1 TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09 PMT GUIDE # 10 Book of Order Section G o: "The session is responsible for the mission and government of the particular church. It therefore has the responsibility and power...to provide for the management of the property of the church, including determination of the appropriate use of church buildings and facilities, and to obtain property and liability insurance coverage to protect the facilities, programs, and offices, including members of the session, staff, board of trustees, and deacons." PURPOSE OF THIS GUIDE To review existing masonry parapet walls and related flat roof systems of existing church structures in consideration of maintenance and repair to insure their integrity. INTRODUCTION Parapet walls and associate roof systems are generally out of sight/out of mind. Unfortunately these components receive the most serious consequences of constant exposure of temperature ranges, wind, rain, and freeze/thaw cycles. In general terms, roofing systems will be more likely the source of building leaks than parapets. Comments in this guide relating to roofing/flashings to parapet walls apply in general to all flat roofs. This memorandum assumes traditional solid masonry wall construction only. Selection of products and systems for a particular project is a mutual responsibility of church personnel, qualified masons and roofing contractors and consultants as may be appropriate. INSPECTIONS Parapets and roofing systems should be inspected either by church personnel and/or by qualified contractors as follows: 1) In the fall after leaves have fallen to insure a clean system for winter. 2) In the spring to review for any damage due to winter exposure. The timing is important to allow for repairs, if required, prior to the next winter season. 3) When inspecting roof systems, wear flat-soled shoes for safety and to avoid making any roof penetrations. Do not step on any roof blisters. Penetration of these areas will promote roof leaks. 4) Except for emergency situation, inspections should be avoided during winter months due to icing conditions of roofs. It is recommended not to remove snow/ice due to risk of damage to roofing/flashing systems promoting leaks and, more importantly, the risk of injury to inspecting personnel. 5) Should serious defects be observed (e.g. bowed or out-of-plumb walls or rotted decking), consideration should be given to retaining professional consultants and/or qualified masons/roofers for resolution and repair/restoration. 6) Parapets and roofs, depending on the building s accessibility, may be difficult to inspect. Church personnel may not be comfortable or able to manage ladders and access to higher places. Contractors are accustomed to these situations and have the appropriate equipment for property access. Recommendation: if in doubt, retain the contractor. Safety first! 7) In consideration of access difficulty, the use of digital cameras, with zoom capability, is recommended, both for church personnel and retained contractors, and consultants. The use of cameras is an excellent means by which to examine parapet/roofing conditions and to record a maintenance and repair history of these building elements. Guide 10 - Page 1 of 3
2 8) As a matter of coordination, PMT GUIDE #5 is an appropriate reference for overall building interior and exterior maintenance checklist and for establishing of a building maintenance program PARAPETS 1) Copings: Serve to direct water from the top of parapet walls. Materials such as stone, clay tile and brick are thermally compatible with masonry walls. Coping tops must slope and project beyond parapet wall faces with drip notches for proper water runoff. The fewer unit joints the better. Brick coping are therefore more susceptible to moisture penetration. Due to temperature differentials of exposure, coping joints tend to open up and should be re-sealed with flexible sealants to prevent water intrusion. Metal copings with drip edges have fewer joints but require expansion joints. 2) All copings require a base flashing continuous at the top of the masonry wall to prevent water penetration into the wall system. For low parapets (e.g. about 12 or less in height), the flashing is usually a continuation of the roofing base flashing. In the case of tall parapets, an independent membrane, e.g. sisalkraft, would be used extending the edges of the flashing beyond the wall faces to provide drip edges to divert water from the face of masonry. Flashing selection must be resistant to puncture and UV deterioration. Asphalt-impregnated felt and plastics tend not to meet these criteria. 