Technical Capabiles in Egypt Planning Recycling Engineering Information Technology Services Project Management for Industrial Plants Integral Plant Maintenance Erection and Installation Commissioning On-Call Service The right people - Technical Services for Capital Investments
Industrial Technical Services For Plants in Egypt Life Cycle of a Plant Costs Planning Phase Construction Phase Operational/ Production Phase Shutdown Phase time System design Planning Projection Engineering Project management Infrastructure services Erection Commissioning Workshop services Maintenance Engineering Project management Erection Commissioning Workshop services Engineering Project management Disassembly Workshop Services Recycling
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Polygon Construction Block 44- Westtown Siac Electro-mechanical supply & Installation Package 6 th of October 133,000,000 3/11 9/12 Spinneys Hypermarket Spinneys Electrical Supply & Installation Package 6 th of October 22,000,000 5/01 8/10 El- Salam Makro cash & carry Makro cash & carrry Egypt Electrical Supply & Installation Package El Salam City 8,100,000 01/10 05/10 Renovation of Old & New Cataract Hotel Arabian Construction Company Electromechanical Works Aswan 115,000,000 09/09 05/10 Saint Gobain Glass Factory Saint Gobain Glass Factory MCC/PCC Ain El- Sokhna 16,000,000 08/09-03/10 Pharoah Gold Mines Electromechanical Package E&I Installation Package Marsa Alam, Red Sea 49,000,000 04/09 08/09
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Mena House Oberoi Hotel Phase II B EGOTH Turnkey Electromechanical Works Giza 15,150,000 12/08 07/09 New Cairo-Alexandria Showrooms Project Bonyan for Development and Trade Electro- mechanical Works 6th of October City 55, 00,000 09/08 05/09 Shoubra El Kheima Water Treatment Plant Cairo Alex. Potable Water Organization (CAPWO) Turnkey Electromechanical Works Cairo 46,000,000 09/08 01/11 Cairo Regional Processing Center HSBC Bank Turnkey Electromechanical Works Smart Village 72, 000, 000 03/08 05/09 Arab Bank Gameat El Dowal Branch SIAC / Arab Bank Turnkey Electromechanical Works Giza 55,000,000 2/08 6/09
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Al Obour Shopping Mall (Carrefour) MAF for Hypermarkets Turnkey Electromechanical Works Al Obour 32,000,000 2/08 07/08 Smart Village B145 Building SIAC / Ministry of Communication Turnkey Electromechanical, Finishing Giza 27,000,000 10/07 10/08 Mena House Oberoi Hotel Wings D & E EGOTH Turnkey Electromechanical & Civil Works Giza 26,000,000 Cairo Water Intake Cairo Alex. Potable Water Organization (CAPWO) Turnkey Electrical Works Cairo 66,000,000 11/07 05/10 Heliopolis Ball Room Gulf Egypt for Hotels & Tourism Turnkey Electromechanical, Finishing Heliopolis Cairo 18,500,000 09/07 09/08 Barclays Bank Call & Data Center Barclays Bank Egypt SAE Turnkey Electrical Works Maadi Cairo 8,000,000 09/07 10/07 Savola United Sugar Co. Electrical Instrumentation Ein Sokhna 1,800,000 08/07 12/07 Cataract Hotel EGOTH Turnkey Electrical Works Aswan 4,150,000 09/06 09/07
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Gas Compression Station - EMG Siemens Power Generation Electrical Instrumentation & Equipment Installation El Arish 8,000,000 04/07 08/07 Golden Pyramids Plaza A7 Building Golden Pyramids Turnkey Electromechanical, Finishing Cairo 65,000,000 03/07 01/08 Grand Egyptian Museum Ministry of Culture Turnkey Electromechanical Works Giza 84,000,000 10/06 12/07 Jolie Ville Summit Hotel Naama Golf for Touristic Investments Turnkey Electromechanical, Finishing Sharm El Sheikh 90,000,000 06/06 03/07 Post Office Building Ministry of Communication Turnkey Electromechanical Works Giza 18,000,000 02/05 09/07 Mena House Oberoi Hotel Energy Building EGOTH Turnkey Electromechanical & Civil Works Giza 40,000,000 01/06 07/07 Sharm El Sheikh International Congress Center Naama Golf for Touristic Investments Turnkey Electromechanical, Finishing Sharm El Sheikh 103,000,000 07/05 04/06
