Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Acceptance Testing

Size: px
Start display at page:

Download "Schneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Acceptance Testing"

Transcription

1 Scopes of Work for Electrical Acceptance Testing Schneider Electric Services: life-cycle solutions for electrical distribution equipment Make the most of your energy SM

2 Scopes of Work for Electrical Acceptance Testing: TABLE OF CONTENTS Bulletin No. 1910DB1302 TABLE OF CONTENTS SECTION 1 INTRODUCTION...4 SECTION 2 GENERAL REQUIREMENTS...5 SECTION 3 AC DRIVES...6 SECTION 4 AIR SWITCHES: LOW VOLTAGE...8 SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED...10 SECTION 6 AIR SWITCHES: HIGH AND MEDIUM VOLTAGE, OPEN STYLE...12 SECTION 7 SWITCHES: HVL/cc...13 SECTION 8 METERING DEVICES...15 SECTION 9 BUSWAYS, METAL- ENCLOSED...16 SECTION 10 OUTDOOR / SUBSTATION BUS...17 SECTION 11 CABLES: LOW VOLTAGE...18 SECTION 12 CABLES: MEDIUM VOLTAGE...19 SECTION 13 CAPACITORS: POWER FACTOR CORRECTION...20 SECTION 14 CIRCUIT BREAKERS: LOW VOLTAGE INSULATED CASE/ MOLDED CASE...21 SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13)...23 SECTION 16 CIRCUIT BREAKERS: MEDIUM VOLTAGE SF SECTION 17 CIRCUIT BREAKERS: MEDIUM VOLTAGE VACUUM...27 SECTION 18 DIRECT CURRENT SYSTEMS: BATTERIES AND CHARGERS...29 SECTION 19 EMERGENCY SYSTEMS: AUTOMATIC TRANSFER SWITCHES...30 SECTION 20 GROUND-FAULT PROTECTION SYSTEMS...32 SECTION 21 GROUND RESISTORS...34 SECTION 22 GROUNDING SYSTEMS...35 SECTION 23 ISOLATED POWER SYSTEMS...36 SECTION 24 MOTOR CONTROL CENTERS: LOW AND MEDIUM VOLTAGE...38 SECTION 25 MOTOR STARTERS: LOW VOLTAGE...41 SECTION 26 MOTOR STARTERS: MEDIUM VOLTAGE...42 SECTION 27 PROTECTIVE RELAYS...44 SECTION 28 STEP VOLTAGE REGULATORS...45 SECTION 29 SURGE ARRESTERS: LOW VOLTAGE SURGE PROTECTION DEVICES...47 SECTION 30 SURGE ARRESTERS: MEDIUM AND HIGH VOLTAGE SURGE PROTECTION DEVICES...48 SECTION 31 SWITCHGEAR AND SWITCHBOARD ASSEMBLIES: LOW AND MEDIUM VOLTAGE...49 SECTION 32 SWITCHGEAR DVCAS SECTION 33 TRANSFORMERS: DRY TYPE: ALL VOLTAGES - LARGE (GREATER THAN 167 SINGLE-PHASE AND 500KVA THREE-PHASE) Schneider Electric All Rights Reserved

3 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: TABLE OF CONTENTS TABLE OF CONTENTS SECTION 34 TRANSFORMERS: DRY TYPE - SMALL (167KVA SINGLE-PHASE, 500KVA THREE-PHASE, AND SMALLER)...54 SECTION 35 TRANSFORMERS, INSTRUMENT...55 SECTION 36 TRANSFORMERS: LIQUID-FILLED: ALL VOLTAGES...57 SECTION XX FUTURE SECTION XX FUTURE LIST OF TABLES TABLE: Insulation Resistance Test Values Electrical Apparatus and Systems...59 TABLE: Switchgear Withstand Test Voltages...60 TABLE: Recommended Dissipation Factor/Power Factor at 20 C Liquid-Filled Transformers, Regulators, and Reactors Acceptance Test Values...61 TABLE: Insulating Fluid Limits...62 TABLE: Transformer Insulation Resistance Acceptance Testing...64 TABLE: Medium-Voltage Cables Acceptance Test Values...65 TABLE: Inverse Time Trip Test at 300% of Rated Continuous Current of Circuit Breaker Molded-Case Circuit Breakers...68 TABLE: Instantaneous Trip Tolerances for Field Testing of Circuit Breakers...69 TABLE: Instrument Transformer Dielectric Tests Field Acceptance...70 TABLE: Maximum Allowable Vibration Amplitude...71 TABLE: RESERVED...72 TABLE: Bolt-Torque Values for Electrical Connections...73 TABLE: SF6 Gas Tests...76 TABLE: Insulation Resistance Conversion Factors (20 C)...77 TABLE: High-Potential Test Voltage Automatic Circuit Reclosers...79 TABLE: High-Potential Test Voltage for Acceptance Testing of Line Sectionalizers...80 TABLE: Dielectric Withstand Test Voltages Metal-Enclosed Bus...81 TABLE: Thermographic Survey Suggested Actions Based on Temperature Rise...82 TABLE: Dielectric Withstand Test Voltages Electrical Apparatus Other than Inductive Equipment...83 TABLE: Rated Control Voltages and their Ranges for Circuit Breakers...84 TABLE: Accuracy of IEC Class TP Current Transformers Error Limit...86 TABLE: Minimum Radii for Power Cable Single & Multiple Conductor Cables with Interlocked Armor, Smooth or Corrugated Aluminum Sheath or Lead Sheath...87 TABLE: Recommended Torque Values for Field Installed Wiring, Bus and Cable Connetions...88 TABLE: Maximum Micro-Ohms Per Pole...90 TABLE: Maximum Micro-Ohms Per Pole...91 TABLE: Maximum Micro-Ohms Per Pole...91 TABLE: Type DS, DSII, DSL, and DSLII Circuit Breaker Schneider Electric All Rights Reserved 3

4 Scopes of Work for Electrical Acceptance Testing: SECTION 1 INTRODUCTION Bulletin No. 1910DB1302 SECTION 1 INTRODUCTION This bulletin details the inspection and testing procedures that Schneider Electric Services technicians follow while performing acceptance testing of electrical equipment. These inspections and tests are performed on new equipment, after installation and prior to energizing, in order to: 1. Check that the equipment has not been damaged during shipment or installation; 2. Verify that the equipment is in compliance with the purchase specification and design intent; and 3. Document test results that can serve as benchmarks for future tests. The standard deliverables to the customer are those services described in the each section of these procedures and titled Visual and Mechanical Inspection and Electrical Tests. Optional Tests will only be performed by Schneider Electric technicians when specified on the customer s purchase order and subsequent field service work order. For testing of equipment not detailed in this document, Schneider Electric Services will refer to manufacturers instructions, NFPA 70B, IEEE, ANSI and other relevant standards. For additional information, contact Schneider Electric Services at Acknowledgement This document has been prepared based on manufacturer instruction bulletins, NFPA, IEEE, NEMA and ANSI standards Tables are based on information from Schneider Electric USA, Inc. and the ANSI/NETA Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems Schneider Electric All Rights Reserved