3) Parapet walls: Are solid masonry construction, and are a vertical extension of the building wall systems. Evidence of moisture and freeze/thaw penetration includes loose and/or open mortar joints, spalled unit faces, loose masonry units and efflorescence. Defective joints require removal of material and re-pointing with new mortar. Existing surface tuck-pointing of in-place joints probably hides defective joints, and is not an effective tuck-pointing technique. Remove and replace mortar joints to a depth at least equal to the width of the joint. Replace cracked and/or chipped masonry wall and coping units. All replacement units to be in kind or original units. 4) As general recommendation, avoid sealing the exterior faces of masonry walls to resist moisture penetration. The wall system naturally will accept and must be able to evaporate moisture. Retention of moisture within the wall system could be a factor in promoting mold growth. If a wall sealant is selected, it must allow moisture to escape. 5) A final thought on parapet walls and copings: Delayed or forgotten maintenance of these components promotes the potential intrusion of excessive moisture that, over a period of time, will cause damage to masonry unit(s) and wall integrity and will be a contributing factor of rusting and spalling of steel lintels particularly over wall openings (windows, doors) in the floor directly below the roof system. Repair/removal and restoration of the wall system, together with associated roofing and flashing systems will be costly; maintain a program of timely inspections and maintenance. ROOFING SYSTEMS 1) Drainage: This guide discusses flat roofs in relationship to parapets. The roof should drain down positively either to related gutters, interior roof drains or roof drains at the vicinity of the interior face of the parapet or by scuppers penetrating the wall to exterior downspouts. All drains should be maintained clear to maintain drainage flow. In many cases, the size of drains or scuppers may be undersized, requiring clearing openings. The units should have their top (invert) level lower than the adjacent roof to insure positive drainage. If such is not the case, the units should be correctly modified. Existing scuppers may have a raised edge at the roof, blocking drainage. If such is the case, providing a weir notch to the roof level may be appropriate. 2) Roofing repairs: Roofing inspection by church personnel and/or by a roofing contractor should include the general aging condition of the roofing and flashing, blister, cracking, differential movement, ponding, penetrations and ballast (gravel or other weighty materials) continuity. Repairs should be by qualified roofing contractors. Some form of record-keeping of repairs is recommended to plan ultimately for roof/flashing replacement. Guide 10 - Page 2 of 3
3 3) Roofing replacement: If the decision is reached to replace a roofing system, the present roofing should be cored to determine the number and type of layers already in place. This is important as building departments are now allowing a new system to be installed only over one in-place layer. More than one layer will probably require the removal of the existing roofing to the structural deck. Additionally, building departments may require the installation of insulation (R-19 or as specified) prior to roofing installation, thereby affecting modification to present structures (e.g. drains, scuppers) to accept the new increased roof thickness. Selected roofing systems and their compatible base flashing is a determination to be made by the church, roofing contractor and any consultant as may be appropriate. A 20-year system is recommended. Examples include but are not limited to the following: a) Modified, NO TORCH b) Adhesive, hot asphalt c) Single-ply FLASHINGS 1) All base flashing sealing the roofing system to parapet walls must be compatible with the roofing system selected. Ideally, the flashing should extend up the full height of the parapet wall and over the wall top to develop a single system. If the parapet wall is high, the base flashing should extend a minimum of 8 and preferably 12 above the roofing level. Depending on the roofing system, cant (angled) strips at the wall base may or may not be required. Flashings that do not extend the full wall height have the top edge counter-flashed with thru-wall metal flashing or termination bar. 2) Metal flashing components should be selected for a 20-year life to match that of the roofing system. Copper minimum thickness is.032 inches. Aluminum (for copings, termination bars) is minimum of.040 inches and should be anodic-coated. Galvanized sheet metal is more subject to rusting within 2 to 3 years. Metal flashing integral to the roofing system should be replaced at the time of roofing replacement. 