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Pepsi Cola Pepsi Cola Egypt Turnkey Electromechanical Works Dandy Mega Mall Carrefour Hypermarket MAF Turnkey Electromechanical Works Nasr City, Cairo Tanta Cairo-Alex Desert Road 6,000,000 01/06-01/07 33,000,000 02/05 07/05 United Gas Derivate Co. (UGDC) UGDC Turnkey Electrical Works Damietta 1,500,000 06/04 01/05 Arab Bank Gomhoria Branch Arab Bank Turnkey Electromechanical Works Cairo 30,000,000 05/04 12/05 Master Foods Plant Master Foods Turnkey Electromechanical Works 6th October 9,000,000 03/04 12/04 Children Oncology Hospital AFNCI Turnkey Electromechanical Works Cairo 120,000,000 04/04 09/05 Egyptian LNG Project Bechtel Overseas Corporation Electrical and Instrumentation Works IDKU El Behaira 18,000,000 01/04 04/05
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End United Gas Derivate Co. (UGDC) UGDC Turnkey Electrical Works Port Said 2,200,000 01/04 01/05 Magic Planet MAF Supply & Erection of Electro-mechanical Abu Zaabal DSD Ferrometalco Electrical &Instrumentation Erection Cairo North Power Plant 220 KV GIS Siemens PTD Electro-mechanical Works Smart Village A7 Building ADCOM Supply & Erection of Electro-mechanical Works Smart Village - Ministry of Communication Office Building B1 Ministry of Communication Electro-mechanical Works Airport Mall Cairo Airport Company Electro-mechanical& HVAC Systems Alex. City Center Abu Zaabal Ismailia Canal Smart Village, Cairo Cairo Airport 2,500,000 12/03 03/04 1,600,000 11/03 08/04 850,000 11/03 04/04 15,000,000 10/03 08/04 33,000,000 10/03 07/04 20,000,000 08/03 07/04
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Locatio n Value in LE Start / End Jolie Ville Congress Victoria United Building Hotels Co. Electrical Works Sharm El Sheikh 2,000,000 05/03 08/03 Villa 29 Golf Resort Naama Golf for Touristic Investments Electrical Works Sharm El Sheikh 1,000,000 05/03 08/03 Steignberger Dahab Resort Misr for Tourism Development SAE MEP Works for Buildings Dahab 5,200,000 11/02 11/03 East Delta Agricultural Services Project Drinking water Components Alex. City Center Carrefour Hypermarket World Bank, IFAD Electro-mechanical& Piping Works Port Said MAF Turnkey MEP Works Alex. 9,000,000 09/02 12/04 13,000,000 06/02 12/02 Pfizer Office Building Pfizer Africa & Middle East Turnkey Electromechanical Works Cairo 16,000,000 03/02 02/04 Borg El Arab Flour Mill Arabian Co. for Flour Milling & Food Industry Turnkey MEP Works & Electromechanical Process Equipment Erection Alex. 5,200,000 02/02 08/04
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Ezz Flat Steel Ezz Heavy Industries Water Pumping Stations Suez 1,000,000 11/01 05/02 Egyptian Automobile & Touring Club Egyptian Automobile & Touring Club Electrical Works Cairo 400,000 08/01 04/02 Hebi Pharmaceutical Plant Hebi Raw Turnkey Electromechanical Works Qena 50,000,000 08/01 08/03 Ministry of Construction Ministry of Construction Renovation of Power House Cairo 600,000 07/01 08/03 White Cement Factory ASA ASEC Electrical Works and Low Current Systems Quena Cement Factory ASA ASEC Electrical Works and Low Current Systems Al Arish Sinai Quena 900,000 07/01 11/01 1,500,000 06/01 10/01 Flour Mill Wadi El Melouk Electromechanical installation 6th October Giza 1,300,000 03/01-07/01
