Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 ( N, E)

Size: px
Start display at page:

Download "Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E)"

Transcription

1 Revision: issue 1 Date: 11 June 2014 Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 ( N, E) 24 th May 2014 Structural Inspection Report Observations & Actions Authors: Robert Read, Piotr Czapko Checked by: Hugh Griffin Approved by: Aidan Madden Category Amber Category RED if actions are not immediately progressed as requested on pages 3 & 4 DEA 1

2 2 Executive summary On Saturday 24 th May 2014 Mr. Robert Read (lead) and Mr Piort Czapko of Arup carried out a visual structural survey of Sisal Composite Ltd. at the address and coordinates shown on the cover of this report. We met with Mr Shahnoor (Chief of Operations), Mr. Md. Sanoar Hossain (Assistant Manager Accounts and Finance) and Mr. Md. Masud Rana (Executive Admin & Compliance). Sisal Composite Ltd. occupy the first floor of two adjacent buildings. The first building ( Building 1 ) is a five storey RC frame which is also occupied by Apparel 4 Ltd, JM Knit Ltd. and Snap Button Industries Ltd. The upper floors are used for garment manufacture whilst the ground floor is used for manufacturing buttons. The adjacent Building 2 has four stories which have been constructed across the whole site with the four bays to the east of the site having an additional fifth storey. Building 2 is principally used for storage by Sisal Composite Ltd, Apparel 4 Ltd and JM Knit Ltd. We inspected all accessible parts of the factory buildings. Construction of the Ground to 3 rd floor of Building 1 was reportedly finished in 2007, the fourth floor was added in We were shown an industrial permit drawing for a five storey industrial building that was signed by the Union Purishad (UP) Chairman in May We were also shown a residential permit drawing for a building on the same site that was approved in July In addition we were shown undated structural layout drawings. Whilst the shape of the buildings inspected was similar to those shown on the drawings there were some discrepancies, most notably the column sizes, slab spans and the location of the rear staircase. No soils report was available for this building.

3 3 Executive summary (Continued) For Building 2 we were shown a permit drawing for a 4-6 storey commercial building which was approved by the UP Chairman in March We understand that the building was constructed in two phases. Phase 1 consisted of the rear 6 bays up to 3 rd floor, during Phase 2 the front 4 bays were built up to 4 th floor (reportedly completed in 2012). There were no structural drawing for Phase 1 although undated drawings were available for the 5 storey portion built in A soils report dated 2011 suggested piled foundations. The permit drawing shows pad foundations. There was no evidence of overloading, distress, damage, excessive deflections or settlements. We have important and urgent concerns in relation to the adequacy of the structural support columns for the both Building 1 and 2. The columns appear to be stressed to levels that require immediate review. The following immediate actions are required to be carried out to reduce the loads in the columns: 1. The water tank on the roof of Building 1 should be emptied. Alternative temporary water tanks may be located elsewhere on the roof. Suitable locations should be determined by a suitably qualified Structural Engineer. 2. Loading restrictions must be imposed in the area highlighted below for Building 2. The toilets may continue to be used but the area external to the toilets must have all loading removed and must remain unoccupied pending completion of a Detailed Engineering Assessment. 3. The high storage loads at the first floor of Building 2 should be reduced. Average floor loading on all floors should not exceed 2 kpa (Building 1 and 2).

4 Executive summary (Continued) Area where immediate actions are required for Building 1 Storage loading and all other loads must be managed to ensure that a maximum load of 2kPa is not exceeded on any floor above Ground Floor. Water tank to be drained 4

5 Executive summary (Continued) Area where immediate actions are required for Building 2 5 The toilets may continue to be used but all loading must be removed from the area shown shaded at all levels above Ground Floor Storage loading and all other loads must be managed to ensure that a maximum load of 2kPa is not exceeded at any floor above ground floor.

6 Executive summary (Continued) We would recommend that a Detail Engineering Assessment for this building be completed within 6 weeks of receiving the report. If the building owners are not in a position to complete these actions immediately, both buildings should be re-classified as Category Red and evacuated. A high level and non exhaustive list of key concerns are: ITEM 1 - High stress in columns. ITEM 2 - Localised areas of storage leading to high imposed loads being applied to the structure. ITEM 3 - Inconsistent and missing record information ITEM 4 - Cantilevering half landing ITEM 5 - Beam depths vary between floors ITEM 6 - Hairline cracking observed in beams and slab soffits We see no reason to suspend operations in the facility due to these concerns (subject to the required actions noted at the end of this report). Further actions with associated priorities and timeframes are given at the end of this report. Please note that these actions should be completed as soon as practically possible and certainly within the timeframe noted. We have reviewed the property from an outline seismic perspective and would consider that the building along with many others in the Dhaka region to have a significant risk in a major Seismic event. Our Limitations and Assumptions are also noted at the end of this report. 6