5 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 2 GENERAL REQUIREMENTS SECTION 2 GENERAL REQUIREMENTS! DANGER HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH Apply appropriate personal protective equipment (PPE) and follow safe electrical work practices. See NFPA 70E or CSA Z462. This equipment must be installed and serviced by qualified electrical personnel. Turn off all power supplying this equipment before working on or inside equipment. Always use a properly rated voltage sensing device to confirm power is off. Replace all devices, doors and covers before turning on power to this equipment. Failure to follow these instructions will result in death or serious injury. Schneider Electric Services (SES) considers the safety of our employees, customers and all persons associated or affected by our work to be our highest priority. All work performed by Schneider Electric will adhere to Schneider Electric Safe Work practices, NFPA 70E, Customer Requirements and State and Federal standards. In all cases the most stringent procedures will be adhered to. At any point if the lead Schneider Electric representative determines work cannot proceed safely in accordance with these requirements work will be halted until a mutually agreeable resolution is reached. Owner / Customer shall supply current one-line and as built drawings for review prior to commencement of work. These will be given to Schneider Electric Personnel for use throughout the testing project. Owner / Customer shall supply OEM (Original Equipment Manufacture) Operations and Maintenance Manuals for all equipment to be tested. Copies of these should be given to Schneider Electric Personnel for use throughout the testing project. Schneider Electric Services Employees are NOT AUTHORIZED to work on energized equipment. However, there are occasions in which it may be necessary to take voltage measurements within an energized enclosure. These measurements will be taken using all applicable procedures for energized work. Schneider Electric Services does not typically perform shutdown and/or switching operations, because these operations may result in damage to property or persons downstream of the equipment as a result of conduct, errors, or omissions made by others. If a customer requests Schneider Electric Company to perform such services, a copy of the Schneider Electric Shutdown/Switching policy must be reviewed and signed by the customer. The onsite technician(s) must also contact their Manager for approval and proper procedures prior to performing any shutdown and/or switching. Schneider Electric maintains an equipment calibration program to assure that the equipment used to monitor and measure data associated with key characteristics will provide data that is both accurate and repeatable. The calibration cycle is defined by manufacturer and industry guidelines. Equipment included in the program is identified by a calibration sticker or tag affixed to each piece of test equipment. Equipment calibration records are available for review based on project specifications Schneider Electric All Rights Reserved 5

6 Scopes of Work for Electrical Acceptance Testing: SECTION 3 AC DRIVES Bulletin No. 1910DB1302 SECTION 3 AC DRIVES A. Visual and Mechanical Inspection 1. Document equipment nameplate data on the test report. Verify equipment nameplate ratings are in accordance with record drawings. 2. Check for shipping damage: broken operators, switches, or pilot lights; dented or bent enclosure structures. 3. Check for excessive dirt, dust, or moisture. 4. Verify that a properly sized grounding conductor is connected to the drive grounding lug and terminates on a ground lug in the power distribution panel. 5. Verify that wires connected between the drive and the motor are correctly sized per the manufacturer s instructions (if not specified refer to the National Electrical Code). Verify that these wires are separated from all other wiring (ideally in their own conduit). Note the length of wire between the drive and the motor on the test report. 6. Tighten all power wiring connections to proper torque value. Check line and load side connections of all disconnect switches, breakers, contactors, and overloads. 7. Check and tighten all control wiring connections, mounting hardware, drive control terminals and terminal block connections. 8. Check door and disconnect switch alignment and opening/closing operation. 9. Test all mechanical interlocking devices. 10. Manually operate all contactors to verify freedom of movement. 11. Verify that customer supplied fusing agrees with the manufacturer s recommendations. 12. Verify mechanical operation of isolation contactor. Tighten power and control connections. Verify the proper coil voltage rating. 13. Verify that all control and option boards are securely fastened and plug-in terminals are connected. 14. Check that properly sized thermal overloads are used in ISO/Bypass unit. 15. Set / program the drive based on the customer provided settings. Settings should include torque type and any applicable communications parameters. If customer provided settings are not available, consult with the customer regarding any recommended settings. 16. Document final settings and customer acceptance of final settings. B. Electrical Tests 1. Verify that the incoming line voltage at the line side of the disconnecting means is within ± 10% of the input voltage rating on the drive nameplate. 2. Set the AFC-Off-Bypass selector switch (if used) to AFC and the Hand Off-Auto to Hand. Slowly turn the manual speed potentiometer clockwise to accelerate the motor. Check the direction of motor rotation at 10hz. Rotation should be clockwise (ABC) unless indicated differently by the project documentation. Note the as-found and as-left rotation on the startup documentation. 3. Set the AFC-Off-Bypass selector switch (if used) to Bypass and the Hand Off-Auto to Hand. Check the direction of motor rotation. Rotation should be clockwise (ABC) unless indicated differently by the project documentation. Note the as-found and as-left rotation on the start-up documentation Schneider Electric All Rights Reserved

7 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 3 AC DRIVES 4. Measure the output voltage of the ac control transformers. Voltages should be within +/-5% of nominal output voltage. Measure dc control supplies (for customer use), and verify that they are within the manufacturer s recommendations. 5. Measure the dc bus voltage and verify that it is equal to the measured RMS Line to Line input voltage x /-5%. 6. With the motor load disconnected, perform phase to phase and phase to ground voltage measurements at the output terminals (T leads). Take measurements in each of the following modes; standby, medium motor load and full motor load. Phase to Phase voltage imbalance must be less than +/-2%. Phase to ground voltage imbalance should be less than +/-5%. 7. Repeat the previous step with the motor load connected. 8. Measure the motor current in each T lead at medium motor load and again at full motor load. Output Phase Current imbalance must be less than 5% at any load. Compare readings taken to displayed value of output current on the Keypad. Note any discrepancies on the test report. 9. Verify that speed control signals vary within the voltage or current range of the input to which they are connected. Check for proper shielding on wires connected to speed control inputs. Verify that signals are isolated from power wires. 10. Verify proper operation based on the High Speed (HSP) setting (maximum motor speed setting). Record your results. 11. Verify proper operation based on Check the Low Speed (LSP) setting (minimum motor speed setting). Record your results. 12. Verify proper operation of acceleration (ACC) and deceleration (DEC) times. 13. Verify that I/O points are assigned to proper functions per factory drawings. 14. Verify that Hand and Auto controls, Start, Stop, and speed input, operate the drive correctly. 15. Check that all indicating lamps illuminate only for their assigned functions. Check all Push to Test lamps Schneider Electric All Rights Reserved 7

8 Scopes of Work for Electrical Acceptance Testing: SECTION 4 AIR SWITCHES: LOW VOLTAGE Bulletin No. 1910DB1302 SECTION 4 AIR SWITCHES: LOW VOLTAGE A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify equipment nameplate ratings are in accordance with the record drawings. 2. Inspect physical and mechanical condition. 3. Confirm application of lubricants at manufacturer s recommended locations. 4. Verify appropriate anchorage and required area clearances. 5. Verify appropriate equipment grounding. 6. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation. 7. Verify and record fuse sizes and types are in accordance with record drawings and, if available, coordination studies. 8. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Table and Check all interlocking systems for correct operation and sequencing, and key distribution, if applicable. 10. Verify correct phase barrier installation. 11. Inspect all indicating and control devices for correct operation. 12. Check the condition of arc contacts and arc chutes. B. Electrical Tests NOTE: When performing dielectric tests, you must disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or be damaged by the applied test voltage. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage. Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer s published data or Table Test all auxiliary devices (solenoid trip, blown main fuse detector, etc.) for proper operation. 3. Perform a Contact Resistance Test across each pole (phase): a. With the main power source de-energized, close and open the switch several times using either manual or electrical means. b. Apply a minimum current of 10 amperes dc through the closed contacts. If the test current does not conform to the manufacturer s specification, consult the manufacturer Schneider Electric All Rights Reserved

9 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 4 AIR SWITCHES: LOW VOLTAGE c. Measure and record the median (middle) value of three readings (toggling the circuit breaker between each reading) compare with the manufacturers published information and adjacent poles. d. If the measured resistances are below the manufacturers published data and balanced, the condition of the device contacts is considered suitable for service. If the measured resistances exceed the manufacturers recommendations or are imbalanced, open and close the device several more times and repeat the test. Contact the factory if acceptable values of resistance cannot be achieved. 4. Measure fuse resistance to verify continuity, record your results. 5. When ground fault protection is installed on switch, confirm settings are in accordance with the owner supplied coordination study. Verify proper calibration and operation by current injection Schneider Electric All Rights Reserved 9

10 Scopes of Work for Electrical Acceptance Testing: SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED Bulletin No. 1910DB1302 SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify equipment nameplate ratings are in accordance with the record drawings. 2. Inspect physical and mechanical condition. 3. Confirm correct application of lubricants at manufacturer s recommended locations. 4. Verify appropriate anchorage and required area clearances. 5. Verify appropriate equipment grounding. 6. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation. 7. Verify that fuse sizes and types are in accordance with drawings and, if available, coordination studies. 8. Inspect fuse holders for tightness and alignment. 9. Verify that expulsion-limiting devices are in place on all holders having expulsion-type elements. Verify that they are installed to vent in the proper direction. 10. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Check all interlocking systems for correct operation and sequencing, and key distribution, if applicable. 12. Verify correct phase-barrier installation. 13. Inspect all indicating and control devices for correct operation. 14. Verify that the Lightning arresters have been connected. Verify that they have the proper voltage rating per the manufacturer s drawings. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with Switchgear industry standards. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer s published data or Table Perform a dielectric test (Hi-Pot) on each pole with switch closed. Test each pole-to-ground with all other poles grounded. Test voltage shall be in accordance with manufacturer s published data or Table Verify that heaters have been connected and are operating properly Schneider Electric All Rights Reserved

