COMMISSIONING TESTS FOR HV UNDERGROUND CABLES (UP TO 33KV) SWP
|
|
|
- Megan Marsh
- 10 years ago
- Views:
Transcription
1 1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for pre commissioning and commissioning tests on high voltage underground cables. Where new cables are jointed to existing cables the test requirements are modified as described in this SWP to cater for the aged insulation of existing cables. 2. STAFFING RESOURCES Electrical Fitter and/or Mechanic or Cable joiner. Competent Assistant. Safety Observer where required. Required Training and Certificates Regulatory Training (as required) Course Code Course Description 2120 Cardio-Pulmonary Resuscitation 2130 Low Voltage/Switchboard Rescue 2140 Pole Top Rescue 2160 EWP Rescue and Escape 3131 Pole Testing for Safe Access 4033 LV Polarity Testing 4491 Safe to Approach to Structures *8115 Test HV UG Cables up to 33kV * Note: This course is part of Cable Joining Training. Staff performing HV Cable Testing should complete this training if not competent. Additional Training (as required) Course Code Course Description 4445 Switching Operator Lines 4440 Switching Operator Assistant T0405 Safe Entry to High Voltage Enclosures and Authorised Access / Test Permit Recipient and Authorised UETTDRRF07A Perform Cable Pit/Trench/Excav Rescue, if required 3070 Safe Work in Confined Spaces 3071 Confined Space Awareness 3. DOCUMENTATION CS000501F115. Daily/Task Risk Management Plan ES000901R102. Health and Safety Risk Control Measures SP0407R01 Commissioning Tests for New HV Cables (up to 33 kv) Job Safety Analysis SP0407R02 Testing HV Cables Supplementary Information SP0407R03. Commissioning Test For HV Underground Cable (up to 33kV) SWP SP Field Instruction SP0407C01 HV Cable Commissioning Test Report Form SP0407C03 HV Cable Inspection Test Plan Form SP0506. Substation Primary Plant and Secondary Systems Field Testing SWP SWMS001. Working at Heights - Poles & Ladders Check this is the latest Process Zone version before use. Page 1 of 12 Standard Work Practice SP0407 Ver 13
2 SWMS002. Working at Heights (Mobile Elevated Work Platform P53. Operate the Network Enterprise Process AS Switchgear Assemblies and Ancillary Equipment for alternating Voltages above 1 kv. BS0435: KEY TOOLS AND EQUIPMENT (as required) Pole Rescue Kit. Switchboard Rescue kit. Confined Space Monitoring and Rescue equipment. Roadway warning signs. Barricading. Work site communication equipment (e.g. 2-way radio). An insulated operating stick and tool head. Insulating Gloves applicable to the task. Dry chemical fire extinguisher. 5kV Insulation Resistance Tester (10 kv for 12.7/22 and 19/33 kv cables). Additional Equipment for testing Major Cables Very Low Frequency (VLF) high voltage Test Set for XLPE cables; DC high voltage test set for Paper Lead cables. 5. TASK STEPS 5.1 On Site Risk Assessment Prior to performing this activity any hazards associated with prerequisite tasks at the worksite shall be identified and assessed with appropriate control measures implemented and documented in Check this is the latest Process Zone version before use. Page 2 of 12 Standard Work Practice SP0407 Ver 13 accordance with Daily/Task Risk Management Plan CS000501F115 and using reference document Health and Safety Risk Control Measures ES000901R102. If any risks cannot be managed or reduced to an acceptable level, do not proceed with the task and seek assistance from your Supervisor. 5.2 Preliminary Steps and Safety Management Ensure appropriate construction and operational drawings are on hand. Use correct methods to positively identify the cable to be tested, including ensuring that cable number (where allocated) has been securely attached. Ensure that the associated switchgear operational nameplates are in place and securely attached. Ensure test equipment suitable for task. Confirm all test equipment is within current test date, calibrated and operational. Ensure all persons required to use test equipment are competent in its operation. Assign adequate staffing resources with required competencies to safely complete task. Persons performing electrical testing must ensure electrical equipment is tested to confirm electrical work performed is electrically safe. All staff to wear appropriate PPE including applicable class of gloves if required. Ensure class 00 gloves, and insulated mats are used while working on or near exposed live LV parts. Use roadway warning signs/ barricading to control vehicle and pedestrian traffic around work zone and relevant exclusion zones around live parts. Ground conditions and potential slip/fall hazards in travel path considered in CS000501F115 Daily/Task Risk Management Plan.
