Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland



Similar documents
Building Condition Assessment: North Howard Street Baltimore, Maryland

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

SECTION 3 ONM & J STRUCTURAL ANALYSIS

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

423 NORTH HOWARD ST. VISUAL STRUCTURAL ASSESSMENT

Slavic Village Building Condition Review

Exterior Elevated Elements Inspection Guidelines

STRUCTURAL ASSESSMENT

Engineers, Civil Structural Survey

PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007

EAST LYME HIGH SCHOOL

Facility Assessment for East Main Street, Huntley, IL

Reference: BRM A0 July 18 th, Cursory Visual Review of Various Below Grade Spaces and Exposed Foundation Walls

REQUEST FOR PROPOSALS FOR: THE PURCHASE AND RENOVATION OF ADJOINING PROPERTIES AT 200/240 SOUTH 16 TH STREET ORD, NEBRASKA BY:

Building Foundation and Structure

BROWNSVILLE STRUCTURES STUDY. July Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania

October 30, Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.

Building Condition Assessment Report

Structural Assessment Report

14 September Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste St. Paul, MN 55102

48. AQUARIUM. Aquarium. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle. Total Area: No.

Garver Feed Mill Condition Evaluation

Excerpts from the Canadian National Building Code (NBC)

29 Broadway- 14 th Fl Tel: New York NY Fax: Due Diligence Report. New York, New York

Certification: Building Plans Examiner. Exam ID: B3

School Construction Authority Architecture & Engineering

May 5, Client Client Address. Re: Inspection Address, Chicago, Illinois. Dear Mr. Client,

CZAR Engineering, L.L.C.

Page & Turnbull imagining change in historic environments through design, research, and technology

A0 SHEET 1 OF LOCUST STREET FRANKFORT, KANSAS FRANKFORT, KANSAS ROOF REPAIR OF THE 400 LOCUST STREET

Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas August 30, Prepared for:

Architectural Condition Survey

BUNKER HILL ELEMENTARY SCHOOL

CLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.

Memorandum. July 16, To: Plan Commission City of Madison

Photos showing the change in condition from 2006 to 2012 are located in Appendix A.

March 19, Ms. Jean McDonald CAP Management th Street, Suite 1010 Denver, Colorado 80202

HEDDERMAN ENGINEERING, INC. Office , Fax

OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007

Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 ( N, E)

Lighthouse Engineering, L.L.C.

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA

Self-Home Inspection Checklist

CONSERVATION MAINTENANCE WORKSHEET Universal Checklist

BUILDING PERMIT SPECIFICATIONS

MEMORANDUM. General: Foundation:

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

DRAPER ELEMENTARY SCHOOL

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

How To Prevent Water Damage To A Home

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

PROFESSIONAL ENGINEERING INSPECTIONS, INC.

October 5, 2015 Dear Client,

17,280 square feet Overview:

Vision Home Inspection

Mark Cramer Inspection Services, Inc.

Chapter 5. In-depth Building Analyses and Recommendations. Planning Study for Downtown Revitalization City of Martinsville

Inspecting to a higher standard.

Historic Preservation Certification Application Part Main Street West South Haven, Vermont NPS Project No

Guernsey s Structural Engineering Experience

CONDITION OF QUALITY ITEMS

PRESERVATION PLANNING ASSOCIATES 519 Fig Avenue, Santa Barbara, CA Telephone (805)

Name of course: Residential Construction Site Management (RCSM) Level 1

Repair and Rehabilitation of Nehru Memorial College of K.V.G. Group of Institutions at Mangalore - A Case Study

Saint Cloud Business Center

National Home Builder - Name Wednesday, August 20, 2014 Regional Customer Care Manager 1234 Main Street Houston, Texas 77067

How Façade Ordinances Affect Your Historic Building

Property Condition Assessment

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

Lighthouse Engineering, L.L.C.

ASHULIA APPARELS LTD. Client Summary Report

Date: March 7, 2006 Report for [removed]

Bernie Nimer, Dave Seton Mayfair Hotel Development Corporation

How to Identify, Evaluate & Repair Shrinkage Cracks in Poured Concrete

HISTORIC PRESERVATION COMMISSION ADMINISTRATIVE APPROVAL ISSUED JULY - SEPTEMBER 2014 DATE PROJECT ADDRESS PROJECT DESCRIPTION

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

Home Inspection Report

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

bout your HOUSE before you start Repairing And Replacing Materials Exterior Walls

Estimated Cost of Repair

Website. King County Council District # WA State Legislative District # Date Incorporated. Federal Tax ID. WA State UBI#

