PHASE 6: DEVELOPMENT PHASE
|
|
|
- April McLaughlin
- 10 years ago
- Views:
Transcription
1 PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product functions as required. To complete the Phase successfully, two elements are required: 1) a complete set of design specifications and 2) proper processes, standards, and tools. 1.0 OBJECTIVE/GOALS Objectives Successful completion of the Phase should comprise: Building the system Testing and integrating the units into larger components Preparing the technical environment for the system Approval to progress to the Test Phase Goals The purpose of the Phase is to convert the system design prototyped in the Design Phase into a working information system that addresses all documented system requirements. At the end of this phase, the working system will enter the Test Phase. 2.0 DELIVERABLES AND APPROVALS SDLC deliverables help State agencies successfully plan, execute, and control IT projects by providing a framework to ensure that all aspects of the project are properly and consistently defined, planned, and communicated. The SDLC templates provide a clear structure of required content along with boilerplate language agencies may utilize and customize. State agencies may use formats other than the templates, as long as the deliverables include all required content. The development and distribution of SDLC deliverables: Ensure common understanding among members and stakeholders, Serve as a reminder of specified plans as projects become increasingly complex, Provide agency senior management and other State officials insight into project risks and ongoing performance, Encourage the execution of repeatable and consistent processes, Facilitate the implementation of project management and agency IT best practices, and Result in a comprehensive record of project performance useful for many purposes (e.g. staff knowledge transfer, budgetary and other assessment activities, lessons learned). During the development of documentation, the should: Write comprehensive, easy to understand documents with no redundant information. Develop an organized document repository for critical project information, so members can easily access, store, and reference project documents and other deliverables from all life cycle phases. Implement routine deliverable reviews to correct inaccuracy, incompleteness, and ambiguities. Single Release Custom Page 1 of 14 Phase 6:
2 Recognize that sample templates for deliverables are available; agencies might accept deliverables in different formats as long as all required information is present. The content of these deliverables might expand or shrink depending on the size, scope, and complexity of the project. Recycle or reference information from earlier documents where possible and beneficial. The following is a listing of deliverables required of all projects for this phase of work. Deliverable Goals Developed By Approved By Software Document details the provisions, including specific coding instructions, unit test cases, and scripts, for developing each unit or module of the system; also includes development procedures for issue tracking and configuration management and any other information that aids in building the functionality of the system. Document all preparations related to the development of each software unit and other items that will help explain the functionality of the software Describe development methodologies System (Application) Software file or set of files that contain the application or software code on discs or other media. Provide software that meets the business needs and all requirements Test Data contains dummy data used for testing; the data is not sensitive or live. Provide sample representative data to use in test activities Ensure that testing results simulate production results Manager Integration Document describes the assembly and interaction of the hardware, software, and any other components of the system. Document planned approach and activities for the integration of hardware, software, and other system components Single Release Custom Page 2 of 14 Phase 6:
3 Deliverable Goals Developed By Approved By Test Analysis Report(s) presents a description of the unit tests and the results mapped to the system requirements; also identifies system capabilities and deficiencies. Record results of tests Present the capabilities and deficiencies for review Provide a means for assessing software progression to the next stage of development or testing Conversion Plan (Update) describes the strategies and approaches for converting/migrating data from an existing system to another hardware or software environment. Document all planned activities to ensure a smooth data conversion from a legacy system to a new environment Implementation Plan (Update) describes how the information system will be deployed as an operational system. Define all planned activities to ensure successful implementation to production operations Operations Manual or Systems Administration Manual The Operations Manual focuses on mainframe systems; the Systems Administration Manual is oriented toward distributed (client/server) applications. Provide detailed instruction for system operations Release Notes provides summary information regarding the current release of the system being built; typically includes major new features and changes and identifies known problems and workarounds. Document critical information regarding the system release Single Release Custom Page 3 of 14 Phase 6:
