1 PPPs: INSIGHTS FROM NORTH AMERICA Presenter: Brian Middleton

2 AGENDA Overview of US PPP market Case studies of sample projects Summary/Conclusions PPPs: An insight from North America

3 SUMMARY OF PPPs IN NORTH AMERICA Total Value per Year (US$ millions) Projects per year PPPs: An insight from North America

4 TRADITIONAL PROJECTS STRUGGLING ON TIMELINESS & COST One study found only: 47% on budget 55% on time Second study found that as projects grow in value, the likelihood of over-running also grows 80 th Percentile of traditional project performance PPPs: An insight from North America

5 MORE U.S. OWNERS CONSIDERING PPPs Transportation PPP projects Study of 10 PPPs showed All substantially on or ahead of completion dates Projects were an average of 22.6% below owner s estimates Reasons include: Alternative technical concepts and risk transfer Innovation and market Contractual structure PPPs: An insight from North America

6 HISTORY OF TRADITIONALLY DELIVERED MEGA PROJECTS Oakland Bay Bridge, San Francisco Original estimate $1.4 billion and 5-years Final cost $6.4 billion and 12- years 400% over budget and 7-years late Eastside Access, New York Projected cost is $4.5 billion over budget 14-years later than planned and still incomplete Oakland Bay Bridge PPPs: An insight from North America

7 MEGA PPP PROJECT HISTORY On average PPPs 15% less than estimated cost Eagle Project, Denver 12% below estimate and almost one year ahead of plan PennDOT bridge project 25% below estimate and 8- months ahead of 50 month planned completion Port of Miami Tunnel 33% under budget PPPs: An insight from North America

8 GENERAL LESSONS LEARNED Many PPP projects complete or underway, sophistication of market developing Owners should have expert technical, legal and financial advisors proposers will have Value for money assessments should be done and take into account qualitative and quantitative factors PPPs can deliver lower costs, budget certainty and guaranteed delivery PPPs: An insight from North America

9 Alternative Delivery Examples

10 TREX, DENVER COLORADO US$1.67 billion transit and highway D&C project Design and construct new 31 kilometre light rail and additional capacity to 27 kilometres of highway Leveraged multiple funding sources in combined project to address corridor problems Provided valuable experience in alternative delivery $39 million under budget, 22 months ahead of plan Payments on earned value during design and construction

11 EAGLE PROJECT, DENVER COLORADO US$2.3 billion Rail PPP project 34-year concession Built on experience from Trex $450 million in private debt and equity $300 million under estimate and 10 months ahead of plan Payments on earned value during design and construction and availability payments during O&M

12 US 36 EXPRESS LANES PROJECT, COLORADO Upgrade of arterial motorway Reconstruct 26 kilometres of US 36, including building one express lane in each direction 18 kilometres Phase 1 8 kilometres Phase 2 Bus Rapid Transit, HOV, SOV Reconstruct six bridges Widen five bridges New commuter bikeway Phase 1 Complete in 2015 Phase 2 Complete in 2016

13 US 36 PHASE 1 DESIGN-CONSTRUCT RFP Project defined by contractual drawings in RFP Defined limits of mainline reconstruction, typical sections Defined structures to be replaced or widened Defined limits of bikeway construction Limited ability to be innovative

14 PHASE 2 PROJECT OVERVIEW Concessionaire will: Construct remaining 8 kilometres Finance portion of remaining construction Operate and maintain entire corridor, and I-25 Express Lanes between US 36 and Denver Receive toll revenue from US 36 Express Lanes Concession term: 50 years

15 PENNDOT BRIDGE PROGRAM $899 million program to replace and maintain 558 bridges across Pennsylvania 58 structurally deficient bridges to be replaced in first year, remainder to be complete in 42- months $835 million in private debt and equity Payments on milestones during design and construction and availability payments Bridges are spread across the 120,000 sq km of Pennsylvania

16 Lyndon B. Johnson Freeway PROJECT LIMITS, TEXAS Project comprises 4 elements Improvements to I-635 Improvements to I-35E Two new interchanges

17 I-635 CORRIDOR 8 Reconstructed General Purpose Lanes 4 to 6 New Managed Toll Lanes 2 and 3 Lane Continuous Frontage Roads

