UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE
|
|
|
- Jack Heath
- 10 years ago
- Views:
Transcription
1 SECTION SUMMARY OF THE WORK - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. 1.2 WORK COVERED BY CONTRACT DOCUMENTS A. State Project No. T Kent County Asbestos Services Hanger Building (Task 27) Agreement #1542, Asbestos Management Services 56 Sign Shop Lane Dover, Delaware 1. Owner: Delaware Department of Transportation (DelDOT) B. Contract Documents: Prepared for the project by BrightFields, Inc. 801 Industrial Street, Wilmington, DE Conditions that are indicated on the Contract Documents include but are not limited to the following: 1. Master Specification for the Delaware Department of Transportation, dated March 1, 2011 and approved on March 4, 2011; 2. Specification Addenda. Notices & Permits: 1. Job Site Notices & Permits: a. Equal Employment Opportunity b. Material Safety Data Sheets c. Federal Environmental Protection Agency (EPA) 10-day Notification; if required d. State of Delaware (DNREC) 10-day Notification; if required e. Prevailing Wage Determination f. Emergency Planning Procedures g. Sub-Contractors List Work to be performed subsequent to work under this contract: Although DelDOT properties are subject for demolition, only asbestos-containing material (ACM) or ACM contaminated materials are to leave the site. All other building materials will be inventoried to ensure that nothing else leaves the site. Water and electricity will be available for abatement activities onsite. Contractor shall make themselves familiar with available utility and follow the requirements of Section The Contractor will be responsible for making any connections or providing water or electric from the source provided. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
2 Contractor will also be responsible for following all Occupational Health and Safety Administration (OSHA) guidelines for the duration of the project. C. The Work consists of the partial demolition of non- asbestos-containing materials to access the following asbestos-containing materials for proper removal: Roofing Materials i. Asbestos-containing roofing tar and associated felt backing (black) associated with small isolated flat roof accessed from office 214 or the southern HVAC chase located on the second floor estimated 348 square feet (5% Chrysotile). ii. iii. Asbestos-containing silver roof coat associated with the lowest slightly angled roof over Rooms 124 and 128 estimated 570 square feet (1.5% Chrysotile). Asbestos-containing silver roof coat associated with the second level flat roof primarily over the boiler, sign fabrication, and screening rooms estimated 4,008 square feet (2.75% Chrysotile). iv. Asbestos-containing silver flashing and patch coating associated with penetrations throughout the second level flat roof primarily over the boiler, sign fabrication, and screening rooms estimated 4,008 square feet (2.75% Chrysotile). v. Asbestos-containing silver roof coat associated with the third level flat roof over the second level office space estimated 4,967 square feet (3% Chrysotile). vi. Asbestos-containing asphalt rolled roofing associated with the third level flat roof over the second level office space estimated 4,967 square feet (6% Chrysotile). Thermal System Insulation i. Asbestos-containing cementitious ventilation system duct and vent hood located in the screening room and across the 2 nd Level flat roof estimated 65 linear feet of 2 diameter duct, 45 linear feet of 1.5 diameter duct, and 68 square feet on vent hood (15 Chrysotile and 15% Crocidolite). ii. Asbestos-containing joint caulk associated with ventilation system duct and vent hood joint connections located in the screening room and across the second level flat roof estimated 140 linear feet (8% Chrysotile). iii. iv. Asbestos-containing rope gasket associated with ventilation system duct and vent hood joint connections located in the screening room and across the second level flat roof estimated 140 linear feet (15% Chrysotile). Asbestos-containing vibration damper cloth associated with ventilation system duct at the connection to the blower fan located on the second level flat roof estimated 8 square feet (90% Chrysotile). v. Asbestos-containing unused pipe insulation and associated debris located in the attic space above the rear maintenance shop estimated 800 square feet (15% Chrysotile and 8% Amosite). Please note that two unused 4 foot sections of the pipe insulation were observed with damage debris scattered across the attic floor and on items stored in the attic. vi. vii. Asbestos-containing 4 cement pipe insulation located in maintenance shop, office and storage area, above the drop and wood ceiling in the sign fabrication room, through a portion of the screening room, and in the boiler room estimated 250 linear feet (15% Chrysotile and 8% Amosite). Asbestos-containing 2 corrugated pipe insulation located in front office area, portions of the screening room, and in the boiler room estimated 400 linear feet (15% Chrysotile). SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
3 viii. ix. Asbestos-containing mudded elbows and valves associated with the brown paper wrapped fiberglass pipe insulation located in front office area, portions of the screening room, and in the boiler room estimated 25 linear feet (5% Chrysotile). Asbestos-containing silver duct coating associated with the exterior 2 x 2 box duct located on the second level flat roof estimated 1,250 square feet (3% Chrysotile). x. Asbestos-containing asphalt duct coating associated with the exterior 2 x 2 box duct located on the second level flat roof estimated 1,250 square feet (5% Chrysotile). xi. xii. Asbestos-containing duct coating associated with the interior 2 x 2 metal box duct located along the northern wall of the metal room and in the boiler room estimated 450 square feet (10% Chrysotile). Asbestos-containing vibration damper cloth associated with two large air handling units located in the boiler room estimated 20 square feet (80% Chrysotile). xiii. Asbestos-containing vibration damper cloth associated with three connections of the 2 x 2 metal box duct to the centrally located large air handling unit located in the boiler room estimated 24 square feet (80% Chrysotile). Miscellaneous i. Asbestos-containing cementitious siding panels (gray) as exterior and interior walls and as ceilings in room 122 and chase areas adjacent to rooms 113 and 113A estimated 14,870 square feet (15% Chrysotile). ii. Asbestos-containing sheet good (white with small multi-color squares pattern) located in the 1 st floor front office area under carpet estimated 2,000 square feet (8% Chrysotile). 1. Removal Procedures: Removal of asbestos-containing roofing materials and exterior cementitious siding panels (miscellaneous): i. Please note: Abatement activities cannot begin or be completed without the Owner s licensed Project Monitor present. ii. iii. iv. Install a remote 3-stage decontamination unit with shower adjacent to the work area (Section 01563). An established hot zone will be established using asbestos danger tape (red in color). Two layers of polyethylene sheeting will be placed on the surface below the asbestoscontaining roofing material. Material that is not consider asbestos-containing or can be segregated from the asbestoscontaining material in a manner that the material is free of asbestos-containing debris, may be removed and staged for disposal by others. v. Once an approval to commence is received from the Owners representative, the roofing materials associated with the structure shall be removed in a manner preventing the materials from becoming friable. The Owners representative will not tolerate the free fall of any asbestos-containing roofing materials during abatement activities. Amended water shall be used during the duration of the removal procedures. Dry removal of any asbestos-containing materials will not be tolerated. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
