OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London.



Similar documents
SAFE REMOVAL AND DISPOSAL OF ASBESTOS CEMENT BUILDING PRODUCTS

ASBESTOS IN THE HOME

Procedures for Cutting and Handling of Asbestos Cement Pipe. City of Richmond Public Works Operations

Demolition & Construction Management Plan

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard

Job safety analysis Installing wall frames and roof trusses on-site

Pollution & Noise from Demolition & Construction Sites

University Arms Hotel, Cambridge

Construction OS&H Working at height

A: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION

SAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399

have been provided with information on whether they do or do not contain asbestos before starting work;

SITE CONTRACTOR PROCEDURES

Description of the Task/Activity: General door/window fitting/replacement. Start Date/Time: Site Address/ Location: Finish Date/Time:

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY

Asbestos Management Policy (Version 3)

ASBESTOS in state and local government

Level 1 Award in Health and Safety in a Construction Environment

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

ASBESTOS AND THE HOME RENOVATOR. A basic guide on what you need to know about asbestos

Asbestos in your home

Independent Contractor Policy

Safety Training Needs Assessment

Policy on the Management of Asbestos

CONTRACTOR INDUCTION HANDBOOK

Environmental Protection Information Sheet: 2. Advice on Asbestos

Table of Contents Introduction How to Use This Manual How to Do a Facility Audit

Document ref: MG(M)201 Version no: 01 Page no: 1 / 12. Contractor rules

The asbestos crisis. Why Britain needs an eradication Law. Background. Levels of mortality

The asbestos crisis Why Britain needs an eradication law

BILL WHYTE FLOORCOVERINGS LTD UNIT 5 KINGS COURT KING ST LEYLAND LANCS PR269RL. Tel: METHOD STATEMENT

WOLVERHAMPTON WASTE SERVICES GUIDANCE FOR THE SAFE REMOVAL, COLLECTION AND DISPOSAL OF MATERIALS CONTAINING ASBESTOS OR ASBESTOS CEMENT

Policy for the Management of Asbestos in the Workplace

HATFIELD TOWNSHIP DEMOLITION PERMIT APPLICATION PROCEDURES

Construction and Civil Work Management

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW

Contractor s Safe Working Agreement

Health & Safety Policy For Locations Hosting Film Production Companies

Policy for the Management of Asbestos in Buildings

Safety and Environmental Information for External Companies Koehler Oberkirch

METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS

CRITERIA FOR REGISTRATION AS ASBESTOS CONTRACTOR

1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY

Working at height A brief guide

WHS CONTRACTOR MANAGEMENT PROCEDURE

Pollution Incident Response Management Plan

UBC Plant Operations Asbestos Work Procedures April 2004

Asbestos Management & Abatement

WHS Contractor Management Procedure

Which generic risk assessments are provided? Construction Risk. Assessments Plus. ervices

DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements Asbestos Abatement Project Exemptions

Discharging of Scrap

Part 2. Overview. Risk management. Workplace health and safety legislation. How should asbestos exposure be managed? Identifying asbestos hazards

ASBESTOS MANAGEMENT POLICY

LIVING WITH FIBRO JUNE 1998 WORKCOVER NSW HEALTH AND SAFETY NOTES. WorkCover. Watching out for you.

Colorado Department of Public Health And Environment Hazardous Materials and Waste Management Division

What is Asbestos Cement and how is it identified?

ASBESTOS REGULATIONS Government Notice No 155 Gazette No dated 10 February 2002

How to Safely Remove Asbestos

SILICA DUST HAZARD ASSESSMENT & WORK PLAN

Management of asbestos in recycled construction and demolition waste

Regulatory Services. Asbestos in the Home. What is asbestos?

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS

Construction Notification and Start-Up

Tremline Pty Ltd trading as The Hills Bark Blower

Asbestos

Asbestos is found naturally in rock formations around the world. It is made up of lots of small fibres.