How To Find Out What Happened To Slave Housing

CABIN A Restored & Preserved 1850 Slave Cabin

TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09

PROPERTY East Wetumpka Commercial Historic District (Boundary Increas NAME: e)

GUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES

Article 5: Building Regulations

Fire Alarm And System Description. Automatic Sprinkler System Description. Fire Suppression Equipment. Fire and Evacuation Drills

Roof Inspection. Summary Report

WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204

General Earthquake Damage Inspection Checklist

Chapter 11: Demolition

HAMILTON SCHOOL Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA

5006 Cherry Ridge Road Richmond, Texas LIMITATIONS AND DISCLAIMERS

GOOD NEWS BUT NOT ALWAYS

G. Common Defects in Buildings - Leakage

BTC. Building Technology Consultants, PC 1845 E. Rand Road, Suite L-100 Arlington Heights, Illinois Main: (847) , Fax: (847)

Transcription:

KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore, Maryland May 7, 2012

EXCUTIVE SUMMARY The roof is leaking at throughout. No leaking was observed at windows. The front wall has open mortar joints and cracked stone units. Exterior walls are structurally sound. There is no danger of failure of structural elements. Opinion of Cost: Immediate Repairs Structural Stabilization Repairs: None required None required Building Envelope Repairs: $59,000 Total: $59,000 Prepared by Kennedy, Porter and Associates, Inc. Page 1

STRUCTURE DESCRIPTION The building is approximately 158 x 70, with three stories over a basement. It was reportedly constructed circa 1930. The building s structure consists of brick masonry exterior walls and wood framed floors. The north face of the building finished with decorative stone. The premises are currently vacant; its most recent uses include offices and retail stores. We have reviewed available information provided to us by Baltimore City about the building. This information was limited to tax records, historic fire insurance maps and land eligibility reports provided by CHAP. INSPECTION OBSERVATIONS Building was inspected by the joint venture of EBA Engineering, Inc. and Kennedy, Porter and Associates, Inc. on May 2, 2012. Our inspection was visual in nature, and was limited to accessible structural elements. Façades were inspected from grade using binoculars. Roofs were accessible and were included in our inspection program. No finishes were removed and no probes were made to determine structural conditions. Figures 1 and 2 show general exterior conditions and photograph locations. The structure is in overall fair to good condition. Observed deficiencies are summarized as follows: Roof Appurtenances Roof Framing The roof is generally flat, and is covered with a membrane roofing system. There are many penetrations through the roof for mechanical equipment (see Photo 1and 2). Steel dunnage supporting mechanical equipment over the roof is in generally fair condition. Paint is peeling throughout and minor corrosion was observed. The upper stair well roof exhibits membrane deterioration and is not able to repel water (see Photo 3). The roofing membrane has generally failed throughout. Active leaks were noted in the fifth floor ceiling below. Standing water was noted against the south parapet near the building s middle. Water damage from leakage was observed along the south wall at two locations (one east of the elevator and over the stair tower (see Photo 3). At these locations, wood plank roof sheathing has been damaged and will require replacement (see Photo 4). Wood roof rafters have minor deterioration. Floor Framing Water damage continues down to the third and second floor framing. Wood plank sub-floor is damaged and leaks in these areas. The second floor southwest corner area exhibits partial failure due to heavy loads imposed on deteriorating floor framing (see Photo 5). Prepared by Kennedy, Porter and Associates, Inc. Page 2

Foundations There are numerous areas that exhibit water damage throughout the third, second, and first floors (see Photos 6-9). No signs of differential settlement, bowing or cracking were observed in the masonry foundation walls (see Photo 10). There are several reinforced concrete beams that exhibit wide horizontal cracks (see Photos 11-14). There are several loose and broken treads in the basement level stair well (see Photo 15). The concrete basement slab exhibits uplift, cracking and settlement in two locations (see Photos 16-18). Interior Bearing Walls Interior walls were concealed by finishes, but no signs of distress, such as settlement or cracking, were noted in these finishes (see Photo 19). South Elevation The south façade consists of common brick. There are step cracks in the brick and mortar joints at the top portions of the wall (see Photos 20 and 21). The cracking at the east end continues horizontally into the east façade plastered finish (see Photos 21 and 22). There are areas of missing brick and deteriorating mortar at the base of the wall, with concrete spalling located along an exit door threshold ( see Photos 23 and 24). Rear (East) Elevation The east elevation consists of common brick. The brick is in generally satisfactory condition, although there are random areas of spalled bricks (see Photo 9). The steel fire escape at this façade is in generally fair condition. Left (North) Elevation The North elevation features three recessed entries. The second and third stories have decorative stone work finishes that exhibit numerous cracks and deteriorating mortar. Several of these locations exhibit vegetation growth (see Photo 25-29). There are two fractured parapet cap stones at the east and west portions of the north wall (see Photos 30 and 31). Interior leakage above the north store front framing in building 219 was observed during the time of inspection thru deteriorated members (see Photo 32). All window and door sashes, lintels, frames, and sills exhibit moderate to severe paint failure. Prepared by Kennedy, Porter and Associates, Inc. Page 3

