Change Management for Mega Projects May 17, 2012



Similar documents
Facilities Development Manual Chapter 2 Project Management Section 15 Project Integration Management

Project Management Terms

Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI (608) Fax: (608)

Alternatives Presentation Meeting Middlebury WCRS(23)

HiCAMS User Guide. Chapter 3: Contract Adjustments. Section 1: Review Claims

Program guidance that details the eligibility, criteria and application process. Ferry Boat Program. Ohio Department of Transportation

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

Contract Administration

Transportation Management Plan Template

Business Plan: Roadway Planning & Design

Risk Committee Charter

PRIORITIZATION PROCESSES

CHAPTER 20 Project Development Cost Estimates Table of Contents

Risk Management in the Development of a Penta-P Project

Section ALTERNATIVES. 3. Alternatives

DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1

BENCHMARK EVALUATION. Highways and Public Works Information and Communications Technology

LOUISVILLE - SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT Initial Financial Plan

SAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011

FHWA Emergency Relief (FHWA-ER) Training

Lee & Man Paper Manufacturing Limited (Incorporated in the Cayman Islands with limited liability) (Stock Code: 2314)

Risk Management Committee Charter

Veterans Health Administration (VHA) Update for Oversight for Uses of Radioactive Materials. Frank A. Miles

Project Risk Management Handbook: A Scalable Approach

CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska REGULAR BOARD OF DIRECTORS MEETING AGENDA ITEM SUMMARY. July 23, 2009

ITRM Guideline CPM Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

National Environmental Policy Act/ Clean Water Act Section 404 (NEPA/404) Merger Process and Agreement for Transportation Projects in Colorado

LOUISVILLE - SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT Updated Financial Plan. December 2010

Background and Goals for the Project

How To Manage A Company

MORE INCURRED-COST AUDITS OF DOT PROCUREMENT CONTRACTS SHOULD BE OBTAINED

AASHTO First Take at the New Surface Transportation Bill FIXING AMERICA S SURFACE TRANSPORTATION (FAST) ACT December 2, 2015

Project Delivery Process Overview

PPPs: INSIGHTS FROM NORTH AMERICA. Presenter: Brian Middleton. worldwide

Department of Veterans Affairs VHA HANDBOOK Washington, DC August 24, 2010 OCCUPATIONAL SAFETY AND HEALTH (OSH) PROGRAM PROCEDURES

DATE: July 25, 2013

U.S. Department of Energy Office of Inspector General Office of Audit Services. Audit Report

South East Water Corporation Finance Assurance and Risk Management Committee Charter

STATE OF MONTANA MONTANA DEPARTMENT OF TRANSPORTATION JOB PROFILE AND EVALUATION. Work Address: District only Glendive

SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY

Manage Deliverables - Construction Step 6. July 12, 2012

Virginia s Approach to Intercity Passenger Rail Development

Majors Program Cost Estimating Software. User Manual. Created by the Construction and Materials Support Center at the University of Wisconsin-Madison

Construction Business Continuity Management Plan. City Centre Revitalization and Redevelopment Project

Task Order Manager. Project Planning, Engineering, Architecture service contract with experience in passenger rail or other modes, and

U.S. Department of Education. Office of the Chief Information Officer

Design-Build Process for Project Managers

ACQUISITION AND PROCUREMENT: NEW JERSEY HIGH-SPEED RAIL IMPROVEMENT PROGRAM HAS COST AND SCHEDULE RISKS

14 FAH-2 H-110 CONTRACTING OFFICER'S REPRESENTATIVE HANDBOOK

CHAPTER TEN. Quality Assurance and Quality Control MAINE RIGHT OF WAY MANUAL

South East Water Corporation Finance Audit and Risk Management Committee Charter. October 2012

Introduction to the ITS Project Management Methodology

AASHTO Equipment Management Technical Services Program. EMTSP Program Update

QUALITY ASSURANCE OPERATIONAL FRAMEWORK. University of Liverpool. Liverpool, L69 7ZX. And. Laureate

KUMBA IRON ORE LIMITED (Registration number 2005/015852/06) ( Kumba or the Company )

SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development

I. Purpose MD #

U.S. DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION. Air Traffic Organization Policy

CHARTER OF SUCCESSION PLANNING COMMITTEE

NON-TRADITIONAL UTILITY COORDINATION on KYTC Projects. KYTC Partnering Conference September 9, 2014