7 7 Building Extents

8 Sisal Composite Ltd. rent the first floor of 2 buildings. Building 1 is 5 stories high. The height of Building 2 varies between 4 and 5 stories. N Building 1 Building 2 8 Building Extents Site Plan

9 Building 1 East elevation Building 2 East elevation 9 Building Extents Elevations

10 Building 1 Building 2 South Elevation 10 Building Extents Elevations

11 Building 1 West Elevation 11 Building Extents Elevations

12 Construction of the ground to 3 rd floor of Building 1 was reportedly finished in 2007, the fourth floor was added in We were shown an industrial permit drawing signed by the Union Purishad Chairman in March 2013 for a five storey industrial building. We were also shown a drawing for a residential building on the site that was approved in July 2012 (see below). There was no soils report available for this building. Industrial permit (2013) Residential permit (2012) Building Extents Permit Information Building 1

13 Roof Telecommunications antenna Fourth Floor Cutting Sewing, Finishing (Apparel 4 Ltd) Third Floor Cutting Sewing, Finishing (Apparel 4 Ltd) Second Floor Cutting Sewing, Finishing (JM Knit Composite) First Floor Cutting Sewing, Finishing (Sisal Composite Limited) Ground Floor Button manufacture (Snap Button Industries Ltd.) Building Extents Floor Usage Building 1

14 A permit drawing for Building 2 was available showing a 4-6 storey commercial building, this was approved by the UP Chairman in March We understand that Building 2 was constructed in two phases. Phase 1 consisted of the rear 6 bays up to 3 rd floor, during Phase 2 the front 4 bays were built up to 4 th floor (reportedly completed in 2012). There were no structural drawings for Phase 1 although undated drawings were available for the 5 storey portion built in A soils report dated 2011 for a 6 storey residential building suggested piled foundations although pad footing details are shown on the permit and structural drawing. Original 4 storey building construction date unknown Permit drawing available Extension built in 2012 Undated structural plans available. Building Extents Permit Information Building 2

15 Roof Fourth Floor Predominantly storage (Apparel 4 Ltd) Third Floor Predominantly storage (Apparel 4 Ltd) Second Floor Predominantly storage (JM Knit Composite) First Floor Storage (Sisal Composite Limited), leather goods manufacture Ground Floor Leather goods manufacture Building Extents Floor Usage Building 2

16 16 Structural System

17 Structural Description Building 1 is a 5 storey reinforced concrete (RC) building with a two way spanning slab supported by downstand beams. There is a two storey RC structure supporting a steel telecommunication tower on the roof. Horizontal stability is assumed to be provided by frame action with additional stiffness provided by masonry façade walls. The floor slabs are assumed to act as diaphragms to transfer stability loads back to the vertical elements. N 17 Structural System Building 1

18 Building geometry Column grid varies, maximum 4.6m x 5.15m at front, 7.0m x 6.2m at the rear Column size varies typically 380mm x 250mm internally at ground floor Slab thickness typically 165mm (excl. finishes) Typical finishes thickness 45mm Record information shows piled foundations, this could not be confirmed on site Slab cantilevers beyond columns along eastern side of building Slab edge along northern edge of building not parallel with grid. Varies from no offset to 1.5m cantilever (max.) Brick aggregate 18 Typical downstand beam/ column junction detail Structural System Building 1 View of cantilevering slab on eastern side of building

19 Structural Description Building 2 is a reinforced concrete (RC) building, the height of which varies between 4 and 5 stories. The two way spanning slab is supported by downstand beams. Horizontal stability is assumed to be provided by frame action with additional stiffness provided by masonry façade walls. The floor slabs are assumed to act as diaphragms to transfer stability loads back to the vertical elements. N 19 Structural System Building 2

20 Building geometry Column grid varies, maximum 3.8m x 4.9m. Column size varies typically 300 x 300mm at ground floor. Slab thickness typically 150mm (excl. finishes). Typical finishes thickness 40mm. Slab cantilevers beyond columns along southern side of building, max. 1.3m Soils report suggests piles, pads foundation shown on drawings, not confirmed on site. Brick aggregate in original columns, stone aggregate in recent extension columns. 20 Balconies on eastern elevation Structural System Building 2 View of cantilevering slab on southern side of building

21 21 Observations

22 22 High column stresses

23 The columns highlighted have very high compressive stresses. Immediate actions are required to reduce the loads in these columns as stated later in this report This column is subject to loads from overhead water tank which is cantilevering beyond the columns High column stresses Building 1 23

24 The columns highlighted have very high compressive stresses. Immediate actions are required to reduce the loads in these columns as stated later in this report This column is subject to loads from toilet cubicles and finishes which sit on a cantilevering slab High column stresses Building 2 24