3 Identify locations defined as confined spaces and ensure compliance with confined space entry requirements. Ensure exclusion zones are maintained at all times while near exposed live parts. Caution Where it is identified that barriers or shields cannot prevent contact with the adjacent energised cable terminations (eg Magnefix cable termination kits), all HV within the exclusion zone shall be isolated, tested and earthed in accordance with P53 High Voltage Isolation and Access Procedures prior to gaining access to HV cable terminations. For other termination kits barriers or shields shall be used to prevent contact with adjacent energised cable terminations. Confirm cables to be tested are isolated from all HV & LV systems including secondary sources of supply and tagged, and locked where provision is made, in accordance with P53 Operate the Network Enterprise Process. Comply with SWMS001. Working at Heights - Poles & Ladders and SWMS002. Working at Heights - Mobile Elevated Work Platforms when working aloft. Ensure ground based persons are clear of drop zone while work is performed aloft. Use equipment to sample atmosphere and ventilate trenches prior to personnel entry in accordance with confined space entry requirements. Confirm cable terminations and lightning arresters/surge diverters are unbolted to perform tests where required. Position HV Test in Progress signs at all ends of the HV cable prior to testing. Where public access is possible, position Safety Observer and barricade exposed ends of cable during insulation test. Refer to SWP SP0506 Substation Primary Plant and Secondary Systems Field Testing for information on control of hazards and risks associated with testing of high voltage cables. In particular, take note of: 5.3 General Stored charge in the core under test. Stored charge in the sheath of the cable under test. Induced stored charge in the sheath and core of cores/cables adjacent to the one under test. It is noted that the insulating qualities of XLPE are very good, and that except in the case of major insulation damage such as physical puncture by a nail XLPE can withstand many times it s rated voltage without failure (typically > 14 times Uo for new cable). Most failures of XLPE cable are related to moisture ingress into joints or terminations or incorrectly applied terminations and joints (both workmanship and materials may be inadequate). One aim of testing of HV cables is to expose, in controlled conditions, any faults that will result in premature failure of the cable and associated terminations. It has been established that DC high voltage testing of deteriorated XLPE cables can accelerate the deterioration process and lead to a reduction in cable life. DC high voltage testing of new XLPE cables is not recognised to cause cable deterioration, however in order to adopt a standard approach VLF AC testing is preferred instead of DC high voltage testing for new and aged XLPE cables. The cable tests described below are to be carried out after installation and termination has been completed. Check this is the latest Process Zone version before use. Page 3 of 12 Standard Work Practice SP0407 Ver 13
4 In addition to the tests outlined below, a sheath integrity test should be done after installation and prior to termination to verify that cable damage during installation has not occurred. As described in later sections, testing of new or aged paper lead or XLPE cables is as per the following sequence: Record information; Sheath Test; Insulation Resistance Test; Phase Out; High Voltage Withstand including subsequent IR Test (additional to major cable testing only); Final Checks. Pre-terminated cables such as transformer leads in padmount substations should be tested as per this SWP. They are classed as minor radial cables and do not require a high voltage withstand test. Regarding the use of DC testing such as insulation resistance or leakage measurement during a high voltage DC withstand, there is a phenomenon called electro endosmosis (evident in older insulation rather than XLPE) that causes a lower IR reading (higher leakage current) when the positive terminal is connected to the grounded side of the insulation being tested. It is therefore preferred, where the test equipment allows a choice, to connect the positive terminal to the cable screen during test. 5.4 Check and Record Cable Identification. The outermost surface of cables should be embossed, printed or, in the case of PVC sheath, may be indented, with the manufacturer s name, year of manufacturer, together with the following information. Note: Cable Designated Voltage Legend To Be Marked 1.9/3.3 (3.6) kv Electric Cable 1.9/3.3 kv 3.8/6.6 (7.2) kv Electric Cable 3.8/6.6 kv 6.35/11 (12) kv Electric Cable 6.35/11 kv 12.7/22 (24) kv Electric Cable 12.7/22 kv 19/33 (36) kv Electric Cable 19/33 kv Indications of rated voltages are expressed in the form as shown above designate the following Uo/U (Um). Uo is the r.m.s. voltage to earth of the supply system for which the cable is designed and U is the r.m.s. voltage between phases of the supply system for which the cable is designed. Um is the highest voltage that can be sustained under normal operating conditions at any time. For multi-core cables, the cores should be identified in one of the following ways: By a printed numeral and word on the outer surface of each core eg 1 ONE; By a printed word on the outer surface of each core eg RED; By colour-marking semi conductive tape or coloured stripes throughout the full length of the cable. Check this is the latest Process Zone version before use. Page 4 of 12 Standard Work Practice SP0407 Ver 13
5 5.5 Verify Sheath Integrity. A sheath integrity test at a voltage of 1000V dc applied for 1 minute should be carried out with an insulation resistance tester, between the outermost metallic layer and earth. This will identify if there has been any damage to the sheath during/after installation. Notes: The screen shall be isolated at both ends and also at any mid circuit bonding for this test. A sheath integrity test should be done after installation (prior to termination) to verify that cable damage during installation has not occurred, and repeated when terminations are complete. Some newer cables may have a semi-conductive outer sheath. This is used to provide improved lightning performance and a more reliable mechanism for detecting sheath faults. The semiconductive HDPE does not require additional bonding to earth. The reading for cable sheath resistance should be greater than the acceptance value set out below for HDPE sheathed cables. This test is required for XLPE and paper lead cables. Distance 250m 500m 1000m 2000m Cable size M M M M 11kV or less mm mm kV or more mm mm Data is not presently available for cables larger than the cables specified above; however the insulation resistance should not be significantly lower than the figures above. For PVC sheathed cables, the acceptance value is 1 M. Earth the screen after test for at least 5 minutes. Where the prescribed values cannot be achieved the connection arrangement should be first checked. Where applicable the assistance of a high voltage test specialist may be sought and the Asset Manager must be advised where the value remains low. The Asset Manager will decide if sheath resistance values lower than the prescribed figures will be accepted. Cables with a suspected or confirmed sheath fault are not to be energised. If the cable has two insulated metallic layers (the cable screen and brass tape termite protection) then the insulation between these layers should be tested as well a further indication of possible cable damage. Note that this test is not required if these layers are bonded together, for example at joints. If a section of new cable is joined to an existing cable, the sheath test should be completed prior to bonding of the two screens. A sheath test of the completed cable should also be carried out for reference, but it is not expected that all aged cables will pass a sheath test. Caution: Where the cables to be tested are not disconnected from the ABB Safelink RMU the following actions must be taken to minimise the risk of injury or damage: Check this is the latest Process Zone version before use. Page 5 of 12 Standard Work Practice SP0407 Ver 13
