TenneT. Stakeholder engagement and Consultation Process OWFs. Day 1 ONL 15-162. Michiel Müller / Rob van der Hage



Similar documents
QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

Annexes to Realisation Agreement

Offshore Wind in Germany

SDE+ tender Borssele december 2015

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Wind Farm Zone. Offshore wind energy. in the Netherlands. Project & Site Description. # Borssele

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)

Grid connection of near shore wind farms

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Profile. Offshore Wind Projects. Sustainable EPC and Marine Contractors

Offshore Wind: some of the Engineering Challenges Ahead

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Offshore Windfarm Egmond aan Zee 4 years of Operation

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

Optimization of the coupled grid connection of offshore wind farms

Cost Reduction Potential in the Offshore Grid

COWI offshore wind marine engineering services

G8 - Contracts for Difference Metering

OFFSHORE WIND PROCUREMENT

Electrical Shore Connections / Cold Ironing

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

HVDC Technology for Large Scale Offshore Wind Connections

OFFSHORE WIND FARM ELECTRICAL CONNECTION OPTIONS. W.Grainger 1 and N.Jenkins 2 SYNOPSIS

Generation and Transmission Interconnection Process

MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION

Passion for Offshore. Wind Power & Renewables Division Market Unit Offshore

Introduction to Ontario's Physical Markets

TENNET, NL OFFSHORE WIND FARM TRANSMISSION SYSTEMS

Council of the European Union Brussels, 20 May 2016 (OR. en)

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

Renewable Energies WIND

Design and Operation of Power Systems with Large Amounts of Wind Power, first results of IEA collaboration

HVDC Light Cables. Submarine and land power cables

Magnus Callavik, ABB Power Systems, HVDC, Västerås, Sweden Phone: +46(0)

Achieving Operational Efficiencies through On-Line Substation Monitoring. Vince Polsoni Powerstream Inc. Manager Station Sustainment EDIST 2016

egrid Calculation of electrical grid connections for WTGs

Grid requirements with scattered load balancing and an open electricity market Poul Alberg Østergaard * Aalborg University

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy

Geotechnical Engineering in Offshore Wind - how can we contribute to lowering the cost of electricity? DGF Seminar, Gentofte, 1 st April 2014

Danish Energy Model RE Policy Tools MAIN Asian Dialog, Bali January Mr. Henrik Breum Special Advisor

Offshore Legal Framework

Advantages of Fixed Circuit Breaker Switchgear

Offshore Work Packages

De Industrie. KIvI Niria Jaarcongres De uitdagingen voor windenergie op zee. Ballast Nedam Offshore. Dolf Elsevier van Griethuysen

Infield Cable Topology Optimization of Offshore Wind Farms

Basics in Energy Information (& Communication) Systems Substation Automation

the Future of engineering

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

Kent Active System Management (KASM) Oct 2015 / Matthieu Michel

CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE

Viking Link Interconnector

Variable Frequency Drives - a Comparison of VSI versus LCI Systems

Renewable Energy Interconnection Requirements for the US. IEEE PES Meeting Denver, CO July 26-30, 2015 J. Charles Smith, Executive Director, UVIG

Lifecycle Strategy DISPOSAL AND DIVESTMENT

Christopher Monk Engineering Manager STRUCTeam Ltd

Substation Automation based on IEC 61850

Data Analytics for Future Energy Systems

ABB PSPS Erich Steinmann; Generator control-2013

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

London Array Off-Shore Wind Farm

V MW. Your best option for low cost energy production at low and medium wind sites. Federico Gonzalez Vives. Director Technology.

HV Submarine Cable Systems Design, Testing and Installation

Service Power Technologies. Retrofitting A future-oriented concept in lifecycle management

Modular Systems wind portfolio overview Power Collection and Grid Connection products

Kostenreductie update, actieplan en governance. Ernst van Zuijlen 17 februari 2016

Offshore Transmission: Guidance for Cost Assessment Guidance Document

EXPRESSION OF INTEREST

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Asset Management Plans

Curriculum Vitae Fredrik Rüter 1 December 2014

Sharing Lessons Learned and Good Practice in Offshore Transmission

High-Voltage GIS yesterday - today - tomorrow

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

Gas turbine power plants

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE

Cable Care. ABB Power Cables Service Products

Overhead lines in Ireland

Future Offshore Wind Power Sites -2025

ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update

Designing A Tidal Energy Ar arrays

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

2012 San Francisco Colloquium

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

2012 San Francisco Colloquium

Comparing IR camera resolutions what high resolution buys you. By Robert P. Madding Infrared Training Center July, 2006

Offshore Platform Powered With New Electrical Motor Drive System

Norwegian offshore wind clusters

Offshore Electricity Transmission: Consultation on tender exercises under the enduring regime (178/11)

RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER. tgood.com. Energy. Fast.

