1 RISK MITIGATION for ELECTRICAL WORK Feb 2013 San Diego CA
2 Agenda I. RISK Define the Risks Arc Flash Review II. MITIGATION 3 Easy Steps New Designs Vs. Existing Systems III. DUKE UNIVERSITY EXAMPLE
3 I. Risk Shock Arc Flash - Arc Blast Equipment Damage Unplanned Outage
4 II. Mitigation Understand the Hazard Have a Plan Know your System / Equipment
5 A. Arc Flash - Review IE = Incident Energy Variables: Fault Current & Time Overcurrent Detection Devices are typically Inverse More Current = Faster Operation Lower Currents = SLOW Operation Time is a much greater influence on Arc Flash Therefore - Lower Fault Current = Higher Arc Flash Hazard!
6 A. Calculated IE Example Available Primary Fault Current =12,000A Available Primary Fault Current = 13,700A %Z = 6.36 Secondary Fault Current = 22,700A Identical Settings %Z = 6.21 Secondary Fault Current = 24,400a Incident Energy = 580 cal/cm 2 Extremely Dangerous Motor Contribution = 3,300A Motor Contribution = 3,000A 480V Switchgear Incident Energy = 16 cal/cm 2 Workable with Adequate PPE
7 A. Trip Times Example CURRENT IN AMPERES 85% Arcing Current 11,030 Amps 100% Arcing Current 12,976 Amps Breaker Trips in 15.9s IE = 580 cal/cm CURRENT IN AMPERES 85% Arcing Current 11,739 Amps 100% Arcing Current 13,810 Ampus XAM - Phase TIME IN SECONDS XBM - Phase TIME IN SECONDS Breaker Trips in 0.33s IE = 16 cal/cm A A K 10K 100K 48XAM.tcc Ref. Voltage: 480V Current in Amps x K 10K 100K 48XBM.tcc Ref. Voltage: 480V Current in Amps x 1
8 B. Safety Plan 1) NFPA 70E & or NESC: a) Require a Task Hazard Assessment b) Require Arc Flash Analysis c) Require Interpretation
9 B. Interpretation Selection of Personal Protective Equipment When Required for Various Tasks. Where selected in lieu of the incident energy analysis of 130.5(B)(1), Table 130.7(C)(15)(a) and Table 130.7(C)(15)(b) shall be used to determine the hazard/risk category and requirements for use of rubber insulating gloves and insulated and insulating hand tools for a task. The assumed maximum short-circuit current capacities and maximum fault clearing times for various tasks are listed in Table 130.7(C)(15)(a). For tasks not listed, or for power systems with greater than the assumed maximum short-circuit current capacity or with longer than the assumed maximum fault clearing times, an incident energy analysis shall be required in accordance with
10 B. Interpretation Choose Wisely: The collective experience of the task group is that, in most cases, closed doors do not provide enough protection to eliminate the need for PPE for instances where the state of the equipment is known to readily change (for example, doors open or closed, rack in or rack out). It is the collective experience of the Technical Committee on Electrical Safety in the Workplace that normal operation of enclosed electrical equipment, operating at 600 volts or less, that has been properly installed and maintained by qualified persons is not likely to expose the employee to an electrical hazard.
11 B. Interpretation Relationships with Contractors (Outside Service Personnel, and So Forth). (A) Host Employer Responsibilities. (1) The host employer shall inform contract employers of the following: a. Known hazards that are covered by this standard, that are related to the contract employer s work, and that might not be recognized by the contract employer or its employees b. Information about the employer s installation that the contract employer needs to make the assessments required by Chapter 1
12 B. Interpretation Parallel Sources vs. Closed Transition 100mS or Less AHJ determination N E
13 C. Know Your System 1. Up to Date Documentation User friendly Accurate Accessible 2. Existing Conditions Age / Condition Factor Interpret the Standards Asses Existing Conditions
14 C. Know Your System 27MW Combustion Turbine Generator Multiple Sources On-Line LOTO / Isolation Emergency Only 2.5MW Emergency Generator Designed to Keep the Power On
15 C. Documentation User Friendly / Accessible / Accurate IF REQUIRED IF REQUIRED SUBSTATION EQUIPMENT - BUILDING - LETTER NUMERIC NUMBER DESCRIPTOR NUMBER IDENTIFIER IDENTIFIER 1,2,3,4,5, EXAMPLES TX, SW, PMH, ,7549, - A,B,C, 1,2,3, 1 TX A 1 F A 3 1 PMH B
16 C. Existing Conditions Interlocking No Instantaneous Function Longer Clearing Times Ventilated Enclosures Adequate PM?