6 1. The Earth Switch on any energised ABB Safelink RMU must not be switched from the EARTH to OFF position when the connected HV Electrical Apparatus are under access (i.e. the Busbar of the RMU must be de-energised using double isolation before the Earth Switch can be operated). 2. After operating the Earth Switch the switching operator must visually confirm that the correct switch state is displayed by the indicator. If the indicator is incorrect or in an indeterminate state personnel must stay well clear of the RMU and associated cable(s) and contact the Switching Co-ordinator for further instructions. 5.6 Core Insulation Test Prior to the high voltage withstand test (if required), the cable shall be tested for insulation resistance (IR). The test voltage used for the core insulation test is specified in the table below. Uo/U New Cables DC Test Voltage (kv ph to earth) Aged Cables DC Test Voltage (kv ph to earth) 1.9/ / / / / The core insulation resistance is to be measured A to B+C+E, B to A+C+E, and C to A+B+E; The insulation resistance shall be recorded 1 minute, 2 minutes and 5 minutes after application of the voltage. For very long cables it may take longer than 5 minutes for the resistance value to stabilise in which case a final reading is taken and the measurement terminated at 10 minutes. Conversely, the 2 and 5 minute readings may not be required for short cables if the reading has already stabilised. No breakdown of the insulation shall occur. The reading for IR for new XLPE cables should be greater than the acceptance values set out below. Distance 250m 500m 1000m 2000m Cable size G G G G 11kV or less mm mm kV or more 630mm mm mm Data is not presently available for cables larger than the cables specified above; however the insulation resistance should not be significantly lower than the figures above. The IR reading for aged XLPE cables should be greater than 1 Gohm. The cable screen should be earthed during the above measurement. Earth the cable conductors after test for at least 5 minutes. Where the prescribed values cannot be achieved the connection arrangement should be first checked. Check this is the latest Process Zone version before use. Page 6 of 12 Standard Work Practice SP0407 Ver 13
7 Termination leakage may need to be guarded out of the measurement to ensure accurate results (refer figure 1). Where applicable the assistance of a high voltage test specialist may be sought and the asset manager must be advised where the value remains low. The Asset Manager will decide if insulation resistance values lower than the prescribed figures will be accepted or if remedial works will be undertaken. How to use the Guard Terminal In cable insulation tests, wind a conductive wire around insulation of the cable under test and connect it to the Guard Terminal with the Guard Lead as per diagram. This is to move out the surface leakage resistance of the cable to make the test results accurate. Figure 1 Typical guard connection Note: One of the cores is used to transfer the guarded leakage at the remote end to the meter so that it does not impact on the measured insulation resistance. 5.7 Verify Phasing And Cable Continuity And Prepare Cable For Testing Verify cable phase identification and continuity by using a continuity tester or diode box. Ensure that any surge diverters or voltage transformers are disconnected from the cable so as not to impact on insulation resistance measurements or high voltage withstand testing. 5.8 Carry Out High Voltage Withstand Test And Record Leakage Currents. A routine high voltage withstand test shall be carried out on all major HV underground cables which are defined as: Check this is the latest Process Zone version before use. Page 7 of 12 Standard Work Practice SP0407 Ver 13 33kV, 66kV, 110kV and 132kV cables. 22kV cables greater than 185mm 2 Cu or 300mm 2 Al 11kV cables greater than 240mm 2 Cu or 400mm 2 Al All zone substation cables and feeder exit cables. A high voltage withstand test is not required on minor radial distribution cables. Categorisation of a cable as a minor radial cable will in most cases be self evident. Prior to any high voltage withstand testing being carried out, check that the cable screen connection to earth has been reinstated and that the test equipment earth is securely connected to this bond. Ensure that the capacitance of the cable under test does not exceed the output capability of the test equipment.
8 XLPE cable shall be tested with a VLF alternating voltage whose waveform shall approximate a sinusoidal waveform of frequency 0.1 Hz. Paper lead cables shall be tested with a DC voltage. The voltage shall be increased gradually and maintained at full value for the specified period. Note that a 30 minute testing period has been specified for XLPE cables on the basis that 89% of cable failures are likely to occur in the first 30 minutes. The value of test voltage used is specified in the following table for new cables. This table applies where the cable is not connected to switchgear or where there is no likelihood of overstressing an open point in the switchgear by the application of the test voltage. Uo/U DC Test Voltage (kv ph to earth) DC Test Voltage (kv ph to ph) VLF Test Voltage (kv peak ph to earth) 50Hz AC Test Voltage (kv RMS ph to earth) 15 min 15 min 30 min 1 min 15 min 1.9/ / / / / In the case of aged cables (say 5 years or older), 75% of the test voltages in the above table should be used. If the high voltage withstand test voltage would overstress the insulation of connected switchgear, for instance by being applied to one side of an open isolator when the other side of the isolator was energised at system voltage, it is preferred to disconnect the cable from the switchgear. Alternatively, where this is impractical, a reduced test voltage and duration applies as per the following table. The below test voltages have been reduced to account for the possibility of aged switchgear, so they do not have to be further reduced to account for aged cables. Uo/U DC Test Voltage (kv ph to earth) VLF Test Voltage (kv peak ph to earth) 50Hz AC Test Voltage (kv RMS ph to earth) 1 min 1 min 1 min 1.9/ / / / / For single core screened cables, the test voltage shall be applied between the conductor & metallic screen. Triplex cables shall be considered as three independent single core screened cables. Where multiple single core cables are being tested simultaneously, the remote ends of the cables should be connected together to limit the surge energy impact should one cable fail during test Where two or more cables are connected in parallel (in order to obtain a higher current rating), the parallel cores do not have to be tested individually they should be tested as a single core. For multicore cables having individual screening of cores, the test voltage shall be applied between each insulated conductor and metallic screen. Check this is the latest Process Zone version before use. Page 8 of 12 Standard Work Practice SP0407 Ver 13
