Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary School 22 Hazel Wolf K-8 at Pinehurst 33 Olympic Hills Elementary School 44 Seattle New World School at TT Minor 53 New Thornton Creek Building 64 October 30, 2015
Arbor Heights Elementary School Elementary School Site: SW 104 th Street is being prepped for concrete curbs, gutters and sidewalk; installation of temporary gravel access around South Building in progress. South Building: Exterior sheathing on-going floor 1. Light-gauge metal framing continues at the exterior and interior walls at floor 2. Hollow metal door frame installation ongoing on floor 2. Mechanical, electrical, and plumbing (MEP) rough-in ongoing at floors 1 and 2. Metal roof decking is being placed and welded. North Building: Installation of capillary break ongoing, concrete slab-ondeck poured at 3rd floor, structural steel erection ongoing, roof joists up to cafeteria have been welded.
Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015
Arbor Heights Elementary School Aerial View from the South September 30, 2015
Arbor Heights Elementary School South Building First Floor Exterior Sheathing Commenced October 26, 2015
Arbor Heights Elementary School South Building - Second Floor Interior Wall Installation October 26, 2015
Arbor Heights Elementary School South Building Second Floor Window Opening Blocking October 26, 2015
Arbor Heights Elementary School South Building - Metal Roof Deck Welding Ongoing October 26, 2015
Arbor Heights Elementary School South Building - Roof Welding October 26, 2015
Arbor Heights Elementary School North Building Capillary Break Ongoing October 26, 2015
Arbor Heights Elementary School North Building - Looking West towards Multi-Purpose and Gymnasium October 26, 2015
Arbor Heights Elementary School North Building - Third Floor Slab-on-Deck October 26, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan
Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Footings, Looking North West October 21, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Parking Lot Preparation, Looking South East October 21, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Forming Concrete Curbs at Elementary School Parking Lot October 21, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School Concrete Retaining Wall, Looking South October 21, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Concrete Block Retaining Wall, East of Pilling s Pond October 21, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Middle School Concrete Footings, Looking North October 21, 2015
Cascadia Elementary School & Robert Eagle Staff Middle School Woodlawn Avenue North Street Restoration Work for SPU October 21, 2015
Genesee Hill Elementary School Site: Excavation and installation of the sanitary sewer conveyance system ongoing; importing crushed rock to winterize site around the building. Area 1: Installation of windows ongoing; CMU veneer installation is complete; installation of spray foam insulation is complete; installation of GWB at level 1 is complete; installation of GWB at level 2 ongoing. Miscellaneous electrical rough-in ongoing. Area 2: Exterior and interior framing ongoing at floors 1 and 2; exterior sheathing installation ongoing; HVAC ductwork installation at mechanical mezzanine ongoing; MEP is ongoing. Area 3: Foam insulation installation at exterior walls ongoing; interior wall framing ongoing; MEP ongoing. Area 4: Exterior framing and sheathing complete; MEP is ongoing.
Genesee Hill Elementary School Site Plan 4
Genesee Hill Elementary School Aerial View October 15, 2015
Genesee Hill Elementary School Installation of Deepest Manhole for Sanitary Sewer Conveyance System
Genesee Hill Elementary School Area 1 - North Elevation Envelop System Installation
Genesee Hill Elementary School Area 1 - Floor 3 Gypsum Wallboard Installation Ongoing
Genesee Hill Elementary School Area 2 - Level 1 Main Entry Stairs
Genesee Hill Elementary School Area 2 - Interior Wall Framing at Library
Genesee Hill Elementary School Area 2 - Mechanical Mezzanine Installation of HVAC Ductwork
Genesee Hill Elementary School Area 2 - Installation of Metal Panels at Roof Fascia
Genesee Hill Elementary School Area 4 - Gym and Commons
Hazel Wolf K-8 at Pinehurst Site: Side sewer installation ongoing, backfilling around concrete foundations, general site clean up. Building A: A1 concrete slab completed. Area A2 metal stud framing ongoing on first and second floors and penthouse, MEP installation ongoing. A3 final concrete footings formed and poured, concrete stem wall pours ongoing, waterproofing started and installation of utilities under slab ongoing. Building B: Structural steel for the outside play area completed. Roof decking started. Building C: Metal roof decking installation completed. Skylight frames installed welded and completed. Slab on deck for 2 nd floor (child care) area concrete pour completed.