17 C. Pad Transformer Door Interlock ANSI C57.12
18 C. Existing Equipment
19 III. Duke University Comprehensive Safety Plan Excellent Documentation Thorough Analysis
20 The End Conclusions Understand the Hazards = Assessment & Studies Have a Plan = Adopt & Interpret Know your System = User Friendly, Accurate, Accessible Documentation Questions? Comments? Constructive Criticism?
Choosing the Best Solution for Reducing Arc Energy
CONVENTION SESSION HANDOUT Choosing the Best Solution for Reducing Arc Energy Terry L. Schiazza, Business Development Manager Square D / Schneider Electric SESSION #11 Independent Electrical Contractors
Arc Flash Hazards. Electrical Hazards. Dan Neeser Field Application Engineer [email protected]. Electrical Hazards 2/18/2015. Shock.
Arc Flash Hazards Dan Neeser Field Application Engineer [email protected] Electrical Hazards Electrical Hazards Shock Arc Flash Arc Blast 2 1 Arcing Fault Basics 35,000 F Radiant Heat & UV Speed of
ARC FLASH CALCULATIONS & LABELING REQUIREMENTS
ARC FLASH CALCULATIONS & LABELING REQUIREMENTS Presented by: Edmund Elizalde EYP Mission Critical Facilities, Inc. Slides by: Lonnie Lindell SKM Systems Analysis, Inc. 1 Agenda NEC 110.16 NFPA 70E IEEE
NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers
NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers A market position paper from the experts in Business-Critical Continuity TM Executive Summary Electrocutions are the fourth
Technical Guide. SKM Arc Flash Line Side vs. Load Side
SKM Arc Flash Line vs. Load The option of choosing the line-side or the load-side arc flash incident energy for arc flash labels is an important decision when performing an arc flash hazard analysis. When
Arc Flash Mitigation. Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear.
Arc Flash Mitigation Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear. Distance is Safety We will discuss through examples of actual occurrences and possible
INTRODUCTION ARC FLASH PROTECTION AND SAFETY MEASURES. September 2010
ARC FLASH PROTECTION AND SAFETY MEASURES September 2010 Introduction Hazards of Electrical Energy Electrical Safety Program Safety-Related Work Practices Electrical Safety Procedures Presented By: Ken
BRANDON AND CLARK INC. // SCOTT W. CLARK, P.E. ELECTRICAL CONTINUING EDUCATION ARC FLASH - NFPA 70E
BRANDON AND CLARK INC. // SCOTT W. CLARK, P.E. ELECTRICAL CONTINUING EDUCATION ARC FLASH - NFPA 70E Training is not a substitute for following corporate safety guidelines. Always refer to the latest safety
Roadmap to Compliance with NFPA 70E Arc Flash Requirements
Roadmap to Compliance with NFPA 70E Arc Flash Requirements TAHFM Interlink 2015 March 30, 2015 Antony Parsons, Ph.D., P.E. Schneider Electric Engineering Services 1 2 How do we get to Reliable Power? >
Understanding Arc Flash
Understanding Arc Flash Presented by Eddie F. Jones, PE 1 2 3 4 5 Five to 10 arc flash explosions occur in electric equipment every day in the United States. This number does not include cases in which
Part 1 System Modeling & Studies for Existing Systems
Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures
IMPLEMENTING THE NEW ELECTRICAL SAFETY REQUIREMENTS
IMPLEMENTING THE NEW ELECTRICAL SAFETY REQUIREMENTS Paul A Zoubek, CSP, CIH Occupational Services, Inc. San Diego, CA 619-861 861-0612 [email protected] OCCUPATIONAL SERVICES, INC. BACKGROUND Update Update
Safety By Design. Strategies for Electrical Contractors
Safety By Design Strategies for Electrical Contractors Introduction Engineering and system design significantly impact worker safety System design provides opportunity to eliminate/minimize workers exposure
misconceptions about arc-flash hazard assessments
misconceptions about arc-flash hazard assessments There are some common misconceptions about Arc-Flash Hazard Assessments which reduce the effectiveness of the Assessments and can increase electrical hazards.