25 25 Localised areas of storage leading to high imposed loads being applied to the structure

26 In a number of locations in Building 2 there are areas of storage leading to significant imposed loads being applied to the structure. A suitably qualified Structural Engineer should confirm the capacity of the structure and produce loading plans showing the maximum allowable imposed load. First floor (used by Sisal Apparel Ltd.) Fourth floor (used by Apparel Four Ltd) 26 High imposed floor loads Building 2

27 27 Inconsistent and missing record information

28 There are inconsistencies between the as-built structural drawings and the structure that was inspected as highlighted below. The spans measured on site differ from dimensions shown on the as built structural drawings. In some areas the slab cantilevers which is not shown on the record information. The stair to the rear of the building is offset from the column grid as shown. Inconsistent and missing record information Building 1 The column sizes shown on the record information do not match the sizes measures on site. Internal columns are shown as C4 (300mm x 660mm). On site these columns were measured as 380mm x 250mm. 28

29 The two storey structure supporting the antennas on the roof and the antennae themselves are not shown on permit or structural drawings. A suitably qualified structural engineer should confirm that there is sufficient capacity in the structure supporting the unpermitted development. Detailed as-built information should be produced. 29 Inconsistent and missing record information Building 1

30 Original Extension Permit drawing There are no structural drawings for the original portion of Building 2, drawings are only available for the recent horizontal extension. The permit drawing is for a proposed commercial building Structural drawing Inconsistent and missing record information Building 2 30

31 31 Cantilevering half landing

32 The half landing of the stair at the back of Building 1 appears to cantilever in both directions from the column that is supporting it. The design of the half landing and column should be checked for patterned imposed loads under crowd loading (i.e. during evacuation in an emergency). At higher levels it is possible that the masonry wall between the stairwell and main floor plate is providing some vertical support. Ground floor View from inside stairwell. Cantilevering half landing Building 1 32

33 33 Beam depths vary between floors in Building 2

34 The depth of the edge beam varied between the 3 rd and 2 nd floor in Building 2, there is no information showing the depth the beam was designed to be. A suitably qualified Structural Engineer should confirm that the shallower beam at second floor has sufficient capacity to support the loads applied to it. Third floor Second floor Varying beam depths Building 2 34

35 35 Hairline cracking observed in beams and slab soffits

36 Cracking in beams was observed at underside of 4th floor and roof slabs. Flexural cracking was observed from the third floor (soffit of fourth floor slab Cracks to be reviewed by removing plaster to confirm that they do not extend into RC structure. If cracks are reflected in the structure, crack widths to be monitored. A suitably qualified Structural Engineer should be consulted if crack widths increase. Cracks in beams and slabs Building 1 36

37 37 Priority Actions

38 Problems Observed ITEM 1 - High stress in columns. ITEM 2 - Localised areas of storage leading to high imposed loads being applied to the structure. ITEM 3 - Inconsistent and missing record information ITEM 4 - Cantilevering half landing ITEM 5 - Beam depths vary between floors ITEM 6 - Hairline cracking observed in beams and slab soffits 38

39 Item 1 and actions High column stresses verify concrete strength in columns Priority 1 (Immediate - Now) Priority 2 (within 6-weeks) Priority 3 (within 6-months) Drain water tank on Building 1. Alternative temporary water tanks may be located on the roof. Suitable locations should be determined by a suitably qualified Structural Engineer. Remove loading from area highlighted in the attached sketch in Building 2. In Building 1 and Building 2 limit floor loading to 2kPa maximum on all floors above ground floor.support each floor down to a firm foundation in area shown overleaf, this may be achieved by propping the area concerned. Qualified Structural Engineer to review design, loads and stresses in all columns as part of a Detailed Engineering Assessment (DEA) (see scope below). Verify in-situ concrete strength by testing 100mm diameter cores taken from 4 no. columns (minimum). Qualified Structural Engineer to determine safe locations for coring. Prior to coring, the floor beams supported by the column should be propped through all levels to ground floor. The column reinforcement should be exposed to ensure that it will not be damaged during coring. Following coring, the column should be repaired using suitable repair mortar before de-propping the floor beams. Detailed Engineering Assessment to be completed. Provide calculations showing the structural adequacy of all columns. Provide results of concrete strength tests. Develop remediation measures as required by findings of DEA. Produce and actively manage a loading plan for all floor plates within the factory giving consideration to floor capacity and column capacity. Continue to implement load plan 39