3) While the discussion of this guide stresses base flashings to parapets for flat roofs, the same principles apply to sloped roofs (e.g. metal, slate or shingle surface) that pitch down to parapet walls. Drainage must be positive as described in paragraph #1 of ROOFING SYSTEMS. Base flashings should extend a minimum of 12 up and under pitched roof roofing materials. 4) Differences of opinion exist within the building trades and professional consultants as to whether the backside of parapets should allow some exposed masonry above base flashing to assist in moisture evaporation of the wall system. As described in this guide, low heights (maximum 12 high) in height are usually continuous with base flashing to the coping, while taller walls have flashings terminating approximately 12 above roof height with separate coping flashings High wall flashing have a potential of separating from the wall thereby promoting leak potential. REFERENCE PHOTOGRAPHS The enclosed photographs define examples of roofing and parapet failures, and are submitted as general references for evaluation and comparison to a particular church/building needs and conditions. In addition, for those interested in background information on design of parapets (not for do-ityourselfers), please click on PMT Publications Detailing masonry parapets by Walter Laska. Updated 11/23/09 Guide 10 - Page 3 of 3
4
5
Commercial Roof Inspection Form
Inspection Date: Inspector: Building Information Building ID: No.: Used For: Year Roof Applied: Building Description: Permanent Temporary Building Type: Retail Industrial Residential Building Name: Building
UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Architectural. Roofing. Basis of Design
Basis of Design This section applies to roofing membranes, flashing and accessories. Design Criteria Adhere to the standards and details of the latest editions of the National Contractors Association (NRCA)
ROOF INSPECTION & MAINTENANCE
Physical Plant Administration Facilities Maintenance Department ROOF INSPECTION & MAINTENANCE All roofs require periodic inspection and maintenance in order to perform as designed and to provide a long
TARRANT COUNTY DETAIL STANDARDS
TARRANT COUNTY DETAIL STANDARDS 1. Standard Coping 2. Coping at End Wall 3. Standard Sheet Metal Engagement Details 4. Gravel Guard 5. Gravel Guard Wall Termination 6. Gravel Guard, Gutter, and Downspout
Commercial Roof Management
Disclaimer: This material is designed and intended for general informational purposes only, and is not intended, nor shall it be construed or relied upon, as specific legal advice. Roof damage is a leading
Water Damage & Repair
Water Damage & Repair Chinatown Preservation Talks 2015 James Engler, P.A Glenn Mason, AIA Mason Architects Program Outline Terminology & Waterproofing Basics Discussion of why this is important Below
SELF-INSPECTION CHECKLIST Maintain Your Roof and Identify Potential Issues With Bloom s Comprehensive Self-Inspection Guide
SELF-INSPECTION CHECKLIST Maintain Your Roof and Identify Potential Issues With Bloom s Comprehensive Self-Inspection Guide Inspection Questions? Call Bloom At 800-483-9932 www.bloomroofing.com DISCLAIMER
Asphalt Shingle Application Requirements
Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt
Bituminous Sheet Flat Roofs: Their repair and maintenance
Bituminous Sheet Flat Roofs: Their repair and maintenance Flat roof covered in sheets of bituminous felt Introduction Whilst flat roofs are often regarded as inferior to their pitched counterparts and
NEW ELECTRICAL SUBSTATION Building 300 SECTION 07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK
ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
Winterizing Your Building
Winterizing Your Building DEC Author: Steven J. Susca This article was originally published in the Hoffmann Architects Journal in Issue 3, 2009. As spring thaws uncover the ravages winter weather has wreaked
ROOFS - Guidance for Repair, Maintenance and Replacement
ROOFS - Guidance for Repair, Maintenance and Replacement Guilford Association Architectural Committee ROOFING Slate and tile roofs are a critical design feature of Guilford homes. The homes were designed
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
Roof. Walking on roofs
Roof The roof cannot be adequately evaluated during dry weather, especially during a hot, dry summer. Consequently, roof problems might not be detected at the time of the inspection and might not be able
Roofing Systems. There are many different systems, each with it's own special requirements and benefits. Browse through all the options below.
