Construction Notification and Start-Up
|
|
|
- Hilary Baldric Charles
- 10 years ago
- Views:
Transcription
1 The University of British Columbia Land and Building Services Prepared by: Frank Geyer Work Procedure Approved by: David Barnes Construction Notification and Start-Up Issue Date: 08 October 2002 Replaces: 27 May 2001 I-D Application This procedure is to be used for the notification of all pertinent parties as to the impending project to be constructed by Land & Building Services. 2. References I-B-28 I-D-18 I-D-23 Hazard Identification & Assessment Minor Capital & Capital Maintenance Projects Departmental Funded Projects 3. Definitions Refer to document I-D-04, Projects Definitions. 4. Procedures A. IN-HOUSE CONSTRUCTION PROJECTS 1. Construction Notification a) Upon authorization of the Pre-construction Estimate and prior to any construction start-up, all affected parties to the project must receive proper notification as to the start and anticipated completion dates of construction. b) The Project Coordinator shall discuss trade resource scheduling with the Scheduler to confirm the earliest possible start date and whether work can be completed by the set deadline, with some allowance for change orders during construction. The Project Manager shall be notified of the construction scheduling, who in turn will advise the Design Leader, Customer and Facility Manager. c) The Project Coordinator shall ensure that all shop hazard assessments have been received from the trades involved in the Project, along with detailed work procedures, in strict conformance with the Policy I-B-28, Hazard Identification & Assessment. Any missing or unclear information shall be remedied by the Project Coordinator prior to any work order being issued to the shop in question, with a copy of the project hazard assessment attached to all work orders issued by the Service Centre Coordinator. d) The Notification of Project Construction shall be issued on all Plant Operations projects exceeding $10,000 in value. The Project Coordinator shall generate such notification using the
2 I-D-29 FG CONSTRUCTION NOTIFICATION & START UP.DOC PAGE Const Notification <rev. date>.doc form (attached as Schedule A), and the draft electronic file to the Project Manager. e) The Project Manager shall complete the form, obtain the Scheduler s sign-off on the dates listed, and shall arrange with the Projects Clerk for distribution of the form by fax or Campus Mail at least 24 hours before construction start-up. The distribution list is given in Appendix I. f) If the Project involves the removal, encapsulation, or enclosure of friable asbestos materials or the demolition, dismantling, or repair of any part of a building or structure in which insulating materials containing asbestos have been used, or in which asbestos products have been manufactured, the Project Coordinator shall contact the LBS Asbestos Coordinator to see if the work is covered by the University s standing Notice of Project (NOP) with the WCB. If not, the Project Coordinator shall furnish all necessary information to the LBS Asbestos Coordinator to enable a special NOP to be issued to the WCB at least 24 hours before construction start-up. A copy of the completed NOP form shall be posted at the worksite, on the Project Safety Board along with all other Hazard Assessment information. 2. Construction Start-Up a) Site mobilization shall take place as per the earliest start date advised by the Scheduler, involving setting up of necessary site office, hoarding, material storage and other temporary facilities, site signage and work start-up. b) The minimum required site signage shall consist of: i) Project Information Board, including copy of the Notification of Project Construction, building permit (if applicable), and relevant construction plans; and ii) Project Safety Board, including copy of Site Safety Rules (attached as Schedule B), all hazard assessment information, asbestos assessments and notices, warning signs, WCB information and a Project Site Sign-In sheet (attached as Schedule C) for all staff entering the job site, acknowledging that they have read all information posted on the Safety Board. c) A Pre-Construction Meeting shall be held by the Project Coordinator to discuss the schedule, roles and responsibilities, lines of communication, key schedule milestones, inspection schedule, safety and hazard issues, logistics, etc. relevant to the Project. All high risk hazards shall be specifically noted and discussed. In attendance shall be the Project Manager, Site Supervisor, Scheduler, all Trade Heads who will have staff participating in the construction, sub-contractor representatives, Design Leader and key design professionals. The form of agenda to be followed is attached as Schedule D. The meeting shall be minuted with copies distributed to all participants. d) All invitees and participants in the Pre-Construction Meeting shall review and sign-off on the Project Safety Board before leaving the site. The Project Coordinator shall advise the Project Clerk to contact all absentees from the Pre-Construction Meeting to visit the site, review and sign-off on the Project Safety Board and report back as soon as that is complete. Until such is undertaken, no staff of the delinquent supervisory staff shall enter the site. It is the responsibility of each Trade Head and all other supervisors of staff assigned to the jobsite to be aware of the site conditions and to advise their staff accordingly, including directing them to read the Project Safety Board and have them sign-in prior to entering the jobsite. Work
