Fire Damage Evaluation. Concrete Garage. Vehicular fires in parking garages are not an
|
|
|
- MargaretMargaret Scott
- 10 years ago
- Views:
Transcription
1 Fire Damage Evaluation and Repair of Precast Concrete Garage By Alfredo E. Bustamante and Michael W. Lee Vehicular fires in parking garages are not an infrequent event. Research by the authors indicates that on average, one fire occurs each day in a parking garage somewhere in the U.S. When fires occur, the elevated temperatures and associated thermal shock associated with the fire and subsequent fire-suppression activities can result in damage to nearby structural components. Fortunately, concrete structures generally have the ability to perform well both during and after exposure to elevated temperatures. This is due to concrete s high capacity for heat absorption, its relatively low thermal conductivity, and the relatively short duration of such fires. The evaluation of the extent of damage a concrete structure may have sustained from a fire, as well as the adequacy of affected members to remain in service, involves a systematic assessment of post-fire conditions. This article describes an evaluation of fire damage and subsequent development and implementation of repairs to the Woodlands Waterway Marriot Parking Garage located in Spring, TX. The garage is a four-story parking structure built in The structural framing consists of precast Fig. 1: Double-tee flange soffit and stem affected by the fire concrete double tees, inverted tees, wall panels, and columns. The double tees were fabricated using lightweight concrete. A field-placed concrete topping slab is present over the double tees. In October 2008, a fire occurred in the northwest portion of the second level of the garage. The fire had a duration of 30 to 45 minutes and involved three parked vehicles. The fire caused readily visible surface damage to the double tees and supporting wall panels located directly above and adjacent to the conflagration. Damage Evaluation An evaluation of the structural elements affected by the fire was conducted to determine the extent of the damage and to design required repairs. Elements indicating significant visible damage included three double tees, three wall panels, and six double-tee support haunches. Detailed field observations revealed localized concrete spalls, cracks, and delaminations in the double tees, haunches, and wall panels. The most severe distress occurred in the double tee stems and flange soffits (Fig. 1). The flange soffit spalling was generally less than 1 in. (25 mm) and exposed portions of embedded welded wire reinforcement. Longitudinal spalls were noted at the corners of the stems, and lengths up to 10 ft (3 m) of welded wire reinforcement were visible. The spalls also exposed the bottom prestressing strand in several stems for lengths up to approximately 15 ft (4.6 m). The spalling occurred due to the following material and structural response mechanisms 1 : 1. Thermal gradient: During the early stages of the fire, rapidly heated double-tee flange surfaces expanded at a greater rate than the cooler underlying material, resulting in a significant thermal gradient and buildup of stresses near the surfaces. When the shear/tensile capacity of the concrete was reached, a failure plane developed and an outer layer concrete was disengaged. 2. Restraint: Upon heating, the surface concrete of the stem or haunches expanded in all directions. At corners, this thermal growth resulted in expansion from two orthogonal 8 Concrete Repair Bulletin september/october
2 directions. This region of the corner was restrained by the relatively cooler, underlying concrete. Upon further heating, the tensile capacity of the concrete near the corner was reached, and cracking or expulsion of this portion occurred. A series of cracks, typically 1 to 3 in. (25 to 76 mm) from the corners developed, as the thermally growing member shed its corners. Craze cracking was noted in vertical faces of the stems throughout the fire-affected area. Regions judged to have been located closer to the fire and thus to have experienced higher thermal exposure exhibited greater cracking. Craze cracking of surfaces reflect an irrecoverable shrinkage of a shallow zone of the paste matrix due to dehydration associated with the thermal excursion. This condition typically produces a fine, but very shallow and structurally inconsequential, network of cracks that does not impair the overall integrity of the affected member. The detailed field observations were supplemented with soundings to aid in assessing the near-surface condition of the concrete. Based on results of the observations, soundings, and other evaluation, it was determined that the post-fire conditions were consistent with a normal anticipated response to a moderate fire exposure. Therefore, it was concluded that the affected members were able to provide future