Inspection and Repair of a Fire Damaged Prestressed Girder Bridge
|
|
|
- Donna Franklin
- 9 years ago
- Views:
Transcription
1 Inspection and Repair of a Fire Damaged Prestressed Girder Bridge RICHARD STODDARD, Washington State DOT, Olympia, WA IBC
2 Section 1 Incident Response DAMAGE INSPECTION REPORT 12/12/02 On December 11, 2002, at approximately 4:00 pm, a railroad tanker collision caused a fire under a prestressed girder bridge that consumed 30,000 gallons of mythanol, (photo 1). This section of the bridge was a relatively new continuous three span frame constructed in The girders had a span length of 146 feet, a 28 day concrete strength of 7000 psi, and 0.5 diameter 270 ksi steel strands. The bridge deck and columns were constructed using 5000 psi concrete and 60 ksi mild steel. Confinement reinforcement in the columns was provided by tightly wound spiral cages. Photo 1. Puyallup River Bridge Railroad Tanker Fire The fire engulfed Span 8 and maintained a high flame temperature for approximately one hour. The interstate freeway was immediately closed to traffic and remained closed pending an all night structural inspection.. The bridge displayed no unusual deflections or misalignments and was reopened to commuter traffic and legal weight trucks on the morning of December 12 th. Over weight trucks were prohibited and routed to I-5. 1
3 Fire Damage: The south face of the both columns at Pier 9 had 2 inch deep concrete spalls that exposed spiral reinforcement for the full height of the pier. Additional concrete was easily removed by hammering at the edges of the spalls. The spiral reinforcement and concrete inside the spiral appeared to be hard but sounded like delaminated concrete. Further analysis showed delaminations had formed within the concrete core just inside of the spiral cage and vertical reinforcement. The crossbeam at Pier 9 had several areas of concrete spalling to depths of 0.5 but no reinforcement was exposed. All 15 lines of girders in Span 8 were damaged by the fire. The color of the bottom flange soffit was a whitish-gray, (photo 2). The whitish-gray concrete at the corners of the bottom flange could be easily removed to expose the outermost prestressing strands for a length of more than 94 feet, (photo 3). There were 0.5 inch deep concrete spalls in the top flange and webs of girders. The load capacity of the girders was investigated by visually checking for excessive Photo 2. Span 8 Heat Damaged Flanges deflections or obvious changes in camber. Spans 7, 8, and 9 showed no change in vertical or horizontal alignment. The soffit of the concrete deck escaped damage and displayed no evidence of concrete spalling. The exterior faces of the bridge railing also escaped obvious damage from the fire. Pipe hangers supporting a suspended 12 inch diameter storm drain pipe between Girders 8G and 8H had several failed attachments to the deck. Additionally, the elastomeric pads at the ends of the horizontal struts that rest against Photo 3. Girder 8E Flange Soffit the girder webs had been vaporize or had fallen out. Structural Recommendations based on the Emergency Inspection: Maintain truck weight restrictions placed on the bridge on December 12, Remove the loose concrete that presents a safety hazard to BNSF and the public. Conduct detailed inspections to verify findings and document extent of damage. 2
4 Section 2 Heat and Energy FUEL The railroad tanker involved in this fire was loaded with 30,000 gallons of Methyl Alcohol, with a chemical formula of CH 3 OH. Product information supplied by Pharmco Products Inc. 1 lists the following Fire Fighting Measures: Fire/Explosive Properties: Flash Point: 52F (11C) Tag Closed Cup Flammable limits in Air (% by Volume): 6% Methanol 36% Methanol NFPA Rating: Health 1, Fire 3, Reactivity 0 Extinguishing Media: Apply alcohol-type or all-purpose foam by manufacturer s recommended techniques for large fires. Use carbon dioxide or dry chemical media for small fires. Special Fire Fighting Procedures: Use water spray to cool fire-exposed containers and structures; Use water spray to disperse vapors re-ignition is possible; Use self-contained breathing apparatus and protective clothing. Unusual Fire and Explosion Hazards: Vapors may travel to source of ignition and flash back. Vapors may settle in low or confined spaces. May produce a floating fire hazard. Static ignition hazard can result from handling and use. ESTIMATED FLAME TEMPERATURE The flame temperatures of the fire were estimated to be approximately 3000 F. This estimate was calculated with the use of an On-Line software program provided by Dr. Allan T. Kirkpatrick, a professor of Mechanical Engineering at Colorado State University, (Figure 1). Adiabatic Flame Temperature 4 : n/thermo/page12/adia_flame/flame main.html Figure 1 Methanol Flame Temperature 3
5 ESTIMATED FIRE INTENSITY & HEAT ENERGY Calculations were made to estimate the heat energy released by the methanol fire. A comparison of the intensity of this fire to ASTM E119 fire tests was helpful in determining the probable heat penetration and concrete damage within the girders. PCI publication MNL , Design for Fire Resistance of Precast Prestressed Concrete 2, provides the temperature and heat energy applied during the ASTM fire tests as well as graphs for establishing isotherms within concrete beams. Furnace temperatures for the ASTM fire test reach a maximum of 2300 F after eight (8) hours of exposure. It is likely that the methanol tanker fire projected temperatures of 2700 F to the bottom of the girders after only one-half (1/2) hour and temperatures fell below 1000 F after two (2) hours. Figure 2 compares the ATSM furnace temperatures to a possible heat time history for the methanol tanker fire. Differences can be seen in temperature and duration. The Figure 2. Temperature vs Time tanker fire was hotter but temperatures subsided more quickly than prescribed for the ASTM test. The heat energy applied during the ASTM test is prescribed to be 8000 BTU per square foot per hour. The estimated energy released by the combustion of 30,000 gallons of Methanol was calculated to be approximately 1,600,000,000 BTU 5. Reducing the total BTU to account for incomplete combustion and heat transfer, and then uniformly distributing the energy to the deck area of Span 8, indicates that the energy exposure may have been in the range of 25,000 BTU to 62,000 BTU per square foot per hour. This indicated that Span 8 was exposed to as much as 7 times the amount of heat energy as expected by the ASTM fire test. The railroad tanker fire on December 11, 2002, clearly exceeded the temperatures and energy release commonly used for predicting fire resistance capabilities of precast prestressed concrete (Table 1). Table 1. Heat Energy Distribution and Rate of Heating, BTU / sf / hour % of 30,000 Gallons Total BTU % of Span 8 Span 8 BTU BTU / sf / hour % of ASTM E119 Upper Bound <<<<<< >>>>>> Lower Bound 100% 90% 80% 70% 1,599,801,036 1,439,820,933 1,279,840,829 1,119,860,725 70% 60% 50% 40% 1,119,860, ,892, ,920, ,944,290 61,768 47,650 35,296 24, % 596% 441% 309% 4
6 Section 3 Visual Inspection and Mapping POST FIRE EXAMINATION PCI Design for Fire Resistance of Precast Prestressed Concrete 2 Chapter 9.4 Post Fire Examination It is sometimes possible to determine the temperatures to which concrete was heated by its color. Concrete which has been heated and then cooled and is not discolored probably was not heated above about 600 F. If the concrete has become pink, it may have been heated to a temperature between 600 F and 1100 F. Concrete heated above 1100 F and then cooled tends to become a whitish-gray, and above 1700 F some concretes turn to a buff color. CONDITION STATE MAP Visual inspections of the damage in Span 8 made note of concrete color variations on the soffit of the bottom flanges that corresponded to changes in concrete condition states. Figure 3 contains a map that was produced to display the boundaries of four fire induced color regions. The color regions were described as Extreme-White, Ash-White, White-Gray, and Soot. Figure 3. Bottom Flange Visual Condition States 5
