Appeals Case Management System Project. Scope Management Plan. November 20, 2014



Similar documents
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD PHONE (410)

VoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2

Project Management Guidelines

MNLARS Project Audit Checklist

Department of Administration Portfolio Management System 1.3 June 30, 2010

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Minnesota Health Insurance Exchange (MNHIX)

Program Lifecycle Methodology Version 1.7

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing

Template K Implementation Requirements Instructions for RFP Response RFP #

ITRM Guideline CPM Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE

ID Task Name Time Pred

Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date:

Project Management Methodology

PHASE 8: IMPLEMENTATION PHASE

PHASE 6: DEVELOPMENT PHASE

CDC UNIFIED PROCESS PRACTICES GUIDE

PHASE 3: PLANNING PHASE

Project Management Professional (PMP) Examination Content Outline

PMP Examination Tasks Puzzle game

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B

IT Project Management Practices Guide

Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director

Project Implementation Process (PIP)

SCOPE MANAGEMENT PLAN <PROJECT NAME>

How To Develop An Enterprise Architecture

Program Management Professional (PgMP) Examination Content Outline

Construction Management System (CMS) Deliverable Review Process

Solution Architecture Framework Toolkit

A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition

PHASE 3: PLANNING PHASE

PHASE 6: DEVELOPMENT PHASE

Introduction to the ITS Project Management Methodology

SECTION I PROJECT SUMMARY (TRW)

Project Lifecycle Management (PLM)

IT Project Management Methodology. Project Execution Support Guide. Version 0.3

Organization. Project Name. Project Overview Plan Version # Date

Project Team Roles Adapted for PAAMCO

Project Management Professional (PMP) Examination Content Outline

PHASE 5: DESIGN PHASE

Project Management Plan for

ITRM Guideline CPM Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>.

Incident Standard Service Request Information Request. IT Request. Minor/Low Impact Change to Existing Service. Capture and refine the idea

PROJECT MANAGEMENT PLAN <PROJECT NAME>

Presenters Sue Ann Lipinski, Cindy Smith, Angela Riley

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

SACWIS PLANNING FOR DEPARTMENT OF HUMAN SERVICES DRAFT - STRATEGIC IMPLEMENTATION PLAN: MILESTONES & TIMELINES FOR A FULL IMPLEMENTATION

Information Technology Project Oversight Framework

IT Project Management Methodology. Project Scope Management Support Guide

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)

Time Management. Herb Pollard III

A COMPARISON OF PRINCE2 AGAINST PMBOK

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

Project Management Standards: A Review of Certifications/Certificates

Using Microsoft SharePoint for Project Management

Colorado Department of Health Care Policy and Financing

Implementation Strategy

Partnering for Project Success: Project Manager and Business Analyst Collaboration

Understand why, when and how-to to formally close a project

<name of project> Software Project Management Plan

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012

Draft Documents RFP 3.2.4

Interpreting the Management Process in IEEE/EIA with the Help of PMBOK

SECTION I PROJECT SUMMARY (TRW)

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004)

Project Management Professional (PMP) Boot Camp

LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN

IT Project Governance Manual Version 1.1

Project Management Professional Exam Prep Plus

Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]

Project Knowledge Areas

Appendix 2-A. Application and System Development Requirements

Manag. Roles. Novemb. ber 20122

Project Scope Management in PMBOK made easy

PHASE 9: OPERATIONS AND MAINTENANCE PHASE

Project Management Certificate (IT Professionals)

Information Technology Project Oversight Framework

National Research Council Canada IP Prosecution and IP License Management Solution Project

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997

Project Management Planning

Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:

Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes

SLCM Framework (Version ) Roles and Responsibilities As of January 21, 2005

A SUGGESTED HARMONIZATION OF DMAIC WITH PMBOK PROJECT LIFE CYCLES FOR PHARMACEUTICAL LEAN SIX SIGMA PROJECTS

2003 Patricia Ensworth Page 1

Project Management Guidelines

Blend Approach of IT Service Management and PMBOK for Application Support Project

Enterprise Project and Portfolio Management Implementation Project. Update to the ETS Customer Utility Board Julie Pearson May 27, 2015

CMMI: Specific Goals and Practices

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Assessment of NCTD Program Management Framework for Positive Train Control Program