strength and serviceability by implementing appropriate repairs to address spalls and cracking, and to restore member geometry. Structural Analysis A limited structural analysis was performed to assess the possible effects of the damaged concrete on the overall load-carrying capacity of the double tees. The analysis was performing using design information indicated on fabrication drawings provided by the precast manufacturer. Flexural and shear capacities were determined using proprietary software for the analysis and design of prestressed concrete beams. The focus of the analysis was on the portion of the double tees within 20 ft (6.1 m) of the support. Of greatest concern was the possible detrimental effect of loss of bond at the bottom prestressing strand due to the corner spalls. To evaluate this possible effect of loss of bond, the bottom strand was modeled as being intentionally debonded, or blanketed, for a distance of 15 ft (4.6 m) measured from the support. In addition, the effect of the craze cracking in the stems was conservatively modeled by reducing the specified concrete compressive strength by 25%. Results of the structural analysis indicated that the flexural capacity of the affected double tees was adequate to resist code-required design loads. The analysis, however, also showed that the shear capacity of the double tees could be slightly inadequate. Therefore, it was decided to provide supplemental shear reinforcing over a portion of the double-tee span. Repairs The repairs consisted of concrete patches, double-tee stem strengthening, haunch extension, and neoprene pad replacement. The double-tee strengthening is a notable feature of the repairs and thus is described in greater detail. Concrete Patch Repairs The spalled areas at stems, wall panels, and double-tee flanges were patched using conventional concrete repair methodologies. Patch repairs for corner spalls of the stems generally consisted of the removal of loose and unsound concrete, preparation of the exposed steel reinforcement, installation of stainless steel threaded rod anchors, and form-andpour application of a polymer-modified portland cement-based patching material. The perimeter of the patch was saw cut to avoid feather edges. In addition to the threaded rod anchors, longitudinal threaded rods were installed along the corner spall repairs to control shrinkage cracking of the patch material. The spall repair at the flange soffit was accomplished using low-pressure spray-applied mortar (Fig. 2). Trowel-applied and form-and-pour repair techniques were considered; but given the overhead application, it was felt that the low-pressure spray technique would provide a higher level of assurance because the repair material was bonded to the sound concrete. Exposed steel reinforcement was cleaned by wire brush/hand methods and coated with an epoxy-modified cementitious material to improve bond with the repair material and provide enhanced corrosion protection. Fig. 2: Application of spray-applied mortar on double-tee flange soffit september/october 2009 Concrete Repair Bulletin 9
3 Double-tee Stem Strengthening Common techniques for double-tee stem strengthening include steel plates and external posttensioning (EPT). In the past several decades, repair techniques using externally bonded fiber-reinforced polymer (FRP) systems have emerged as an effective means to repair and strengthen concrete structures. For this project, it was decided that a FRP-based repair approach provided the needed structural enhancements while assuring an aesthetically pleasing solution as an added benefit. Design of the FRP system was performed following guidelines presented in ACI 440.2R Two plies, or layers, of a bidirectional carbon FRP system were used. The first layer consisted of a U-wrap configuration along the portion of the stem located approximately 15 ft (4.6 m) from the support. This layer provided the necessary supplemental shear capacity. The upper end of the fabric was extended to within several inches of the flange soffit. In addition to providing the shear capacity, the fabric also served to confine the repair material for the corner spalls. The second layer consisted of a short section of fabric placed at the end of the stem. This layer was oriented in a plan view U-shaped configuration such that it extended around the end of the stem (Fig. 3 and 4) and for 3 ft (0.9 m) on each face toward the midspan of the member. The purpose of the second layer was to provide supplemental strength to a localized region of the stem exhibiting more extensive cracking. In general, installation of the FRP system proceeded in the following manner: 1. Patch materials along the stem corners were allowed to cure, and cracks 0.01 in. (0.3 mm) and wider were epoxy injected. 2. Surface preparation was specified to achieve a texture equivalent to ICRI Concrete Surface Profile (CSP) 3. Corners at the end of the stems were ground to eliminate sharp edges. 3. Initial cutting of the FRP material was performed in the presence of the fabric manufacturer. 4. A solvent was applied to the concrete surface immediately prior to epoxy adhesive application. 5. The FRP material was saturated in the epoxy adhesive. 6. After allowing the solvent to flash off the concrete surface, the epoxy adhesive was applied to the concrete surface and allowed to set for several minutes. Fig. 3: Double-tee stem FRP repair Fig. 4: (a) Schematic plan view of end of double-tee stem showing FRP layers; and (b) installation of FRP Layer 2 10 Concrete Repair Bulletin september/october