9 The cores shall be tested in the configuration as described in the test report form to stress phase-phase insulation at the crutch whilst stressing the phase-earth insulation. For multicore cables without individual screening but an overall screen (eg. belted cables) the test voltage shall be applied between each insulated conductor and all adjacent conductors and metallic screen. The conductors may be suitably connected in groups as described in the test report form to reduce the number of tests. The cable has passed the high voltage test if no disruptive discharge occurs. Note that some VLF sets may show a reduction in output voltage in the event of cable failure but not trip out this is still considered a failure and the output voltage should therefore be monitored throughout the test. Caution In all cases, cores not under test shall be earthed at all times. Due to capacitive coupling, it is likely that unearthed cores not under test will be charged up by the electric field from the core under test and present a hazard to test staff. Caution Some cable boxes may have internal clearances insufficient to withstand the voltage applied during a high voltage withstand test and therefore they will flashover during test. This may also occur if cables are not in their final position during testing for example lugs not bolted up or boots installed. As a rule of thumb, allow 1 inch (25mm) per 10 kv RMS test voltage for air insulation during testing. If this clearance cannot be obtained, use additional insulation such as insulated mats where the clearance is reduced. Heat-shrink tubing or boots rated at the same voltage as the cable are satisfactory, but remember that these are NOT suitable for personal protection from high voltage because they are not regularly tested. Check this is the latest Process Zone version before use. Page 9 of 12 Standard Work Practice SP0407 Ver 13 Such insulation therefore should only be used where other personnel safeguards are in place (for example exclusion zones, earthed metallic barriers). As a rule of thumb, allow 1 mm of insulating material per 10 kv RMS test voltage. Refer to SP0407R02 for further information. Earth conductors after test for at least 5 minutes. An alternative to the VLF high voltage withstand test for XLPE cables is to use a one minute or fifteen minute 50 Hz AC high voltage withstand test. Although technically the 50 Hz withstand is a better test, it is recognised that the difficulty in supplying the associated high level of 50 Hz charging to a cable in a field situation will preclude this test being used in most situations. The test voltages specified have been derived from AS2067 and AS1824, recognising that the test requirements of AS are for routine tests at the manufacturer s works and may be too onerous for a terminated cable, especially considering any switchgear bushings and buswork that will be subjected to the test voltage. The 50 Hz AC high voltage withstand test can be useful when a pitch cable box precludes disconnection of a transformer from the cable (in which case 75% of the stated test voltage shall be used). 5.9 Post High Voltage Withstand Test Core Insulation Test After completion of the high voltage withstand test, the cable shall be re-tested for insulation resistance as per paragraph 5.6. There should be no decrease in insulation resistance due to insulation damage. It is noted that in a very good insulation system such as XLPE it may take several hours for polarization of the insulation to return to its original state. During this time the insulation resistance measurement may be significantly lower than the original measurement, however the minimum acceptable values of paragraph 5.6 are still applicable.
10 5.10 Insulation Condition Diagnostic Assessment For subtransmission and transmission cables, as well as distribution cables of strategic importance, the Asset Manager (via the Project Manager) may specify that additional testing is required prior to the cable being energised to provide a footprint for future management of the cable. Such tests may include Partial Discharge, Dielectric Dissipation Factor, Internal Relaxation Current, Polarisation Depolarisation Current, Oscillating Wave or other tests Final Checks Verify, if applicable, that the cable screen earthing has not shorted any frame leakage protection. Verify that single core cables do not have a continuous ferrous metallic path around them. This may be in the form of cable glands, cable clamps, or cable box entry. Trefoil clamping arrangement is preferred for single core cables. Verify that the cable screen is earthed at the correct end/s (for new distribution cables both ends will normally be earthed however this must be validated with the design). Confirm where the design requires one end only to be earthed that any control measures specified for hazardous voltages that may appear at the unearthed screen end under fault conditions are in place. Such control measures may be signage, insulation, surge diverters or personnel guards/barriers. If the cable has a separate metallic screen and outer metallic termite protection (brass tapes) then the brass tapes should be earthed at the same earth locations as the metallic screen. Verify that cable assembly has been completed eg surge diverters and/or voltage transformers reconnected, cable lugs securely bolted in place, insulating covers/boots/guards in place, switchgear reassembled. Verify that the cable number is clearly marked at both ends of the cable and the switchgear associated with the cable has an operational number/name clearly marked. Verify that cable box clearances meet or exceed the requirements of BS 0435:1984. Rated Voltage 12 kv 24 kv 36 kv Enclosure Type Phase to Phase clearance (mm) Phase to Earth clearance (mm) Fully Insulated Air Insulated 127 (184) 76 (160) Fully Insulated Air Insulated 242 (322) 140 (280) Fully Insulated Air Insulated 356 (437) 222 (380) For comparison, AS2067 clearances are shown in brackets and should be used where vermin entry or cable box contamination is possible Finalise Results For minor cables test results shall be approved by the workgroup supervisor or his delegate. For major cables the test results are to be approved by the Project Manager or his delegate before the cable is placed into service. In most cases this will be a delegated approval to the supervisor of the cable test team. A copy of the test results is to be sent to the Project Manager, and a copy retained by the work group carrying out the test. Additionally, a Check this is the latest Process Zone version before use. Page 10 of 12 Standard Work Practice SP0407 Ver 13
