Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client



Similar documents
Cover Page page 1. Table of Contents page 2. Section 1 Introduction page 3. Section 2 Variable Air Volume System Components page 4

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) March

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings

NYC Department of Education Building Condition Assessment Survey BROADWAY EDUCATION CAMPUS - MANHATTAN, 26 BROADWAY, MANHATTAN, NY, 10004

HVAC Systems: Overview

for K-12 School Buildings

ENHANCED LABORATORY HVAC SYSTEM

Mechanical Systems Proposal revised

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations

COMPARATIVE LIFE-CYCLE ANALYSIS OF ENERGY-EFFICIENCY MEASURES AT TVA S CHATTANOOGA OFFICE COMPLEX: PHASE II RESULTS & FINAL DESIGN

Major Project Experience Page 1 of 12

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

Air Conditioning Clinic

Sample - Existing Building Commissioning Plan

Data Realty Colocation Data Center Ignition Park, South Bend, IN. Owner: Data Realty Engineer: ESD Architect: BSA LifeStructures

HVAC SYSTEMS ACOUSTICAL, COST & ENERGY STUDY

Glossary of HVAC Terms

HVAC Simplified Approach Option

SAM HOUSTON STATE UNIVERSITY

The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.

HVAC Systems in Schools & Commercial Buildings and Radon

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP

Subpart 1. Installation. All plumbing systems must be. installed and tested according to this chapter and chapter 4715,

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

Engineers Newsletter. Understanding Single-Zone VAV Systems. providing insights for today s hvac system designer. volume 42 2

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

Innovent LASER Packaged Fresh Air Conditioning Units

Xcel Business Customers: Program and Rebate Summary

1. What percent of a commercial business s energy usage comes from their HVAC system? A. 13% B. 23% C. 33% D. 43% E. 53%

Nominal Life Expectancy for Building Components

1.2 Refrigerant Equipment. General

Building Energy Systems. - HVAC: Heating, Distribution -

newsletter engineers energy-saving strategies for Water-Source Heat Pump Systems volume 36 2 providing insights for today s hvac system designer

Enclosed Football Stadium Design History and Lessons Learned

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

Challenges and Failures in Green Building Design Using Under-Floor Air Distribution. Ken Urbanek, PE, HBDP, LEED AP Director of Engineering

B.C. Buildings Corporation. Mandatory Preventive Maintenance Standard. To Meet Section 4.78 of the WCB OH & S Regulation

HVAC Checklist - Long Form

Using Autodesk Fabrication Software from TSI

SECTION HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT

Chilled Beam Solutions ADVANCING THE SCIENCE OF AIR DISTRIBUTION. Redefine your comfort zone.

SECTION PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM

Energy Efficiency Opportunities in Federal High Performance Computing Data Centers

Energy Efficiency in Industrial HVAC Systems

SECTION TABLE OF CONTENTS. H Proposed Material, Product or Equipment Substitution Request

Basics of HVAC Cleaning

NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES

BPC Green Builders. Green building for new and existing homes. Health Comfort Energy

Proper Applications & Sequences for Constant Volume Pressure Dependent Zoning Systems. History

RFI Response RFP: HSCG88-16-R-PQQ015 Replace HVAC Bldg A & C San Diego, CA.


MEETING AGENDA. Project Administrator:

University of Maryland s Gossett Field House College Park, MD

HOURLY ANALYSIS PROGRAM QUICK REFERENCE GUIDE

HVAC Characteristics. Test Space HVAC Characteristics

Methods for Effective Room Air Distribution. Dan Int-Hout Chief Engineer, Krueger Richardson, Texas

Commissioning - Construction Documents (Page 1 of 6)

HVAC Processes. Lecture 7

Defining Quality. Building Comfort. Precision. Air Conditioning

National Competency Based Skill Training Refrigeration and Air-conditioning Mechanic Logbook

Mechanical, Plumbing, and Fire Protection Conditions

Dehumidification Design

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

ASHRAE Rocky Mountain Chapter. RickPhillips Phillips, P.E., PE LEED AP Senior Mechanical Engineer The RMH Group, Inc.