7 EXTREME-WHITE The Extreme White bottom flange color appeared to represent exposure to the most intense heat directly over the fire source. The boundaries of this region were difficult to see but the region was clearly visible in photos of span 8. This region represented approximately 10% of the Span 8 area and included Girders 8D, 8E, 8F, 8G, and 8H. An elliptical shape directly above the tanker was placed to approximate the size and position of this region. Concrete on the soffit of the bottom flanges crumbled when tapped with a rock hammer. Prestressing strands on the east and west edges of the bottom flange were easily exposed. Concrete spalls were noted on the soffit and both sides of the webs and both sides of the top flanges. Heat deformation was also noted in mild steel in the top flange. The nylon reinforcing chairs in the bottom flanges burned during the fire leaving deep pockets of charred nylon in the flange soffit. ASH-WHITE The Ash-White bottom flange region encompassed approximately 30% of the Span 8 area and included all fifteen (15) girders. The North and South boundaries were relatively easy to see from the ground. Their position was measured from the center of Pier 9. Concrete on the soffit of the bottom flanges crumbled or spalled when tapped with a rock hammer. Prestressing strands on the edges of the bottom flange were easily exposed. Concrete spalls were noted in the webs and the top flanges. Web spalls occurred only on the side facing the heat source, due to shadowing effects from the adjacent girders. The density and extents of spalling on the webs appeared to increase with distance from the heat source. This is probably another demonstration of shadowing effects that occurred near the heat source. The girder webs furthest away from the fire were actually more exposed to the radiant heat than were the webs nearest to the fire. Web spalling and top flange spalling did not occur outside of this color region. The nylon reinforcing chairs in the girders had melted with some indication of being burned during the fire. Melted nylon formed stalactites and pockets of charred nylon were visible. WHITE-GRAY The White/Gray bottom flange region encompasses approximately 30% of the Span 8 area and included all fifteen (15) girders. This region was characterizes by obvious delamination sounds in the bottom flanges when struck with a rock hammer. Concrete spalling could be produced with forceful strikes using a rock hammer. The concrete did not crumble and the spalled pieces were 6 inches to 12 inches in size. Prestressing strands on the edges of the bottom flange were difficult to expose using a rock hammer. The web and top flanges were covered with soot but appeared to have sound concrete. The nylon reinforcing chairs in the girders had melted during the fire leaving long nylon stalactites. SOOT The Soot colored region encompasses approximately 20% of the Span 8 area beginning at about 6 feet from Pier 8 and extending to Pier 9. The region outside of the White/Gray boundary was dark gray in color. The concrete appeared sound but delamination sounds were evident on the edges of the bottom flange when struck with a rock hammer. The nylon reinforcing chairs in the girders melted during the fire leaving marks on the bottom side of the bottom flange, stalactites were not seen in this area. 6
8 Section 4 Concrete Hardness Mapping SCHMIDT HAMMER HARDNESS TESTING PCI Design for Fire Resistance of Precast Prestressed Concrete 2 Chapter 9.4 Post Fire Examination To evaluate fire-damaged concrete structures is advisable to determine the extent of severe damage. The limits of the area of concrete damage can often be ascertained through the use of an impact rebound hammer. An average hammer reading should first be obtained in the obviously un-damaged areas for each type of unit. Readings in the damaged areas will generally be substantially lower than those in undamaged areas. By taking a large number of readings throughout the areas suspected of damage, the severely damaged areas can be isolated. Hardness testing was performed on the bottom flanges and webs of the girders using a Schmidt Hammer. These tests were conducted at eighty-nine (89) locations on the soffit of the bottom flanges and eighty-nine (89) locations on the webs facing the heat source. The purpose of the tests was to map relative changes in concrete hardness along the length of each girder. VISUAL CONDITION STATES & BOTTOM FLANGE HARDNESS Two locations in Span 9 were tested to provide an expected hardness value for concrete not affected by the fire. The average rebound hammer reading for the soffit of the bottom flange in Girder 9N was The rebound hammer readings for the soffit of the bottom flanges in Span 8 ranged from a low of 42.0 to a high of The minimum hardness reading was found to be directly over the heat source and in general, flange hardness increase with distance Figure 4. Visual Condition States and Flange Hardness Contours 7
9 away from the heat source. A contour map overlay was added to the flange color variations to check for correlations. As can be seen in Figure 4, the hardness measurements were consistent with the visual damage assessments. FLANGE AND WEB HARDNESS MAP The average rebound hammer readings for Girder 9N was The rebound hammer reading in the webs of Span 8 ranged from a low of 47.9 to a high of The web harness reading proved impossible to represent with a contour map because values did not follow a pattern of regular change. Color bands were developed as a method to display the hardness changes on a map. Figure 5 overlays the Web Hardness Color Bands and the Flange Hardness Contours to show that the location of the lowest web hardness values corresponds with the lowest flange hardness values. In general, web hardness increases with distance from the source of the fire but shadowing affected the distribution of web damage. Webs lying outside of the small circle in the center of the heat source were damaged by heat if they were not shadowed and if their angle of exposure to the heat source was less than 40 degrees. One could see how the shadowing occurred by standing at the location of the tanker during the fire. Webs directly above and near that location could not be seen because they were blocked by the bottom flanges. Webs of the exterior girders became more visible resulting in a greater exposure to radiant heat. The web damage (reduced hardness) outside of the Extreme White color region actually increased with distance from the fire. Figure 5. Flange Hardness Contours and Web Hardness Color Bands 8
10 Section 5 Prestressing Steel Evaluation ESTIMATED CONCRETE TEMPERATURES AROUND STRANDS PCI Design for Fire Resistance of Precast Prestressed Concrete 2 Chapter 9.4 Post Fire Examination Prestressing steel that has been heated to temperatures below about 750 F and then cooled retains its room temperature strength. If the steel is heated to 900 F and then is cooled, it retains about 70% of its room temperature strength while prestressing steel heated to 1100 F and then cooled retains about half its original strength. Concrete in the bottom flanges surrounding the straight prestressing strands was easy to remove with the use of a light rock hammer, (photo 4). A small hand held air powered impact hammer was used to remove concrete to exposed prestressing strands in Girder 8F directly above the tanker fire, referred to as location F2. The concrete around strands labeled as number 2, 8, 16, and 18 was removed without difficulty. The color of the exposed concrete varied from ash-white at the surface to light tan (buff color) to a depth of about 0.25 inches, and then a normal gray concrete color on the interior. Beyond a depth of about 1 inch, the concrete became difficult to remove with the rock hammer but remained very easy to remove with the air hammer. Possible temperature isotherms shown in Figure 6, were developed by combining visual observation of the concrete color, estimated flame temperatures, ease of concrete removal, and the use of Figure A.4(2) on page 77 of PCI Publication Design for Fire Resistance of Precast Prestressed Concrete. 2 The buff colored 0.25 inch shell indicates possible temperatures of 1700 F. The ease of concrete Photo 4. Crumbling Concrete Girder 8E Photo 5. Buff Color Concrete Girder 8E Figure 6. Possible Isotherms in Bottom Flanges 9
