prepared by Kennedy, Porter and Associates, Inc. Page 8
10 Photo 5: Typical Water Damage in Second Floor Ceiling at East Wall Photo 6: Typical Condition of Third Floor Prepared by Kennedy, Porter and Associates, Inc. Page 9
11 Photo 7: Typical Condition of First Floor Photo 8: Water Damage in First Floor Ceiling Area along East Wall Prepared by Kennedy, Porter and Associates, Inc. Page 10
12 Photo 9: Water Damage in First Floor Ceiling Area along East Wall Photo 10: Water Damage in First Floor Ceiling Area along North Wall Prepared by Kennedy, Porter and Associates, Inc. Page 11
13 Photo 11: Typical Water Damage at Basement Level Photo 12: Typical Water Damage in Basement Level Ceiling Prepared by Kennedy, Porter and Associates, Inc. Page 12
14 Photo 13: Typical Water Damage in Basement Level Ceiling Photo 14: Loose Metal Spandrel Panel on West Façade Prepared by Kennedy, Porter and Associates, Inc. Page 13
15 Photo 15: Typical Wall Condition in Basement Boiler Room Photo 16: Typical Wall Condition in Basement Boiler Room Prepared by Kennedy, Porter and Associates, Inc. Page 14
16 Photo 17: Plaster on North Elevation Wall above Adjacent Building Photo 18: South Elevation above Adjacent Building Prepared by Kennedy, Porter and Associates, Inc. Page 15
17 Photo 19: Missing Lintel Panel above Roll-Up Door on West Elevation Prepared by Kennedy, Porter and Associates, Inc. Page 16
18 Photo 20: Water Damage at West Wall Second Floor Location Prepared by Kennedy, Porter and Associates, Inc. Page 17
19 Photo 21: Crack in Brick Masonry at Roof Level (East Elevation) Photo 22: Crack in Brick Masonry at Fourth Floor Level (East Elevation) Prepared by Kennedy, Porter and Associates, Inc. Page 18
20 Photo 23: Crack in Brick Masonry at Second Floor Level (East Elevation) Photo 24: Crack in Brick Masonry at First Floor Level (East Elevation) Prepared by Kennedy, Porter and Associates, Inc. Page 19
21 Photo 25: Crack in Brick Masonry at Second Floor Level (Interior Face of East Elevation) Prepared by Kennedy, Porter and Associates, Inc. Page 20
Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA
STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael
201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
SECTION 3 ONM & J STRUCTURAL ANALYSIS
Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION
423 NORTH HOWARD ST. VISUAL STRUCTURAL ASSESSMENT
Urgent Needs II City of Baltimore No. 1099 423 NORTH HOWARD ST. 423 North Howard Street (circa 1880) is a multi-story building constructed second in row south of Franklin Street and between the vacant
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
Slavic Village Building Condition Review
Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities
14 September 2015. Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102
Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102 Project No.: 15538.00 Re: Structural Condition Review of the building at 700 4 th St. E. Dear Sarah: We
STRUCTURAL ASSESSMENT
STRUCTURAL ASSESSMENT Project: 1432-1434 East Commerce St. Job. No: 122200 Location: San Antonio, TX Date: Dec. 10, 2012 Weather: Sunny, Windy,60 deg Performed by: Jeff Haughton and Frank Lamas, Alpha
Structural Assessment Report
Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive
Engineers, Civil Structural Survey
Engineers, Civil Structural Survey 317 STREET 0 6 3 6 0 886-1966 886-9165 FAX. September 1 1 Mr. Alan Bergren City Manager City of Norwich Broadway, Floor Norwich, 06360 Re: Limited Structural Condition
Building Foundation and Structure
Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original
PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007
PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT November 2007 PURPOSE OF INVESTIGATION Determine possible locations of moisture intrusion into and through facade. Determine cause of horizontal and vertical
Page & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
Reference: BRM-00220488-A0 July 18 th, 2014. Cursory Visual Review of Various Below Grade Spaces and Exposed Foundation Walls
Reference: BRM-00220488-A0 July 18 th, 2014 Toronto Catholic District School Board 80 Sheppard Avenue East Toronto, Ontario M2N 6E8 Re: 1.0 Introduction Exp Services Inc. (exp) was retained by the Toronto
BROWNSVILLE STRUCTURES STUDY. July 2012. Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208
BROWNSVILLE STRUCTURES STUDY July 2012 Prepared by LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208 TABLE OF CONTENTS I. SUMMARY OF BUILDING ANALYSIS.. 1 II. INDIVIDUAL BUILDING
Facility Assessment for. 11801 East Main Street, Huntley, IL
Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested
STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA
STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA College of Marin c/o Swinerton Management & Consulting P.O. Box 144003 835 College Avenue, Building MS-3 Kentfield, California
Exterior Elevated Elements Inspection Guidelines
Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code
Photos showing the change in condition from 2006 to 2012 are located in Appendix A.
