Investigation of short-circuit analysis conducted at Kromco

Similar documents
The following table shows approximate percentage wise the

Chapter 9 Balanced Faults

Simple Methods for Calculating Short Circuit Current Without a Computer By Dennis McKeown, PE GE Senior System Application Engineer

Short Circuit Current Calculations

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

How To Choose A Transformer

DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION

SIMULATING HYBRID ENERGY GRIDS IN SMART CITIES FOCUS ON ELECTRIC ENERGY SYSTEMS

SYNCHRONOUS MACHINES

The Importance of the X/R Ratio in Low-Voltage Short Circuit Studies

CIRCUIT BREAKER INTERRUPTING CAPACITY AND SHORT-TIME CURRENT RATINGS

SPECIAL TOPICS ON GROUND FAULT PROTECTION AND PROTECTION COORDINATION IN INDUSTRIAL AND COMMERCIAL POWER SYSTEMS

Simulation of Cable Overloading Problem on a University Distribution System

Power Quality Paper #3

6 ELECTRICAL PARAMETERS

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO

Chapter 1. Network Structures

Rule Fast Track Analysis for National Life Insurance Co.

Unified requirements for systems with voltages above 1 kv up to 15 kv

Module Title: Electrotechnology for Mech L7

Low Voltage Transformer Through-Fault Protection: A System Approach

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V V V (at 50 Hz)

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

EVALUATION OF FAULT ANALYSIS IN TRANSMISSION LINES USING RELAY SETTINGS

Power Technology Issue 104. Modeling of Two-Winding Voltage Regulating Transformers for Positive Sequence Load Flow Analysis in PSS E

Typical Data Requirements Data Required for Power System Evaluation

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System

Loading Considerations When Paralleling Transformers

Hyperlinks are Inactive

MEDIUM VOLTAGE SUBSTATION PRACTICES Medium Voltage (MV) is defined as: 1000V< MV 44kV

Earth Fault Detection Basics in Theory

Electrical Fault Level Calculations Using the MVA Method

EDS KV TRIPLEX CABLE

Design of Electrical Power Supply System in an Oil and Gas refinery. Master of Science Thesis in Electric Power Engineering

The electrical energy produced at the gen

7. Reactive energy compensation

Cables, Cable Laying & Accessories Manual

Part 1 System Modeling & Studies for Existing Systems

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

13. Electrical network design methodology and application example

Power transformers. Special transformers Railway

HIGH VOLTAGE SHORE CONNECTION

Overcurrent Protection for the IEEE 34 Node Radial Test Feeder

Modeling of Transmission Lines

Comparative study for cables and busbars

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

Instrument Transformers Application Guide

Guideline for Energy Efficient Electrical systems for building. Presentation by TERI

Engineering innovation

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Electrical Shore Connections / Cold Ironing

6. Synchronous machine dynamics

TYPE TEST CERTIFICATE OF SHORT-CIRCUIT PERFORMANCE. A three-phase outdoor oil-immersed distribution transformer

SHORT CIRCUIT CURRENT CALCULATION AND PREVENTION IN HIGH VOLTAGE POWER NETS

Cahier technique no. 158

3 Calculation of Short-Circuit Currents in Three-Phase Systems

AUTOMATIC TRANSFER SWITCH. Changeover Type from 250A to 2500A

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

Electrical network protection. Protection guide. Guide

SURVEY OF HARMONIC DISTORTION IN LV AND MV NETWORKS: RESULTS AND CORRECTIVE STRATEGIES

Earthing Guidance Notes

Open Phase Conditions in Transformers Analysis and Protection Algorithm

Electrical network protection. Protection guide. Guide G 51G 51G 51G 51G. network protection solutions

FAQs-Main switchboard design criteria

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

Three phase circuits

Advantages of Fixed Circuit Breaker Switchgear

THE PER-UNIT SYSTEM. (2) The per-unit values for various components lie within a narrow range regardless of the equipment rating.