Roofing Systems There are many different systems, each with it's own special requirements and benefits. Browse through all the options below. BUR (Built-Up Roofing) Built-Up-Roofing, BUR is a roof that
APPLICATION INFORMATION FOR RESIDENTIAL ROOFING AND RESIDENTIAL ROOFING PACKET
Environmental Protection and Growth Management Department PERMITTING, LICENSING AND CONSUMER PROTECTION DIVISION 1 N. University Drive, Box #302 Plantation, Florida 33324 954-765-4400 www.broward.org/permittingandlicensing
Basement Moisture Problems
Foundations Foundation Purpose The purpose of a foundation is to distribute the weight of a structure securely into the ground. Engineering data regarding soil, rock and water conditions are used to design
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry
Vision Home Inspection
Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the
bout your HOUSE before you start Repairing And Replacing Materials Exterior Walls
A bout your HOUSE before you start Repairing And Replacing Materials Exterior Walls CE 28 h Exterior finish materials are expected to protect the house from the elements while providing an attractive appearance.
The Perfect Fit For Metal Retrofit
D u r o - S h i e l d M e t a l R e t r o f i t R o o f i n g S y s t e m The Perfect Fit For Metal Retrofit Lock out leaks. Lock in your investment. Has time caught up with your metal roof? There are
Water Management & Damage Prevention:
Water Management & Damage Prevention: A Guide for Homeowners This article provides homeowners with basic information to make these decisions and take the appropriate actions to keep their homes dry and
Building Owners Guide to a Duro-Last System!
Building Owners Guide to a Duro-Last System Table of Contents Section 1: Introduction to Duro-Last Roofing Systems Section 2: Benefits of a Duro-Last Roofing System Section 3: Comparing a Duro-Last Roof
Inspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com [email protected]
CHAPTER VII. TITLE: STANDARDS FOR NEW ROOFING July 2015 CONSTRUCTION, RE-ROOFING CONSTRUCTION AND ROOFING SYSTEM GUARANTEE REQUIREMENTS
TITLE: STANDARDS FOR NEW ROOFING CONSTRUCTION, RE-ROOFING CONSTRUCTION AND ROOFING SYSTEM GUARANTEE REQUIREMENTS Responsible Organization: Office of Facilities Planning Instructions: This Manual supersedes
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
!!! !!!! !!! !!! !!! !!! !!!!!!!!! Table of Contents! Section 1: Most Common Types of Flat Roofing! Section 2: Better Understand Your Flat Roof!
Table of Contents Section 1: Most Common Types of Flat Roofing Section 2: Better Understand Your Flat Roof Section 3: Flat Roofing Cost in 2015: Four Factors that Dictate Section 4: Planning A Flat Roofing
Waterproofing Problems: A Simple Explanation, A Simple Solution
Waterproofing Problems: A Simple Explanation, A Simple Solution The purpose of this paper is to point out the underlying causes of waterproofing problems and simple means of preventing them. Such problems
SINGLE FAMILY RESIDENCE HURRICANE MITIGATION APPLICATION
SINGLE FAMILY RESIDENCE HURRICANE MITIGATION APPLICATION As of October 1, 2007, this mitigation form must be submitted as part of the roofing permit application package. Secondary water barrier (if applicable)
CITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503. Re-Roofing: Asphalt Shingles
CITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503 Re-Roofing: Asphalt Shingles This is a summary of the standard requirements based on the
PERIMETER FLASHING. Table of Contents
FM Global Property Loss Prevention Data Sheets 1-49 February 1985 Revised September 2000 Page1of25 PERIMETER FLASHING Table of Contents Page 1.0 SCOPE... 3 1.1 Changes... 3 2.0 LOSS PREVENTION RECOMMENDATIONS...
Roof Repair Project Report. Fairbank Complex 40 Fairbank Road Sudbury, Massachusetts. February 14, 2014. RBA Project No. 2014007.00.