Low Voltage Switchgear
Arc Resistant Switchgear n Insulated and isolated bus n Separation barriers and top venting n Breaker shutters 12 SWITCHGEAR Arc resistant metal-enclosed low voltage switchgear is an optional product offering
OSHA & ARC FLASH HAZARD ANALYSIS
OSHA & ARC FLASH HAZARD ANALYSIS Impact of Revisions to the OSHA Electrical Safety Regulations Presented by: John J. Kolak, MS, CSP Introduction Important Definitions Understanding OSHA Applicable standards
Arc Flash Mitigation & Selective Co-ordination
Arc Flash Mitigation & Selective Co-ordination Michael Hodder March 2015 Overview This seminar will provide information on: Mitigating arc flash hazards Selective Coordination What can we do to make these
ARC FLASH HAZARD OVERVIEW. Presented August 13, 2015 WWOA Lake Michigan District by Mead & Hunt, Inc.
ARC FLASH HAZARD OVERVIEW Presented August 13, 2015 WWOA Lake Michigan District by Mead & Hunt, Inc. ARC FLASH EXPERIENCE Christopher J. DeWaal, MS, MEM, PE, LEED AP, HACCP How did I get involved? A client
Understanding 2015 Changes to NFPA 70E Safety-related work practices and maintenance requirements mandate more robust electrical safety programs for
Understanding 2015 Changes to NFPA 70E Safety-related work practices and maintenance requirements mandate more robust electrical safety programs for data centers Executive Summary Every three years, the
ELECTRICAL SAFETY RISK ASSESSMENT
ELECTRICAL SAFETY RISK ASSESSMENT The intent of this procedure is to perform a risk assessment, which includes a review of the electrical hazards, the associated foreseeable tasks, and the protective measures
ARC FLASH HAZARD MITIGATION. Industrial Tests, Inc. [indtests.com]
ARC FLASH HAZARD MITIGATION ARC FLASH HAZARD MITIGATION NWHA TECHNICAL SEMINAR May 17, 2012 Richard D Reese Power Systems Manager Industrial Tests, Inc. Rocklin, California [[email protected]; 916-660-2837]
What s up with Arc Flash?
What s up with Arc Flash? Presented by Mark Haskins, CSP Practical Safety Solutions, LLC CONN OSHA Breakfast Roundtable February 18, 2014 2014 Practical Safety Solutions, LLC What is Arc Flash? Definition
2012 NFPA 70E. Ten Most Important Changes. John A. DeDad
2012 NFPA 70E Ten Most Important Changes John A. DeDad GE Energy Management 41 Woodford Avenue Plainville, CT 06062 USA 860-747-7344 [email protected] Abstract The 2012 Edition of NFPA 70E, Standard for