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Ministry of Finance Ministry of Finance Fire Fighting Works Cairo 1,500,000 02/01 04/02 Electro-George Metals Factory Electro-George Metals Factory Electrical Works and Low Current Systems Ismailia 1,800,000 07/00 03/01 Steignberger Dahab Resort Misr for Tourism Development SAE Turnkey for External Utilities Networks Dahab 5,100,000 05/00 11/00 Grey Cement Factory ASA ASEC Electrical Works andlow Current Systems Gas Turbine Power Plant Siemens AG and Flow Waste GmbH Electrical Erection Works Johnson Wax Factory Johnson Wax Egypt Electromechanical and Industrial Works Al Arish Sinai Al Amerya Free Zone Alex. Belbais Desert Road 2,200,000 03/00 09/00 3,100,000 02/00 08/00 2,700,000 02/00 08/03 Midelec Power Station Midor Electrical & Instrumentation Works Alex. Free Zone 1,101,600 02/00-08/00
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End Midor Refinery TECHNIP TTIL SNC Electrical works and Commissioning DSD - Ferrometalco - New Factory in Belbeis Al Amerya Free Zone Alex. DSD Ferrometalco TurnKey Electrical Works Belbeis 3,200,000 2,500,000 01/00-09/00 05/99-09/99 Suez Fertilizer Plant Krupp Uhde TurnKey Works for HVAC Ain Sukhna 3,800,000 02/99-12/99 Siemens New Head- Quarters Alex. National Iron and Steel Making Plant & Hot Strip Rolling Mill Procter & Gamble - Various Packages Alex. National Iron & Steel - 220 Kv Substation Siemens Ltd. Turnkey MEP Works Mohande ssin Cairo Alex. National Iron & Steel Co. Procter & Gamble Egypt Contrasteel /Alex. NationalIron & Steel Co. E & I Works Electromechanical Works for Buildings and Process Area E & I Works Alex. 6th of October City Alex. 7,000,000 10/99-06/00 11,900,000 11/98-10/99 2,700,000 11/98-12/99 3,000,000 11/98-08/99
Projects Executed & Under Execution in Egypt By Siemens Technologies S.A.E I IS IN. Description Customer Name Work Description Location Value in LE Start / End East Quantara- 220 Kv Substation E.E.A. Complete Electromechanical Installation& Commissioning Neweiba - 220 Kv Station E.E.A Complete Electromechanical Work East Quantara Neweiba 1,000,000 01/98-11/98 1,000,000 01/98-11/98 Taba - 220 Kv Station E.E.A Complete Electromechanical Work Taba 1,000,000 01/98-11/98 Sharm El Sheikh 220 Kv Substation E.E.A Complete Electromechanical Work Sharm El Sheikh 1,000,000 01/98-11/98 Oyoun Mousa T.P.P 2 x 330 MW E.E.A Turbine Island Oyoun Mousa 98-00 Sidi Kerair T.P.P 2 x 330 MW E.E.A Turbine Island E & I Works 97-98
Children Oncology Hospital Detailed engineering. Supply & installation works Testing, pre-commissioning, Commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works.Fire Alarm, Nurse Call, CCTV, Clock system
Mena House Cairo Oberoi Hotels Detailed engineering. Supply & installation works Testing, pre-commissioning, Commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works: - Energy Building - Guest Building B&C Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Telephone, Fire Alarm, Public Address, CCTV, Clock
National Post Authority - B146 Smart Village Basic & detailed engineering. Project management & coordination Supply & installation works. Testing, pre-commissioning, commissioning & start up. Basic & Detailed Engineering, Supply, Installation & Commissioning of all the Electromechanical Works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System / Plumbing Works Fire Fighting System Fire Alarm, Security, Access, Telephone & Audio Visual Systems.
