1 Specification for Installation of Underground Conduit Systems November 2008 Version 2.0
2 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: 2.0 Table of Contents Page Definitions... 3 User Notifications Scope Responsibility of Developer Source of Materials Joint Installation Inspection of 3 rd Party Installations Safety Precautions Excavation Conduit Installation Pole Risers Drainage of Pre-Cast Boxes Trenching Concrete and Grout This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 2
3 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: 2.0 Definitions The following definitions shall apply to this document: COMPANY shall mean FortisBC, or its duly authorized representatives. CONTRACTOR shall mean a qualified constructor who holds a valid certificate issued by the Governing Authority. In the context of this document, the Contractor has been retained by, and is acting under the direction and authority of the Developer or their duly appointed representative to physically construct the underground distribution facilities as defined in the plans. DEVELOPER shall mean the Registered Owner or Corporation, or its duly appointed representative(s), including their engineering consultant(s) and/or contractor(s), having an interest in the land on which the underground electrical system specified is being installed. DEPOT shall mean a supplier's warehouse or storage yard, a Company storage yard or any other place or places designated by the Company as a material pick-up point. GOVERNING AUTHORITY shall mean the British Columbia Safety Authority, City, Municipality, Regional District, Provincial Government Agency, First Nations Band or Federal Government Agency having jurisdiction over the work site. PLANS shall mean the drawings, approved by the Governing Authority and issued by the Company, detailing the location and grades of conduit, pre-cast concrete boxes, concrete pads or like structures required to be placed for the Company on a specific project. PROPERTY OWNER shall mean the person(s) and/or entity(ies) named as the registered owner(s) of real property as registered on the property title with the Land Titles Office. STANDARD DRAWINGS shall mean those drawings illustrating typical installations and/or specifying materials to be used. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 3
4 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: 2.0 User Notifications Use of FortisBC Engineering and Construction Standards. a) In accordance with FortisBC Engineering Practices Policy, FortisBC Engineering and Construction Standards are developed and used only for FortisBC designs and construction, and only for FortisBC distribution facilities. b) FortisBC Engineering and Construction Standards are copyright protected. Drawings and specification within this document, in whole or in part, shall not be copied, modified, amended nor changed without written consent from FortisBC. c) Use of FortisBC Engineering and Construction Standards by any Developer is done at the Developer s own risk and liability. d) These standards may carry the name or logo of West Kootenay Power, UtiliCorp Networks Canada or Aquila Networks Canada. Any such references shall be taken as reference to FortisBC. e) FortisBC expects that construction by others for any electrical system or distribution facility adjoining, attaching, or otherwise affecting FortisBC distribution facilities shall meet or exceed FortisBC Engineering and Construction Standards. f) FortisBC recommends that the Developer retain a professional engineer to coordinate and assess the completeness of the overall project design and/or construction to ensure that it meets the requirements as defined by this document and those of other parties involved. Overall project design and/or construction includes, but is not limited to, underground electrical distribution facilities, underground sanitary sewer installations, underground storm sewer installations, underground water distribution and irrigation facilities, underground cable television facilities, underground natural gas facilities, underground telephone facilities, underground fiber optic cable installations, legal survey requirements, required permits, etc. g) Review and/or comment on the overall project designs and/or constructions by FortisBC does not relieve the Developer from full responsibility and liability for designs and/or constructions produced by themselves or on their behalf. h) By requesting and/or accepting copies of any FortisBC Engineering and Construction Standards, the Developer automatically accepts the terms and conditions of this letter. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 4
5 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Scope This specification describes the materials to be used, the standard of work required, and the responsibility of the Developer in the construction of the underground electrical system. These standards in no way imply that the Developer is allowed to construct anything other than what he or she is authorized to do in the FortisBC design package or as otherwise instructed by the FortisBC local representative. These Standards shall not be used for work other than for FortisBC. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 5
