Description of the Task/Activity: General door/window fitting/replacement. Start Date/Time: Site Address/ Location: Finish Date/Time:
|
|
|
- Shawn Booker
- 9 years ago
- Views:
Transcription
1 Method Statement This method statement is to be read in conjunction with the attached risk assessments and the Wembley Windows (SC) Ltd Health and Safety Policy and Procedures Manual. Description of the Task/Activity: Project Name: General door/window fitting/replacement Project Ref: Site Address/ Location: Personnel involved: Name Start Date/Time: Finish Date/Time: Role/Trade Works Supervisor/Senior Window Fitter Window Fitter Labourer Works Supervisor: Key Plant and Tools Required: Key Materials Required: Other Essential Equipment: Specific Identified Residual Hazards: Role: Works Supervisor Tel: Chop saw, jig-saw Spanners, Screwdrivers, Chisels, Stanley knife, Pliers, Hammers, Hand Saws, Files and other small tools Wrecking bar Lump hammer Hammer drill Reciprocating saw Battery powered cordless drill/screwdrivers Work bench Miscellaneous trims and packing UPVc doors and door frames Replacement UPVc windows and associated frames Miscellaneous hinges, brackets, locks and fixings PVA Wood Glue/Adhesive Expanding builders foam Gripfill Podium steps Clamps Fire extinguisher First aid kit Inspection lamp Dust sheets Hop-ups Crawl boards Please refer to the attached risk assessments. The key hazards are: Manual handling Use of power tools Working at height Slips, trips and falls Page 1 of 9
2 A competent and experienced site supervisor will be appointed to manage and oversee the works, including on-site health and safety. All operatives are to receive information and instruction on the content of this method statement and the attached risk assessments. All operatives are to receive a site safety induction prior to the commencement of works. Specific Staff Training Requirements: All operatives using power tools are to have received suitable and sufficient training in the use of the equipment. Only those considered competent to use such equipment shall be permitted to operate such tools. All operatives are to receive training on safe manual handling techniques and asbestos awareness. All operatives are also to receive training in safe working practices for work at height and are to be advised that the use of step-ladders/ladders shall only be used where there is no other suitable alternative, such as full access scaffold, mobile tower scaffold or MEWP. All work is to be carried out by competent experienced window fitters, as a company we are registered and audited by FENSA to ensure that we maintain their high standards of workmanship. A record of all training shall be maintained and will be available on request. Sequence of 1. Liase with the client prior to the start of works to determine start dates and durations for the works. Advise the client of the hazards associated with the works. 2. Ensure all materials, parts and equipment have been ordered and are available for the start of works. 3. On Commencement of works, prepare the site for work by advising the residents of the property of the scope of works and the restrictions that will be placed upon the working area in terms of where the client and other contractors can and cannot go whilst the works are being undertaken. 4. Carry out a visual inspection of the work area to ensure that the required works are as per the specification and that no additional works or materials are likely to be required. Check to see if any suspect substances, such as asbestos are present. If additional works are required, or any suspicious substances have been identified, contact head office immediately and advise the client. 5. Deliver all parts and materials to site, ensuring that appropriate care is taken when manual handling large, heavy or awkward shaped objects, such as heavy glazed units. 6. Cover all affected areas of flooring, soft furnishings, white goods and other items with dust sheets or other appropriate protective sheets to prevent any damage being caused to them. Page 2 of 9
3 Sequence of Door Replacement/Installation 7. This should be carried out in strict accordance with the manufacturers recommendations and in the sequence specified by the manufacturer. Before starting work ensure that the correct door and frame sizes have been supplied, together with all the necessary ironmongery, locks and fixings etc. 8. Where applicable any existing door should first be removed by removing the hinges from the door frame. The existing door frame can then be removed from the wall; this will be done by cutting through the frame and levering the frame away from the wall with a wrecking bar. 9. Carefully remove all old fixings and other parts of the door frame assembly from the wall and dispose of safely in the site skip. 10. Prior to the fitting of the new door and door frame, the walls must be checked to ensure that they are sound and secure, and suitable for the fittings to be used. Where sections of the wall are damaged or are not suitable, the area should be made good or alternative fixings used. 11. Clean the area and prepare the recess for the installation of the new door frame. Fit the frame into position, ensuring a tight fit, checks should also be made to ensure the frame is plumb and square. 