Pasila Tripla, Helsinki. Hannu Jokiniemi

Similar documents
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

BUTE Department of Construction Management and Technology

MASS STABILIZATION of. peat, mud and contaminated sediments. Geoteknikerdag Juni 1st & 2nd 2007 Mikko Leppänen & Jorma Havukainen Ramboll Finland Oy

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Monitoring of Tunnel End Plug Performance in ONKALO

How To Retaining Wall Guide

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Member Nation Report 2010 from Denmark.

(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT Nina Tveiten Norwegian National Rail Administration

Specification Guidelines: Allan Block Modular Retaining Wall Systems

SECTION SUPPORT OF EXCAVATION

Design and Construction of Auger Cast Piles

Safe & Sound Bridge Terminology

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Building Pit Roche Building 1 Basel, Switzerland

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Slab Track Austria. System ÖBB-PORR elastically supported slab

Soils, Foundations & Moisture Control

Unit Price Averages Reports

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

Söderströmtunnel: immersion in downtown Stockholm, Sweden

High Capacity Helical Piles Limited Access Projects

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

hs2 Ground A non-technical guide

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

BIM-based falling prevention planning

1. Safety. 2. The Lining Contractor. DEPARTMENT OF AGRICULTURE, AND FOOD Farm Development Service November 2002 S126

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Supplier ID: Local Office: GLASGOW 69 Buchanan Street Glasgow G1 3HL

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

BRIDGES ARE relatively expensive but often are

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

LAYING BLOCK AND BRICK

September September Consulting Structural and Civil Engineers. 100 St John Street London EC1M 4EH. akt-uk.com

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

METHOD OF STATEMENT FOR STATIC LOADING TEST

Improving the flood resistance of your home. Advice sheet 6: Flood-resilient floors

Embedded Parts Introduction - Anchors

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

The International Workshop on Micropiles, 2007

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

constructive solutions Fosroc total waterproofing protection of below-ground structures

Moving Small Mountains Vesuvius Dam Rehab

Milan M5 metro extension the construction of Lotto station

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

C. Section TESTING LABORATORY SERVICE.

FRANKIPILE. High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process

Gas Explosion at a Subway Construction Site

Permeable Pavement Construction Guide

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

PILE FOUNDATIONS FM 5-134

Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio

Leakage Management & Control

SECTION SHEETING, SHORING AND BRACING

[4] SA1.2 The student demonstrates an understanding of the processes of science by observing,

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

TBM CROSSING OF STATIONS

HOUSE BUILDING DIGEST

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Membrane for tunnels and underground construction

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

Construction Technology 3

Guide to working on Public Sewers

METHOD STATEMENT 006 TORCH APPLIED MEMBRANE TO BASEMENT WALLS

ADVANCED SYSTEMS FOR RATIONAL SLAB REINFORCEMENT

Piling Datasheets. Continuous flight auger (CFA) Driven Rotary

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Emergency repair of Bridge B421

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

Types of Retaining Walls - Gravity walls - Pre-cast crib walls - Gabion walls - Reinforced concrete walls - Sheet pile walls - MS walls (mechanically

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

Chapter 2 Basis of design and materials

Watershed Works Manual

Corrosion protection linings. Issue 1

COSMOS 2012: Earthquakes in Action COSMOS 2012

For a Coastal Site. A Pier-and-Beam Foundation. Our company specializes in oceanfront

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

Federation of Piling Specialists July 2010

Section 2100-Trenching and Tunneling

SECTION 411 DRILLED PIERS

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

Specifications for Residential Property Owners Connection to New Public Sewer

PRESENT ISSUES FOR CENTRE DE LA MANCHE DISPOSAL FACILITY

CITY OF HELSINKI. Introducing Major Urban Development Projects EXPO REAL, München, October

Wastewater Capital Projects Management Standard Construction Specification

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

Preventing water damage in the basement

Transcription:

Pasila Tripla, Helsinki Hannu Jokiniemi 2016-04-14

Outline Pasila Tripla Description of the project Soil conditions & investigation program Design boundaries Alternative solutions for the retaining barrier wall Selected solution Long term durability Installation Anchors Excavation Summary 2

Pasila Tripla quick facts A massive construction project that will encompass three city blocks including a shopping centre, public transportation hub, housing, hotels and headquarterslevel offices Tripla-project was a result of a design competition PasilaONE, which was arranged by City of Helsinki (2013-2014): YIT s winning proposal Pasila Tripla The total area will be 183,000 floor square metres Total value >1 mrd Tripla will be constructed in stages during 2018 2021. Shopping mall part ready 2019, 1 st apartments 2020 3