Recommendations: Our recommendations below refer to structural elements of the building only. These are based on conditions observed at the time of our inspection. Our Engineer s Opinion of Probable Cost included with the repair recommendations is schematic in nature, consistent with the level of detail provided in our general repair recommendations. Immediate Repairs These repairs are required to be performed immediately on an emergency basis in order to prevent an imminent collapse or because the noted conditions pose a safety risk to the general public. - None required Structural Stabilization Repairs These should be scheduled as soon as possible. These recommendations require action to prevent accelerated deterioration of the structure, or in order to prevent the development of dangerous conditions in the future. - None required Building Envelope Repairs These repairs should be performed in order to maintain the building s longevity and ensure its continued usability, in part or in whole. - Patch roofing system $8,000 - Repoint open mortar joints at front façade $36,000 - Repair cracked stone units at front façade $15,000 Total $59,000 Prepared by Kennedy, Porter and Associates, Inc. Page 4

30 27 28 25 31 26 29 Figure 1: West Elevation Prepared by Kennedy, Porter and Associates, Inc. Page 5

20 21 Figure 2: North Elevation Prepared by Kennedy, Porter and Associates, Inc. Page 6

Photo 1: Roof Condition Looking North Photo 2: Roof Condition Looking South Prepared by Kennedy, Porter and Associates, Inc. Page 7

Photo 3: Deteriorating Roof Membrane Photo 4: Water Damage in Third Floor Ceiling at South Wall Prepared by Kennedy, Porter and Associates, Inc. Page 8

Photo 5: Collapsed Second Floor in Southwest Room Photo 6: Typical Water Damage in Floor Ceiling Prepared by Kennedy, Porter and Associates, Inc. Page 9

Photo 7: Typical First Floor Ceiling Photo 8: Water Damage in First Floor Framing Prepared by Kennedy, Porter and Associates, Inc. Page 10

Photo 9: Water Damage in Second Floor Framing Photo 10: Typical Basement Foundation Wall Prepared by Kennedy, Porter and Associates, Inc. Page 11

Photo 11: Cracking Concrete Beam in Basement Level Ceiling Photo 12: Cracking Concrete Beam in Basement Level Ceiling Prepared by Kennedy, Porter and Associates, Inc. Page 12

Photo 13: Cracking Concrete Beam in Basement Level Ceiling Photo 14: Cracking Concrete Beam in Basement Level Ceiling Prepared by Kennedy, Porter and Associates, Inc. Page 13

Photo 15: Broken Basement Steps Photo 16: Spalling Concrete Basement Slab Prepared by Kennedy, Porter and Associates, Inc. Page 14

Photo 17: Spalling Concrete Basement Slab Photo 18: Spalling Concrete Basement Slab Prepared by Kennedy, Porter and Associates, Inc. Page 15

Photo 19: Typical Condition of Interior Bearing Walls Photo 20: Cracking in West corner of South Façade Prepared by Kennedy, Porter and Associates, Inc. Page 16

Photo 21: Cracking in East corner of South Façade Photo 22: Cracking in West Elevation Prepared by Kennedy, Porter and Associates, Inc. Page 17

Photo 23: Deteriorating Mortar at Base of South Wall Photo 24: Spalling Concrete at Base of South Wall Prepared by Kennedy, Porter and Associates, Inc. Page 18

Photo 25: Cracked Stone Lintel in North Façade Photo 26: Deteriorating Mortar in North Facade Prepared by Kennedy, Porter and Associates, Inc. Page 19

Photo 27: Deteriorating Mortar in North Facade Photo 28: Cracked Stone Lintel in North Facade Prepared by Kennedy, Porter and Associates, Inc. Page 20

Photo 29: Cracked Stone Lintel in North Facade Photo 30: Crack in Parapet Cap Stone Prepared by Kennedy, Porter and Associates, Inc. Page 21

Photo 31: Crack in Parapet Cap Stone Photo 32: Interior North Face Water Damage at Window Lintel Prepared by Kennedy, Porter and Associates, Inc. Page 22