11 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 5 AIR SWITCHES: MEDIUM VOLTAGE, METAL-ENCLOSED 4. Measure fuse resistance to verify continuity, record your results. 5. Perform a Contact Resistance Test across each pole (phase) a. With the main power source de-energized, close and open the switch several times using either manual or electrical means. b. Apply a minimum current of 10 amperes dc through the closed contacts. c. Measure and record the median (middle) value of three readings (toggling the circuit breaker between each reading) compare with the manufacturers published information and adjacent poles. d. If the measured resistances are below the manufacturers published data and balanced, the condition of the device contacts is considered suitable for service. If the measured resistances exceed the manufacturers recommendations or are imbalanced, open and close the device several more times and repeat the test. Contact the factory if acceptable values of resistance cannot be achieved Schneider Electric All Rights Reserved 11

12 Scopes of Work for Electrical Acceptance Testing: SECTION 6 AIR SWITCHES: HIGH AND MEDIUM VOLTAGE, OPEN STYLE Bulletin No. 1910DB1302 SECTION 6 AIR SWITCHES: HIGH AND MEDIUM VOLTAGE, OPEN STYLE A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify equipment nameplate ratings are in accordance with the record drawings. 2. Inspect physical and mechanical condition. 3. Confirm correct application of lubricants at manufacturer s recommended locations. 4. Verify that grounding is in accordance with industry standards and project specifications. 5. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and Perform mechanical operator tests in accordance with manufacturer s instructions. 7. Verify correct operation and adjustment of motor operator limit-switches and mechanical interlocks. 8. Verify correct blade alignment, blade penetration, travel stops, arc interrupter operation, and mechanical operation (over toggle). 9. Inspect fuse holders for tightness and alignment. 10. Check the condition of arc contacts and arc chutes. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with Switchgear industry standards. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage should be in accordance with manufacturer s published data or Table Perform a dielectric test (Hi-Pot) on each pole with switch closed. Test each pole-to-ground with all other poles grounded. Test voltage shall be in accordance with manufacturer s published data or Table Perform a contact-resistance test across each switch blade and fuse holder, record results. Compare with the manufacturer s published information and adjacent poles. Investigate any values that deviate from adjacent poles or similar switches by more than 25 percent. 4. Verify Operator targets and Gas targets, where applicable, are in proper sequence Schneider Electric All Rights Reserved

13 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 7 SWITCHES: HVL/cc SECTION 7 SWITCHES: HVL/cc A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify equipment nameplate ratings are in accordance with the record drawings. 2. Inspect physical and mechanical condition. 3. Verify appropriate anchorage and required area clearances 4. Verify that all power cables are properly terminated and supported. NOTE: When routing shielded cable through window-type current transformers or ground sensor current transformers, the shield-ground connection wire is normally routed back through the current transformer and solidly grounded 5. Check all control wiring for compliance with the wiring diagrams and connection across shipping splits. 6. If FuseLogic fuse trip system is installed, verify proper operation. 7. Verify that all connections are properly made and tightened to the proper torque values, 8. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer's data is available, use the values in Tables and Verify all fuses are properly installed and clips lubricated with Mobil Verify that fuse sizes and types are in accordance with drawings and, if available, coordination studies. 11. Verify all current transformer circuits are complete and not shorted. 12. Check all interlocking systems for correct operation and sequencing, and key distribution, if applicable. 13. If any isolating switch is not in operation and is left without incoming cables, the corresponding grounding switch must be closed and blocked by means of a padlock to avoid possible unintentional operation. 14. Verify appropriate equipment grounding. 15. Verify that all insulating surfaces are clean and dry. 16. Verify that all barriers and covers are secured 17. When equipped, verify proper operation of the ground switch and related interlocks. 18. Perform a minimum of 5 open / close operations while verifying smooth operation of the mechanism and all indicators. 19. Inspect all interlocks, indicating and control devices for correct operation Schneider Electric All Rights Reserved 13

14 Scopes of Work for Electrical Acceptance Testing: SECTION 7 SWITCHES: HVL/cc Bulletin No. 1910DB1302 B. Electrical Tests NOTE: Prior to performing dielectric tests, disconnect all Instrument and Control Transformers, Arresters, Control and Power cables units, and other sensitive electronic equipment that may cause erroneous results or be damaged by the applied test voltage. Capacitive dividers supplied with the equipment must be properly connected or grounded. Verify no paths to ground exist with an ohmmeter or initially testing insulation resistance at a low voltage. Record the date of the last calibration for each piece of test equipment used. 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with the below table. 2. Perform Hi-Pot test a. Apply voltage to each phase individually for one minute with the other two phases and enclosure grounded. (see below table for hipot test values b. Gradually increase voltage. Hi-Pot Test Values Equipment Field Test Voltages Rating AC DC 4.76kV 14kV 20kV 15kV 27kV 38kV 17.5kV 28.5kV 40kV 27kV 45kV 63kV 38kV 60kV 85kV Schneider Electric All Rights Reserved

15 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 8 METERING DEVICES SECTION 8 METERING DEVICES A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify equipment nameplate ratings are in accordance with the record drawings. 2. Inspect physical and mechanical condition. 3. Confirm case is properly grounded. 4. Verify tightness of electrical connections. 5. For electro-mechanical devices, verify freedom of movement, correct travel, alignment, and tightness of mounting hardware. 6. For microprocessor based meters confirm and record settings for system configuration, CT and PT ratios, multipliers, communications and other specified parameters are in accordance with record drawings or customer supplied specifications. B. Electrical Tests Record the date of the last calibration for each piece of test equipment used. 1. Check calibration of meters according to the manufacturer s published data. 2. Electrically confirm that current transformer and voltage transformer secondary circuits are intact Schneider Electric All Rights Reserved 15

16 Acceptance Testing Procedures: SECTION 9 BUSWAYS, METAL-ENCLOSED Bulletin No. 1910DB1302 SECTION 9 BUSWAYS, A. Visual and Mechanical Inspection METAL- ENCLOSED 1. Document equipment nameplate data on test report. Verify busway nameplate ratings in accordance with record drawings. 2. Inspect the busway for physical damage and correct connection in accordance with the record drawings. 3. Inspect for appropriate bracing, suspension, alignment, clearances and enclosure grounding and bonding. 4. Verify that the neutral is only grounded at one point in accordance with NEC, CSA or other applicable standards. 5. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Verify installation and proper operation of heaters, when applicable, 7. Verify that the busway phasing matches the system phasing at all connection points (transformers, switchboards, tie sections etc.). 8. For outdoor busway, confirm removal of weep-hole plugs, if applicable, and the correct installation of joint shield(s). Verify that proper gasketing is in place. B. Electrical Tests NOTE: Prior to testing, confirm that all tap-off or plug-in devices are in the off position. Isolate the entire busway run by disconnecting any ties to transformers, switchboards, meters or other devices. Record the date of the last calibration for each piece of test equipment used. 1. Measure insulation resistance of each busway with an insulation resistance tester rated at 1000 volts. Make measurements phaseto-ground, phase-to-neutral and phase-to-phase and for one minute. Compare your results with Table NOTE: The megohm readings should not be less than the value calculated from the following formula. Megohms = 100 / length of run (in feet) or Megohms = 30.5 / length of run (in meters) C. Optional Tests 1. Perform contact-resistance test on each connection point of non insulated busway. On insulated busway, measure resistance of assembled busway sections and compare values with adjacent phases. 2. Perform a dielectric test (Hi-Pot) on each busway, phase-to-ground with phases not under test grounded, in accordance with manufacturer s published data. Apply test voltage for one minute. Use test voltage values as shown in Table Schneider Electric All Rights Reserved

