Evaluating. A Case Study



Similar documents
Inspection and Repair of a Fire Damaged Prestressed Girder Bridge

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

Detailing of Reinforcment in Concrete Structures

Bridge Structural Rehabilitation Using FRP Laminates

A transverse strip of the deck is assumed to support the truck axle loads. Shear and fatigue of the reinforcement need not be investigated.

Safe & Sound Bridge Terminology

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim.

PRE INSTALLATION MANUAL

Structural Failures Cost Lives and Time

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

METHOD OF STATEMENT FOR STATIC LOADING TEST

Precast Concrete Parking Structures

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

The Strength of Concrete

Reinforced Concrete Slab Design Using the Empirical Method

Residential Deck Safety, Construction, and Repair

A Simple Method of Gripping Prestressing Strands for Tension Tests

Risk - Based Inspection Frequencies

Incorporating Innovative Materials for Seismic Resilient Bridge Columns

Technical Notes 3B - Brick Masonry Section Properties May 1993

Tension Development and Lap Splice Lengths of Reinforcing Bars under ACI

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

Fire Damage Evaluation. Concrete Garage. Vehicular fires in parking garages are not an

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Guidelines for the Design of Post-Tensioned Floors

Fire Preventive and Fireproof Performance Test and Evaluation Procedure Manual

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

Owner s Guide to Understanding Checks in Glued Laminated Timber

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

Field Welding Inspection Guide

Index Series Prestressed Florida-I Beams (Rev. 07/12)

EFFECTS ON NUMBER OF CABLES FOR MODAL ANALYSIS OF CABLE-STAYED BRIDGES

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Measuring the Condition of Prestressed Concrete Cylinder Pipe

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE

Robert H. White, Research Wood Scientist, U.S. Forest Products Lab., Madison, WI, USA, Brian Kukay, Associate Professor of General

EAST LYME HIGH SCHOOL

Concrete Repair. Applications and Procedures

NON-DESTRUCTIVE METHODS. CE 165: Concrete Materials and Concrete Construction

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

PCI BIG BEAM COMPETITION

SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

Condition assessment and repair of antenna towers concrete foundations

WSDOT Bridge Elements

Prestressed Storage Tanks

SECTION PRECAST CONCRETE STRUCTURES

Session 5D: Benefits of Live Load Testing and Finite Element Modeling in Rating Bridges

INTRODUCTION TO BEAMS

Bridge Type Selection

SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE

TABLE OF CONTENTS. Roof Decks 172 B, BA, BV Deck N, NA Deck. Form Decks FD,.6 FDV Deck 1.0 FD, 1.0 FDV Deck 1.5 FD Deck 2.0 FD Deck 3.

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

UX-30 PERFORMANCE TESTING SUMMARY REPORT Revision 0

Chapter 3 Pre-Installation, Foundations and Piers

Proper use of the Rebound Hammer Updated to reflect the changes to ASTM C805

Evaluation of Bridge Performance and Rating through Nondestructive

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

Fire and Concrete Structures

ASSESSMENT AND PROPOSED STRUCTURAL REPAIR STRATEGIES FOR BRIDGE PIERS IN TAIWAN DAMAGED BY THE JI-JI EARTHQUAKE ABSTRACT

HIGH-PERFORMANCE CONCRETE IN A BRIDGE IN RICHLANDS, VIRGINIA. Celik Ozyildirim, Ph.D. Principal Research Scientist

Elevated Roads for Sri Lanka

The ACI 562 Repair Code

STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

HIGH TENSION CABLE BARRIER

HfHMD uses LP SmartSide siding and trim.

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

MATERIALS AND MECHANICS OF BENDING

Fire-induced damage in prestressing steels

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

US 51 Ohio River Bridge Engineering and Environmental Study

Detailed Non-Destructive Bridge Inspection Guidelines. Concrete and Steel Bridges (Level 3 Inspections) Structures Engineering

Green Thread Product Data

Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS

Value Engineering vs. Alternate Designs in Bridge Bidding

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

Optimum proportions for the design of suspension bridge

ABSTRACT 1. INTRODUCTION 2. DESCRIPTION OF THE SEGMENTAL BEAM

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

GARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION

SEISMIC REHABILITATION OF COLUMN TO PIER CAP ACCELERATED BRIDGE CONSTRUCTION CONNECTIONS AND ACOUSTIC EMISSION MONITORING ASSESSM ENT

Structural Forensic Engineering Case Study : MRR2 Project. Prof. Dr. Azlan Abdul Rahman Forensic Engineering Universiti Teknologi Malaysia

SECTION 1 GENERAL REQUIREMENTS

1.054/1.541 Mechanics and Design of Concrete Structures (3-0-9) Outline 1 Introduction / Design Criteria for Reinforced Concrete Structures