Report Fairbank Complex 40 Fairbank Road RBA Project No. 2014007.00 Prepared by: 33 Center Street, 2 nd Floor Burlington, MA Tel: 781-273-1537 Fax: 781-273-1695 TABLE OF CONTENTS Roof Repair Project Report...
SECTION 07 61 13 STANDING SEAM METAL ROOFING
SECTION 07 61 13 STANDING SEAM METAL ROOFING PART 1 GENERAL 1.01 SCOPE OF WORK A. The Work shall include all labor, materials, equipment and supervision required to complete the work of the above referenced
HOME INSPECTION CHECKLIST
CLOSING.COM LEARNING CENTER HOME INSPECTION CHECKLIST CONTENTS Attic 1 Balconies 1 Basement 1 Bathroom 2 Ceiling, Floors and Walls 2 Crawlspace 3 Decks and Porches 3 Doors and Windows 4 Drainage 4 Driveways
Roof Inspection. Summary Report
www.real-estate-inspections.com Roof Inspection Summary Report Subject Property Prepared for: File Number: Client in Detroit 05-15-RF-004 Inspector: Craig Milliken, PE # 32779 CPM Real Estate Inspections,
PETERSONS WATERFRONT CONDOMINIUMS
CONSULT DESIGN CONSTRUCT PETERSONS WATERFRONT CONDOMINIUMS 103 Park Street Chelan, Washington Findings Summary Report Prepared for: Petersons Waterfront Condominium Association March 21, 2014 J2 Project
Final inspections are completed by site visit only. Access to fenced yards shall be planned.
ROOFING RESIDENTIAL BUILDING INSPECTIONS DEPARTMENT www.ci.blaine.mn.us This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building Code, Blaine City ordinances,
Maintenance & Inspection Guide
ADDRESSING THE NEEDS OF OUR CUSTOMERS AND THE ENVIRONMENT ONE high Performance roofing SOLUTION AT A TIME. Maintenance & Inspection Guide TABLE OF CONTENTS Topic: Page: I. Introduction 1 II. Maintenance
Warranty Information TABLE OF CONTENTS PROCEDURES FOR WARRANTY 2
Warranty Information TABLE OF CONTENTS PROCEDURES FOR WARRANTY 2 PROTECTING YOUR DURO-LAST ROOFING 3 Safety Measures 3 Inspection 3 Maintenance Program 4 Sealants 4 Drainage 4 Parapets Walls 4 Building
March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202
Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request
PREMIUM LAMINATED ASPHALT SHINGLES Dallas, TX Tuscaloosa, AL Phillipsburg, KS
Application Instructions for THESE ARE THE MANUFACTURER S APPLICATION INSTRUCTIONS FOR THE ROOFING CONDITIONS DESCRIBED. TAMKO BUILDING PRODUCTS, INC. ASSUMES NO RESPONSIBILITY FOR LEAKS OR OTHER ROOFING
Memtec Single Ply PVC Membrane Roofing and Waterproofing Technology. Modern Efficient Performance Cost Effective Flat Roofing Systems
Memtec Single Ply PVC Membrane Roofing and Waterproofing Technology Modern Efficient Performance Cost Effective Flat Roofing Systems Introduction A complete range of Memtec Roofing and Waterproofing Single
Total Home Inspection Checklist
Total Home Inspection Checklist Use a checklist like this to make sure that you are looking at all parts of the house. Check off those items that are in good condition and make notes about those that are
Repair of Spalling and Leaking Clay Brick Building Walls
B etter buildings Repair of Spalling and Leaking Clay Brick Building Walls Overview A few years after being built in Waterloo in 1980, a condominium of three, six-storey buildings showed severe spalling
Structural Assessment Report
Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive
PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007
PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT November 2007 PURPOSE OF INVESTIGATION Determine possible locations of moisture intrusion into and through facade. Determine cause of horizontal and vertical
Roof Condition Analysis
Roof Condition Analysis Prepared for: J.W. Nelson John Evans Middle School - Gym Dome 2900 15th Avenue Greeley, Colorado Prepared by: Gregory Ham Coastal Specified Products 5252 Sherman Street Denver,
EXTERNAL WATERPROOFING MEMBRANES BEST PRACTICE GUIDELINES
Building and Construction Industry A joint industry initiative produced by BSA Supershow logo.indd 1 30/01/2008 9:43:29 AM EXTERNAL WATERPROOFING MEMBRANES BEST PRACTICE GUIDELINES FAILING WATERPROOFING
Residential Roofing Guide
Residential Roofing Guide TABLE OF CONTENTS Building Detail and Accessories...... 1 Panel Introduction and Handling...... 2 Cutting and Trimming.... 3 Roof Preparation..... 3 Roof Slope..... 3 Re-roofing...
Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association
Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-
Metropolitan Builders Association Masonry & Concrete Standard
Metropolitan Builders Association Masonry & Concrete Standard Background Masonry and concrete work in residential construction often provides the base structure upon which the house is built or as a veneer.
ROOF ASSEMBLIES CHAPTER 9
CHAPTER 9 ROOF ASSEMBLIES SECTION R901 GENERAL R901.1 Scope. The provisions of this chapter shall govern the design, materials, construction and quality of roof assemblies. SECTION R902 ROOF CLASSIFICATION
Basement & Foundation Damage
Basement & Foundation Damage Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case
INSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
DIVISION 7 - THERMAL AND MOISTURE PROTECTION Note: This is a guide for Designers only. Contents shall not be used in lieu of specifications as part of the Designer s Contract Documents. SECTION 07 1000
Your guide to home maintenance. Flat Roofs
Your guide to home maintenance Flat Roofs Your guide to home maintenance is a series of information leaflets that gives you all the information you need to keep your home in tiptop condition. Flat Roofs
Ver. 2. Guide to. Inspecting Residential Brick Veneer
Ver. 2 Guide to Inspecting Residential Brick Veneer 1. A guide created by industry professionals. The knowledgeable staff at MASONPRO together with technical support from the Masonry Institute of Michigan
THERMOTEK MODIFIED BITUMEN TORCH MEMBRANE OVER POLYSOCYANURATE SYSTEM DESCRIPTION TORCH SYSTEM OVER POLYISO (15,17,19 YR) TH/BS-TH/CS
OPTIONAL TITLE 24 CRITICAL POINTS POLYISO THERMOTEK MODIFIED BITUMEN TORCH MEMBRANE OVER POLYSOCYANURATE DESCRIPTION TORCH OVER POLYISO (5,7,9 YR) TH/BS-TH/CS 2 No 0. SUBSTRATE. THERMOTEK USA PRO 2.0 FV
CONSERVATION MAINTENANCE WORKSHEET Universal Checklist
3.1 SITE 1 Concrete curbs Check for cracks, spalling, growth from joints X 2 Stone curbs Check for cracks, spalling, growth from joints X 3 Concrete walkways Look for uneven surfaces, ponding, growth from
Shingle Installation Guide
Shingle Installation Guide Getting Started Dedicated to improving the environment, NewTech manufactures roofing tiles that are composed of up to 90% recycled post-industrial plastic. The manufacture of
FAST FACTS ADVANTAGES OF MULTI PLY BUILT-UP ROOFING. Asphalt Roofing Manufacturers Association
FAST FACTS ADVANTAGES OF MULTI PLY BUILT-UP ROOFING Roofing Manufacturers Association Why is a built-up roof considered a multi-ply roof? ARMA defines a built-up roofing system as a roof where multiple
FLAT ROOF REPAIR CUT COST WITHOUT CUTTING CORNERS
FLAT ROOF REPAIR CUT COST WITHOUT CUTTING CORNERS Table of Contents Chapter 1: FLAT ROOF REPAIR - CUT COST WITHOUT CUTTING CORNERS Chapter 2: PVC RECOVER SYSTEM HOW IT WORKS Chapter 3: 8 STRATEGIES TO
Garver Feed Mill Condition Evaluation
Garver Feed Mill Condition Evaluation OUTLINE Brick masonry overview Condition assessment & methodology Project overview Existing conditions Stabilization Probable costs Summary BRICK MASONRY OVERVIEW
BLACK JACK ALL WEATHER ROOF COATING
PAGE: 1 of 6 PRINT DATE: 16/09/2004 BLACK JACK ALL WEATHER ROOF COATING DESCRIPTION BLACK JACK ALL WEATHER ROOF COATING is a solvent based, full bodied black brushable compound with added fibres for reinforcement.