11 removal indicates that concrete temperatures surrounding the lower row of prestressing strands and the exterior strands of the second row exceeded 900 F (strands 1 thru 10 and strands 17 and 18). Contract plans also revealed that the bottom flange soffit provided only 2 inches of cover for the lower bundle of harped strands. Additional observations of warped mild steel reinforcement in the top flanges supported the concern for a temperature induced relaxation of the prestressed strands. Field Test of Prestress Force Prior to removing samples of prestressing strands for material testing, a simple deflection test was performed to calculate the prestressing force remaining in the exposed strands. The deflection tests were conducted on exposed strands with exposed lengths varying from 8 feet to 14 feet. The tests were conducted before the strands were cut and after the cable replacement splices were tensioned. Cable defections were induced by hanging a 4 foot piece of rail provided by the BNSF Railroad. The rail and the attachment cable provided a dead weight of pounds. The cable deflections were measured multiple times by two inspectors using a dial reading caliper with an accuracy of inches. The readings were averaged to Photo 6. Deflection Test Dead Weight provide a deflection for the tension calculation. The exposed span length for the deflection test was measured between the points at which the strands re-entered the concrete. The deflection tests were performed 40 feet above the ground and there was concern about the accuracy of the measurements. The actual location of vertical support points for the exposed strands could extend into the concrete, the displacement measurements Photo 7. Deflection Test Measurement could be affected by random placement of the calipers, and the overall accuracy could also be affected by error in the dead weight. Based on these concerns, it was concluded that the span length measurements were accurate to within 2 inches, the dead weight was accurate to within 0.1 pound, and the deflection measurements were accurate to within inches. Combining all of these possible measurements errors produces a 3% change in the calculated tension. Additional errors may be present in this method but it is believed that the field test had a 10
12 probable accuracy of 5% and was certainly accurate to within 10% of the actual tension force. Figure 7 shows the calculations used in the deflection tests. Conclusions: The prestressed strand force in girders 8F and 8N appeared to be unaffected by the heat of the fire. Strands within the hot zone at locations F2 and N2, (Figure 8), appeared to have retained 100% of their design force despite high temperatures in the surrounding concrete. We have theorized that the steel strands were able to conduct heat to cooler concrete away from the hot zone and prevent a substantial reduction in the yield stress. Transmission of heat away from the hot zone through the steel strands provides an explanation for the delaminations that have been detected in bottom flanges in the Soot colored region shown in Figure 7. Calculation of Strand Tension from Displacement Test Figure 3, only 6 feet from Pier 8. MATERIAL AND STRENGTH TESTING OF STRANDS Three samples of the prestressing strands in Span 8 were removed for lab testing to determine their material properties, Figure 8. Two samples of strand number 2 were removed from Girder 8F. Sample F1 was located near Pier 8 at the boundary of the Soot colored region well away from the hot zone, (Figure 3). The concrete in this region displayed very little damage from the fire. Sample F2 was located directly above the tanker fire in the Extreme-White color region, (Figure 3). Concrete in this region crumbled when tapped with a hand held rock hammer and could be crushed with finger pressure. One sample from Girder 8N, labeled N1, was taken at the eastern edge of the Ash-White color region, (Figure 3). Concrete in this region spalled when struck with a hand held rock hammer resulting in 6 inch long chunks that were difficult to break with hand pressure. The material and strength tests were performed by Smith-Emery Laboratories in Los Angeles, California. The report 6 concluded that the material and strength properties of the strands samples met the requirements for 0.5 inch diameter uncoated seven wire prestress strands as described in ASTM A and ASTM A370. Test results are shown in Table 2. 11
13 Figure 8. Concrete Core Sample and Prestress Stand Sample Locations Table 2. Prestress Strand Sample Material Testing Results 6 ID NUMBER F1 F2 N1 ASTM A Area, inches Yield Strength, lbs. 39,000 40,100 40,100 37,170 Min. Maximum Load, lbs. 43,800 43,700 43,700 41,300 Min. Modulus of Elasticity 26,190,000 27,200,000 28,140,000 Conclusions: The prestressing strands retained the original material properties and design prestress force despite being surrounded by concrete that was significantly degraded by the heat of the fire. 12
14 Section 6 Core Samples for Girder Evaluations CORE DRILLING LOCATIONS Concrete core samples were removed from eighteen locations in the webs and bottom flanges of six girders in Span 8. Vertical cores measuring 3 inches in diameter by approximately 13½ inches deep were removed from ten locations in four girders. Eight of the vertical cores were taken from the hot zone in Girders 8A, 8F, 8G, and 8N. Two vertical cores were taken from in the coolest heat zone of Girder 8E, which was near Pier 8. Eight horizontal cores measuring 3 inches in diameter by 6 inches deep were take in the hot zones near mid-span of Girders 8A, 8E, 8F, and 8N. Figure 9. Concrete Coring Located to Avoid Prestressing Strands and Rebar PETROGRAPHIC EXAMINATION OF HARDENED CONCRETE 7 Dominion Labs received seven concrete cores for petrographic examination. The V-B series cores (A2, F1, G2 and N2) were drilled vertically into the bottom flange of the bridge girders and the H-B series cores (A3, E3 and N1) were taken horizontally into the web section of the girders. No steel reinforcement or tendon pieces were present in the cores examined. Sample Preparation and Examination Methods 7 Cores were prepared for microscopic analysis in general accordance with ASTM C 856, Standard Practice for Petrographic Examination of Hardened Concrete. The cores were 13
15 sawn lengthwise to obtain slabs for lapping. A stereomicroscope was used to observe ground surfaces for crack frequency/distribution and discoloration of paste and aggregate (10-80X). Examination of the cement matrix was performed on 25-micron-thick sections (0.001-inch) prepared from selected locations near both ends and the middle of each core. The microstructure and mineralogy of the aggregate and cement paste were observed using a polarizing microscope at magnifications up to 400X. A muffle furnace was used to heat selected whole pieces and sawn longitudinal slabs from V-B and H-B cores to observe general changes in aggregate and cement paste characteristics. Heating tests were informal and performed only for general comparison purposes. Alkalinity was determined by applying Rainbow Indicator, a phenolphaleinbased solution, to freshly broken surfaces and comparing actual color changes to a standard ph color chart. Common Changes During Heating Phase 7 Up to 200 F (100 C) Little or no concrete damage. Paste expands with loss of some free water, but few or no cracks and no color changes. 500 F (250 C) Localized cracks. Paste is dehydrating with complete loss of free water causing ½% or more decrease in volume. Iron-bearing aggregates begin to acquire pink/red color. 700 F (370 C) Cracks appear around aggregate due to differential thermal properties. Very rapid aggregate expansion of metamorphic and igneous rocks. Numerous microcracks present in cement paste observed in thin-sections. (Most normal weight concrete has lost approximately one half of its compressive strength). 900 F-1000 F (480 C-550 C) Concrete may begin to change to a purple-gray color if enough iron and lime present. Portlandite (calcium hydroxide), a major secondary hydration product, is altering to calcium carbonate. Paste has a patchy appearance in thin-sections F (550 C) Serious cracking of paste and aggregates due to expansion. Purplegray color may become more pronounced F (800 C) Cement paste is completely dehydrated with severe shrinkage cracking and honeycombing. Concrete may begin to be friable and porous F (1200 C) Some components of concrete begin to melt. By 2550 F (1400 C) Concrete is completely melted. Summary of Petrographic Findings 7 Core No. A2-V-B: Outer 2 inches poor condition ( 700 F-900 F); remainder appears sound. Core No. F1-V-B: Outer 1 inch fair condition (up to 200 F); remainder appears sound. 14