Relion. Power system protection and automation reference Extending substation life cycle with IEC 61850

Secondary Unit Substations

Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template

Physical Address: City: State: Zip Code:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA

CT Analyzer: Coming to the Rescue. Introduction. Equivalent Circuit. Construction. Classification of a CT. Tony Porrelli, OMICRON, UK

EARTHING SYSTEM CALCULATION

FIT TIER 2 Application

PI144K - Winding 311 APPROVED DOCUMENT. Technical Data Sheet. Generator Solutions AS

DESCRIPTION DWG DESCRIPTION DWG

PI044E - Winding 311 APPROVED DOCUMENT. Technical Data Sheet

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

1 Introduction. 2 The Symmetrical Component Transformation. J.L. Kirtley Jr.

Relion. Power system protection and automation reference Fast substation busbar protection with IEC and GOOSE

Product Data Bulletin

System Grounding and Ground-Fault Protection Methods for UPS-Supplied Power Systems

Management Systems 10 Electrical Safety Audit 14 PPE 20 Arc Mitigation 22 Hazard Assessment 26

DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS

GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software

STANDARDS. Site-Specific Loss Adjustments PUBLIC

Technical Information Requirement for MV transformers and transformer for internal power supplies for SUNNY CENTRAL

SAMPLE OF THE STUDY MATERIAL PART OF CHAPTER 3. Symmetrical Components & Faults Calculations

Assessment of the Technical Issues relating to Significant Amounts of EHV Underground Cable in the All-island Electricity Transmission System

Circulating Current Relay. Type IRXm

Power System Analysis

Residual Current Circuit Breaker

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV a. Section INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

Chapter G Sizing and protection of conductors

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU

Measurement, Modeling and Simulation of Capacitor Bank Switching Transients

Transcription:

Investigation of short-circuit analysis conducted at Kromco by Bantubonke Matika and Alan Meru, Cape Peninsula University of Technology This article presents a short-circuit analysis conducted for the Kromco electrical power system using power system modelling, analysis and simulation software called DIgSilent PowerFactory. The main focus is determining the maximum short-circuit currents and fault levels at various locations on the network, and verifying the adequacy of power system components, to see if they can withstand rated prospective short-circuits. An efficient and reliable power system is a vital component of any industry especially manufacturing and packaging industries. Hence, a need arose to conduct short-circuit analysis in industrial power systems to evaluate the power delivery and utilisation operation efficiency [1]. Symmetrical three phase faults were investigated using the superposition method. Three operating conditions are analysed: 100%, 80% transformer full load, and when plant 2A is feeding via plant 1, which is normally open. Kromco is one of the large deciduous packing facilities in the Western Cape situated in Grabow, near Cape Town. Its dedication to delivering quality fruit to local and international markets makes Kromco a trusted brand. With its high tech cold stores and machinery for supplying consistent quality fruit it is vital that Kromco s electrical power system operates efficiently with minimal interruptions as each interruption may cause loss in production which can lead to high losses of revenue. Due to the modernisation programme of replacing old ring main units with new digitally controlled systems, a need arose for the study which was motivated to re-evaluate and verify the existing power system components and reliability. The system consists of an 11 kv feeder from Eskom as its source of electrical power. The supply voltage for the distribution system is then stepped down to 400 V, and 220 V as required by the loadings, from the main substation to ring main units feeding the transformers located at the packing shed, and plants 1, 2, 3 and 4. There are a total of eleven operating transformers in Kromco. These transformers range from 315 kva to 1000 kva. System models are constructed and simulations are conducted with certain assumptions being made in order to commence with the study. Loads are modelled as inductive loads at a power factor of 0,8 due to the fact that is was difficult to obtain actual load rated capacity and real time data. The IEC 60076 standard was used to obtain transformer X/R ratios. Research statement The main objective of the short-circuit analysis is to properly determine the shortcircuit currents and fault levels at various system locations using simulation software. This is to verify the adequacy of existing power system components as to whether they can withstand prospective shortcircuits. This was deemed necessary due to the fact that the current electrical system has never been revised and lacks proper documentation of load addition and system expansion since the establishment of the distribution network. Theoretical background Short-circuit analysis Electrical power systems in industrial plants are designed to supply loads in a safe, economical and reliable manner. However, even in a perfectly designed system, the occurrence of short-circuit currents are unavoidable [2]. According to IEC 60909, a short-circuit, or fault as its commonly known, is the accidental or unintentional conductive connection through a relatively low resistance or impedance between two or more points of a circuit which are normally at different potentials [3]. Fig. 1: Fault types. The duration of this fault can be at divided into three different areas: energize - December 2013 - Page 49