12. Use packers where necessary to secure and level the frame in position and then drill through the frame into the masonry/stud wall for the frame fixings. A minimum of 3 frame fixings should be used on each element of the door frame. 13. Once the frame fixings have been inserted and securely fixed /tightened, any voids at the back of the frame should be filled with expanding foam to provide added protection against the weather/water ingress and from unwanted noise. 14. The door hinges can then be fitted to the frame and the door hung on the frame and the door furniture added, this will involve simple hand tools and electric screwdrivers etc. 15. The glazed panels can then be carefully lifted into position, grip gloves should be worn at all times when lifting glazed units and for large panels a minimum of 2 persons should be used to lift and secure the panels in place. The use of suction lifters should also be used to provide a safe and secure grip when lifting large and heavy glass panels/units. Page 3 of 9
4 Sequence of 16. The door should then be tested to ensure that it opens and closes smoothly without rubbing or catching, if necessary the hinges and door should be adjusted to ensure a suitable fit. 17. Once the door has been suitably adjusted, the remaining door locks, handles and other ironmongery can be fitted into the pre-formed recesses and secured into place. 18. The door frame should then be trimmed and sealed both internally and externally and the area cleaned and made good. 19. Remove all rubbish, scrap and waste materials/packaging from the premises and dispose of appropriately. Thoroughly vacuum and clean through the area and all transit routes leaving the property in a clean and tidy state. Window Installation 20. This should be carried out in strict accordance with the manufacturers recommendations and in the sequence specified by the manufacturer. All work will also be carried out in strict accordance with FENSA requirements. 21. Before starting work ensure that the correct window sizes have been supplied, together with the necessary fixtures and fittings. 22. Where applicable the existing windows should first be removed by removing the hinges from the window frame. The existing widow frame can then be removed from the wall; this will be done by cutting through the frame and levering the frame work from the wall with a wrecking bar. 23. The old windows and frames will be removed from site and disposed of via a licensed waste carried for disposal at a licensed waste site. 24. All work will generally be carried out from the inside of the property, however, where work is being carried out on floors other than the ground floor, or where work is carried out on the ground floor and level of the ground outside of the window is more than 1.5m below the sill height AND where the internal sill height is less than 910mm (or 950mm on properties constructed after April 2005) above the internal floor level, then additional measures must be implemented to safeguard against falls through the open window aperture. This is to ensure compliance with the Work at Height Regulations In such instances where the sill height is below 910mm (or 950mm on new properties) either a temporary hand rail at 950mm must be erected; or those carrying out the works, must wear a full body harness with a lanyard attached to a suitable anchor point. Page 4 of 9
5 Sequence of 25. Prior to the fitting of the new window and window frame, the walls must be checked to ensure that they are sound and that any old fixings have been removed and disposed of. Where sections of the wall have been damaged or are not suitable, the area should be made good or alternative fixings used. 26. Clean the area and prepare the recess for the installation of the new windows. Fit the new window frame into position, ensuring a tight fit and ensuring that the frame is plumb and square. 27. Use packers where necessary to secure the frame in position and then drill through the frame into the masonry wall for the frame fixings. A minimum of 2 frame fixings should be used on each element of the window frame, though for long windows additional fixings will be required. 28. Once the frame fixings have been inserted and securely fixed /tightened, the back of the frame should be filled with expanding foam to provide added protection against the weather, water ingress and from unwanted noise. 29. Where applicable the individual windows openings can be inserted and fixed to the window frame with the hinges. Generally all windows and frames should be supplied pre-assembled prior to arriving on site. 30. Once the windows and frames have been installed, the glazing units can be inserted. Each unit should be installed and secured into position with the appropriate beading/seals. The glazed panels can then be carefully lifted into position, grip gloves should be worn at all times when lifting glazed units and for large panels a minimum of 2 persons should be used to lift and secure the panels in place. The use of suction lifters should also be used to provide a safe and secure grip when lifting large and heavy glass panels/units. 31. The windows should then be tested to ensure that they open and close smoothly without rubbing or catching, if necessary the hinges should be adjusted to ensure a suitable fit. 32. The window frame should then be trimmed and sealed both internally and externally and the area made good. 33. Upon completion of the works, Wembley Windows (SC) Ltd will remove all rubbish, scrap and waste materials/packaging from the premises and dispose of appropriately. Thoroughly vacuum and clean through the area and all transit routes leaving the property in a clean and tidy state. 34. Care must be taken to ensure that the glass is not broken and that when handling glass and windows, that appropriate gloves are worn. Page 5 of 9