16 Core No. G2-V-B: Outer 3½ inches fair condition (up to 500 F); remainder appears sound. Core No. N2-V-B: Outer 2 inches poor condition (up to 700 F); 6-9 inches fair condition (up to 500 F); remainder of concrete appears sound. Core No. A3-H-B: West 2 inches fair condition (up to 500 F); remainder appears sound. Core No. E3-H-B: East ½ inch fair condition (up to 500 F); remainder appears sound. Core No. N1-H-B: West ½ inch fair condition (up to 300 F); remainder appears sound. Petrographer s Conclusion: The most fire-damage observed in the cores examined appears to be present in the sample vertically extracted from Girder N2. Girder A2 also contains some severely damaged concrete in the outermost 2 inches. Girders G2 and A3 appear to have experienced some damage up to 3½ inches deep. Other girder concrete shows little or no damage. Extent and severity of fire-damage to the cores examined was based on changes observed in aggregate and cement paste color, mineralogy and microstructure. Comparisons were made to results obtained in research experiments, documented observations of structure fires, and informal heating of selected bridge samples. WSDOT Comments on Strength and Petrographic Examinations Figure 11. Core Sample G2-V-B Taken from Extreme-White Color Region Figure 12. Core Sample A2-V-B Taken from Ash-White Color Region Compression tests 8 performed on the core samples indicated that much of the girder core has excellent strength with compressive strengths that exceed 9000 psi. Figure 13 shows the strength test profile and petrographic analysis profile for location A2. However, concrete core samples taken from Girders 8A, 8F, and 8G showed numerous physical signs of concrete degradation. For example, the drilling operation was easier to perform than in regions away from the hot zone. The cores were missing 0.75 inches of concrete from the flange soffit, (Figures 11 and 13). They fractured during the drilling process at the bottom row of strands and at the interface of the web and the flange, (Figures 11 and 12). The cores broke at additional locations if not handled with care. Core samples taken at location F1, in the Soot colored region away from the hot zone, were exceptionally difficult to drill and were very 15
17 durable when handled. Theses differences indicated significant heat damage, but the compression tests did not indicate much change or a performance problem. The petrographic analysis supported the conclusion that extensive damage occurred in all 15 girders. However, the petrographer concluded that the worst case of heat damage occurred in the girder furthest from the heat source. Inspection observations did not support this conclusion. Based on visual analysis, and hardness tests, girders directly over the heat source experienced the most extensive damage to the bottom flange concrete. Core samples from these girders broke during the drilling process and concrete that would have provided valuable clues to the petrographer was destroyed. The petrographic analysis was performed on the solid remnants and did not include large portions of damaged concrete that was not strong enough to survive the drilling process. Based on the petrographer's informal heating tests and description of concrete changes during the heating phase, WSDOT was convinced that surface temperatures on the bottom flange soffits exceeded 1500 F during the fire. Figure 13. Compression Test Profile Core A2-V-A 8, Petrographic Profile Core A2-V-B 8, Photo Core A2-V-B 7. 16
18 Section 7 Pier 8 and Pier 9 Damage NTIS GCR Response of High Performance Concrete to Fire Conditions Chapter 2.1 Overview At the beginning of the fire, the temperature of the exposed side of the concrete slab will rise rapidly. Free moisture, both liquid and vapor, will migrate toward the cold side of the concrete... As the temperature of the fireexposed side increases, any free liquid water will boil off and migrate toward the colder side where it will condense... However, high-strength concrete is not very permeable to water vapor and is even less permeable to liquid water... Eventually, liquid water may fill the concrete pores at a location ahead of the temperature front, creating a condition known as moisture clog, where the liquid water blocks the transfer of water vapor toward the cold side of the slab. Under such conditions, the pore pressure will result in forced convective mass transfer of superheated steam and air to the heated side of the slab. Column 8B was approximately 88 feet from the source of the fire a the railroad tanker, (Figure 14), and showed no significant effects on the side facing the tanker. However, the east face was exposed to methanol flames emanating from the adjacent drainage ditch. Concrete spalling occurred in the bottom 8.5 feet of the column, Photo 8. The concrete spalls were found to be less than 1 inch in depth. No reinforcement was exposed and no concrete delaminations were discovered. The remaining concrete was not discolored and appeared to have serviceable strength. Columns 9A and 9B were approximately 60 feet from the source of the fire, (Figure 14). Concrete spalling occurred for the full height of the columns on the south face of Column 9A and the southwest face of Column 9B. The spalled concrete thickness frequently exceeded 1½ inches resulting in areas of exposed spiral reinforcement. The remaining concrete was not discolored and appeared hard but delaminated. Exposed aggregate appeared to be in good condition except for one specific type of red rock. This rock was found in many locations to be highly fractured and could be crumbled between a persons fingers. The rock was similar in appearance to red brick and contained a white colored mineral or granule. Efforts were made to remove all of the delaminated concrete from the columns with the use of air hammers but the removal process was stopped at the outer edge of the vertical reinforcement at a depth of approximately 2¼ inches. Many areas of the remaining concrete in both columns sounded hollow indicating that delamination fractures continued inside the column reinforcement cage. A core sample taken from Column 9A at 37 feet above the base of the column (12.92 feet below the top of the column) showed concrete delamination had occurred at a depth of 5¼ inches from the original surface of the column. 17
19 COLUMN EXPOSURE & CONDITION STATE MAP Figure 14. Pier 8 and Pier 9 Heat Exposure and Damage 18