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005

1. CALL TO ORDER/ROLL CALL John Zoglin, Chair 4:00 4:01. John Zoglin, Chair 4:01 4:02 2. POTENTIAL CONFLICT OF INTEREST DISCLOSURES

US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing

Cross Asset Management Revamped Revisiting Asset Manager NT and PT Presented by : Jose Aldayuz, PE IHEEP Conference New Orleans

(1) To approve the proposals set out in paragraphs to ensure greater transparency of partnership board activity; and

CalPERS Budget Policy

SUMMARY... iii INTRODUCTION... 1 PROJECT SPONSORS... 1 PROJECT DESCRIPTION... 1 PROJECT HISTORY... 3 PROJECT MANAGEMENT AND OVERSIGHT...

Application of the Framework is relevant to clinical networks, units and health service teams within each service or organisation.

THE GAP, INC. CORPORATE GOVERNANCE GUIDELINES (As of February 1, 2015)

Department of Finance

Transmission Function Employees Job Titles and Descriptions 18 C.F.R 358.7(f)(1)

Facilities Development Manual Chapter 19 Plans, Specifications and Estimates Section 5 Estimates

IND Process and Review Procedures (Including Clinical Holds) CONTENTS

CONGESTION MANAGEMENT PROCESS UPDATE & STATUS

PamHa~Y"'-.~ \_-..\<J.L.'e_

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS

TRUST SECURITY MANAGEMENT POLICY

Board Risk & Compliance Committee Charter

WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT

OFFICE OF THE CIO. PROCEDURE Informational VERSION: 1.0

Financial Services FINANCIAL SERVICES UTILITIES 57 FINANCIAL SERVICES AND UTILITIES BUSINESS PLAN. CR_2215 Attachment 1

2010 FINANCIAL PLAN ANNUAL UPDATE

Mainstreaming Incident Management in Design-Build: The T-REX Experience

MNLARS Project Audit Checklist

South East Coast Ambulance Service NHS Trust. Information Governance Working Group. Terms of Reference

AUDIT COMMITTEE TERMS OF REFERENCE

RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS

PIONEER NATURAL RESOURCES COMPANY AUDIT COMMITTEE OF THE BOARD OF DIRECTORS CHARTER

IDOT Chicago - St. Louis High-Speed Rail Program Management

GARMIN LTD. CORPORATE GOVERNANCE GUIDELINES

REAL ESTATE SPECIALIST CLASSIFICATION SERIES

Trust Board Report. Review of the effectiveness of the IM&T Committee

CHEVRON CORPORATION AUDIT COMMITTEE CHARTER

Business Continuity Management Framework

AGENDA REGULAR MEETING SERVICE AUTHORITY FOR FREEWAYS AND EXPRESSWAYS

DCO No. Released By: Effective Date Document No. Rev.

Transcription:

Change Management for Mega Projects May 17, 2012 All Department Mega project budgets shall be managed within the project estimate developed within the section: Budget Estimation and Management for Mega Projects. This process includes development of and adherence to a project contingency. Department Divisions DTSD and DTIM have a variety of ways to manage change in its improvement projects and programs. These methods vary from project level, business area, region level, division and cross division. For management purposes the Department has chosen to manage all mega projects as if they were in the Major Projects Program. As such, Project Teams and Regions with Mega Projects will participate in the Major Projects Peer Review Team processes. The DTSD Administrator may assign additional High Profile projects to the committee as well. Projects that are defined by FHWA as federal major projects or Mega Projects can be funded in managed in different programs. Examples include: Southeastern Wisconsin Freeway Mega projects such as the Marquette Interchange, I-94 North South corridor, and the Zoo Interchange. Major Program Mega projects such as USH 41 and I-39/90 High Cost Bridge Program Mega projects. Examples could include multi-state bridge river crossings. The I-94 N-S project, Zoo Interchange project, I-794 / Hoan Bridge Project, and St. Croix Crossing project all have budgets established outside of the Major Highway Appropriation. As long as these projects are kept within total project estimates, the Major Projects Peer Review Committee will be utilized as a knowledge sharing forum vs. a decision making forum. Change Management for Mega, Major, and High Profile projects shall utilize the change management process outlined in this section. Change Management Summary Tables Project Concept through Environmental Document completion. Level of Decision DTIM / DTSD Administrators and Monthly Program Team Major Projects Peer Review Team Region Scope Additions and Deletions Quarterly Updates Quarterly Updates Quarterly Updates The Major Projects Peer Review Committee shall review all Major projects, future SE Freeway reconstruction appropriation Mega projects, and DTSD Administrator assigned high profile projects. An initial project scope and estimate is developed at the time of concept definition, when a project is considered for study as part of the Major Highways Program or when a new SE Project Mega Project is identified for the biennial budget process. 1