4 Deliverable Goals Developed By Approved By Maintenance Manual details effective system maintenance. Appendices might document maintenance procedures, standards, or other essential information. Training Plan outlines technical and user training needs on the new or enhanced information system. User Manual describes to end users how to make full use of the information system, including system functions and capabilities, contingencies and alternate modes of operation, and step-by-step procedures for system access and use. Provide maintenance personnel with the information necessary to maintain the system effectively Ensure the schedule accounts for all necessary training needs to implement, operate, and maintain the system successfully Provide users with detailed information to fully utilize the system All deliverables other than those identified as Updates should be developed in this phase. Deliverables identified as Updates should be revisited and enhanced as necessary as prescribed in this phase. Deliverables produced during this phase must be reviewed in detail and should follow the approval path as defined in the above table. A signature page or section should accompany each deliverable requiring approval. DoIT will periodically request copies of these documents as part of its oversight responsibilities. 3.0 ROLES The following personnel participate in the work activities of this phase: Executive Manager Stakeholders Single Release Custom Page 4 of 14 Phase 6:
5 RACI Key Responsible Describes role that executes the activities to achieve the task. Accountable Describes roles that own the quality of the deliverable and sign off on work that Responsible provides. Consulted Describes roles that provide subject matter expertise. Informed Describes roles that receive information about the task. Deliverable Executive Manager Software Document I I A R I I System (Application) Software I A A R I C Test Data I I A R I C Integration Document I A A R I I Test Analysis Report(s) I I A R I I Conversion Plan I I A R I I Implementation Plan I A A R I I Operations Manual or Systems Administration Manual Stakeholders I I A R I I Release Notes I I A R I I Maintenance Manual I I A R I I Training Plan I A A R I I User Manual I I A R I I Possible RACI Matrix The Roles and Responsibilities page has detailed descriptions of these roles and their associated responsibilities. Single Release Custom Page 5 of 14 Phase 6:
6 4.0 TASKS AND ACTIVITIES Phase 6 Phase Manager START 4.1 Review Phase Prerequisites 4.2 Monitor Performance 4.3 Update PMP & Communications Plan 4.4 Perform Risk Management Activities Deliverables Executive Agency CIO Single Release Custom Page 6 of 14 Phase 6:
7 Phase 6 Phase Executive Agency CIO Manager 4.5 Initiate Activities 4.6 Code and Test Software 4.7 Integrate Software 4.8 Conduct Integration Training Deliverables Software Document System (Application) Software Test Data Test Analysis Report Single Release Custom Page 7 of 14 Phase 6:
8 Phase 6 Phase Manager 4.11 Plan for Operations & Maintenance Activities Executive Agency CIO 4.9 Plan the System Integration 4.10 Plan the System Implementation Deliverables Conversion Plan Integration Document Implementati on Plan Operations Manual or Systems Admin Manual Single Release Custom Page 8 of 14 Phase 6:
9 4.1 Review Phase Prerequisites. The Manager ensures the following prerequisites for this phase are complete: The Management Plan is current, and the schedule showing the target termination date for the system is current. The has completed: o System Design Document o Test plans for unit and integration testing (draft) o Conversion Plan (draft) o Implementation Plan (draft) Single Release Custom Page 9 of 14 Phase 6:
10 o Operations or System Administration Manual (draft) o Maintenance Manual (draft) o Training Plan (draft) o User Manual (draft) 4.2 Monitor Performance. The Manager monitors project performance by gathering status information about: All changes to baseline data Change management information Activity progress with status details List of complete and incomplete deliverables Activities initiated and finished Estimated time to completion Resource utilization data Changes to project scope The Manager also organizes and oversees systematic quality management reviews of project work as a part of monitoring the project performance. To measure project effort at all phases of the life cycle, the Manager establishes timelines and metrics for success at each phase of work when planning project tasks. PMBOK provides additional details on controlling project work in sections 4.4 and 4.5 and on project scope control in section Update PMP and Communication Management Plan. The Manager updates the PMP routinely (at least quarterly) to ensure the PMP reflects project performance accurately. Review project performance controls and risks for deviations from the baseline. Information distribution is one of the most important responsibilities of the Manager. The Manager reviews and updates the Communication Management Plan at least quarterly to account for potential changes in project stakeholders. The Manager distributes the updated PMP and risk management information according to the revised Communication Management Plan. PMBOK Chapter 10 contains additional details on project communications and information distribution. 4.4 Perform Risk Management Activities. The Manager conducts risk management activities during the Phase; these activities include: Identification determination of initial risks that might affect the project and emerging risks as well as each risk characteristic Risk Analysis conducting quantitative and/or qualitative analysis of each identified risk. Usually, qualitative risk management techniques are the most applicable for State projects. Single Release Custom Page 10 of 14 Phase 6:
11 These risk analysis methods, as well as the conditions under which each method might be used, are described in detail in PMBOK, section 11. Response Planning planning of methods for developing mitigation, transfer, or avoidance strategies to reduce risk Monitoring and Control definition of procedures to track risks, monitor residual risk, identify new risks, execute response plans, and evaluate risk management effectiveness These activities occur throughout the project duration to track and mitigate any new or changed project risks. PMBOK has details for risk management activities in section 11, particularly sections 11.2 through Initiate Activities. The begins development by: Verifying selection for standards, methods, tools, and computer programming languages Consulting with the Maryland EA Repository for available tools and components of the system Carrying out Phase activities according to the detailed project WBS prepared during the Planning Phase Performing configuration management and change control Documenting and resolving problems and non-conformances found in the software products and tasks with an issue-tracking process stakeholders should be involved periodically throughout the Phase to ensure that the development team understands their expectations and that it develops the system in accordance with requirements. 4.6 Code and Test Software. The develops and documents each software unit and database. Members of the involved in constructing the software may include software architects, business analysts, technical analysts, programmers with different levels of expertise, database administrators, test or quality assurance engineers, and other roles. Because the effort is so large, the may request assistance from infrastructure groups, such as telecommunications or networking. While developing the code, the should consult the Maryland EA Repository for any usable components and strive to build reusable code. Reusing code is particularly valuable when the project involves new software or software components or replacing large legacy components. After building the software, the should enable future software reuse on State projects by submitting the code or software to the Maryland EA Repository. The creates test procedures and data for testing each software unit and database. Single Release Custom Page 11 of 14 Phase 6:
12 The performs unit tests of each software unit and documents the results in the Test Analysis Report(s). The also updates the RTM to include pointers to test results and updates the test requirements. The conducts routine code reviews to monitor progress and quality according to: Traceability to the requirements and design of the system Quality of coding documentation Test coverage of units Resolution of testing deficiencies Appropriateness of coding methods and standards used 4.7 Integrate Software. The integrates the software units and software components and tests as the aggregates are developed. The must ensure that each aggregate satisfies the requirements of the software item and that the software item is integrated at the conclusion of the integration activity. 4.8 Conduct Integration Testing. The conducts integration testing of integrated software units. Integration testing involves the testing of aggregated software units, which were previously unit-tested. Through integration testing, s are able to verify requirements of major groupings of the software. The summarizes the testing results in the Test Analysis Report(s). The also updates the RTM to include pointers to test results. 4.9 Plan the System Integration. The develops an Integration Document to assemble the software units, software components, and the hardware into the system. The document includes procedures, responsibilities, and a schedule for combining the units into a working information system. The Manager and review the Integration Document while considering: Traceability to the system requirements Consistency with system design Quality of units based on test results The Manager conducts project-level and technical reviews of the Integration Document Update the System Implementation Plan. The updates the implementation procedures as necessary for the system in the target environment. Single Release Custom Page 12 of 14 Phase 6:
13 4.11 Plan for Operations & Maintenance Activities. The Manager and review Phase deliverables, and the Manager adds any necessary tasks to the project plan for the Operations & Maintenance Phase Complete the System Documentation. The finalizes the following documents: Conversion Plan Implementation Plan Maintenance Manual Operations or Systems Administration Manual Training Plan Release Notes User Manual 4.13 Perform Phase-Closure Activities. The Manager and the prepare and present a project status review for the,, Executive, and other project stakeholders after completion of all Phase tasks. This review addresses: Status of Phase activities Planning status for all subsequent life cycle phases, with significant detail about the next phase Status of resource availability scope control as described in the Scope Statement/System Boundary Document and any required adjustments to the scope Changes to the project schedule and estimated completion date Go-No Go decision made to proceed to next phase, based on Phase information Verification that all changes are conducted in accordance with the approved Change Management Plan The Manager compares actual project performance to the PMP and the projected cost of the project to detect and understand any variances from the cost baseline during the phase-end review. The Manager also performs a comprehensive risk assessment of the project to update the risk analysis. The Manager updates the Maryland EA Repository with any new or updated components before beginning the next phase, Test. The Manager must obtain deliverable approval signatures before proceeding to the Test Phase. Update the project documentation repository upon completion of the phase-closure activities. Single Release Custom Page 13 of 14 Phase 6:
14 5.0 CONCLUSIONS At the end of the Phase, the has created a working information system. The completion of the System (Application) Software, approval of the Phase deliverables, the completion of the project status review, and the approval to proceed to the next phase, signify the end of the Phase. Single Release Custom Page 14 of 14 Phase 6:
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
PHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
PHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
PHASE 1: INITIATION PHASE
PHASE 1: INITIATION PHASE The Initiation Phase begins when agency management determines that a business function requires enhancement through an agency information technology (IT) project and investment
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
Draft Documents RFP 3.2.4
Draft Documents RFP 3.2.4 In accordance with RFP 3.2.4, CNSI includes the required draft documents in the following order: Work Plan: Team CNSI provides a comprehensive draft Work Plan for the Iowa EHR
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
Manag. Roles. Novemb. ber 20122
Information Technology Manag gement Framework Roles and Respo onsibilities Version 1.2 Novemb ber 20122 ITM Roles and Version History Version ed By Revision Date Approved By Approval Date Description of
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
Appeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Independent Verification and Validation of SAPHIRE 8 Software Project Plan
INL/EXT-09-17022 Rev. 2 Independent Verification and Validation of SAPHIRE 8 Software Project Plan March 2010 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
Peer Review Process Description
Peer Review Process Description Version 1.0 draft1 Table of Contents 1. Overview... 1 2. Work Aids... 1 3. Risk Assessment Guidance... 1 4. Participants... 2 5. Inspection
Appendix 2-A. Application and System Development Requirements
Appendix 2-A. Application and System Development Requirements Introduction AHRQ has set up a Distributed Systems Engineering Lab (DSEL) to support all internal development efforts and provide a facility
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date: 07-31-2012
Minnesota Health Insurance Exchange Project (MNHI) Deliverable Definition Document (DDD) For Project Plan Date: 07-31-2012 11/9/2012 1:18 PM Page 1 of 8 1. High Level Deliverable Description The Project
RFP Attachment C Classifications
RFP 1. Applications IT Architect Analyzes and designs the architecture for software applications and enhancements, including the appropriate application of frameworks and design patterns and the interrelationships
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
Peer Review Process Description
Peer Review Process Description Version 1.0 draft1 Table of Contents 1.Overview...1 2.Work Aids...1 3.Risk Assessment Guidance...1 4.Participants...2 5.Inspection Procedure...4
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
How To Write An Slcm Project Plan
SLCM 2003.1 Artifacts in a Nutshell ( as of 01/21/2005) Project Development Phases Pension Benefit Guaranty Corporation s (PBGC) System Life Cycle Methodology (SLCM) is comprised of five project development
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Certified Software Quality Engineer (CSQE) Body of Knowledge
Certified Software Quality Engineer (CSQE) Body of Knowledge The topics in this Body of Knowledge include additional detail in the form of subtext explanations and the cognitive level at which the questions
IT Project Management Methodology. Project Execution Support Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution
Systems Development Life Cycle (SDLC)
DEPARTMENT OF BUDGET & MANAGEMENT (SDLC) Volume 1 Introduction to the SDLC August 2006 Table of Contents Introduction... 3 Overview... 4 Page 2 of 17 INTRODUCTION 1.0 STRUCTURE The SDLC Manual consists
How To Implement An Enterprise Resource Planning Program
ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing
Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director
Overview of Florida Information Technology Project Management and Oversight Standards Jason M. Allison, Executive Director AGENCY FOR STATE TECHNOLOGY Statutory duties and responsibilities of AST: Establish
Release Management Policy Aspen Marketing Services Version 1.1
Release Management Policy Version 1.1 John Toso 5/10/2010 2 Contents Release Management Policy Overview:... 3 Critical Success Factors... 3 Service Level Management (SLM)... 4 Key Performance Indicators:...