3 I-D-29 FG CONSTRUCTION NOTIFICATION & START UP.DOC PAGE procedures for high risk hazards are to be submitted by Trade Heads to the Project Manager for approval prior to starting any work. B. OUTSOURCED CONSTRUCTION PROJECTS 1. Construction Notification a) Upon authorization of the Pre-construction Estimate, contract award to the successful Contractor and prior to any construction start-up, all affected parties to the project must receive proper notification as to the start and anticipated completion dates of construction. b) The Contractor shall forward to the Project Manager a Gantt chart showing the proposed construction scheduling. The Project Manager shall in turn advise the Design Leader, Customer and Facility Manager. c) The Notification of Project Construction shall be issued on all Plant Operations projects exceeding $10,000 in value. The Project Manager shall generate such notification using the Const Notification <rev. date>.doc form (attached as Schedule A), and shall arrange with the Projects Clerk for distribution of the form by fax or Campus Mail at least 24 hours before construction start-up. The distribution list is given in Appendix I. d) The Project Manager shall notify the Contractor to ensure that the Contractor s Safety Program is prepared and submitted to the Worker s Compensation Board and copied to the Project Manager. The safety program shall include, but not be limited to: i) The Contractor s policy statement of aims and responsibilities of the employer, supervisors and workers, with reference to the latest version of the WCB Regulations; ii) Provision for the regular inspection of the premises, equipment, work methods and practices and procedures to be taken to correct any hazardous conditions; iii) Policy on investigation of accidents/incidents and determination of corrective action; iv) Emergency preparedness information; v) Policy on personal protective clothing and equipment standards and first aid services; vi) Formation of a job site safety committee, frequency of meetings and reporting criteria; and vii) Maintenance of records and statistics for tracking and planning purposes and the availability of this information for the WCB, the University s Health, Safety & Environment groups, management and the workers; The Project Manager shall forward a copy of the Contractor s Safety Program to the LBS Health, Safety & Environment group. e) If the Project involves the removal, encapsulation, or enclosure of friable asbestos materials or the demolition, dismantling, or repair of any part of a building or structure in which insulating materials containing asbestos have been used, or in which asbestos products have been manufactured, the Contractor shall also prepare and submit a Notice of Project Asbestos form to Worker s Compensation Board and copied to the Project Manager at least 24 hours before construction start-up. A copy of the completed NOP form shall be posted at the worksite, on the Project Safety Board along with the Contractor s Safety Program.
4 I-D-29 FG CONSTRUCTION NOTIFICATION & START UP.DOC PAGE 2. Construction Start-Up a) Site mobilization shall take place as per the start date agreed to between the Contractor and Project Manager, involving setting up of necessary site office, hoarding, material storage and other temporary facilities, site signage and work start-up. b) The minimum required site signage shall consist of: i) Project Information Board, including copy of the Notification of Project Construction, building permit (if applicable), and relevant construction plans; and ii) Project Safety Board, including copy of Site Safety Rules (attached as Schedule B), the Contractor s Safety Program, asbestos assessments and notices, warning signs, WCB information and a Project Site Sign-In sheet (attached as Schedule C) for all staff entering the job site, acknowledging that they have read all information posted on the Safety Board. c) A Pre-Construction Meeting shall be held by the Project Manager to discuss the schedule, roles and responsibilities, lines of communication, key schedule milestones, inspection schedule, safety and hazard issues, key requisition and shutdown procedures, logistics, etc. relevant to the Project. All high risk hazards shall be specifically noted and discussed. In attendance shall be the Project Manager, Contractor, sub-contractor representatives, Design Leader, key design professionals and Customer/User. The form of agenda to be followed is attached as Schedule D. The meeting shall be minuted, with copies distributed to all participants, by the Design Leader, who shall conduct the balance of the meeting after the Project Manager has completed the initial administrative procedures. d) All invitees and participants in the Pre-Construction Meeting shall review and sign-off on the Project Safety Board before leaving the site. 5. Appendices and Schedules Appendix I Notification of Project Construction Distribution List Schedules: A. Notification of Project Form B. Site Safety Rules Form C. Project Site Sign-In Sheet D. Pre-Construction Meeting Agenda Form