Presented By: WALTER E. JOHNSTON, PE CEM, CEA, CLEP, CDSM, CPE

SECTION GENERAL PROVISIONS FOR HVAC WORK

HIGH EFFICIENCY RTU. HIGH EFFICIENCY, PACKAGED SPACE CONDITIONING. DX System IEER> 13.2 Gas Heat Efficiency > 92% Capacities Tons

HVAC Basic Science - System Capacity

APPLICATION GUIDE. Comparison of Latent Cooling Performance of Various HVAC systems in a Classroom Application

Energy Efficiency Analysis for a Multi-Story Commercial Office Building. (LG Multi V Water II Heat Recovery VRF System)

Data Center Energy Profiler Questions Checklist

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

Preliminary Final Proposal

COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES

MECHANICAL SYSTEMS DESIGN. Team

CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers

BSD Technical Standard Division 23: HVAC

Selection Tips For Air-Conditioning Cooling Systems

Energy Efficiency Analysis for a Multi-Story Commercial Office Building. (LG Multi V III Heat Recovery VRF System)

Active & Passive Beams

PULASKI AND DUBLIN MIDDLE SCHOOLS

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION

How To Design An Hvac System

for Plans Examiners and Building Inspectors

CLASS B AIR CONDITIONING CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

Installation Manual. Rental Services. Air Handling Units CHS-SVN01A-EN. July 2008

Chilled Water HVAC Systems

Acumen Enterprises, Inc.

HVAC Technologies for Building Energy Efficiency Improvements 2013 National Symposium on Market Transformation. Richard Lord Carrier Fellow

NEW JERSEY CENTER OF EXCELLENCE

Element D Services Plumbing

BASE PERMIT FEE x.80 = PLAN CHECK FEE*: $ BASE PERMIT FEE x.10 = MECHANICAL INSPECTION FEE: $ BASE PERMIT FEE x.12 = ENERGY CODE REVIEW FEE: $

Comparing Energy Savings of Different VAV Systems

Aurora Mall. Aurora (Denver), Colorado

Riverside City College. Math & Science Building HVAC Investigation. May 23, 2013

School of Human Ecology Building UW Madison, Wisconsin. By Arnold & O Sheridan, Inc. A&O Project No Draft Report 01/12/01 revised

UNDER FLOOR AIR DISTRIBUTION (UFAD) SOLUTIONS

Transcription:

Order of Magnitude Mechanical Estimating Justin Apprill, P.E. Topics for Today Estimate Goals A Concept for Accurate Conceptual Estimating HVAC Systems Common System Types and Rules of Thumb Pricing Example Estimate Managing the Budget During Design Project Delivery Methods Order of Magnitude Estimate Goal Conceptual Estimating applies to each type of delivery. Plan and Spec. Lump Sum Bid Design-Assist Lump Sum, GMP, T&M Design-Build Lump Sum, GMP, T&M IPD Integrated Project Delivery Determine today what the job will cost tomorrow. Questions for Client General Discovery Questions First Question: What will you do with the information? Occupancy Owner End User Design Team Building Square Footage Small or Disadvantaged Business Goals Schedule Jobsite Logistics Overall project budget Sole Sourced Vendors or Subs

Mechanical Discovery Questions Desired Systems % of Glass Building Orientation Desired Conditions (temp & humidity) Outside Air Requirements Specialty Areas Energy Code Compliance BIM Requirements LEED / Sustainable Design LEED Design Over 1/3 of LEED points can be mechanical related Estimating Concepts and Relative Accuracy The Concept of Accurate Conceptual Estimating Estimate based on final construction documents Accuracy = +/- 0% to 5% Good conceptual estimate evaluating all system components Accuracy = +/- 5% to10% $/square foot or $/building unit (bed, cell, etc.) Accuracy = +/- 10% to 20% Quantities and capacities of all HVAC equipment & systems Quantities and capacities of all plumbing fixtures, equipment, and systems Apply established unit values to quantities and capacities Accuracy is very dependent upon understanding of systems and accuracy/application of the unit values Required Information Required Information Specifications establishing required materials and equipment quality Conceptual drawings or systems narrative Types of systems System capacities System layout Specifications (be careful of assumptions) Types of piping for each application Types of insulation Quality of plumbing fixtures Quality and type of equipment Accepted manufacturers Trade responsibilities

Required Information Specifications Specialty requirements Process systems Owner furnished equipment connections Vibration or sound isolation Temporary heating/cooling provisions Custom equipment Water filtration Interface between HVAC controls and other building systems Equipment utilize rule of thumb or actual cost from vendors Equipment labor utilize established unit values for labor hours per piece of equipment Piping utilize established unit values which include material and labor per lineal foot Ductwork utilize established unit values which include material and labor per cfm or pound Indirect Costs Plumbing Unit values need to consider indirect costs Tools, equipment rental, trucks Testing Delivery and hoisting Detailing/BIM Modelling Material handling Safety Consumeables Supervision Start-Up and Functional Testing Indirect costs can add 20% to 40% to the direct cost Roof drainage Quantity of drains Overflow drains or scuppers Separate overflow system or connected to primary drainage system Utility connections Plumbing Plumbing Fixtures Back to Back? Level of finish? Equipment Quantity and type of water heaters Special Systems Generator fuel system Boiler fuel oil system Medical Gas Recirculation system concept Mixing valve requirements Water booster pump requirements Sewage ejector (lift station) requirements Water softening equipment Water filtration equipment Laboratory Gas Special drainage requirements Interceptors and traps Acid waste piping Grease waste piping Ground water pumping equipment