4 vi. vii. A thorough visual inspection will be performed to evaluate if the area has been sufficiently cleaned of ACM and all visible debris. During abatement activities, the Owner s representative may collect phase contrast microscopy air samples to evaluate if the Contractor is removing materials in a nonfriable manner. Removal of asbestos-containing Thermal Systems Insulation (TSI): Method 1: Wrap and Cut/Tented Glove Bag i. Please note: Abatement activities cannot begin or be completed without the Owner s licensed Project Monitor present. ii. iii. iv. Install a remote 3-stage decontamination unit with shower that is adjacent to the work area (Section 01563). Install and run high efficiency particulate absolute (HEPA) air filtration devices in each work area. Establish and maintain a pressure differential of inches of water measured on a strip chart recorder or other approved method in each work area. The Owners representative shall inspect and record the pressure differential at least 2 times per 8-hour shift. The Contractor shall supply a pressure differential manometer that is capable of monitoring and recording on a strip chart, pressure differential of inches of water. The manometer shall be equipped with an automatically activated alarm system that will sound if the pressure differential drops below the pre-set value. The Owner s representative may request that all strip charts be turned at the completion of the project phase. Work shall not commence until an adequate pressure differential is achieved and maintained in each work area. Establish a tent enclosure around the pipe insulation area utilizing one layer of six mill polyethylene sheeting. In addition install a floor consisting of polyethylene sheeting under the asbestos-containing pipe insulation. Please note this work may require separate tent enclosures depending on the obstructions from building materials limiting access. v. Once the tent enclosure has been erected and approved by the owner s licensed Project Monitor, adequately wet the pipe insulation utilizing amended water and wrap the pipe insulation with two layers of six mill polyethylene sheeting. If necessary utilize glove bag methods in accordance with Section to create access points on the pipe to cut the section of pipe out of the structure. vi. vii. viii. Upon removal of the wrapped pipe from the work areas, the contractor shall sufficiently clean the work area utilizing a HEPA vacuum cleaner and deconstruct the tent enclosure, Section All asbestos-containing materials are to be properly labeled and removed from the work area to the waste trailer. After this procedure is completed and a visual inspection has passed, the contractor shall deconstruct the tent enclosure. HEPA filtered air filtration devices shall remain in use until the tent enclosure has been completely deconstructed. After this procedure is completed and a visual inspection has passed, final clearance sampling will be performed by the Owner s representative. Final Clearance shall be conducted by phase contrast microscopy (PCM) analysis using EPA approved protocol. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
5 ix. HEPA filtered air filtration devices shall remain in use until final analytical clearance has been established. Removal of asbestos-containing Thermal Systems Insulation (TSI): Method 2: Type C Gross Removal i. Please note: Abatement activities cannot begin or be completed without the Owner s licensed Project Monitor present. ii. Please note in the event that the gross removal technique is utilized, abatement activities will be completed under Type C Supplied Air Respiratory Protection, as described in Section Respiratory Protection. Each work area shall establish the following guidelines. iii. Install 3-stage decontamination unit with shower that is attached to the work area. The decontamination unit will be erected in such a manner as to allow for a separate equipment room/bag-out. In no instance will the personal decontamination unit be used as a bag-out/equipment passage unless there is only one entry way into the work area and the method has been approved by the Owner s Project Monitor present. iv. Install and run high efficiency particulate absolute (HEPA) air filtration devices in each work area. Pre-clean the entire work area. Install critical barriers within the individual work areas. Install a minimum of 2 layers of polyethylene sheeting to walls, ceilings and floors of work area. Please note that all critical barriers be sealed for the entire area. v. Establish and maintain a pressure differential of inches of water measured on a strip chart recorder or other approved method in each work area. The Owners representative shall inspect and record the pressure differential at least 2 times per 8- hour shift. The Contractor shall supply a pressure differential manometer that is capable of monitoring and recording on a strip chart, pressure differential of inches of water. The manometer shall be equipped with an automatically activated alarm system that will sound if the pressure differential drops below the pre-set value. The Owner s representative may request that all strip charts be turned at the completion of the project phase. Work shall not commence until an adequate pressure differential is achieved and maintained in each work area. vi. A pre-commencement inspection shall be conducted by the abatement Contractor s supervisor and the Owner s representative; when approval from the Owner s representative is received the abatement activities may commence. The asbestoscontaining materials shall be adequately wetted with amended water during the abatement process. Dry removal of any asbestos-containing materials will not be tolerated. The asbestos-containing building materials shall be continuously wetted and immediately placed into 6 ml. asbestos disposal bags for proper disposal, according to section of the Master Specification. vii. Once an approval to commence is received from the owners representative, the thermal system insulation shall be removed After removal of all thermal system insulation within the work area is complete, the area must be thoroughly cleaned and encapsulated. Amended water shall be used during the duration of the removal procedures. Dry removal of any asbestos-containing materials will not be tolerated. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
6 viii. After this procedure is completed and a visual inspection has passed, final clearance sampling will be performed by the Owner s representative. Final Clearance shall be conducted by phase contrast microscopy (PCM) analysis using EPA approved protocol. ix. HEPA filtered air filtration devices shall remain in use until final analytical clearance has been established. Removal of asbestos-containing Thermal Systems Insulation and debris located in maintenance shop attic space (TSI): i. Please note: Abatement activities cannot begin or be completed without the Owner s licensed Project Monitor present. ii. Please note in the event that the gross removal technique is utilized, abatement activities will be completed under Type C Supplied Air Respiratory Protection, as described in Section Respiratory Protection. Each work area shall establish the following guidelines. iii. Install 3-stage decontamination unit with shower that is attached to the work area. The decontamination unit will be erected in such a manner as to allow for a separate equipment room/bag-out. In no instance will the personal decontamination unit be used as a bag-out/equipment passage unless there is only one entry way into the work area and the method has been approved by the Owner s Project Monitor present. iv. Install and run high efficiency particulate absolute (HEPA) air filtration devices in each work area. Pre-clean the entire work area. Install critical barriers within the individual work areas. Install a minimum of 2 layers of polyethylene sheeting to walls, ceilings and floors of work area. Please note that all critical barriers be sealed for the entire area. v. Establish and maintain a pressure differential of inches of water measured on a strip chart recorder or other approved method in each work area. The Owners representative shall inspect and record the pressure differential at least 2 times per 8- hour shift. The Contractor shall supply a pressure differential manometer that is capable of monitoring and recording on a strip chart, pressure differential of inches of water. The manometer shall be equipped with an automatically activated alarm system that will sound if the pressure differential drops below the pre-set value. The Owner s representative may request that all strip charts be turned at the completion of the project phase. Work shall not commence until an adequate pressure differential is achieved and maintained in each work area. vi. A pre-commencement inspection shall be conducted by the abatement Contractor s supervisor and the Owner s representative; when approval from the Owner s representative is received the abatement activities may commence. The asbestoscontaining materials shall be adequately wetted with amended water during the abatement process. Dry removal of any asbestos-containing materials will not be tolerated. The asbestos-containing building materials shall be continuously wetted and immediately placed into 6 ml. asbestos disposal bags for proper disposal, according to section of the Master Specification. vii. Please note that all debris located within the attic space is considered contaminated and will be disposed as asbestos-contaminated waste. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