6 Sequence of 35. Wembley Windows (SC) Ltd have a policy of a Tidy Site is a Safe Site and in this respect all employees are required to remove and dispose of waste as it is generated, leaving a clean and tidy site at all times. All waste is to be segregated where applicable and placed into the appropriate waste containers/skips. At the end of each working day, a check is to be made to ensure that all waste has been removed from the site and placed into the appropriate waste containers/skips and that the site is left in a clean and tidy state. Temporary Supports and Props needed to facilitate the works: At the end of each shift, ensure that all working areas are left tidy, safe and secure and remove or cover anything which may constitute a trip hazard, or result in a danger to other workers/persons. Method of Access and Egress to the work area: Access and egress to the working area will be via the front/rear doors of the premises, access to the first floor will be via the internal staircase. In areas where external access is needed all work will be carried out from full access scaffolds or tower scaffolds, the use of ladders will not be permitted for use as a working platform. Do not store tools or materials on top of working platforms or around holes in the floor when working above ground level. Fall Protection Measures: Exclusion zones shall also be established in the area beneath all such works, to protect others from the risk of falling tools, equipment and materials etc. Access scaffolds are to be used for all external work at height to provide a safe working platform and protection from falls, all scaffolds will be provided with close boarded platforms, toe boards and double handrails in full accordance with the Work at Height Regulations Hazardous Substances: Very Toxic Harmful/ Irritant Corrosive Dangerous for the environment Oxidising Highly flammable Explosive Applicable: No Yes No No No No No SWL's: Not applicable. Page 6 of 9
7 Required Personnel Protective Equip.: Safety Boots Hard Hats Safety Gloves Hearing Protection Respiratory Protection Eye Protection Yes Yes Yes Yes Yes Yes When When When When using using At all At all using using selected selected times times power power power power tools tools tools tools Call 999 and advise the appropriate emergency services Isolate any plant, machinery or other equipment. Other: 1. Hi-Viz 2. Coveralls 3. Emergency Procedures: Do NOT move the injured person unless it is absolutely necessary and they are in danger by remaining where they are. Keep the injured person warm and dry. Inform the site manager and head office. Name of On-Site First Aider: First Aid Facilities: First Aid Box Location: A first aid box is available within each of the company s vehicles. Location of Nearest Hospital: All plant, machinery, tools and equipment will be inspected on each occasion before it is used and in accordance with the manufacturers and statutory requirements. If any defects are identified, the equipment shall be taken out of use and replaced. Other Information & Comments: Wembley Windows (SC) Ltd are very aware of the potential health hazards presented by hand arm vibration (HAV) and whole body vibration (WBV), the use of tools such as angle grinders which can be responsible for HAV will therefore be limited to reduce the effects of HAV, a limit of 10 minutes (max.) will be placed on the usage of such tools for each individual. There must then be a break of at least 20 minutes before the tool, or another similar tool is used again. Page 7 of 9
8 The use of low vibration tools will be utilised where possible, only low vibration models will be purchased and when tools are being hired, consideration is to be given to lower vibration models. Other Information & Comments: As with vibration, low noise tools will be selected where appropriate, consideration has been given to the selection of appropriate tools in this method statement and quieter methods of working are selected where appropriate. All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with the company s Health and Safety Policy. Reviewed by: Position: Works Supervisor Date: Page 8 of 9
9 Method Statement Briefing Record Briefing delivered by: Position: Date: We (the undersigned) have read and understood the attached method statement and will comply with the specified requirements and control measures. If the work activity changes or deviates from that originally envisaged, we will seek further advice and request an amended method statement. Name (Print) Signature Date Page 9 of 9
A: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION
ELECTRICAL CONTRACTOR RISK ASSESSMENT AND KEY CONTROL MEASURES CONTRACTOR NAME: AEC Automation Ltd. NAME OF CONTRACT: A: SIGNIFICANT RISKS Initial Risk Rating H/M/L Slips, trips and falls. Manual handling.
OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London.
OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London. N5 1XB Document Control Revision No. Date Approved Signature
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY CONTENTS Page No 1 INTRODUCTION 2 2 LEGISLATION 2 3 HIERARCHY OF CONTROL 2 4 WORK AT HEIGHT POLICY 3 5 ROLES AND RESPONSIBILITIES 3 6 RISK ASSESSMENTS
Installation Instructions
Installation Instructions 1. Position the unit onto bridging packers. These keep the unit away from any water sitting inside the frame. 2. Centralise the unit within the frame and pack the edges with appropriate
Health & Safety Policy For Locations Hosting Film Production Companies
Health & Safety Policy For Locations Hosting Film Production Companies Throughout this document, the location will be referred to as The Venue and the film production company as The Contractor. The following
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin americancraftsmanwindows.com Project Requirements: Failure to follow these instructions may void product
BILL WHYTE FLOORCOVERINGS LTD UNIT 5 KINGS COURT KING ST LEYLAND LANCS PR269RL. Tel: 01772 432120 METHOD STATEMENT
BILL WHYTE FLOORCOVERINGS LTD UNIT 5 KINGS COURT KING ST LEYLAND LANCS PR269RL Tel: 01772 432120 METHOD STATEMENT Prepared For The Main Activities / Operations Performed By The Employees Of Bill Whyte
The Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting
The Tomato Plant Company Ltd Method Statement and Risk Assessment Loads requiring lifting Generic method statement & risk assessment for the removal of portable accommodation units and/or shipping containers
Installation Instructions
Installation Instructions READ BEFORE INSTALLING UNIT For Low Profile Window Air Conditioner INSTALLATION WARNINGS AND CAUTION Carefully read the installation manual before beginning. Follow each step
Unit FFL 1 Respond to requests for fire damage limitation work
Unit FFL 1 Respond to requests for fire damage limitation work FFL 1.1 FFL 1.2 FFL 1.3 FFL 1.4 Get and confirm details and specific information related to fire damage limitation jobs Agree initial plan
ASTFFL2 - SQA Unit Code H54D 04 Assess and estimate work required to limit damage to structures post fire
Assess and estimate work required to limit damage to structures post Overview 1 Confirm extent and nature of damage caused to structures by 2 Carry out risk assessments to confirm premises are safe to
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment
Method Statement. Risk Assessment
Method Statement Risk Assessment Client: Location: Page 1 of 6 Health and Safety Method Statement and Risk Assessment Customer & Address: Site Address: Description of Works: Method Statement: Risk Assessment:
Employee Health and Safety Induction Training Record
COMPANY NAME Employee Health and Safety Induction Training Record Employee name Job Title Department Start Date - PBS 2010/2 Employee Health & Safety Induction Training Record Page 1 of 6 INDUCTION TRAINING
FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING
JOB NO: PROJECT: DATE: SWMS NO: SWMS 001.1 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: December 2015 MINIMUM PERSONAL PROTECTIVE
IMPORTANT INSTALLATION GUIDE VALENCIA SQUARE CORNER SHOWER READ ALL INSTRUCTIONS CAREFULLY BEFORE STARTING THE INSTALLATION
INSTALLATION GUIDE VALENCIA SQUARE CORNER SHOWER SEALANT REQUIRED TO COMPLETE THIS INSTALLATION: (Not supplied) Sika Sikasil NG (Arctic White) To seal the WHITE shower door and returns to the shower tray.
Basement Window Installation Guide Hopper and Sliding
Basement Window Installation Guide Hopper and Sliding americancraftsmanwindows.com Project Requirements: Installation must comply with all applicable building codes. Existing window frame, wall and weatherresistant
CAER Construction and Environmental Resource
CAER Construction and Environmental Resource OLD COLONY HABITAT FOR HUMANITY WORK CREW SAFETY: Construction Safety Policy INTRODUCTION Safety is everybody's concern and is always an important consideration
Contractor s Safe Working Agreement
Contractor s Safe Working Agreement This statement provides details on how I/we, the Trade Contractor will manage the health and safety hazards associated with my/our work. ASSESSING WORKPLACE HEALTH AND
Safety Systems Review Facilities Management Guidance and specification Version 1 2014
Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page Safety Systems Review
Safety and Environmental Information for External Companies Koehler Oberkirch