Roof Inspection. Summary Report
Phone: (561) 866 9956 www.real-estate-inspections.com Roof Inspection Summary Report Subject Property File Number: 05-15-RF-002 Inspector: Craig Milliken, PE CPM Real Estate Inspections, Inc. Date of Inspection:
NEOGARD. Preventive Maintenance Manual
NEOGARD Preventive Maintenance Manual Fluid-Applied Roof Coating Systems December 2014 Notes NEOGARD luid-applied roof coating systems are designed to be long lasting, monolithic membranes which provide
Smooth cap sheet - 0-10 SQ $ 139.00. Smooth cap sheet - 11-50 SQ $ 63.00. Smooth cap sheet - 51-100 SQ $ 36.00 Smooth cap sheet - 101-200 SQ $ 36.
Demolition/Removal of Work 4-ply built up roofing to the insulation (smooth cap sheet) Smooth cap sheet - 0-10 SQ $ 63.00 Smooth cap sheet - 11-50 SQ $ 63.00 Smooth cap sheet - 51-100 SQ $ 35.00 Smooth
A. This Section includes rubberized asphalt sheet membrane waterproofing systems.
SECTION 07110 SHEET MEMBRANE WATERPROOFING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
Advice Series. the maintenance and repair of historic buildings
Advice Series the maintenance and repair of historic buildings Jacqui Donnelly - Architectural Conservation Advisor, Department of the Environment, Heritage & Local Government Current publications in the
FORENSIC INVESTIGATION QUESTIONNAIRE
FORENSIC INVESTIGATION QUESTIONNAIRE PSE Project Number: - - Project Name: Person(s) Interviewed: Relationship to House: Please answer the following questions to the best of your ability. Exact dates are
www.citiesinspection.com October 5, 2015 Dear Client,
www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.
May 5, 2010. Client Client Address. Re: Inspection Address, Chicago, Illinois. Dear Mr. Client,
PROPERTY INSPECTION PROFESSIONALS May 5, 2010 Client Client Address Re: Inspection Address, Chicago, Illinois Dear Mr. Client, On May 4, 2010, Tomacor completed a property inspection of the above referenced
Water Intrusion 101. Presented by: Michael D. Spensieri, P.E. Regional Engineering Manager Office: 800-482-5611 Ext: 2018 www.donan.
Water Intrusion 101 Presented by: Michael D. Spensieri, P.E. Regional Engineering Manager Office: 800-482-5611 Ext: 2018 www.donan.com Goals Open environment Interactive discussion PLEASE ask questions
Roof Maintenance Scope of Work
Roof Maintenance Scope of Work Reviewed By: Approved By: Version 3.0 Date 08-09-07 Author K. Vandenbussche 1 BACKGROUND The Integrated Service Provider s program will provide superior on-site equipment,
Self-Home Inspection Checklist
To be used as a first home visit for note taking. Visit www.homeinspectiondirect.com for more tips and information about buying a home and hiring a home inspector. This form in no way replaces a professional
Crescent Valley High School Roof Investigation
Crescent Valley High School Roof Investigation Project: Corvallis School District Crescent Valley High School Roof Date: July 26, 2011 Report By: Rowell Brokaw Architects: Mark Young, AIA, Chris Andrejko
Roofing/Flashings/ Chimneys. Chimneys
Roofing/Flashings/ Chimneys Roofing/Flashings/ Chimneys introduction The primary purpose of a roof is to protect the building from rain, snow, sun and wind. Roofs also affect the appearance of a building.
foot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.