7 viii. Once an approval to commence is received from the owners representative, the thermal system insulation shall be removed. After removal of all thermal system insulation and associated debris within the work area is complete, the area must be thoroughly cleaned and encapsulated. Amended water shall be used during the duration of the removal procedures. Dry removal of any asbestos-containing materials will not be tolerated. ix. After this procedure is completed and a visual inspection has passed, final clearance sampling will be performed by the Owner s representative. Final Clearance shall be conducted by phase contrast microscopy (PCM) analysis using EPA approved protocol. x. HEPA filtered air filtration devices shall remain in use until final analytical clearance has been established. Removal of asbestos-containing interior cementitious siding panels and asbestos-containing flooring materials (miscellaneous): i. Please note: Abatement activities cannot begin or be completed without the Owner s licensed Project Monitor present. Each work area shall establish the following guidelines. ii. Install 3-stage decontamination unit with shower that is attached to the work area. The decontamination unit will be erected in such a manner as to allow for a separate equipment room/bag-out. In no instance will the personal decontamination unit be used as a bag-out/equipment passage unless there is only one entry way into the work area and the method has been approved by the Owner s Project Monitor present. iii. Install and run high efficiency particulate absolute (HEPA) air filtration devices in each work area. Pre-clean any areas needing critical barriers and install critical barriers within the individual work areas. Please note that all critical be sealed for the entire area. iv. Establish and maintain a pressure differential of inches of water measured on a strip chart recorder or other approved method in each work area. The Owners representative shall inspect and record the pressure differential at least 2 times per 8- hour shift. The Contractor shall supply a pressure differential manometer that is capable of monitoring and recording on a strip chart, pressure differential of inches of water. The manometer shall be equipped with an automatically activated alarm system that will sound if the pressure differential drops below the pre-set value. The Owner s representative may request that all strip charts be turned at the completion of the project phase. Work shall not commence until an adequate pressure differential is achieved and maintained in each work area. v. A pre-commencement inspection shall be conducted by the abatement Contractor s supervisor and the Owner s representative; when approval from the Owner s representative is received the abatement activities may commence. The asbestoscontaining materials shall be adequately wetted with amended water during the abatement process. Dry removal of any asbestos-containing materials will not be tolerated. The asbestos-containing building materials shall be continuously wetted and immediately placed into 6 ml. asbestos disposal bags for proper disposal, according to section of the Master Specification. i. Once an approval to commence is received from the owners representative, the SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
8 cementitious panels and/or flooring materials shall be removed in a manner preventing the materials from becoming friable. BrightFields will not tolerate the free fall of any asbestos-containing cementitious panels during abatement activities. Amended water shall be used during the duration of the removal procedures. Dry removal of any asbestos-containing materials will not be tolerated vi. After this procedure is completed and a visual inspection has passed, final clearance sampling will be performed by the Owner s representative. Final Clearance shall be conducted by phase contrast microscopy (PCM) analysis using EPA approved protocol. vii. HEPA filtered air filtration devices shall remain in use until final analytical clearance has been established. 2. The following inspections shall be performed during the project phases indicated: a. Pre-Cleaning: A visual inspection of all pre-cleaned surfaces must be performed by the Contractors on-site supervisor and the Owners representative together prior to any abatement activities. b. Daily Project Inspections: An inspection of the integrity of the work area shall be performed a minimum of twice daily by the Owners representative. c. Final Visual Inspection (air clearance): A final visual inspection of the work area shall be performed by the Contractors on-site supervisor and Owners representative prior to aggressive final air clearance sampling. d. Project Completion Inspection (post air clearance): A final visual inspection of the work area shall be performed by the Contractors on-site supervisor and Owners representative after aggressive final air clearance sampling has passed and containment system has been demobilized, prior to turning the area (s) over to the Owner. Minimum Respiratory protection for this project shall include full face Powered Air Purifying Respirators (PAPR) for set up and removal of the asbestos-containing materials. In the event that the Contractor chooses to remove the thermal system insulation via method 2, Type C Supplied Air Respiratory Protection will be required. All existing electric power in the work area shall be confirmed de-energized by the abatement Contractor and temporary power shall be brought to the work area from outside see section of the Specification. The Owner shall not supply temporary utilities. It is the Contractors responsibility to comply with all OSHA requirements. All workers must have their current State of Delaware Asbestos Worker/Supervisor Badge and current medical information available daily for verification and recording purposes by the Owners representative in order to work on the project. NO EXCEPTIONS SHALL BE TOLERATED. The abatement Contractor shall supply extra, new respirators (PAPR or Type C ), respirator cartridges, disposable coveralls (w/head and foot covers) at the decontamination unit for use by authorized visitors as well as the Owners representative at all times. All decontamination procedures shall be strictly followed and enforced. A signed copy of the Workers Acknowledgment shall be obtained from each worker - section of the Specification. Measurements provided in this section are approximate and it is understood that ALL SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
9 measurements must be verified by the Contractor and reported to the Owners representative. 1. All work shall be performed in accordance with the requirements of the specification and all applicable Federal, State and local regulations. 2. Related Specifications Master Specification for Asbestos Abatement/Decontamination for Delaware Department of Transportation. 3. Submittals: Prior to starting work, submit the following to the Owners representative for review. Do not begin without the approval of the Owners representative. a. Scope of Work - Submit a detailed plan of the procedures to be used in complying with the requirements of this specification. Include the location and layout of decontamination unit(s), the sequencing of work, the interfacing of other trades, methods to be used to assure the safety of the building occupants and visitors, detailed disposal plan and a detailed description of the methods to be used to control pollution. The plan shall be submitted at the pre-work meeting and approved by the Owners representative prior to starting work. 4. Inspection: Prior to starting work, inspect work areas. Prepare a list of damages to the structure, surfaces and equipment of surrounding areas of the building that may be construed as damage caused by the work. Photograph or videotape existing conditions as necessary to document these conditions. Submit to the Owners representative prior to starting work. 1.3 WORK SEQUENCE A. The Work will be conducted in one phase: Roofing Materials 1. Asbestos-containing roofing tar and associated felt backing (black) associated with small isolated flat roof accessed from office 214 or the southern HVAC chase located on the second floor estimated 348 square feet (5% Chrysotile). 2. Asbestos-containing silver roof coat associated with the lowest slightly angled roof over Rooms 124 and 128 estimated 570 square feet (1.5% Chrysotile). 3. Asbestos-containing silver roof coat associated with the second level flat roof primarily over the boiler, sign fabrication, and screening rooms estimated 4,008 square feet (2.75% Chrysotile). 4. Asbestos-containing silver flashing and patch coating associated with penetrations throughout the second level flat roof primarily over the boiler, sign fabrication, and screening rooms estimated 4,008 square feet (2.75% Chrysotile). 5. Asbestos-containing silver roof coat associated with the third level flat roof over the second level office space estimated 4,967 square feet (3% Chrysotile). 6. Asbestos-containing asphalt rolled roofing associated with the third level flat roof over the second level office space estimated 4,967 square feet (6% Chrysotile). Thermal System Insulation 1. Asbestos-containing cementitious ventilation system duct and vent hood located in the screening room and across the 2 nd Level flat roof estimated 65 linear feet of 2 diameter duct, SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