40 Detail Engineering Assessment This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment. The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team. We expect that the following will be carried out: 1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions, levels, foundations and framing on Plan, Section and Elevation drawings. 2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made. 3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed. 4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied. 5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated loads. 6. The Engineering team will prepare an assessment report that covers the following: As-Built drawings including Plans at each level calling up and dimensioning all structural components Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the structure Highlight any variation between As-built compared to the designed structure Results of testing for strength and materials Results of geotechnical assessment and testing/investigation Details of loading, inputs and results of computer modelling Commentary on adequacy/inadequacy of elements of the structure Schedule of any required retrofitting required for safety or performance of Structure Any proposals for Retrofitting to follow guidance developed in the Tripartite Document 40

41 Executive summary (Continued) Area where immediate actions are required for Building 1 Storage loading and all other loads must be managed to ensure that a maximum load of 2kPa is not exceeded on any floor above Ground Floor. Water tank to be drained 41

42 Executive summary (Continued) Area where immediate actions are required for Building 2 42 The toilets may continue to be used but all loading must be removed from the area shown shaded at all levels above Ground Floor Storage loading and all other loads must be managed to ensure that a maximum load of 2kPa is not exceeded at any floor above ground floor.

43 Item 2 and actions Areas of localised high storage loads Priority 1 (Immediate - Now) None required. Priority 2 (within 6-weeks) Suitably qualified Structural Engineer to confirm capacity of structure supporting storage areas in Building 1 and 2 and to produce plans showing maximum allowable floor loads. Priority 3 (within 6-months) Continue to implement load plan. 43

44 Item 3 and actions Inconsistent and missing record information Priority 1 (Immediate - Now) Priority 2 (within 6-weeks) Priority 3 (within 6-months) None required As part of DEA (see Item 1) a suitably qualified Structural Engineer is to confirm that as-built structure has sufficient capacity, particularly areas that differ from as-built structural information e.g. undocumented cantilevers, columns that are smaller than shown on drawings. Suitably qualified engineer to confirm that there is sufficient capacity in the structure supporting the unpermitted antennae support structure. Suitably qualified engineer to confirm that foundation type for Building 2. Engineer should also confirm that foundations have sufficient capacity for the applied loads. Suitably qualified structural engineer to check, collect information and produce accurate and complete as-built documentation as soon as possible. 44

45 Item 4 and actions Cantilevering half landing in rear stair of Building 1 Priority 1 (Immediate - Now) None required Priority 2 (within 6-weeks) Suitably qualified engineer to check capacity of cantilevering half landing and column at ground floor in Building 1. Particular attention should be given to patterned crown loading (e.g. during an evacuation) Priority 3 (within 6-months) None required 45

46 Item 5 and actions Varying edge beam sizes between 2 nd and 3 rd floor in Building 2 Priority 1 (Immediate - Now) None required Priority 2 (within 6-weeks) A suitably qualified engineer should confirm that the shallower beam at second floor has sufficient capacity to support the loads applied to it. Priority 3 (within 6-months) None required 46

47 Item 6 and actions Hairline cracks in beams and slabs in various locations. Priority 1 (Immediate - Now) Priority 2 (within 6-weeks) Priority 3 (within 6-months) None required. Sections of plaster finish to beams to be removed to investigate if cracks penetrate the building structure. As part of DEA for Item 1, Building Engineer to carry out design check on beams to confirm that these cracks are non-structural. Building Engineer to prepare allowable floor loading plans. None required. 47

48 Survey Limitations and Assumptions This report is for the private and confidential use of Accord for whom it was prepared together with their professional advisors as appropriate. It should not be reproduced in whole or in part or relied upon by third parties for any use without the express written permission of Arup. This report can be used in discussion with the supplier or factory owner as a means to rectify or address any observations made. The report is not comprehensive and is limited to what could be observed during a visual inspection of the building. This Report is not intended to be treated as a generalised inspection and does not cover the deterioration of structural members through dampness, fungal or insect attack, nor does it deal with problems and defects of a non-structural nature. Other non structural aspects of the building such as fire safety have not been assessed in this survey. Except as otherwise noted, drains and other services were not viewed or tested during our inspection and are therefore similarly excluded from this Report. We have not inspected any parts of the structure which are covered, unexposed or inaccessible and we are therefore unable to report that any such part of the property is free from defect. External inspection of the façade walls has generally been carried out from ground level only by visual sighting. No opening up works were carried out (except as noted) and we rely on the Architects and Engineers drawings provided to us for our views on concealed parts of the structure and in particular foundations. Strengths of materials and components are untested and we recommend that the factory owners Building Engineer carries out insitu testing over and above those suggested to satisfy themselves with the material strengths and component details. Recommendations, where given, are for the purpose of providing indicative advice only, are not exhaustive, relate solely to identifying key and obvious structural defects as identified in this presentation, and do not take the form of or constitute a specification for works. We take no responsibility for the works as constructed. This report does not interfere with the factory owners Building Engineers responsibility for the structural performance of this building, The Building Engineer remains fully responsible for the structural adequacy of the building. This report does not comment in detail on the future seismic performance of the building and only highlights the fact that the building may experience significant damage or collapse in a seismic event along with many others in the Dhaka region. The observations in this report are based on the Engineering Judgement of the lead surveyor/engineer at the time of the survey. We assume in making these observations that no covering up of faults defects, filling or plastering over cracking or significant repair work has been carried out by the building owner. Any future alteration or additional work by the building owner will void this report. 48