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

Pro-Lift Steel Pile Foundation Repair

Transcription:

A Case Study Evaluating by Richard B. Stoddard, Washington State Department of Transportation In December 2002, a railroad tanker collision caused a fire under a prestressed concrete girder bridge crossing the Puyallup River in Tacoma, Washington. The bridge, constructed in 1997, had span lengths of 146 ft with W74 girders spaced at 5-ft 0-in. centers. Specified 28-day concrete strengths were 7000 psi in the girders and 5000 psi in the columns and bridge deck. The fire consumed 30,000 gallons of methanol, engulfed Span 8, and maintained a high flame temperature for approximately 1 hour. The bridge was closed immediately pending further inspections. The bridge displayed no unusual deflections or misalignments and was reopened to commuter traffic and legal weight trucks on the morning after the fire. Visual Inspection and Mapping Visual inspection of both columns at Pier 9 approximately 60 ft from the source of the fire, showed 2-in.-deep spalls that exposed spiral reinforcement for the full height of the column. The concrete inside the spiral sounded like delaminated concrete. Further investigation revealed delaminations 24 ASPIRE, Spring 2008

within the concrete just inside the spiral cage and vertical reinforcement. The crossbeam above the columns had several areas of spalling but no reinforcement was exposed. All 15 lines of girders in Span 8 were damaged and the corners of the bottom flanges could easily be removed to expose the outermost strands. The soffit of the concrete deck displayed no evidence of spalling. Visual inspection of the damage in Span 8 included recording the concrete color variations on the soffit of the bottom flanges that corresponded to changes in concrete condition. The color regions were described as extreme-white, ash-white, white-gray, and soot. The different colors corresponded with different exposures to the fire with the extreme-white region representing the most intense exposure directly over the fire source. Concrete Hardness Mapping In accordance with the recommendations for Post Fire Examination of the PCI Design for Fire Resistance of Precast, Prestressed Concrete, hardness testing was performed on the bottom flanges and webs of the girders using a Schmidt hammer. The purpose of the tests was to map relative changes in concrete hardness along the length of each girder. The rebound hammer readings for the soffit of the bottom flanges in Span 8 ranged from 42 to 61 compared to 61 in girder concrete not affected by the fire. The minimum hardness occurred directly over the heat source and in general, hardness increased with distance away from the heat source. The web hardness readings did not follow a pattern of regular change because shadowing by the bottom flange affected the distribution of web damage. The bottom flange protected some parts of the webs from severe fire damage. Prestressing Strand The prestressing steel in the girders consisted of 1/2-in.-diameter 270 ksi strands. Concrete surrounding the straight strands in the bottom flange was easy to remove with a light rock hammer. Because of the high temperatures, there was concern that the strands could have lost strength and that relaxation of the prestress force could have occurred. Prior to removing samples of prestressing strands for material testing, simple deflection tests were performed to calculate the prestressing force. The tests were conducted before the strands were cut and after the strand replacement splices were tensioned. The strand deflections were induced by hanging a 173 lb weight on the strand. Deflections were measured multiple times by two inspectors using a dial caliper with a measurement accuracy of 0.001 in. This method was estimated to have a probable accuracy of 5 percent and was certainly accurate to within 10 percent of the actual tensile force. Based on this approach, the strands in the hottest zones appeared to have retained 100 percent of their design force. Three samples of strand were removed and tested for yield strength, tensile strength, and modulus of elasticity. The strand samples met the requirements for 1/2-in.- diameter uncoated seven-wire prestressing strands per ASTM A 416-96 indicating that no metallurigical changes occured. The fire engulfed Span 8 and maintained a high flame temperature for approximately 1 hour. ASPIRE, Spring 2008 25