U.S. Department of Education Federal Student Aid

The ITS Project Management Framework

How To Manage The Health Benefit Exchange At Mhix

Transcription:

Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration

Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF CHANGES 1.0 11/20/14 Carolyn B Final Draft ACMS Scope Management Plan Template Revision Approvals Rick Murphy Melody Hayes NAME ROLE DATE Project Manager Project Director i

Table of Contents 1. INTRODUCTION... 1 1.1 PURPOSE... 1 1.2 REFERENCES... 1 1.2.1 External References... 1 1.2.2 Project Centralized Repository Document... 1 1.3 GLOSSARY AND ACRONYMS... 1 1.4 DOCUMENT MAINTENANCE... 2 2. SCOPE MANAGEMENT... 2 2.1 SCOPE MANAGEMENT PLANNING... 2 2.2 SCOPE MANAGEMENT APPROACH... 2 2.3 SCOPE DEFINITION... 4 2.3.1 Project Scope:... 4 2.4 SCOPE VERIFICATION/VALIDATION... 5 2.5 SCOPE CONTROL... 5 APPENDIX A. ACMS PROJECT SERVICES AND PRODUCTS... 7 Table of Tables TABLE 1. SCOPE CHANGES REQUIRING PMC OR ESC ACTION... 3 TABLE 2. SAMPLE DELIVERABLE VERIFICATION MATRIX... 5 ii

1. INTRODUCTION 1.1 Purpose The purpose of the is to help ensure that the project is composed of all the work required, and only the work required, to successfully complete the project. It is the blueprint for how the project s scope will be defined, developed, verified and controlled. The documents the scope management approach and roles and responsibilities pertaining to project scope. It further defines those who will be responsible for managing project scope and serves as a guide for actually managing and controlling the project scope. Project Scope Management consists of the processes detailed in the sections below. ning Scope Management Approach Scope Definition Work Breakdown Structure Creation Scope Verification / Validation Scope Control 1.2 References 1.2.1 External References Project Management Institute (PMI ) Project Management Body of Knowledge (PMBOK) Guide, 5th Edition, Chapter 5 Project Scope Management California Department of Technology California Project Management Methodology (CA-PMM), Section 3.1.2 1.2.2 Project Centralized Repository Document The Appeals Case Management Project (ACMS) Project will utilize a California Department of Social Services (CDSS) shared drive as the Project Centralized Document Repository. The location of the Project Centralized Document Repository is: \\cdss\common\acms. The project will move documents to OSI Clarity once that is available to the project staff. 1.3 Glossary and Acronyms CA-PMM California Project Management Methodology CDSS California Department of Social Services CALHEERS California Eligibility, Enrollment and Retention System CWD County Welfare Department CWS-NS Child Welfare Services-New System DAD Deliverable Acceptance Document 1

DD&I DED DHCS DVM FSR HHS IAPD PCR ACMS PM PMBOK PMI RTM SAWS SHD SI SURGE WBS 1.4 Document Maintenance Design, Development and Implementation Deliverables Expectation Document California Department of Health Care Services Deliverable Verification Matrix Feasibility Study Report Health and Human Services Implementation Advanced Planning Document Project Change Request ACMS Project Manager Project Management Body of Knowledge Project Management Institute Requirements Traceability Matrix Statewide Automated Welfare System State Hearings Division Systems Integrator Service Utilization and Review Guidance Evaluation Work Breakdown Structure This document will be reviewed quarterly and updated as needed, as the project proceeds through each phase of the system development life cycle. This document contains a revision history log. When changes occur, the document s revision history log will reflect an updated version number as well as the date, the owner making the change, and change description. 2. SCOPE MANAGEMENT 2.1 ning Multiple project documents are key inputs that inform the definition of the project scope and the creation of a project scope statement. The ACMS project objectives and requirements found in the ACMS Feasibility Study Report (FSR) and carried forward to the ACMS Project Charter, Work Breakdown Structure (WBS), stakeholder register, and other project planning and procurement documents provide the foundation for the project scope, and detail the work composition, products, peoples and processes that characterize the project and provide information required to establish the project s scope. 2.2 Scope Management Approach For the ACMS, scope management is the sole responsibility of the ACMS Project Manager (ACMS PM). The scope of this project is defined by: Scope Statement 2