January 27, 2012 Ms. Theresa Gallavan Economic Development Director City of Lompoc 100 Civic Center Plaza Lompoc, California 93436 RE: Lompoc Theater Limited Visual Condition Assessment Dear Theresa: Representatives
CLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.
CLIENT Inspection Report 271 Front St. Alert Bay, B.C. Island Building Inspections 2013 V ANCOUVER I SLAND B. C. Elevation Photos For the Property at 271 Front Street Alert Bay, BC ELEVATION PICTURES Front
October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.
117 S. Market St. Benton, AR 72015 * 501-315-2626 * Fax 501-315-0024 October 30, 2014 Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR Re: Report of Findings,, Benton, Arkansas, Dear Mr. Vick: This
DRAPER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
29 Broadway- 14 th Fl Tel: 212.888.8334 New York NY 10006 Fax: 212.419.1939. Due Diligence Report. New York, New York
Due Diligence Report New York, New York Prepared for Mr. On February 8, 2010 P a g e 1 Table of Contents PAGE 3.. GENERAL INFORMATION PAGE 4 FILINGS PERMITS AND ENCUMBRANCES PAGE 6. CORE AND SHELL PAGE
48. AQUARIUM. Aquarium. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle. Total Area: No.
Classification: Cluster: Location: Total Area: No. of Stories Aquarium Acreage Owned: Acquired: 1904 Most Recent Improvements: THE AQUARIUM Close to junction of Inselrhue and Loiter Way, Belle Isle Two
Building Condition Assessment Report
Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.
School Construction Authority Architecture & Engineering
SCOPING GUIDELINES 1.0 GENERAL GUIDELINES 2.0 BUILDING ENVELOPE SCOPING GUIDELINES 3.0 CATEGORIES AND COMPONENTS: The Flood Elimination/Below Grade Capital Category may include some or all of the following
Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas 77089. August 30, 2012. Prepared for:
A Full Service Real Estate Inspection & Engineering Firm for Houston, Texas 77089 August 30, 2012 Prepared for: CLIENT S NAME MAILING ADDRESS Houston, Texas 77089 Prepared by: Charles J. Jenkins, P.E.
Report on Sanctuary/Chancel Crawl Space Inspection. St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove. Project No.
Report on Sanctuary/Chancel Crawl Space Inspection St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove Project No. E112056 1. Background St. John in the Wilderness (SJITW) is considering
Inspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com [email protected]
Excerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
Saint Cloud Business Center
Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with
Lighthouse Engineering, L.L.C.
Monday, May 07, 2012 Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website:
MEMORANDUM. General: Foundation:
MEMORANDUM State of Alaska Department of Transportation and Public Facilities Central Region - Division of Construction and Operations Public Facilities Branch TO: Jennifer Murrel DATE: August 19, 2010
Lighthouse Engineering, L.L.C.
Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: [email protected] Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering
Vision Home Inspection
Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the
HAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA
INITIAL YEAR BUILT 1968 BUILDING AREA 187,700 SF CURRENT PROGRAM CAPACITY N/A ENROLLMENT 2008 129 WARD 5 PROPOSED PROGRAM CAPACITY N/A Site Plan HAMILTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:
Texas Depadment of Transpo,tation Bridge Condition Survey Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Irving Street Facility Name: Lone Wolf Bridge Structure Number: B00315-031
17,280 square feet Overview:
CENTRAL OFFICE Located at 167 Boston Post Road, East Lyme, Connecticut, the Central Office was built in 1916 as the original Flanders Elementary School and remains connected to the current school. The
REQUEST FOR PROPOSALS FOR: THE PURCHASE AND RENOVATION OF ADJOINING PROPERTIES AT 200/240 SOUTH 16 TH STREET ORD, NEBRASKA BY:
REQUEST FOR PROPOSALS FOR: THE PURCHASE AND RENOVATION OF ADJOINING PROPERTIES AT 200/240 SOUTH 16 TH STREET ORD, NEBRASKA BY: THE COMMUNITY DEVELOPMENT AGENCY OF THE CITY OF ORD JULY 2014 A. STATEMENT
Property Condition Assessment
Property Condition Assessment Business, Wisconsin Inspection Date: 8/2009 Prepared For: Business Owner Report Number: TD999909 Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar
Garver Feed Mill Condition Evaluation
Garver Feed Mill Condition Evaluation OUTLINE Brick masonry overview Condition assessment & methodology Project overview Existing conditions Stabilization Probable costs Summary BRICK MASONRY OVERVIEW
CZAR Engineering, L.L.C.
CZAR Engineering, L.L.C. Lamont H. Czar, P.E. Phone: (609) 653-9445 5014 Fernwood Avenue Fax:(609)653-2015 Egg Harbor Township, New Jersey 08234 www.czarengineering.com May 3, 2013 Craig Dothe, Architect
Estimated Cost of Repair
1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:
WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204
WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204 Structural Inspection Report Client: CSArch Architecture Engineering Construction Management 19 Front Street, Newburgh,
National Home Builder - Name Wednesday, August 20, 2014 Regional Customer Care Manager 1234 Main Street Houston, Texas 77067
Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com
How To Prevent Water Damage To A Home
Having inspected about 800 homes in the last four years, I have seen a lot of problems with many homes. Most of these problems are minor; however, there are some problems that are quite serious. One of
Lighthouse Engineering, L.L.C.
Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: [email protected] Thursday, September 04, 2014 TO: Our Client RE: Engineering Evaluation
A0 SHEET 1 OF 5 400 LOCUST STREET FRANKFORT, KANSAS 66427 FRANKFORT, KANSAS 66427 ROOF REPAIR OF THE 400 LOCUST STREET
POYNTZ AVENUE, STE 9 MANHATTAN, KS 0..0..9 FAX WEST th STREET JUNCTION CITY, KS.... FAX 0, Bruce McMillan AIA, Architects, P.A. HERITAGE TRUST FUND GRANT PROJECT NO. 0-0 ROOF REPAIR OF THE 00 LOCUST STREET
May 5, 2010. Client Client Address. Re: Inspection Address, Chicago, Illinois. Dear Mr. Client,
PROPERTY INSPECTION PROFESSIONALS May 5, 2010 Client Client Address Re: Inspection Address, Chicago, Illinois Dear Mr. Client, On May 4, 2010, Tomacor completed a property inspection of the above referenced
Project Report. Structural Investigations Hotel del Sol Yuma, Arizona
Project Report Structural Investigations Yuma, Arizona Prepared by: 2619 Spruce Street Boulder, CO 80302 303-444-3620 Prepared for: Principle Engineering Group, Inc. 833 East Plaza Circle, Suite 100 Yuma,
www.citiesinspection.com October 5, 2015 Dear Client,
www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.
Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
Chapter 5. In-depth Building Analyses and Recommendations. Planning Study for Downtown Revitalization City of Martinsville
75-77 East Washington Street In-depth Building Analyses and Recommendations Chapter 5 In-depth Building Analysis Overview Four of the nineteen downtown buildings selected for façade assessments and recommendations
Mark Cramer Inspection Services, Inc.
Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction
Home Inspection Report
Home Inspection Report Report Number: 144 For The Property Located On: 123 Any Street 27587 Prepared For Exclusive Use By: Mr. Sample N/A,,, Report Prepared By: Edward Carapezza; License No.: 3447 Inspector
Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By
Project Structural Conditions Survey and Seismic Vulnerability Assessment For SFCC Civic Center Campus 750 Eddy Street San Francisco, California 94109 Prepared For San Francisco Community College District
HISTORIC PRESERVATION COMMISSION ADMINISTRATIVE APPROVAL ISSUED JULY - SEPTEMBER 2014 DATE PROJECT ADDRESS PROJECT DESCRIPTION
HISTORIC PRESERVATION COMMISSION ADMINISTRATIVE APPROVAL ISSUED JULY - SEPTEMBER 2014 DATE PROJECT ADDRESS PROJECT DESCRIPTION 07/02/14 212A King George Street Remove existing picket fence from side yard
Certificate of Appropriateness Applications
Certificate of Appropriateness Applications Huntsville Historic Preservation Commission August 10, 2015 Applicant: Philip Buzzetta Submission Date: 07/07/15 Architectural Style: Dutch Colonial Status:
Memorandum. July 16, 2008. To: Plan Commission City of Madison
Memorandum July 16, 2008 To: Plan Commission City of Madison From: Marc Schellpfeffer Engberg Anderson Re: Structural/Architectural Assessment of Homes for Proposed Demolition Findorff Yards Office Lofts
Appendix 2-A: Asbestos Assessment Summary Table
Final Environmental Impact Statement Cricket Valley Energy Project Dover, NY Appendix 2-A: Assessment Summary Table Earth Resources 1 Main First Floor A33 Heater Unit 1 EA F Poor Y Assumed ACM 1 Main Second
Self-Home Inspection Checklist
To be used as a first home visit for note taking. Visit www.homeinspectiondirect.com for more tips and information about buying a home and hiring a home inspector. This form in no way replaces a professional
OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007
OTTAWA CIVIC CENTRE & NORTH SIDE STANDS at LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007 for CITY OF OTTAWA REAL PROPERTY ASSET MANAGEMENT prepared by ADJELEIAN ALLEN RUBELI LIMITED
HEATING, VENTILATING, AND AIR CONDITIONING EQUIPMENT. Application Guidelines
HEATING, VENTILATING, AND Application Guidelines The Landmarks Preservation Commission (LPC) is the Mayoral agency charged with designating and regulating individual landmarks and historic districts. The
Historic Preservation Certification Application Part 2 343-345 Main Street West South Haven, Vermont NPS Project No. 12345
Exterior Features 1 site and drainage 2 foundation 3 wood siding and trim 4 exterior doors 5 windows / storm windows 6 porches front and rear 7 chimneys 8 roofing Interior Features 9 frame 10 basement
ASHULIA APPARELS LTD. Client Summary Report
Revision : Issue 1 Date: 18 March 2014 ASHULIA APPARELS LTD Samad Mansion, Sec # 6, Block # kha, Road No# 1, Plot #14, Shenpara Parbata, Mirpur, Dhaka (23.8065N,90.3683E) 4th March 2014 Client Summary
Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training
Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline
PROFESSIONAL ENGINEERING INSPECTIONS, INC.
PROFESSIONAL ENGINEERING INSPECTIONS, INC. P. O. BOX 271492 HOUSTON, TEXAS 77277 Registered Engineering Firm #1503 http://www.profengineering.com (713) 664-1264 July 8, 2004 Mr. Simple Samson 2831 Octoberfest
HOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663)
HOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663) Fire-Retardant-Treated Wood Framed Wall Assemblies GENERAL INFORMATION Fire-resistant construction
Odd Fellows Hall. 63-65 Warren Avenue, East Providence, RI Historic Structure Assessment. June 2014
Odd Fellows Hall 63-65 Warren Avenue, East Providence, RI Historic Structure Assessment June 2014 Ms. Jeanne M. Boyle, Executive Director East Providence Waterfront Commission East Providence City Hall
Lighthouse Engineering, L.L.C.