17 Bulletin No. 1910DB1302 Acceptance Testing Procedures: SECTION 10 OUTDOOR / SUBSTATION BUS SECTION 10 OUTDOOR / SUBSTATION BUS A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify bus nameplate ratings in accordance with record drawings. 2. Inspect the bus for physical damage and correct connection in accordance with the record drawings. 3. Inspect for appropriate bracing, suspension, alignment, and proper grounding. 4. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and Verify that all support insulators are clean and undamaged. 6. Verify that the bus phasing matches the system phasing at all connection points (transformers, circuit breakers, switches, tie sections etc.). B. Electrical Tests Record the date of the last calibration for each piece of test equipment used. 1. Perform an insulation resistance test to confirm the system is free of any ground faults. Compare your results with Table Perform a dielectric test (Hi-Pot) on each bus, phase-to-ground with phases not under test grounded, in accordance with manufacturer s published data. Apply test voltage for one minute. Use test voltage values as shown in Table C. Optional Tests 1. Perform contact-resistance test on each connection point Schneider Electric All Rights Reserved 17

18 Scopes of Work for Electrical Acceptance Testing: SECTION 11 CABLES: LOW VOLTAGE Bulletin No. 1910DB1302 SECTION 11 CABLES: LOW VOLTAGE A. Visual and Mechanical Inspection 1. Verify that cable sizing and insulation temperature rating are in accordance with final approved or record drawings and specifications, if available. Note any deviations. 2. Inspect the exposed sections of cables for physical damage and correct connection in accordance with the record drawings. 3. Using a calibrated torque wrench, verify that the tightness of accessible bolted connections is in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Inspect compression-applied connectors for correct cable match and indentation. 5. Verify cable color coding with project specifications, where applicable. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with industry standards. 1. Verify that the opposite end of the cable run being tested is properly isolated from both adjacent equipment and personnel during testing. 2. Record the date of the last calibration date for each piece of test equipment used. 3. Cables and leads shall be tested for continuity to ensure correct cable connection and phasing. 4. Perform an insulation resistance test on each conductor between one conductor and ground with the other conductors grounded. Each conductor shall be tested in the same manner. a. The test shall be performed at 1000 volts dc for one minute. b. Each 480V feeder cable shall be tested with the cable connected to the racked-in but open breaker or switch at the equipment. Connection at the other end of each of these cables shall be as follows: i. Cables to Motor Control Centers shall be connected to the bus with the switches or breakers in the starters open. ii. Cables to motors and other equipment shall be connected to the motors and equipment with feeder switches open. C. Optional Test Perform a dielectric test on shielded cable or as specified per Table Refer to the manufacturer s published data, Perform at standard intervals, checking leakage current and decay voltage over the specified time period Schneider Electric All Rights Reserved

19 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 12 CABLES: MEDIUM VOLTAGE SECTION 12 CABLES: MEDIUM VOLTAGE A. Visual and Mechanical Inspection 1. Verify that cable sizing and insulation temperature rating are in accordance with final approved or record drawings and specifications, if available. Note any deviations. 2. Inspect the exposed sections of cables for physical damage and correct connection in accordance with the record drawings. 3. Using a calibrated torque wrench, verify that the tightness of accessible bolted connections is in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and Inspect compression-applied connectors for correct cable match and indentation. 5. Verify cable color coding with applicable engineer s specifications. 6. Inspect cable terminations for proper installation in accordance with the termination manufacturers instructions. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance industry standards. 1. Verify that the opposite end of the cable run to be tested is disconnected and isolated from personnel. 2. Record the date of the last calibration for each piece of test equipment used. 3. Test cables for continuity and to ensure correct connection and phasing. 4. Perform a shield continuity test on each conductor 5. With cables isolated at both ends, perform an insulation resistance test on each conductor between the conductor and ground with the conductors not under test grounded. Each conductor shall be tested in the same manner. The test shall be performed at 1000 volts dc for one minute. 6. Perform a dielectric test on medium voltage shielded cable per Table Refer to the manufacturer s published data, and perform in accordance with IEEE 400, checking leakage current and decay voltage over the specified time period. NOTE: Cable testing technology is an evolving science. DC testing may not be suitable for some cable types (Such as XLPE), however, may be best suited for other types (such as EPR). An alternate test method may be employed in lieu of step 6 based on project requirements and discussions with the project engineer. C. Optional Tests 1. Very Low Frequency (VLF) 2. Perform power-factor or dissipation-factor tests on each cable. NOTE: For long cable runs it may be necessary to utilize a resonating inductor due to the large amount of capacitance in the cable Schneider Electric All Rights Reserved 19

20 Scopes of Work for Electrical Acceptance Testing: SECTION 13 CAPACITORS: POWER FACTOR CORRECTION Bulletin No. 1910DB1302 SECTION 13 CAPACITORS: POWER FACTOR CORRECTION A. Visual and Mechanical Inspection Document equipment nameplate data on the test report. 1. Verify that the capacitor nameplate ratings are in accordance with the record drawings. 2. Inspect the physical and mechanical condition of the equipment. 3. Inspect the capacitors for the correct mounting and required clearances, per the manufacturer s recommended procedures. 4. Confirm all ventilation openings are clear and unobstructed. 5. Verify that capacitors are electrically connected in their specified configuration, per the manufacturer s recommended procedures. 6. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer s data is available, use the values in Tables and B. Electrical Tests 1. Record the date of the last calibration date for each piece of test equipment used. 2. Perform insulation-resistance tests from terminal(s) to case for one minute on capacitors with more than one bushing. The test voltage and minimum resistance shall be in accordance with the manufacturer s instructions or Table Measure and record the input voltage for the capacitor / bank. Voltage should not exceed the capacitor nameplate rating by more then 10%. 4. Measure the capacitance of all terminal combinations. 5. Measure the resistance of the internal discharge resistors Schneider Electric All Rights Reserved

21 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 14 CIRCUIT BREAKERS:LV INSULATED CASE/ MOLDED CASE SECTION 14 CIRCUIT BREAKERS: LOW VOLTAGE INSULATED CASE/ MOLDED CASE A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify equipment nameplate ratings are in accordance with the record drawings. 2. Inspect circuit breaker for shipping damage, correct mounting, alignment and grounding. 3. Open and close the circuit breaker to insure smooth operation. 4. Confirm that lubricants have been correctly applied at the manufacturer s recommended locations. 5. Inspect case for cracks or other defects. 6. When applicable, inspect condition and alignment of arc chutes, moving and stationary contacts. 7. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism. 9. Verify installation and operation of specified accessories, such as Blown Fuse Indicators. Auxiliary Contacts, Cell Switches, Shunt Trip Devices, and Undervoltage Release. 10. Exercise the push to trip button to verify trip and reset. 11. Verify that the breaker is equipped with the correct rating plugs and current sensors. 12. Verify that the breaker has the specified trip unit / relay type and functions, (LI, LS, LSI, and LSIG). 13. Verify that the secondary control plug/connections are in accordance with the wiring diagram and specifications. 14. Verify that the Ground Fault System has been wired in accordance with the specified wiring diagram, and that the Sensor Grounds are either present or not present as specified. 15. When applicable, activate the Blown Fuse Indicator (BFI) and confirm by attempting to close the breaker without reset. 16. Check the operation of electrically operated breakers in their cubicles. 17. Make adjustments for the final settings in accordance with the coordination study supplied by the owner, if available. 18. Verify that all maintenance devices are available for servicing and operating the breaker. B. Electrical Tests NOTE: When performing dielectric tests, remove rating plugs and disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with molded case circuit breaker industry standards. Record the date of the last calibration for each piece of test equipment used. 1. Perform a contact-resistance test in accordance with the following procedure Schneider Electric All Rights Reserved 21