Work Breakdown Structure Project Charter Other Project Planning and Procurement Documents The Project Sponsor, Project Director, ACMS PM, ACMS Program Manager, and stakeholders are responsible for establishing and approving documents for project scope measurement, this would include deliverable quality checklists and any work performance measurements. As the project moves through its lifecycle and planned scope becomes completed project objectives, managers and stakeholders use these tools to monitor project accomplishments. For the ACMS project, scope monitoring tools include: Project Charter Work Breakdown Structure Project Schedule updates Weekly Project Status Reports Any proposed change in scope can be compared to the project scope as defined in the WBS and the approved Project Charter. This comparison step performed by the ACMS PM and Project Management Analyst (PM Analyst) helps ensure that only work described in the project s original scope is completed. The completion of items in scope will be tracked as part of the project schedule update and reported in weekly project status meetings. If changes to project scope are absolutely necessary a formal change control process is followed. Minor changes to scope may be approved by the Project Management Committee (PMC) comprised of the ACMS PM and ACMS Program Manager. Major changes are deferred to the Executive Steering Committee for a decision. Table 1 presents potential changes to project scope that trigger action by the PMC and/or ESC. Significant changes to scope are submitted to the appropriate State or federal agency for approval. Please refer to the Change Control Plan for further information). Table 1. Scope Changes Requiring PMC or ESC Action Entity Condition Trigger Body Action (1) Any change to the project scope defined in the project charter that does not add a new category of work. (2) Any change to the project scope defined in the project (1) When the scope change is within the trigger boundaries, proceed with the change after PMC consensus is gained. Scope charter that does not remove (2) Complete the all or a major portion of a PMC Decision Template category of work. (3) Any change to the project scope that does not impact the project goals and objectives. (Governance Plan, Exhibit A) and submit to the ESC when any trigger is exceeded or the PMC defers the decision to the ESC. 3

Entity Condition Trigger Body Action (1) Any change in the scope defined in the project charter that is either beyond the (1) Forward the Decision Template to the ESC when the delegated decision making decision is either authority of the PMC, or the ESC beyond the delegated PMC chooses to defer to a higher authority level for authority of the PMC or deferred. decision closure. 2.3 Scope Definition The ACMS scope definition is included within project planning documents to include the Project Charter and Master Project Management Plan. Project scope is communicated to the Project Sponsor and key stakeholders so there is a common understanding about what the project will or will not address. 2.3.1 Project Scope: The ACMS Project scope includes: Design, development, and implementation of an integrated and automated system that will combine intake, adjudicatory functions, scheduling, and reporting functions into a single workflow. Finalization and implementation of project management plans and implement project and contract management processes, to include quality management, requirements management, and project documentation review and control processes. Clarification, definition, and documentation of ACMS business and technical requirements in a format which will support the subsequent procurement strategy and plans including long-term interoperability. Securing project funding through the draft and approval of an ACMS Implementation Advance Planning Document (IAPD), a Budget Change Proposal, and Special Project Report (SPR). Update the state and federal documents throughout the project duration as needed. Development of ACMS solicitation documents, with evaluation criteria, to conduct procurement to acquire the products and services to support the requested system. Selection and management of integration vendor activities to design, develop, test, pilot, and implement the ACMS. Management and oversight of ACMS transition for maintenance and operations, and project closeout activities. Development of capability to interface with state and federal systems. The scope of the project does not include: Development of system-to-system interfaces. 4