System Development Life Cycle Guide
TEXAS DEPARTMENT OF INFORMATION RESOURCES System Development Life Cycle Guide Version 1.1 30 MAY 2008 Version History This and other Framework Extension tools are available on Framework Web site. Release
Colorado Department of Health Care Policy and Financing
Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500
Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: [email protected] Phone:
Essentials of the Quality Assurance Practice Principles of Testing Test Documentation Techniques. Target Audience: Prerequisites:
Curriculum Certified Software Tester (CST) Common Body of Knowledge Control Procedures Problem Resolution Reports Requirements Test Builds Test Cases Test Execution Test Plans Test Planning Testing Concepts
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
WHAT IS SOFTWARE PERFORMANCE ENGINEERING? By Michael Foster www.cmgaus.org
WHAT IS SOFTWARE PERFORMANCE ENGINEERING? By Michael Foster www.cmgaus.org DEFINITION Software Engineering is: A systematic and quantitative approach for the cost effective development of software systems
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
COMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF HEALTH AND HUMAN SERVICES
COMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF HEALTH AND HUMAN SERVICES The Office of Information Technology Project Methodology and Lifecycle Guide Version 4.4 Last Updated: November 15, 2011 CE M
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
Partnering for Project Success: Project Manager and Business Analyst Collaboration
Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,
Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
Blend Approach of IT Service Management and PMBOK for Application Support Project
Blend Approach of IT Service and PMBOK for Application Support Project Introduction: This paper addresses the process area, phases and documentation to be done for Support Project using Project and ITSM
PMAP. Project Management At Penn PMAP
Project Management At Penn 1 Fundamentals Course Objective To provide you with an overview of Topics Project Management at Penn () Project Governance Phases & Project Management Activities Project Management
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Customer Account Data Engine 2 Systems Development Guidelines; However, Process Improvements Are Needed to Address Inconsistencies September 30, Year
Test Plan (a Real Sample) SoftwareTestingHelp.com Live Project Training - OrangeHRM
www.softwaretestinghelp.com Test Plan (a Real Sample) SoftwareTestingHelp.com Live Project Training - OrangeHRM 2/1/2014 SoftwareTestingHelp.com Name of the tester Note: This is a sample test plan created
IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT
United States Department of Agriculture Agricultural Marketing Service Directive 3130.8 IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT I. PURPOSE... 1 II. POLICY... 1 III. DEFINITIONS... 1 IV. DOCUMENTATION
CDC UNIFIED PROCESS PRACTICES GUIDE
Purpose The purpose of this document is to provide guidance on the practice called Project Close-Out and to describe the practice overview, requirements, best practices, activities, and key terms related
Practice Overview. REQUIREMENTS DEFINITION Issue Date: <mm/dd/yyyy> Revision Date: <mm/dd/yyyy>
DEPARTMENT OF HEALTH AND HUMAN SERVICES ENTERPRISE PERFORMANCE LIFE CYCLE FRAMEWORK PRACTIICES GUIIDE REQUIREMENTS DEFINITION Issue Date: Revision Date: Document
July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services
John Keel, CPA State Auditor The ReHabWorks System at the Department of Assistive and Rehabilitative Services Report No. 12-045 The ReHabWorks System at the Department of Assistive and Rehabilitative Services
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010
CDC UNIFIED PROCESS PRACTICES GUIDE
Document Purpose The purpose of this document is to provide guidance on the practice of Requirements Definition and to describe the practice overview, requirements, best practices, activities, and key
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP)
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Version 1.0 Prepared by: Date: November 24, 2008 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0 Responsible
IT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Project Management Professional (PMP) Boot Camp
Project Management Professional (PMP) Boot Camp According to the Project Management Institute, the world's leading association for the project management profession: "PMP Certification is the profession's
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
DOC Electronic Timekeeping System Quarterly Project Oversight Report: Comprehensive Review For Period January March 2015
Department of Corrections Electronic Timekeeping System Project For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Corrections (DOC) Project Name: Electronic Timekeeping
Managing Small Software Projects - An Integrated Guide Based on PMBOK, RUP, and CMMI
Managing Small Software Projects - An Integrated Guide Based on PMBOK, RUP, and CMMI César Cid Contreras M.Sc. Prof. Dr. Henrik Janzen Published at the South Westphalia University of Applied Sciences,
ájoƒ ùdg á«hô dg áµلªÿg Yesser Overall SDLC Process Definition
ájoƒ ùdg á«hô dg áµلªÿg Yesser Overall SDLC Process Definition Version 0.6 - Page 3 / 43 Table of Contents 1. Process Introduction... 5 1.1. Process Scope... 5 1.2. Process Objectives and Benefits... 5
Example Software Development Process.