HVAC Heating Plant Boiler capacity Pumping scheme & sizes Pump VFDs Specialties Expansion tanks, air separators, triple duty valves, gauges Water treatment HVAC Cooling Plant Chiller type & capacity Pumping scheme & sizes Pump and/or chiller VFDs Cooling tower type & capacity Water treatment Specialties Free cooling heat exchanger(s) HVAC HVAC Air Handling Equipment RTU or AHU capacity (tons/cfm) Unit specifications Casing construction Heat recovery Integral return/exhaust fans Economizer cycle If RTU type of roof curb Piping Mains Establish unit values for each type of pipe which consider: Hanger requirements Pipe routing / available ceiling space Material specification/joining method HVAC Piping Branches Establish $/connection for each type of coil Review piping connection details if available Gauges, isolation valves, balancing valves Large coils may require multiple connections Sheet Metal Terminal boxes (fan powered and vav) Ductwork Specifications Exhaust fans Air devices types (grilles, registers, diffusers, louvers) Specialty ductwork (kitchens, labs, process)

Insulation Plumbing HVAC piping & equipment Ductwork Estimate as $/l.f. by size, or % of piping and ductwork (6% to 12%) Temperature Controls Operator interface terminal (PC) Cooling plant Heating plant Air handling units VAV / Fan powered boxes Fan coil units / heat pumps Terminal devices (unit heaters, etc.) Make-up air and Exhaust systems Other Items to Consider Commissioning LEED Certification Security Requirements Design Responsibility Mechanical Systems Rule of Thumb Prices Site Logistics Local Jurisdiction/Code Requirements HVAC & Plumbing Cost as % of Overall Budget Mechanical Cost by System Type (Ballpark Ranges - $/s.f.) Standard/Office Bldg 15%-20% Recreational Buildings Hospital 20%-25% Plumbing $5 to $7 per s.f. Data Center 30%-40% HVAC $17 to $22 per s.f. Laboratory 30%-35% Apartment/Hotel 15%-20% Prison/Correctional Facility 15%-20% Office Buildings Plumbing $5 to $7 per s.f. HVAC (2 pipe) $15 to $23 per s.f. HVAC (4 pipe) $23 to $28 per s.f.

Mechanical Cost by System Type (Ballpark Ranges - $/s.f.) Mechanical Cost by System Type (Ballpark Ranges - $/s.f.) Hospitals (new construction) Hotel/Condo High Rise Plumbing $25 to $30 per s.f. Plumbing $11 to $15 per s.f. HVAC (4 pipe) $45 to $55 per s.f. HVAC (2 pipe) $15 to $18 per s.f. HVAC (4 pipe) $18 to $21 per s.f. Prisons Plumbing $13 to $18 per s.f. Hotel/Condo Low Rise HVAC (4 pipe) $30 to Plumbing $9 to $12 per s.f. $40 per s.f. HVAC (d/x) $5 to $8 per s.f. Plumbing Rules of Thumb HVAC Rules of Thumb Roof drainage $0.75/s.f. to $2.00/s.f. Depends greatly on building height, roof configuration, quantity of drains Method of overflow is important Waste/vent & domestic water $2k to $4k per fixture Includes water heaters not specialty items Depends on type of building/quantity of fixtures Don t forget non-typical/specialty items!! Boiler Plant $9/MBH to $13/MBH Chiller Plant $750/ton to $1200/ton Piping Mains can vary greatly HVAC Rules of Thumb HVAC Rules of Thumb Roof Top Units Insulation $650/ton to $900/ton 6% to 12% of total HVAC Air Handling Units (modular) $1.50/cfm to $2.50/cfm Air Handling Units (custom) $2.50/cfm to $5.00/cfm (Includes labor to set equipment) (Does not include piping and controls) and plumbing cost Sheet Metal $4/cfm to $8/cfm Temperature Controls Very large range. ($0.75/sf to $5.00/sf) Test and Balance $0.20/sf to $.50/sf

Rules of Thumb for System Selection HVAC Systems Common System Types Single Story < 25,000 s.f. DX Split or Rooftop Unit Single Story >25,000 s.f. VAV System Water Source / Geothermal Heat Pump Two Story < 25,000 s.f. VAV System Water Source / Geothermal Heat Pump Two Story and Greater > 25,000 s.f. VAV System Water Source / Geothermal Heat Pump Under floor Air Multi-Story VAV System Under floor or Overhead Air Unitary or Chilled Water System, Boiler System or Electric Heat, Specialty systems (dedicated outside air, chilled beams, etc. Single Zone, Constant Volume single, constant volume Packaged DX Rooftop System EA OA cooling coil RA supply fan SA packaged rooftop air conditioner sheet-metal supply duct diffuser thermostat multiple s, constant volume Changeover Bypass System Rooftop VAV System packaged rooftop air conditioner diffuser modulating damper packaged rooftop air conditioner VAV terminals bypass damper system-level controller system-level controller