10 45 linear feet of 1.5 diameter duct, and 68 square feet on vent hood (15 Chrysotile and 15% Crocidolite). 2. Asbestos-containing joint caulk associated with ventilation system duct and vent hood joint connections located in the screening room and across the second level flat roof estimated 140 linear feet (8% Chrysotile). 3. Asbestos-containing rope gasket associated with ventilation system duct and vent hood joint connections located in the screening room and across the second level flat roof estimated 140 linear feet (15% Chrysotile). 4. Asbestos-containing vibration damper cloth associated with ventilation system duct at the connection to the blower fan located on the second level flat roof estimated 8 square feet (90% Chrysotile). 5. Asbestos-containing unused pipe insulation and associated debris located in the attic space above the rear maintenance shop estimated 800 square feet (15% Chrysotile and 8% Amosite). Please note that two unused 4 foot sections of the pipe insulation were observed with damage debris scattered across the attic floor and on items stored in the attic. 6. Asbestos-containing 4 cement pipe insulation located in maintenance shop, office and storage area, above the drop and wood ceiling in the sign fabrication room, through a portion of the screening room, and in the boiler room estimated 250 linear feet (15% Chrysotile and 8% Amosite). 7. Asbestos-containing 2 corrugated pipe insulation located in front office area, portions of the screening room, and in the boiler room estimated 400 linear feet (15% Chrysotile). 8. Asbestos-containing mudded elbows and valves associated with the brown paper wrapped fiberglass pipe insulation located in front office area, portions of the screening room, and in the boiler room estimated 25 linear feet (5% Chrysotile). 9. Asbestos-containing silver duct coating associated with the exterior 2 x 2 box duct located on the second level flat roof estimated 1,250 square feet (3% Chrysotile). 10. Asbestos-containing asphalt duct coating associated with the exterior 2 x 2 box duct located on the second level flat roof estimated 1,250 square feet (5% Chrysotile). 11. Asbestos-containing duct coating associated with the interior 2 x 2 metal box duct located along the northern wall of the metal room and in the boiler room estimated 450 square feet (10% Chrysotile). 12. Asbestos-containing vibration damper cloth associated with two large air handling units located in the boiler room estimated 20 square feet (80% Chrysotile). 13. Asbestos-containing vibration damper cloth associated with three connections of the 2 x 2 metal box duct to the centrally located large air handling unit located in the boiler room estimated 24 square feet (80% Chrysotile). Miscellaneous 1. Asbestos-containing cementitious siding panels (gray) as exterior and interior walls and as ceilings in room 122 and chase areas adjacent to rooms 113 and 113A estimated 14,870 square feet (15% Chrysotile). 2. Asbestos-containing sheet good (white with small multi-color squares pattern) located in the 1 st floor front office area under carpet estimated 2,000 square feet (8% Chrysotile). SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
11 1.4 ASBESTOS-CONTAINING MATERIALS: A. The work of this contract involves activities that will disturb asbestos-containing materials. The location and type of asbestos-containing materials known to be present at the worksite is set forth in the Schedule of Asbestos-Containing Materials at the end of this section. If any other asbestoscontaining materials or suspect asbestos-containing materials are found, notify the Owner, other employers and employees about the location and quantity of the asbestos-containing materials or suspect asbestos-containing materials within 24 hours of the discovery. The following asbestos-containing materials are known to be present at the worksite. If any other materials are found that are suspected of containing asbestos, notify the Owners representative immediately. Roofing Materials 1. Asbestos-containing roofing tar and associated felt backing (black) associated with small isolated flat roof accessed from office 214 or the southern HVAC chase located on the second floor estimated 348 square feet (5% Chrysotile). 2. Asbestos-containing silver roof coat associated with the lowest slightly angled roof over Rooms 124 and 128 estimated 570 square feet (1.5% Chrysotile). 3. Asbestos-containing silver roof coat associated with the second level flat roof primarily over the boiler, sign fabrication, and screening rooms estimated 4,008 square feet (2.75% Chrysotile). 4. Asbestos-containing silver flashing and patch coating associated with penetrations throughout the second level flat roof primarily over the boiler, sign fabrication, and screening rooms estimated 4,008 square feet (2.75% Chrysotile). 5. Asbestos-containing silver roof coat associated with the third level flat roof over the second level office space estimated 4,967 square feet (3% Chrysotile). 6. Asbestos-containing asphalt rolled roofing associated with the third level flat roof over the second level office space estimated 4,967 square feet (6% Chrysotile). Thermal System Insulation 1. Asbestos-containing cementitious ventilation system duct and vent hood located in the screening room and across the 2 nd Level flat roof estimated 65 linear feet of 2 diameter duct, 45 linear feet of 1.5 diameter duct, and 68 square feet on vent hood (15 Chrysotile and 15% Crocidolite). 2. Asbestos-containing joint caulk associated with ventilation system duct and vent hood joint connections located in the screening room and across the second level flat roof estimated 140 linear feet (8% Chrysotile). 3. Asbestos-containing rope gasket associated with ventilation system duct and vent hood joint connections located in the screening room and across the second level flat roof estimated 140 linear feet (15% Chrysotile). 4. Asbestos-containing vibration damper cloth associated with ventilation system duct at the connection to the blower fan located on the second level flat roof estimated 8 square feet (90% Chrysotile). 5. Asbestos-containing unused pipe insulation and associated debris located in the attic space above the rear maintenance shop estimated 800 square feet (15% Chrysotile and 8% Amosite). Please note that two unused 4 foot sections of the pipe insulation were observed with damage debris scattered across the attic floor and on items stored in the attic. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
12 6. Asbestos-containing 4 cement pipe insulation located in maintenance shop, office and storage area, above the drop and wood ceiling in the sign fabrication room, through a portion of the screening room, and in the boiler room estimated 250 linear feet (15% Chrysotile and 8% Amosite). 7. Asbestos-containing 2 corrugated pipe insulation located in front office area, portions of the screening room, and in the boiler room estimated 400 linear feet (15% Chrysotile). 8. Asbestos-containing mudded elbows and valves associated with the brown paper wrapped fiberglass pipe insulation located in front office area, portions of the screening room, and in the boiler room estimated 25 linear feet (5% Chrysotile). 9. Asbestos-containing silver duct coating associated with the exterior 2 x 2 box duct located on the second level flat roof estimated 1,250 square feet (3% Chrysotile). 10. Asbestos-containing asphalt duct coating associated with the exterior 2 x 2 box duct located on the second level flat roof estimated 1,250 square feet (5% Chrysotile). 11. Asbestos-containing duct coating associated with the interior 2 x 2 metal box duct located along the northern wall of the metal room and in the boiler room estimated 450 square feet (10% Chrysotile). 12. Asbestos-containing vibration damper cloth associated with two large air handling units located in the boiler room estimated 20 square feet (80% Chrysotile). 13. Asbestos-containing vibration damper cloth associated with three connections of the 2 x 2 metal box duct to the centrally located large air handling unit located in the boiler room estimated 24 square feet (80% Chrysotile). Miscellaneous 1. Asbestos-containing cementitious siding panels (gray) as exterior and interior walls and as ceilings in room 122 and chase areas adjacent to rooms 113 and 113A estimated 14,870 square feet (15% Chrysotile). 2. Asbestos-containing sheet good (white with small multi-color squares pattern) located in the 1 st floor front office area under carpet estimated 2,000 square feet (8% Chrysotile). 1.5 ASBESTOS HEALTH RISK: A. The disturbance or dislocation of asbestos-containing materials may cause asbestos fibers to be released into the atmosphere, thereby creating a potential health risk to workers. Apprise all workers, supervisory personnel, subcontractors and consultants who will be at the job site of the seriousness of the risk and of proper work procedures which must be followed. B. Where in the performance of the work, workers, supervisory personnel, subcontractors, or consultants may encounter, disturb, or otherwise function in the immediate vicinity of any identified asbestos-containing materials, take appropriate continuous measures as necessary to protect all building occupants from the risk of exposure to airborne asbestos. Such measures shall include the procedures and methods described herein, and compliance with regulations of applicable federal, state and local agencies. 1.6 CONTRACTOR USE OF PREMISES A. General: During the abatement period the Contractor shall have limited use of the premises for abatement operations. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