5 APPENDIX I - NOTIFICATION OF PROJECT CONSTRUCTION DISTRIBUTION LIST Department/Title Land & Building Services In-House Construction Outsourced Construction < $250K $250K < $250K $250K Associate Vice President X X X Director, UBC Utilities X X X X Director, Transportation Planning * * Supervisor, Health, Safety & Environment X X UBC Plant Operations Director X X Associate Director, Project Services X X X X Associate Director, Operations Engineering X X X X Associate Director, Building Operations (circulates to Trade Supervisors) X X X X Associate Director, Municipal & Business Services X X * * Manager, Design Office X * X * Manager, Technical Services X X X X CRDM Program Manager X X X X Resource Planner X X * * Project Manager X X X X Project Coordinator X X Facility Manager X X X X Campus Planning & Development University Architect/Landscape Architect X X X X Director, Campus Planning * X * X Space Administration Manager X X X X Capital Programs Manager X X X X Physical Access Advisor X X X X Associate Director, Campus & Community Planning X X X X Space Inventory Manager X X X X Others Manager, Network Facilities (IT Services) X X X X Director, Campus Security X X X X Director, Parking & Access Control X X X X Secure Access Manager X X X X Manager, Fire Protection Services X X X X Director, Health, Safety & Environment X X X X Major Contracts Officer (Supply Management) X X Manager, Risk & Insurance (Treasury) X X X X Director, Classroom Services X X X X Director, Disability Resources Centre X X X X Workers Compensation Board (New Project Notification) X X X X Contractor X X Client/User X X X X X mandatory * - optional (project specific)
6 SCHEDULE A SAMPLE SAMPLE
7 SCHEDULE B UBC PLANT OPERATIONS PROJECT SERVICES DIVISION SITE SAFETY RULES 1. Only approved substantial footwear with safety toes shall be worn. 2. Hard hats must be worn while on site. 3. Hand, eye, ear, respiratory and skin protection is required when exposed to hazards. 4. All floors, ceilings and walls shall be checked against the asbestos inventory to determine the presence of ACM and appropriate work procedures prior to commencing work. 5. Guardrails and handrails are not to be removed unless required by the work in the immediate area and railings so removed must be replaced before the worker leaves the area. 6. No horseplay of any kind will be tolerated. 7. Any worker, as determined by the site supervisor, found to be unfit for his/her duties shall be removed from the site. 8. The site must be kept clean and orderly at all times. 9. No music shall be played which inhibits communication between workers or disrupts building occupants. 10. Ladders must be secured top and bottom. Do not use poorly constructed or defective ladders. 11. Scaffold planks or beams must be of sound material and clear of defects. Do not use poorly constructed scaffold. See that scaffolding is provided with guardrails. 12. Shorts and torn clothing exposing skin are not permitted. 13. All persons entering the site must report to the Site Supervisor or person in charge. 14. All trades personnel must read the site notice boards before commencing work. 15. Personnel not trained in specific UBC policies or procedures related to work practices shall not undertake such work. 16. Persons failing to comply with the above or any WCB regulation and thereby causing hazards to either himself or his fellow workers will be removed from the site. SAFETY COMES FIRST
8 SCHEDULE C UBC Plant Operations LBS Projects Services 2329 West Mall Vancouver, BC Canada V6T 1Z4 Tel: (604) Fax: (604) PROJECT SITE SIGN-IN SHEET IT IS THE RESPONSIBILITY OF ALL PERSONS ENTERING THIS SITE TO REVIEW AND UNDERSTAND ALL INFORMATION POSTED ON THIS BOARD. ALL VISITORS REQUIRING ACCESS TO THIS SITE MUST FIRST OBTAIN PERMISSION FROM THE ATTENDING SITE SUPERVISOR OR PROJECT COORDINATOR. VISITORS MUST COMPLY WITH ALL POSTED SITE SAFETY REQUIREMENTS. PROJECT COORDINATOR: TEL: COMPANY: SITE SUPERVISOR: TEL: NAME (PRINT) DEPARTMENT SIGNATURE DATE
9 SCHEDULE D UBC PLANT OPERATIONS PROJECT SERVICES DIVISION AGENDA FOR PRE-CONSTRUCTION MEETING FOR Project No. Date: 1. Introduction of participants 2. Lines of communications, emergency contact numbers 3. Access to work areas, parking and locations of lay-down or material storage areas 4. Temporary facilities, use of existing sanitary facilities 5. Protection of property, site safety and protection of public 6. Review of high risk safety hazards (asbestos, excavations, electrical contact, etc.) 7. Cleaning operations and disposal of waste materials 8. Procedures for key acquisitions, service shutdowns (contractors) 9. Submittals (shop drawings, product data) 10. Construction schedule 11. Regulatory inspections, schedule 12. Quality control 13. Extra work and changes to contract 14. Drawing and specification review 15. Site visit and review 16. Review of Project Safety Board and sign-off by all participants
CSC-DIVISION 1-MASTER SECTIONS Description
CSC-DIVISION 1-MASTER SECTIONS Description 01 11 00 Summary of Work by Consultant 01 12 00 Multiple Contract Summary by Consultant 01 14 00 Work Restrictions see below 01 21 00 Allowances by Consultant
Approved by: UBC ACT Committee
The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy
Policy for the Management of Asbestos in Buildings
in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably
CONTRACTOR SAFETY MANAGEMENT PROCEDURE
CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,
Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy
ASBESTOS POLICY Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy This is a controlled document. It should not be altered in any way without the express permission of the author or their representative.