Pasila Tripla covers three city blocks 4

What is Tripla? Under Station & Western blocks will be shopping mall & underground parking facility for 2500 cars -> utilize RD pile wall 5 2015-09-30 Hannu Jokiniemi 3000 citizens and 15000 jobs Permitted building volume 183,000 floor square m Execution during 10 next years Pasila Station block 100 trains daily Conference center HQ offices & public transportation terminal Center block Hotel, City Suites, etc. Western block Apartments Garden/resident park

6 2015-09-30

7 2015-09-30 Hannu Jokiniemi

Soil conditions A lot of variations Ground level +15.0 15,5 PW & GW levels +14.0 Perch and groundwater flow from the Northern Pasila to South The whole area is covered with a layer of filling (typically 2 3 m) Gravel, sand and in part of the areas also some blasted rock (up to 6 m) Part of the fills are polluted (such as creosote) Under the fill there are thin layers of peat and clay including gyttja After that layers of clay and sand until the moraine layer which is very dense just above bedrock. Bed rock can be found at deepest at the level of -16.5 (i.e. 32 meters below the ground surface). The bedrock includes two major weathered zones 8

Extensive soil investigation program 300 locations (10 m distance at wall line) 9

Some boundary conditions Existing nearby structures: East: Pasila railway station (founded on Cast in-situ piles and on rock) and ground supported railway line embankments South: The Old and the new Pasila Bridges. The Old Bridge is founded on Cast in-situ piles and the new one on RD piles. West: Pasilankatu (street) on loose & mixed fill incl. large boulders which has normal traffic and also tram lines North: Nothing major To implement: A barrier wall structure, which prevents perch (PW) and groundwater (GW) levels from dropping. Southside of Tripla, is an old railway engine hall, which is founded partly on wooden piles and partly ground supported on clay. Separate PW and GW transfer systems that will collect and transfer PW and GW from the Northern part into South where they are absorbed into the ground again. This is because the barrier wall cuts the normal flow of PW and GW from North to South. A barrier wall and foundations on the parking facility which have design age of 200 years A barrier wall structure and the excavation itself which may leak only 60 l/min 10 2015-09-30 Hannu Jokiniemi

Alternatives for the retaining barrier wall Pros & Cons of RD pile wall RD pile wall Selected solution after technical & economical comparison Cast-in-situ concrete secant pile wall Cast-in-situ concrete piles & Jet Grouting columns in between Considered to include major risks already at the beginning of the evaluation Pros & Cons pf RD pile wall according to contractor: Fast to install Reliable water tightness during the excavation Good positional tolerance after the installation Can take large loads (steel grade, wall thickness, reinforcement and concreting) Doubts on long-term (200 years) water tightness at interlock location Corrosion (some organic and contaminated soil layers exist) Disturbance of the soil layers during the installation (air) Large amount drilling mud 11

Piling solution for Central-Pasila Tripla underground parking facility Mainly RD700/14.2 S440J2H pile wall 746 pcs of piles (16.6 km / 4050 t) ranging from 5.5 m to 33.5 m installed in one pieces Design life 200 years (corrosion allowance 6.5 mm) RM/RF interlocks provided with bitumen Installed first by vibrating and finally by drilling into the bedrock Reinforced and concreted Small amount RD400/12.5 S440J2H pile wall 60 pcs of piles (1.2 km / 150 t) ranging from 23 m to 26 m with element length of 4 m RD400/12.5 piles will be reinforced by inner RD320/12.5 S550J2H pipes Altogether close to 4200 tons of piles / 13500 square m Over 130 on-time deliveries to site in less than six months Designer: Ramboll Finland Oy Main contractor: YIT Rakennus Oy Piling contractor: KSBR Oy and Fort Ehitus OU 12

13500 m 2 of RD pile wall, avg. depth 24 m and max 32 m Width x length of excavation 220 x 110 m 13

Doubts on long-term (200 years) water tightness at interlock location Steel plate, PL5 Excavation Steel plate is welded to the piles and the gap will be filled with grout/mortar 14