13 B. Use of the Site: Limit use of the premises to work in areas indicated. Confine operations to areas within contract limits indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated. 1. Owner Occupancy: Allow for Owner occupancy and Owner s representative. 2. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Owner, the Owner's employees, and emergency vehicles at all times. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. C. Use of the Existing Building: Maintain the existing building in a weather tight condition throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building during the construction period. 1. Smoking: Smoking or open fires will not be permitted on the property. 2. Toilet Rooms: Use of onsite toilets will not be permitted. It will be the Contractors responsibility to provide temporary sanitary facilities. 1.7 OCCUPANCY REQUIREMENTS A. Partial Owner Occupancy: The Owner reserves the right to occupy and to place and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placing of equipment and partial occupancy shall not constitute acceptance of the total Work. 1. The Owners representative will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner occupancy. 1.8 AIR MONITORING BY THE OWNER: A. The Owner has contracted for air monitoring. Air monitoring may be conducted both outside and inside of the work area during the work, and for clearance sampling at the end of the project 1. Outside of the Work Area: The Owner's air monitoring firm may sample air outside of the Work Area to detect faults in the Work Area isolation such as: a. Contamination of the building outside of the Work Area with airborne asbestos fibers, b. Failure of filtration or rupture in the differential pressure system, c. Contamination of air outside the building envelop with airborne asbestos fibers. 2. Inside the Work Area: The Owners air monitoring firm may monitor airborne fiber counts in the Work Area. The purpose of this air monitoring is to detect airborne asbestos concentrations which may challenge the ability of the Work Area isolation procedures to protect the balance of the building or outside of the building from contamination by airborne fibers. B. Work area clearance: Clearance air sampling by the Owners air monitor at the completion of asbestos abatement work is described in Section Project Decontamination. C. Air monitoring required by OSHA is work of the Contractor and is not covered in this section. Contractor shall comply with all applicable regulatory sampling requirements as well as all SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
14 monitoring requirements detailed in the Section. 1.9 SCHEDULE OF AIR SAMPLES BY OWNER: A. Sample cassettes: Samples will be collected on 25 mm. cassettes as follows: 1. PCM: 0.8 micrometer mixed cellulose ester. B. Number and Volume of Samples: The number and volume of air samples given in the schedules is approximate. The exact number and volume of samples collected by the Owner may vary depending upon job conditions and the analytical method used. C. Sample Volume and Sensitivity: 1. PCM: The sample volumes collected by the Owners air monitor will be determined by the following formula: (# Fibers in sample fibers in blank) 385mm squared (Vol. Liters) (1000) ( mm squared) (# fields) = fibers/cc Where: Number of fibers = 5.5 fibers/100 fields, based on a limit of detection (LOD) of 7 fibers/mm 2 on the filter Area of 100 fields = 0.785mm 2 Total Filter Area = 385mm 2 Limit Value = as specified in the schedules of samples below a. For purposes of this specification, the sample volume calculated above will be considered to be of sufficient size so that there is a 95% level of confidence that the value measured by each individual sample at the limit of detection (LOD) is less than or equal to the limit values specified below. b. For purposes of this specification, the Limit of Detection (LOD) is defined as 7 fibers/mm 2 on the filter or 5.5 fibers/100 fields. c. For purposes of this specification overloaded samples will be considered as exceeding the applicable limit value. D. Base Line: 1. Before Start of Work: The owners representative may secure air samples to establish a base line. 2. Base Line: a level expressed in fibers per cubic centimeter which is twenty-five percent greater than the largest of the following: a. Average of the PCM samples collected outside each Work Area b. Average of the PCM samples collected outside the building c fibers per cubic centimeter 3. Samples collected for Transmission Electron Microscopy (TEM) analysis will be held without analysis. These samples will be analyzed under the conditions and terms set forth in "Fibers Counted" and "Affect on Contract Sum". SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
15 4. PCM Samples Location Number Limit Approx. Rate Sampled of Value Volume (Liters/ Samples (Fibers/cc) (Liters) Minute) Each Work Area Outside Each Work Area Outside Building TEM Samples: Location Number Analytical Approx. Rate Sampled of Sensitivity Volume (Liters/ Samples (Struct. /cc.) (Liters) Minute) Each Work Area , Outside Each , Work Area Outside Building , E. Daily: 1. From start of work of Section Temporary Enclosures through the work of Section Project Decontamination, the Owner may take samples. 2. Sample volume and sensitivity: inside the work area may vary depending upon conditions in the work area. If samples are overloaded at the sample volume required for a limit value equal to the Stop Action Levels or Immediate Stop Action Levels given later in this section, the level is considered to have been exceeded. 3. PCM Samples: Location Number Limit Approx. Rate Sampled of Value Volume (LPM) Samples (Fibers/cc) (Liters) Each Work Area Outside Each Work Area at Critical Barrier Clean Room Equipment Decon SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
16 Outside Building Output of Pressure Differential System F. Additional samples may be taken at the Owner's or Owners representatives discretion. If airborne fiber counts exceed allowed limits additional samples may be taken as necessary to monitor fiber levels ANALYTICAL METHODS USED BY THE OWNER: A. The following methods will be used by The Owner in analyzing filters used to collect air samples. Sampling rates may be varied from printed standards to allow for high volume sampling. 1. Phase Contrast Microscopy (PCM) will be performed using the NIOSH 7400 method. 2. Transmission Electron Microscopy (TEM) will be performed using the analysis method set forth in the AHERA regulation 40 CFR Part 763 Appendix A (when applicable) LABORATORY TESTING BY OWNER: A. The services of a testing laboratory may be employed by the Owner to perform laboratory analyses of the air samples. A technician will be at the job site, and samples will be sent daily by carrier for next day delivery, so that verbal reports on air samples can be obtained within 24 hours. B. A complete record of all air monitoring and results will be furnished to the Owners representative, the Owner, and the Contractor. C. The Contractor will have access to all air monitoring tests and results upon request. D. Written Reports: of all air monitoring tests will be posted at the job site on a daily basis FIBERS AND STRUCTURES A. Fibers Counted: The following procedure will be used to resolve any disputes regarding fiber types when a project has been stopped due to excessive airborne fiber counts. 1. Large Fibers: "Airborne Fibers" referred to above include all fibers regardless of composition as counted by phase contrast microscopy (PCM), unless additional analysis by transmission or scanning electron microscopy demonstrates to the satisfaction of the Owners representative that non-asbestos fibers are being counted. "Airborne Fibers" counted in samples analyzed by transmission electron microscopy shall be asbestos fibers, greater than 5 microns in length. For purposes of stop action levels, subsequent to analysis by electron microscopy, the number of "Airborne Fibers" shall be determined by multiplying the number of fibers, regardless of composition, counted by PCM by the proportion of fibers that are asbestos as determined by TEM (a number equal to, asbestos fibers counted, divided by all fibers counted in the electron microscopy analysis). 2. Small Structures: "Airborne Fibers" referred to above include asbestos structures (fibers, SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