Asbestos Management & Abatement
Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &
Contractor Safety Management
1.0 Introduction Memorial University will ensure that a diligent contractor management process is established. This procedure establishes requirements for contract administration and oversight of contractor
Asbestos Management Policy (Version 3)
Asbestos Management Policy (Version 3) Contents Page Introduction 3 College Policy Statement for Asbestos Management 3 Objectives (of this Policy and Procedure) 3 Application of Policy 4 Licensed Asbestos
The Management of Asbestos containing Materials
The Management of Asbestos containing Materials Status Owner Approval by University Court Draft Head of Estates and Building 1 Purpose... 1 2 Scope... 3 3 Principles... 4 4 Procedure... 5 5 Accountabilities...
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD
POLICY Contents. 1.0 Introduction Statement
POLICY Contents 1.0 Introduction Statement 2.0 Legal Responsibility 2.1 Asbestos Management Hierarchy 2.2 Duty Holders Responsibility 2.3 Employees Responsibility 3.0 Asbestos Management Procedure 4.0
Asbestos Management Plan EC 45 Page 1
Name: Asbestos and ACBM (asbestos containing building material) Management Plan Areas Affected: All buildings that contain asbestos and ACBM on campus Effective Date: 1/1/09 Reviewed/Revised: 12/15/12
British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT
BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk
COLUMBUS STATE COMMUNITY COLLEGE EMPLOYEE SAFETY MANUAL
COLUMBUS STATE COMMUNITY COLLEGE EMPLOYEE SAFETY MANUAL HAZARDOUS MATERIAL MANAGEMENT Effective October 15, 1995 Page 1 of 4 Updated August, 2008 Revised August, 2009 A. Columbus State Community College
ASBESTOS CONTROL PLAN
ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization
Vendor Management Program
The Corporation of the City of Kawartha Lakes is committed to the provision of a safe and healthy work environment for its employees, contractors and visitors. To promote this type of environment, the
CONTRACTOR SAFETY MANAGEMENT PROGRAM
CONTRACTOR SAFETY MANAGEMENT PROGRAM 16 th June 2010 TABLE OF CONTENTS 1.0 PURPOSE AND SCOPE 1.1 Intent 1.2 Scope 1.3 Program Elements 2.0 REGULATORY REQUIREMENTS 3.0 BACKGROUND AND GLOSSARY 3.1 Background
CONSTRUCTION SAFETY POLICY
California Institute of Technology CONSTRUCTION SAFETY POLICY Caltech Environment, Health, and Safety Office 1200 E. California Blvd., M/C 25-6 Pasadena, CA 91125 Phone: 626.395.6727 Fax: 626.577.6028
University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
Contractor Safety Program Office of Environmental Health and Safety University of Toronto
Office of Environmental Health and Safety Table of Contents Overview... 3 Program Objectives... 3 University Health and Safety Policy... 4 Environmental, Health and Safety Mission Statement... 4 Roles
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
ASBESTOS MANAGEMENT POLICY
ASBESTOS MANAGEMENT POLICY Published : 4th Revision December 2014 1 Table of Contents INTRODUCTION... 3 DUTY TO MANAGE ASBESTOS... 3 DUTIES OF CAMPUS SERVICES... 3 1.0 POLICY OBJECTIVES... 5 2.0 RESPONSIBILITIES...