18 I-35E CORRIDOR 4 Elevated Managed Lanes Miscellaneous Ramps/Frontage Roads Existing Main Lanes to Remain in Place Capacity Improvement (Optional)

19 FUNDING AND SCHEDULE Public funds amount is $489 million TIFIA/PABS financing amount is approximately $1.45 billion Construction cost is approximately $2.2 billion Debt retirement and O&M cost through tolling revenue PPPs: An insight from North America

20 SUMMARY PPPs are coming of age in North America Mix of availability and revenue risk models Best value obtained from performance led RFPs Value for money obtained Lower upfront and life cycle costs Earlier and guaranteed delivery PPPs: An insight from North America

Infrastructure Banking

Infrastructure Banking Public-Private Partnership Structures May 2013 Edward Fanter Managing Director 212-605-1614 [email protected] Infrastructure Banking June 2011 0 Infrastructure Banking Leading P3 Platform BMO Capital

More information

Introduction to Public-Private Partnerships (P3s)

Introduction to Public-Private Partnerships (P3s) Introduction to Public-Private Partnerships (P3s) Today s Instructor Patrick DeCorla-Souza P3 Program Manager Office of Innovative Program Delivery Program Development Team Course Outline Slide 2 Lesson

More information

Annual Meeting of Senior PPP Officials 2010

Annual Meeting of Senior PPP Officials 2010 Paris _ 12th of April 2010 PPP Risk Pricing PPPs Vs Traditional Procurement PPPs Strengths PPPs around the World Best PPPs Practices PPP Risk Pricing DESIGN DIFFERENT PPP DELIVERY MODELS BOT BUILD FINANCE

More information

SF Bay Area Transportation Management Systems: An Innovative DOT and MPO Partnership

SF Bay Area Transportation Management Systems: An Innovative DOT and MPO Partnership SF Bay Area Transportation Management Systems: An Innovative DOT and MPO Partnership Radiah Victor Principal, Operations Metropolitan Transportation Commission Oakland, California ITS CA Annual Meeting

More information

PRESIDIO PARKWAY FINANCIAL PROPOSAL 2.1.2. FINANCIAL PROPOSAL EXECUTIVE SUMMARY GOLDEN LINK PARTNERS

PRESIDIO PARKWAY FINANCIAL PROPOSAL 2.1.2. FINANCIAL PROPOSAL EXECUTIVE SUMMARY GOLDEN LINK PARTNERS 2.1.2. EXECUTIVE SUMMARY The Presidio Parkway Project (the Project ) is a landmark transaction in a high profile location and as the Project is the first transportation P3 in the State, its success is

More information

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan. 3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation

More information

INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS

INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS WITH AVAILABILITY PAYMENTS Dr. Silviu Dochia, Senior Associate Michael Parker, Managing Director SUMMARY Public-private partnerships ( P3s ) can provide the

More information

Public-Private Partnerships Forum PPP Law, Structures and Contracting

Public-Private Partnerships Forum PPP Law, Structures and Contracting Public-Private Partnerships Forum PPP Law, Structures and Contracting AGC California Fall Conference 2010 Hyatt Grand Champions, Indian Wells November 4, 2010 MAKING IT HAPPEN. Overview California PPP

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships

Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships May 29, 2013 Introduction With you today from KPMG Years of Experience: 30+ Tim

More information

Parsons Transportation Moving the world forward.

Parsons Transportation Moving the world forward. Parsons Transportation Moving the world forward. Alternative Delivery Get on the fast track to project success. In a changing marketplace, everyone has decisions to make. And Parsons innovative delivery

More information

Public/Private Partnerships and the Public Procurement Process

Public/Private Partnerships and the Public Procurement Process ELEVATING OUR PROFESSIONALISM 48 TH ANNUAL CONFERENCE MAY 17-20, 2015 ORLANDO, FLORIDA Public/Private Partnerships and the Public Procurement Process By Roman Martinez, MPA, CPPO, CPPB DEFINITION OF P3S

More information

HRTAC Regional Financial Planning. October 29, 2015

HRTAC Regional Financial Planning. October 29, 2015 HRTAC Regional Financial Planning October 29, 2015 PFM s Transportation Experience For 29 years PFM has been ranked the leading financial advisor, including investment and commercial banks, to transportation