17 1.13 ADDITIONAL TESTING: bundles, clusters or matrices) of any diameter and any length greater than 0.5 microns. A. The Contractor may conduct air monitoring and laboratory testing. If Contractor elects to do this the cost of such air monitoring and laboratory testing shall be at no additional cost to the Owner. The Contractor is required to provide Owner with results of all air monitoring and testing within 3 days of receiving results PERSONAL MONITORING: A. Owner will not perform air monitoring for the Contractor to meet Contractor's OSHA requirements for personal sampling or any other purpose MISCELLANEOUS PROVISIONS A. None. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 STOP ACTION LEVELS: A. Inside Work Area: Maintain an average airborne count in the work area of less than the Stop Action Level given below for the type of respiratory protection in use. If the fiber counts rise above this figure for any sample taken, revise work procedures to lower fiber counts. If the Time Weighted Average (TWA) fiber count for any work shift or 8 hour period exceeds the Stop Action Level, stop all work except corrective action, leave pressure differential and air circulation system in operation and notify Owners representative. After correcting cause of high fiber levels, do not recommence work for 24 hours unless otherwise authorized, in writing, by Owners representative. STOP IMMEDIATELY MINIMUM ACTION STOP RESPIRATOR PROTECTION LEVEL LEVEL REQUIRED FACTOR (F/cc) (F/cc) Half face PAPR 1, Supplied Air 1,000 Pressure Demand 1. If airborne fiber counts exceed Immediate Stop Level given above for type of respiratory protection in use for any period of time cease all work except corrective action. Notify the Owners representative. Do not recommence work until fiber counts fall below Stop Action Level given above for the type of respiratory protection in use. After correcting cause of high fiber levels, do not recommence work for 24 hours unless otherwise authorized, in writing, by the Owners representative. B. Outside Work Area: If any air sample taken outside of the Work Area exceeds the base line SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
18 established in Part 1 of this section, immediately and automatically stop all work except corrective action. The Owners representative will determine the source of the high reading and so notify the Contractor in writing. C. Corrective Action: 1. If the high reading was the result of a failure of Work Area isolation measures initiate the following actions: a. Immediately erect new critical barriers as set forth in Section Temporary Enclosures to isolate the affected area from the balance of the building. Erect Critical Barriers at the next existing structural isolation of the involved space (e.g. wall, ceiling, and floor). b. Decontaminate the affected area in accordance with Section Cleaning & Decontamination Procedures. c. Require that respiratory protection as set forth in Section Respiratory Protection be worn in affected area until area is cleared for re-occupancy in accordance with Section Project Decontamination. d. Leave Critical Barriers in place until completion of work and insure that the operation of the pressure differential system in the Work Area results in a flow of air from the balance of the building into the affected area. e. If the exit from the clean room of the personnel decontamination unit enters the affected area, establish a decontamination facility consisting of a Shower Room and Changing Room as set forth in Section Decontamination Units at entry point to affected area. f. After Certification of Visual Inspection in the Work Area remove critical barriers separating the work area from the affected area. Final air samples will be taken within the entire area as set forth in Section Project Decontamination. 2. If the high reading was the result of other causes initiate corrective action as determined by the Owners representative. D. Effect on Contract Sum: Complete corrective work with no change in the Contract Sum if high airborne fiber counts were caused by Contractor's activities. The Contract Sum and schedule will be adjusted for additional work caused by high airborne fiber counts beyond the Contractor's control. 3.2 STOP WORK: A. If the Owner or Owners representative presents a written stop work order, immediately and automatically conform to that stop work order, while maintaining temporary enclosures and pressure differential. Do not recommence abatement work until authorized in writing by Owner or Owners representative. B. Immediately initiate the following actions: After being presented with a stop work order immediately: 1. Cease all asbestos removal activities, or any other activities that disturbs asbestos-containing materials. 2. Repair any fallen, ripped or otherwise failed work area isolation measures. SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
19 3. Maintain in operation all work area isolation measures including those required by Sections Temporary Enclosures, Temporary Pressure Differential & Air Circulation System, Decontamination Units. 4. Maintain all worker protections including those required by Sections Worker Protection - Asbestos Abatement, and Respiratory Protection. 5. Fog the air in the work area with a mist of amended water to reduce airborne fiber levels. C. Do not recommence work until authorized in writing by the Owner or Owners representative. 3.3 SCHEDULE OF ASBESTOS-CONTAINING MATERIALS: Quantities are estimations only and need to be field verified by Contractor. APPROXIMATE QUANTITIES AND LOCATIONS CONTRACTOR MUST VERIFY ALL QUANTITIES AND LOCATIONS OF ASBESTOS- CONTAINING MATERIALS 59 Sign Shop Lane, Dover, Delaware Type Location Material Quantity % Asbestos Small flat roof accessed on second Roofing tar, thin coat 348 square feet 5% Chrysotile floor office area. (black) Small flat roof accessed on second Felt paper (black) 348 square feet 5% Chrysotile floor office area. Low level roof, top layer Silver coat (silver) 570 square feet 1.5% Chrysotile Roofing Material Second level roof, 1st layer under stone Second level roof, 1st layer under stone around equipment and penetrations Second level roof 2'x2' square duct outer layer Silver coat (silver) 4,008 square feet 2.75% Chrysotile Built-up silver flashing patch (silver) 4,008 square feet 2.75% Chrysotile Duct outer layer (silver) 1,250 square feet 3% Chrysotile Under second level roof 2'x2' square duct outer layer Asphalt duct coating (black) 1,250 square feet 5% Chrysotile High roof, 1st layer Silver coat (silver) 4,967 square feet 3% Chrysotile High roof, 2nd layer Asphalt rolled roofing (black) 4,967 square feet 6% Chrysotile SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
20 2' diameter duct (65' exterior), 1.5' diameter duct (18' exterior & 27' interior), 3x2, 1x20 & 2x2x2 vent hood Cementitious ventilation hood (grey) 68 square feet on vent, 110 linear feet of duct 15% Chrysotile 15% Crocidolite 15 exterior joints, 6 interior joints associated with cementitious ventilation hood Joint caulk associated (beige/red) 140 square feet 8% Chrysotile 15 exterior joints, 6 interior joints associated with cementitious ventilation hood Rope gasket (white) 140 square feet 15% Chrysotile Roof side of duct at blower inlet and outlet associated with HA03 Vibration damper cloth (grey/white) 8 square feet 90% Chrysotile Thermal System Insulation Maintenance shop attic. Unused insulation in box, debris on attic Pipe insulation (white) 800 square feet floor Maintenance shop attic from garage to interior connection changes to fiberglass on interior side of wall. Boiler room. 4" pipe insulation (white) 250 linear feet Sign fabrication room. Screening room. Boiler room. Office. Screening room. 15% Chrysotile 8% Amosite 15% Chrysotile 5% Amosite 2" corrugated pipe 400 linear feet 15% Chrysotile insulation (white/gray) Associated with 1" brown wrap fiberglass lines in front office area, 1st floor. Mudded elbow and joints Screening room. Boiler room. Above (gray) bath in front office. 2'x2' metal duct in metal/boiler Duct board coating rooms (white) 25 linear feet 5% Chrysotile 450 square feet 10% Chrysotile Air handlers in boiler room Vibration damper cloth (black) 20 square feet 80% Chrysotile Air handler connected to 2'x2' duct in boiler room Vibration damper cloth (tan) 24 square feet 80% Chrysotile Misc. 4'x8', 1/8" thick panels. Front & rear office and paint booth area. Cementitious siding panels (grey) 14,870 square feet 15% Chrysotile Front office area Sheet good (white) 2,000 square feet 8% Chrysotile END OF SECTION SUMMARY OF THE WORK - ASBESTOS ABATEMENT PHASE
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
LEGAL REVIEW & UPDATE
LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break
Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site
for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in
Standards for Asbestos Abatement
19a-332a-1. Definitions Standards for Asbestos Abatement 19a-332a-1. Definitions The following definitions shall apply for the purpose of Section 19a-332a-1 to Section 19a-332a- 16 inclusive. (a) "Adequately
DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions
DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of
The Richard Stockton University ASBESTOS MANAGEMENT PLAN
The Richard Stockton University ASBESTOS MANAGEMENT PLAN January 2015 Asbestos Management Plan Table of Contents I. Introduction II. III. IV. Definitions Identification of Asbestos Notification and Labeling
UBC Plant Operations Asbestos Work Procedures April 2004
UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations
Asbestos Management POLICY
Asbestos Management POLICY All Asbestos Containment Material (ACM) removal activities shall comply with applicable federal, state, and local regulations. Areas of responsibility of Facilities Management
Loss Control TIPS Technical Information Paper Series
Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM Asbestos-Containing Material (ACM) In Buildings The presence of asbestos in buildings, particularly those
SECTION 02 8213 ASBESTOS ABATEMENT
PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.