6 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Responsibility of Developer The Developer must construct the underground electrical system in compliance with this document. Where the Developer retains a Contractor to construct the underground electrical system, the responsibilities outlined herein will remain with the Developer. The developer is responsible to verify the qualifications of their retained contractor and must be prepared to provide documentation of said qualifications at the request of FortisBC Where there is any question regarding the interpretation of these standards, or where information may be lacking, it is incumbent upon the Developer or his representative to contact the local FortisBC representative for a written explanation. The Developer must obtain the latest revision of this document and the Company stamped APPROVED FOR CONSTRUCTION plans before commencing work. Any work undertaken on the basis of supplied preliminary information is done so at the risk and responsibility of the Developer. Extra costs may result if not working from approved for construction drawings and information. The Developer shall comply with all requirements of the Governing Authority as to the manner in which all work is done. This means that all conduit, grounding, bonding and transformer pads are to be installed under the direct on-site supervision of a Field Service Representative (FSR) as per Safety Standards Act ELECTRICAL SAFETY REGULATION (B.C. Reg 100/2004) The on-site installation crew must be lead by a certified FSR who must be present at all times that work is being preformed. The Developer shall be fully responsible for proper coordination of the project including the provision of sufficient lead times for submission and approval of plans, field inspections, testing, and energization of the system. The Developer shall be responsible for all costs associated with: a) Purchase and installation of all materials necessary to install the electrical system as specified in the Standard Drawings and Plans. b) Transportation of all materials supplied by the Company from the designated depots to the job site, and the return of surplus materials to the depots unless otherwise directed by the Company. c) Replacement of any materials lost or damaged after receipt of them. d) Supply of materials such as gravel, sand, pre-cast or poured in place material, forming lumber and other miscellaneous construction items. e) All machine and hand excavations necessary for placing conduit, pre-cast concrete boxes, concrete pads, and other facilities as may be required in the standard drawings and plans. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 6
7 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: 2.0 In all locations the Developer shall be responsible to minimize damage and restore all damaged pavement, sidewalks, curbs, gutters, developed or undeveloped areas to the satisfaction of the Property Owner(s) and the Governing Authority. Prior to excavation, the Developer shall: a) Comply with all regulatory requirements of the Governing Authority. b) Consult with the owners of buildings, retaining walls, poles, lamp standards, landscaping or any other structures which may be endangered by the work, and provide adequate support or measures necessary to protect those items to the satisfaction of the owner and the Governing Authority. After civil construction has been completed the Developer shall provide as-constructed information clearly noted in red on one of the FortisBC drawings. FortisBC will not issue a Certificate of Total Performance or schedule electrical installation until as-constructed plans have been received by the Company. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 7
8 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Source of Materials FortisBC reserves the right to specify material manufacturers in order to ensure the quality of materials installed. The supply of conduit, fittings, pre-cast concrete products and grounding materials shall be the Developer's responsibility. 3.1 Pre-cast Concrete Boxes, Vaults and Lids Description Manufacturer / Part No. FortisBC Item No. Assembly or Structure No. service box with lid Kon Kast / 1060 / 1061 / SOCP / 0600 / 0602 single phase junction vault Kon Kast / 1031 SOCP / single phase junction vault lid Kon Kast / SOCP / Civil Box separable splice Kon Kast / SOCP / 0620 Civil Box separable splice lid Kon Kast / SOCP / junction vault with lid Kon Kast / SOCP / 0624 / single phase transformer box Kon Kast / SOCP / single phase transformer box lid Kon Kast / SOCP / street light base Kon Kast / 1045 & 1050/1042/ SOCP / 0632 Switching cubicle Kon Kast Pre cast Pad 3 phase transformer Kon Kast 1058D Above Grade 200 A Junction Kon Kast This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 8