At this time a design budget and initial project construction estimate (often on a per mile basis) is developed. Alternatives for study during the environmental phase shall receive concurrence at the region level and division administrator level. Some projects may require concurrence at the Oversight Committee level as well. If work is anticipated on off corridor routes (ex. Parallel routes or mitigation on off corridor routes), these should be identified when alternatives are defined. Alternative refinement and the addition of new alternatives shall receive the similar concurrence at the region and division administrator level. During the development and refinement process, bureaus and other divisions will be involved and coordinated with. The preferred alternative shall reflect the department s choice and meet all of the NEPA / WEPA requirements. Post Environmental Document (Enumerated/Approved for Construction) Design, Utilities, Railroads, and Real Estate through Project Letting Major Highway Mega Projects, future SE Freeway Appropriated Mega Projects, and DTSD Administrator assigned High Profile Projects Major Projects Peer Review Committee* Region Project Scope Changes and cost increases > $ 500k ** Scope Changes and cost increases > $ 500k Cost increases, excluding scope changes < $500K *BSHP Director will elevate issues to DTIM and DTSD Administrators on an as-needed basis **The investigation of project scope changes that would increase project cost more than $5M must receive Major Peer Review Committee approval prior to proceeding with the investigation or study of the possible change 2

For I-94 N-S, Zoo IC, I-794 / Hoan Bridge, and St. Croix Crossing, the % of Project Reserve DTIM / DTSD Administrators Issues from Oversight Team or > Total Estimated Cost. Note: The project team shall be sharing updates on the use and status of project reserves at the Region, Major Projects Peer Review Committee, and Oversight Committee. Major Projects Peer Review Committee Region Cost increases and scope additions shared for knowledge transfer and information purposes 50-100% of Project Reserves Project < 50% of Project Reserves Examples of scope changes could include: Major Projects Peer Review Team and/or Administrator s Monthly Program Meeting Addition of a new interchange Resurfacing a local route (ex. STH or Local Road outside chosen alternative from environmental document) Significant and sensitive local project issues. Industry trends Standards changes Estimate revisions Region Level: Issues above TOIP improvements outside chosen alternative from environmental document. Consideration and Preparation of issues for Major Projects Peer Review Committee and monthly program meeting. Development Issues within and/or adjacent to the project. Post project letting through final project close-out. The Major Projects Peer Review Committee shall review all Major projects, future SE Freeway Reconstruction Appropriation Mega projects, and DTSD Administrator assigned High Profile Projects. 3

Level of Decision DTIM / DTSD Administrators and Monthly Program Team DTSD Director Meeting Sub-Group Topic * ** Region Project % of Annual Project Change Order Budget *** Issues elevated from Major Projects Review Team, DTSD Director s Sub-Team, or assigned from Oversight Team. >Annual Project Change Order Budget 50-100% of Annual Change Order Budget < 50% of Annual Change Order Budget For I-94 N-S, Zoo IC. I- 794 / Hoan Bridge, and St. Croix Crossing, the % of Project Reserve Issues elevated from DTSD Director s Subgroup, or assigned from Oversight Team. > Estimated Total Project Cost 50-100% of Project Reserves <50% of Project Reserves * Any CCO > $500k over the project budget shall be reported to the DTIM BHSP Director and Program Chief. This allows an evaluation of potential program impact and TPC cost impact. Project Development Chiefs regularly discuss change order issues at the project and program level and may request issues be elevated to DTSD Director s Sub-Group Meeting as discussion items. ** Subgroup of DTSD Directors: BPD Director, BOS Director, Region Directors and Deputy Directors. Meets after bi-weekly teleconference or at face to face director s meetings *** The Major Projects Peer Review Committee will establish an annual construction project change order budget for each project (Major Highway Program, future SE Freeway Reconstruction Appropriation Mega projects, and DTSD Administrator assigned High Profile projects). Examples of Issues: DTSD Director Level and/or Administrator s Monthly Program Meeting: Project overruns that are projected to exceed annual change order budget. The various groups can do a value engineering review of trends. Significant TMP or Cost Savings proposal by contractor with incentives and public involvement components. Ex. System Interchange TMP Changes to environmental document scope. Region Level Meeting: Same as above Significant Issues affecting other business areas Preparation of issues for DTSD Director s Sub-group or Administrator s Monthly Program Meeting. Change Management Prior to Completion of Environmental Document (determination phase) Mega projects, Major projects, and High Profile projects all follow the Facilities Development Manual (FDM) process as the environmental document phase of the project is carried out. On these types of efforts, the project team will deal with issues that may not regularly be dealt with on a standard project. The FDM and these sets of Mega Project guidelines, particularly the Best Practices section, provide a resource to the project team as they carry out the project. The project team established also provides a great set of resources to check in with. Other Mega project teams can also serve as resources 4