STANDARD OPERATING INSTRUCTION. Safe Handling and Removal of Asbestos Cement Pipes Procedure

Occupational health and safety specification for construction works contracts

Asbestos in the home. Health and safety in the home. Asbestos in the home A

Temporary Batch Plants

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

DEMOLITION PERMIT CHECKLIST* B.H.M.C. Section

SAFETY AND ENVIRONMENTAL INFORMATION FOR EXTERNAL COMPANIES. Koehler Kehl

Rutgers Environmental Health and Safety

ASBESTOS MATERIALS IN SCHOOLS

HOW TO SAFELY REMOVE ASBESTOS

RSPH Level 3 Certificate in Asbestos Project Management. February Guided Learning Hours 2 Prior Learning Hours

Managing the risk of falls while working on roofs in housing construction

PAINT REMOVAL SYSTEM PAINT REMOVAL SPECIFICATION SAFE WORK METHOD STATEMENT FOR LEAD PAINT REMOVAL

Schneps, Leila; Colmez, Coralie. Math on Trial : How Numbers Get Used and Abused in the Courtroom. New York, NY, USA: Basic Books, p i.

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material

Construction Management Statement. Introduction. Contents

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

For ease of reference the clauses are arranged in 12 sections as follows:-

Tool Box Talk. Forklift Operations

Asbestos Disposal in the Northern Territory

KEEP ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET THIS GUIDE

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT

Control Provisions under the Air Pollution Control Ordinance

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)

CHAPTER 10. FALL PROTECTION PROGRAM

Safety Systems Review Facilities Management Guidance and specification Version

PERSONAL PROTECTIVE EQUIPMENT HAZARD ASSESSMENT, EQUIPMENT SELECTION AND TRAINING DOCUMENTATION

UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE

Control of Asbestos. Blue crocidolite Brown amosite White chrysotile

Traffic Management Issue 1.0 Revision: v2 October 2014

How a client and contractor working together can benefit both partners, and ensure work is carried out with good standards of health and safety.

Transcription:

OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London. N5 1XB Document Control Revision No. Date Approved Signature 1

Table of Contents PROJECT SPECIFIC DETAILS / ARRANGEMENTS SECTION 1 SECTION 2 SECTION 3 Project Team Scope of Works Method of Works SECTION 4 Training SECTION 5 Emergency Arrangements 2

Section 1. Project Team Client: TBC Independent Safety Solutions Address: Address: Uplands House. Warren Road, Rettendon Common, Essex. CM3 8DF Contact: Name: Tel: Mobile: Email: Name: Tel: Fax: Mobile: Email: Name: Chris Webber Tel: 01245 403313 Fax: 01375 677638 Mobile: 07545 921869 Email: independentsafetysolutions@live.co.uk 3

Section 2 Scope of Works This is an outline tender stage method statement which will be developed to construction phase upon award of the works. It should be noted that this Method Statement is INDICATIVE only. The works generally consist of the following elements: Attendance during the construction of the reinforced concrete wall to support the existing distressed party boundary wall. Removal of the asbestos cement roof covering and mansard panels. Erection of a scaffold platform and dust screen to rear elevation. Removal of internal M&E services. Demolition of the building to ground slab level. 4

SECTION 3 Method of Works. Plant Assigned to the project: 1 x 360 Excavator with pulveriser 1 x 25 Tonne Dump Truck 1 x Mobile Elevated Working Platform 1 x Crushing Station 1 x Hygiene Unit 1. Upon arrival on site operatives will receive a site specific induction detailing the arrangements in the site specific RAMS. Operatives will be required to sign the site induction register to confirm that the induction has been received and understood. 2. Site access will be via the main entrance gates off Ronald road. 5. Operatives will don the following PPE before entering the building: Hard Hat High Visibility Tabard Safety Footwear Gloves Safety Goggles Ear Protection Ori-nasal Half masks rated at FFP3. Attendance during the construction of the RC retaining wall. i) Operatives will carefully clear overgrown vegetation around the disused steel store by means of handheld tools to reduce likelihood of further structural distress. 5

ii) The steel store will be accessed and the contents emptied into a waste skip. The exact contents are not known at this stage as access has not been possible. Any items that can be recycled will be segregated and placed in an appropriate skip. iii) The empty steel store will be lifted onto a flatbed lorry by means of a hiab and carted from site for recycling. iv) The structural engineer will be invited to inspect the exposed section of the boundary wall. v) The principle contractor will commence construction of a secondary reinforced concrete wall to provide support to the existing distressed brickwork wall. Removal of Internal M&E i) The PC will arrange for the disconnection of all electrical, gas and water services. ii) The PC will issue a permit to work confirming the extent of service isolations. iii) Operatives will enter the building and remove all high level air conditioning units, water storage tanks, electrical fittings and the mezzanine floor. Access to high level will be via a suitable MEWP. Where a MEWP is not practicable due to space restraints, a scaffold tower will be utilised. Ladders will only be used for inspection and short duration works. 6