Wellesley College Asbestos Management Program
Wellesley College Asbestos Management Program Table of Contents Page Policy 2 Impacts of Asbestos Containing Materials (ACM)... 3 Compliance... 3 Objectives... 4 Operational Controls Standard Operating
Administrative Procedure. Asbestos
Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY CONTENTS Page No 1 INTRODUCTION 2 2 LEGISLATION 2 3 HIERARCHY OF CONTROL 2 4 WORK AT HEIGHT POLICY 3 5 ROLES AND RESPONSIBILITIES 3 6 RISK ASSESSMENTS
THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL
THE CORPORATION OF DELTA ENGINEERING CONSULTANT PROJECT PROCEDURAL MANUAL OCTOBER, 2013 TABLE OF CONTENTS 1. CHECKLIST PAGE NO. 2. CHECKLIST DETAILS A. Design Path 3 B. Property Acquisition 6 C. Outside
ROYAL HOLLOWAY, UNIVERSITY OF LONDON
ROYAL HOLLOWAY, UNIVERSITY OF LONDON ASBESTOS MANAGEMENT POLICY (Version 2) This Policy defines the College s arrangements for the management of asbestos and the measures to be taken for the protection
INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations...
March 2006 INTRODUCTION... 3 1.0 Purpose... 4 2.0 Policy... 4 Exception for Short-Term Workplace Visits... 4 Relevant Legislation and Regulations... 5 Definitions... 5 Contractor Safety Coordination Overview...
UBC Plant Operations Asbestos Work Procedures April 2004
UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other
UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN
UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 0.2 Jul 2013 Initial draft for comment Jon Fahie 0.3 Sep
Facilities Division Integrated Safety Management Plan March 16, 2006
Facilities Division Integrated Safety Management Plan March 16, 2006 Contents Facilities Division Introduction 1.0 Integrated safety Management 2.0 Accountability 3.0 Satellite Accumulation Area 4.0 Facilities
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons
Accommodation Officers Information Booklet. Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy
Accommodation Officers Information Booklet Asbestos The Asbestos Abatement Programme and the Asbestos Management Policy This Guideline has been produced solely for use by State Authorities that come within
Managing Asbestos Policy
Managing Asbestos Policy Liverpool Mutual Homes Page 1 of 16 Table of Contents 1. MANAGEMENT INFORMATION 2. POLICY STATEMENT 3. POLICY AIMS AND KEY OBJECTIVES 4. INTRODUCTION 5. DETAIL 6. LINKS TO LMH
Accident/Incident Investigation & Reporting Procedure
Accident/Incident Investigation & 1. Overview The recognises its obligation to ensure that all accidents and incidents are reported, recorded and investigated. We are committed to identifying corrective
BCIT. CNST 1100 Construction Safety Officer Training. Lesson Plan
BCIT CNST 1100 Construction Safety Officer Training Lesson Plan BCIT Two Week Outline- CNST 1100 (Please note there may be adjustments made to this outline) Monday- Day #1 Week #1 0730 Paperwork Introductions
ASBESTOS MANAGEMENT PLAN. Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU
ASBESTOS MANAGEMENT PLAN Borough of Poole Transportation Services, Property Management, Civic Centre, Poole, Dorset BH15 2RU CONTENTS 1. INTRODUCTION 2. HOW DOES THE BOROUGH OF POOLE MANAGE ITS ASBESTOS
Asbestos Management Plan
Harlow Council Asbestos Management Plan Version 4 Scope: This management plan applies to the management of all asbestos containing materials to properties under the ownership/management of Harlow Council
CONTRACTOR INDUCTION HANDBOOK
CONTRACTOR INDUCTION HANDBOOK POLICY The health and safety of all school employees and contractor employees is a vital concern at the school. Contract personnel will be treated in a manner consistent with
ASBESTOS MANAGEMENT PLAN
ASBESTOS MANAGEMENT PLAN PREPARED BY: Scott Gregory: Estates - Property Services DATE: 18/04/2014 STATUS: Draft ISSUE: 2014 (02) September 2014 NEXT REVISION DATE: April 2014 Contents 1.0 Introduction
Whistler Village Construction Management Strategy
Whistler Village Construction Management Strategy Purpose: To mitigate the impacts of construction activity on the Whistler Village resort experience and on Village businesses and property owners. Objectives:
Asbestos Policy. Planning, Performance Management and Support Services. Legacy Causeway Asbestos Policy (Ref: CHSST/04/211)
Asbestos Policy Reference Number: NHSCT/09/192 Responsible Directorate: Planning, Performance Management and Support Services Replaces (if appropriate): Legacy Causeway Asbestos Policy (Ref: CHSST/04/211)
Asbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety
Asbestos Abatement Management Program Facilities Operations and Development Environmental Health & Safety November 7, 2012 INTRODUCTIONS David Kos (EHS) Director of Environmental Affairs David Kehl (EHS)
Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004
Estates Division Imperial College London Room 503 Sherfield Building South Kensington Campus London SW7 2AZ, UK Tel: +44 (0)20 7594 9832 Fax: +44 (0)20 7594 9050 [email protected] www.imperial.ac.uk
North Carolina State University. Asbestos Management Plan
North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building
Course Guidelines. Occupational Health and Safety for the Asbestos Worker
Course Guidelines Occupational Health and Safety for the Asbestos Worker February 2013 Table of Contents 1.0 Introduction...................................................... 1 2.0 Course Criteria...................................................