4 7. The first layer of FRP was installed and pressed into place. 8. The second layer of FRP was installed immediately after the first layer. Epoxy adhesive was applied to the end of the stem prior to the application of the second layer. Due to the tight gap between the end of the stem and the face of the wall, a sacrificial FRP extension wrapped on a piece of cardboard was used to facilitate pulling the FRP around the end of the stem. 9. All repaired areas were painted with acryliclatex coating. Haunches The double-tee support haunches were repaired by removing unsound concrete, installing repair mortar, and installing a haunch extension. The extension consisted of cast-in-place concrete located beneath the original haunch, effectively lengthening the haunch. Stems of supported doubletees were shored during this repair. Neoprene Pads Some neoprene bearing pads located on the haunches were damaged by the fire and required replacement. Pad replacement was performed by slightly jacking and lifting the double-tee to allow removal of the damaged bearing pad and creation of a gap into which the new pad could be inserted. Lifting of precast double tees for bearing pad replacement could lead to minor cracking of the topping, so the design drawings specified routing and sealing of all cracks in the topping slab located above the lifted members. Quality Assurance A quality assurance program was implemented to verify that the repairs performed were in general compliance with the intent of the design drawings. The quality assurance procedures included preconstruction inspections of surfaces to be repaired, periodic observations, bond testing of concrete surfaces, and inspection and sounding of completed repairs. Tensile pulloff tests were performed following ICRI Technical Guidelines. 3 The purpose of the tests was to quantify the near-surface tensile strength of the concrete substrate and to evaluate the quality of surface preparations prior to the installation of the FRP. Measured tensile strength september/october 2009 Concrete Repair Bulletin 11
5 from a car fire at this facility, a number of elements required evaluation. Structural modeling was performed to aid in assessing the possible reduction in strength of the double tees. As a result of the assessment, it was determined that the damaged members could provide satisfactory strength and serviceability after implementation of repairs. The result was a repair solution that is expected to be structurally functional and aesthetically pleasing for users of the facility. References 1. Lie, T. T.; Rowe, T. J.; and Lin, T. D., Residual Strength of Fire-Exposed Reinforced Concrete Columns, SP-92, T. Z. Harmathy, ed., American Concrete Institute, Farmington Hills, MI, 1986, pp ACI Committee 440, Guide for the Design and Construction of Externally Bonded FRP Systems for Strengthening Concrete Structures (ACI 440.2R-08), American Concrete Institute, Farmington Hills, MI, 2008, 76 pp. 3. ICRI Committee 210, Guide for Using In-Situ Tensile Pull-Off Tests to Evaluate Bond of Concrete Surface Materials ( ), ICRI, Des Plaines, IL, 2004, 12 pp. Fig. 5: Woodlands Waterway Marriot Parking Garage of the concrete surface was determined to be adequate and failure modes observed indicated satisfactory surface preparation. Mechanical sounding was performed at selected locations of completed spall repairs to qualitatively assess intimacy of repair mortar applications. In general, sounding revealed adequate bond between the patch repairs and sound concrete. Fire Damage Can Be Repaired Concrete-framed parking structures generally experience relatively minimal damage during and after exposure to car fires. Nonetheless, a systematic assessment is needed to identify the nature, extent, and structural significance of any damage. As indicated by the conditions resulting Woodlands Waterway Marriot Parking Garage Evaluation and Repairs Structural Repair Engineer-of-Record Wiss, Janney, Elstner Associates, Inc. Houston, TX Repair Contractor Structural Concrete Systems, LLC Magnolia, TX Material Supplier Sika Corporation Lyndhurst, NJ Alfredo E. Bustamante, PE, CDT, is a Senior Associate with the Houston Office of Wiss, Janney, Elstner Associates, Inc. Bustamante has been involved with the evaluation