20 COLUMN 9A Photo 9. Pier 9 Core Sample Location CORE SAMPLES Five (5) 2 diameter by 7 long core samples were removed from the south face of Column 9A and labeled at Cores 9A-1 to 9A-5. Three (3) 2 diameter core samples were removed from the south face of the crossbeam at Pier 9. The cross beam coring effort encountered steel reinforcement at two locations below Girder F, referred to as Cores 9xb-FA and 9xb-FB 9. Core sample lengths were limited to 2 and 1.5 respectively. The crossbeam core sample retrieved below Girder G, Core 9xb-G, avoided the reinforcement and produced a core length of 7. Core samples from Column 9A confirmed the existence of delamination fractures in the interior core of the column. The maximum depth of a delamination fracture was found to be 5 from the original surface and more than 1inch inside of the vertical column reinforcement, Photo 12. Aside from the delamination fractures, the concrete remaining on Column 9A appeared to have very good strength. Core sample from Crossbeam 9 did not show any abnormalities and indicate that the crossbeam sustained only superficial damage from the fire. 19
21 COLUMN REPAIR STRATEGY The recommended repair strategy for the damaged area of Column 8B is to perform a simple concrete pour-back with dry concrete mix to provide environmental protection for the column reinforcement. The concrete repair must be performed according to WSDOT repair proceedure, ie; Concrete Removal: Remove damaged concrete with hand held air hammers. Saw cut perimeter of damaged areas with a ¾ deep / vertical cut. Chip out all loose and soft concrete material within the saw cut area. Provide a minimum of ¾ clearance around all reinforcing steel bars that are exposed 50% or more after removal of the loose and soft material. Thoroughly clean contact surface area. Formed Vertical Repair Surface Treatment: Prior to placement of patch material, thoroughly wet the contact surfaces with potable water. Patch Material: Non-shrink grout that can be pumped; such as Masterflow 928 Grout manufactured by Master Builders, or a concrete mix similar to the approved mix used in the structure. Patch Placement: Pumped Grout: If pumped grout is used, construct a pumping port at the low spot of the repair area. Construct one or more stand pipes located at the high points of the repair area (to provide a head for the concrete). Concrete Mix: If a concrete mix is used, construct stand pipes at high points of the repair area accessible to place the repair concrete. Repair area must be accessible to a vibrator. If vibrator can not be used through the stand pipe, form windows must be utilized for vibrator access. Air relief holes may be required at high points of the repair area. The recommended repair strategy for Column 9A and Column 9B is to perform a seismic column retrofit using a steel confinement shell and grout to fill the annular space between the steel shell and the column. The delaminated concrete in Column 9A and 9B present a concern for the performance of the columns during a seismic event. Providing a steel shell will assure confinement of the column core and assist with the placement of grout or concrete to protect the exposed reinforcement. CROSSBEAM REPAIR STRATEGY Structural repairs of the crossbeams at Pier 8 and Pier 9 are not recommended. There is no evidence that the crossbeams experience any degradation of capacity. However, cosmetic treatments such as a light sand blast and application of a pigmented sealer would remove and cover the soot and charred nylon on the south face of Pier 9. 20
22 Section 8 Repair or Replace Repair Option A successful repair or replacement of the damaged girders in Span 8 must meet the following performance criteria. Restoration of the pre-fire ultimate strength capacity. Restoration of pre-fire service life, the bridge was newly constructed in Restoration of pre-fire inspection and maintenance schedule typical for prestress girder bridges. Maintain visual inspection access to structural components for the detection of corrosion in prestress strands and mild steel reinforcement and detection of loss of concrete compressive strength in the girders and deck slab. Maintain easy access for bridge maintenance typical for prestress girder bridges. Minimize traffic delays and traffic congestion while repairs or replacement construction is being performed. Perform construction activities without being encumbered by frequent and continuous use of the railroad tracks below Span 8. The service load moment capacity of prestress bridge girders is controlled by maximum allowed tension in the bottom flange. At WSDOT, prestress girders are required to remain fully compressed under the maximum service load condition. That is to say, zero tension is allowed in the bottom flange concrete. Any tension that occurs is assumed to cause the formation of concrete cracks that lead to corrosion of the prestressing strands. Girder concrete provides important protection for the steel strands and its integrity must be preserved to achieve a normal service life of the bridge. Repair strategies for the damaged bottom flanges must address the issue of tension in pour back concrete and how corrosion resistance will be established. Replacement concrete will not have the advantage of being in a pre-compressed state unless additional prestress is added or the bridge is preloaded during the repair process. The service life of prestress girder bridges is well documented and this type of bridge is one of the most durable and long lasting types of bridges constructed in Washington. Many prestress girder bridges are approaching 50 years of service life. They display almost no deterioration in the girders and have required very little maintenance to preserve their service requirements. The Puyallup River Bridge discussed in this paper was newly constructed in An inspection of the bridge in November, 2002, just prior to the fire, found the girders in Span 8 to be in excellent condition. A small rock pocket on the bottom flange of Girder 8N and construction related rust staining on the east face of Girder 8I were the only defect. Repair ideas fell into one of the three strategies listed below. 1. Encasement. 2. Hydro-blast / Preload / Pour-Back. 21
23 3. Hydro-blast /Prestress / Pour-Back. ENCASEMENT: The objective of the encasement alternatives is to provide some type of permanent confinement around the damaged girders to prevent further deterioration. The fire effectively destroyed the concrete protection for the prestressing strands. If the service life could be restored, the post fire strength of the bridge might be acceptable. Encasement alternatives included: shot-crete and wire mesh, stay in place steel forms with pressurized epoxy grout, stay in place forms with a combination of concrete and pressurized epoxy grout, and removable forms with concrete and pressurized epoxy grout. One major draw back of the encasement alternatives is the added weight of the encasement shell and a corresponding reduction in live load capacity of the girders. Another drawback is the difficulty a protective shell creates for future bridge inspections. All encasement alternatives would hide the damaged concrete and prevent visual inspections from detecting corrosion of the prestressing strands and continued deterioration of the damaged concrete. An encasement repair strategy would require future bridge inspection to be made with some type of specialized non destructive testing technology. HYDRO-BLAST / PRELOAD / POUR- BACK: The objectives of this alternative is to safely remove and replace all damaged concrete, (Figure 15). Pre-compression would be added to the bottom flange by adding a vertical preload to the bridge deck prior to placing the concrete. Epoxy grout would be injected into the cold joint between the new concrete and remaining Figure 15. Hydro-Blast / Preload / Pourgirder concrete. The pre-load would be Back removed to compress the pour back concrete. HYDRO-BLAST / PRESTRESS / POUR-BACK: The objectives of this would be similar to the previous alternative but prestress would be used instead of a pre-load, (Figure 16). Compression in the new bottom flange concrete would be established by installing bonded prestress strands. The damaged concrete would be removed with hydro-blast methods The prestress strands would be installed above and below the existing bottom flange. A Figure 16. Hydro-Blast / Prestress / Pour- Back strand anchorage point would be established on the far side of Pier 8 and a jacking point would be established on the far side of Pier 9. Epoxy grout tubes and mild steel stirrups would be attached to the remnants of the bottom flange prior to the placement of new concrete. The pour back concrete would be placed, epoxy would be injected into the cold 22