More information

Smart Cities & Integrated Corridors: from Automation to Optimization

Smart Cities & Integrated Corridors: from Automation to Optimization Smart Cities & Integrated Corridors: from Automation to Optimization Presentation to the National Rural ITS Conference August 28, 2013 Cary Vick, Director of Business Development; Smart Mobility for Smart

More information

Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010)

Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010) Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010) Summary Description Proposed Project: Electrified Commuter Rail 30.2 Miles, 13 Stations Total

More information

INDOT 2000-2025 Long Range Plan

INDOT 2000-2025 Long Range Plan Chapter 9 INDOT 2000-2025 Long Range Plan Highway Needs Analysis Overview The statewide transportation planning process provides for the identification of highway needs through a comprehensive process

More information

Implementation of PPPs for Transit: The Request for Proposal Process ADVISORY

Implementation of PPPs for Transit: The Request for Proposal Process ADVISORY Implementation of PPPs for Transit: The Request for Proposal Process ADVISORY Agenda KPMG Introduction The Gotham BIA Connector The initial stages RFI to RFQ The final stages RFP to Evaluation 2 KPMG Infrastructure

More information

Massachusetts Public- Private Partnership Oversight Commission

Massachusetts Public- Private Partnership Oversight Commission July 25, 2014 Massachusetts Public- Private Partnership Oversight Commission PROJECT SPAN: Third Crossing of the Cape Cod Canal P3 Process Update Today s Agenda Sector overview SPAN progress to date Next

More information

Dallas-Fort Worth Area Major Transportation Projects

Dallas-Fort Worth Area Major Transportation Projects Dallas-Fort Worth Area Major Transportation Projects Presented by: Jeffrey C. Neal Program Manager Transportation North Central Texas Council of Governments (NCTCOG) August 14, 2014 Texas Society of Professional

More information

LBJ Freeway in Dallas

LBJ Freeway in Dallas LBJ Freeway in Dallas Texas/USA Ferrovial Agroman is redeveloping the LBJ Freeway to increase capacity and relieve severe congestion in one of the fastest growing areas in the United States. Ribera del

More information

Public Works Financing

Public Works Financing Public Works Financing Published monthly since 1988 by William G. Reinhardt, editor Westfield, NJ PWFinance.net [email protected] Reprinted from June 2010 LBJ Managed Lanes, The Ultimate Greenfield Test

More information

California Self-Help Counties and Transportation Funding

California Self-Help Counties and Transportation Funding California Self-Help Counties and Transportation Funding 2015 IBTTA Washington Briefing Tuesday, March 31, 2015 Michael Blomquist Toll Program Director Riverside County Transportation Commission Traditional

More information

Financing PPPs: Project Finance June 2006

Financing PPPs: Project Finance June 2006 Financing PPPs: Project Finance June 2006 Index Section I. Section II. Section III. Project Finance Spanish Market Advantages Risk Matrix P. 2 Section I Project Finance Project Finance Definition Definition:

More information

PRIORITIZATION PROCESSES

PRIORITIZATION PROCESSES PROJECT SELECTION & PRIORITIZATION PROCESSES STIP Workshop Presented by: Bill Lawrence April 2011 Purpose and Review Overview of Project Selection Process Review Various Prioritization Processes Tk Take

More information

Transportation Asset Management Best Practices for Canada

Transportation Asset Management Best Practices for Canada Primer Transportation Asset Management Best Practices for Canada Introduction Canada ranks seventh in the world in terms of road network size, with a two-lane equivalent length of 1.04 million kilometres,

More information

ORANGE COUNTY TRANSPORTATION AUTHORITY. Final Long-Range Transportation Plan - Destination 2035. Attachment A

ORANGE COUNTY TRANSPORTATION AUTHORITY. Final Long-Range Transportation Plan - Destination 2035. Attachment A ORANGE COUNTY TRANSPORTATION AUTHORITY Final Long-Range Transportation Plan - Destination 2035 Attachment A DESTINATION 2035 DESTINATION 2035 EXECUTIVE SUMMARY ATTACHMENT A Moving Toward a Greener Tomorrow

More information

2014/TPTWG39/IIEG/007 Agenda Item: 07. Implementation of ITS in Malaysia. Purpose: Information Submitted by: Malaysia