Source IVI V Ideal voltage source 1 p.u. 0 Table 1: Source parameters. Transformer Z [%] Voltage X/R ratio kva Vector group T 1 5,11 11 kv/400 V 3,5 1000 Dyn 11 T 2 5,11 11 kv/400 V 3,5 1000 Dyn 11 T 3 5,12 11 kv/400 V 3,5 1000 Dyn 11 T 4 4,591 11 kv/400 V 3,5 1000 Dyn 11 Fig. 2: Symmetrical fault. T 5 4,91 11 kv/400 V 3,5 1000 Dyn 11 T 6 4,66 11 kv/400 V 3,5 1000 Dyn 11 T 7 4,29 11 kv/400 V 1,5 315 Dyn 11 T 8 5,16 11 kv/400 V 3,5 1000 Dyn 11 T 9 5,296 11 kv/400 V 3,5 1000 Dyn 11 T 10 5,01 11 kv/400 V 3,5 1000 Dyn 11 T 11 4,8 11 kv/400 V 3,5 1000 Dyn 11 Table 2: Transformer parameters. Cable R1 [Ω/km] X1 [Ω/km] Main sub to pack shed RMU (XLPE) 0,09352 0,01848 Main sub to plant 1 RMU1 (XLPE) 0,30591 0,04587 Main sub to plant 2 RMU2A (XLPE) 0,05928 0,02688 Main sub to plant 3 RMU3 (XLPE) 0,04008 0,00792 Main sub to plant 4 RMU4 (ABC) 0,62883 0,09639 Pack shed RMU to plant 2 RMU2B (XLPE) 0,23175 0,03475 Plant 1 RMU1 to plant 2 RMU2A (XLPE) 0,10197 0,01529 Plant 2 RMU2B to offices TRF (XLPE) 0,23175 0,03475 Table 3: Cable parameters. Load kva Voltage pf Load 1 1000 400 V 0,75 inductive Load 2 1000 400 V 0,75 inductive Load 3 1000 400 V 0,75 inductive Load 4 1000 400 V 0,75 inductive Load 5 1000 400 V 0,75 inductive Load 6 1000 400 V 0,75 inductive Load 7 315 400 V 0,75 inductive Load 8 1000 400 V 0,75 inductive Load 9 1000 400 V 0,75 inductive Load 10 1000 400 V 0,75 inductive Load 11 1000 400 V 0,75 inductive Table 4: Load parameters. The sub-transient period, which occurs directly at the fault point and only lasts for a few cycles The transient period, which occurs for tens of cycles The steady-state period, which will last for a longer time, usually until there is a change in the system such as a line-fail or if a circuit breaker is opened. Fig. 1 shows the different states. Types of faults Fault currents may involve all three phases in a symmetrical manner, or may be asymmetrical where usually only one or two phases are involved. Faults may also be caused by either short-circuits to earth or between live conductors, or may be caused by broken conductors in one or more phases. Sometimes simultaneous faults may occur involving both shortcircuit and broken conductor faults (also known as open-circuit faults). Symmetrical three phase faults This study will be confined to symmetrical three phase faults as they are the most severe faults that can occur in a power system. These faults give the maximum short-circuit currents (SCC) and fault MVA. Hence, this worst-case result is then used as the basis to select the shortcircuit capabilities of switchgear from manufacturers tables. A three phase fault is a function of three equal fault impedances to the three phases as shown in Fig. 2. If = 0 then the fault is called a solid or bolted fault. These faults can be of two types: (a) phase to phase to phase to ground (PPPG) fault or (b) phase to phase to phase (PPP) fault. The system will remain balanced because all three phases are affected equally. Since the system is balanced we only need to know the positive sequence to analyse the fault. A single line diagram can be used, as energize - December 2013 - Page 50

