1 Presenters Sue Ann Lipinski, Cindy Smith, Angela Riley
2 Authorizes the Chief Technology Officer (CTO) oversight authority on agency information technology (IT) projects Establishes the Project Management Office (PMO) within the West Virginia Office of Technology (WVOT) Authorizes the PMO to provide project management on major IT projects* *Major Information Technology Project means any information technology project estimated to cost more than $100,000 or require more than 300 man hours to complete.
3 Establish a methodology for managing IT projects throughout the entire project life cycle Provide support and leadership across state government by establishing standards for IT projects and training of agency project managers Provide oversight for state IT projects by ensuring compliance with state-wide strategic plan Issue standards for IT projects Develop and deliver training to agency project managers
4 Apply standards and establish a methodology that is based on PMBOK Present project concept(s) to the WVOT Project Steering Committee for review Work with agencies and vendors on technology projects to ensure that project objectives are achieved Provide oversight by monitoring the implementation of information management and IT plans and periodically report findings to CTO
5 Primavera will assist us in managing the entire project lifecycle, including projects of all sizes Benefits Optimize resources utilization Reduce costs Manage changes Meet delivery dates Ultimately make better decisions Centralized repository
6 Project management is the application of knowledge, skills, tools, and a standardized process of organizing and planning project activities to meet project requirements. (WVOT EPMO adapted definition)
7 A project is an endeavor undertaken to meet specific goals and objectives that has a defined schedule and follows the project life cycle.
8
9 Initiating Identify and authorize a new project or a new phase of an existing project Planning Establish the scope, define objectives, gather requirements, and determine the actions to complete the project Executing complete the tasks to achieve project objectives according to scope and budget Monitoring and Controlling track, review, report, and regulate the progress of the project within each cycle. One must also identify changes to the plan and initiate a change control process Certification & Accreditation Audit the quality of deliverables and measure results against project requirements to ensure project objectives are met while demonstrating compliance with project standards Closing ensure all tasks are complete; develop a plan for on-going maintenance, and conduct a post project review
10 Complete the Project Concept Form Present the concept to the WVOT Project Steering Committee, in many cases the sponsor is invited to present their concept Determine, at a high level, project budget, schedule and scope Identify stakeholders WVOT EPMO will notify the sponsor of the WVOT Project Steering Committee s decision. Normally, the response is within 30 days of submitting a Project Concept Form Certification & Accreditation
11 General Information Date Submitted, Sponsor, Contact Name, Contact Number, etc. Background and Objectives Project Objectives Project Drivers Organization Scope Funding Sources Acquisition/Support Plans Return On Investment (ROI)
12 Create a Statement of Work (SOW) Assemble the project team Prepare a project plan (budget, schedule, change, issues, risks, communication and quality plans) Prepare requirements specifications Certification & Accreditation
13 Manage the following according to the project plan and report on the following items: Budget Scope Change Issues Risks Quality Develop, acquire, or provide services to meet the project objectives and requirements Certification & Accreditation
14 Project Status reporting to Sponsors and the WVOT Project Steering Committee Hold Project Team Meetings Monitor and Control the following according to the project plan Budget Scope Change Issues Risks Certification & Accreditation
15 Determine if requirements have been met Testing complete w. certification Security and Controls certification complete Documentation complete Plans established and implemented Maintenance Data backup and recovery Data archiving Verify customer acceptance is complete
16 Perform post project review Develop an ongoing maintenance plan Transition to maintenance Deliver documentation to maintenance team and project sponsor Complete the closeout checklist Certification & Accreditation
17 START Project Close-Out Checklist etc.) Functional Requirements Met (reports, screens, forms, performance requirements, etc.) Technical Requirements Met Testing Complete w/certification & Accreditation Security and Controls Certification Complete Documentation Complete Training Complete (End-user, Service Desk, Developers, DBA s, Knowledge Transfer Demonstrated Maintenance Plans Established Support Agreements Implemented Account Authorization and Management Procedures Data Backup and Recovery Data Archiving Plan Licensing Agreements Complete Statement of Work Requirements Achieved Customer Formal Acceptance Complete (Customer Sign-Off) Other Checklist Items NO YES Continue the project Is this Project Complete? Transition to maintenance PROJECT MAINTENANC E
18
CDC UNIFIED PROCESS PRACTICES GUIDE
Purpose The purpose of this document is to provide guidance on the practice called Project Close-Out and to describe the practice overview, requirements, best practices, activities, and key terms related
Appeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
The IT Project Management Framework
The IT Project Management Framework Information Technology Unit Project Management Office Updated: May 2010, Version 1.0 Contacts & Document Control Contact Information ITU Project Management Office, (703)993-2906,
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
Sound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
ID Task Name Time Pred
0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive
How To Write An Slcm Project Plan
SLCM 2003.1 Artifacts in a Nutshell ( as of 01/21/2005) Project Development Phases Pension Benefit Guaranty Corporation s (PBGC) System Life Cycle Methodology (SLCM) is comprised of five project development
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
Project Management for the Professional Professional Part 4 - Stakeholder Analysis. Michael Bevis, JD CPPO, CPSM, PMP
Project Management for the Professional Professional Part 4 - Stakeholder Analysis Michael Bevis, JD CPPO, CPSM, PMP Topic 3 Common Project Stakeholders Who are Stakeholders and what is stakeholder management?
VoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2
VoteCal Statewide Voter Registration System Project Master Project Management Plan Version 1.2 October 2010 October 2010 i REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF CHANGES 0.1 3/12/2009
Domain 1 The Process of Auditing Information Systems
Certified Information Systems Auditor (CISA ) Certification Course Description Our 5-day ISACA Certified Information Systems Auditor (CISA) training course equips information professionals with the knowledge
Program Management Professional. PgMP
Program Management Professional PgMP COURSE BACKGROUND COURSE LENGTH: 3 days (2.1 CEUs / 21 PDUs) COURSE DESCRIPTION: The Program Management course addresses the essential aspects or Program selection,
SLCM Framework (Version 2003.1) Roles and Responsibilities As of January 21, 2005
SLCM Framework (Version 2003.1) Roles and Responsibilities As of January 21, 2005 ROLE RESPONSIBILITY REVIEW SIGN- OFF CTO Manage IT assets to meet corporate goals Establish and chair the Information Technology
The ITS Project Management Framework
The ITS Project Management Framework Information Technology Services Project Management Framework v1.0 1 Table of Contents Introduction 3 Why Create a Project Management Framework? 4 Projects versus Operational
Module 11 Stakeholder Management PMP Exam Questions
Module 11 Stakeholder Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 You are the project manager
Understand why, when and how-to to formally close a project
Project Closure Purpose: Understand why, when and how-to to formally close a project Audience: Project managers, project sponsors, team members and other key stakeholders Learning Objectives: Describe
Using Your PMO to Drive Successful Organizational Change Management
Using Your PMO to Drive Successful Organizational Change Management Joe Saliunas, Booz Allen Hamilton 11 November 2012 1 Agenda Organizational change management overview Case studies PMBOK Guide processes
COMMONWEALTH OF VIRGINIA
COMMONWEALTH OF VIRGINIA Information Technology Resource Management (ITRM) TECHNOLOGY MANAGEMENT PROJECT MANAGEMENT STANDARD Virginia Information Technologies Agency (VITA) Reviews This publication was
44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam
44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION
Gartner, Inc. DIR-SDD-2042
Texas Department of Information Resources STATEMENT OF WORK (SOW) FOR DELIVERABLES-BASED INFORMATION TECHNOLOGY SERVICES Identity & Access Management Analysis IT Assessment & Planning Gartner, Inc. DIR-SDD-2042
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Project Closure. ProPath. Office of Information and Technology
Project Closure ProPath Office of Information and Technology Table of Contents Project Closure Process Map... 1 Process: Project Closure... 2 Project Closure Description and Goals... 3 Description... 3
<INSERT PROJECT NAME> DATA MIGRATION CHECKLIST
DATA MIGRATION CHECKLIST Ensure you always have the latest version of this document. Document Location This document is only valid on the day it was printed. The source of the document
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo
Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading
Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
What you need to know about PMOs
What you need to know about PMOs By Bahar Banyahmad 2009 Overview With PMOs becoming more pervasive in large and medium enterprises, this whitepaper explores different PMO models and functions. It explores
Project Implementation Process (PIP)
Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO
ITS Project Management
ITS Project Management Policy Contents I. POLICY STATEMENT II. REASON FOR POLICY III. SCOPE IV. AUDIENCE V. POLICY TEXT VI. PROCEDURES VII. RELATED INFORMATION VIII. DEFINITIONS IX. FREQUENTLY ASKED QUESTIONS
Information Technology Services Project Management Office Operations Guide
Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...
IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT
United States Department of Agriculture Agricultural Marketing Service Directive 3130.8 IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT I. PURPOSE... 1 II. POLICY... 1 III. DEFINITIONS... 1 IV. DOCUMENTATION
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
ITS Project Management Methodology
ITS Project Management Methodology Standards and Guidelines for managing projects at Information Technology Services, NYU July, 2008 Version 1.4 TABLE OF CONTENTS 1 INTRODUCTION.3 1.1 Overview..3 1.2 Purpose....3
Companion Notes for LTC Process Flowcharts. Notes for Initiation Stage
Companion Notes for LTC Process Flowcharts Contents Notes for Initiation, Planning, Execution/Production and Close Stages Glossary and Acronyms Page 1 4 5 6 Notes for Initiation Stage Purpose The purpose
DIRECTIVE NUMBER: 141.03.04.001 v2.0. SUBJECT: Correctional Integration Systems Change Management Plan
DEPARTMENT OF CORRECTION SUPPORT Management Services DIRECTIVE NUMBER: SUBJECT: Correctional Integration Systems Change PAGE NUMBER: 1 of 10 Adopted: 12-15-03 01.00.00. POLICY OF THE DEPARTMENT It is the
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
Information Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004)
The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) is the processes required to ensure that the various elements of the project are properly coordinated. the processes required to ensure
OFFICE OF AUDITS & ADVISORY SERVICES IT DISASTER RECOVERY AUDIT FINAL REPORT
County of San Diego Auditor and Controller OFFICE OF AUDITS & ADVISORY SERVICES IT DISASTER RECOVERY AUDIT FINAL REPORT Chief of Audits: Juan R. Perez Audit Manager: Lynne Prizzia, CISA, CRISC Senior Auditor:
Project Charter Updated
Enterprise IT Service Management Pilot Proof of Concept Project Charter Updated Prepared By: M. Riley & J. Foster Date of Publication: March 13, 2006 Date Last Revised: April 25, 2007 PMO CH1, 8/01 Document
Manag. Roles. Novemb. ber 20122
Information Technology Manag gement Framework Roles and Respo onsibilities Version 1.2 Novemb ber 20122 ITM Roles and Version History Version ed By Revision Date Approved By Approval Date Description of
PHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
PROJECT MANAGEMENT PROCESS
PROJECT MANAGEMENT PROCESS DOCUMENT # 1.0 SCOPE This Process defines the Enterprise Project Management Office (EPMO) minimum requirements to effectively manage Information Technology (IT) Projects. The
Since its inception, the PMO has functioned to support government entities in implementing project management practices through the:
South Carolina IT Project Management Office Executive Summary As the benefits offered through the use of project management became more apparent to public and private institutions, governmental entities
COMMERCIALISM INTEGRITY STEWARDSHIP. Back-up Policy & Guidance
Back-up Policy & Guidance Document Control Document Details Author Adrian Last Company Name The Crown Estate Division Name Information Services Document Name Back Up Policy Version Date 10/10/12 Effective
Integrating Project Management and Service Management
Integrating Project and Integrating Project and By Reg Lo with contributions from Michael Robinson. 1 Introduction Project has become a well recognized management discipline within IT. is also becoming
Lenovo White Paper. Automated Windows 7 Migration No Desk-side Technicians Required
Lenovo White Paper Automated Windows 7 Migration No Desk-side Technicians Required Lenovo White Paper Automated Windows 7 Migration No Desk-side Technicians Required On April 8, 2014 Microsoft intends
U.S. Department of Education Federal Student Aid
U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Stage Gate Review Process Description Version 1.3 06/30/2015 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Lifecycle
PROJECT GOVERNANCE IN PRACTICE
PROJECT GOVERNANCE IN PRACTICE The everlasting journey towards Value-adding Project Governance Elize van Straten, MBL, PMP, Prince2 South African State Information Technology Agency SOC OVERVIEW Corporate
More on Software Project Management Project and Organizations, Project Portfolio Management, Procurement Management
Planning and Managing Software Projects 2011-12 Class 4 More on Software Project Management Project and Organizations, Project Portfolio Management, Procurement Management Emanuele Della Valle http://emanueledellavalle.org
TRANSITION PLAN TEMPLATE
TRANSITION PLAN TEMPLATE In this template, instructions are included in italics. When you have completed the template and no longer need the instructions, delete them. Provide a brief overview of the transition
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Final Audit Report. Audit of Data Integrity MCCS Feeder System Interfacing with SAP
Final Audit Report Audit of Data Integrity MCCS Feeder System Interfacing with SAP April 2008 Table of Contents Executive Summary... ii Introduction...........1 Background... 1 Audit Objectives... 1 Scope
Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing
STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the
Planning for a Successful Information Governance Program. Kathy Downing, MA, RHIA CHPS,PMP AHIMA Senior Director IG
Planning for a Successful Information Governance Program Kathy Downing, MA, RHIA CHPS,PMP AHIMA Senior Director IG Objectives Overview of Project Management Applying Project Management techniques to Information
IT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
Foundations of Project Management. Presented by: Kelly Baumer, MBA, PMP Mindy Rings, MBA, PMP
Foundations of Project Management Presented by: Kelly Baumer, MBA, PMP Mindy Rings, MBA, PMP August 18, 2014 Project Management Basics In the next slides we will cover: Basic project management terminology
Business Intelligence
1 3 Business Intelligence Support Services Service Definition BUSINESS INTELLIGENCE SUPPORT SERVICES Service Description The Business Intelligence Support Services are part of the Cognizant Information
Project Management Methodology
Project Management Methodology 1/6/2015 PAGE 1 OF 28 Version 2.0 Contents INTRODUCTION... 4 1. Overview... 4 PHASE 1 PROJECT INITIATION... 5 1. Governance Model... 6 2. Project Prioritization Process...