2008 Eaton Corporation. All rights reserved.
FlashGard TM Motor Control Center Electrical Safety Hazards Design Philosophy The Product 2008 Eaton Corporation. All rights reserved. Research studies say. Five to 10 arc flash explosions occur in electrical
HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE
Appendix B-2 - Electrical Safety In Design Final Report TECHNOLOGIES THAT REDUCE LIKELIHOOD OF INJURY FROM ELECTRICAL HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE The following are technologies that reduce
NFPA 70E Updates Affect Your Most Valuable Assets
NFPA 70E Updates Affect Your Most Valuable Assets EXECUTIVE SUMMARY Electrocution is a well-known hazard associated with direct contact with electrical energy. According to the U.S. Department of Labor,
Introduction to Arc Flash
Introduction to Arc Flash Worker Training of Electrical Hazards Including Arc Flash SH-16614-7 This material was produced under grant number SH-16614-7 from the Occupational Safety and Health Administration,
How to reduce exposure to arc flash hazards
GE Energy Industrial Solutions How to reduce exposure to arc flash hazards Multiple solutions for new and existing facilities imagination at work Multiple Issues Today s power system engineer must not
The Other Hazard of Electricity. Larren Elliott Ph.D. Lindsay Polic, CSP, REHS
The Other Hazard of Electricity Larren Elliott Ph.D. Lindsay Polic, CSP, REHS Presenters Larren Elliott Ph.D. EORM Electrical Safety Service Partner 45 years practical and hands-on industrial experience
4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS
4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS for DATA CENTERS Michael Mosman, PE Chief Technical Officer CCG Facilities Integration Incorporated FACILITIES INTEGRATION INCORPORATED MEDIUM VOLTAGE
Protection Considerations to Mitigate Arc-Flash Hazards
1 Protection Considerations to Mitigate Arc-Flash Hazards echnical Report to the Substation Subcommittee of the Power Systems Relaying Committee Working Group: Chair: K. Zimmerman, Vice Chair: R.A. Hedding,
Electrical Safety Program
California State University-Fullerton 800 N. State College Blvd. Fullerton, CA 92831 Prepared by: Paul A Zoubek, CSP, CIH President/Principal Consultant Zoubek Consulting, LLC 3737 Granada Ave. San Diego,
A USERS GUIDE TO ARC RESISTANT LOW VOLTAGE SWITCHGEAR & MOTOR CONTROL ANALYTICAL COMPARISON VS ARC FLASH TEST RESULTS
A USERS GUIDE TO ARC RESISTANT LOW VOLTAGE SWITCHGEAR & MOTOR CONTROL ANALYTICAL COMPARISON VS ARC FLASH TEST RESULTS By: Gabriel Arce, ABB, San Luis Potosi, Mexico Casey McCollum, ABB, Houston, TX John
How to Build a Safe and Effective Electrical Maintenance Program
How to Build a Safe and Effective Electrical Maintenance Program The Business Case Ask Yourself the Following Questions: What is your dependence on electrical energy and control systems? What are the consequences
Power-Zone 4 Arc Resistant Low Voltage Switchgear
Power-Zone 4 Arc Resistant Low Voltage Switchgear with ArcBlok Technology Make the most of your energy SM Workplace safety 2 I Power-Zone 4 Arc Resistant Low Voltage Switchgear Five to ten arc flash explosions
MEDIUM VOLTAGE. Michael Mosman, PE. CCG Facilities Integration Incorporated FACILITIES INTEGRATION INCORPORATED
MEDIUM VOLTAGE ELECTRICAL SYSTEMS for DATA CENTERS Michael Mosman, PE Chief Technical Officer CCG Facilities Integration Incorporated FACILITIES INTEGRATION INCORPORATED CCG Facilities Integration Incorporated
Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services
Circuit Breakers and Switchgear Thomas Greer Director of Engineering TLG Services Presentation Outline Switchgear Definition Overcurrent Protection Devices Circuit Breaker Trip Curves and Coordination
Arc Flash Avoidance and its Application to Overhead Traveling Cranes
Arc Flash Avoidance and its Application to Overhead Traveling Cranes Whitepaper August 2012 Jason Wellnitz, Controls Product Manager Material Handling Numerous technical papers, bulletins, magazine articles
Arc Flash Energy Mitigation Techniques
Arc Flash Energy Mitigation Techniques When short circuits occur on an electrical distribution system, an arc flash event usually forms. These arc flash events can cause dangerous and potentially fatal
Written Program ELECTRICAL SAFETY. Based on OSHA Subpart S and NFPA 70E Standards
Written Program ELECTRICAL SAFETY Based on OSHA Subpart S and NFPA 70E Standards Revised November 2012 Disclaimer The presentations and program provided by Workplace Safety Solutions, Inc. are based on
SAFE ELECTRICAL WORK PRACTICES & 2015 NFPA 70E
SAFE ELECTRICAL WORK PRACTICES & 2015 NFPA 70E This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description of the program
Extend the Life of Existing Switchgear
Extend the Life of Existing Switchgear January 2011/1910DB1002 by Hal Theobald, Product Manager Schneider Electric USA, Inc. Make the most of your energy SM Summary Introduction... p 3 Maintenance Requirements...