CS1 11 kv Main sub to plant 1 19,78119 1,03824 Plant 1to T 2 (primary) 19,13223 1,00418 T 2 (secondary) to 400 V busbar 19,13223 27,6154 Plant 1 400 V busbar 11 kv Main sub to plant 1 1 19,74469 1,03633 Plant 1 to T 3 (primary) 19,09561 1,00226 T 3 (secondary) to 400 V busbar 19,09567 27,56223 Pack shed 400 V busbar 11 kv Main sub to pack shed 20,28911 1,06490 Pack shed to T 1 (primary) 19,42322 1,01945 T 1 (secondary) to 400 V busbar 19,42322 28,03500 Pack shed to plant 2B cable 1,01004 0,05301 11 kv Main sub to plant 3 19,98117 1,04874 Plant 3 to T 4 (primary) 19,31990 1,01403 T 4 (secondary) to 400 V busbar 19,31990 27,8858 11 kv Main sub to plant 3 19,48697 1,02280 Plant 3 to T 5 (primary) 18,82516 0,99612 T 5 (secondary) to 4 00 V busbar 18,82516 27,17177 11 kv Main sub to plant 2A 22,27746 1,16926 Plant 2A to T 6 (primary) 21,61845 1,13467 T 6 (secondary) to 400 V busbar 21,61845 31,20355 11 kv Main sub to plant 2A 20,88374 1,09611 Plant 2A to T 8 (primary) 20,22329 1,06145 T 8 (secondary) to 400 V busbar 20,22329 29,18981 11 kv Main sub to plant 4 19,61061 1,02929 Plant 4 to T 10 (primary) 18,97866 0,99612 T 10 (secondary) to 400 V busbar 18,97866 27,39334 11 kv Main sub to plant 4 20,39569 1,07050 Plant 4 to T 9 (primary) 19,76584 1,03744 T 9 (secondary) to 400 V busbar 19,76584 28,52953 Plant 2B 400 V busbar Pack shed cable to plant 2B 21,10405 1,10768 Plant 2B to T 11 (primary) 20,90265 1,09710 T 11 (secondary) to 400 V busbar 20,90265 31,17038 Office transformer 400 V busbar Pack shed to plant 2B 7,0409 0,41489 Plant 2B to office transformer (primary) 7,15948 0,37577 Office transformer (secondary) to 400 V busbar 7,15948 10,33381 Table 5: 80% load capacity. Fig. 3: Equivalent single phase circuit. all three phases are equal but displaced by 120 [4]. where: I sc3 = Three-phase short-circuit V ph = Phase voltage [1] Z SC = Positive sequence impedance per phase Power system analysis tools Complete method The complete method is utilised to perform the short-circuit study. This method is commonly known as the superposition method and is summarised in Fig. 4. Modelling consideration The network consists of an ideal 11 kv voltage source with no internal impedance. Two winding transformer The two-winding transformer is modelled with a positive sequence network. Shortcircuit voltage Uk (%) and ratio X/R or copper losses. The magnetising circuit is not included due to the magnetising current being negligible [5]. Cables The positive sequence network for cables is modelled identically using the nominal π-method. The values for positive and negative is assumed to be equal. The sequence impedances consist of series resistance R in ( /km), series reactance X ( /km) [5]. DIgSilent neglects the capacitance in the positive and negative sequence networks when the nominal π-method is used. The positive sequence network of the simulation is illustrated in Fig. 5. Linear load The loads are modelled as fixed impedance loads. The loads contain static components which do not provide short-circuit contribution to a fault. Network parameters The parameters for the AC voltage source, energize - December 2013 - Page 52

CS2 11 kv Main sub to plant 1 19,93246 1,04618 Plant 1to T 2 (primary) 19,12487 1,00380 T 2 (secondary) to 400 V busbar 19,12487 27,60438 Plant 1 400 V busbar 11 kv Main sub to plant 1 19,89601 1,04427 Plant 1 to T 3 (primary) 19,08833 1,00188 T 3 (secondary) to 400 V busbar 19,08833 27,55163 Pack shed 400 V Busbar 11 kv Main sub to pack shed 20,49779 1,07585 Pack shed to T 1 (primary) 19,42010 1,01929 T 1 (secondary) to 400 V busbar 19,42010 28,03050 Pack shed to plant 2B cable 1,25207 0,06572 11 kv Main sub to plant 3 20,14194 1,05718 Fig. 4: Superposition calculation method flow diagram. Plant 3 to T 4 (primary) 19,31890 1,01398 T 4 (secondary) to 400 V busbar 19,31890 27,88443 11 kv Main sub to plant 3 19,64804 1,03125 Plant 3 to T 5 (primary) 18,82418 0,98801 T 5 (secondary) to 400 V busbar 18,82418 27,17037 Fig. 5: Short-circuit nominal π model for a cable in DIgSilent. transformers, cables and loads are indicated in Tables 1, 2, 3 and 4. Simulation case study Three case studies were conducted. For all studies, firstly a load flow investigation was conducted to obtain pre-fault conditions. Secondly, a short-circuit study was performed using the superposition calculation method to attain maximum fault currents and fault levels. Case study 1 (CS1) For the first case study a symmetrical threephase fault on plant 1 400 V busbar, and then plant 2A 400 V busbar was performed at 80% full load capacity. Case study 2 (CS2) For the second case study a symmetrical three-phase fault on plant 1 400 V busbar, and then plant 2A 400 V busbar was performed 100% full load capacity. Case study 3 (CS3) A symmetrical three-phase fault was performed when plant 2 is fed via plant 1, which is normally open. Results Only the short-circuit power and phase 11 kv Main sub to plant 2A 22,43692 1,17763 Plant 2A to T 6 (primary) 21,61648 1,13457 T 6 (secondary) to 400 V busbar 21,61648 31,20071 11 kv Main sub to plant 2A 21,04403 1,1453 Plant 2A to T 8 (primary) 20,22144 1,06135 T 8 (secondary) to 400 V busbar 20,22144 29,18714 11 kv Main sub to plant 4 19,74972 1,03659 Plant 4 to T 10 (primary) 18,96337 0,99532 T 10 (secondary) to 400 V busbar 18,96337 27,37127 11 kv Main sub to plant 4 20,53350 1,07773 Plant 4 to T 9 (primary) 19,74998 1,03661 T 9 (secondary) to 400 V busbar 19,74998 28,50664 Plant 2B 400 V busbar Pack shed cable to plant 2B 21,14742 1,10995 Plant 2B to T 11 (primary) 20,89735 1,09683 T 11 (secondary) to 400 V busbar 20,89735 30,16272 Office transformer 400 V busbar Pack shed cable to plant 2B 8,0896 0,42414 Plant 2B to office transformer (primary) 7,15567 0,37558 Office transformer (secondary) to 400 V busbar 7,15567 10,32832 Table 6: 100% load capacity. energize - December 2013 - Page 53