Spalling of concrete cover on the columns resulted in areas of exposed spiral reinforcement. The pink color shown in this girder from the Puyallup bridge fire indicates that the concrete was exposed to temperatures higher than 500 F. Concrete Core Samples Eight vertical concrete cores from the hot zone, two vertical cores from the coolest zone, and eight horizontal cores from the hot zone were removed from the prestressed concrete beams. Seven cores were examined petrographically in general accordance with ASTM C 856. The extent and severity of fire damage was based on observed changes in aggregate and cement paste color, mineralogy, and microstructure. Based on the petrographers evaluation, which also included some informal heating tests, the state was convinced that surface temperatures on the bottom flange soffits exceeded 1500 F during the fire. Compression tests performed on core samples indicated that much of the undamaged concrete had a compressive strength exceeding 9000 psi. Significant portions of core samples from the hottest zone, however, were fractured and untestable. Eight concrete cores were taken from the two columns at Pier 9. These confirmed the existence of delaminations in the interior core of the column. The maximum depth of fracture was found to be 5 in. from the original surface and more than 1 in. inside the vertical column reinforcement. Aside from the delaminations, the concrete remaining in the column appeared to have very good strength. A core sample from the crossbeam at Pier 9 did not show any abnormalities and indicated that the crossbeam sustained only superficial damage from the fire. Summary The railroad tanker fire subjected all 15 girders in Span 8 to intense heat in a short period of time. Flame temperatures were estimated to be approximately 3000 F and surface temperatures on the soffit of the prestressed concrete girders may have reached 1700 F. Internal temperatures in the bottom flange and webs were estimated to range from 500 to 1100 F. The prestressing steel survived the fire without noticeable loss of prestress. Rapid identification of concrete damage zones can be made by observing the variation in concrete color immediately following a fire. The visual color mapping correlated very well with variations in concrete hardness. The rebound hammer test validated the visual observations and provided an objective description of the damaged areas. With this information, rational discussions could be made about repair or replacement. All 15 lines of girders in Span 8 were damaged by the fire but the bridge was opened on the next morning. 26 ASPIRE, Spring 2008

Reference Design for Fire Resistance of Precast, Prestressed Concrete, Second Edition, MNL-124-89, Precast/Prestressed Concrete Institute, Chicago, IL, 1989, 96 pp. Acknowledgement This article is based on a full-length paper titled Inspections and Repair of a Fire Damaged Prestressed Girder Bridge, presented at the International Bridge Conference, Pittsburgh, June 2004, Paper No. IBC-04-17 which is available at www. aspirebridge.org/resources. Richard B. Stoddard is Bridge Design Engineer with the Bridges and Structures Office of the Washington State Department of Transportation. Advertisers Index BASF........... Inside Back Cover Bentley/LEAP.... Inside Front Cover Campbell Scientific............ 63 CH2M Hill.................... 7 DSI.... 15 Eriksson Technologies...Back Cover Finley Engineering............. 51 FIGG......................... 3 Gerdau Ameristeel... 27 Lehigh Cement... 23 PCAP CABA... 14 Scott System... 33 Splice Sleeve.... 33 Stalite... 57 Standard Concrete Products... 43 T.Y. Lin International............ 5 Williams Form Eng. Corp.... 61 VSL.......................... 4 ZBar ad_bris_aspire-mar:zbar ad 2/14/08 1:20 PM Page 1 High Performance Corrosion Protection Patent-Pending Dual Coating Process Some surface damage occurred in the top flanges. Fusion-Bonded Powder Outer Coating ZBAR s first line of defense against water and chlorides which lead to corrosion. Thermal Zinc Inner Coating Durable; providing sacrificial galvanic protection if damaged. Next Generation Corrosion Protection Compliant With The Federally Funded Highways for Life Program Contact Us For Complete Details. Damage concrete surrounding the straight prestressing strands was easy to remove. For more information on this or other projects, visit www.aspirebridge.org. CALL 888-637-9950 FOR SALES & ORDERING INFORMATION www.gerdauameristeel.com/zbar ASPIRE, Spring 2008 27

PUYALLUP RIVER Bridge / WASHINGTON

PUYALLUP RIVER Bridge / WASHINGTON ASPIRE, Spring 2008 Web

Web ASPIRE, Spring 2008 PUYALLUP RIVER Bridge / WASHINGTON

PUYALLUP RIVER Bridge / WASHINGTON ASPIRE, Spring 2008 Web

Web ASPIRE, Spring 2008 PUYALLUP RIVER Bridge / WASHINGTON

PUYALLUP RIVER Bridge / WASHINGTON ASPIRE, Spring 2008 Web

Web ASPIRE, Spring 2008 PUYALLUP RIVER Bridge / WASHINGTON

PUYALLUP RIVER Bridge / WASHINGTON ASPIRE, Spring 2008 Web

Web ASPIRE, Spring 2008 PUYALLUP RIVER Bridge / WASHINGTON

PUYALLUP RIVER Bridge / WASHINGTON ASPIRE, Spring 2008 Web

Web ASPIRE, Spring 2008 PUYALLUP RIVER Bridge / WASHINGTON

PUYALLUP RIVER Bridge / WASHINGTON ASPIRE, Spring 2008 Web

Bell island Bridge / oklahoma city, oklahoma Photos: Oklahoma, DOT Web ASPIRE, Spring 2008

bell island Bridge / oklahoma city, oklahoma Photos: Oklahoma, DOT ASPIRE, Spring 2008 Web

Web ASPIRE, Spring 2008 NORWALK RIVER Bridge / Ridgefield, connecticut

NORWALK RIVER Bridge / Ridgefield, connecticut ASPIRE, Spring 2008 Web

Web ASPIRE, Spring 2008 NORWALK RIVER Bridge / Ridgefield, connecticut