and design repair of parking structures, evaluation and testing of davit systems, nondestructive testing of concrete structures, structural metal computer modeling and analysis, and exterior wall cladding evaluation and design repair. Bustamante is a member of the American Concrete Institute (ACI) and the American Institute of Steel Construction (AISC). He is Chair of the Foundations Performance Association Structural Subcommittee for Foundation Evaluations Methods (FPA CS-02). Bustamante can be contacted at [email protected]. Michael W. Lee, PE, is a Principal with the Dallas Office of Wiss, Janney, Elstner Associates, Inc. Lee s interests include investigation and remediation of parking structures, buildings, and other structures using a broad range of materials and techniques. He is a member of ACI Committees 117, Tolerances; 440, Fiber Reinforced Polymer Reinforcement; and 437, Strength Evaluation of Existing Concrete Structures. He is also a member of the Precast/Prestressed Concrete Institute s (PCI) Committee on Parking Structures, and is a board member of the Structural Engineers Association of Texas. Lee can be contacted at [email protected]. 12 Concrete Repair Bulletin september/october
Precast Concrete Parking Structures
Precast Concrete Parking Structures Durability starts at the joints BY DAVID C. MONROE AND JOSEPH L. WHITE Parking structures comprise the largest market segment for the structural precast, prestressed
Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries
Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Introduction Wastewater of petrochemical industries and refineries contains high amounts of emulsified aliphatic or
738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted 02-20-14)
POLYMERIC CONCRETE BRIDGE DECK OVERLAY (Adopted 02-20-14) Description The polymeric concrete bridge deck overlay shall consist of an epoxy polymer that acts together with special aggregate to form an overlay
The ACI 562 Repair Code
The ACI 562 Repair Code Code Requirements for Evaluation, Repair and Rehabilitation of Concrete Buildings by Keith Kesner 1 Chair ACI 562 Lawrence Kahn 2 Former Chair ACI 562 1. Associate WDP & Associates,
The Original Carbon Fiber Reinforced Polymer System
Infrastructure The Original Carbon Fiber Reinforced Polymer System Phone: 52.292.39 Toll Free: 866.38.269 Fax: 52.48.5274 282 E. Fort Lowell Rd. Tucson, AZ 8576 www.dowaksausa.com Test results are supported
Building Foundation and Structure
Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original
Detailing of Reinforcment in Concrete Structures
Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For
SECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements
University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt
Chapter 5 Bridge Deck Slabs. Bridge Engineering 1
Chapter 5 Bridge Deck Slabs Bridge Engineering 1 Basic types of bridge decks In-situ reinforced concrete deck- (most common type) Pre-cast concrete deck (minimize the use of local labor) Open steel grid
Structural Failures Cost Lives and Time
Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one
Concrete Repair. Applications and Procedures
Concrete Repair Applications and Procedures Objectives Identify what surface preparation is needed Identify typical modes of failure and testing methods How to choose the correct material for the repair
Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14
Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318
Meeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training
Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline
PART E SPECIFICATIONS
PART E SPECIFICATIONS Page 1 of 5 PART E - SPECIFICATIONS GENERAL E1. APPLICABLE SPECIFICATIONS, STANDARD DETAILS AND DRAWINGS E1.1 The City of Winnipeg Works and Operations Division Standard Construction
APE T CFRP Aslan 500
Carbon Fiber Reinforced Polymer (CFRP) Tape is used for structural strengthening of concrete, masonry or timber elements using the technique known as Near Surface Mount or NSM strengthening. Use of CFRP
MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS
MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS May 29, 2013 Revision B Structural Guideline for Design and Installation Holes in Composite Floor Slab Terminal 3, Departure Level
September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900
September 1, 2003 CONCRETE MANUAL 5-694.900 5-694.901 GENERAL CONCRETE PAVEMENT REHABILITATION 5-694.900 Concrete Pavement Rehabilitation is an extremely valuable tool of the Minnesota Department of Transportation
The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma
The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma Bart B. Barrett, B.S., P.E.1 Kerry S. Lee, M.B.A., P.E., M. ASCE2 Erik L. Nelson, Ph.D., P.E., M. ASCE3
Bridge Structural Rehabilitation Using FRP Laminates