Multiple Zones, Constant Volume multiple s, constant volume Multi Air Handler EA RA EA RA OA cooling coil supply fan SA reheat coil OA multi air handler SA thermostat thermostat Multiple Zones, Variable Volume multiple s, variable volume DX Rooftop VAV System EA RA packaged DX rooftop air conditioner return supply OA cooling coil supply fan thermostat SA VAV box VAV terminal, diffusers system-level controller multiple s, variable volume Self-Contained DX VAV System cooling tower Split VAV Distribution System outdoor-air inlet diffuser sheet-metal supply duct flexible duct diffuser self-contained DX air conditioner VAV terminal system-level controller return-air inlet central air handler VAV terminal hot-water boiler, pumps

Small Chilled-Water System water chiller multiple s, variable volume Central Chilled-Water VAV System cooling tower pump cooling coil VAV terminal, diffusers control valve air handler system-level controller hot-water boiler, pumps water-cooled chiller Dedicated Outdoor-Air System single, constant volume Water-Source Heat-Pump System OA ducted directly to spaces OA ducted to terminal units cooling tower off plate-and and-frame heat exchanger boiler off OA ducted to plenum near terminal units heat pumps in cooling mode heat pumps in heating mode single, constant volume Water-Source Heat-Pump System single, constant volume Ground-Source Heat-Pump System dedicated outdoor-air unit cooling tower heat pump, duct, diffuser heat pump system-level controller boiler, pumps, air separator geothermal heat exchanger pumps

Underfloor Air Distribution System Make-up Return @ 80-8282 o F Heat Source Displacement Zone Boundary Layer Perimeter Zones Outer +/-15 ft. Interior Zone High Induction Floor Diffusers Manual or Zoned Mixing Zone Underfloor Supply Plenum Induced Room Air Supply @ 60-6464 o F Common Discharge Plenum or Ducted Supply FTU Series Fan Terminal w/reheat Capabilities New Office Building Kansas City Metro Area 178,000 s.f. Completely Finished (not core-shell) Standard Office Plumbing PLUS Commercial Kitchen/Cafeteria Chilled water system serving large air handling units Underfloor air distribution Based on square footage alone: Plumbing: $5 to $7 per s.f. HVAC (2 pipe): $15 to $23 Range is $3,916,000 to $5,162,000 Average is $4,539,000 or $25.50/s.f. Range/Average = 27% spread Roof Drainage Plumbing Fixtures 2 story building Flat roof Overflow scuppers $1.00/s.f. x 178,000 = $178,000 138 fixtures Fixtures are spread out due to bldg. layout 138 x $3,000 = $414,000

Commercial Kitchen/Cafeteria Historical Cost?? Number of Connections?? 100 Connections x $1,500 = $150,000 Chilled Water Plant Water cooled with cooling towers 900 tons Free cooling heat exchanger LEED Silver project = efficient chillers Cooling towers adjacent to chillers 900 tons x $800/ton = $720,000 HVAC Piping Air handling units spread out Pipe quantities known?? $1.00 to $3.00 per s.f. 178,000 s.f. x $1.50/s.f. = $267,000 Air Handling Units 200,000 cfm (includes kitchen make-up air) Large capacity units 40,000 cfm for major units 200,000 cfm x 1.75/cfm = $350,000 Sheet Metal Underfloor air system Perimeter electric heat terminal units under floor Perimeter automatically controlled s Interior manually controlled s Commercial kitchen systems 200,000 cfm x $6.00/s.f. = $1,200,000 Insulation $3,279,000 x 5% = $163,950 Temperature Controls 178,000 s.f. x $1.50 = $267,000 Test & Balance 178,000 x $0.25/s.f. = $44,500

Subtotal = $3,774,075 OH&P (15%) = $452,889 Total = $4,226,964 $23.75/s.f. Managing to the Budget How do you make the budget real? What accurate today can change quickly during design. Must get control of the things that are out of your control. Actual Estimate on Completed Documents $3,880,000 or $21.80/s.f. 8% lower than budget How GC can help? How GC can help? Clear scope of work issued with bid documents General conditions requirements Clean up Temporary utilities Use of tower crane Supervision requirements Safety requirements QA/QC staff requirements Temporary conditioning Define the Schedule Define the Schedule Overtime expectations Clean up requirements Coordination requirements and plan Billing method (schedule of values versus cost plus fee) Site logistics plan Avoid bid day! Questions? Thank You!