Corrosion (some organic and contaminated soil layers exist) Soil samples were taken from 2 locations from the layers below the fill layer. ph, conductivity, amount of sulfate (SO4) ions and total amount of sulfur. The report from Technical Research Centre of Finland (VTT) indicated that the corrosion margin in the clay layer should be in 12 mm/200 years and for mineral soil layers 2 mm/200 years. However when old Pasila Bridge was constructed, old railroad rails were used as a rack piling. One such pile with a length of 23 m was found (produced in Britain at the end of the 19th century. The rail had been in ground for more than 30 years! The rail was cut into pieces and the pieces were taken into laboratory for measurements. The measurements were taken every 10 cm from the foot, the stem and the top of the rail. After thorough analysis the new info was simplified by using corrosion margin on 12 mm all the layers above level +9.0 and below that it was used a corrosion margin of 6 mm. 15

Installation phase I Vibrating into moraine layer, no splice welding with RD700 piles 16 2015-09-30 Hannu Jokiniemi

Installation phase II Augering the pile pipe empty 17 2015-09-30 Hannu Jokiniemi

Installation phase III Drilling into the bedrock 18 2015-09-30 Hannu Jokiniemi

Robit Steel Fist Wing Pilot 19 2015-09-30 Hannu Jokiniemi

Use of template clearly improves the tolerance of the wall 20 2015-09-30 Hannu Jokiniemi

Drilling mud The amount of replaced soil by RD pile wall in the job site is 7000 m 3 Amount of drilling mud is increased by the existing weathered rocks below ground water table Drilling muds were collected into reservoirs where they were mixed with dry soils in order to facilitate the transportation away 21

Drilling of RD400/12.5 pile wall under railway platform 22 2015-09-30 Hannu Jokiniemi

Splice welding of RD400/12.5 pile wall 23 2015-09-30 Hannu Jokiniemi

Concreting of the piles & space between pile pipe and bedrock 24 2015-09-30 Hannu Jokiniemi

Anchors RD pile wall is supported by temporary rock anchors Appr. 800 pcs (14.2 km of soil drilling and 6 km of rock drilling) Anchors are strands with 15.7 mm strand and nr of the strands vary fro 5 to 19 (design loads 450-2910 kn) Anchors are generally inclined 1:1 and grouted into the rock. The longest soil drilling are >40 m long Casing tubes are SSAB threaded RDc140/5 & bevelled RD140/4.5 and RD170/4.5. All anchors will finally be deactivated (cut) and the supporting will be implemented with the floor slabs of the parking facility 25

Excavation ongoing Appr. 640 000 m 3 26 2015-09-30 Hannu Jokiniemi

SUMMARY

RD pile wall in Pasila Tripla, Finland Reliable and watertight retaining wall in demanding soil conditions and busy urban environment with fast installation

RD pile wall in Pasila Tripla, Finland Reliable and watertight retaining wall in demanding soil conditions and busy urban environment with fast installation OUR SOLUTION SSAB s RD pile wall solution enabled fast installation with tight tolerances. Accuracy and speed in addition to water tightness made RD pile wall best solution for the customer. Installation method was also least risky for the surroundings as removing the clay with auger creates little to no spatter. Piles were transported full-length sections. Exceptional length of the piles was up to 33,5 m (8,5 t). CUSTOMER CASE Pasila Tripla is three-block retail, office and housing complex to be built in Pasila district close to the city center of Helsinki. It will be completed in stages by the early 2020s. Customer s challenge was to find a watertight retaining wall solution to surround the 640 000m3 excavation for the garage. Location is critical right by a bridge with foot traffic, railway track and busy Pasilankatu street. Delivery and installation speed were critical for the customer: it was important to have piles delivered in one piece to avoid additional welding at site. The retaining wall cuts through groundwater layers, which exerts an enormous pressure on the underground structures making water-proofing the retaining wall demanding. Watch video Delivery (2015-2016) so far: SSAB RD pile walls 754 pcs RF/RM-interlocked drilled piles RD700/14,2, 16 700 m in total 60 pcs RF/RM-interlocked drilled piles RD400 /12,5, 1 300 m in total 60 pcs structural pipes RD323/12,5, 1300 m in total Anchor casing tubes: RDc140 /5,0 and RD170/5,0, 20 000 m in total Co-operation partners: Client/Project owner: YIT Rakennus Oy Main contractor: Keski-Suomen Betonirakenne Oy Drilling contractor: Fort Ehitus OÜ and YIT Rakennus Oy Drilling consultant: Ilmi Solutions Oy Drill bit supplier: Robit Oyj Design: Ramboll Finland Oy Contact: jari.mara@ssab.com

QUESTIONS?