Bridge Structural Rehabilitation Using FRP Laminates South Santiam River Quartzville Road, Linn County Linn County Road Department 2011 Cooperative Partnerships Making Linn County a Better Place to Live
Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units
Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units Thomas Kline Director- Concrete Repair Solutions STRUCTURAL TECHNOLOGIES, LLC Houston, Texas USA November
External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902
External Wrapping of Steel Riser Pipe Case Study HJ3 CS200902 Introduction Refineries process a wide variety of petroleum products. As part of the process, they rely on cooling towers, which recycle water
Figure A. Maximum load testing of new precast concrete floor plank system
Load Testing of Precast Concrete Plank By Peter Gorgas, E.I.T. Figure A. Maximum load testing of new precast concrete floor plank system Overview Testing was performed in July 2012 at Northeast Precast
University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage
University of Missouri Hospitals and Clinics Structural Repair and Protection of Post-tensioned Parking Garage 1 University of Missouri Project The University of Missouri Health Care Patient and Visitor
FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS
FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form
Experimental assessment of concrete damage due to exposure to high temperature and efficacy of the repair system
MATEC Web of Conferences 6, 06002 (2013) DOI: 10.1051/matecconf/20130606002 C Owned by the authors, published by EDP Sciences, 2013 Experimental assessment of concrete damage due to exposure to high temperature
PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta
PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM Installed in Pre-engineered Steel Buildings Provides Lowest Cost Construction Method for CORROSIVE AND WET Environments PREFERRED SOLUTIONS, INC.
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS
Fracture Mechanics of Concrete Structures Proceedings FRAMCOS-3 AEDIFICA TIO Publishers, D-79104 Freiburg, Germany SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS H.
Evaluating. A Case Study
A Case Study Evaluating by Richard B. Stoddard, Washington State Department of Transportation In December 2002, a railroad tanker collision caused a fire under a prestressed concrete girder bridge crossing
PCI BIG BEAM COMPETITION
PCI BIG BEAM COMPETITION Official Rules for the PCI Engineering Design Competition Academic Year 2015-16 PROGRAM The PCI Student Education Committee is inviting entries from students to participate in
BRIDGE REHABILITATION TECHNIQUES
BRIDGE REHABILITATION TECHNIQUES Yogesh Chhabra, General Manager, The D S Brown Company, 57 Pioneer Road, Singapore 628508 Web www.dsbrown.com E-Mail [email protected] Ph. +6598444104, +6565588111
SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.
SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,
The Minnesota Lath and Plaster Bureau Repairing Cracks in Stucco
The Minnesota Lath and Plaster Bureau Repairing Cracks in Stucco Disclaimer: This guide contains general information on stucco installation and related materials. It is provided as a guide only and is
4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.
Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls
Chapter 2 Basis of design and materials
Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural
Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.
P-5 The P-5 is hot forged from carbon steel. The formed head provis spherical seating that the Lifting Eye engages, while a disc-shaped foot is embedd in the concrete. Due to its being a forged part, the
LEGACY REPORT. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council. *Corrected March 2014
ICC-ES Legacy Report PFC-3700* Issued October 2003 www.icc-es.org (00) 423-57 (52) 99-0543 A Subsidiary of the International Code Council Legacy report on the 1997 Uniform Building Code and the 2000 International
NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES
1.00 PART 1 GENERAL 1.01 SCOPE A. It is the intent of this contract to install a 100% solids epoxy monolithic coating to the walls, benches and inverts of all manholes and the specified surfaces of other
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
Guidelines for the Design of Post-Tensioned Floors
Guidelines for the Design of Post-Tensioned Floors BY BIJAN O. AALAMI AND JENNIFER D. JURGENS his article presents a set of guidelines intended to T assist designers in routine post-tensioning design,
Prestressed Concrete Pipe Fitness for Service and Repair
Prestressed Concrete Pipe Fitness for Service and Repair Rasko Ojdrovic [email protected] 781-907-9231 IAEA - EPRI 15 October 2014 www.sgh.com SGH Pipeline Experience More than 25 years of research, analysis,
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
beams columns blast walls slabs pipes protective coatings polymer concrete Solutions Looking for Problems...