ASHULIA APPARELS LTD. Client Summary Report

ASHULIA APPARELS LTD. Client Summary Report Revision : Issue 1 Date: 18 March 2014 ASHULIA APPARELS LTD Samad Mansion, Sec # 6, Block # kha, Road No# 1, Plot #14, Shenpara Parbata, Mirpur, Dhaka (23.8065N,90.3683E) 4th March 2014 Client Summary

More information

Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland

Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,

More information

Fame Design Ltd (10295) Plot # A-115/116,BSCIC Hosiery I/A, Narayangonj, Bangladesh (+ 23.623412, +90.478442) 18.June.2014

Fame Design Ltd (10295) Plot # A-115/116,BSCIC Hosiery I/A, Narayangonj, Bangladesh (+ 23.623412, +90.478442) 18.June.2014 Fame Design Ltd (10295) Plot # A-115/116,BSCIC Hosiery I/A, Narayangonj, Bangladesh (+ 23.623412, +90.478442) 18.June.2014 Identified Priority 1 Concerns 1 st Priority 1 Concern This column was checked.

More information

Structural Audit of Buildings

Structural Audit of Buildings International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 4 (2014), pp. 411-416 Research India Publications http://www.ripublication.com/ijcer.htm Structural Audit of Buildings

More information

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline

More information

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,

More information

PERIODIC STRUCTURAL INSPECTION OF EXISTING BUILDINGS GUIDELINES FOR STRUCTURAL ENGINEERS

PERIODIC STRUCTURAL INSPECTION OF EXISTING BUILDINGS GUIDELINES FOR STRUCTURAL ENGINEERS PERIODIC STRUCTURAL INSPECTION OF EXISTING BUILDINGS GUIDELINES FOR STRUCTURAL ENGINEERS Jan 2012 CONTENTS GENERAL... 1 1 Background... 1 2 Qualifications and Expectations of Structural Engineers... 1

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT Property Inspection 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT March 2013 This document has been prepared for the benefit of Clint Marston. No liability is accepted by this company

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

Re: Damages to Alaska Building from Legislative Information Office Construction

Re: Damages to Alaska Building from Legislative Information Office Construction 510 L Street Suite 200 Anchorage, AK 99501-1949 (907) 274-22362236 Phone (907) 274-25202520 Fax www.bbfm.com July 22, 2015 Jim Gottstein Alaska Building 406 G Street, Suite 206 Anchorage, AK 99501 Re:

More information

BROWNSVILLE STRUCTURES STUDY. July 2012. Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208

BROWNSVILLE STRUCTURES STUDY. July 2012. Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208 BROWNSVILLE STRUCTURES STUDY July 2012 Prepared by LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208 TABLE OF CONTENTS I. SUMMARY OF BUILDING ANALYSIS.. 1 II. INDIVIDUAL BUILDING

More information

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,

More information

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael

More information

Technical Notes 3B - Brick Masonry Section Properties May 1993

Technical Notes 3B - Brick Masonry Section Properties May 1993 Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications

More information

Photos showing the change in condition from 2006 to 2012 are located in Appendix A.

Photos showing the change in condition from 2006 to 2012 are located in Appendix A. January 27, 2012 Ms. Theresa Gallavan Economic Development Director City of Lompoc 100 Civic Center Plaza Lompoc, California 93436 RE: Lompoc Theater Limited Visual Condition Assessment Dear Theresa: Representatives

More information

Chapter. Earthquake Damage: Types, Process, Categories

Chapter. Earthquake Damage: Types, Process, Categories 3 Chapter Earthquake Damage: Types, Process, Categories Earthquakes leave behind a trail of damage and destruction. People s lives are affected by the loss of loved ones, destruction of property, economic

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

Building Foundation and Structure

Building Foundation and Structure Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original

More information

14 September 2015. Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102

14 September 2015. Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102 Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102 Project No.: 15538.00 Re: Structural Condition Review of the building at 700 4 th St. E. Dear Sarah: We

More information

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona Project Report Structural Investigations Yuma, Arizona Prepared by: 2619 Spruce Street Boulder, CO 80302 303-444-3620 Prepared for: Principle Engineering Group, Inc. 833 East Plaza Circle, Suite 100 Yuma,