Arc Flash Safety in 400V Data Centers
Arc Flash Safety in 400V Data Centers Strategies for protecting employees from underappreciated yet potentially deadly hazards By Dave G. Loucks PCM Solution Manager Eaton Corporation Executive summary
MEDIUM VOLTAGE SUBSTATION PRACTICES Medium Voltage (MV) is defined as: 1000V< MV 44kV
MEDIUM VOLTAGE SUBSTATION PRACTICES MEDIUM VOLTAGE SUBSTATION PRACTICES Medium Voltage (MV) is defined as: 1000V< MV 44kV MEDIUM VOLTAGE SUBSTATION PRACTICES This presentation covers some safety aspects
FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid
Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars Presented By: Greg Pelster & Robert Schmid FFI Ferrie, Franzmann Industries LOW VOLTAGE SWITCHGEAR & LOW VOLTAGE
New standardized approach to arc flash protection
New standardized approach to arc flash protection Samuel Dahl Juha Arvola Tero Virtala Arcteq Relays Ltd Arcteq Relays Ltd Arcteq Relays Ltd Wolffintie 36 F 11 Wolffintie 36 F 11 Wolffintie 36 F11 65200
Demystifying arc flash hazard management
Demystifying arc flash hazard management Presented by Matt Brazier Senior Electrical Engineer Gove Operations November 2013 Standard NFPA 70E IEEE 1584 AS/NZS 4836 TERMINOLOGY Arc arc flash hazard analysis
! WARNING Arc Flash and Shock Hazard Appropriate PPE Required
Arc Flash Hazard Labeling Do s and Don ts! WARNING Arc Flash and Shock Hazard Appropriate PPE Required 11' - 3" Flash Hazard Boundary 9 cal/cm2 Flash Hazard at 18 inches #3 PPE Level Cotton underwear plus
A Guide to Performing An Arc Flash Hazard Assessment Using Power Analysis Software
A Guide to Performing An Arc Flash Hazard Assessment Using Power Analysis Software Abstract: The nature of explosive equipment failures, and the rate of serious burn injuries in the electrical industry
SALISBURY ASSESSMENT SOLUTIONS
SALISBURY ASSESSMENT SOLUTIONS Electrical engineering services for a safe and compliant workplace Electrical Safety Program Assessments - Electrical Safety Training Arc Flash Risk Assessments - Power Systems
Analyzing Electrical Hazards in the Workplace
Analyzing Electrical Hazards in the Workplace By Dennis K. Neitzel, CPE AVO Training Institute, Inc. The need for analyzing electrical hazards in the workplace has been recognized by a small segment of
OSHA and NFPA 70 Understanding NFPA 70 and its Implications in Electrical Inspections 2010
OSHA and NFPA 70 Understanding NFPA 70 and its Implications in Electrical Inspections 2010 By: Martin Robinson, Level III Thermographer 18-1030-0005 Rev. A The National Fire Protection Association (NFPA)
Common Electrical Hazards in the Workplace Including Arc Flash. Presented by Ken Cohen, PhD, PE & CIH (Ret.)
Common Electrical Hazards in the Workplace Including Arc Flash Presented by Ken Cohen, PhD, PE & CIH (Ret.) 1 What s New In February 1972, OSHA incorporated the 1971 edition of the National Fire Protection
Short-circuit, Protective Device Coordination & Arc Flash Analysis. By Albert Marroquin Operation Technology, Inc.