2014/TPTWG39/IIEG/007 Agenda Item: 07. Implementation of ITS in Malaysia. Purpose: Information Submitted by: Malaysia 2014/TPTWG39/IIEG/007 Agenda Item: 07 Implementation of ITS in Malaysia Purpose: Information Submitted by: Malaysia 39 th Transportation Working Group Meeting Christchurch, New Zealand 31 March - 4 April

More information

Florida Transportation Commission: A Meeting of the Modes

Florida Transportation Commission: A Meeting of the Modes Florida Transportation Commission: A Meeting of the Modes Corridors of the Future: A National and I-95 Corridor Perspective George Schoener, Executive Director I-95 Corridor Coalition February 12, 2007

More information

Who is implementing managed lanes with pricing strategies? Operational Under Construction/ Development

Who is implementing managed lanes with pricing strategies? Operational Under Construction/ Development Who is implementing managed lanes with pricing strategies? Operational Under Construction/ Development Managed Lane Facilities in the U.S. Operational Under Construction Under Development I-10 (Katy Freeway),

More information

Public Sector Comparator for Highway PPP Projects. Henry Kerali Lead Transport Specialist

Public Sector Comparator for Highway PPP Projects. Henry Kerali Lead Transport Specialist Public Sector Comparator for Highway PPP Projects Henry Kerali Lead Transport Specialist Presentation Outline Purpose and Definition of PSC Basis for comparison between Public v. Private Valuing risk Characteristics

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution Reducing Bid Costs for Outcome-Based Procurements in NSW Infrastructure and Structured Finance Unit: Partnering to Create Partnerships December 2015 1. Evolution of infrastructure procurement in NSW 2.

More information

1. RECOMMENDATIONS. It is recommended that:

1. RECOMMENDATIONS. It is recommended that: Clause No. 7 in Report No. 3 of was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on February 20, 2014. (Mayor Hackson declared an interest in this

More information

Gebze Izmir Motorway & Izmit Bay Crossing Project

Gebze Izmir Motorway & Izmit Bay Crossing Project Gebze Izmir Motorway & Izmit Bay Crossing Project F.Mehmet Coşan CFO Haluk BÜYÜKBAŞ Secretary General, TCA Gebze Orhangazi Izmir Project is the landmark transaction for the infrastructure sector in Turkey

More information

Monitoring Program Results and Next Steps

Monitoring Program Results and Next Steps 8 Monitoring Program Results and Next Steps The improving economy and greater levels of employment observed in 2014 have generally resulted in higher demands on the transportation network. This is apparent

More information

Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents

Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents August 7, 2007 PAGE 1 OF 57 Table of Contents 1. Introduction... 5 1.1 Project Scope Overview... 5 1.2 Short-listed

More information

PPP Experience on the Canada Line

PPP Experience on the Canada Line PPP Experience on the Canada Line International Practicum on Innovative Transit Funding & Financing June 13, 2014 Fred Cummings, P.Eng. President and General Manager BC Rapid Transit Co. Outline TransLink

More information

Asset Management Policy for Major PFI Projects

Asset Management Policy for Major PFI Projects Asset Management Policy for Major PFI Projects Agenda Asset Management Drivers Typical AM positioning in Motorway PFI Asset management Strategy Works Planning and Scheduling Innovation & Risk Mitigation

More information

Availability Payment Mechanisms For Transit Projects ADVISORY

Availability Payment Mechanisms For Transit Projects ADVISORY Availability Payment Mechanisms For Transit Projects ADVISORY Agenda Availability Payments Overview Structure Financial Implications Case Study Additional Considerations KPMG Infrastructure 2 What is an

More information

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City Mayors Welcome Strong Surrey Votes Yes Coalition Support Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City February 11, 2015 Vancouver, BC The Mayors Council on Regional Transportation

More information

The Allen Group, LLC. Company Background and Project Experience

The Allen Group, LLC. Company Background and Project Experience Company Background and Project Experience Resources and Capabilities The Allen Group was first established in the mid-1970s to provide services to the engineering and construction industry. Today, The

More information

Examples of Transportation Plan Goals, Objectives and Performance Measures

Examples of Transportation Plan Goals, Objectives and Performance Measures Examples of Transportation Plan Goals, Objectives and Performance Measures The next step in the Long Range Transportation Plan (LRTP) process is to develop goals, objectives, and performance measures.