More information

How To Build A Luxury Apartment Complex In London

How To Build A Luxury Apartment Complex In London Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

Design and Construction of Cantilevered Reinforced Concrete Structures

Design and Construction of Cantilevered Reinforced Concrete Structures Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures

More information

HOUSE BUILDING DIGEST

HOUSE BUILDING DIGEST HOUSE BUILDING DIGEST (Construction Specifications-Foundations) Creating Enabling Environment for Affordable Housing for All This is an attempt by BMTPC to provide useful but often ignored information

More information

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,

More information

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma Bart B. Barrett, B.S., P.E.1 Kerry S. Lee, M.B.A., P.E., M. ASCE2 Erik L. Nelson, Ph.D., P.E., M. ASCE3

More information

Residential Decks. Planning and Development Services Department

Residential Decks. Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Planning and Development Services Department Residential Decks

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

6 RETROFITTING POST & PIER HOUSES

6 RETROFITTING POST & PIER HOUSES Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This

More information

ASSESSMENT AND RETROFITTING OF EXISTING RC BUILDINGS IN VIETNAM IN TERMS OF EARTHQUAKE RESISTANCES

ASSESSMENT AND RETROFITTING OF EXISTING RC BUILDINGS IN VIETNAM IN TERMS OF EARTHQUAKE RESISTANCES GEM-SEA Workshop on Seismic Vulnerability of Buildings Nanyang Technological University, Singapore 1 st July 2013 ASSESSMENT AND RETROFITTING OF EXISTING RC BUILDINGS IN VIETNAM IN TERMS OF EARTHQUAKE

More information

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

Structural Assessment Report

Structural Assessment Report Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive

More information

Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By

Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By Project Structural Conditions Survey and Seismic Vulnerability Assessment For SFCC Civic Center Campus 750 Eddy Street San Francisco, California 94109 Prepared For San Francisco Community College District

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

Post Earthquake Quick Damage Inspection of Buildings in Nepal

Post Earthquake Quick Damage Inspection of Buildings in Nepal Post Earthquake Quick Damage Inspection of Buildings in Nepal Collaborative Research and Development (R&D) Project for Disaster Mitigation in Earthquake Prone Areas in Asia (Sep 27, 2007) Presented By

More information

Simplifying design and construction. Alan Tovey, Director The Basement Information Centre

Simplifying design and construction. Alan Tovey, Director The Basement Information Centre Simplifying design and construction Alan Tovey, Director The Basement Information Centre Simplifying design and construction Grades of construction Construction options Design and waterproofing issues

More information

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA College of Marin c/o Swinerton Management & Consulting P.O. Box 144003 835 College Avenue, Building MS-3 Kentfield, California

More information

PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007

PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007 PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT November 2007 PURPOSE OF INVESTIGATION Determine possible locations of moisture intrusion into and through facade. Determine cause of horizontal and vertical

More information

Requirements for Building Application Submission

Requirements for Building Application Submission THE DEVELOPMENT CONTROL AND PLANNING BOARD P O Box 597 Phone: 869 465-2277 Bladen Commercial Development Fax: 869 465-5842 Basseterre, St. Kitts Email: phyplskb@caribsurf.com To: Architects, Designers

More information

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com, 2011 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,

More information

19.1 Overview...19.1 19.2 Repair or replace...19.1 19.3 Relevelling... 19.3

19.1 Overview...19.1 19.2 Repair or replace...19.1 19.3 Relevelling... 19.3 GUIDANCE E CONTENTS Part E: Repairing and rebuilding multi-unit residential buildings Contents 17. Introduction 17.1 17.1 Background...17.1 17.2 Scope...17.2 17.3 General principles...17.4 17.4 Regulatory

More information

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems: Reading Assignment SLAB DESIGN Chapter 9 of Text and, Chapter 13 of ACI318-02 Introduction ACI318 Code provides two design procedures for slab systems: 13.6.1 Direct Design Method (DDM) For slab systems

More information

Chapter 2 Basis of design and materials

Chapter 2 Basis of design and materials Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural

More information

Engineers, Civil Structural Survey

Engineers, Civil Structural Survey Engineers, Civil Structural Survey 317 STREET 0 6 3 6 0 886-1966 886-9165 FAX. September 1 1 Mr. Alan Bergren City Manager City of Norwich Broadway, Floor Norwich, 06360 Re: Limited Structural Condition

More information

Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas 77089. August 30, 2012. Prepared for:

Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas 77089. August 30, 2012. Prepared for: A Full Service Real Estate Inspection & Engineering Firm for Houston, Texas 77089 August 30, 2012 Prepared for: CLIENT S NAME MAILING ADDRESS Houston, Texas 77089 Prepared by: Charles J. Jenkins, P.E.