9 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Grounding Description Manufacturer /Part No. FortisBC Item No. cable, #2/0 stranded copper, soft drawn, bare cable, #2/0 stranded copper, soft drawn, poly covered RW 90, 600 volts connector, copper, wrench installed, #2/0 copper to #2/0 copper connector, copper, wrench installed, #2/0 copper to ¾ ground rod rod, ground, sectional, ¾ x 6, steel, tapered both ends cable, #4 stranded copper, soft drawn, bare, for welding or bonding. Nexans / Pirelli / General Cable Nexans / Pirelli / General Cable Burndy GXW26C Ampac - Tyco / Burndy GXW29C Ampac Tyco / any manufacturer as per description General Cable This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 9
10 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Conduit and Fittings Description Manufacturer / Part No. FortisBC Item No. Pipe conduit, 2, rigid PVC, 10ft length, bell end Ipex / conduit, 3, rigid PVC, 10ft length, bell end Ipex / conduit, 4, rigid PVC, 10ft length, bell end Ipex / conduit, 2, DB2, 20ft length, bell end Ipex / (gray) conduit, 3, DB2, 20ft length, bell end Ipex / (gray) conduit, 4, DB2, 20ft length, bell end Ipex / (gray) conduit, 2, rigid PVC, 20ft length, bell end Ipex / conduit, 3, rigid PVC, 20ft length, bell end Ipex / conduit, 4, rigid PVC, 20ft length, bell end Ipex / End Bell Fittings end bell, for 3 DB2 Ipex / end bell, for 4 DB2 Ipex / end bell, socket molded, for 3 rigid PVC Ipex / end bell, socket molded, for 4 rigid PVC Ipex / Couplers coupler, DB2, 2 Ipex / coupler, DB2, 3 Ipex / coupler, DB2, 4 Ipex / coupler, rigid PVC, 2 Ipex / coupler, rigid PVC, 3 Ipex / coupler, rigid PVC, 4 Ipex / Sweeps sweep, 90 degree, DB2, 2, 24 radius Ipex / sweep, 90 degree, DB2, 3, 36 radius Ipex / sweep, 90 degree, DB2, 4, 36 radius Ipex / sweep, 90 degree, rigid PVC, 2, 24 radius Ipex / sweep, 90 degree, rigid PVC, 3, 36 radius Ipex / sweep, 90 degree, rigid PVC, 4, 36 radius Ipex / Adapters adapter, rigid PVC to DB2, 2 Ipex / ARIG20 or adapter, rigid PVC to DB2, 3 Ipex / adapter, rigid PVC to DB2, 4 Ipex / Miscellaneous tape, underground warning, "CAUTION BURIED ELECTRIC LINE", red tape with black lettering, 6 wide, heavy duty polyethylene, 4.0 mil thick Brady / This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 10
11 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: 2.0 Description pull string, 3/16 stranded polyvinyl, 2500 pound minimum tensile strength Manufacturer / Part No. any manufacturer as per description FortisBC Item No. The developer shall supply incidental construction materials such as PVC solvent weld, grout, sand and gravel appropriate for the construction method and conduit material. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 11
12 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Joint Installation When FortisBC facilities are to be installed jointly in the same trench with the facilities of telephone, cable, gas or any other utility, it is a responsibility of the Developer to ensure coordination is maintained with the respective parties. The Developer shall ensure that the minimum physical separations are maintained between FortisBC facilities and the facilities of other Utilities such as telephone, cable television, gas, water, sewer, fiber optic, etc. Standard Structure Drawing No of this document specifies FortisBC s minimum requirements; it should however be noted that other Utilities may specify separations that exceed those of FortisBC. The Developer shall ensure that facility separations meet or exceed the requirements of all parties involved. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 12
13 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Inspection of Installations Inspection by FortisBC shall take place at the following construction phases. Note that survey evidence must be in place before an inspection can occur. a) After the ducts have been installed, but before sand back-fill or concrete capping. b) After ground rods and counterpoise connections have been made. c) During installation of pull strings. d) Upon completion of the curb installations, or if no curbs are being installed, upon completion of boulevard grading and road paving. e) After the Developer advises FortisBC that the conduit system has been installed according to FortisBC standards and is ready for the electrical construction. After any inspection, all openings in boxes must be covered with securely fastened 1/2" plywood. 5.1 Development Owner/Service Provider Constructed Subdivision Inspections The Engineer of Record is responsible to provide proof that a competent person(s) inspect the conduit systems as per a, b, & d in the above inspection schedule. FortisBC will have access and the right to inspect the conduit system at any point/phase in its construction. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 13
14 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Safety Precautions The Developer shall perform all work in conformity with Workers Compensation Board of BC or like regulations. Any directive given by a FortisBC representative shall not supercede WCB or like regulations. If civil work is required on or near structures containing energized cables, the Developer shall give FortisBC 48 hours notice to arrange for a qualified Company representative to be on site during the excavation. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 14