Winddag 2015: Innovation need and necessity. Bob Meijer 20 juni 2015

POWER TRANSMISSION FROM OFFSHORE WIND FARMS

Opening the CfD support scheme to non-uk renewables projects

Protection and Substation Automation. Training Programmes

Power products and systems. Intelligent solutions for power distribution Zone concept

Siemens Integrated Substation Condition Monitoring System. Circuit Breaker Monitoring

Transcription:

TenneT ONL 15-162 Stakeholder engagement and Consultation Process OWFs Day 1 Expert Meeting, 15-16.04.2015, Arnhem Michiel Müller / Rob van der Hage

Stay tuned. Safety first! Voor uw en onze veiligheid vragen we uw aandacht voor de volgende veiligheidsmaatregelen. In geval van een ontruiming van het pand: Volg de vluchtroute zoals aangegeven. Gebruik de trap in plaats van de lift. Ga naar het verzamelpunt. Volg de aanwijzingen van de bedrijfshulpverlener. Deze is geval van een ontruiming aanwezig.

Welcome 3

Agenda (15.04.2016) WHEN WHAT TYPE OF SESSION 10.00-10.15 Welcome Looking back at meeting of March Agenda for today Introduction 10.15-10.30 General update on process Presentation 10.30-11.30 T.1 Voltage level [D] Discussion 11.30-12.15 T.3 Point of Common Coupling [N] T.4 Access to platform [I] T.9 Metering [I] 12.15-12.45 Break & collect lunch Presentation 12.45-13.45 T.2 # of J tubes / bays [D] Discussion 13.45-14.45 T.5 Operation of bays [D] Discussion 14.45-15.30 15.30-15.45 Closure O.1 Innovation [N] O.2 Stranded asset mitigation [I] T.12 Redundancy / availability [I] Presentation [N] [D] [I] Notification session Discussion session Information session 4

Agenda (16.04.2016) WHEN WHAT TYPE OF SESSION 09.30-09.40 Welcome Introduction Agenda for today 09.40-10.30 T.6 Protection [D] Discussion 10.30-11.20 T.11 Overplanting [D] Discussion 11.20-12.10 P.1 Planning [D] Discussion 12.10-12.30 Break & collect lunch 12.30-14.30 14.30-14.45 Closure L.1 Connection Agreement, Realisation Agreement and implementation of net code [D] Discussion - Dedicated Legal Session [N] [D] [I] Notification session Discussion session Information session 5

General update on process 6

T1_Voltage level Discussion 7

T1_Voltage level Input Previous Expert Meetings and Bi-lateral meetings External report DNV-GL & Memo with answers to additional questions Position paper TenneT (ONL15-058-T1_Voltage level_pp_v2) 8

T1_Voltage level Main considerations TenneT contributes to the overall cost reduction target, through standardisation of all 5 offshore platforms to be realised for the development of 3450 MW offshore wind, with a single platform serving concentrated large (700 MW) wind areas and use of technology that is ready for future large capacity wind turbines. Implementation of 66 kv infield cable voltage is considered technically feasible, with respect to both the cables, turbines and all connecting electrical equipment. Cable length difference 33/66 kv: As a general estimate, based on the draft layouts with 7 MW wind turbines, using 66 kv infield cables, reduces the total length of inter-array cable on average by 24% (21-28%), relative to the use of 33 kv infield cables for all five wind areas. Based on draft layouts it can be concluded that the site specific constraints for the different wind areas do not lead to an increase of the minimum number of strings required to connect the wind farm to the offshore platform (21 for 33 kv / 12 for 66 kv). 9

T1_Voltage level Main considerations Cable supply @ 66 kv: DNV-GL concludes that the six well-known cable manufacturers contacted and having EPR and/or XLPE cables for 66 kv inter array cabling available should lead to necessary competition and therefore to reasonable market prices for such cables". Turbine supply @ 66 kv: TenneT concludes from the survey of DNV-GL that with respect to turbine supply there is likely to be sufficient competition for the first Borssele tender when standardising at 66 kv to realise competitive pricing. Standardisation at 66 kv is expected to be the cheapest option available, reducing cable length, number of J-tubes, installation work and losses, already for the first Borssele tender and even more so for the future tenders. Position: TenneT intends to standardise the connection voltage level of the inter-array systems to the TenneT offshore transformer platform at 66 kv for all five platforms to be realised by TenneT up to 2023. 10

T1_Voltage level 11

T1_Voltage level Questions & concerns 12

T.3 Point of Common Coupling Notification: The connection point (CP) between the offshore power park module (PPM) and TenneT is specified at the cable termination of the inter-array cables and the switchgear installation on the platform. 13

T.4 Access to platform Access requirements of WPO s can be split into: Access for maintenance (planned / unplanned) of WPO equipment on offshore platform; Access after cable fault (for fault location measurements) and testing; Access for commisioning Safe haven 14