Scaffold Access Platform/Dust & Debris Screen. i) The PC will arrange via the client for residents to remove all garden items a minimum of three metres away from the boundary wall. ii) A specialist scaffold contractor will be appointed to erect a screen and single lift scaffold to the rear of the property within the residents gardens. The working platform will be used by our operatives to remove the asbestos cement panels to the mansard. iii) Scaffold operatives will be required to have received basic asbestos awareness training as part of their competencies. iv) The screen will be erected to ensure that the top extends at least one metre beyond the building ridge. v) Monoflex will be secured to the fan from ground level to the top secured with toggles. vi) Upon completion the scaffold contractor will invite the PC to inspect the structure and provide a completion certificate and scafftag. vii) The scaffold will be inspected prior to each use and by a competent person on a frequency not exceeding seven days. Note/ Design drawings will be required for this scaffold due to the potential imposed loading due to weather conditions. Asbestos Removal. The existing roof is constructed from corrugated asbestos cement sheets. Although this material is non-licensable we will be complying with best practice as detailed in the following documents: Control of Asbestos Regulations 2006 Asbestos Essentials HS (G) 210. i) Operatives will set up suitable water jets to suppress the asbestos cement sfairp. ii) Operatives will don disposable coveralls rated at class 3 (5/6 particulate tight) and ori-nasal half masks for which they have a current face-fit certificate fitted with P3 filters. iii) By means of a MEWP, operatives will access the internal straw board lining and lower to the ground for disposal as contaminated waste. 7

iv) Operatives will spray the straw board with a water /surfactant solution during removal to reduce the likelihood of fibre release. v) An initial high level asbestos cement roof sheet will be carefully broken out, (sacrificial sheet) whilst suppressing to gain access to the ridge tile/capping from inside. vi) Retaining bolts will be carefully cropped and passed through the asbestos cement sheets. vii) The asbestos cement sheets will be carefully lowered inwards and lowered to the ground. viii) Asbestos cement sheets will be placed on the forklift truck and placed in the asbestos skip. ix) The mansard asbestos cement sheets will be accessed via the scaffold to the rear of the property. All sheets will be removed in the same way as the roof sheets, However a sacrificial sheet will not be necessary. x) AC sheets will be passed into the building and placed on the FLT for disposal in the asbestos skip. xi) Upon completion of each shift, operatives will decontaminate in the Hygiene unit provided. Left: Asbestos Cement roof to be removed by hand under suppression. Right: Asbestos Cement sheet to mansard as viewed from within the building. 8

Demolition of Masonry Walls. i) Prior to commencement of works the client s structural engineer is to confirm the structural integrity of the wall. ii) The client and the appointed demolition contractor will agree any temporary shoring that may be required prior to disturbance. iii) Water jets will be utilised for the duration of the demolition works to reduce the likelihood of noise nuisance to the neighbouring residents. iv) Due to the structural distress of the building a 360 degree excavator fitted with a long reach pulveriser will be utilised to demolish the structure. v)the excavator will cause the walls to fall inward within its own footprint to reduce the need for operatives to work on an unstable structure. vi) Arisings will be loaded onto the dumper truck and conveyed to the crushing station. vii) Arisings will be crushed to the clients specification and/or removed from site for recycling. viii) Plant will be secured and immobilised whenever not in use. ix) Upon completion of the demolition works the site will be swept and handed back to the client. Site Clearance. Upon completion of the works all plant and equipment will be removed from site. 9

SECTION 5 Emergency Arrangements 1. The muster point will be located at the entrance gate located off Ronald Road. 2. Upon notification of imminent danger operatives will stop works immediately and make their way to the muster point. 3. The site manager or his deputy will check that all operatives are present by means of the site signing in book. 4. There will be a minimum of two first aiders on the site at all times. 5. Emergency services will be summonsed via the mobile phone network by dialling 999 or 112. 10