Policy on the Management of Asbestos
WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other
ASBESTOS MANAGEMENT INTRODUCTION
SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous
C162 Asbestos Convention, 1986
C162 Asbestos Convention, 1986 Convention concerning Safety in the Use of Asbestos (Note: Date of coming into force: 16:06:1989.) Convention:C162 Place:Geneva Session of the Conference:72 Date of adoption:24:06:1986
Construction (Design and Management) Regulations 2007
MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by
PROJECT BRIEF Version (insert number)
PROJECT BRIEF Version (insert number) 1 Project Name ------------------------------------------------------------------- 1.1 The Project Project Address Nature of Work Location 1.2 DCC Client for Project
Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue
Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority
LEGAL REVIEW & UPDATE
LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break
SITE SPECIFIC FALL PROTECTION PLAN
1 THIS PLAN IS SPECIFIC TO: PROJECT & ADDRESS 1.1 THIS PLAN IS SPECIFIC TO THE FOLLOWING AREA(S) ON SITE: Parkade level: Typical level: Other: Between G/L: 1.2 THIS PLAN IS APPLICABLE TO THE FOLLOWING
Fall Protection Safe Work Plan Fall Distance of 7.5M or More
Department of Facilities Management Occupational Health and Safety Fall Protection Safe Work Plan Fall Distance of 7.5M or More When employees are involved in jobs with a risk of falling they must: Shop:
ASBESTOS CONTAINING MATERIALS POLICY
ASBESTOS CONTAINING MATERIALS POLICY Document Control Version 3 Ratified by Risk Management Sub Group Date Ratified 19 December 2012 Name of Originator/Author Head of Estates and Facilities Name of Responsible
This procedure applies to all DECS employees, students and others in worksites, schools, preschools and departmental offices. 1.0 PURPOSE...
OCCUPATIONAL HEALTH SAFETY AND WELFARE INJURY / INCIDENT REPORTING and INVESTIGATION PROCEDURE SCOPE This procedure applies to all DECS employees, students and others in worksites, schools, preschools
Independent Contractor Policy
Independent Contractor Policy This Policy has been implemented to prevent accidents and personal injuries. It is not intended to be entirely inclusive. It is the responsibility of the Independent Contractor
DUTIES and GUIDANCE. for. BOARDS of MANAGEMENT. DEALING with ASBESTOS CONTAINING MATERIALS. before, during & after
DUTIES and GUIDANCE for BOARDS of MANAGEMENT on DEALING with ASBESTOS CONTAINING MATERIALS before, during & after SCHOOL REFURBISHMENT WORKS, DEMOLITIONS AND BUILDING WORKS PROJECTS CONTENTS CONTENTS...2
7. Do you perform any out of state work?... If yes, in what states and provide details of work performed
Applicant s Name* (*If more than one entity, attach separate sheet with description of each entity s operations, relationship to each other and ownership.) Contractors Application Agent Applicant Mailing
SECTION 02 8213 ASBESTOS ABATEMENT
PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.