More information

KEEPING NEVADA CONNECTED: Future Mobility in the Silver State

KEEPING NEVADA CONNECTED: Future Mobility in the Silver State KEEPING NEVADA CONNECTED: Future Mobility in the Silver State MARCH 2014 202-466-6706 www.tripnet.org Founded in 1971, TRIP, of Washington, DC is a nonprofit organization that researches, evaluates and

More information

Major & State Significant Projects Committee. East West Link Consolidated Business Case SUBMISSION PROPOSAL

Major & State Significant Projects Committee. East West Link Consolidated Business Case SUBMISSION PROPOSAL Cabinet Secretariat Reference Submission No. MSSPC 12 Copy No. Submission to: Submission Title: Portfolio/s: Major & State Significant Projects Committee East West Link Consolidated Business Case Roads,

More information

Introduction. Evaluating Value for Money. Hans de Kievit Senior PPP Consultant. Projects: Auditing Public Private Partnerships; the work continues

Introduction. Evaluating Value for Money. Hans de Kievit Senior PPP Consultant. Projects: Auditing Public Private Partnerships; the work continues Evaluating Value for Money Auditing Public Private Partnerships; the work continues Seminar for Supreme Audit Institutions 26 and 27 November 2012 The Hague, The Netherlands Introduction Hans de Kievit

More information

Summary of MAP-21 Matrix

Summary of MAP-21 Matrix Summary of MAP-21 Matrix Overview On July 6, 2012, President Obama signed into law P.L. 112-141, the Moving Ahead for Progress in the 21st Century Act (MAP-21). Funding surface transportation programs

More information

Integrating State of Good Repair with PPP s

Integrating State of Good Repair with PPP s Los Angeles County Metropolitan Transportation Authority Integrating State of Good Repair with PPP s NCPPP Conference San Diego, California, July 7-8, 2009 Denise L. Longley Deputy Executive Officer, Facilities-Operations,

More information

OVERVIEW PROJECT SUMMARY

OVERVIEW PROJECT SUMMARY OVERVIEW Cesar Chavez showcases how to successfully redesign a primary arterial route into a neighborhood destination, improving modal share, water sensitive design, biodiversity and safety whilst maintaining

More information

I-595 Corridor Roadway Improvements Value for Money Analysis

I-595 Corridor Roadway Improvements Value for Money Analysis I-595 Corridor Roadway Improvements Value for Money Analysis Table of Contents Table of Contents 0. Executive Summary... 2 1. Project Background... 4 1.1. Project History... 4 1.2. Location... 4 1.3. Scope...

More information

Dallas ICM Conception to Implementation

Dallas ICM Conception to Implementation Dallas ICM Conception to Implementation Transit ITS Best Practices Workshop November 13-14, 2013 Agenda Background Conception Procurement -Deployment Q&A Background-DFW Region 5 th most congested region

More information

Preliminary Value for Money Analysis

Preliminary Value for Money Analysis Preliminary Value for Money Analysis Comparison of Project Delivery Methods and Financing Options C-470 ExpressLanes November 2014 Outline Executive Summary Comparison of Delivery Options Base Case Plan

More information

Public Works Financing

Public Works Financing Public Works Financing Published monthly since 1988 by William G. Reinhardt, Editor/Publisher Westfield, NJ www.pwfinance.net [email protected] Reprinted from April 2012 Midtown Financial Close Ignites

More information

Houston TranStar. Greater Houston Transportation and Emergency Management Center. www.houstontranstar.org

Houston TranStar. Greater Houston Transportation and Emergency Management Center. www.houstontranstar.org Houston TranStar Greater Houston Transportation and Emergency Management Center www.houstontranstar.org Houston TranStar Greater Houston Transportation and Emergency Management Center Four Partners Working

More information

Project Rijksweg 15, Maasvlakte-Vaanplein

Project Rijksweg 15, Maasvlakte-Vaanplein Project Rijksweg 15, Maasvlakte-Vaanplein challenges of a DBFM-contract Adrie Franken, Contractmanager A15 MaVa Rijkswaterstaat Topics Project scope Procurement strategy characteristics of the DBFM-contract

More information

The Need for Traffic Incident Management

The Need for Traffic Incident Management The Need for Traffic Incident Management With traffic incidents responsible for approximately 50-60% of the congestion delays motorists encounter on the nation s roadways every day, increased roadway capacity