Hazel Wolf K-8 at Pinehurst Site Plan
Hazel Wolf K-8 at Pinehurst Aerial View looking North West
Hazel Wolf K-8 at Pinehurst Area A2 Looking North West October 20, 2015
Hazel Wolf K-8 at Pinehurst Area A2 First Floor Interior Framing October 21, 2015
Hazel Wolf K-8 at Pinehurst Area A2 First Floor Floor Grinding October 21, 2015
Hazel Wolf K-8 at Pinehurst Area A2 Penthouse October 22, 2015
Hazel Wolf K-8 at Pinehurst Area A2 Penthouse Roofing October 21, 2015
Hazel Wolf K-8 at Pinehurst Area A3 Admin Concrete Stem Wall October 20, 2015
Hazel Wolf K-8 at Pinehurst Area B Structural Steel October 21, 2015
Hazel Wolf K-8 at Pinehurst Area C Gym Metal Deck and Skylights October 20, 2015
Olympic Hills Elementary School Site Plan
Olympic Hills Elementary School Aerial Photo October 15, 2015
Olympic Hills Elementary School Removing Soil Stockpile, Looking South October 21, 2015
Olympic Hills Elementary School Underground Detention Vault Backfilled and Covered, Looking North October 21, 2015
Olympic Hills Elementary School Manhole at Detention Vault October 21, 2015
Olympic Hills Elementary School Underground Utilities, Looking West October 21, 2015
Olympic Hills Elementary School Geothermal Well Drilling, Looking East October 21, 2015
Olympic Hills Elementary School Geothermal Well Drilling, Looking South October 21, 2015
Olympic Hills Elementary School Site View, Looking South October 21, 2015
Seattle World School at T.T. Minor Area A Administration Office, Student Services, Health Clinic and Library: Administration office addition concrete footings poured, underground utilities ongoing, temporary shoring installed. Health Clinic underground utilities ongoing, concrete grade beam complete. Library demolition complete. Area B Multipurpose, Kitchen, Boiler Room: Concrete stem wall pour complete, concrete slab preparation ongoing. Boiler Room hazardous material abatement complete, demolition ongoing. Area C Classrooms: CMU wall layout ongoing, CMU rebar installation ongoing, underground utilities complete, CMU grade beams complete, 2 nd floor demolition ongoing.
Seattle World School at T.T. Minor Site Plan
Seattle World School at T.T. Minor Area A - Administration Addition Concrete Footings Poured October 27, 2015
Seattle World School at T.T. Minor Area A Original Building Seismic Footing Retrofit Concrete Pour October 27, 2015
Seattle World School at T.T. Minor Area A Administration Area Temporary Shoring October 27, 2015
Seattle World School at T.T. Minor Area A Library Hazardous Material Abatement and Demolition Complete October 27, 2015
Seattle World School at T.T. Minor Area A Health Clinic Underground Utilities Ongoing October 27, 2015
Seattle World School at T.T. Minor Area B New Kitchen and Commons Addition Slab Preparation October 27, 2015
Seattle World School at T.T. Minor Area B Boiler Room Abatement Complete Demolition Ongoing October 27, 2015
Seattle World School at T.T. Minor Area C Science Classrooms Underground Utilities Complete October 27, 2015
Seattle World School at T.T. Minor Area C 2 nd Floor Demolition Ongoing October 27, 2015
New Thornton Creek Building Site: Continued installing footing drainage piping and downspouts. Continued remove excess soil stockpile. Began Phase 2 geothermal well drilling in playfield north of the parking lot. Building A: Continued with interior backfill around footings. Began installing below grade masonry around footing. Set subgrade for remaining concrete slab-on-grade. Building B: Continued erecting structural steel in both library and two story academic wing. Began placing steel joist and decking in both library and first story of two story wing. Place edge form for slab-on-deck. Building C: Continued interior framing on classrooms. Continued installing interior hollow metal window frames in hallway for classrooms. Began installing roof. Continued installing HVAC ductwork and above ceiling plumbing and electrical. Continued with MEP rough-in in classroom walls.
New Thornton Creek Building Key Plan
New Thornton Creek Building Aerial Photo October 15, 2015
New Thornton Creek Building Inserting Piping into Geothermal Well
New Thornton Creek Building Building A Preparing to Place Below Grade Masonry
New Thornton Creek Building Building C Installing Backing to Interior Framing
New Thornton Creek Building Building C Installing Hollow Metal Frames for Interior Windows
New Thornton Creek Building Building C Electrical Rough-in
New Thornton Creek Building Building C Installing Exterior Sheathing to Parapet
New Thornton Creek Building Building C Roofing
New Thornton Creek Building Building C Hot Mopping Asphalt on Roof