Ministry of Telecommunication - (Smart Village) Detailed engineering. Supply & installation works. Testing, pre-commissioning, commissioning & start up. Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Fire Alarm, Security, Access, Telephone & Data, CCTV & Audio Visual Systems.
Sharm El Sheikh International Conference Complex (SICC) Basic & detailed engineering. Project management & coordination Supply & installation works. Testing, pre-commissioning, commissioning & start up. Basic & Detailed Engineering, Supply, Installation & Commissioning of all the Electromechanical Works, together with Finishing Works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Fire Alarm, Security, Access, Telephone & Data, CCTV, Clock, Intrusion, Sound Conference & Audio Visual Systems.
Cairo International Airport Mall Detailed engineering. Supply & installation works. Testing, pre-commissioning, commissioning & start up. Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Fire Alarm, Telephone & Data, CCTV, Audio Visual & Clock Systems.
Pfizer Africa & Middle East New Office Building Detailed engineering. Supply & installation works Testing, pre commissioning, commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Low Current, Security, Audio Visual, Telephone & Data Systems.
Arab Bank Gomhouria Branch Detailed engineering. Supply & installation works Testing, pre-commissioning, Commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Telephone, Fire Alarm, Public Address, CCTV, Clock, Intrusion & Burglary Alarm, Access Control Systems.
Grand Egyptian Museum Phase II w Detailed engineering. w Supply & installation works w Testing, pre-commissioning, commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works: w Power Supply, Distribution System & Lighting. w Building Management System. w HVAC System w Plumbing Works w Telephone, Data, Intercom, CCTV & Access Control Systems
HSBC Regional Office, Smart Village Detailed engineering. Supply & installation works Testing, commissioning & start up Contract Description MV Power solutions (Transformers, MDB) Bus Duct and cabling Systems LV Cables, Power Supply, Distribution & Lighting Systems Plumbing and Fire Fighting System HVAC and BMS Voice & Data, Intercom, CCTV, Access Control, MATV Building Description: Basement, Ground and three Typical Floors Total area of the building is 21,000 m2
Barclays Bank Maadi Call & Data Center Detailed engineering. Supply & installation works Testing, pre-commissioning, Commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works regarding the execution of the Maadi Call & Data Center Power Supply, Distribution System & Lighting. HVAC System Fire Fighting Works Low current Networks
Carrefour Hypermarket Alex. City Center Detailed engineering. Supply & installation works. Testing, pre-commissioning, commissioning & start up. Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Low Current, Security & Telephone Systems, including Wiring Duct System
Carrefour Hypermarket Dandy Mega Mall Basic & detailed engineering. Supply & installation works. Testing, pre-commissioning, commissioning & start up. Basic Detailed Engineering, Supply, Installation & Commissioning of all the Electromechanical Works: MV & LV Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Fire Alarm, Security, Access, Sound & Telephone Systems.
Carrefour Hypermarket El Obour City Basic & detailed engineering. Supply & installation works. Testing, pre-commissioning, commissioning & start up. Basic Detailed Engineering, Supply, Installation & Commissioning of all the Electromechanical Works: MV & LV Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Fire Alarm, Security, Access, Sound & Telephone Systems.
Fairmont Heliopolis New Ballroom, Cairo Detailed engineering. Supply & installation works Testing, pre commissioning, commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Low Current, Security, Audio Visual, Telephone & Data Systems.
United Gas Derivate Company (UGDC), Port Said Plant Design Detailed engineering. Manufacturing & fabrication, factory test. Supply, testing, commissioning & start up Turnkey CCTV System Project, including the following items: Interactive video management system. Pan & till monitoring units. Certified zone 1, Gas group IIA, Hazardous area. Fiber optic transmitter/receiver units. Control unit management center.