cable between the main sub and plant 4 being buried in the ground does not comply with regulations. Buried cables must be mechanically protected, e.g. by being armoured or by being laid in a protective pipe, or otherwise protected by laying concrete slabs above the cable 300 400 mm below ground level. ABC cables are not meant to be buried, although this is done in some instances. It is advisable to use Bucholtz relay protection on transformers rated at 1 MVA or higher. This type of protection can give early warning of faults developing within the transformer thus preventing catastrophic failure. The low voltage switchgear on the secondary of the transformers should be rated at, or higher then obtained values of fault level on the 400 V busbar. 11 kv Main sub to plant 1 21,49228 1,12805 Plant 1 to T 1 (primary) 19,04769 0,99974 T 1 (secondary) to 400 V busbar 19,0476 27,49297 Fig. 6: Kromco's electrical network. Plant 1 to plant 2A 21,75727 1,14196 Plant 2Ato T 6 (primary) 20,96169 1,10020 T 6 (secondary) to 400 V busbar 20,96169 30,25559 CS3 Table 7: Plant 2A fed via plant 1. Cable Size (mm 2 ) Current rating (A) 1 s short circuit rating XLPE 25 140 3,58 XLPE 35 170 5,01 XLPE 95 290 13,6 ABC 50 160 currents results were obtained for each case study. Table 5 indicates the results of the total short circuit power and the short circuit currents at 80% load capacity. Table 6 indicates the results of the total short-circuit power and the short-circuit currents at 100% load capacity. Table 8: Typical cable ratings. Table 7 indicates the results of the total short-circuit power and the short-circuit currents when plant 2A is fed via plant 1. Analysis of results Table 8 compares cables for short-circuit results. All cables will operate well within their rated short-circuit capacity. The ABC At 100% load capacity the transformers are heavily loaded from about 95,06 to 95,11% rated capacity which will operate the protection continuously if transformers are overloaded. Conclusion Fault analysis plays a vital role in a power system analysis as it is used to determine the appropriate protection scheme for a power system. The short circuit current based on the rated equipment values are used in properly determining the minimum protection requirement as the obtained fault current is the maximum fault current that may occur within the system. Thus, the obtained fault levels in this paper acts as prerequisite for protection coordination studies. Despite limitations of obtaining the necessary data PowerFactory simulations can be a guide line on loading of the network and short-circuit currents flowing in the network, for the system expansions. A thorough investigation can be conducted in future with cost implications for attaining time synchronous data loggers for measuring real time data of the different loading conditions of the plant. Therefore contingency plans can be drafted on a more efficient manner on the operation of the plant. References [1] MH Hairi, H Zainuddin, MHN Talib, A Khamis and JY Lichun: An investigation of short circuit analysis in Komag Sarawak operations factory, World Academy of Science, Engineering and Technology, 2009. [2] IEEE Violet Book: Recommended practice for calculating short-circuit currents in industrial and commercial power systems, 2006. [3] IEC 60909-0: Short-circuit currents in threephase ac systems, 2001. [4] John J Grainger, William Stevenson. [5] DIgSILENT PowerFactory: DIgSILENT PowerFactory version 14v0E Technical Reference, DIgSILENT, 2004. Contact Bantubonke Matika, Metrorail, Tel 021 507-2003, bmatika@metrorail.co.za energize - December 2013 - Page 54