CIRCUIT BREAKER TESTING SWP

Similar documents
CAPACITOR BANK TESTING SWP

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

COMMISSIONING TESTS FOR HV UNDERGROUND CABLES (UP TO 33KV) SWP

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

MEDIUM VOLTAGE SUBSTATION PRACTICES Medium Voltage (MV) is defined as: 1000V< MV 44kV

Unified requirements for systems with voltages above 1 kv up to 15 kv

SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV a. Section INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

High Voltage Circuit Breakers 3AP Type 72.5 kv to 800 kv Answers for energy.

Release: 2. UEENEEJ194A Solve problems in low voltage refrigeration circuits

Hyperlinks are Inactive

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Electrical safety rules

Circuit Electrical Testing

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

The Intelligent AX1 Switchgear for Medium Voltage

PROPER SELECTION OF CONTROL CIRCUIT TRANSFORMERS WHITE PAPER BULLETIN 1497, 1497A, AND 1497B

Part 1 System Modeling & Studies for Existing Systems

DESCRIPTION DWG DESCRIPTION DWG

Siemens Integrated Substation Condition Monitoring System. Circuit Breaker Monitoring

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

ELECTRICAL SAFETY RISK ASSESSMENT

Reyrolle Protection Devices. 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy

SECTION ELECTRICAL ACCEPTANCE TESTS

Secondary Unit Substations

Arc Flash Avoidance and its Application to Overhead Traveling Cranes

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

Advantages of Fixed Circuit Breaker Switchgear

High-Voltage Circuit-Breakers 3AP1/ kv up to 550 kv. Power Transmission and Distribution

Erik Backström, High Voltage breakers, After Sales & Service High voltage SF 6 live tank circuit breakers After Sales & Service Training course

What s up with Arc Flash?

NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers

PowlVac Vacuum Integrity Tester

The following components are common to most cubicles; this example is an ABB HK cubicle.

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

Arc Flash Hazards. Electrical Hazards. Dan Neeser Field Application Engineer Electrical Hazards 2/18/2015. Shock.

Code of Practice Electricity transmission and distribution asset management. February 2009

Positive-guided relay outputs: 3 safety contacts (N/O), instantaneous. 1 auxiliary contact (N/C), instantaneous

NFPA 70E Updates Affect Your Most Valuable Assets

SECTION STANDBY GENERATOR TESTING AND COMMISSIONING

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev July 17 and Testing, ROPEC Page 1

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...

Medium Voltage Products. ZN1 12 kv arc-proof air-insulated switchgear for primary distribution

E&I MAINTENANCE ENTRY TEST ENABLING OBJECTIVES. DESCRIBE hazards and precautions taken to avoid injury in the workplace.

Outdoor circuit breaker GVR Recloser Hawker Siddeley Switchgear. rated voltage 15, 27 and 38 kv rated current 630 A

Primary and Secondary Electrical Distribution Systems

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / SC / SC / 1250SC / 1600SC / 1800SC / 2000SC

How To Choose A Transformer

3AH5 Vacuum Circuit-Breakers. Answers for energy. Medium-Voltage Equipment Selection and Ordering Data. Catalog HG

49 Series - Relay interface modules A. Features

SECTION POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

CoDe of PRACtICe on electrical safety for work on or near high voltage electrical apparatus. the blue book

D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify.

Switchgear and Metal-Enclosed Bus

Instruction Bulletin. MCS025 Sync-Check Module Installation Sheet

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

Practical Transformers: Operation, Maintenance and Testing

Insulation resistance

FAQs-Main switchboard design criteria

Design of electrical power system for a 1000MW nuclear power generating station

Specification Guide. for RVAC. Direct Replacement. AC Medium Voltage. Circuit Breakers

Earth Fault Detection Basics in Theory

11. Assessment of service 12. S-phase supply 13. Water heaters NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS

Permissible ambient temperature Operation Storage, transport

High-Voltage Compact Switchgear 3AP1 DTC for 145 kv and 245 kv

GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE)

SM6 Series Circuit Breaker Monitors CONSOLIDATED. Electronics, Inc. MONITORING THE FUTURE