22 Scopes of Work for Electrical Acceptance Testing: SECTION 14 CIRCUIT BREAKERS:LV INSULATED CASE/ MOLDED CASE Bulletin No. 1910DB1302 a. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. Trip the circuit breaker with the push to trip button if so equipped. Close the breaker. b. Measure the resistance across each pole with a digital lowresistance ohmmeter. c. Compare the resistance values with manufacturers published data and between phases. d. For circuit breakers manufactured by Schneider Electric compare your results to the values in Table Perform an insulation-resistance test at 1000 volts dc from pole-to-pole and from each pole-to-ground with breaker closed and across open contacts of each phase. Insulation resistance should be greater than 100 Megohms. 3. Verify correct operation of any auxiliary features such as trip and pickup indicators, electrical close and trip operation, trip-free, and anti pump function. 4. Perform the following trip unit / relay tests by secondary injection: a. Minimum pickup current. b. Long-time delay. c. Short-time pickup and delay. d. Ground-fault pickup and delay. e. Instantaneous pickup. C. Optional Tests 1. Perform the trip unit / relay tests utilizing primary current injection. 2. Perform a dielectric withstand test Schneider Electric All Rights Reserved

23 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13) SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13) A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify equipment nameplate ratings are in accordance with the record drawings. 2. Inspect circuit breaker for shipping damage, correct mounting, alignment and grounding. 3. Open and close the circuit breaker to insure smooth operation. 4. Confirm that lubricants have been correctly applied at the manufacturer s recommended locations. 5. Inspect condition and alignment of arc chutes, moving and stationary contacts. 6. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no, manufacturer s data is available, use the values in Tables and Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism. 8. Verify installation and operation of specified accessories, such as Blown Fuse Indicators. Auxiliary Contacts, Cell Switches, Shunt Trip Devices, and Undervoltage Release 9. Verify that the breaker is equipped with the correct rating plugs and current sensors. 10. Verify that the breaker has the specified trip unit / relay type and functions, (LI, LS, LSI, and LSIG). 11. Verify that the secondary control plug/connections are in accordance with the wiring diagram and specifications. 12. Verify that the Ground Fault System has been wired in accordance with the specified wiring diagram, and that the Sensor Grounds are either present or not present as specified. 13. When applicable, activate the Blown Fuse Indicator (BFI) and confirm by attempting to close the breaker without reset. 14. Check the operation of electrically operated breakers in their cubicles. 15. Make adjustments for the final settings in accordance with the coordination study supplied by the owner, if available. 16. Verify that all maintenance devices are available for servicing and operating the breaker Schneider Electric All Rights Reserved 23

24 Scopes of Work for Electrical Acceptance Testing: SECTION 15 CIRCUIT BREAKERS: LOW VOLTAGE POWER (ANSI/IEEE C37.13)) Bulletin No. 1910DB1302 B. Electrical Tests NOTE: When performing dielectric tests, remove rating plugs and disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment that is not rated in accordance with molded case circuit breaker industry standards. Record the date of the last calibration for each piece of test equipment used. 1. Perform a contact-resistance test in accordance with the following procedure. a. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. Trip the circuit breaker with the push to trip button if so equipped. Close the breaker. b. Measure the resistance across each pole with a digital lowresistance ohmmeter. c. Compare the Resistance values with manufacturers published data and between phases. d. For circuit breakers manufactured by Schneider Electric compare your results to the values in Table Perform an insulation-resistance test at 1000 volts dc from pole-to-pole and from each pole-to-ground with breaker closed and across open contacts of each phase. Insulation resistance should be greater than 100 Megohms. 3. Verify correct operation of any auxiliary features such as trip and pickup indicators, electrical close and trip operation, trip-free, and anti pump function. 4. Perform the following trip unit / relay tests by secondary injection: a. Minimum pickup current. b. Long-time delay. c. Short-time pickup and delay. d. Ground-fault pickup and delay. e. Instantaneous pickup. C. Optional Tests 1. Perform the trip unit / relay tests utilizing primary current injection. 2. Perform a dielectric withstand test Schneider Electric All Rights Reserved

25 Bulletin No. 1910DB1302 Scopes of Work for Electrical Acceptance Testing: SECTION 16 CIRCUIT BREAKERS: MEDIUM VOLTAGE SF6 SECTION 16 CIRCUIT BREAKERS: MEDIUM VOLTAGE SF6 A. Visual and Mechanical Inspection 1. Document equipment nameplate data on test report. Verify that equipment nameplate ratings are in accordance with the record drawings. 2. Inspect the physical and mechanical condition of the breaker. 3. Confirm that lubricants have been correctly applied at the manufacturer's recommended locations. 4. Inspect anchorage and grounding. 5. Inspect and verify that adjustments of the mechanism are in accordance with the manufacturer's instructions. 6. Check indicators for gas leaks in accordance with the manufacturer's instructions. 7. Verify correct operation of all air and SF6 gas pressure switches, alarms and cutouts. (NOTE: For sealed interrupters, the pressure cannot be varied to change the state of pressure switches.) 8. Slow close/open breaker and check for binding. (This may not be possible in all cases where special or optionally supplied tooling is required) 9. Using a calibrated torque wrench or low resistance ohmmeter, verify that the tightness of accessible bolted connections and/or cable connections are in accordance with the manufacturer s published data. If no manufacturer's data is available, use the values in Table and Record as-found and as-left counter operations. B. Electrical Tests NOTE: When performing dielectric tests, disconnect all Instrument and Control Transformers, Arresters, TVSS units, and other sensitive electronic equipment that may cause erroneous results or cause damage to equipment. Surge Protection Devices must be completely disconnected from the electrical system (including neutral and ground). Record the date of the last calibration for each piece of test equipment used. 1. Perform a contact-resistance test in accordance with the following procedure. a. Open and close circuit breaker manually several times to ensure the mechanism linkages are free and operate properly. b. Measure the resistance across each pole with a digital lowresistance ohmmeter. c. Compare the Resistance values with manufacturers published data and between phases. 2. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles in accordance with Table Perform a Hi-Pot (dielectric) test in accordance with the manufacturer s instructions. For Schneider Electric circuit breakers, perform the test in accordance with Table Verify trip, close, trip-free, and antipump functions. 5. Trip the circuit breaker by operating each protective device Schneider Electric All Rights Reserved 25

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services Circuit Breakers and Switchgear Thomas Greer Director of Engineering TLG Services Presentation Outline Switchgear Definition Overcurrent Protection Devices Circuit Breaker Trip Curves and Coordination

More information

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less.

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. PART 1 - GENERAL SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. RELATED SECTIONS Division 16 Section "Basic Electrical Materials and Methods" for general

More information

Primary and Secondary Electrical Distribution Systems

Primary and Secondary Electrical Distribution Systems Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility

More information

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated

More information

Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000

Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000 Product Description Full Voltage Starting Electric Fire Pump Controllers FTA1000 Description Firetrol FTA1000 Full Voltage Fire Pump Controllers are intended for use with electric motor driven fi re pumps

More information

Atlanta Chapter IEEE Industry Applications Society

Atlanta Chapter IEEE Industry Applications Society Atlanta Chapter IEEE Industry Applications Society Electrical Equipment Room Design Considerations presented at the Sheraton Buckhead Hotel Atlanta, Georgia November 20, 2006 Outline 1. Definitions 2.

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. 2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers

More information

SECTION 16999 ELECTRICAL ACCEPTANCE TESTS

SECTION 16999 ELECTRICAL ACCEPTANCE TESTS SECTION 16999 ELECTRICAL ACCEPTANCE TESTS PART 1 2. AND 3. COMBINED 1.1 SUMMARY A. Description of Systems 1. Furnish all labor, materials, test equipment, and technical supervision to perform and record

More information

D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify.

D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify. SECTION 263354 STATIC UPS TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. System start-up services. 2. Battery charging. 3. Load bank testing. 4. Battery load testing. 5.

More information

Fusible Disconnect Switch

Fusible Disconnect Switch Circuit Breakers Circuit breakers are used in panelboards and switchboards to provide circuit protection and provide a means of energizing and de-energizing a circuit. Siemens Sentron molded case circuit

More information

Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600

Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600 Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600 Data Bulletin 0600DB1104 03/2012 Retain for future use. Electronic Trip Circuit Breaker Basics 0600DB1104 Table of Contents

More information

CAPACITOR BANK TESTING SWP

CAPACITOR BANK TESTING SWP 1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.