United Gas Derivate Company (UGDC), Damietta Plant Design Detailed engineering. Manufacturing & fabrication, factory test. Supply, testing, commissioning & start up Turnkey CCTV System Project, including the following items: Interactive video management system. Pan & till monitoring units. Certified zone 1, Gas group IIA, Hazardous area. Fiber optic transmitter/receiver units. Control unit management center.
Saint Gobain Glass Egypt Sokhna Plant Design Detailed engineering. Manufacturing & fabrication, factory test. Supply, testing, commissioning & start up LV Package, MCCs, PCCs Cable Networks / Cable Ways Step down transformers Profibus Network Fibre Optics Network
Gold Mine SUK_180 Gold Mine SUK_190 Detailed engineering. Supply & installation works. Testing, pre-commissioning, commissioning & start up. Detailed Engineering, supply, installation & commissioning of all the electromechanical Works. Equipments Control PLCs LV Panels MV Panels Transformers Diesel Generator Mechanical System Piping Instrumentation
MAKRO Cash and Carry Hypermarket Detailed engineering. Supply & installation works. Testing, pre-commissioning, commissioning & start up. Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Low Current, Security & Telephone Systems, including Wiring Dect System
Our Security Solutions Video surveillance Access control Intrusion detection Fire Alarm System Fire Fighting System SiteI surveillance Command & Control
Security Solutions offers a wide range of Security Solutions Access Control Intrusion Intelligent Video Management Security Management System Command and Control Our Integrated Security Solutions and Services Siveillance SiteIQ Fire Alarm System Fire fighting System C C
Grand Egyptian Museum Phase II w Detailed engineering. w Supply & installation works w Testing, pre-commissioning, commissioning & start up Detailed Engineering, supply, installation & commissioning of all the electromechanical works: w Power Supply, Distribution System & Lighting. w Building Management System. w HVAC System w Plumbing Works w Telephone, Data, Intercom, CCTV & Access Control Systems
Jolie Ville Summit Hotel, Sharm El Sheikh Detailed Engineering, Supply, Installation & Commissioning of all the Electromechanical Works, together with Finishing Works: w Power Supply, Distribution System & Lighting. w Building Management System. w HVAC System w Plumbing Works w Fire Fighting System w Fire Alarm, Telephone & Data, CCTV, MATV, DJ & Public Address Systems w Detailed engineering. w Project coordination w Supply & installation works. w Testing, pre-commissioning, commissioning & start up.
Golden Pyramids Plaza Stay Bridge City Stars w Installation works & Supply of security works w Commissioning w Testing & Precommissioning Various security packages including the following items: w IP based CCTV system. w Fire Alarm system.
Pharaoh Gold mine Marsa Allam w Detailed engineering. w Supply & installation works. w Testing, pre-commissioning, commissioning & start up. Detailed Engineering, supply, installation & commissioning of the security systems works: Equipments Control PLCs LV Panels MV Panels Transformers Diesel Generator Mechanical System Piping Instrumentation Access Control System CCTV
The Polygon Construction Block 44 Westown Business Park Cairo/Alex Desert Road Detailed Engineering, supply, installation & commissioning of all the electromechanical works: Power Supply, Distribution System & Lighting. Building Management System. HVAC System Plumbing Works Fire Fighting System Fire Alarm, Security, Access, Telephone & Data, CCTV Project is including the following: 9 (Class A) office buildings, a business hotel, & a service appt building. The project occupies a total land area of 33,000 sq mt., a total buildup area of 86,000 sq. mt. situated km38 of Cairo/alex desert road It offers a parking area of 1700 cars capacity, banks, restaurants, & a full gym equipped with swimming pool & squash courts
Egyptian LNG Project Idku, Beheira
Egyptian LNG Project Idku, Beheira
HSBC Regional Office Bank LEED Certificate