and al and at Work 1. Delivery, Notice, Signature After receiving the following information sheets, the team leader from every external company is required to read through them, explain them to their employees,
Safety Training Needs Assessment
Safety Needs Assessment Form Instructions: Please review each question and either check YES or NO. If a question is checked YES you will be required to complete the training topic before initial assignment
CONTRACTOR INDUCTION HANDBOOK
CONTRACTOR INDUCTION HANDBOOK POLICY The health and safety of all school employees and contractor employees is a vital concern at the school. Contract personnel will be treated in a manner consistent with
Document ref: MG(M)201 Version no: 01 Page no: 1 / 12. Contractor rules
Page no: 1 / 12 Contractor rules Table of Contents Purpose... 2 Scope... 2 1. Responsibilities... 2 2. Planning Stage... 3 3. Site induction, emergency procedures and documentation... 3 4. Risk Assessment
Working at Height. Procedure
Procedure *All Forth Valley College Health, Safety and Welfare Procedures are covered under the overarching Health, Safety and Welfare Policy. Status: Date of version: Reviewed by: Author/Contact Person;
Level 1 Award in Health and Safety in a Construction Environment
Level 1 Award in Health and Safety in a Construction Environment Student notes (sample) www.britsafe.org Membership Training Qualifications Audit and Consultancy Audit and Policy Consultancy and Opinion
Window Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard
Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard UNIVERSITY COLLEGE LONDON Engineering, Maintenance & Infrastructure
1.1. EMERGENCY PROCEDURE On discovering a fire or being informed of an emergency;
Fire Action Plan FIRE ACTION PLAN SEStran aims to provide and maintain safe & healthy working conditions, equipment and systems of work for all our employees, and to provide such information, training
SITE CONTRACTOR PROCEDURES
SITE CONTRACTOR PROCEDURES Asset Collection Type B Assets are considered High risk ; the site activities must be in accordance with Graysonline contractor procedures and are to be collected by appointment
Awning Instructions. Standard Manual 1.5m to 4.5m
Awning Instructions Standard Manual 1.5m to 4.5m English Standard Manual Instructions Contents Warning 1.5m 3.0m Awnings 4 x Expansion bolts (2 per bracket)** 2 x brackets 1 x Awning 1 x Winder handle
School of Engineering University of Glasgow
School of Engineering University of Glasgow Electronics Workshops Rankine Building 319A (2 Technicians) 510 (1 Technician) 712A (4 Technicians, 1 Modern Apprentice) James Watt South 619 (2 Technicians)
7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS
ACTIVITY HAZARD ANALYSIS (AHA) 1. Contract Number: 2. Contractor Name: 3. Date prepared: 4. Title/Activity Performed: FIXED SCAFFOLDING 5. Location: 6. Estimated Date of Completion: 7. PRINCIPAL STEPS
Safety and Environmental Information for External Companies
Health and and al Health and at 1. Delivery, Notice, Signature After receiving the following information sheets, the assembly leader from every external company is required to read through them, explain
REDI-EXIT COMMERCIAL FIRE DOOR AND EXTERIOR DOOR KITS INSTALLATION GUIDELINES
REDI-EXIT COMMERCIAL FIRE DOOR AND EXTERIOR DOOR KITS INSTALLATION GUIDELINES Tools Required Tape Measure Hammer Slotted Screw Driver #2 & #3 Philips Screw Driver 3-4 Foot Level 12 Pry Bar Cold Chisel
CONSTRUCTION SITE HEALTH AND SAFETY SELF AUDIT
www.veritas-consulting.co.uk CONSTRUCTION SITE HEALTH AND SAFETY SELF AUDIT This checklist identifies some of the hazards most commonly found on construction sites. The questions it asks are intended to
Safety and Environmental Information for External Companies
1. Delivery, Notice, Signature After receiving the following information sheets, the team leader from every external company is required to read through them, explain them to their employees, and after
Greenhouse Assembly Instructions
Greenhouse Assembly Instructions 6 x 1.93m) 6 x 8 GREENHOUSE 01 ASSEMBLY INSTRUCTIONS 6 x 6 GREENHOUSE 02 ASSEMBLY INSTRUCTIONS 6 x 4 GREENHOUSE 03 ASSEMBLY INSTRUCTIONS 6ft (1.93m x 1.9 Introduction Safety
Notes. Material 1. Tools the employee is expected to operate
OSHA Standard29 CFR 1910.211-.247, Subpart O, Machinery and Machine Guarding, and Subpart P, Hand and Portable-Powered Tools and other Hand- Held Equipment. Hand Tool Safety Preparation 1. Read Applicable
This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site.