beams columns blast walls slabs pipes protective coatings polymer concrete Solutions Looking for Problems... CarbonWrap Solutions Services Turnkey Innovative Solutions and Products CarbonWrap Solutions,
STRENGTHENING AND LOAD TESTING OF THREE BRIDGES IN BOONE COUNTY, MO
STRENGTHENING AND LOAD TESTING OF THREE BRIDGES IN BOONE COUNTY, MO S. Schiebel 1, R. Parretti 1, A. Nanni 2, and M. Huck 3 ABSTRACT Three bridges in Boone County, Missouri (Brown School Road Bridge, Coats
GARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION
GARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION Issam ElKhatib, P.Eng., Dennis Baxter, P.Eng. Totten Sims Hubicki Associates, Canada Abstract The rehabilitation history of the Garden City Skyway Bridge
OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007
OTTAWA CIVIC CENTRE & NORTH SIDE STANDS at LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007 for CITY OF OTTAWA REAL PROPERTY ASSET MANAGEMENT prepared by ADJELEIAN ALLEN RUBELI LIMITED
2006 ICRI Baltimore Washington Chapter Outstanding Repair Project Award George Washington University Ross Hall Façade Restoration
2006 ICRI Baltimore Washington Chapter Outstanding Repair Project Award George Washington University Ross Hall Façade Restoration 2006 ICRI Baltimore Washington Chapter Outstanding Repair Project Award
Common Perils of Ceramic Floor Tile Systems. Parkway, Suite 220, Plano, Texas 75093; PH (469) 429-9000; email: bbarrett@architecturalengineers.
Common Perils of Ceramic Floor Tile Systems Bart B. Barrett, P.E. 1 and James M. Falls, E.I. 2 1 Central Florida Branch Director, Nelson Architectural Engineers, Inc., 2740 Dallas Parkway, Suite 220, Plano,
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
Strengthening and Repair of Reinforced Concrete Structures. Ian Wienholt Business Development Manager
Strengthening and Repair of Reinforced Concrete Structures Ian Wienholt Business Development Manager 34 years of Concrete Repair and Strengthening Experience Over 12,000 Repair Project Over 25,000 PT Projects
DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS
8601 North Black Canyon Highway Suite 103 Phoenix, AZ 8501 For Professionals Engaged in Post-Tensioning Design Issue 14 December 004 DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS by James D. Rogers 1 1.0
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps
Foundations on Expansive Clay Soil Part 3 - Investigation of Failed Foundations Presented by: Eric Green, P.E. Structural Engineer Slide 1 Copyright Eric Green 2005 Investigation of Foundation Failure
Condition assessment and repair of antenna towers concrete foundations
Condition assessment and repair of antenna towers concrete foundations I. Banjad Pecur, N. Stirmer & B. Milovanovic Department of materials, Faculty of Civil Engineering, University of Zagreb, Zagreb,
Structural Assessment Report
Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive
Causes and Repair Method
Point Shilshole Condominium Building Concrete Deterioration Causes and Repair Method KAMRAN M. NEMATI, PH.D., P.E. CONSULTING CIVIL ENGINEER Copyright (2006) P.O. Box 95233 Seattle, Washington 98145-2233
~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:
Texas Depadment of Transpo,tation Bridge Condition Survey Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Irving Street Facility Name: Lone Wolf Bridge Structure Number: B00315-031
The unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION
CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything
The Strength of Concrete
Chapter The Strength of Concrete.1 The Importance of Strength.2 Strength Level Required KINDS OF STRENGTH. Compressive Strength.4 Flexural Strength.5 Tensile Strength.6 Shear, Torsion and Combined Stresses.7
Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete
Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete Ming-Gin Lee 1,a, Yi-Shuo Huang 1,b 1 Department of Construction Engineering, Chaoyang University of Technology,Taichung
INJECTION MOLDING COOLING TIME REDUCTION AND THERMAL STRESS ANALYSIS
INJECTION MOLDING COOLING TIME REDUCTION AND THERMAL STRESS ANALYSIS Tom Kimerling University of Massachusetts, Amherst MIE 605 Finite Element Analysis Spring 2002 ABSTRACT A FEA transient thermal structural
Project Report. Structural Investigations Hotel del Sol Yuma, Arizona
Project Report Structural Investigations Yuma, Arizona Prepared by: 2619 Spruce Street Boulder, CO 80302 303-444-3620 Prepared for: Principle Engineering Group, Inc. 833 East Plaza Circle, Suite 100 Yuma,
Fire and Concrete Structures