Asbestos Inspection Project Procedure
EOSMS 402 Date: 01/13/2014 Page 1 of 6 1) Purpose This document is intended to specify the scope of services required of Asbestos Contractor in asbestos inspection projects at Kennesaw State University
North Carolina State University. Asbestos Management Plan
North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building
Characteristics/Applications
Facilities Operations and Development Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://fod.osu.edu The Ohio State University Asbestos Management
NDSU TABLE OF CONTENTS
NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD
ASBESTOS CONTROL PLAN
ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization
University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
Asbestos abatement Sampling & Analysis. Abatement Project Supervision
Asbestos abatement Sampling & Analysis Abatement Project Supervision TOPICS FOR DISCUSSION Air Sampling PERSONNEL AREA Analysis PCM Analysis TEM Analysis TYPES OF SAMPLING Two types of air sampling are
British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT
BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk
Asbestos Frequently Asked Questions
Asbestos Frequently Asked Questions What is asbestos? Asbestos is a mineral which is mined, processed, and used in many building materials. Since 1988, asbestos has been banned in most US building components;
Asbestos Management Program
Asbestos Management Program Facilities and Operations Revision #4: February 17, 2012 Page IMPORTANT Asbestos related incidents must be reported IMMEDIATELY to your supervisor Emergency Contacts During
Asbestos Management. 2. Introduction. Contents
Asbestos Management Contents 1. Policy 2. Introduction 3. Scope 4. Definitions 5. Asbestos Inventory and Identification 6. Inspection 7. Access Control 8. Repair and Maintenance of Asbestos-Containing
Asbestos Operations and Maintenance Program. San José State University
San José State University One Washington Square San José, California Facilities Development and Operations Department July 25, 2012 1) Purpose and Scope The purpose of the Asbestos Operations and Maintenance
Asbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety
Asbestos Abatement Management Program Facilities Operations and Development Environmental Health & Safety November 7, 2012 INTRODUCTIONS David Kos (EHS) Director of Environmental Affairs David Kehl (EHS)
Lead Exposure Management Plan
Lead Exposure Management Plan 1.0. Policy CSUF has developed the Lead Exposure Management Plan to reduce occupational and environmental exposure to lead, a potent neurotoxin and carcinogen that causes
ASBESTOS BACKGROUND INFORMATION
ASBESTOS BACKGROUND INFORMATION Asbestos Facts What is Asbestos? Asbestos is a mineral. It is a natural rock mined from the ground. Most of the asbestos used in this country comes from Quebec in Canada.
Control Provisions under the Air Pollution Control Ordinance
ProPECC PN 2/97 ENVIRONMENTAL PROTECTION DEPARTMENT PRACTICE NOTE FOR PROFESSIONAL PERSONS Handlin of Asbestos Containin Materials in Buildins Introduction Asbestos is a generic name given to a group of
Asbestos Work Permit Procedures
These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,
AHERA 3-Year Asbestos Re-Inspection
AHERA 3-Year Asbestos Re-Inspection Denver 940 Fillmore Street Denver, Colorado 80206 Report Date: November 20, 2013 OEI Project No. 13.159 Prepared For: John Lewis Denver 940 Fillmore Street Denver, CO
EVERYONE'S RESPONSIBILITY
EVERYONE'S RESPONSIBILITY Guidelines for an Asbestos Operations and Maintenance Program February 2007 Guidelines for an Asbestos Operations and Maintenance Program Workplace Safety & Health Division 200
CONTROL METHODS. There are five ways to control the release of asbestos fibers:
Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based
OGS LIMITED ASBESTOS & LEAD SURVEY REPORT
our people and our passion in every project OGS LIMITED ASBESTOS & LEAD SURVEY REPORT Building 44 Willard Drug Treatment Center 7116 County Road 132 Willard, NY Prepared for: NYSOGS 33 rd Floor, Corning
have been provided with information on whether they do or do not contain asbestos before starting work;
Health Effects of Asbestos If your work involves possible exposure to asbestos, you should: be aware of the risks from asbestos exposure; understand the importance of keeping exposure as low as possible;
Asbestos Management & Abatement
Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &
Vermont Regulations for Asbestos Control
Vermont Regulations for Asbestos Control V.S.A. Title 18, Chapter 26 Effective February 1987; Amended November 1995 Vermont Department of Health 1 08 Cherry Street, Box 70 Burlington, VT 05402 Agency of
ASBESTOS MANAGEMENT PLAN
ASBESTOS MANAGEMENT PLAN SAN JOSE STATE UNIVERSITY Environmental Health & Occupational Safety Asbestos Management Plan 1.0 Introduction 2.0 Policy 3.0 Responsibilities 4.0 Contract Administration 5.0 In-House
2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987.
Penn State University Environmental Health and Safety Asbestos Management Program I. Introduction Over the past several decades the hazards of asbestos exposure have become well known. With this influx
Miami University s Asbestos Operations & Maintenance Program Administered by
Miami University s Asbestos Operations & Maintenance Program Administered by ENVIRONMENTAL SAFETY & RISK MANAGEMENT 529-2829 Table of Contents Purpose 2 Personnel Covered Under the Asbestos Mangement Plan
ASBESTOS CONTROL PROGRAM
WESTERN UNIVERSITY OCCUPATIONAL HEALTH AND SAFETY ASBESTOS CONTROL PROGRAM Last Update: August 2012 TABLE OF CONTENTS 1.0 INTRODUCTION AND SCOPE... 3 2.0 DEFINITIONS... 4 3.0 HISTORICAL INFORMATION...
Guidelines for Mold Remediation (Removal)
Guidelines for Mold Remediation (Removal) Indoor mold growth, water damage, or musty odors should be addressed quickly. Removing mold growth and correcting the underlying cause of water accumulation can
ASBESTOS MANAGEMENT INTRODUCTION
SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous
Approved by: UBC ACT Committee
The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy
ASBESTOS BUILDING INSPECTION REPORT. for the. City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823.
ASBESTOS BUILDING INSPECTION REPORT for the City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823 at the City of East Lansing Waste Water Treatment Plant and Woodingham Pump Station
Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials
Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Park Potomac Place 12500 Park Potomac Avenue Potomac, Maryland 20854 KEM Project # 21703 Prepared for: Park Potomac Place
Asbestos Management Program (EHS Program Manager 7.5)
Asbestos Management Program (EHS Program Manager 7.5) 1.0 Introduction The Weill Cornell Medicine (WCM) Asbestos Management Program protects the WCM community from the health hazards related to asbestos
SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC
ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION
Asbestos WHAT TO DO? Studies of people who were exposed to high levels of asbestos in factories and shipyards, are at increased risk of:
Asbestos WHAT TO DO? What Is Asbestos? Asbestos is mineral fiber. It can be positively identified only with a special type of microscope. There are several types of asbestos fibers. In the past, asbestos
Asbestos Procedures. Asbestos Products
Asbestos Procedures Asbestos Products Where is asbestos known to be located on The Evergreen State College? Please see Appendix A for a list of known asbestos containing materials located on the Olympia
Washington University Asbestos Operations and Maintenance Plan
1. Purpose Washington University Asbestos Operations and Maintenance Plan 1.1. The purpose of this Asbestos Operations and Maintenance (O&M) Plan is to minimize the potential for exposure to airborne asbestos
EXHIBIT A SCOPE OF SERVICES
EXHIBIT A SCOPE OF SERVICES 1.0 INTRODUCTION Asbestos consulting services are required for Item/Segment No. 227775-1, SR-7 (US 441) from Fillmore Street to South of Stirling Road, Hollywood, Broward County,
Preparing the Work Area
Preparing the Work Area Work Area Preparation Objectives of Work Area Prep Sequence and Methods for Prep Engineering Controls: Negative Pressure Requirements, Equipment and Set-up Purpose of Area Prep
UI Procedures for Asbestos Management
UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing
ASBESTOS AWARENESS IN THE WORKPLACE. This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation.