More information

Matters Raised by PPV Guide to Expert Evidence

Matters Raised by PPV Guide to Expert Evidence Appendix A Matters Raised by PPV Guide to Expert Evidence 7 P a g e a) The name and address of the expert: Michael John Veitch 24 Ferry Street, Sherwood, Brisbane 4075 b) The expert s qualifications and

More information

IDOT Chicago - St. Louis High-Speed Rail Program Management

IDOT Chicago - St. Louis High-Speed Rail Program Management 1 www.idothsr.org www.connectthemidwest.com IDOT Chicago - St. Louis High-Speed Rail Program Management Lessons Learned: Sealing the Corridor For 110 MPH Operations Thomas W. Hunter Parsons Brinckerhoff

More information

Transportation Alternatives

Transportation Alternatives 1 Transportation Alternatives Transportation alternatives involve a variety of components: Location Alternatives - when and where service is provided - general location as well as level of service on the

More information

ANAS Italian Infrastructure Day 2014

ANAS Italian Infrastructure Day 2014 ANAS Italian Infrastructure Day 2014 Borsa Italiana Milan, September 9 th 2014 Key milestones ANAS Group structure 1928 1946 A.A.S.S. (National Autonomous Agency for roads) was established to develop and

More information

Michael I. Schneider Senior Vice President and Managing Director HDR / InfraConsult

Michael I. Schneider Senior Vice President and Managing Director HDR / InfraConsult Senior Vice President and Managing Director HDR / InfraConsult Michael Schneider is co-founder and Managing Partner of InfraConsult LLC, a program management and strategic advisory firm with primary focus

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities PPP Modalities Types and characteristics of PPP are presented in several sections of the Toolkit: refer Types of PPP in Key Issues. This section provides some consideration of which modality, or which

More information

CRISIL Infrastructure Advisory. Key Trends and Outlook Indian Roads Sector

CRISIL Infrastructure Advisory. Key Trends and Outlook Indian Roads Sector CRISIL Infrastructure Advisory Key Trends and Outlook Indian Roads Sector Overview of the Presentation What is the update on road development (NHDP and state road projects)? What are the key trends? What

More information

Agenda. Presentation of SNC-Lavalin Capital Projects presentation PPP Definition Stakeholders Major risks

Agenda. Presentation of SNC-Lavalin Capital Projects presentation PPP Definition Stakeholders Major risks PPP EXPERTISE AND PROJECTS VILNIUS JANUARY 26, 2012 Agenda Presentation of SNC-Lavalin Capital Projects presentation PPP Definition Stakeholders Major risks SNC-LAVALIN AT A GLANCE HIGHLY SKILLED AND FLEXIBLE

More information

THE GLOBAL INFRASTRUCTURE GROUP. Global Capabilities, Sector-Focused Expertise

THE GLOBAL INFRASTRUCTURE GROUP. Global Capabilities, Sector-Focused Expertise THE GLOBAL INFRASTRUCTURE GROUP Global Capabilities, Sector-Focused Expertise GLOBAL CAPABILITIES, SECTOR-FOCUSED EXPERTISE Infrastructure is a rapidly evolving business demanding global capabilities with

More information

Eagle P3 Project Procurement Lessons Learned. Acronyms

Eagle P3 Project Procurement Lessons Learned. Acronyms Eagle P3 Project Procurement Acronyms Regional Transportation District August 31, 2011 1600 Blake Street Denver, Colorado 80202-1399 303.628.9000 RTD-Denver.com As the Regional Transportation District

More information

An Overview of Managed Lanes in the U.S.A. Darren Henderson, AICP

An Overview of Managed Lanes in the U.S.A. Darren Henderson, AICP An Overview of Managed Lanes in the U.S.A. Darren Henderson, AICP Today s s Discussion The Basics HOV Lanes Pricing Darren Henderson, AICP PB, Houston, TX Active Traffic Management The Latest Projects

More information

Implementation of PPPs for Transit

Implementation of PPPs for Transit Implementation of PPPs for Transit The National Council for Public-Private Partnerships Conference, Boston KPMG Infrastructure Advisory September 17, 2009 DRAFT Overview Page Introduction to KPMG Availability

More information