24 joint region, and the supplemental prestressing strands would be cut at Pier 8 and Pier 9. Release of the strand anchorages would transfer tension into the girder and establish compression in the pour back concrete. Replacement Option Objectives of the replacement strategies are to restore the service life and ultimate moment capacity by replacing all 15 girders in Span 8, (Figure 17). The demolition and construction sequences must minimize disruption to highway and railway operations. Three alternative design concepts were considered. Alternative 1, replace In-Kind with 15 lines of W74G girders using the As-Built specification for concrete strength and strand diameter. Alternative 2, replace with 10 lines of W74G girders using 9000 psi concrete and 0.6 inch diameter prestressing strands. Alternative 3, (Figure 18), replace with 8 lines of WF74G girders using 9000 psi and 0.6 inch diameter prestressing strands. The WF74G girder section is a new long span section with greater capacity than the W74G girders. The construction sequence for all three alternatives would be similar. Traffic would be reduced to two lanes and diverted to one side of the span. The unloaded side would be separated with a longitudinal cut along the center of the bridge deck and with transverse cuts at the face of the end diaphragms. Additional cuts in the deck would be made to allow the girders to be removed and lowered to the ground for demolition. Temporary bearing seats Figure 17. Span 8 Replacement Profile would be added to the crossbeams at Pier 8 and Pier 9 to support the new girders. New end diaphragms would be doweled into and cast against the existing end diaphragms to provide permanent support for the new girders. Longitudinal reinforcement in the deck would be extended into Span 7 and Span 9 to re-establish live load continuity. The sequence would be repeated for the other side and a longitudinal closure pour in the deck would join the two units. Figure 18. Span 8 Replacement Section 23
25 Cost Comparison Cost estimates were developed to compare the Hydro-blast/Preload/Pour Back strategy with a replacement strategy using 8-Lines of WF74G girders. The cost study shows that a replacement using high performance concrete and the new WSDOT prestress girder section is equal to the cost of repair. Tables 3 and 4 list the comparative costs. The replacement option also resolves risks that are associated with the repair options. Repair activity could cause additional structural damage to the girders. Repair work would be made directly over the railroad resulting in frequent disruptions to railway operations and repair activities. The replacement also provides a clear forecast of long term performance and liability. Concrete girder repairs are typically more problematic than new high quality precast girders. The conclusion of the WSDOT Bridge Office is that a replacement strategy provides a lower long term cost and a much lower long term risk. Table 3. Cost of Repair UNIT ITEM UNIT QUANTITY COST COST HYDRO-BLAST / POUR BACK REPAIR OPTION MOBILIZATION L.S. 1 L.S. 78, GIRDER REPAIR S.F , EPOXY CRACK SEALING EST. 1 EST. 50, FORCE ACCOUNT COLUMN JACKETING L.S. 1 L.S. 110, PIGMENTED SEALER S.F , Table 4. Cost of Replacement UNIT ITEM UNIT QUANTITY COST COST 8 - LINES OF WF74G REPLACEMENT OPTION MOBILIZATION L.S. 1 L.S. 78, REMOVING SPAN 8 S.F , EPOXY COATED ST. REINF. BAR LBS , ST. REINF. BAR LBS , CONC. CLASS 4000D C.Y , CONC. CLASS 4000 C.Y , TOTAL = 867, SAY 870, P.C. GIRDERS (W74G) L.F , TRAFFIC BARRIER L.F , CONDUIT PIPE 2 INCH DIAM. L.F , COLUMN JACKETING L.S. 1 L.S. 110, TOTAL = 868, SAY 870, Section 9 Summary In summary the railroad tanker fire subjected all fifteen girders in Span 8 to intense heat in a short period time. Flame temperatures approached 3000 F and surface temperatures on the soffit of the prestressed girders may have reached 1700 F. Internal temperatures in the bottom flange and webs ranged from 1100 F to 500 F. The concrete heating rate was rapid and the cooling rate was accelerated by water spray from fire trucks. Both of these factors contributed to concrete damage in the girders and the adjacent columns. The prestressing steel survived the fire without noticeable loss of prestress despite being embedded in concrete that was heated to 900 F. The conductive property of steel 24
26 apparently transferred heat to cooler regions of the girders and prevented yielding of the steel in the hottest regions. Petrographic analysis confirmed extensive heat penetration and micro cracking in Girder 8N that was furthest from the source of the fire. Girders directly over the fire displayed more extensive damage with the loss of concrete integrity around the prestress strands in the bottom flange. Concrete in the hot zone crumbles and spalls with light blows from a hand held rock hammer and most of the bottom flange concrete can easily be removed with the use of hand held air powered impact hammers. Replacement of Span 8 with eight lines of WF74G girders is favored over all suggested repair strategies. A replacement can be made for approximately the same cost as a repair. and it restores the bridge to its pre-fire strength and service life. Columns will be repaired with steel jackets and grout injection typically used for seismic retrofit designs. The overall seismic response will be analyzed to consider the change in column stiffness and mass of the superstructure. CONCLUSIONS Risk of fire damage for bridges over railroad yards and switching complexes should be considered in the design of highway bridges. Track switches, changes in track alignment, and soft rail beds are common area for derailments and coupler jumping. Experimental data and literature to aid in analyzing the effects of tanker fires under bridges is limited. Most all experimental data, research, and design documents pertain to building fires and their affects on concrete within the buildings. Tanker fires caused by highway fuel truck or railway tanker cars are explosive in nature and greatly exceed the temperatures and rate of heating prescribed in the ASTM fire resistance test. Additionally, the heat transfer mechanism in taker fires is dominated by radiant energy as opposed to hot air and heat convection. Additional research addressing highway structures and fuel tanker fires would be beneficial. Rapid identification of concrete damage zones can be made by observing the variation in concrete color immediately following a fire. The visual color mapping performed for this bridge fire correlated very well with variations in concrete hardness. Inspectors easily established the general shape and boundaries of four damage levels. The rebound hammers test validated the visual observations and provided an objective description of damage areas. 25
27 References 1. Pharmco Products, Inc., Methanol, Material Safety Data Sheets, Revision 1.0, October, Armand H. Gustaferro (ahg) and Leslie D. Martin (ldm), Design for Fire Resistance of Precast Prestressed Concrete, Prestressed Concrete Institute, MNL , Second Edition, Robert T. Ratay (rtr), Forensic Structural Engineering Handbook, McGraw- Hill, Copyright Allan T. Kirkpatrick (atk), Adiabatic Flame Temperature, Colorado State University Web Site, 5. C. David Cooper (cdc) and F. C. Alley (fca), Air Pollution Control, Table A.6 and Table B.6, Waveland Press, Inc., Second Edition, V. Andrew Tan, ½ inch Uncoated Seven Wire Prestress Strand Test, Smith- Emery Laboratories, Project , February, Dick M. Glasheen (dmg), Petrographic Examination of Hardened Concrete WSDOT Bridge 509/11, Dominion Labs, Inc., Project No. S2084, March, Stuart J. Carter (sjc), Fire Damage Concrete Testing, Puyallup River Bridge, Mayes Testing Engineers, Project No. S2084, June, Douglas F. Burke (dfb), Marine Concrete Repair, Naval Facilities Engineering Service Center, March 12, Daniel R. Flynn (drf), Response of High Performance Concrete to Fire Conditions: Review of Thermal Property Data and Measurement Techniques, National Institute of Standards and Technology, NIST GCR , March,