11 records copy of the test report SP0407C01 is to be ed to the Ergon address Cable Test Results. The filename of the test report should be the following format: Location_From_To_CableNumber_Date.doc where Location = geographic location eg Smith St From = source end of cable eg Mareeba Sub To = destination end of cable eg HVL12 Cable Number = unique cable ID (if allocated) Date = date of test yyyyymmdd eg These results will be subsequently filed at \\ecasd01\protection\test Data - (Test-Commissioning-Maintenance)\Region\Cable Tests\Town 5.13 Energise HV Cable It is preferred that a remote switching device is used to energise any new HV cables (including plant) for the first time. The earthfault protection operating time of the cable s protection system may be reduced during the initial cable energisation. Ensure the auto reclose on the feeder is blocked for the duration of the switching. The remote switching device for energising must have full fault make capabilities. It is envisaged that the remote switching device would be an RMU further upstream at a safe distance from the cable to be energised or a remotely controlled circuit breaker. Because not all minor HV Cables have to undergo an applied high voltage withstand test as per paragraph 5.8, and where the cable doesn t have to supply customer load within a 24 hour period the cable should be energised and left until supply is required. This will minimise loss of supply or damage should a fault develop Prior to loading the cable, a phase out must be completed. In a radial system, a phase rotation check must be used in lieu of a phase out. For minor HV Cables only that can t be remotely energised then the following additional measures shall be taken. Perform the high voltage withstand as per paragraph 5.8 and/or Confirm insulation resistance test was carried out and within tolerances Inspect cable terminations to ensure they are not damaged Ensure terminations are not porcelain or oil filled * Inspect switching device (e.g. ABS/HV Links) is operational Consider the effect of ferroresonance ** Close switch The Switching Operators Assistance will ensure that the switching device closes correctly. If the device doesn t function correctly DO NOT attempt to reopen. Comply with the requirements of P53 HV Switching and Access. * Caution If the terminations are porcelain or oil filled then the cable shall be energised remotely. If this is not possible then a voltage withstand test as per paragraph 5.8 shall be carried out. **Ferroresonance In power systems, the most common place to find ferroresonance is with a three phase distribution transformer energised through an underground cable of moderate length. Under no load, or very light load conditions, the capacitance of the cable is sufficient to precipitate ferroresonant behaviour under single phase switching conditions (e.g. the operation of an HV fuse or asynchronous operation of single phase 11kV switches such as a drop-out fuse unit.) The four most effective methods of controlling ferroresonance are: a) three-phase switching; Check this is the latest Process Zone version before use. Page 11 of 12 Standard Work Practice SP0407 Ver 13
12 b) single-phase switching at transformers; c) resistive load on the transformer; and d) limiting cable length. Methods (a) and (d) require action on the part of the system designer. Methods (b) and (c) require special operating procedures to ensure that there is effectively no length of cable being energised or deenergised at the same time as the transformer, or the presence of some load. supply is often provided by paralleling the low voltage network to adjoining substations. Should the LV network not be disconnected before HV switching, back energisation of the transformer would occur. Therefore this option is generally unavailable. Similarly on commissioning a transformer, there is usually no load available for this option to be used. Table1 Three-phase Switching The use of ganged three-phase switching is one of the most effective and commonly used methods of avoiding ferroresonance. Single Phase Switching at Transformers The practice of switching at the transformer terminals themselves is a particularly effective means of controlling ferroresonance. By doing this, the cable length between the transformer and the switch is essentially zero and the only possible capacitance in the network is that of the internal capacitance of the transformer. This is a particularly suitable method and can be applied in distribution systems using single-phase switchgear. Where a cable transformer combination is to be energised, the cable only should be energised and then the transformer. Conversely on de-energising, the transformer only should be de-energised first and then the cable. Both sets of switchgear can then be single phase operating. Since the critical cable length, which is actually proportional to the critical cable capacitance, is inversely proportional to the function of the square of the voltage, the critical capacitance for higher system voltages is quite small and the transformer capacitance can become significant. Refer Table 1 Resistive Load on the Transformer A resistive loading of 2 to 3% is generally sufficient to control ferroresonance. However in a distribution network, alternative Check this is the latest Process Zone version before use. Page 12 of 12 Standard Work Practice SP0407 Ver 13
CAPACITOR BANK TESTING SWP
1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.
ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV
1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled
DESCRIPTION DWG DESCRIPTION DWG
DESCRIPTION DWG DESCRIPTION DWG Ferroresonance 3451/1 3451/2 3451/3 Electro-magnetic Fields (EMF) 3462/1 HV & LV Insulators (Links) 3463/1 A ORIGINAL ISSUE B 14.07.09 APPROVED DATE J. Brooks 25.02.03 INDEX
Unified requirements for systems with voltages above 1 kv up to 15 kv
(1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to
SURGE PROTECTIVE DEVICES
SURGE PROTECTIVE DEVICES 1. INTRODUCTION In order to ensure safety of people, protection of equipment and, to a certain extent, continuity of supply, insulation co-ordination aims at reducing the likelihood
FAQs-Main switchboard design criteria
FAQs-Main switchboard design criteria Q: What is the Australian standard for main switchboards? Current Australian standard is AS/NZS 3439.1: 2002 originating from IEC 60439. The new series of standard
Electrical safety rules
Electrical safety rules 2015 DISCLAIMER The material contained in this publication has been developed for the use of ActewAGL, its contractors and all others working on or near ActewAGL s electricity
EARTHING AND BONDING AT SECONDARY SUBSTATIONS
DISTRIBUTION CONSTRUCTION MANUAL SECTION 4 - SUBSTATIONS ISSUE B SEPT 1996 4.4.4 EARTHING AND BONDING AT SECONDARY SUBSTATIONS 1 SCOPE This section of the Distribution Construction Manual lays down the
Code of Practice Electricity transmission and distribution asset management. February 2009
Code of Practice Electricity transmission and distribution asset management February 2009 CONTENTS 1 PREFACE...4 2 APPLICATION AND OBJECTIVES...5 3 SCOPE...6 4 DEFINITIONS...7 5 DESIGN AND CONSTRUCTION...11
12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting
12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.
Circuit Electrical Testing
Safe Isolation Procedure Circuit Electrical Testing Site Safety Management It is essential from the outset that effective management and control of the system, apparatus and equipment used on site is achieved
ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU
ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU George CURCANU, Constantin ILINCA, Ilie SBORA ICMET Craiova, Romania, Calea Bucuresti 144, phone:
Part 1 System Modeling & Studies for Existing Systems
Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures
TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta?
TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS What Is Tan δ, Or Tan Delta? Tan Delta, also called Loss Angle or Dissipation Factor testing, is a diagnostic method of testing
Trade of Electrician. Three-phase Distribution Boards And Socket Circuits
Trade of Electrician Standards Based Apprenticeship Three-phase Distribution Boards And Socket Circuits Phase 2 Module No. 2.3 Unit No. 2.3.2 COURSE NOTES Created by Charlie Walsh - Athlone TC Revision
CHECKING AND TESTING ELECTRICAL INSTALLING WORK
CHECKING AND TESTING ELECTRICAL INSTALLING WORK Department of Consumer and Employment Protection Energy Safety Preface It is a requirement of the Electricity (Licensing) Regulations 1991 that all electrical
3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance
SPECIFICATION FOR LOW VOLTAGE SWITCHBOARD SEN I N D E X Description 10 STANDARD TECHNICAL REQUIREMENTS 11 Standards 12 General Operating Conditions 13 General Description Of Switchboard 131 Structure 132
High Voltage Electrical Equipment Failure Diagnosis. Presented by: Spencer Tang & Terence Ng T&T Inspection & Engineering Sdn Bhd
High Voltage Electrical Equipment Failure Diagnosis Presented by: Spencer Tang & Terence Ng T&T Inspection & Engineering Sdn Bhd High Voltage Electrical Equipment Failure Diagnosis Definition of High Voltage
High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance
Annex I To Loughborough University (LU) Facilities Management (FM) Health and Safety Policy High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance 1. Introduction a. These Safety
A Practical Guide to Dielectric Testing
Chroma Systems Solutions, Inc. A Practical Guide to Dielectric Testing 19032 Series Electrical Safety Analyzer & 19050 Series Hipot Tester AC/DC/IR/SCAN Keywords: Dielectric tests, insulation resistance
DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)
DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DETAILS OF THE CLEINT Client and address ADDRESS OF THE INSTALLATION Installation
Work in Substations - General
Work in Substations - General Summary: This document supports the Power System Safety Rules and its requirements assembled under Work in Substations General Category 3 and apply to all persons working
ESP 120 M1, ESP 208 M1, ESP 240 M1, ESP 415 M1, ESP 277 M1, ESP 480 M1 and M1R variants. Installation instructions ESP M1/M1R mains protectors
ESP 120 M1, ESP 208 M1, ESP 240 M1, ESP 415 M1, ESP 277 M1, ESP 480 M1 and M1R variants Installation instructions Contents Key points of installation Before installation Installation Installation check
PowlVac Vacuum Integrity Tester
Instructions IB-60025B PowlVac Vacuum Integrity Tester POWELL ELECTRICAL MANUFACTURING COMPANY 8550 MOSLEY DRIVE HOUSTON, TEXAS 77075 USA PHONE (713) 944-6900 FAX (713) 947-4453 www.powellelectric.com
Reyrolle Protection Devices. 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy
Reyrolle Protection Devices 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy Siemens Protection Devices Limited 2 7PG17 XR101 & XR102 Intertripping Relay
WIRE AND CABLE ENGINEERING GUIDE
DC Hi Pot Testing Excerpt from PRYSMIAN S WIRE AND CABLE ENGINEERING GUIDE (FOR INFORMATIONAL PURPOSES ONLY) Page 1 of 6 DC HIGH POTENTIAL TESTING DC Hi-Pot testing can be applied as a withstand test (a
Two different types of cables are used in primary airfield lighting circuits: - unshielded cables and - shielded cables
Two different types of cables are used in primary airfield lighting circuits: - unshielded cables and - shielded cables Classically both cables have a single AWG 8 copper conductor or a cross section of
Exploring the Necessity of the Hot Hipot Test
Exploring the Necessity of the Hot Hipot Test Introduction In an industry comprised of workers with varying electronics knowledge, a Hipot test can seem a daunting task for some. Indeed, many test operators
MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING
Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star
MiCAFIL. 1 RIP Technology. Bushings. Z. Zic 09/2003
MiCAFIL 1 RIP Technology Z. Zic 09/2003 )XQFWLRQRI+LJK9ROWDJH%XVKLQJ Uncontrolled (natural) electrical field Capacity-controlled electrical field %XVKLQJV0DLQ,QVXODWLRQ6\VWHPV 7\SH 0DLQ,QVXODWLRQ +RXVLQJFRYHU
Arc Terminator Active Arc-Resistant Switchgear
Arc Terminator Active Arc-Resistant Switchgear Increasing safety and productivity by extinguishing internal arcing faults within the switchgear. The Square D Arc Terminator from Schneider Electric offers
Pressure monitoring equipment for oil-sf 6. bushings, type GOEK
Pressure monitoring equipment for oil-sf 6 bushings, type GOEK Installation and maintenance guide 5693 827-6 en, Rev. 3, 2002-01-30 This document must not be copied without our written permission, and
MEDIUM VOLTAGE SUBSTATION PRACTICES Medium Voltage (MV) is defined as: 1000V< MV 44kV
MEDIUM VOLTAGE SUBSTATION PRACTICES MEDIUM VOLTAGE SUBSTATION PRACTICES Medium Voltage (MV) is defined as: 1000V< MV 44kV MEDIUM VOLTAGE SUBSTATION PRACTICES This presentation covers some safety aspects
Network Standard Advice No. 1420C 9/6/2011
Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides
MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4
CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,
Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time
Trial Exams C Standards and Regulations Examination No: GH-08-C- This test is intended to gauge your knowledge of essential information contained within AS/CA S009:2013. To qualify for an allpication to
Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards
Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards Abstract This Guide is an informative listing of selected terms and definitions found in IEC Glossary entry
Release: 2. UEENEEJ194A Solve problems in low voltage refrigeration circuits
Release: 2 UEENEEJ194A Solve problems in low voltage refrigeration circuits UEENEEJ194A Solve problems in low voltage refrigeration circuits Modification History Not Applicable Unit Descriptor Unit Descriptor
Union County Public Schools. Facilities Department. Electrical. Safe Work Practices
1 Union County Public Schools Facilities Department Electrical Safe Work Practices 2 Purpose In accordance with OSHA Standards 1910.331-335, safety-related work practices shall be used by Union County
The Intelligent AX1 Switchgear for Medium Voltage
The Intelligent AX1 Switchgear for Medium Voltage Leif Lundin, Manager of Research and Development, Division Medium Voltage and Compact Substations, ABB Distribution, Sweden Abstract The newly launched
Hyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
Electrical safety code of practice 2013. Managing electrical risks in the workplace
Electrical safety code of practice 2013 Managing electrical risks in the workplace This Queensland code of practice has been approved by the Attorney-General and Minister for Justice and commences on 1
Electrical Practices for Construction Work
1. Purpose Electrical Practices for Construction Work The purpose of this Code is to provide practical guidance and set minimum safety requirements for electrical practices on all construction sites in
ScottishPower Distribution Cables & Equipment. Metal Theft
ScottishPower Distribution Cables & Equipment Metal Theft April 2012 As an aid to deterring to metal theft this booklet has been put together to help identify the types of utility power cables and associated
SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS
SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS Michael Hensel HIGHVOLT Prüftechnik Dresden GmbH 2 3 Content 1 Introduction Test parameters and their significance Differences
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components
Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education
This section applies to the design and installation of transformers.