ASBESTOS AWARENESS IN THE WORKPLACE This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description of the program and the
DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE
1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to
Building Owners Responsibilities for Asbestos
Building Owners Responsibilities for Asbestos August 2012 Minnesota Department of Labor and Industry Occupational Safety and Health Division This material can be provided to you in a different format (Braille,
LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material
LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material Asbestos Policy and Criteria Policy: Pierce County Recycling Composting and Disposal (LRI) has established an
Asbestos Management Program and Procedures. Northern Illinois University
Asbestos Management Program and Procedures Northern Illinois University Department of Environmental Health and Safety 8/12/2013 INTRODUCTION Contents INTRODUCTION... 2 PURPOSE... 6 DEFINITIONS... 8 GENERAL
ASBESTOS MANAGEMENT POLICY
ASBESTOS MANAGEMENT POLICY Published : 4th Revision December 2014 1 Table of Contents INTRODUCTION... 3 DUTY TO MANAGE ASBESTOS... 3 DUTIES OF CAMPUS SERVICES... 3 1.0 POLICY OBJECTIVES... 5 2.0 RESPONSIBILITIES...
CITY OF BOSTON DEPARTMENT OF HEALTH AND HOSPITALS ASBESTOS REGULATIONS
Section 1.01 Authority, Purpose and Scope 1.02 Definitions 1.03 General Requirements 1.04 Reserved 1.06 Reserved 1.07 Reserved 1.08 Reserved 1.09 Reserved 1.10 Reserved 1.11 Record Keeping 1.12 Permit
STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION
West Virginia University Environmental Health and Safety STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION Origination Date August 2013. Contents Purpose:... 2 Job Scope... 2 Definitions... 2 Roles/Responsibilities:...
CITY OF PHILADELPHIA DEPARTMENT OF PUBLIC HEALTH BOARD OF HEALTH ASBESTOS CONTROL REGULATION
CITY OF PHILADELPHIA DEPARTMENT OF PUBLIC HEALTH BOARD OF HEALTH ASBESTOS CONTROL REGULATION Philadelphia Department of Public Health Air Management Services 321 University Avenue Philadelphia, PA 19104
Policy on the Management of Asbestos
WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other
Policy for the Management of Asbestos in the Workplace
Southwark Council Management of Asbestos in the Workplace November 2011 Page 1 of 15 CONTENTS 1. INTRODUCTION... 3 2. POLICY STATEMENT... 3 3. ASBESTOS RISK CLASSIFICATION SCHEME... 5 4. SAMPLING OF ASBESTOS
HART ENVIRONMENTAL RESOURCES
HART ENVIRONMENTAL RESOURCES 262 Hedge Dr. Springfield, OH 45504 (937) 325-8777 (937) 324-0288 FAX ASBESTOS INSPECTION REPORT 933 Xenia Ave. Dayton, Ohio 45410 PREPARED FOR: Mr. Dennis Zimmer Montgomery
BLR s Safety Training Presentations
BLR s Safety Training Presentations Asbestos Safety 29 CFR 1910.1001 I. Background for the Trainer: The OSHA Asbestos Standard for general industry, found in 29 CFR 1910.1001, requires information and
POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT. for
POTENTIALLY HAZARDOUS MATERIALS BUILDING INSPECTION REPORT for Michigan State University Engineering and Architectural Services Physical Plant Building, Room 101 East Lansing, Michigan 48824-1326 at Michigan
Asbestos Containing Material MANAGEMENT PLAN
Asbestos Containing Material MANAGEMENT PLAN Introduction Extensive research has shown exposure to asbestos containing material (ACM) when it becomes airborne (commonly referred to as friable) poses a
Fact Sheet on Asbestos
Fact Sheet on Asbestos WHAT IS ASBESTOS? Asbestos is a naturally occurring mineral found in certain rock formations, mined from open pit mines. Most of the asbestos used in the United States today comes
WORK PROCEDURES FOR ASBESTOS RELATED ACTIVITIES
California Institute of Technology WORK PROCEDURES FOR ASBESTOS RELATED ACTIVITIES Caltech Environment, Health, and Safety Office 1200 E. California Blvd., M/C 25-6 Pasadena, CA 91125 Phone: 626.395.6727
ASBESTOS CONTAINING MATERIALS (ACM) REFERENCE GUIDE
ASBESTOS CONTAINING MATERIALS (ACM) REFERENCE GUIDE by Environmental Health & Safety Office January 2012 Page 1 of 38 ASBESTOS ON CAMPUS... 3 MAG BLOCK... 5 AIRCELL... 6 SWEATWRAP... 7 CAPOSITE... 8 PARGING
Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%)
Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%) I. Asbestos Survey Requirements Prior to performing any construction,
Managing your asbestos hazards
Managing your asbestos hazards Asbestos is a naturally occurring mineral fiber mined from the earth. It was used in over 3,000 products, including many found in homes. When asbestos fibers become airborne,
ASBESTOS MATERIALS IN SCHOOLS
CODE OF PRACTICE FOR MANAGEMENT OF ASBESTOS MATERIALS IN SCHOOLS CONTENTS 1. Introduction 1.1 Scope 1.2 The OPW Health and Safety Unit 2 Background 2.1 General Information 2.2 Main Risks 2.3 Main Risk
CHEMICAL CONTROL ORDER FOR ASBESTOS
DENR ADMINISTRATIVE ORDER No. 02 Series of 2000 Subject: CHEMICAL CONTROL ORDER FOR ASBESTOS Section 1. Legal Authority This Chemical Control Order (CCO) is issued on the basis of authority given to the
ASBESTOS AWARENESS TRAINING
ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVRESITY Substance: Asbestos CAS Registry Number: 1332-21-4 ASBESTOS AWARENESS TRAINING Synonyms: chrysotile, amosite (cummingtonite-grunerite), actinolite,
Procedures and Guidelines for Texas A&M University-Kingsville Employees
Procedures and Guidelines for Texas A&M University-Kingsville Employees ENVIRONMENTAL HEALTH & SAFETY OFFICE 1010 RETAMA DRIVE SUPPORT SERVICES BUILDING KINGSVILLE, TX 78363 MARCH 2004 TABLE OF CONTENTS
ASBESTOS SCIENCE TECHNOLOGIES, INC.
ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - [email protected] Report for Lincoln Elementary School 1582 Lincoln Road Yuba City, Ca. 95993 Mold Report
ASBESTOS OPERATIONS AND MAINTENANCE PLAN
UNIVERSITY OF FLORIDA ASBESTOS OPERATIONS AND MAINTENANCE PLAN Administered by: Environmental Health and Safety Building 179 PO Box 112190 Gainesville, Florida 32611 Introduction The following document
ASBESTOS. CSEA / Local 1000 AFSCME / AFL-CIO. 143 Washington Avenue, Albany, New York 12210. Danny Donohue, President
S A F E T Y & H E A L T H ASBESTOS QUESTIONS AND ANSWERS FOR BUILDING OCCUPANTS CSEA / Local 1000 AFSCME / AFL-CIO 143 Washington Avenue, Albany, New York 12210 Danny Donohue, President : CSEA OCCUPATIONAL