RISK MITIGATION for ELECTRICAL WORK. Feb 2013 San Diego CA

22 kv OUT DOOR VACUUM CIRCUIT BREAKER

AUTOMATIC TRANSFER SWITCH. Changeover Type from 250A to 2500A

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions

REVIEWED BY CAPITAL PROJECTS MANAGER (DAN REDDY) GENERAL MANAGER EQUIPMENT ENGINEERING & ASSET MANAGEMENT (HAMILTON NXUMALO)

A Practical Guide to Dielectric Testing

IEC and IEEE Standards for High-Voltage Switchgear and Controlgear Present Situation and Future Evolution

Circuit Breaker LTB D with Motor Drive. Motor Drive. ABB PP/H/HV - Page 1. Ed

Earthing Guidance Notes

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

Dead Tank Outdoor Vacuum Circuit Breaker, Type VOX

TWENTIES WORKSHOP, EWEA 2012 Unveiling the future energy system: full scale demonstrations to reach 2020 targets. 17th April 2012

Exploring the Necessity of the Hot Hipot Test

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

Electrical switchgear and safety: A concise guide for users

SIEMENS Transmission and Distribution

GENERIC REQUIREMENTS FOR UNINTERRUPTIBLE POWER SYSTEMS (UPS) TABLE OF CONTENTS

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

Electrical safety code of practice Managing electrical risks in the workplace

Union County Public Schools. Facilities Department. Electrical. Safe Work Practices

Table of Contents. TransformerIQ FAQs 1

The standards mentioned in this document

Engineering Specification

Written Program ELECTRICAL SAFETY. Based on OSHA Subpart S and NFPA 70E Standards

Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Acceptance Testing

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission

RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 June 2016

Guidance for upgrading to GB (IEC : 2005, MOD)

Transcription:

1. PURPOSE AND SCOPE Provide guidelines for testing of circuit breakers. Details of specialised circuit breaker tests are not included in this SWP. 2. STAFFING RESOURCES Adequate staffing resources with the competencies to safely complete the required tasks as per MN000301R165: 8 Level Field Test Competency. These competencies can be gained from, but not limited to any or all of the following:- Qualifying as an Electrical Fitter Mechanic Qualifying as a Technical Service Person Training in the safe use of relevant test equipment Requirement for all live work: Safety Observer (required for all live work as defined in the ESO Code of Practice for Electrical Work). All resources are required to: Have appropriate Switching and Access authorisations for the roles they are required to perform and have the ability to assess and maintain relevant exclusion zones from exposed live electrical apparatus Hold current licences for any vehicles and equipment they may be required to operate. Required Training Staff must be current in all Statutory Training relevant for the task. All workers must have completed Field Induction or have recognition of prior Ergon Energy Field Experience. Contractors must have completed Ergon Energy's Generic Contractor Worker Induction. 3. DOCUMENTATION CS000501F115. Daily / Task Risk Management Plan ES000901R102. HSECH Risk Control Guide MN000301R165. 8 Level Field Test Competency SP0509R01. Circuit Breaker Testing Job Safety Analysis SP0509C01. Circuit Breaker Test Report SP0509C01R01. Circuit Breaker Sample Test Report SP0509C02. Circuit Breaker HV Withstand Test Report. SP0509C03. Circuit Breaker Testing Competency Assessment SP0506. Substation Primary Plant and Secondary Systems Field Testing SWP AS 1931 1996 High Voltage Test Techniques Parts 1 and 2 AS 2006 1986 High Voltage A.C. Switchgear and Controlgear Circuit Breakers for Rated Voltages Above 1,000V AS 2650 1986 High Voltage A.C. Switchgear and Controlgear Common Requirements AS 2467 1981 Maintenance of Electrical Switchgear Test Equipment Manual Circuit breaker Manual / Manufacturer s Drawings 4. KEY TOOLS AND EQUIPMENT Test Equipment within calibration date, tested and tagged Page 1 of 6 Standard Work Practice SP0509 Ver 3