Appendix A. ACMS Project Services and Products lists services and products within the Project scope. 2.4 Scope Verification/Validation Scope verification is the process of determining how deliverables will be compared to the original project scope and how they will be formally accepted. Project deliverables should be verified to project scope and to a Deliverable Expectations Document (DED) and formally accepted by the appropriate stakeholders throughout the life of the project. As the project progresses, the SI PM and ACMS PM must verify that interim deliverables correspond to deliverables originally specified in the project s scope statement and the WBS. After the SI PM and ACMS PM verify that the project s scope is in alignment with all the requirements in the project plan, and that the requirements have been met, deliverables can be formally accepted. Acceptance and approval of deliverables, as well as validation that the deliverables are correct and the project s scope has been met, will be confirmed by the signing of a Deliverable Acceptance Document (DAD). The ACMS project will use a Deliverable Verification Matrix (DVM) in order to track this process. A sample of a DVM is shown below. ACMS Project WBS WBS Level Code Table 2. Sample Deliverable Verification Matrix WBS Element Name Planned Deliverable Deliverable Submitted Variance Comments 1 1.1 Project Communication See Below See Below See Below None 1 1.1.1 Weekly Status Meetings Meeting agenda and notes Meeting agenda and notes None None 1 1.1.2 Weekly Manager s Meetings Meeting agenda and notes Meeting agenda and notes None None 1 1.1.3 Monthly Status Reports Monthly Project Status Report Monthly Project Status Report None None 2.5 Scope Control The process of Scope Control involves monitoring scope elements and drivers over the course of the project for possible changes that can impact approved project scope baselines. The ACMS PM and PM Analyst are responsible for monitoring and addressing any unplanned impacts to scope and must resolve scope change issues before they become critical. It is for this reason that scope elements and drivers should be reviewed regularly. Proposed changes in project scope may be initiated by the Project Sponsor, Project Director, ACMS Program Manager, ACMS PM, team members and other stakeholders 5

by completing Project Change Requests (PCRs). Completed PCRs must be submitted to the PM Analyst who will evaluate the scope change request. Any change being considered must be analyzed for impacts that the change may have on the project. Risk factors must be identified and presented to affected stakeholders. Please refer to the project Change Control Plan for information on the project's change management process, change control roles and responsibilities, and instructions on completing and submitting a Project Change Request. 6

APPENDIX A. ACMS PROJECT SERVICES AND PRODUCTS OSI Planning and Initiation Products Business, Functional and Non-Functional Requirements Report Technical Approach Analysis Report Master Project Management Plan Project Charter Governance Management Plan Communications Management Plan Risk and Issue Management Plan Cost Management Plan Change Control Management Plan Schedule Management Plan Procurement Management Plan Organizational Change Management Plan Knowledge Transfer Plan ACMS Implementation Advance Planning Document (IAPD) ACMS RFP Conduct the solicitation and vendor selection Systems Integrator Products and Services Initiation, Concept and Planning Deliverables Project Management Services Project Management Plan Project Schedule Deliverables Management Plan Work Breakdown Structure Communication Management Plan Monthly Project Status Reports Project Kick-Off Activities and Documents Validated State Hearings Division (SHD) Business Reference Model Validated SHD Business Process Model Validated SHD Process Flows ACMS Use Cases Draft Build Plan Requirements Traceability Matrix (RTM) (Initial and Updates) Requirements Analysis and Design Deliverables ACMS Architecture Detailed Design ACMS General System Design Per-Release Detailed Designs RTM (Updates) 7

Development and Configuration Deliverables Release Packages QA/Testing Deliverables Master Test Plan Test Scripts End of Test Phase Report Release Management Deliverables Release Management Plans Release Management Procedures New Services Rollout Plan New Services Rollout Schedule Release Plans Release Control Monitoring Plan Release Control Processes and Procedures Release Services Implementation Planning Deliverables Implementation Plan Staffing Plan Software and Hardware Purchase Plan Implementation Communication Plan Digital Asset Management Plan Digital Asset Inventory Organizational Change Management Deliverables Organizational Change Management Plan Organizational Change Readiness Assessment Tools Training Deliverables Training Plan Training Materials Instructional Sessions Help Desk Deliverables Help Desk Plan Help Desk Personnel Training Help Desk Services Maintenance and Operations Deliverables Availability Management Plan Availability Management Services Configuration Management Plan Configuration Management Services 8

Capacity Management Plan System Failure and Recovery Plan System Failure Prevention Services System Failure Mitigation Services Performance Management Plan Performance Management Services System Change Management Plan Security Management Plan Security Management Services Transition Deliverables Transition Plan Post-transition Personnel Training Transition Services Service Level and Performance Deliverables Service Level Monitoring Plan Service Level Remediation Plan(s) Service Level Remediation Services Application Maintenance Deliverables Application Maintenance Plan Application Maintenance Services Environment Management Deliverables Environment Management Plan Environment Management Services Archiving Deliverables Archiving Design 9