Short-circuit, Protective Device Coordination & Arc Flash Analysis By Albert Marroquin Operation Technology, Inc. Agenda Short-circuit Calculations for Arc Flash Analysis Protection and Coordination Principles
CIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS
CIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS David D. Roybal, P.E. Senior Member, IEEE Eaton Electrical 3697 Mount Diablo Boulevard Lafayette, CA 94549 Abstract Low-voltage circuit
Fusible Disconnect Switch
Circuit Breakers Circuit breakers are used in panelboards and switchboards to provide circuit protection and provide a means of energizing and de-energizing a circuit. Siemens Sentron molded case circuit
Bypass transfer switch mechanisms
Power topic #6013 Technical information from Cummins Power Generation transfer switch mechanisms > White paper By Gary Olson, Director, Power Systems Development This paper describes the configuration
Switchgear and Metal-Enclosed Bus
Section 18 Switchgear and Metal-Enclosed Bus 180. SWITCHGEAR ASSEMBLIES 180A. General Requirements for All Switchgear. This rule covers general requirements for all switchgear. Examples of switchgear found
Implementation of arc flash mitigating solutions at industrial manufacturing facilities
Thought leadership White paper Implementation of arc flash mitigating solutions at industrial manufacturing facilities David B. Durocher Senior Member, IEEE Global Industry Manager Eaton 26850 SW Kinsman
Enhancing Personnel Safety with Arc Resistant Equipment
Enhancing Personnel Safety with Arc Resistant Equipment Carl Christian Power LV Offer Marketing Nashville, TN Sponsored by the Water Wastewater Competency Center 1 Enhancing Personnel Safety 5-10 Five
Integrating SPDs in Switchgear & Switchboards Causes More Problems than it Solves
Integrating SPDs in Switchgear & Switchboards Causes More Problems than it Solves White Paper July 2010 Integrating surge protective devices (SPD) into distribution equipment (i.e. switchgear, switchboards,
Arc Flash Mitigation. Executive summary. by Antony Parsons, Ph.D., P.E.
by Antony Parsons, Ph.D., P.E. Executive summary Arc flash events can result in significant injury to workers, including severe burn injuries. The most effective arc flash safety programs are not those
Mitigation of Arc-Flash Hazards and Reduction of Costs by Selective Arc-Flash Protection
Mitigation of Arc-Flash Hazards and Reduction of Costs by Selective Arc-Flash Protection L. Kumpulainen, S. Dahl J. Ma Vamp Ltd, Finland Vamp Ltd, China 1 ABSTRACT This paper describes causes and characteristics
Common Sense and Knowledge Approach to Electrical Safety
Common Sense and Knowledge Approach to Electrical Safety L. Bruce McClung Distinguished Lecturer on Electrical Safety Issues for IEEE-IAS/PES 2002-03 3/30/2004 1 For IEEE-Brazil Section in Guararema -
Management Systems 10 Electrical Safety Audit 14 PPE 20 Arc Mitigation 22 Hazard Assessment 26
Management Systems 10 Electrical Safety Audit 14 PPE 20 Arc Mitigation 22 Hazard Assessment 26 Assessing The Hazards Of High and Low Voltage Single-Phase Arc-Flash By Albert Marroquin One common question
2004 TRANSMISSION SYSTEMS SEMINAR MEDIUM VOLTAGE, METAL-CLAD ARC RESISTANT SWITCHGEAR: ENHANCING WORKPLACE SAFETY
2004 TRANSMISSION SYSTEMS SEMINAR MEDIUM VOLTAGE, METAL-CLAD ARC RESISTANT SWITCHGEAR: ENHANCING WORKPLACE SAFETY Thomas P. McNamara, P.E. Manager, Development Engineering ABB Inc. Power Technologies Medium
Engineering innovation
Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems
Electrical Safety in the Marine Environment
January 3, 2001 TEHNIAL BULLETIN 010 Electrical Safety in the Marine Environment Approach Boundaries Electrical Safety in the Marine Environment presented by adick orporation 1 Overview Electrical power
What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin?
What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin? Comparing apples-to-apples bids Plant Services Special Report A shock hazard analysis should be included as part of an arc
Union County Public Schools. Facilities Department. Electrical. Safe Work Practices
1 Union County Public Schools Facilities Department Electrical Safe Work Practices 2 Purpose In accordance with OSHA Standards 1910.331-335, safety-related work practices shall be used by Union County
Submit shop drawings for equipment provided under this section Shop drawings shall indicate:
Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,
Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600
Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600 Data Bulletin 0600DB1104 03/2012 Retain for future use. Electronic Trip Circuit Breaker Basics 0600DB1104 Table of Contents
Journeyman Class Schedule
Journeyman Class Schedule San Diego Electrical Training Center Spring 2016 semester 4675 Viewridge Avenue Vol. 2016-1 tri-annual San Diego, CA 92123-1644 The classes listed in this schedule are designed
Atlanta Chapter IEEE Industry Applications Society
Atlanta Chapter IEEE Industry Applications Society Electrical Equipment Room Design Considerations presented at the Sheraton Buckhead Hotel Atlanta, Georgia November 20, 2006 Outline 1. Definitions 2.