15 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Excavation The Developer shall guarantee all grades. Any discrepancies between design and actual grades discovered during the final inspection shall be corrected by the Developer at the Developer's expense. Road crossings shall be excavated at right angles to the road. The Developer shall be responsible for determining whether road cuts will be allowed by the Governing Authority. The Developer shall be responsible for any additional costs associated with boring or tunneling under road. Survey pins displaced by the Developer shall be reinstalled within 60 days by a legal surveyor at the Developer s expense. Final approval cannot be granted by FortisBC until survey pins have been established. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 15
16 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Conduit Installation Conduit shall not be installed below 10 º C temperature because of the high risk of duct damage and/or coupling separation. Conduit shall not be installed into any existing FortisBC infrastructure without a qualified Company representative on site. Modification of conduit entrance to structures, pads, buildings, etc. shall be pre-approved by FortisBC. Conduit terminating at buildings shall be installed in accordance with the latest version of CSA standard C22.3 No. 7, Underground Systems, requiring that the ducts be adequately sealed, drained, graded or vented to prevent entry of gas or water, either from the outside surface or through the ducts. Unless otherwise noted, all conduit for secondary shall be 100 mm Conduit shall enter, exit, and be located in pre-cast concrete boxes and concrete pads in accordance with the following Standard Drawings. FortisBC Structure Description No Concrete Service box Civil 1591 Single Phase 200A 15/25 Kv Junction Civil x 58 Civil Box Phase Low Profile Padmount Transformer Phase Junction Vault (200A) 15/25 Kv 832 Style Kv Pre-cast switch Cubicle Base Phase Transformer base larger than 500 KVA 1597 Pre-cast 3 phase transformer base 500 KVA or less 1598 Above Grade 200A Junction All conduit terminated in full sized deep junction boxes shall be terminated with preformed end bells, grouted into place. All others shall be capped. Conduit terminating in side walls of junction and transformer boxes shall leave at right angles to the box wall for a minimum distance of 1 meter before being formed into the trench configuration. All terminated conduit shall be capped (but not sealed) and shall be marked with lot number and or duct designation. All conduit shall have polyvinyl 5 mm stranded pull string installed. The pull string shall have a minimum tensile strength of 11,000 N All conduit shall extend at least 50 mm and no more than 100 mm above drain rock or finished grade. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 16
17 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Pole Risers Conduit bends shall be installed at the base of poles designated as riser poles on the plans. These bends shall be located on the quadrant of the pole as illustrated in Standard Structure Drawing No All conduit bends shall be located to permit the use of standoff brackets on the pole. The Developer shall install appropriately sized 90º sweeps terminating at the base of the riser pole; these shall be capped and identified, but not sealed. FortisBC shall supply and install conduit up the riser structure when the underground electrical system installed by the Developer is connected to the FortisBC distribution system. In other words, the Developer shall not be required to supply nor install conduit up the pole when the underground system being installed connects to FortisBC s overhead primary facilities. On customer owned 1 secondary services over 200A, or any three phase secondary services, the Developer shall supply the duct required to run up the pole. FortisBC shall install this customer owned conduit up the pole. 1 Refer to the FortisBC Service and Metering Guide available at for more information on demarcation between customer and FortisBC owned and maintained facilities. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 17
18 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Drainage of Pre-Cast Boxes The Developer shall ensure that drain holes in all pre-cast boxes are clear and free draining (open), and are positioned or oriented at the lowest point of grade. Where water drains are required, the Developer shall provide a means of drainage to storm sewers or catch basins as indicated on the standard plans and drawings. Such drain systems shall meet the approval of the Company and the Governing Authority. Out-fall shall be proven prior to boxes being placed. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 18