How To Deal With Asbestos In Minster Of Minsteria
RELATED TO EXPOSURE TO ASBESTOS AT WORK [S.L.424.23 1 SUBSIDIARY LEGISLATION 424.23 RELATED TO EXPOSURE TO ASBESTOS AT WORK REGULATIONS LEGAL NOTICE 323 of 2006. 15th December, 2006 1. (1) The title of
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment
CRITERIA FOR REGISTRATION AS ASBESTOS CONTRACTOR
Published: March 2003 Department of Labour CRITERIA FOR REGISTRATION AS ASBESTOS CONTRACTOR Chief Directorate of Occupational Health and Safety NO: OHC 3 2 1. BACKGROUND In terms of the Asbestos Regulations,
ASBESTOS POLICY MANAGEMENT PLAN
ASBESTOS POLICY & MANAGEMENT PLAN HS20 Version V2 Approved by: Health, Safety and Security Committee Date approved: March 2011 Ratified by: Hospital Executive Committee Date ratified 24 th April 2012 Document
UNVERSITY HIGH SCHOOL U0018 65-108-9010-0001 500 W. Gregory St. Normal, IL 61761. School Asbestos Management Plan. Supplemental.
UNVERSITY HIGH SCHOOL U0018 65-108-9010-0001 500 W. Gregory St. Normal, IL 61761 School Asbestos Management Plan Supplemental Prepared By: David Martin Management Planner Environmental Health and Safety
4.00 Student means a Student registered, enrolled or participating in any course or program offered by the university.
ENVIRONMENTAL HEALTH AND SAFETY POLICY University Policy No: SS9200 Classification: Safety and Security Approving authority: Board of Governors Effective date: March, 2012 Supersedes: May, 1999 Last Editorial
ASBESTOS MATERIALS IN SCHOOLS
CODE OF PRACTICE FOR MANAGEMENT OF ASBESTOS MATERIALS IN SCHOOLS CONTENTS 1. Introduction 1.1 Scope 1.2 The OPW Health and Safety Unit 2 Background 2.1 General Information 2.2 Main Risks 2.3 Main Risk
SECTION 16 ASBESTOS MANAGEMENT
SECTION 16 ASBESTOS MANAGEMENT 16.1 Asbestos Management Procedure 16.2 Asbestos O&M Procedure Reviewed: October 2008 Revised: February 2003 Date Accepted: April 2002 Draft Date: December 2001 16.1 ASBESTOS
Asbestos Storage Facility Plan Examples
Asbestos Storage Facility Plan Examples The purpose of this document This document contains examples of what an operational plan, plans and specification, contingency plan and closure plan should look
Occupational Health & Safety Policy Injury & Incident Reporting
Occupational Health & Safety Policy Injury & Incident Reporting Policy number 46 Version 1 Approved by board on 6 June 2014 Responsible person President Review date June 2016 Introduction Living Positive
TRU Asbestos Management
Number: OH&S 9.20.1 Revision Date: 09/08/2015 TRU Asbestos Management TRU Asbestos Management Page 1 of 5 1. PURPOSE 1.1. To describe the process and management of asbestos containing materials on the
Fire Damage Repairs, 2510 Burton Street
Fire Damage Repairs, 2510 Burton Street Introduction: The Housing Authority of the County of San Joaquin (Authority) is seeking quotes from Class B General Building Contractors (Contractor) to provide
Facilities management Contractor Safety Guideline
TABLE OF CONTENTS 1. POLICY...2 2. PURPOSE...2 3. SCOPE...2 4. DEFINITIONS...2 5. FACILITIES MANAGEMENT CONSTRUCTION PROJECTS...3 5.1. GENERAL...3 5.2. JOB START SAFETY MEETING PREPARATION...3 5.3. GENERAL
OCCUPATIONAL HEALTH AND SAFETY AUTHORITY ACT (CAP. 424) Protection of Workers from the Risks related to Exposure to Asbestos at Work Regulations, 2006
L.N. 323 of 2006 B 4649 OCCUPATIONAL HEALTH AND SAFETY AUTHORITY ACT (CAP. 424) Protection of Workers from the Risks related to Exposure to Asbestos at Work Regulations, 2006 IN EXERCISE of the powers
Asbestos Control Programs
Asbestos Control Programs Effective: September 2000 Vice-President, Finance and Administration Applicable Legislation: Occupational Health and Safety (OHSA), R.S.O. 1990 O.Reg 837, R.R.O. 1990, Designated
OCCUPATIONAL HEALTH AND SAFETY POLICY: INCIDENT AND INJURY REPORTING ERJ 6.28.1
OCCUPATIONAL HEALTH AND SAFETY POLICY: INCIDENT AND INJURY REPORTING ERJ 6281 INTRODUCTION The Edmund Rice Justice Aotearoa New Zealand Trust recognises that the health and safety of its employees is a
STANDARD OPERATING INSTRUCTION. Worksite Safety Traffic Management Procedure