Project Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published by: Project Management
Information Technology Governance Overview and Charter
Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author
MGMT 4135 Project Management. Chapter-16. Project Oversight
MGMT 4135 Project Management Chapter-16 Project Oversight Project Oversight: defined as a set of principles and processes to guide and improve the management of projects. Ensures projects meet the needs
STATE OF MARYLAND 2017 INFORMATION TECHNOLOGY MASTER PLAN (ITMP) Department of Information Technology David Garcia; State CIO
STATE OF MARYLAND 2017 INFORMATION TECHNOLOGY MASTER PLAN (ITMP) Department of Information Technology David Garcia; State CIO Introduction Since taking office in January 2015, Governor Larry Hogan has
ENTERPRISE PROJECT MANAGEMENT OFFICE
ENTERPRISE PROJECT MANAGEMENT OFFICE QUALITY MANAGEMENT SYSTEM ISO 9001:2008 STATE CHIEF INFORMATION OFFICER CHRIS ESTES DEPUTY STATE CHIEF INFORMATION OFFICER AARON WIENSHIENK DEPARTMENT MANAGER JAMES
Document Management Software Rollout Plan
Document Management Software Rollout Plan A guide to managing your document control implementation from start to finish, on time and on budget Copyright 2015 SoftTech Health Starting a Project and Picking
State of West Virginia Office of Technology Policy: Information Security Audit Program Issued by the CTO
Policy: Information Security Audit Program Issued by the CTO Policy No: WVOT-PO1008 Issue Date: 08.01.09 Revised: Page 1 of 12 1.0 PURPOSE The West Virginia Office of Technology (WVOT) will maintain an
PMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases
Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor
Assessing the Appropriate Level of Project, Program, and PMO Structure
PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects
Company A Project Plan
Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures
The Fast Track Project Glossary is organized into four sections for ease of use:
The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face
Selecting a project management methodology
VICTORIAN GOVERNMENT CIO COUNCIL Project Management Selecting a project management methodology Guideline This guideline provides advice for selecting and tailoring a project management methodology. Keywords:
Project Management Methodology
Bridgewater State University Information Technology Project Management Office Project Management Methodology February 5, 2015 Version 15 1 2 Table of Contents REVISIONS HISTORY... 4 PROJECT MANAGEMENT
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Contents. Contract Number (VA-130620-CAI) Contingent Labor Statement of Requirements (SOR) Template v 2.0 January 1, 2014
Contract Number (VA-130620-CAI) Contents STATEMENT OF REQUIREMENTS (SOR)... 2 STATEMENT OF REQUIREMENTS TEMPLATE INSTRUCTIONSError! Bookmark not defined. Page 1 of 10 STATEMENT OF REQUIREMENTS (SOR) SOR
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their
Module 2: The Project Initiation Stage
Overview Initiation stage is highly instrumental in the life cycle of a project as it defines the boundaries of the project gives clarity to all participants about the objectives, scope, cost timescale
Project Management Office Charter
Old Dominion University Office of Computing and Communication Services Project Management Office Charter Version: 1.0 Last Update: February 18, 2010 Created By: Anthony Fox, PMP OCCS Project Management
Blend Approach of IT Service Management and PMBOK for Application Support Project
Blend Approach of IT Service and PMBOK for Application Support Project Introduction: This paper addresses the process area, phases and documentation to be done for Support Project using Project and ITSM
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Enterprise Project Management Office Overview
Enterprise Project Management Office Overview IT Oversight Committee November 12, 2009 Presentation by Kathy Bromead, Director, EPMO Office of Information Technology Services Improving the Management of