Introduction This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site. It was put together by members of the Food & Drink
68 Metal Industry Guidelines for Safe Work
3 68 Metal Industry Guidelines for Safe Work section 3 high-risk 3 activities Metal Industry Guidelines for Safe Work 69 section 3 high risk activities 3.1 working at heights Falls from heights have been
SKAC222 (SQA Unit Code - DD38 04) Carry out basic glazing and carpentry repairs
Overview This unit is about carrying out basic repairs to windows, doors and carrying out other carpentry repairs. Manual and power operated tools are used. The purpose of the repair could be to: 1. repair
DIY CABINET REFACING INSTALLATION GUIDE
DIY CABINET REFACING INSTALLATION GUIDE CABINET REFACING INSTALLATION Are you ready to reface your outdated cabinets? This guide will show you how to install your new Facelifters Cabinet Refacing Products
Tremline Pty Ltd trading as The Hills Bark Blower
JSA No: Rev: 10011 Date: 10010 ABN 1 07 880 6 Website: wwwbarkblowercomau Job Number Start Time: Vehicle : Max Length Hose Date: Company Name: Product: Quantities Depth Job site address: Description of
Job safety analysis Installing wall frames and roof trusses on-site
Job safety analysis Installing wall frames and roof trusses on-site 1. Taking delivery: - unloading the truck - moving materials manually to the work area Body sprains and strains from lifting materials
RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager
RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Working at Height above 2trs Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE:
GHD EPCM Standard operating procedure Working at height May 2013 v1
GHD EPCM Standard operating procedure Working at height May 2013 v1 Table of contents 1. Purpose 2. Scope 3. Duty of care 4. Lifesaving rules; An overview 5. Roles and responsibilities 4.1 Operating centre
SLIPS, TRIPS AND FALLS POLICY
SLIPS, TRIPS AND FALLS POLICY First Issued Issue Version Purpose of issue/description of change Planned Review Date 2 Root cause analysis (RCA), RIDDOR August 2012 and inspection of communal areas referenced
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
Method Statements. Debenham House, 8 Addison Road, London, W1J 8DJ Debenham House 8 Addison Road Holland Park W14 8DJ.
Method Statements Debenham House, 8 Addison Road, London, W1J 8DJ Debenham House 8 Addison Road Holland Park W14 8DJ Method Statements Method Statement - Plumbing Central Heating - Gas & domestic Pipework
Wren Kitchens Installation Tips... 3. Carefully check your kitchen delivery... 4. Measuring out and marking up... 5. Fitting the base cabinets...
tra 1 Index Wren Kitchens Installation Tips... 3 Carefully check your kitchen delivery... 4 Measuring out and marking up... 5 Fitting the base cabinets... 6 Fitting the corner cabinets... 7 The 972mm or
00MK-MA0190-EN00. Mounting System ASSEMBLY INSTRUCTIONS. Universal Light system with locking brackets, for sloped roof
00MK-MA0190-EN00 Mounting System ASSEMBLY INSTRUCTIONS Universal Light system with locking brackets, for sloped roof Rev.02 November 2014 Table of contents General instructions 2 General safety instructions
CHARISMA SHOWER/TUB DOOR INSTALLATION INSTRUCTIONS
CHARISMA SHOWER/TUB DOOR INSTALLATION INSTRUCTIONS IMPORTANT DreamLine reserves the right to alter, modify or redesign products at any time without prior notice. For the latest up-to-date technical drawings,
WHS Contractor Management Procedure
Procedure Approved: 09/07/2013 Next Review: 09/07/2015 1. Overview The District council of Mount Remarkable Council is committed to engaging quality Contractors who have a sound understanding and commitment
Machine/Woodworking Shop The Basic Rules
Machine/Woodworking Shop The Basic Rules 1. Eye protection or face shields are required when working in the shop. A selection of protective goggles and safety glasses are available in the shop. The eyeglasses
New Employee / Applicant - Information Pack (Includes: Driver Back round Release Form, Skills & Tools Assessment
New Employee / Applicant - Information Pack (Includes: Driver Back round Release Form, Skills & Tools Assessment Included are the following: Personal information form Driver Back round Check Authorization
Procedural Guidance for Roof Access/Roof Work
University of Central Lancashire Safety, Health & Environment Section Procedural Guidance for Roof Access/Roof Work Document Number: FM/HSE 001 Revision Number: 2 Review Date: August 2005 Reviewed by:
FRAME DOOR OPENING, DOOR AND SIDE PANEL OUTER
NUBIRA/LACETTI FRAME DOOR OPENING, DOOR AND SIDE PANEL OUTER 6 1 SECTION 6 FRAME DOOR OPENING, DOOR AND SIDE PANEL OUTER CONTENTS 1. FRAME DOOR OPENING........................................... 6 2 1.1.GENERAL
METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS
METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS Revision Date Prepared By Approved By Method Statement IF Kits BAC Corrosion Control Limited Stafford Park 11 Telford TF3 3AY Tel: 01952 290321 Fax:
INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION FOR DOUBLE-HUNG VENT REPLACEMENT WINDOW
Vinyl Windows and Doors Manufactured by Pella Corporation INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION FOR DOUBLE-HUNG VENT REPLACEMENT WINDOW Lea las instrucciones en español en el reverso.