Skylight Installation Instructions This document provides instruction and guidelines for installation of both curb mount (CM) and self flashing (SF) unit skylights on flat, pitched (> or equal to 3/12
Reroof or Restore? The right decision can save weeks of time and thousands of dollars
APOC A DIVISION OF GARDNER - GIBSON 5903 Paramount Boulevard Long Beach, California 90805 Telephone (800) 562-5669 Fax (562) 423-9597 www.apoc.com THE FOLLOWING TECHNICAL ARTICLE WAS PUBLISHED IN A MAJOR
The Wo rd. Shingle Warranties - Getting Real
The Wo rd A look at terms used in home inspection reports Photo I ONCE AGAIN THE WORD INVITES YOU TO TRAVEL into the dark realm of subjects that are sometimes misunderstood by home inspectors. The Word
Shingle Roofing: What s below the surface is important
What s below the surface is important The roof is leaking, the shingles look old, and the downspouts are dripping. It must be time to replace the roof or is it? Shingle roofs may seem simple, but a roof
TABLE OF CONTENTS" SECTION 3: Comparing Standing Seam Metal to Other Metal Roofs PAGE 7"
2 TABLE OF CONTENTS SECTION 1: What is a Standing Seam Metal Roof PAGE 3 SECTION 2: Common Types of Standing Seam Metal Roofs..PAGE 5 SECTION 3: Comparing Standing Seam Metal to Other Metal Roofs PAGE
ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
CHAPTER 15 ROOF ASSEMBLIES AND ROOFTOP STRUCTURES SECTION 1501 GENERAL 1501.1 Scope. The provisions of this chapter shall govern the design, materials, construction and quality of roof assemblies, and
RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012
RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012 Commercial rooftops represent the most available, sustainable and secure real estate for new
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 87 88 GOOD INDUSTRY PRACTICES 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12.1 BACKGROUND Most roofs in Singapore are constructed using reinforced
Chapter 9: INSTALLING ROOFING
9.1 LEAK BARRIER (ICE AND WATER SHIELD) 9.2 SHINGLE UNDERLAYMENT 9.3 INSTALLING GUTTER APRON AND GABLE D-EDGE 9.4 INSTALLING SHINGLES 9.5 RIDGE VENT AND CAP Tools needed by each volunteer: Hammer (16 oz.
Delaney-Vogel School
Wrentham Public Schools Delaney-Vogel School Schematic Design 1. INTRODUCTION Wrentham Public Schools contracted with Turowski2 Architecture, Inc. on November 11, 2015 to assess necessary roof repairs
Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
Detached accessory structures that contain no conditioned floor area are exempt.
RESIDENTIAL ROOFING PERMITS: A roofing permit is required for roofing of residential dwellings and garages in accordance with Section R105 of the International Residential Code. Updated 11/2013 City of
Exterior Elevated Elements Inspection Guidelines
Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code
ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
CHAPTER 15 ROOF ASSEMBLIES AND ROOFTOP STRUCTURES SECTION 1501 GENERAL 1501.1 Scope. The provisions of this chapter shall govern the design, materials, construction and quality of roof assemblies, and
The history of brick in Scotland Signs of deterioration in brickwork Causes of deterioration Repair and maintenance of brick structures
Repairing brickwork Introduction Bricks can be defined as small rectangular blocks of fired clay. They come in a variety of sizes, shapes and colours. They also vary in age and quality. A large number
Safeguarding our clients interests. Active Roof Leaks
Safeguarding our clients interests. Active Roof Leaks Vendor Requirements Visually inspect the roof for any damages Exterior inspection of the roof and gutters Interior ceiling inspection Interior attic