More information

Section 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services

Section 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services Section 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services Introduction Power Distribution Equipment is a term generally used to describe any apparatus used for the generation,

More information

Evaluating Water-Damaged Electrical Equipment

Evaluating Water-Damaged Electrical Equipment Evaluating Water-Damaged Electrical Equipment 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been exposed to water through flooding, fire

More information

Transfer Equipment Controls

Transfer Equipment Controls Control Types Manual Transfer Switches Nonautomatic Transfer Switches Automatic Transfer Switches The type of control system for the transfer switch will vary depending on the type of switching equipment

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Secondary Unit Substations

Secondary Unit Substations 14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically

More information

IRRIGATION PUMPING Table of Contents - Section 900

IRRIGATION PUMPING Table of Contents - Section 900 IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS

More information

Instruction Bulletin. MCS025 Sync-Check Module Installation Sheet

Instruction Bulletin. MCS025 Sync-Check Module Installation Sheet Instruction Bulletin 63230-216-244B1 LaVergne, TN, USA MCS025 Sync-Check Module Installation Sheet Retain for future use. DANGER HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH Only qualified electrical

More information

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 READ CAREFULLY These instructions are intended to cover good practices in

More information

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars Presented By: Greg Pelster & Robert Schmid FFI Ferrie, Franzmann Industries LOW VOLTAGE SWITCHGEAR & LOW VOLTAGE

More information

Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches

Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Emergency Power System Services Industrial UPS, Batteries, Chargers, Inverters and Static Switches Downtime Is Not An Option The industrial uninterruptible power supply (UPS) is the foundation of your

More information

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1 2015 July 17 and Testing, ROPEC Page 1 PART 1 GENERAL 1.1. Scope.1 Equipment replacement and testing for a 44 kv 4.16kV/600V substation: a. Replacement of Insulators as indicated on the drawings in Appendix

More information

Part 1 System Modeling & Studies for Existing Systems

Part 1 System Modeling & Studies for Existing Systems Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures

More information

Evaluating Water-Damaged Electrical Equipment

Evaluating Water-Damaged Electrical Equipment Evaluating Water-Damaged Electrical Equipment 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been exposed to water through flooding, fire

More information

Vacuum Circuit Breaker Type VAD-3

Vacuum Circuit Breaker Type VAD-3 Instruction Bulletin Bulletin 6055-11 Vacuum Circuit Breaker Type VAD-3 4.76 kv, 29 ka (250 MVA) 4.76 kv, 41 ka (350 MVA) 8.25 kv, 33 ka (500 MVA) 15.0 kv, 18 ka (500 MVA) 15.0 kv, 28 ka (750 MVA) 15,0

More information

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches PART 1 GENERAL 1.01 Scope Optional Standby Power Generator Systems A. Furnish and install automatic transfer switches

More information

Evaluating Water-Damaged Electrical Equipment

Evaluating Water-Damaged Electrical Equipment Evaluating Water-Damaged Electrical www.nema.org Evaluating Water-Damaged Electrical 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been

More information

Short Circuit Current Calculations

Short Circuit Current Calculations Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that

More information

Single Phase Soft Starter

Single Phase Soft Starter Single Phase Soft Starter Installation & Operating Manual 6/02 Table of Contents Section 1 General Information................................................... 1 1 General Description................................................

More information

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES SECTION 26 29 23 VARIABLE FREQUENCY DRIVES PART 1 GENERAL 1.01 SCOPE A. Furnish and install individual freestanding variable frequency AC drives (VFD) as shown on the Drawings and specified herein. 1.02

More information

Sample - No Commercial Use

Sample - No Commercial Use COMPLETE REVISION October 2010 Electrical PIP ELSSG01 Design and Fabrication of Low-Voltage Metal-Enclosed AC Power Circuit Breaker Switchgear PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort

More information

Bypass transfer switch mechanisms

Bypass transfer switch mechanisms Power topic #6013 Technical information from Cummins Power Generation transfer switch mechanisms > White paper By Gary Olson, Director, Power Systems Development This paper describes the configuration

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

SURGE PROTECTIVE DEVICES (SPDs) LOW VOLTAGE AC INTEGRATED SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION SYSTEMS SECTION 16671A SECTION 16671A

SURGE PROTECTIVE DEVICES (SPDs) LOW VOLTAGE AC INTEGRATED SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION SYSTEMS SECTION 16671A SECTION 16671A SURGE PROTECTIVE DEVICES (SPDs) INTEGRATED UNITS LOW VOLTAGE AC SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION SYSTEMS PART 1 GENERAL 01 02 03 SCOPE The Contractor shall furnish and install the Surge Protective

More information

SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING

SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING SECTION 263235 STANDBY GENERATOR TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Standby generators. 2. Automatic Transfer Switches (ATS). 3. System start-up services. 4.

More information

Product Description Primary Resistance Starting Electric Fire Pump Controllers FTA1500

Product Description Primary Resistance Starting Electric Fire Pump Controllers FTA1500 Product Description Primary Resistance Starting Electric Fire Pump Controllers FTA1500 Description Firetrol FTA1500 Primary Resistance Fire Pump Controllers use resistors in the line to reduce line voltage

More information

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... ..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... TIME MARK CORPORATION 11440 EAST PINE STREET TULSA, OK 74116 USA tel 918 438-1220 fax 918 437-7584 www.time-mark.com

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

Arc Terminator Active Arc-Resistant Switchgear

Arc Terminator Active Arc-Resistant Switchgear Arc Terminator Active Arc-Resistant Switchgear Increasing safety and productivity by extinguishing internal arcing faults within the switchgear. The Square D Arc Terminator from Schneider Electric offers

More information

AC Electric Motors best practice

AC Electric Motors best practice If you want to learn more about best practice machinery maintenance, or world class mechanical equipment maintenance and installation practices, follow the link to our Online Store and see the Training

More information

HVL 5 38 kv Load Interrupter Switchgear. The Standard for Performance, Protection and Dependability

HVL 5 38 kv Load Interrupter Switchgear. The Standard for Performance, Protection and Dependability HVL 5 38 kv Load Interrupter Switchgear The Standard for Performance, Protection and Dependability For a generation of engineers, Square D High Voltage Load (HVL ) Interrupter Switchgear by Schneider Electric

More information

The Intelligent AX1 Switchgear for Medium Voltage

The Intelligent AX1 Switchgear for Medium Voltage The Intelligent AX1 Switchgear for Medium Voltage Leif Lundin, Manager of Research and Development, Division Medium Voltage and Compact Substations, ABB Distribution, Sweden Abstract The newly launched

More information

GUIDELINES FOR WATER-DAMAGED ELECTRICAL EQUIPMENT

GUIDELINES FOR WATER-DAMAGED ELECTRICAL EQUIPMENT GUIDELINES FOR HANDLING WATER-DAMAGED ELECTRICAL EQUIPMENT NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION 1300 NORTH 17 TH STREET, SUITE 1752 ROSSLYN, VIRGINIA 22209 703 841-3200 703 841-5900 FAX WWW.NEMA.ORG

More information

Arc Flash Hazards. Electrical Hazards. Dan Neeser Field Application Engineer DanRNeeser@Eaton.com. Electrical Hazards 2/18/2015. Shock.

Arc Flash Hazards. Electrical Hazards. Dan Neeser Field Application Engineer DanRNeeser@Eaton.com. Electrical Hazards 2/18/2015. Shock. Arc Flash Hazards Dan Neeser Field Application Engineer DanRNeeser@Eaton.com Electrical Hazards Electrical Hazards Shock Arc Flash Arc Blast 2 1 Arcing Fault Basics 35,000 F Radiant Heat & UV Speed of

More information

Fortune Oregon Data Center Increases Reliability with a High Resistance Grounding System

Fortune Oregon Data Center Increases Reliability with a High Resistance Grounding System Fortune Oregon Data Center Increases Reliability with a High Resistance Grounding System Cory David Smith, Project Manager, ECOM Engineering Inc., and David Lawrence Smith, Principal, ECOM Engineering

More information

The following components are common to most cubicles; this example is an ABB HK cubicle.

The following components are common to most cubicles; this example is an ABB HK cubicle. 4.0 CIRCUIT BREAKER CUBICLE Learning Objectives The circuit breaker cubicle is the component of the switchgear that holds the circuit breaker, and the controls and cabling for the distribution system.