Safety Barriers HVIA Operating Equipment PED s, Live Line Tester, Class 0 gloves. All equipment to be inspected and confirmed within test date prior to use PPE including full-length protective cotton clothing, safety footwear, helmet. Additional PPE as required: brim for safety helmet, leather work gloves, class 00 gloves, hearing protection, safety eyewear, high visibility clothing when working on or near roadways. All PPE to be inspected and confirmed within test date (where applicable) prior to use Sun protection to be used when working outdoors 5. TASK STEPS 5.1. Carry out an on site risk assessment Prior to performing this activity any hazards associated with prerequisite tasks at the worksite shall be identified and assessed with appropriate control measures implemented and documented in accordance with the Daily/Task Risk Management Plan CS000501F115 and using reference document HSECH Risk Control Guide ES000901R102. If any risks cannot be managed or reduced to an acceptable level, do not proceed with the task and seek assistance from your Supervisor. 5.2. All work to be done with circuit breaker de-energised All of the tests described in this SWP should be carried out with the CB de-energised and appropriate control measures in place (eg barriers, matting) to prevent inadvertent contact with adjacent live plant or breaching exclusion zones. Furthermore, the P53 Operate the Network Process is applicable at all times for isolation and earthing. Careful consideration should be taken with the selection and placement of test leads. Only use appropriately rated test leads that are placed to be clearly visible to reduce the risk of them being not seen and removed prior to placing plant back into service. Where possible, use leads that are supplied with the test equipment since these will have suitable connectors and the correct current and voltage rating. Leads should be selected and used such that it is not possible to leave leads connected to the plant under test when the test equipment is removed (for example an integrated lead set or trifurcated leads). As described in Carry Out Field Testing SWP SP0506, particular safety risks applicable to Circuit Breakers include: Contact with high voltage at CB primary connections. High fault current at CB primary connections. Stored energy (eg charged spring) in the closing and tripping mechanism Initiation of other protection or control functions by change in state of circuit breaker auxiliary contacts 5.3. Record identification details. Manufacturer s name, manufacturer s type description and manufacturer s serial number: Plant number; Description, ie. dead tank, live tank etc; Rated voltage and insulation level; Rated nominal and short-circuit current and duration; Rated operating sequence; Page 2 of 6 Standard Work Practice SP0509 Ver 3

Interrupting medium; Specialised requirements such as: Rated Transitional Recovery Voltage envelope, Rated Out of Phase Breaking Current, Rated Cable Charging Breaking Current, Rated Capacitor Bank Breaking and Inrush Making Currents, Rated Small Inductive Breaking Current. 5.4. Visual inspection of Circuit Breaker condition. Inspect the circuit breaker for any sign of damage or leaks both externally and in the circuit breaker marshalling box. Confirm that the interrupting medium level/pressure is correct before commencing tests and that assembly is complete and no transport bracing has been left in place. Inspect the external surfaces and ensure the circuit breaker is clean and dry. Check all connections for adequate labelling. The connections should be unambiguous, legibly and adequately marked. 5.5. Auxiliary and Control Circuit Voltage Withstand. The circuit breakers auxiliary and control circuitry shall be subjected to a 1 minute power frequency withstand test at 2kV to confirm insulation integrity. The circuitry shall be considered to have passed if no disruptive discharge occurs during the test. Consideration shall be given where electronic components are used in the auxiliary and control circuitry. Different testing procedures and values maybe adopted subject to agreement by the Commissioning Engineer. 5.6. Measure Resistance of the Main Circuit. Measurement shall be made using D.C. current of at least 50A and less than the nominal current rating of the circuit breaker. The test shall be conducted as close as practical to ambient temperature. A four wire ductor should be used for measuring the resistance of the main contacts. Measure Insulation Resistance. DC insulation tests are to be carried out between terminals of the circuit breaker as detailed below. Note that these connection arrangements have been specified for consistency with AS2650 and to allow for future insulation condition diagnostic assessment. The voltage applied will be as per Table 1 for a duration of 1 minute. With the circuit breaker in the closed position: A or a to Earth and all other terminals B or b to Earth and all other terminals C or c to Earth and all other terminals With the circuit breaker in the open position: A to Earth and all other terminals B to Earth and all other terminals C to Earth and all other terminals a to Earth and all other terminals b to Earth and all other terminals c to Earth and all other terminals Page 3 of 6 Standard Work Practice SP0509 Ver 3