19 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Trenching Backfilling shall not be performed until a Company inspector has approved the phase of the project to be backfilled. Visual checks completed by the FortisBC Inspector shall include: The bottom of the trench and the backfill material is rock free. Sand bedding is installed. Proper compaction of excavated areas. Proper location, placement and depth of conduit. Proper placement of marker tape along conduit alignment. Pads, boxes and bases installed to proper level and grade according to designs and plans. If native fill is specified it shall mean excavated material free of organic material and rock larger than 150 mm in diameter. Frozen material shall not be used as backfill. Under freezing conditions, backfill material shall be dry. Where no suitable backfill material is available all ducts shall be encased in concrete. Sand shall be added and hand tamped or compacted with a plate vibrator to give a minimum cover of 150 mm over the conduit. Mechanical impact tampers shall not be used as they could damage the conduits. Underground warning tape shall be installed mm below finished grade. Only red plastic tape bearing the words CAUTION BURIED ELECTRIC LINE shall be used. All backfilling and compaction shall be done to the satisfaction and acceptance of FortisBC and the Governing Authority, and shall be subject to inspection at all times. The Developer shall maintain open excavations at his or her own liability and expense, and shall also be fully responsible to minimize hazards to people and property while trenches are open. The Developer shall be responsible for maintaining the backfilled excavation until all settlement has ceased. This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 19
20 Specification For Installation of Underground Conduit Systems Revision Date: November, 2008 Version No.: Concrete and Grout All concrete, reinforced or not, shall meet the requirements of the current edition of the Canadian Standards Association standard CSA-A , Concrete Materials and Methods of Concrete Construction. Concrete shall be sulphate resistant, Type 50, 3000 psi (20 MPA) minimum 28 day compressive strength. Air entraining agents shall be between 4-7% of final product, and shall conform to the requirements of ASTM International standard ASTM C260-01, Standard Specification for Air- Entraining Admixtures for Concrete. Calcium chloride accelerators shall not be used in the pour. Alternate accelerators might be used, subject to FortisBC approval. Grout or mortar shall be prepared as per the manufacturer s instructions. All conduit sweeps except street lights shall be encased in concrete in accordance with the following Standard Drawings. FortisBC Drawing No. Description F-20 Placement of Facilities; Concrete Encasement - Bends F-21 Placement of Facilities; Concrete Capping - Pole Riser F-23 Placement of Facilities; Concrete Capping - Deep Box Entry Mechanical separation shall be maintained between utilities by means of 6 mil poly barrier, or 100 mm layer of clean fine sand. Concrete capping shall be formed in place and finished to a minimum thickness of 100 mm Maximum thickness shall not exceed 200 mm This document is the property of FortisBC and is for authorized use only. The most current version of this document is available at Page 20
21
22
23
24
25
26
27
28
29
30 Fortis B i l l o f M a t e r i a l 2008/02/16 Structure # 1342 POLE RISER FOR MULTI DUCT ENTRANCE Item # UI Description BOLT, MACHINE, 3/4 X 12 INCH BOLT, MACHINE, 3/4 X 14 INCH BOLT, MACHINE, 3/4 X 16 INCH BOLT, MACHINE, 3/4 X 18 INCH BOLT, LAG, 1/2 X WASHER, SQ, 3 X 3 X 1/4, 13/16 HOLE WASHER, SPRING LOCK, DOUBLE 3/ BRACKET, ALUMINUM, STANDOFF BRACKET, T SLOT, 4 WAY,12 INCHES LONG BRACKET, T SLOT, 4 WAY, 24 INCHES LONG STRAP, KIT, 3 INCH STRAP, KIT, 4 INCH REMARKS: for single duct entrance with provision for 1 extra conduit for single duct entrance with provision for 1 extra conduit for multi duct entrance with provision for 3-3 inch duct for multi duct entrance with provision for 3 4 inch duct 5. Order additional length of T-Slots as required. 12" item " item " item " item Order appropriate DB2 to Rigid PVC adaptor as required; 1.- Item is for 2" applications 2.- Item is for 3" applications 3.- Item is for 4" applications
31
32 Fortis B i l l o f M a t e r i a l 2007/10/20 Structure # 1416 CIVIL, PAD, STREET LIGHT BASE Item # UI -1 Description BASE, STREET LIGHT, CONCRETE REMARKS: 1. Does not meet MMCD requirements for highways and arterial, collector, roadways. Use for residential roadways only
33
34 Fortis B i l l o f M a t e r i a l 2007/10/20 Structure # 1417 CIVIL, STREET LIGHT CONTR BASE, TYPE C-1 Item # UI -1 Description BASE,HIGH AND ROAD WAYS LIGHTING,TYPE C1 REMARKS: 1. The base is used for mounting street lighting controller s Meets MMCD requirements for highways, collector and arterial roadways
35
36 Fortis B i l l o f M a t e r i a l 2007/10/28 Structure # 1418 CIVIL, STREET LIGHT BASE, TYPE C Item # UI -1 Description BASE,HIGH&ROAD WAYS POLEMOUNTING,TYPEC REMARKS: 1. The maximum pole height mounted on this base is 11 meters (33 feet) 2. Meets MMCD requirements for highway, collector and arterial roadways.
37
38
39 Fortis B i l l o f M a t e r i a l 2007/11/30 Structure # 1590 CIVIL, BOX, CONCRETE SERVICE BOX Item # UI -1 Description ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED VAULT, CONCRETE, SERVICE BOX REMARKS: 1. For use with structure 1501.