T.4 Access to platform TenneT s design considerations (at this moment): Unmanned platform; No helideck WPO access to platform only when accompanied by TenneT representative; Access to platform for fault location measurements will always be possible (max. response time to be defined) Transportation of personnel by TenneT or WPO vessel Minimize need for WPO access by limiting WPO equipment on offshore platform. This will be covered in: T.6 Protection T.8 / T.10 SCADA / Data links / communication T.9 Metering 15

T.9 Metering Starting points: Network code: metering by certified body to be assigned by customer. CP is offshore: defined on cable termination of the inter array cables Options: Metering organised by WPO s. For 10 wind farms max. 10 certified bodies requiring access to platform. Metering organised by TenneT Assignment of 1 certified body responsible for metering of all (10) wind farms; 16

Break & lunch 17

T2_ # of J tubes / bays Discussion 18

T2_ # of J tubes / bays Input Position paper TenneT (ONL15-060-T2_ J tubes_ bays_pp_v2) Main considerations Taking into account the general available cable types and a power factor of 0.9, the maximum transmission capacities are set to 35 MW for a 33 kv infield cable and 70 MW for a 66 kv infield cable. For the 66kV cables, the calculations for the amount of J-tubes are performed with 64 MW per infield cable, to provide an extra margin. To provide flexibility in wind tuirbine distribution TenneT uses as starting point that the number of strings should be such that on average there is 20% spare capacity, on top of the 380 MW (maximum overplanting) installed. 19

T2_ # of J tubes / bays Position: TenneT states that in case of 66 kv inter-array cables (based on conservative 64 MW per cable) a standard platform shall be equipped with 18 J-tubes for the inter array system: o 2x 8 J-tubes for offshore PPM o 1 J-tube installed for possible test purposes o 1 J-tube installed for the connection to the neighbouring platform TenneT states that in case of 33 kv inter-array cables (based on 35 MW per cable) a standard platform shall be equipped with 34 J-tubes for the inter array system: o 2x 16 J-tubes for offshore PPM o 1 J-tube installed for possible test purposes o 1 J-tube installed for the connection to the neighbouring platform 20

T2_ # of J tubes / bays Questions & concerns 21

T5_Operation of Bays Discussion 22

T5_Operation of Bays Input Position paper TenneT (ONL 15-079-T5_Operation of Bays_PP_v1) Main considerations Two options for the operation of bays considered: 1. The whole switchgear installation (disconnector, earthing switches and circuit breakers) is operated by the owner of the switchgear, TenneT. TenneT has a 24/7 manned dispatch centre which can operate the switchgear on request of the PPM at any time of day. 2. The disconnectors and the earthing switches are operated by TenneT and the circuit breaker by the PPM, which gives freedom to the PPM for switching of their strings. Position: TenneT is inclined to standardise the operation of bay s for the offshore platform, similar to the current practice for the operation of switchgear onshore for the connected parties, where the switchgear installation with connections to the offshore PPM is fully operated by TenneT, as the owner of the switchgear.. 23

T5_Operation of Bays Questions & concerns 24

O.1 Innovation [N] 25

O.2 Stranded asset mitigation [I] When: 1. Export cable(s) / offshore platform installation delay 2. Export cable(s) / offshore platform (transformer) failure Mitigation measures installation delay: Alignment of TenneT and wind farm installation schedules Mitigation measures cable/transformer failure: 2 (50%+) export cables and transformers per platform Additional redundancy cable between 2 platforms (foreseen for: 4 out of 5 platforms) No provisions on platform for emergency generator capacity to power windturbine generators. 5-7% weight increase to take into account increase in cost 26

T.12 Redundancy / availability [I] To determine level of redundancy, different scenario s were assessed. Scenario s based on variation of: Coupling (at 33kV/66kV, offshore 220kV, onshore 220kV) Transformer capacity (50% versus 70% offshore and 100% onshore) # of offshore transformers (2 x 50% or 3 x 33%) Assumptions for determining risk of loss of income: 20% increase of typical offshore wind farm performance Availability and MTTR based on internal figures and literature (Cigré) Price per MWh in a range of 20-120 27

T.12 Redundancy / availability [I] Main 5 scenario s: 50% 50% 50% 50% LAND SEA LAND SEA OPTION 1: base case 2x 350MW (no coupling at all) OPTION 2: basic coupling (coupling offshore at 66kV/33kV side) 100% 70% 100% 70% LAND SEA LAND SEA OPTION 3: additional coupling (full offshore coupling) OPTION 4: full coupling (on+offshore coupling) 35% 100% LAND SEA 35% OPTION 5: additional coupling with 3 offshore transformers

T.12 Redundancy / availability [I] Preliminary results: Basic coupling (on 33kV / 66kV side): increase overall availability of 0,4% with minimal additional costs Any other increase of redundancy does not weigh up to the additional costs (CAPEX / OPEX) 50% 50% LAND SEA OPTION 2: basic coupling (coupling offshore at 66kV/33kV side) 29

Concept single line diagram / Reactive power compensation 30

Closure 31

Thank you