WINDOW REPAIR MANUAL & REFERENCE GUIDE
WINDOW REPAIR MANUAL & REFERENCE GUIDE TABLE OF CONTENTS DOUBLE HUNG & SINGLE HUNG PARTS 4-5 CASEMENT PARTS 6 SCREEN PARTS 7-8 HOW TO REMOVE TILT-IN SASH 9 HOW TO REMOVE A BALANCE 10 HOW TO INSTALL BALANCE
CPPSEC2021A Install security equipment and systems
CPPSEC2021A Install security equipment and systems Release: 1 CPPSEC2021A Install security equipment and systems Modification History Not Applicable Unit Descriptor Unit descriptor This unit of competency
No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974
The Police Treatment Centres Health and Safety Legal Compliance Register No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974 2.
Working at height - Practical Guidance for Schools
Working at height - Practical Guidance for Schools N.B. The following guidance is provided as an example of best practice, and should be adapted to suit the specific work being undertaken following a suitable
SAFETY AND ENVIRONMENTAL INFORMATION FOR EXTERNAL COMPANIES. Koehler Kehl
1. Delivery, Notice, Signature After receiving the following information sheets, the team leader from every external company is required to read through them, explain them to their employees, and after
Site Induction Presentation
ABC Contracting Site Induction Presentation This presentation provides a mock site induction and serves to help those people in the process of preparing and delivering site inductions It is essential that
TEMPORARY EMPLOYEES SAFETY PROCEDURES
TEMPORARY EMPLOYEES SAFETY PROCEDURES Temporary Agencies will ensure that any temporary employee sent to work at Modern will have received and understand the General Safety Rules. GENERAL SAFETY RULES
Packaged Terminal Air Conditioner Wall Sleeve Installation
Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation
BSH Exhibition Sample Risk Assessment for exhibitors / contractors
BSH Exhibition Sample Risk Assessment for exhibitors / BSH Conferences Ltd have produced this risk assessment for its exhibitors to use as a template if they have not undertaken risk assessment before.
Active and Passive Sash Replacement
for Andersen Gliding Windows Read all instructions carefully before attempting this procedure. If you have any questions about your ability to complete the procedure, call Andersen at 1-888-888-7020 for
ISSUE 2. Installation Guide
ISSUE 2 Installation Guide Here at Slide and Fold, we LOVE our Bi-Fold Plus range of folding-sliding doors. We want to ensure that your customers love them too. So we have created a new, detailed installation
INSTALLATION INSTRUCTIONS for Bifold Doors (JII103)
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for premium composite, hollow and solid core molded Bifold Doors. Bifolds are designed for fast
RESIDENTIAL ROOF TRUSS INSTALLATION PROCEDURES
RESIDENTIAL ROOF TRUSS INSTALLATION PROCEDURES Construction Safety Association of Ontario, October 2008 Prepared for the Low-Rise Residential Trade Labour-Management Health and Safety Committee CONTENTS
S4 - Top Hung Window. Outside view. Inside view. Interior frame. Exterior frame. Glazing Panel
S4 - Top Hung Window Outside view Inside view Interior frame Exterior frame Glazing Panel Dometic Seitz GmbH 1 S4-Top Hung Window.doc Exterior frame End cap Sealing rubber between exterior frame and wall
Fire Safety Log Book
Fire Safety Log Book Company... Address........ Responsible Person. Competent Person. Date Started For Additional Information: Safety Management (UK) Ltd Holme Suite, Clawthorpe Hall Business Centre, Burton
ISLE OF MAN FIRE & RESCUE SERVICE FIRE PRECAUTIONS LOGBOOK. Website www.iomfire.com
ISLE OF MAN FIRE & RESCUE SERVICE FIRE PRECAUTIONS LOGBOOK Website www.iomfire.com ADDRESS OF PREMISES FIRE CERTIFICATE No. (where applicable).. LOCATION OF LOG BOOK. CONTENTS OF LOG BOOK Useful telephone
Premier & Deluxe 3-Season Room Sliding Glass Door
DTSSGD-11 Premier & Deluxe 3-Season Room Sliding Glass Door Installation Instructions Screen Door Seal Left Side Track Top Track Assembly Right Side Track Right Side Trim Sliding Glass Door Sliding Screen
WORKSAFE VICTORIA A HEALTH AND SAFETY SELF-ASSESSMENT CHECKLIST FOR SMALL BUSINESS
Aug 2013 WORKSAFE VICTORIA A HEALTH AND SAFETY SELF-ASSESSMENT CHECKLIST FOR SMALL BUSINESS As a small business operator, you need to be aware of your health and safety responsibilities, and identify risks
WORKING AT HEIGHT GUIDELINES. Version II
WORKING AT HEIGHT GUIDELINES Version II 21 st September 2011 WORKING AT HEIGHT GUIDELINES EXECUTIVE SUMMARY Working at height is where an individual is carrying out work in any place in the course of obtaining
Lifting Equipment - Work equipment for lifting or lowering loads and includes its attachments used for anchoring, fixing or supporting it.