40
41 Aquila Networks Canada 2004/01/09 Structure # 1591 B i l l o f M a t e r i a l CIVIL, BOX, SINGLE PHASE JUNCTION Item # UI Description M 13 WIRE, COPPER, STR, SD BARE, 2/ M 8 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECT.3/4 CU TO 2/0 COND CONNECT. 2/0 CU COND ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED BOX-TRANSF.SUPPORT- 48X40X24C/W UNISTRUT LID-PLATE-STEEL-RECESSED-48X 40. REMARKS: 1. For use with structure 1511 and 1512
42
43 Fortis B i l l o f M a t e r i a l 2008/05/14 Structure # 1592 CIVIL, BOX, SEPERABLE SPLICE Item # UI -2 Description M 15 WIRE, COPPER, STR, SD BARE, 2/ M 8 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECTOR, 3/4 CU GRD ROD TO 2/0 CU CONNECTOR, 2/0 TO 2/0 CU ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED BOX-CONCRETE PULL-58X58X54 C/W UNISTRUTS LID-PLATE STEEL-RECESSED-58X 58. Remarks: To be use with s1533
44
45 Fortis B i l l o f M a t e r i a l 2008/04/28 Structure # 1593 CIVIL, SUPPORT BOX 15/25 KV SINGLE PH TR Item # UI -1 Description M 13 WIRE, COPPER, STR, SD BARE, 2/ M 8 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECTOR, 3/4 CU GRD ROD TO 2/0 CU CONNECTOR, 2/0 TO 2/0 CU ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED BOX-TRANSF.SUPPORT- 48X40X24C/W UNISTRUT LID-CONCRETE # X 40LESS METAL FIL
46
47 Fortis B i l l o f M a t e r i a l 2008/03/26 Structure # 1594 CIVIL, BOX 3-PHASE 832 JUNCTION Item # UI -1 Description M 17 WIRE, COPPER, STR, SD BARE, 2/ M 10 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECTOR, 3/4 CU GRD ROD TO 2/0 CU CONNECTOR, 2/0 TO 2/0 CU ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED VAULT, 832 JUNCTION, C/W COLLAR REMARKS: 1. For use with structures 1536/1537.
48
49 Fortis B i l l o f M a t e r i a l 2007/05/15 Structure # 1595 CIVIL, BOX 15 KV Item # UI -1 Description M 17 WIRE, COPPER, STR, SD BARE, 2/ M 10 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECTOR, 3/4 CU GRD ROD TO 2/0 CU CONNECTOR, 2/0 TO 2/0 CU ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED PULL BOX, PRECAST, 2.1M X 2.0M X 1.2M
50
51
52 Fortis B i l l o f M a t e r i a l 2008/10/09 Structure # 1596 CIVIL, TRANSFORMER BASE 15/25 KV Item # UI -1 Description M 17 WIRE, COPPER, STR, SD BARE, 2/ M 6 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECTOR, 3/4 CU GRD ROD TO 2/0 CU CONNECTOR, 2/0 TO 2/0 CU ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED REMARKS 1. Concrete Transformer base may be poured on site or pre-cast
53
54 Fortis B i l l o f M a t e r i a l 2008/04/28 Structure # 1597 CIVIL, SUPPORT BOX 15/25 KV THREE PH TR Item # UI -1 Description M 16 WIRE, COPPER, STR, SD BARE, 2/ M 8 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECTOR, 3/4 CU GRD ROD TO 2/0 CU CONNECTOR, 2/0 TO 2/0 CU ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED PAD, PRECAST CONCRETE, TRANS, KVA
55
56 Fortis B i l l o f M a t e r i a l 2008/10/02 Structure # 1598 BASE FOUNDATION FOR ABOVE GRADE 200 A Item # UI -1 Description M 6 WIRE, COPPER, STR, SD BARE, 2/ M 3 CONDUCTOR, STR CU, 2/0 POLY, 600 VOLTS CONNECTOR, 3/4 CU GRD ROD TO 2/0 CU CONNECTOR, 2/0 TO 2/0 CU ROD, GRD, SECTIONAL, 3/4 X 6' TAPERED BASE, PRECAST FOR ABOVE GROUND 3 PHASE REMARKS: 1. Structure 1598 is the base foundation for Standard Structure 1543 (Above Grade 200A junction)
57
58
59
60
Specification 6020. Underground Services - Subdivisions. Issue 12
Building Industry Consulting Services (BICS) Specification 6020 Underground Services - Subdivisions Issue 12 Page 1 of 59 Distribution Conduit Are Provided By Others In Accordance With CRTC Tariff 21461,
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING
TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
SECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements
16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Underground Service Requirements and Instructions
This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
COMMERCIAL CONDUIT RULES AND REGULATION
Electric Engineering Division COMMERCIAL CONDUIT RULES AND REGULATION S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies\Residential 1805 NE 30th Ave., Bldg. 400 Ocala, FL 34470-4875
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
Town House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
TABLE OF CONTENTS. PUD SERVICE TERRITORY & CONTACTS... Page 1. NEW SERVICE QUESTIONNAIRE... Page 2. GENERAL... Page 3
UNDERGROUND TABLE OF CONTENTS PUD SERVICE TERRITORY & CONTACTS... Page 1 NEW SERVICE QUESTIONNAIRE... Page 2 GENERAL... Page 3 TRENCHING SECONDARY (120/240 volts)... Page 3 CONDUITS FOR PUD-INSTALLED CONDUCTORS...