Project teams will be faced with unique issues that may present challenges to the project scope and estimate. Project teams shall utilize the Project Team s Change Management process, the Region Change Management process, DTSD Director s Sub-Group Meeting, Administrator s Monthly Program Meeting, and when appropriate the Oversight Committee to seek guidance prior to making project commitments. It is expected that each Mega Project and DTSD assigned High Profile projects will have an appropriate amount of risk (contingency) and allowance factors incorporated into the original project cost estimate. The level of the risk and allowance used in the cost estimate will be reviewed by the Departments Major Projects Peer Review Team, as part of a formal cost estimate review. The link to the Major Project Cost Estimating Tool is http://dotnet/consultants/estimates/estimatesmajor.shtm For non Major Highway Mega Projects such as the Southeast Region s existing Mega Projects, Marquette Interchange - complete, I- 94 North South Corridor, Zoo Interchange, St. Croix Crossing, and I-794 / Hoan Bridge change management budgets or reserves have been established as part of a total build out budget. Change management decisions for these projects will continue to be made from the projects identified and established reserves. However, these projects shall become part of the Major Project Peer Review Team s responsibilities for information sharing and knowledge transfer purposes. Cost estimates for new projects in the Major Highway Program or future SE Freeway Reconstruction appropriation Mega projects, and DTSD Administrator assigned High Profile projects will be reviewed by the Departments Major Projects Peer Review Team, As a project moves through final design, real estate acquisition, utility and railroad process, and construction, the amount of risk and allowance is expected to be reduced as unknowns become known, and are therefore discretely itemized in a refined estimate. For all Major Highway Mega Projects, it is expected that typically only a very small amount of risk, if any would be included in the final estimate prior to let. Please note that inflationary risk would be handled by a Majors Program reserve, and not at an individual project level. Project contingency levels begin by utilizing historical information and considering specific project risks. 5

Department-Level Change Management Decisions (design, utilities, railroad, and real estate through project letting) The process ensures consistent treatment of Mega, Major, and High Profile project change management issues at the Region level. The Major Projects Peer Review Team shall carry out this responsibility Project and program issues that cannot be resolved by the Major Projects Peer Review Team shall first come to the DTIM / DTSD Administrator s monthly program meeting and likely will need discussion and consideration in the Secretary s Office and Oversight Committee. The Department s Major Projects Peer Review Team is made up of: Chairperson: Meeting Facilitator: Members: Typical Attendees: Projects Included: Meeting Frequency: Typical Agenda: DTIM BHSP Director DTIM BHSP Program Chief and/or Majors Program Manager DTSD Region Director Representative(s), and a mix of DTSD Planning and Design Chiefs, Majors Peer Review Members, Chiefs involved with Mega Projects, and FHWA. Any project defined as a Federal Major Project / Mega Project. Monthly. The agenda and meeting materials are submitted to members and attendees the week prior to the meeting. Items covered during the meeting include: Establishment and management of Annual Construction Let Change Order Budget for each Major Highway, High Profile Projects assigned by DTSD Administrator, and future SE Freeway Reconstruction appropriation project letting. Cost report reviews Cost trend reviews Cost to complete projections Cost saving opportunities See Change Management summary tables New division and department level issues arising from Mega, Major, and High Profile Projects. Note: Major Highway Projects with very time-sensitive change management issues that cannot wait for the next monthly meeting will be presented directly to the BSHP for a funding decision. 6