More information

Fundamentals of Power

Fundamentals of Power Fundamentals of Power Fundamentals of Power 2008 American Power Conversion Corporation. All rights reserved. All trademarks provided are the property of their respective owners. Learning Objectives At

More information

Choosing the Best Solution for Reducing Arc Energy

Choosing the Best Solution for Reducing Arc Energy CONVENTION SESSION HANDOUT Choosing the Best Solution for Reducing Arc Energy Terry L. Schiazza, Business Development Manager Square D / Schneider Electric SESSION #11 Independent Electrical Contractors

More information

Evaluating Fire- and Heat-Damaged Electrical Equipment

Evaluating Fire- and Heat-Damaged Electrical Equipment Evaluating Fire- and Heat-Damaged Electrical Equipment www.nema.org 1 USE OF THIS PUBLICATION This publication provides information on how to evaluate electrical equipment that has been exposed to heat

More information

01.4IB.51200B PowlVac-AR Arc Resistant Switchgear. 5kV & 15kV 1200A, 2000A, 3000A, & 4000A Forced Cooled. Powered by Safety

01.4IB.51200B PowlVac-AR Arc Resistant Switchgear. 5kV & 15kV 1200A, 2000A, 3000A, & 4000A Forced Cooled. Powered by Safety PowlVac-AR Arc Resistant Switchgear 1200A, 2000A, 3000A, & 4000A Forced Cooled Powered by Safety PowlVac-AR Arc Resistant Switchgear 01.4IB.51200B Contact Information Powell Electrical Systems, Inc. www.powellind.com

More information

WE-350 Series ¼ Turn Electric Actuator

WE-350 Series ¼ Turn Electric Actuator WE-350 Series ¼ Turn Electric Actuator Operation and Installation Manual Pg 1 (Rev. 020113) Table of Contents 1.0 General 1.1 Pre-Installation Inspection 1.2 Storage 1.3 Features & General Information

More information

STANDARDS AND RATINGS FOR THE APPLICATION OF MOLDED CASE, INSULATED CASE, AND POWER CIRCUIT BREAKERS

STANDARDS AND RATINGS FOR THE APPLICATION OF MOLDED CASE, INSULATED CASE, AND POWER CIRCUIT BREAKERS STANDARDS AND RATINGS FOR THE APPLICATION OF MOLDED CASE, INSULATED CASE, AND POWER CIRCUIT BREAKERS David D. Roybal, P.E. Senior Member, IEEE Cutler-Hammer, Inc. 3697 Mount Diablo Boulevard Lafayette,

More information

SERVICE-LIFE EVALUATIONS OF LOW-VOLTAGE POWER CIRCUIT BREAKERS AND MOLDED-CASE CIRCUIT BREAKERS

SERVICE-LIFE EVALUATIONS OF LOW-VOLTAGE POWER CIRCUIT BREAKERS AND MOLDED-CASE CIRCUIT BREAKERS SERVICE-LIFE EVALUATIONS OF LOW-VOLTAGE POWER CIRCUIT BREAKERS AND MOLDED-CASE CIRCUIT BREAKERS Michael J Sprague Member, IEEE Cutler-Hammer, Inc. 130 Commonwealth Drive Warrendale, PA 15086 USA Abstract

More information

Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide

Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Instruction Bulletin EAV85226 08/2014 Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Retain for future use. Product Description Kit Contents The Wiser Panel Meter is for use in energy management

More information

Extend the Life of Existing Switchgear

Extend the Life of Existing Switchgear Extend the Life of Existing Switchgear January 2011/1910DB1002 by Hal Theobald, Product Manager Schneider Electric USA, Inc. Make the most of your energy SM Summary Introduction... p 3 Maintenance Requirements...

More information

HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE

HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE Appendix B-2 - Electrical Safety In Design Final Report TECHNOLOGIES THAT REDUCE LIKELIHOOD OF INJURY FROM ELECTRICAL HAZARDS, INCLUDING SHOCK, ARC FLASH AND FIRE The following are technologies that reduce

More information

PREFACE. Your comments or suggestions are welcome and appreciated. They should be sent to:

PREFACE. Your comments or suggestions are welcome and appreciated. They should be sent to: PREFACE UL developed the Dead-Front Switchboard Marking Guide for code authorities, electric utilities, contractors, installers, users, designers, and other interested parties to aid in understanding deadfront

More information

Application of Four-Pole Circuit Breakers within Data Centers

Application of Four-Pole Circuit Breakers within Data Centers Application of Four-Pole Circuit Breakers within Data Centers December 2013/AT324 by Frank Waterer, Fellow Engineer, Schneider Electric Engineering Services Make the most of your energy SM Revision #1

More information

Power/Vac Metal-Clad Switchgear and Vacuum Circuit Breakers Maintenance and Troubleshooting Suggestions

Power/Vac Metal-Clad Switchgear and Vacuum Circuit Breakers Maintenance and Troubleshooting Suggestions 1 GE Consumer & Industrial Electrical Distribution Applications / Specifications DET-456 Power/Vac Metal-Clad Switchgear and Vacuum Circuit Breakers Maintenance and Troubleshooting Suggestions 2 POWER/VAC

More information

Dead Tank Outdoor Vacuum Circuit Breaker, Type VOX

Dead Tank Outdoor Vacuum Circuit Breaker, Type VOX Dead Tank Outdoor Vacuum Circuit Breaker, Type VOX Class 6065 Instruction Bulletin 6065-13 11/2011 Retain for future use. Hazard Categories and Special Symbols Read these instructions carefully and look

More information

Installation Instructions for Alarm Module Kit A043F059

Installation Instructions for Alarm Module Kit A043F059 Instruction Sheet 07-2013 Installation Instructions for Alarm Module Kit A043F059 1 Introduction The information contained within is based on information available at the time of going to print. In line

More information

This section applies to the design and installation of transformers.

This section applies to the design and installation of transformers. ELECTRICAL: TRANSFORMERS BASIS OF DESIGN This section applies to the design and installation of transformers. Design Criteria 13.8-kV equipment shall be 15-kV class. Coordinate with short-circuit studies

More information

2004 TRANSMISSION SYSTEMS SEMINAR MEDIUM VOLTAGE, METAL-CLAD ARC RESISTANT SWITCHGEAR: ENHANCING WORKPLACE SAFETY

2004 TRANSMISSION SYSTEMS SEMINAR MEDIUM VOLTAGE, METAL-CLAD ARC RESISTANT SWITCHGEAR: ENHANCING WORKPLACE SAFETY 2004 TRANSMISSION SYSTEMS SEMINAR MEDIUM VOLTAGE, METAL-CLAD ARC RESISTANT SWITCHGEAR: ENHANCING WORKPLACE SAFETY Thomas P. McNamara, P.E. Manager, Development Engineering ABB Inc. Power Technologies Medium

More information

SURGE PROTECTIVE DEVICES (SPDs) LOW VOLTAGE AC EXTERNAL SIDEMOUNT SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION SYSTEMS SECTION 16671B SECTION 16671B

SURGE PROTECTIVE DEVICES (SPDs) LOW VOLTAGE AC EXTERNAL SIDEMOUNT SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION SYSTEMS SECTION 16671B SECTION 16671B SURGE PROTECTIVE DEVICES (SPDs) EXTERNAL SIDEMOUNT UNITS LOW VOLTAGE AC SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION PART 1 GENERAL 01 02 03 SCOPE The Contractor shall furnish and install the Surge Protective

More information

Owner's Manual. Automatic Transfer Switch. This manual should remain with the unit.