Evaluating. A Case Study
A Case Study Evaluating by Richard B. Stoddard, Washington State Department of Transportation In December 2002, a railroad tanker collision caused a fire under a prestressed concrete girder bridge crossing
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China
Advanced Materials Research Vols. 163-167 (2011) pp 1147-1156 Online available since 2010/Dec/06 at www.scientific.net (2011) Trans Tech Publications, Switzerland doi:10.4028/www.scientific.net/amr.163-167.1147
September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900
September 1, 2003 CONCRETE MANUAL 5-694.900 5-694.901 GENERAL CONCRETE PAVEMENT REHABILITATION 5-694.900 Concrete Pavement Rehabilitation is an extremely valuable tool of the Minnesota Department of Transportation
Detailing of Reinforcment in Concrete Structures
Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
PRE INSTALLATION MANUAL
REINFORCED CONCRETE PIPE PRE INSTALLATION INSPECTION & REPAIR MANUAL Kentucky Transportation Cabinet Kentucky Department of Highways Division of Materials 1227 Wilkinson Boulevard Frankfort, KY 40601 (502)
Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14
Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318
Project Report. Structural Investigations Hotel del Sol Yuma, Arizona
Project Report Structural Investigations Yuma, Arizona Prepared by: 2619 Spruce Street Boulder, CO 80302 303-444-3620 Prepared for: Principle Engineering Group, Inc. 833 East Plaza Circle, Suite 100 Yuma,
SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.
SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM Installed in Pre-engineered Steel Buildings Provides Lowest Cost Construction Method for CORROSIVE AND WET Environments PREFERRED SOLUTIONS, INC.
MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS
MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS May 29, 2013 Revision B Structural Guideline for Design and Installation Holes in Composite Floor Slab Terminal 3, Departure Level
NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries
Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Introduction Wastewater of petrochemical industries and refineries contains high amounts of emulsified aliphatic or
Residential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
SECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
Structural Failures Cost Lives and Time
Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)
University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage
University of Missouri Hospitals and Clinics Structural Repair and Protection of Post-tensioned Parking Garage 1 University of Missouri Project The University of Missouri Health Care Patient and Visitor
Pavement Patching Repair for AC and PCC Pavement Surfaces. Vern Thompson www.crafco.com
Pavement Patching Repair for AC and PCC Pavement Surfaces Vern Thompson www.crafco.com Overview and Objective New Methods For Pavement Patching-Overview What are they How they are applied New Methods Secti
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
Basement & Foundation Damage
Basement & Foundation Damage Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case
Metropolitan Builders Association Masonry & Concrete Standard
Metropolitan Builders Association Masonry & Concrete Standard Background Masonry and concrete work in residential construction often provides the base structure upon which the house is built or as a veneer.
Measuring the Condition of Prestressed Concrete Cylinder Pipe
Measuring the Condition of Prestressed Concrete Cylinder Pipe John Marshall, P.E.I, I J.W. Marshall and Associates, and Paul S. Fisk, President NDT Corporation Introduction Prestressed Concrete Cylinder
Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements
University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted 02-20-14)
POLYMERIC CONCRETE BRIDGE DECK OVERLAY (Adopted 02-20-14) Description The polymeric concrete bridge deck overlay shall consist of an epoxy polymer that acts together with special aggregate to form an overlay
Concrete Repair. Applications and Procedures
Concrete Repair Applications and Procedures Objectives Identify what surface preparation is needed Identify typical modes of failure and testing methods How to choose the correct material for the repair
GARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION
GARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION Issam ElKhatib, P.Eng., Dennis Baxter, P.Eng. Totten Sims Hubicki Associates, Canada Abstract The rehabilitation history of the Garden City Skyway Bridge
Residential Foundations and Basements
Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article
Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units
Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units Thomas Kline Director- Concrete Repair Solutions STRUCTURAL TECHNOLOGIES, LLC Houston, Texas USA November
Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training
Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline
CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.
CONCRETE REPAIR GUIDELINES Concrete repairs can be broken down into four basic types, plus special repairs and planing. Note: It is recommended that investigation into soundness of pavement be performed
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry
CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS
AN ERGONARMOR COMPANY TECHNICAL INFORMATION SPECIFICATION FOR INSTALLATION 07/11 SUPERSEDES 04/00 PAGE 1 OF 6 CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS 1. SCOPE 1.1 This specification
Virginia Approach Spans
Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 [email protected]
Garver Feed Mill Condition Evaluation
Garver Feed Mill Condition Evaluation OUTLINE Brick masonry overview Condition assessment & methodology Project overview Existing conditions Stabilization Probable costs Summary BRICK MASONRY OVERVIEW
BRIDGE REHABILITATION. Maintaining and Repairing Existing Structures
BRIDGE REHABILITATION Maintaining and Repairing Existing Structures Types of Bridge Rehabilitation Bridge Deck Overlays Bridge Deck Widening or Replacement Making Bridge Decks Continuous and/or Composite
REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE
REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE A.Rito Proponte, Lda, Lisbon, Portugal J. Appleton A2P Consult, Lda, Lisbon, Portugal ABSTRACT: The Figueira da Foz Bridge includes a 405 m long cable stayed
The following definitions apply with regard to requirements specified in this document:
GUIDELINES FOR INSTALLATION OF TEMPORARY AND PERMANENT ABOVEGROUND DIESEL FUEL TANKS FOR EMERGENCY AND STANDBY POWER SYSTEMS LOCATED OUTSIDE OF BUILDINGS For Use by Unidocs Member Agencies or where approved
Preservation, Repair and Rehabilitation of Concrete Bridges, Pavements and Tunnels in Virginia
Preservation, Repair and Rehabilitation of Concrete Bridges, Pavements and Tunnels in Virginia International Concrete Repair Institute Spring Convention Reno, Nevada March 20, 2014 Michael Sprinkel, PE.,
The minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs
Long Life Concrete Pavement Joint Performance Joint Rehabilitation Gary Fick, Trinity Construction Management Services, Inc. Representing the National CP Tech Center Driving Forces for Concrete Pavement
High Performance PSA in Sheet Membrane in Water Protection
High Performance PSA in Sheet Membrane in Water Protection Xia Cao, Senior R&D Chemist, W. R. Grace, Cambridge MA 02140 Jyoti Seth, Strategic Program Leader, W. R. Grace, Cambridge MA 02140 Concrete is
Minor Cracks in Horizontal Surfaces
Cracks, chips and broken or flaking areas in concrete are not only unsightly, they can lead to further deterioration of the surface. The result is a costly replacement project as opposed to a simple repair.