ELECTRICAL: TRANSFORMERS BASIS OF DESIGN This section applies to the design and installation of transformers. Design Criteria 13.8-kV equipment shall be 15-kV class. Coordinate with short-circuit studies
Dielectric Withstand Testing in a Production Environment
Dielectric Withstand Testing in a Production Environment Performing a routine product safety test should not in itself represent a shock hazard to the operator who is conducting the test, yet anytime you
Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points
Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points Features SELV Compliant No Detection Passive Injector Gigabit Compatible Full Protection
Fault location on power cables. Fault location on power cables
Fault location on power cables Fault location on power cables Contents: 1. Introduction 2. Construction of power cables 3. Cable faults 01. Introduction Fault location on communication and power cables
CoDe of PRACtICe on electrical safety for work on or near high voltage electrical apparatus. the blue book
CoDe of PRACtICe on electrical safety for work on or near high voltage electrical apparatus the blue book VICtoRIA 2012 ISSUE SHEET Copy Number... CONTROLLED COPY UNCONTROLLED COPY Note: Uncontrolled copies
The Electrical Safety Regulation (pre and post 1 January 2014)
The Electrical Safety Regulation (pre and post 1 January 2014) The following table provides an overview comparison between the Electrical Safety Regulation 2002 (the ESR 2002) current as at 1 July 2013
Phase Attribute Identification using GPS Technology
Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits
INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23
INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 GUIDELINES FOR WORKING WITH PORTABLE POWER DISTRIBUTION SYSTEMS AND OTHER ELECTRICAL EQUIPMENT "ADDENDUM C" WORKING WITH 480 VOLT SYSTEMS
ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas
ENERGY NETWORKS ASSOCIATION Electricity Industry EMF Measurement Protocol for High Field Areas Contents 1 Introduction 1.1 Background 1.2 High Field Areas 2 High Field Area - Generation Businesses 2.1
Earthing Guidance Notes
Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head
Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.
Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the
Distribution Design Manual
1 6 DESIGN PARAMETERS 4 6.1 Glossary and Definitions 4 6.2 Standard Voltages and Frequency 5 6.2.1 Transmission 5 6.2.2 Subtransmission 6 6.2.3 MV Distribution 6 6.2.4 LV Distribution 7 6.3 Point of Supply
Specification for Cable Accessories, Termination and Jointing Materials for Underground Electrical Power Cables for Nominal System Voltage Up to 33kV
Ergon Energy Corporation Limited Specification for Cable Accessories, Termination and Jointing Materials for Underground Electrical Power Cables for Nominal System Voltage Up to 33kV Specification ETS
Model 1756 Test Lead Kit
Keithley Instruments 28775 Aurora Road Cleveland, Ohio 44139 1-888-KEITHLEY http://www.keithley.com Model 1756 Test Lead Kit Gerneral Purpose Test Lead Information Description These test leads allow you
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated
Lightning Arresters P30027 18 KVA P30038 10 KVA. Description & Installation
Lightning Arresters P30027 18 KVA P30038 10 KVA Description & Installation Printed in USA 09/11 TO330 Rev. B Table of Contents Page 1.0 SCOPE 2 2.0 PRODUCT OVERVIEW 2 2.1 Intended Uses 2 2.2 Lightning
DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS
MIOSHA-STD-1313 (10/15) 6 Pages For further information Ph: 517-284-7740 www.michigan.gov/mioshastandards DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS
Understanding Arc Flash
Understanding Arc Flash Presented by Eddie F. Jones, PE 1 2 3 4 5 Five to 10 arc flash explosions occur in electric equipment every day in the United States. This number does not include cases in which
Electrical Shore Connections / Cold Ironing
STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version
CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS
CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS Customer Handout Date Aug 2, 2010 Version 1.0 File Name Customer Requirements At Power Substations Document Id Outside Plant Engineering 1 Table Of Contents 1.0
Submit shop drawings for equipment provided under this section Shop drawings shall indicate:
Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,
Electrical Safety Tester Verification
Ensuring Validity of Regulatory Tests Verification of electrical safety testing equipment is a procedure that is often overlooked by manufacturers. Running test verification is crucial to ensuring that
Checklist Testing and inspection without interconnection
Shams Dubai Checklist Testing and inspection without interconnection Version.0 AUGUST 205 TABLE OF CONTENTS Scope...5. PV PLANT AND INSPECTION DATA... 6 2 TESTING EQUIPMENT...7 3 DOCUMENTS... 8 3. Reference
Aerial Fibre Optics. Complete One Stop Solution for Aerial Fibre Optics. OPGW Cable and Fittings for OPGW
Complete One Stop Solution for OPGW Cable and Fittings for OPGW 53, Justice Chandra Madhav Road, Kolkata - 700020. India. Phone: 91-33-24748575 / 7565 Fax: 91-33-2476-1955 Email: [email protected] Website:
AutoLink Three-Phase Sectionalizer Specifications. Scope. General. Applicable Standards. Operating principle
Scope This specification stipulates the minimum requirements for mechanically linked three-phase electronic sectionalizers, for use on outdoor medium voltage overhead lines of 15, 27, and 38 kv. Electronic
33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application
33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application Features Compliant with the IEEE802.3at Standard -40 to +60 C Temperature Range Diagnostic LEDs Full Protection
World Leader in HV Testing Technology
World Leader in HV Testing Technology Cable Fault Locators w/tdr Oil/Fluid Dielectric Testers Very Low Frequency AC Technology W/TD & PD Diagnostics Portable AC Hipots ---------------------------------
Test Before Touch Easier Said Than Done. Ken Crawford, DuPont Kent Haggerty, Dupont
Test Before Touch Easier Said Than Done Ken Crawford, DuPont Kent Haggerty, Dupont Overview Test Before Touch (TBT) Principles Key Learnings by One Company One Method for Performing a TBT Induced Voltages
Best Methods for Safe Hipot Testing
Best Methods for Safe Hipot Testing When working with electrical safety test equipment, instruments that output potentially dangerous voltages and currents, it is always important to regular review and
Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms
Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity
Insulation Resistance Testing of Low Voltage Cables in the Field
Insulation Resistance Testing of Low Voltage Cables in the Field Table of Contents 1. Background...3 1.1. Before Making Measurements...3 1.2. How to Apply the Temperature Correction Factor...4 1.2.1. Calculation...4
FAULT FINDING MANUAL. For Stamford AC Generators
FAULT FINDING MANUAL For Stamford AC Generators 1 SAFETY PRECAUTIONS Test procedures recommended in this manual assume that the reader is fully conversant with electrical safety principles, and is familiar
Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation
Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage
ICTCBL2065B Splice and terminate optical fibre cable for carriers and service providers
ICTCBL2065B Splice and terminate optical fibre cable for carriers and service providers Release 1 ICTCBL2065B Splice and terminate optical fibre cable for carriers and service providers Modification History
R.C.C.B. s two-pole LEXIC
87045 LIMOGES Cedex Telephone : (+33) 05 55 06 87 87 Fax : (+ 33) 05 55 06 88 88 R.C.C.B. s two-pole LEXIC 089 06/09/10/11/12/15/16/17/18/ 27/28/29/30/35, CONTENTS PAGES 1. Electrical and mechanical characteristics...