Owner's Manual. Automatic Transfer Switch. This manual should remain with the unit. Owner's Manual Automatic Transfer Switch REFERENCE THE OWNER'S MANUAL SUPPLIED WITH THE GENERATOR WHEN USING THIS DOCUMENTATION. NOT INTENDED FOR USE IN CRITICAL LIFE SUPPORT APPLICATIONS. THIS PRODUCT

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

How To Operate A Gec Transfer Switch Open Transition 40 2000 Amp Power Supply

How To Operate A Gec Transfer Switch Open Transition 40 2000 Amp Power Supply GTEC Transfer switch open transition 40 2000 amp Description GTEC transfer switches combine reliability and flexibility in a small, economical package for transferring loads between a utility and a generator

More information

Product Description Digital Solid State Starting Electric Fire Pump Controllers FTA1930

Product Description Digital Solid State Starting Electric Fire Pump Controllers FTA1930 Product Description Digital Solid State Starting Electric Fire Pump Controllers FTA1930 Description Firetrol FTA1930 Digital Solid State Starting Fire Pump Controllers feature soft start, soft stop and

More information

Bolted contact switches. Pringle switches

Bolted contact switches. Pringle switches Bolted contact switches Pringle switches Eaton s Pringle bolted contact switches History Eaton s PringleT switches have helped pioneer the development of high-quality electrical products for commercial

More information

Oil and Coolant Circulating Heating System. Model - OCSM

Oil and Coolant Circulating Heating System. Model - OCSM Oil and Coolant Circulating Heating System Model - OCSM Installation & Operation Manual 216280-000 REV 2 Identifying Your System The HOTSTART heating system is designed to heat fluids for use in marine

More information

Arc Flash Mitigation. Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear.

Arc Flash Mitigation. Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear. Arc Flash Mitigation Remote Racking and Switching for Arc Flash danger mitigation in distribution class switchgear. Distance is Safety We will discuss through examples of actual occurrences and possible

More information

Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services.

Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services. Spending too much to maintain aging switchgear? Circuit breaker solutions from Square D Services. Spending too much time and money on equipment maintenance? Square D Services: Your source for circuit breaker

More information

DORMA MODEL PS-406BB POWER SUPPLY INSTALLATION INSTRUCTIONS

DORMA MODEL PS-406BB POWER SUPPLY INSTALLATION INSTRUCTIONS Features: INSTALLATION Install in accordance with NFPA 70. DORMA MODEL PS-406BB POWER SUPPLY INSTALLATION INSTRUCTIONS Up to 1.95 Amps Load Capacity Class 2 Rated Outputs Overload, Over Voltage, and Short

More information

SECTION 262413 SWITCHBOARDS

SECTION 262413 SWITCHBOARDS PART 1 - GENERAL... 1 1.1 RELATED DOCUMENTS... 1 1.2 SUMMARY... 1 1.3 DEFINITIONS... 1 1.4 SUBMITTALS... 2 1.5 QUALITY ASSURANCE... 3 1.6 DELIVERY, STORAGE, AND HANDLING... 3 1.7 PROJECT CONDITIONS...

More information

Low Voltage Switchgear

Low Voltage Switchgear Arc Resistant Switchgear n Insulated and isolated bus n Separation barriers and top venting n Breaker shutters 12 SWITCHGEAR Arc resistant metal-enclosed low voltage switchgear is an optional product offering

More information

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

What are the basic electrical safety issues and remedies in solar photovoltaic installations? What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic

More information

Learning Module 13: Panelboards and Switchboards. 101 Basic Series

Learning Module 13: Panelboards and Switchboards. 101 Basic Series Learning Module 13: Panelboards and Switchboards 101 Basic Series What You Will Learn We ll step through each of these topics in detail: Introduction 4 Definitions 4 Similarities Between Panelboards and

More information

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

SF 6 Gas Insulated Switchgear Type SDF for 170 kv Three Phase Encapsulated Type SF 6 Gas Insulated Switchgear Type SDF for 170 kv 06B1-E-0001 With Trustworthy Technology, Structure Fuji Electric as a manufacturer of comprehensive substation equipment

More information

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation MTE SERIES RLW World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930 2009 MTE Corporation IMPORTANT USER INFORMATION NOTICE MTE Series RLW reactors are components designed to improve the reliability

More information

SWITCHGEAR. EGP Switchgear

SWITCHGEAR. EGP Switchgear SWITCHEA EP Switchgear Cat generator set paralleling switchgear has been designed to integrate with Cat EMCP3 generator set controls. Now you can get greater efficiency, reliability and dependability all

More information

COMPARISON OF ANSI/IEEE AND IEC REQUIREMENTS FOR LOW- VOLTAGE SWITCHGEAR

COMPARISON OF ANSI/IEEE AND IEC REQUIREMENTS FOR LOW- VOLTAGE SWITCHGEAR COMPARISON OF ANSI/IEEE AND IEC REQUIREMENTS FOR LOW- VOLTAGE SWITCHGEAR Copyright Material IEEE Paper No. PCIC 2003-13 Eddie Wilkie Eaton Cutler-Hammer 3990 Old Tasso Road NE Cleveland, TN 37312 USA Abstract

More information

ELECTRICAL SAFETY. The standard unit for measuring electrical current.

ELECTRICAL SAFETY. The standard unit for measuring electrical current. ELECTRICAL SAFETY Introduction The following sections provide general safety guidelines and procedures for electrical safety. This chapter covers the following topics: TOPIC PAGE General Electrical Safety

More information

MCC Ratings. Voltage Rating

MCC Ratings. Voltage Rating MCC Ratings In addition to the various ratings of individual components used in motor control centers, the overall ratings of the motor control center must also be considered. Voltage Rating Motor control

More information

SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original

SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original A motor starter is a combination of devices to allow an induction motor to start, run and stop according

More information

LTR Series Uninterruptible Power Systems 700 VA - 2.1 KVA. General Specification

LTR Series Uninterruptible Power Systems 700 VA - 2.1 KVA. General Specification 08/17/12 Rev2 LTR Series General Specification 700 VA to 2.1 KVA 1.0 General LTR Series Uninterruptible Power Systems 700 VA - 2.1 KVA General Specification This specification describes the features and

More information

SECTION 16341 MEDIUM VOLTAGE SWITCHGEAR

SECTION 16341 MEDIUM VOLTAGE SWITCHGEAR PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes metal-enclosed

More information

Understanding Arc Flash

Understanding Arc Flash Understanding Arc Flash Presented by Eddie F. Jones, PE 1 2 3 4 5 Five to 10 arc flash explosions occur in electric equipment every day in the United States. This number does not include cases in which

More information

GTEC transfer switch open transition

GTEC transfer switch open transition GTEC transfer switch open transition 40-1250 Amp Description The GTEC automatic transfer switch combines reliability and flexibility in a small, economical package for transferring loads between a utility

More information

PRODUCT GUIDE. SL Medium Voltage IEC Vacuum Contactors

PRODUCT GUIDE. SL Medium Voltage IEC Vacuum Contactors PRODUCT GUIDE SL Medium Voltage IEC Vacuum Contactors Table of Contents 1 Overview Introduction....................................................2 Features........................................................2

More information

CONTROL PANEL INSTALLATION INSTRUCTIONS. Single Phase Simplex Page 2-7. 3-Phase Simplex Page 8-13

CONTROL PANEL INSTALLATION INSTRUCTIONS. Single Phase Simplex Page 2-7. 3-Phase Simplex Page 8-13 CONTROL PANEL INSTALLATION INSTRUCTIONS Single Phase Simplex Page 2-7 3-Phase Simplex Page 8-13 Single Phase Simplex SXL21=3, SXL24=3, SXH21=3, and SXH24=3 Manufactured by SJE-Rhombus Installation Instructions

More information

How To Test A Power Switch On A Power Supply

How To Test A Power Switch On A Power Supply transfer switches Soft load Innovative, reliable, integrated solution Built with years of experience Powered with innovation Delivered with reliability A history of experience, innovation and reliability

More information

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms

Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms Dead Tank Circuit Breaker 72PM40-C Proven reliability through common platforms ABB innovations for changing demands ABB (www.abb.com) is a leader in power and automation technologies that enables utility

More information

Switchgear and Metal-Enclosed Bus

Switchgear and Metal-Enclosed Bus Section 18 Switchgear and Metal-Enclosed Bus 180. SWITCHGEAR ASSEMBLIES 180A. General Requirements for All Switchgear. This rule covers general requirements for all switchgear. Examples of switchgear found

More information

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK Pressure monitoring equipment for oil-sf 6 bushings, type GOEK Installation and maintenance guide 5693 827-6 en, Rev. 3, 2002-01-30 This document must not be copied without our written permission, and

More information