More information

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia DESIGN OF SLABS Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia Introduction Types of Slab Slabs are plate elements

More information

CHAPTER 2 QUANTITY TAKE-OFF

CHAPTER 2 QUANTITY TAKE-OFF CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate

More information

9.8.1.1. General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and guards.

9.8.1.1. General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and guards. Section 9.8. Stairs, Ramps, Handrails and Guards 9.8.1. Application 9.8.1.1. General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Wednesday, August 20, 2014 Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website:

More information

INSPECTION PROPERTY ADDRESS: Fort Bend County, Texas

INSPECTION PROPERTY ADDRESS: Fort Bend County, Texas 5006 Cherry Ridge Road Richmond, Texas 77406 281-342-9944 harris31@sbcglobal.net INSPECTION PROPERTY ADDRESS: INSPECTION PERFORMED FOR: XXXX Drive Fort Bend County, Texas Mr. and Mrs. New Construction

More information

DESIGN OF BLAST RESISTANT BUILDINGS IN AN LNG PROCESSING PLANT

DESIGN OF BLAST RESISTANT BUILDINGS IN AN LNG PROCESSING PLANT DESIGN OF BLAST RESISTANT BUILDINGS IN AN LNG PROCESSING PLANT Troy Oliver 1, Mark Rea 2 ABSTRACT: This paper provides an overview of the work undertaken in the design of multiple buildings for one of

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

National Home Builder - Name Wednesday, August 20, 2014 Regional Customer Care Manager 1234 Main Street Houston, Texas 77067

National Home Builder - Name Wednesday, August 20, 2014 Regional Customer Care Manager 1234 Main Street Houston, Texas 77067 Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com

More information

March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202

March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request

More information

Certification: Building Plans Examiner. Exam ID: B3

Certification: Building Plans Examiner. Exam ID: B3 Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building

More information

Chapter. Restoration of Damaged Structures

Chapter. Restoration of Damaged Structures 5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

Detailing of Reinforcment in Concrete Structures

Detailing of Reinforcment in Concrete Structures Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For

More information

Vision Home Inspection

Vision Home Inspection Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the

More information

4.3.5 - Breakaway Walls

4.3.5 - Breakaway Walls 4.3.5 - Breakaway Walls Elevation of a structure on a properly designed foundation reduces the potential for water damage from flooding. When the space below the lowest elevated floor is maintained free

More information

SECTION 7: C - STRUCTURAL ENGINEERS SPECIFICATIONS

SECTION 7: C - STRUCTURAL ENGINEERS SPECIFICATIONS SECTION 7: C - STRUCTURAL ENGINEERS SPECIFICATIONS SITE C SHOPPING CENTRE, KHAYELITSHA PROJECT NO 2369 Project Specification Refer all queries to: John Meiring Tel: +27 21 425 0065 REVISION P01 E-mail:

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

G. Common Defects in Buildings - Leakage

G. Common Defects in Buildings - Leakage F. Common Defects in Buildings - Structural 32. Recently, some concrete chips have fallen from the ceiling in my kitchen. There are rusty steel bars and the area in question measures about 300 x 400mm.

More information

Metropolitan Builders Association Masonry & Concrete Standard

Metropolitan Builders Association Masonry & Concrete Standard Metropolitan Builders Association Masonry & Concrete Standard Background Masonry and concrete work in residential construction often provides the base structure upon which the house is built or as a veneer.

More information

Commercial Building Valuation Report

Commercial Building Valuation Report INSURED University of Houston - Victoria Effective Date: Expiration Date: Cost as of: 09/2010 BUILDING 1 217 - University Center 77901 Location Adjustments Climatic Region: High Wind Region: Seismic Zone:

More information

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057 Lecturer: Jim Cahill 29 th November 2011 TABLE OF CONTENTS SUMMARY 1 MAIN BODY SECTION

More information

October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.

October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr. 117 S. Market St. Benton, AR 72015 * 501-315-2626 * Fax 501-315-0024 October 30, 2014 Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR Re: Report of Findings,, Benton, Arkansas, Dear Mr. Vick: This

More information

Reference: BRM-00220488-A0 July 18 th, 2014. Cursory Visual Review of Various Below Grade Spaces and Exposed Foundation Walls

Reference: BRM-00220488-A0 July 18 th, 2014. Cursory Visual Review of Various Below Grade Spaces and Exposed Foundation Walls Reference: BRM-00220488-A0 July 18 th, 2014 Toronto Catholic District School Board 80 Sheppard Avenue East Toronto, Ontario M2N 6E8 Re: 1.0 Introduction Exp Services Inc. (exp) was retained by the Toronto

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE Multi-storey Precast Concrete Framed Structures Kim S. Elliott BTech, PhD, CEng, MICE Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE WI LEY Blackwell Contents Preface Notation Precast Concepts, History