Wednesday, August 20, 2014 Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website:
Simpson Engineering A state licensed engineering firm F-1607
Simpson Engineering A state licensed engineering firm F-1607 4126 Allencrest 13901 Midway Lane, Dallas, Road, Texas Ste.102-136 75244 Telephone: 214-351-1637 Dallas, - Fax: TX 214-351-1639 75244-4388 Telephone:
PROPERTY East Wetumpka Commercial Historic District (Boundary Increas NAME: e)
REQUESTED ACTION: UNITED STATES DEPARTMENT OF THE INTERIOR NATIONAL PARK SERVICE EVALUATION/RETURN SHEET NOMINATION PROPERTY East Wetumpka Commercial Historic District (Boundary Increas NAME: e) MULTIPLE
CONSERVATION MAINTENANCE WORKSHEET Universal Checklist
3.1 SITE 1 Concrete curbs Check for cracks, spalling, growth from joints X 2 Stone curbs Check for cracks, spalling, growth from joints X 3 Concrete walkways Look for uneven surfaces, ponding, growth from
ELIGIBLE REPAIR PROJECT PARAMETERS
THE DISTRICT MUNICIPALITY OF MUSKOKA ONTARIO RENOVATES PROGRAM FOR HOMEOWNERS ELIGIBLE REPAIR PROJECT PARAMETERS 1. To have your project considered and payment processed, all projects requiring a Building
Steve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022
M G C O N S T R U C T O R S & E N G I N E E R S, I N C. I N S P E C T O R S E N G I N E E R S B U I L D E R S C A L I F O R N I A E N G I N E E R I N G A N D B U I L D I N G L I C E N S E A / B 6 4 2 0
LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -
The original section of this building was constructed in 1941. The exterior walls are built of good quality stone. In the early 1980 s a similar addition was added to the north elevation. The exterior
GUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES
GUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES PAGE 13 DESIGN GUIDELINES The following design guidelines have been developed to guide appropriate design in the Downtown
Timber Frame Construction
Timber Frame Construction Introduction Design and Detailing What is timber? Failure modes History of timber frame construction Forms of timber frame construction Live and dead loads Wind loads Roof construction
CONDITION OF QUALITY ITEMS
CONDITION OF QUALITY ITEMS FOUNDATION Always look for moisture problems and any bulges or irregularities in the walls. Lines on the walls or floors may indicate water problems. Have these been cured? If
COMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
Basement & Foundation Damage
Basement & Foundation Damage Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case
Solving Persistent Moisture Problems and Moisture Damage
B etter buildings Solving Persistent Moisture Problems and Moisture Damage Summary This three-storey, 15-unit, 1,300 square metre (13,993 sq. ft) walk-up was built in 1958. In the 1980s, the building started
MURCH ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E)
Revision: issue 1 Date: 11 June 2014 Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E) 24 th May 2014 Structural Inspection Report Observations
PRESERVATION PLANNING ASSOCIATES 519 Fig Avenue, Santa Barbara, CA 93101 Telephone (805) 450-6658 Email: [email protected]
PRESERVATION PLANNING ASSOCIATES 519 Fig Avenue, Santa Barbara, CA 93101 Telephone (805) 450-6658 Email: [email protected] June 17, 2015 Ms. Kimberley Heaton McCarthy Supervising Planner Building and Safety
Chapter. Restoration of Damaged Structures
5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.
University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage
University of Missouri Hospitals and Clinics Structural Repair and Protection of Post-tensioned Parking Garage 1 University of Missouri Project The University of Missouri Health Care Patient and Visitor
March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202
Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request
D Sample Notices to Property Owners, Sample Affidavits, and Other Material
D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully
RESIDENTIAL MASONRY A BEST PRACTICES GUIDE
RESIDENTIAL MASONRY A BEST PRACTICES GUIDE Build With Brick Build With Boral CONTENTS BRICK :01 MASONRY CEMENT :03 MASONRY SAND :04 WALL TIES :05 STEEL LINTELS :07 DRAINAGE WALL SYSTEM :09 FLASHING :11
BUNKER HILL ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1970 BUILDING AREA 98,200 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 387 WARD 5 PROPOSED PROGRAM CAPACITY 750 Site Plan BUNKER HILL - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
Expected Performance Rating System
Expected Performance Rating System In researching seismic rating systems to determine how to best classify the facilities within the Portland Public School system, we searched out what was used by other
Chapter 11: Demolition
City of Independence Chapter 11: Demolition In this chapter you will find: Demolition Mothballing Treatment Types of Demolition By Neglect and Recommended Corrective Measures DEMOLITION Photograph on cover
POST AND FRAME STRUCTURES (Pole Barns)
POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000
Block Lofts Condominiums
Block Lofts Condominiums Building Envelope Condition Assessment 747 Ralph McGill Boulevard Atlanta, Georgia Presented to: Block Lofts Condominium Home Owners Association C/o Heritage Property Management