Power transformers. Special transformers Railway
Power transformers Special transformers Railway A leader in railway systems Our compact and low-weight transformers fully comply with the customer s specifications. The products are developed together
Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Acceptance Testing
Scopes of Work for Electrical Acceptance Testing Schneider Electric Services: life-cycle solutions for electrical distribution equipment Make the most of your energy SM Scopes of Work for Electrical Acceptance
ELECTRICAL PRACTICES FOR CONSTRUCTION WORK
CONTRACTOR S CHECKLIST ELECTRICAL PRACTICES FOR CONSTRUCTION WORK 2007 WorkCover. Watching out for you. New South Wales Government Disclaimer This publication contains information regarding occupational
HIGH VOLTAGE SHORE CONNECTION
Guide for High Voltage Shore Connection GUIDE FOR HIGH VOLTAGE SHORE CONNECTION NOVEMBER 2011 American Bureau of Shipping Incorporated by Act of Legislature of the State of New York 1862 Copyright 2011
Electrical Grounding. Appendix C
Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment
National Craft Assessment and Certification Program S P E C I F I C A T I O N S
National Craft Assessment and Certification Program S P E C I F I C A T I O N S INDUSTRIAL ELECTRICIAN V4 ELEC26_O4 Released September 2013 Focus Statement An Industrial Electrician must be able to interpret
The table below lists the symbols used on the Clamp and/or in this manual. Important Information. See manual.
i800 AC Current Clamp Instruction Sheet Introduction The i800 AC Current Clamp, the Clamp, has been designed for use with multimeters, recorders, power analyzers, safety testers, etc., for accurate non-intrusive
How To Test For Safety On A Power Cable
T H E M A G A Z I N E O F 7 x 2 4 E X C H A N G E I N T E R N AT I O N A L A Green Approach to Building a Superior Data Center S P R I N G 0 9 BUILD FOR TODAY. EXPAND ON DEMAND. Modularity in the data
3. TYPES OF SERVICE AVAILABLE. 3.1 Scope
3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service
Advantages of Fixed Circuit Breaker Switchgear
Advantages of Fixed Circuit Breaker Switchgear by Lionel Mackay, EDF Energy, and Mike Adams, Schneider Electric Ltd Introduction The purpose of this paper is to review the advantages of fixed circuit breaker
ARC FLASH CALCULATIONS & LABELING REQUIREMENTS
ARC FLASH CALCULATIONS & LABELING REQUIREMENTS Presented by: Edmund Elizalde EYP Mission Critical Facilities, Inc. Slides by: Lonnie Lindell SKM Systems Analysis, Inc. 1 Agenda NEC 110.16 NFPA 70E IEEE
Regulations for the Installation of Electrical Wiring, Electrical Equipment and Air Conditioning Equipment
Regulations for the Installation of Electrical Wiring, Electrical Equipment and Air Conditioning Equipment Qatar General Electricity & Water Corporation KAHRAMAA Customer Services Department State of Qatar
AC and DC Drive System Installation Information
Purpose This document contains the Parker SSD Drives recommendations for installing drive systems. These instructions must be followed for safe and reliable operation. Instructions CODES AND REGULATIONS
IRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
Project Name: Nortrax Section 26 41 00 Project No: 13-013 SURGE PROTECTION DEVICES Page 1
Page 1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General: Drawings and general provisions of the Contract, including General and Supplementary Conditions and Divisions 1 Specification sections apply to
Transformer Bushings for GIS
Transformer Bushings for GIS Oil to SF6 Connections GARIP RTKG 725-55 kv SQS certified ISO 91 / ISO 141 Bushings RIP - Technology for SF6 / Oil - Bushings In modern metal enclosed switchgear SF6 -gas is
ELECTRICAL SAFETY RISK ASSESSMENT
ELECTRICAL SAFETY RISK ASSESSMENT The intent of this procedure is to perform a risk assessment, which includes a review of the electrical hazards, the associated foreseeable tasks, and the protective measures
CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION
Page 1 of 11 ****This Standard Supercedes BECo CS2.13-2.3 & ComElectric OH Construction Manual, System Grounding Section, drawings CGND, GRDSUM, and C2**** 1.0 Bill of Materials GROUNDING AND BONDING POLE-MOUNTED