A, B and C refer to one set of CB high voltage terminals (eg fixed contact top of CB) and a, b, and c refer to the other set of terminals (eg moving contact middle of CB) Minimum acceptance value for new plant is 1,000M. Table 1. Applied Voltages for IR Tests Primary Voltage Rating Up to 1kV 1 Above 1kV to 3.6kV 2 Above 3.6kV to 12kV 5 Above 12kV 10 Measure Timing. Test Voltage in kv (D.C.) The time taken for the circuit breaker to complete an operation shall be measured for both opening or closing. Timing should be started by the application of voltage to the trip/close coil and stopped by operation of the main contacts. For both single and three pole CBs, each pole is timed independently as per clause HH2.4.2.1 of AS2006-1986 Note test both trip coils. Time travel measurement is required for 110 kv and above CBs or any CBs assembled on site. Measure spring charge time following close operation. 5.7. Carry out HV Testing. AS 2006 1986 specifies that normally no dielectric tests are performed at site on the main circuit, however AS 2067 1984 specifies that a 90% power frequency withstand test be carried out on site after erection. The level of high voltage testing to be applied is therefore: a) Where no HV testing has been carried out at the manufacturer s works 100%. b) Where HV testing has been carried out at the manufacturer s works but subsequent assembly of the HV chamber / bushings is required on site 90%. c) Where HV testing has been carried out at the manufacturer s works and no on-site assembly is required No HV withstand test. d) If the circuit breaker is aged or refurbished 75%. Where Um<=66kV the value of voltage applied shall be as per AS 2650-1986 as listed in the table below. Where Um>66kV the value of test voltage shall be in accordance with AS 2650-1986. Note that the test voltage used may be limited by the output capability of the test equipment. In this case a reduced test voltage for an extended duration as specified in Table 11.1 of AS 2067 1984 may be used. The requirements of the test are satisfied if no disruptive discharge occurs. An insulation resistance test is to be repeated after the HV withstand test to confirm that insulation degradation has occurred. Application of a 1 minute power frequency withstand test is to be in accordance with AS1931 Part 1 between the load and line terminals of the circuit breaker as detailed below. Note that these connection arrangements have been specified for consistency with AS2650 and AS2006 (Clause 7.1). Page 4 of 6 Standard Work Practice SP0509 Ver 3

With the circuit breaker in the closed position: A/a and C/c to Earth and all other terminals B/b to Earth and all other terminals With the circuit breaker in the open position. A, B and C to Earth and all other terminals a, b and c to Earth and all other terminals Nominal voltage of system (Un) kv r.m.s. Highest Voltage for equipment (Um) kv r.m.s. 3.3 3.6 10 6.6 7.2 20 11 12 28 22 24 50 33 36 70 66 72.5 140 Rated Short term Power-frequency withstand voltage (PFWV) KV r.m.s. Schedule of Tests The table below details the circumstances in which different tests are carried out: Test New Circuit Breaker Aged or refurbished Circuit Breaker High Voltage Withstand Auxiliary and Control Circuit Voltage Withstand Insulation Resistance Resistance Of Main Circuit Workshop or on-site test required at discretion of Commissioning Engineer *. Review manufacturers test result only Workshop or on-site test required. Reduced values apply. if circuit breaker wiring has been substantially modified Timing Time Travel Required for transmission CBs or CBs assembled on site Required for transmission CBs or CBs assembled on site *otherwise review manufacturer s results only DDF and capacitance measurement of the CB insulation may be required at the request of the client, particularly if DLA test equipment is available on site at the time of commissioning. Page 5 of 6 Standard Work Practice SP0509 Ver 3

5.8. Complete Pre-commissioning Checklist Circuit breakers being placed in service for the first time or after refurbishment require that the following items are checked prior to energisation: a) Check closing with 85% normal supply volts; b) Check closing with 85% normal air pressure; c) Check tripping with 70% normal supply volts (85% if AC); d) Check insulation medium/pressure; e) Check gas pressure alarm; f) Check gas pressure trip/lockout; g) Check fuses and links in service position; h) Check main earth on cabinet and support structure; i) Check motor overload/excess run timer set; j) Check local trip operation, including operation with both trip coils in parallel; k) Check local close operation; l) Check remote trip operation; m) Check remote close operation; n) Check SCADA trip operation; o) Check SCADA close operation; p) Check protection trip operation; q) Check protection reclose operation; r) Function test all Local/Remote/Maintenance switch; s) Check operation of pole discrepancy protection (if fitted); t) Check anti-pumping relay operation ie apply a close command and then a trip command while the close is maintained; u) Apply a latched trip command and then a close command while the trip is maintained; v) Check operation of interlocks; w) Check operation of all alarms; x) Check control switches in service position; y) Check operational nameplate and labels are in place. Page 6 of 6 Standard Work Practice SP0509 Ver 3