STANDARD OPERATING INSTRUCTION Worksite Safety Traffic Management Procedure November 2012 Title System Reference Number Approved By Worksite Safety Traffic Management People and Wellbeing SOI-GVW-329 Manager
A Workplace Accident and Injury Reduction (AWAIR) Program for Small Construction Employers
A Workplace Accident and Injury Reduction (AWAIR) Program for Small Construction Employers May 2012 Minnesota Department of Labor and Industry Occupational Safety and Health Division This material can
Student Residency Agreement Academic Year 2015/2016
Student Residency Agreement Academic Year 2015/2016 This student residency agreement ( Agreement ) is dated on the Date of Occupancy between the Resident and the Operator. The following pages, Schedules
Bachelor of Computer Science (ICS) Program. 2011 Application Form
Bachelor of Computer Science (ICS) Program 2011 Application Form Information for Applicants: Requirements: 1. A bachelor's degree: in a non-computer related area (e.g., arts, science, commerce, music,
Communication of Health and Safety Policy and Information
Modules 1 4 1. Communication of Health and Safety Policy and Information 2. Allocation of Responsibility/Accountability for Health and Safety 3. Purchasing Controls 4. Contractors Communication of Health
Control of Asbestos Policy
Control of Asbestos Policy Version Number: V1D Name of originator/author: Estates Manager 0161 277 1235 Name of responsible committee: Estates and Facilities Committee Name of executive lead: Director
This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor.
Big Four Construction Hazards: Fall Hazards This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor. It does not necessarily
OH&S Management Systems Audit Checklist (NAT, E3)
3.1.2 3.1.1 Introduction OH&S Management Systems Audit Checklist (NAT, E3) This audit checklist is based on Element 3 (Implementation) of the National Self-Insurers OHS Audit Tool. For a full copy of the
LOS ANGELES UNIFIED SCHOOL DISTRICT DIVISION OF ADULT AND CAREER EDUCATION SAFETY TEST FOR ELECTRICIAN PROGRAM
LOS ANGELES UNIFIED SCHOOL DISTRICT DIVISION OF ADULT AND CAREER EDUCATION SAFETY TEST FOR ELECTRICIAN PROGRAM Service Area: Industry Sector: Energy, Environment & Utilities Class Teacher (Please Print)
Asbestos Policy. Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust. November 2007. All Staff.
Appendix 1 Ymddiriedolaeth GIG Gwasanaethau Ambiwlans Cymru Welsh Ambulance Service (NHS) Trust Asbestos Policy Approved by Date Review Date Target Audience Trust Board November 2007 November 2008 All
Author G Morton July 2015. Newcastle University Asbestos Management Plan 2015
Newcastle University Asbestos Management Plan 2015 1 Contents 1.0 Introduction 2.0 Asbestos Management Duty Holder Responsibilities 2.1 Asbestos Manager (Head of Maintenance) 2.2 University Asbestos Survey
COMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE COMMANDER 56TH FIGHTER WING (AETC) AIR FORCE INSTRUCTION 32-1052 LUKE AIR FORCE BASE Supplement 1 5 NOVEMBER 2008 Civil Engineering FACILITY ASBESTOS MANAGEMENT COMPLIANCE WITH THIS PUBLICATION
Construction and Civil Work Management
STANDARD LME-12:001901 Uen Rev A Contents 1 Introduction... 3 2 Definitions... 3 3 Requirements... 4 3.1 General... 4 3.2 Responsibilities... 4 3.3 OHS Safety Plan... 5 3.4 Start of Construction Phase...
A Casebook of Fatal Accidents Related to Work-at-Height
A Casebook of Fatal Accidents Related to Work-at-Height Occupational Safety and Health Branch Labour Department Occupational Safety and Health Council This casebook is prepared by the Occupational Safety
STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE
BCD.26 STRATEGIC PLANNING & PLACE BUILDING CONTRACT DIRECTIVE DATE: March 2015 Copyright Reserved TESTING, ASSESSMENT AND WORK WITH ASBESTOS CONTAINING MATERIALS (ACM S) REFERENCE This Directive deals
Management of Health and Safety for Work and Services Contractors Policy June 2010
June 2010 Contents 1. Introduction 3 2. Policy Statement 4 3. Policy Objectives 5 4. Application 6 5. Organisational Responsibilities 7 6. Glossary of Terms 11 7. Authorised Directors Appendix 1 2 www.surrey.ac.uk