Example Software Development Process. The example software development process is shown in Figure A. The boxes represent the software development process kernels. The Software Unit Testing, Software Component
Testing Metrics. Introduction
Introduction Why Measure? What to Measure? It is often said that if something cannot be measured, it cannot be managed or improved. There is immense value in measurement, but you should always make sure
Earned Value Management for Enterprise Resource Planning Implementations
Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,
PMLead. Project Management Professional. edition. Based on PMBOK Guide 4 th. www.pmlead.net
PMLead Project Management Professional Based on PMBOK Guide 4 th edition www.pmlead.net SECTION II Chapter 3 Project Management Processes Chapter 3 Project Process Groups A process is a set of interrelated
Sample Quality Management Plan
This reference documents project-specific quality assurance and quality control procedures appropriate to the size, complexity, and nature of the project. Quality improvements are also documented and may
ITS Projects Systems Engineering Process Compliance Checklist
ITS Projects Systems Engineering Process Compliance Checklist FHWA Final Rule (23 CFR 940) This checklist is to be completed by the MDOT or LPA Project Management Staff. Please refer to the accompanying
Draft Requirements Management Plan
BAO111: Core Competencies for the Business Analyst Draft Requirements Management Plan 1.0 INTRODUCTION 1.1 Purpose This document outlines requirements roles and responsibilities, presents a stakeholder
Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development
Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software
Project Management. Training Courses
Project Management Certification and Training Courses Table of Contents Page On Site Training 4 Custom Course Development and Training 5 Project Management Training and Certification Courses Project Management
PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP
TSE015 PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP Course Outline I. Introduction and Course Objectives A. About PMI B. PMP and CAPM
Course Syllabus. Project Management Certificate
Course Syllabus Project Management Certificate Prerequisite(s): Some college and professional experience in managing projects. Required Materials/Texts: ISBN: PMBOK Guide 5 th Edition 978-1935589679 Managing
HOW NOT TO ATTRACT AN ENTREPRENEURIAL PM
HOW NOT TO ATTRACT AN ENTREPRENEURIAL PM FORTUNE 500 HIGH-TECH EQUIPMENT AND SERVICES COMPANY Process-focused job description indicates low potential for career enhancement and discourages talent from
SEVEN KEY TACTICS FOR ENSURING QUALITY
SEVEN KEY TACTICS FOR ENSURING QUALITY 1 INTRODUCTION Besides avoiding disasters and fatal flaws, quality assurance (QA) delivers significant benefits for banks. Strong QA planning provides the groundwork
Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
TASPO-ATS-L System Test Plan
TASPO-ATS-L System Test Plan Automated Targeting System-Land ATS-L_(WR_1941)_STP_1.1 Document Number: ATS-L_(WR_1941)_STP_1.1 October 6, 2011 For Official Use Only - 42414 - TASPO-ATS-L System Test Plan
Project Lifecycle Management (PLM)
Project Lifecycle Management (PLM) Process or Tool? Why PLM? Project Definition Project Management NEW REQUEST/ INITIATIVES SUPPORT (Quick fixes) PROJECT (Start Finish) ONGOING WORK (Continuous) ENHANCEMENTS
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Project Management Life Cycle (PMLC)
Project Management Life Cycle (PMLC) Page 2 Project Management Life Cycle (PMLC) Introduction PMLC Working Group IT Business Process Management(BPM) IT Project Management Office (PMO) Finance System Support
Qlik UKI Consulting Services Catalogue
Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction
Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