Department-Level Change Management Decisions (post project letting through final project close-out) Project Teams and Regions shall utilize the Change Management Summary tables for discussion and resolution of issues. The Major Highway Peer Review Committee shall be responsible for all projects funded out of the Major Highway Program, High Profile projects assigned by the DTSD Administrator to the committee, and all future SE Freeway Reconstruction Appropriation Mega projects. An annual and individual project change order budget shall be established for each Department Mega, and assigned High Profile Project. This shall be established by the Departments Major Projects Peer Review Team. It will be based on a part of the total department un-programmed cost budget. The annual un-programmed costs budget and total un-programmed costs (life of project) is expected to fall within the project estimate developed at the time of enumeration. This estimate includes a project contingency. Historically, un-programmed cost program level budgets have been based on a percentage of the previous year s let amount. Future annual individual Mega project un-programmed cost budgets will need to consider the project contingency estimate, project risk, the fluctuation of let amounts on an annual basis, as well as the multi-year nature of lettings. Existing biennial budgeted Mega Projects and high profile projects outsides the major highway program have change management budgets or reserves that have been established as part of a total build out budget. These projects include the Marquette Interchange - complete, I-94 North South Corridor, Zoo Interchange, I-794 / Hoan Bridge, and St. Croix Crossing projects Change management decisions for these projects will continue to be made from the projects identified and established reserves. However, these projects shall become part of the Major Project Peer Review Team s responsibilities for knowledge transfer and information sharing purposes. Scheduling Project Costs: Major High projects have cost estimates developed prior to enumeration. A cost estimate is calculated in current year dollars, and an inflated build-out cost estimate is also prepared for environmental document requirements. High Profile projects and SE Freeway Reconstruction Appropriation Mega projects both follow a similar path. All these projects are managed using current year dollars. Nearly all estimated project costs will be scheduled in FIIPs. Only a minimal amount of project costs are un-programmed all costs are programmed except for a small un-programmed CCO reserve and possibly an un-programmed reserve for unused contingency late in a project s life (nearing the end of construction lets). This means all other contingency and reserve should be programmed in the year it is estimated to occur (e.g. a $100M let package includes all contingency associated with the let package). Programming guidance is provided by DTIM BHSP. Region-Level Change Management Decisions To ensure consistent treatment of Mega project change management issues at the region level a Change Management Team will be formed. 7

The Region s Mega Project Change Manage Team is made up of: Chairpersons: Region Deputy Director and Region Director Meeting or Topic Facilitator: Mega Project Chief Members: Typical Attendees: Projects Included: Meeting Frequency: Typical Agenda: Region Directors, Mega Project Chief(s), and Region Chiefs Team members. Project personnel or additional expertise, when appropriate. Any project defined as a Federal Major Project / Mega Project. Utilize a portion of a regular region senior management meeting or establish a monthly meeting for this topic. The agenda and meeting materials are submitted to members and attendees the Friday prior to the meeting. Items covered during the meeting include; Management of Annual Construction Project Change Order budget. Cost report reviews Cost trend reviews Cost to complete projections Cost saving opportunities See Change Management Summary Tables New region, division, and department level issues arising from Mega, Major, and High Profile Projects. Project -Level Change Management Decisions To ensure consistent treatment of Mega project change management issues at the project level, a Change Management Team will be formed. Project changes in the construction phase will also follow the communication and involvement process outlined in the Construction and Materials Manual (CMM). The Project s Mega Project Change Manage Team is made up of: Chairperson: Meeting or Topic Facilitator: Members: Typical Attendees: Projects Included: Meeting Frequency: Typical Agenda: Region Deputy Director Mega Project Chief Region Directors, Mega Project Chief(s), Supervisors, FHWA, BPD Liaison, and key project staff. Team members. Additional expertise when appropriate. Any project defined as a Federal Major Project / Mega Project. At least monthly. The agenda and meeting materials are submitted to members and attendees the Friday prior to the meeting. Items covered during the meeting include: 8

Management of Annual Construction Project Change Order budget. Cost report reviews Cost trend reviews Cost to complete projections Cost saving opportunities See Change Management Summary Tables New project, region, division, and department level issues arising from Mega, Major, and High Profile Projects. 9