More information

DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES

DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES WBCA 403 DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES A guide to assist those intending to install or who are involved in installing conservatories. Includes information about: conservatory and component

More information

Optimum proportions for the design of suspension bridge

Optimum proportions for the design of suspension bridge Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering

More information

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar, Volume, Special Issue, ICSTSD Behaviour of Steel Bracing as a Global Retrofitting Technique Miss S. S. Nibhorkar M. E (Structure) Scholar, Civil Engineering Department, G. H. Raisoni College of Engineering

More information

4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections. Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls

More information

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)

More information

Current Status of Seismic Retrofitting Technology

Current Status of Seismic Retrofitting Technology CONTENTS Current Status of Seismic Retrofitting Technology Damages of Past Earthquakes Seismic Diagnosis Method Building Control Section Urban Building Division Bureau of Urban Development, TMG Seismic

More information

Uncovered Decks & Porches

Uncovered Decks & Porches Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed

More information

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3279 SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP Yuming DING 1, Bruce HAMERSLEY 2 SUMMARY Vancouver

More information

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION -SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION -Unit number- 4420798 -Unit title- CONSTRUCTION TECHNOLOGY 2: SUBSTRUCTURE AND REMEDIAL WORKS -Superclass category-

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

Code of Standard Practice for Timber Frame Structures

Code of Standard Practice for Timber Frame Structures TFEC 2-2013 Code of Standard Practice for Timber Frame Structures August 2013 Preface This Code is intended to represent a reasonable consensus of what constitutes ordinary and acceptable practice within

More information

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab, DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared

More information

Basic Requirements for Residential Plan Review _

Basic Requirements for Residential Plan Review _ Basic Requirements for Residential Plan Review _ Below you will find the basic requirements for your plan submittal. General: Drawn to scale Plan Size minimum: 9 x 12 Designer, Engineer, or Architect name,

More information

PROJECT COST ESTIMATES & FEASIBILITIES

PROJECT COST ESTIMATES & FEASIBILITIES PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed

More information

9.3 Two-way Slabs (Part I)

9.3 Two-way Slabs (Part I) 9.3 Two-way Slabs (Part I) This section covers the following topics. Introduction Analysis and Design Features in Modeling and Analysis Distribution of Moments to Strips 9.3.1 Introduction The slabs are

More information

WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204

WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204 WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204 Structural Inspection Report Client: CSArch Architecture Engineering Construction Management 19 Front Street, Newburgh,

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

THE STAR, DARLING HOTEL AND SPA PYRMONT, NSW. Associate Director, Taylor Thomson Whitting Ltd, Sydney, Australia

THE STAR, DARLING HOTEL AND SPA PYRMONT, NSW. Associate Director, Taylor Thomson Whitting Ltd, Sydney, Australia THE STAR, DARLING HOTEL AND SPA PYRMONT, NSW H Nguyen BE (Hons), CPEng MIEAUST NPER Associate Director, Taylor Thomson Whitting Ltd, Sydney, Australia ABSTRACT The redevelopment at The Star in Sydney includes

More information

BELL ASSOCIATES ARCHITECTURE PLANNING

BELL ASSOCIATES ARCHITECTURE PLANNING BELL ASSOCIATES ARCHITECTURE PLANNING Roger Bell dip. arch. tech. Bsc. CAD Rogerstown, Rush, Co. Dublin. Muchgrange, Greenore, Co. Louth E bellassociates@eircom.net T 01-8430267 T 042 938 3865 M 087 2371984

More information

423 NORTH HOWARD ST. VISUAL STRUCTURAL ASSESSMENT

423 NORTH HOWARD ST. VISUAL STRUCTURAL ASSESSMENT Urgent Needs II City of Baltimore No. 1099 423 NORTH HOWARD ST. 423 North Howard Street (circa 1880) is a multi-story building constructed second in row south of Franklin Street and between the vacant

More information

RESIDENTIAL WOOD DECKS

RESIDENTIAL WOOD DECKS RESIDENTIAL WOOD DECKS 1 A Building Permit is required for the construction of a wood deck where the deck is more than 600 mm above grade at any point. Definition: For the purposes of this pamphlet, a

More information

How To Repair A House

How To Repair A House Assessing Structural Damages Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides

More information

STRUCTURAL ASSESSMENT

STRUCTURAL ASSESSMENT STRUCTURAL ASSESSMENT Project: 1432-1434 East Commerce St. Job. No: 122200 Location: San Antonio, TX Date: Dec. 10, 2012 Weather: Sunny, Windy,60 deg Performed by: Jeff Haughton and Frank Lamas, Alpha

More information

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS Johnson County Building Officials Association January 2008 Residential Foundation Guideline Foundation designs for one-and two-family dwellings may use

More information