LIFTING EQUIPMENT POLICY Background and Legislation The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) apply in all premises and work situations subject to the Health and Safety at Work,
WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING
WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING IMPORTANT NOTICES AND INFORMATION Read these instructions in their entirety prior to installing windows. Any local building code requirements
Guide for Contractors and Project Supervisors
Guide for Contractors and Project Supervisors Safety, Health and Welfare at Work (Construction) Regulations 2013 Our vision: A country where worker safety, health and welfare and the safe management of
All-Season Sunroom Sliding Glass Door Installation Instructions
ASRESGD-08 All-Season Sunroom Sliding Glass Door Installation Instructions Panel Frame Door Frame Left Side Foam Insulator IE241 H Bar Assembly Door Frame Top Track Panel Frame Door Frame Right Side Stationary
Event Planning Guidance Notes EVENT PLANNING GUIDANCE NOTES
EVENT PLANNING GUIDANCE NOTES 1 Event Planning Guidance Notes Important issues This documentation is not a full and authoritative statement of the law, statutory guidance or best practice in planning,
SITE SPECIFIC FALL PROTECTION PLAN
1 THIS PLAN IS SPECIFIC TO: PROJECT & ADDRESS 1.1 THIS PLAN IS SPECIFIC TO THE FOLLOWING AREA(S) ON SITE: Parkade level: Typical level: Other: Between G/L: 1.2 THIS PLAN IS APPLICABLE TO THE FOLLOWING
APPENDIX A BUILDING MAINTENANCE MECHANIC D.O.T. CODE 899.381-010 O*NET CODE 49-9042.00
APPENDIX A BUILDING MAINTENANCE MECHANIC D.O.T. CODE 899.381-010 O*NET CODE 49-9042.00 This training outline is the current standard for Work Processes and Related Instruction. Changes in technology, regulations,
Example risk assessment for a motor vehicle mechanical repair workshop
Example risk assessment for a motor vehicle mechanical repair workshop Setting the scene The garage manager did the risk assessment. The business employed 12 mechanics, including two apprentices who carried
Independent Contractor Policy
Independent Contractor Policy This Policy has been implemented to prevent accidents and personal injuries. It is not intended to be entirely inclusive. It is the responsibility of the Independent Contractor
Chelsea Loft Bed WARNING:
Chelsea Loft Bed WARNING: Failure to follow these warnings and assembly instructions could result in serious injury or death. Read all instructions before assembling bunk bed. KEEP INSTRUCTIONS FOR FUTURE
Greater Manchester Fire and Rescue Service
Greater Manchester Fire and Rescue Service Record of Fire Safety Equipment Testing CONTENTS 1. MEANS OF ESCAPE 2. FIRE WARNING AND AUTOMATIC FIRE DETECTION 3. FIRE EXTINGUISHERS AND HOSEREELS 4. EMERGENCY
Workshop Self Inspection Checklist WORK01
Workshop Self Inspection Checklist WORK01 General Mechanical Workshops Location Assessor Date This core checklist is provided by the Health and Safety Department as a template, which provides a basic framework
K. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11
K. D. FRAME ASSEMBLY FOR MASONRY WALLS...........................Ins 2 FRAME INSTALLATION DETAILS FOR MASONRY WALLS......................Ins 3 INSTALLING EXISTING MASONRY WALL ANCHORS IN FRAME..................Ins
This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor.
Big Four Construction Hazards: Fall Hazards This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor. It does not necessarily
UBC Plant Operations Asbestos Work Procedures April 2004
UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other
IF YOU NEED A POLE BARN OR DIY KIT CALL NOW AND LETS MAKE A DEAL
IF YOU NEED A POLE BARN OR DIY KIT CALL NOW AND LETS MAKE A DEAL Check out our Affordable Selection of DIY Pole Barn kit sizes and prices below. We offer a complete DIY pole barn kit plus independent experienced
Temporary Worker Safety Checklist
Temporary Worker Safety Checklist The following checklists provide guidance for staffing agencies and employers that hire temporary workers regarding the steps each party should take to ensure it is meeting
Safety Inspection Checklist
Inspector(s): Building: Room Number (s): Department/Unit: Date Inspected: Supervisor: To customize your local inspection checklist, delete or add as required. Inspection Headings: 1. Administrative 8.