Electrical Safety Program
CALIFORNIA STATE UNIVERSITY, STANISLAUS Electrical Safety Program LAST UPDATED 6/2/11 CALIFORNIA STATE UNIVERSITY, STANISLAUS ELECTRICAL SAFETY PROGRAM TABLE OF CONTENTS 1.0 Purpose......2 2.0 Scope......2
NFPA 70E: What Contractors and Employers Need to Know
2014 NFPA Conference & Expo NFPA 70E: What Contractors and Employers Need to Know Presented by: Michael J. Johnston Execu
OSHA Published First-Ever Arc Flash Protection Requirements for the Electric Power Industry Significant changes and unprecedented compliance
OSHA Published First-Ever Arc Flash Protection Requirements for the Electric Power Industry Significant changes and unprecedented compliance deadlines require high-voltage facilities to take immediate
What are the basic electrical safety issues and remedies in solar photovoltaic installations?
What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic
Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services.
Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services. Spending too much time and money on equipment maintenance? Square D Services: Your source for circuit breaker
ARC Flash Boundary & NFPA-70E Requirements PPE Program
ARC Flash Boundary & NFPA-70E Requirements PPE Program 1. Purpose and Scope The Arc Flash Boundary - PPE Program was developed to minimize the risk to AMS employees from safety and health hazards in the
Campus Safety Procedure Electrical Safety
Campus Safety Procedure Electrical Safety Electrical Safety Procedures 1.0 Purpose The purpose of this procedure is to provide guidance in the performance of work on electrical systems, wiring, and equipment
Job Site Electrical Safety A Matter of Life and Death
Job Site Electrical Safety A Matter of Life and Death Scott Forsyth, PE Senior Engineer Johnson Controls Performing the Job Right and on Time is Top Priority!!!! Right? Wrong!!!! Performing the Job Safely
PROCEDURES FOR SAFE WORKING AND TESTING OF ENERGIZED ELECTRICAL EQUIPMENT
Human Resources Support Services Health, Wellness and Safety PROCEDURES FOR SAFE WORKING AND TESTING OF ENERGIZED ELECTRICAL EQUIPMENT 1 SCOPE The electrical safety procedure shall be part of the Peel
ELECTRICAL SAFETY PROGRAM
ELECTRICAL SAFETY PROGRAM Adopted January 2014 Table of Contents Chapter 1: Introduction... 1 1.1 Purpose... 1 1.2 Scope... 1 1.3 Definitions... 1 1.4 Responsibilities... 8 1.5 Basic Electrical Safety
100% Rule Alternate Method Arc Blast Arc Flash Approved Approved Equipment Authority Having Jurisdiction (AHJ) Authorized Work Bare Hand Work
Definitions 100% Rule Work on or near energized parts must be performed only after all participating qualified electrical workers are in 100% agreement on the work to be completed, on the sequence in which
Electrical Safety Program. Electrical Safety Program Audit (Appendix: X) Performed By: Date:
Performed By: Date: The following sets of audit questions can be used to validate and verify that the is understood and being properly applied. Any non-compliant issues will be identified and prioritized
Electrical Predictive and Preventative Maintenance
Electrical Predictive and Preventative Maintenance Electrical and mechanical equipment is subject to failure at the worst possible time for no apparent reason. - Mose Ramieh III There are two types
Unified requirements for systems with voltages above 1 kv up to 15 kv
(1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to
SALISBURY ASSESSMENT SOLUTIONS
SALISBURY ASSESSMENT SOLUTIONS Electrical engineering services for a safe and compliant workplace Electrical Safety Program Assessment - Safety Training Arc Flash Hazard Analysis - Power Systems Engineering
Cal/OSHA Guide to. Electrical Safety. Cal/OSHA Consultation Service Research and Education Division of Occupational Safety and Health
Cal/OSHA Guide to Electrical Safety Research and Education Division of Occupational Safety and Health This guide is not meant to be either a substitute for or a legal interpretation of the occupational