Installation PowerPoint for Grasscrete Formers
Installation PowerPoint for Grasscrete Formers 1 This document describes the two single-use tools utilized to create the Grasscrete product. The original Former is a vacuum formed light gauge plastic mold
COMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
MEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525
1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 To: From: Date: Subject: Mr. Thomas Gibson, City of St. Petersburg Jeffrey D. Malyszek, PE and Deborah C.
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
CAUSES, EVALUATION AND REPAIR OF CRACKS IN CONCRETE
3.0 Causes and control of cracking: 3.1 Plastic Shrinkage Cracking: It occurs within 1 to 8 hours after placing, when subjected to a very rapid loss of moisture caused by a combination of factors, which
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the
Rehabilitation of an Aging Concrete Reservoir Adit Tower
Rehabilitation of an Aging Concrete Reservoir Adit Tower Raymond S. Tombaugh, Senior Coatings Consultant KTA-Tator, Inc. and Mongkol Mahavongtrakul, P.E. Corrosion Control Contract Manager San Francisco
March 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202
Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request
Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling
7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling Asphalt Pavements 7-7 Chapter 7 Pavement Rehabilitation Pavement rehabilitation can be accomplished
STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
WSDOT Bridge Elements
Chapter 4 WSDOT Bridge Elements 4.01 List of WSDOT Elements by Number 12 Concrete Deck............................... 4-14 13 Bridge Deck Surface........................... 4-14 14 Fully Supported Concrete
UX-30 PERFORMANCE TESTING SUMMARY REPORT Revision 0
UX-30 PERFORMANCE TESTING SUMMARY REPORT Revision 0 Prepared By: Patrick L. Paquin, EnergySolutions Date Reviewed By: Mirza I. Baig, EnergySolutions Date Approved By: Thomas F. Dougherty, Columbiana Hi
Meeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
PC-Concrete Injectable Concrete Anchoring and Repair System
PC-Concrete Injectable Concrete Anchoring and Repair System DESCRIPTION: PC-Concrete is a two component (1:1 ratio), 100% solids, high modulus, structural epoxy paste. PC-Concrete is a solvent free, no
Cold Weather Concrete Practices
Cold Weather Concrete Practices The Information below is an outline of common practice for residential foundation placement and winter construction utilize Edmonton and surrounding Area. Conditions in
PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta
PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major
Analysis II Façade Redesign: Architectural Precast Panels
Analysis II Façade Redesign: Architectural Precast Panels Analysis II Façade Redesign: Architectural Precast Panels Overview: This analysis covers the comparison of the current EIFS façade and my proposed
Chapter 5 Bridge Deck Slabs. Bridge Engineering 1
Chapter 5 Bridge Deck Slabs Bridge Engineering 1 Basic types of bridge decks In-situ reinforced concrete deck- (most common type) Pre-cast concrete deck (minimize the use of local labor) Open steel grid
Field Welding Inspection Guide
Field Welding Inspection Guide Assistance in interpretation of any specification or questions concerning field welding issues can be obtained from the Office of Materials Management, Structural Welding
Weight Measurement Technology
Kistler-Morse (KM) introduced bolt-on weight measuring systems three decades ago. These devices featured Walter Kistler s invention, the Microcell. Over the years, many improvements were made to the Microcell
Overhang Bracket Loading. Deck Issues: Design Perspective
Deck Issues: Design Perspective Overhang Bracket Loading Deck overhangs and screed rails are generally supported on cantilever brackets during the deck pour These brackets produce an overturning couple
ASSESSMENT AND PROPOSED STRUCTURAL REPAIR STRATEGIES FOR BRIDGE PIERS IN TAIWAN DAMAGED BY THE JI-JI EARTHQUAKE ABSTRACT
ASSESSMENT AND PROPOSED STRUCTURAL REPAIR STRATEGIES FOR BRIDGE PIERS IN TAIWAN DAMAGED BY THE JI-JI EARTHQUAKE Pei-Chang Huang 1, Graduate Research Assistant / MS Candidate Yao T. Hsu 2, Ph.D., PE, Associate
Guide for SOLID CONCRETE BLOCK SEALS
Guide for SOLID CONCRETE BLOCK SEALS July, 2006 Mine Safety and Health Administration SOLID CONCRETE BLOCK SEAL Formersection 30 CFR 75.335(a)(1) specifies requirements for seals constructed using solid
US 51 Ohio River Bridge Engineering and Environmental Study
US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
Chapter. Restoration of Damaged Structures
5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.
June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina
Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain
METHOD OF TEST FOR UNIT WEIGHT OF FRESH CONCRETE
STATE OF CALIFORNIA BUSINESS, TRANSPORTATION AND HOUSING AGENCY DEPARTMENT OF TRANSPORTATION DIVISION OF ENGINEERING SERVICES Transportation Laboratory 5900 Folsom Blvd. Sacramento, California 95819-4612
Lighthouse Engineering, L.L.C.
Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: [email protected] Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
DIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
Optimum proportions for the design of suspension bridge
Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering
SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS
Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and
NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE
NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE GENERAL a. These specifications may be used in whole or in part by any party without
07 21 19 Guide Specification STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
07 21 19 STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM 7819 Broadview Road Cleveland, OH 44131 800-522-4522 February, 2011 SPEC NOTE: This guide specification is intended for use when specifying
SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
SECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
By Narendra K. Gosain, Ph.D., P.E., Ray F. Drexler, P.E., and Dilip Choudhuri, P.E.
Structural Forensics investigating structures and their components Evaluation and Repair of Fire-Damaged Buildings By Narendra K. Gosain, Ph.D., P.E., Ray F. Drexler, P.E., and Dilip Choudhuri, P.E. A
ABSTRACT 1. INTRODUCTION 2. DESCRIPTION OF THE SEGMENTAL BEAM
Ninth LACCEI Latin American and Caribbean Conference (LACCEI 11), Engineering for a Smart Planet, Innovation, Information Technology and Computational Tools for Sustainable Development, August 3-, 11,
REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE
Proceedings of the International Symposium on Engineering Lessons Learned from the 2011 Great East Japan Earthquake, March 1-4, 2012, Tokyo, Japan REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE
Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.
P-5 The P-5 is hot forged from carbon steel. The formed head provis spherical seating that the Lifting Eye engages, while a disc-shaped foot is embedd in the concrete. Due to its being a forged part, the
The unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