Fire and Concrete Structures Authors: David N. Bilow, P.E., S.E., Director, Engineered Structures, Portland Cement Association 5420 Old Orchard Road, Skokie, IL 60077,Phone 847-972-9064, email: [email protected]
SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP
13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3279 SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP Yuming DING 1, Bruce HAMERSLEY 2 SUMMARY Vancouver
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
Concrete Removal Using Hydrodemolition
ACI RAP Bulletin 14 American Concrete Institute Advancing concrete knowledge FIELD GUIDE TO CONCRETE REPAIR APPLICATION PROCEDURES Concrete Removal Using Hydrodemolition Concrete Removal Using Hydrodemolition
Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling
7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling Asphalt Pavements 7-7 Chapter 7 Pavement Rehabilitation Pavement rehabilitation can be accomplished
LAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
Measuring the Condition of Prestressed Concrete Cylinder Pipe
Measuring the Condition of Prestressed Concrete Cylinder Pipe John Marshall, P.E.I, I J.W. Marshall and Associates, and Paul S. Fisk, President NDT Corporation Introduction Prestressed Concrete Cylinder
HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 [email protected]
HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 [email protected], 2011 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,
Technical Notes 3B - Brick Masonry Section Properties May 1993
Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications
Construction Specifications for Keyhole Pavement Coring and Reinstatement
F I N A L Construction Specifications for Keyhole Pavement Coring and Reinstatement Gas Technology Institute 1700 S. Mount Prospect Rd. Des Plaines, Illinois 60018 www.gastechnology.org Version 13 October
Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China
Advanced Materials Research Vols. 163-167 (2011) pp 1147-1156 Online available since 2010/Dec/06 at www.scientific.net (2011) Trans Tech Publications, Switzerland doi:10.4028/www.scientific.net/amr.163-167.1147
Structural Audit of Buildings
International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 4 (2014), pp. 411-416 Research India Publications http://www.ripublication.com/ijcer.htm Structural Audit of Buildings
Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs
Long Life Concrete Pavement Joint Performance Joint Rehabilitation Gary Fick, Trinity Construction Management Services, Inc. Representing the National CP Tech Center Driving Forces for Concrete Pavement
6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
09/07/07 GLASSFIBER REINFORCED CEMENT (GRC) C. S. I. Spec 03500 Master Spec. 03 49 00 Page 1
C. S. I. Spec 03500 Page 1 PART 1 - GENERAL 1.01 SUMMARY:.01 Provide special glassfiber reinforced cement (GRC) shapes in accordance with the requirements of the contract documents..02 The installing contractor
Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System
Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Luis Aguiar Miami-Dade Water & Sewer Department Anna Pridmore, PhD Structural Technologies PROJECT BACKGROUND Miami-Dade Water & Sewer Department
Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars
Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)
SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:
Reading Assignment SLAB DESIGN Chapter 9 of Text and, Chapter 13 of ACI318-02 Introduction ACI318 Code provides two design procedures for slab systems: 13.6.1 Direct Design Method (DDM) For slab systems
INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.
INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee
Bridge Type Selection
Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when
PRE INSTALLATION MANUAL
REINFORCED CONCRETE PIPE PRE INSTALLATION INSPECTION & REPAIR MANUAL Kentucky Transportation Cabinet Kentucky Department of Highways Division of Materials 1227 Wilkinson Boulevard Frankfort, KY 40601 (502)
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
INSTALLATION. General. Important Note. Design. Transport
General The roof trusses you are about to install have been manufactured to precise engineering standards. To ensure that the trusses perform as designed, it is essential that they be handled, erected
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word
HSE Information Sheet. Advice on acceptance criteria for damaged Passive Fire Protection (PFP) Coatings. Offshore Information Sheet No.
HSE Information Sheet Advice on acceptance criteria for damaged Passive Fire Protection (PFP) Coatings Offshore Information Sheet No. 12/2007 Introduction...2 Background...2 Additional information...3