MOBILE HOME SERVICE REQUIREMENTS GAS
ELECTRIC AND GAS 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL 4.0 REFERENCE MATERIAL 5.0 TYPICAL UNDERGROUND UTILITY LAYOUT 6.0 METER PAD DETAILS 7.0 GENERAL INSTALLATION PROCEDURES 8.0 PEDESTAL SPECIFICATIONS
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
LS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding
AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding A Guide for California Developers of Com m ercial Property This guide consists of
SECTION 16402 UNDERGROUND ELECTRIC SERVICE
SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum
SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
505.3.6 For a building with a crawl space, see Figure 10. 505-1
505 WATER SERVICE INSTALLATION 505.1 DEFINITION A service line is comprised of the piping and related appurtenances including the connection installed from the Des Moines Water Works water main to the
ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS
Prepared by: ABB1 ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS 052521 Asset Type: Electric Metering Function: Construction Issued by: Quoc Hoang (QxH1) Date: 07-01-16 Rev. #06: This document
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
Ontario Electrical Safety Code - Info Sheet
Ontario Electrical Safety Code - Info Sheet The following are the Code requirements and explanatory material for buried electrical wiring that are applicable to most residential applications. 12-012 Underground
Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL
155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS
Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes
CANTEX INC. 301 Commerce Ste 2700 Fort Worth, Texas 76102 817-215-7000 Fax: 817-215-7001 Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes YOUR FULL
EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
CABLE TRENCH INSTALLATION GUIDE
1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL INFORMATION 4.0 PLANNING INFORMATION 5.0 CREW INFORMATION 6.0 CONTRACTOR INFORMATION 7.0 PRECASTED/ POURED-IN-PLACE TRENCH DRAWINGS 2.0 PURPOSE This standard
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
Beacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0
Merrimac Municipal Light Department. Residential Developments Policy
Merrimac Municipal Light Department Residential Developments Policy General: This document provides specific instructions for the provision of underground electrical facilities associated with the construction
08003-1 WATER SERVICE 2
08003_Mar08_2011.pdf Page 1 of 7 INDEX Page 08003-1 WATER SERVICE 2 1.1 Pipe 2 1.1.1 Copper 2 1.1.2 Polyethylene 2 1.2 Valves and Fittings 2 1.2.1 Main Stops 3 1.2.2 Curb Stops 3 1.2.3 Curb Box 3 1.2.4
CHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
CARROLL COUNTY ELECTRICAL DEPARTMENT SERVICE POLICIES. EFFECTIVE MARCH 1, 1995 Revised 1/01/2013
CARROLL COUNTY ELECTRICAL DEPARTMENT SERVICE POLICIES EFFECTIVE MARCH 1, 1995 Revised 1/01/2013 CARROLL COUNTY ELECTRICAL DEPARTMENT 103 WEST PARIS ST. P. O. BOX 527 HUNTINGDON, TENNESSEE 38344 Telephone
SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS
1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General
SECTION 18370 SIGNAL WIRE AND CABLE
SECTION 18370 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for all cable and wire required for signal and signal power system wiring to wayside shelters, junction boxes, and factory
The Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21
September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,
Underground Commercial Electric Service
Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
Least Cost Cable System. Strategies to Reduce Cable and Infrastructure Costs When Transitioning to an All Conduit Systems
Least Cost Cable System Strategies to Reduce Cable and Infrastructure Costs When Transitioning to an All Conduit Systems Cost Sharing of Cable Systems Underground Extensions The Company will construct
Exhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
Construction Specifications for Keyhole Pavement Coring and Reinstatement
F I N A L Construction Specifications for Keyhole Pavement Coring and Reinstatement Gas Technology Institute 1700 S. Mount Prospect Rd. Des Plaines, Illinois 60018 www.gastechnology.org Version 13 October
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
IRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
Guidelines for Fiber Optic Cable Permits
Guidelines for Fiber Optic Cable Permits NOVA District (Fairfax/Arlington) Permits www.virginiadot.org/business/fairfax-permits-main.asp Email: [email protected] 14685 Avion Parkway
MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3
TOWN OF SIDNEY Multi-Family, Commercial, Industrial and Institutional Building Permit Guide The information provided is intended as a guide only and does not replace current bylaws and regulations. Complete
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
Gas Meter Clearances and Service Installation Requirements
March 2015 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE s Customer Construction Services 1-888-321-7779 or visit PSE.com/CustomerConstruction
SHALLOW UTILITIES JOINT PROVISIONING GUIDELINES SCOPE
AN INFORMATION GUIDE SCOPE PROJECT MANAGER Joint Provisioning Guidelines for Shallow Utility Services in Residential Areas where the Electric, Gas, Telephone & Cable TV facilities are Buried in the same
SECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General
SECTION 15 AIR RELEASE VALVE ASSEMBLIES 15-1.01 Scope 15-1 General This section describes the requirements for furnishing and installing Air Release Valve Assemblies of the size and type shown on the plans,
Please check with your local inspection authority for any additional requirements before installation.
Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be
3. TYPES OF SERVICE AVAILABLE. 3.1 Scope
3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
X Planning X Quality X Maintenance & Operations
Delaware Department of Transportation Division of Transportation Solutions Design Guidance Memorandum Memorandum Number 1-20 Revised 1. Road Design Manual 2. Bridge Design Manual 3. Utilities Design Manual
Welcome: What is U Drain? Drain Materials. Flow
Welcome: Thank you for looking into the U Drain floor drain system. This paper will explore the functional features of the U Drain and why it is superior to other grated systems in the marketplace. We
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
Electric Service Guide for Commercial Construction
Electric Service Guide for Commercial Construction Contents Contacting KCP&L... 2 Voltages... 2 Temporary Service... 2 Customer-Provided Temporary Service... 2 KCP&L-Provided Temporary Service.... 2 Current
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
EFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection
EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED
SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS
1 SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS TABLE OF CONTENTS I. Introduction II. General Information and Requirements A. Applying for Sewer connection B. Excavation C. Cutting Concrete and Asphalt
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
Specifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
DIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
Section 600 Incidental Construction
Table of Contents 1. Pipe Culverts... 600-1 A. Endwalls, Inlets, Manholes, and Spring Boxes... 600-5 2. Grade Adjustment of Existing Miscellaneous Structures... 600-8 3. Rebuilt Miscellaneous Structures...
SECTION 02845 GUARDRAILS
SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein
NEW SERVICE INSTALLATION STEPS. Common Slow Downs. Other Necessary Steps
NEW SERVICE INSTALLATION STEPS Here is the step-by-step process required to fulfill your service installation request. Please take a few minutes to review the steps, become familiar with key milestones
Electric Service Guide. Residential Subdivision
January 1, 2016 Contact MID s Electric Engineering Department ([email protected]) with any questions about this Service Guide. Check MID s website (www.mid.org) Electric Service Guide for the
Electrical Service Guidelines
Electrical Service Guidelines Middle Tennessee Electric Membership Corporation Revised: May 23, 2013 MTEMC's Electrical Guidelines TABLE OF CONTENTS Right-of-Way Clearance Guide 3 MTEMC Requirements 4
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12
SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes grounding and bonding products, design requirements and installation for communications
1 Town of Lyons Electrical Distribution System Design Standards
Town of Lyons Electrical Distribution System Material and Design INDEX 6.1 Design Criteria 6.11 Submissions 6.1.2 Method 6.1.3 Criteria 6.2 Specifications 6.2.1 Scope 6.2.2 General Requirements 6.2.3 Materials
CP2 Buried Cable Pedestal Initial & Rehab Installation Instructions
Printing 3 March 2008 CP2 Buried Cable Pedestal Initial & Rehab Installation Instructions This instruction is intended for CP2 cable pedestal installations and replacements. The following tools will be
SPECIAL SPECIFICATION 5757 Power Duct System
2004 Specifications CSJ 0353-04-088 SPECIAL SPECIFICATION 5757 Power Duct System 1. Description. This Item shall govern for the furnishing and installing of all materials, equipment, and labor listed in
Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
Developer s/consultants Field Services Guidelines
Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872
CITY OF SELMA, TEXAS Inspection Checklist: Commercial
Rev Y71004 The Permits and Inspections Department welcomes you to the City of Selma. The following information is provided to you as guidance through the inspection process. The City of Selma provides
Specifications for Electrical Installations
Electric Service Bulletin No. 759B April 2014 Supplement to Specifications for Electrical Installations Underground Commercial Distribution (UCD) Installation and Responsibility Guide Liberty Utilities
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
TELUS Residential Service Conduit Requirements for Stand Alone Homes and Duplexes in Fibre Only Communities
1 TELUS Residential Service Conduit Requirements for Stand Alone Homes and Duplexes in Fibre Only Communities Beginning in January 2010 TELUS began designing new subdivisions within the Top 48 population