1 Project Development Revised 4/17/13 Process PROJECT INITIATION PHASE 1. Upon receipt of a signed Budgetary Estimate, including an index number, the work of creating a Project begins as follows: PRE-DESIGN Scoping Phase Feasibility Phase Programming Phase Scoping phase a) PM establishes a file for the project b) Identify client s single point of contact c) Is project within a facility worth the investment of funds d) Will proposed changes significantly increase the cost of maintaining and operating the facility e) If project will significantly increase operating costs, a mitigation plan should be developed. f) Address code compliance issues; Life Safety, ADA, IBC g) Does not cause a permanent negative impact on adjacent space/facilities h) Conforms with Campus Master Plan principles i) Is in a space or facility assigned to the requesting department j) If initial budgetary estimate is greater than $300k, project will need approval from BOR, HED, BOF. k) What are the client s budgetary and schedule expectations l) Is this a current or future BRR project Feasibility Phase Administration a) Define team composition and specific roles/responsibilities for each group on the team b) Consider project delivery method: 1) Internal design services 2) Professional services contract ($20k range limit) 3) Initiate an RFP for external design services Program Analysis a) Review the physical and functional opportunities for this project b) Conduct preliminary architectural and engineering review with either internal staff or external firm.

2 c) Assess the risks of not proceeding with this project d) Determine compliance with the University Master Plan e) If new construction, identify potential sites and requisite adjacencies Conceptual Plans a) Develop conceptual plans for each option under consideration with sufficient detail to illustrate project scope, test adequacy of layout, and provide basis for intermediate budget estimates. b) Assess preexisting building conditions that may affect project s outcome c) Identify building materials and systems d) Determine conceptual building massing Financial Analysis a) Review authorizations for funding b) Develop benchmark budgets for each option Utility Review a) Outline utility infrastructure requirements: location, capacity, condition b) Determine utility infrastructure availability, condition, capacity, and extension requirements to the site c) Determine communications infrastructure requirements to the site Code Assessment a) Consult with Construction Industries Division to identify extraordinary or atypical code requirements b) Review accessibility issues, if any c) Refine list of applicable codes Project Schedule a) Refine planning schedule b) Identify factors that will influence the implementation schedule c) Evaluate schedule options for each option. Site Analysis a) Identify logistical issues with regard to construction and/or operation b) Review possible program adjacency requirements c) Review parking at proposed site and vehicular, pedestrian, bicycle, mass transit, and building services access (maintenance parking, loading dock, etc.) d) Review site boundary and topographic surveys e) Review building orientation f) Review preliminary storm water requirements Deliverables a) Feasibility study for options b) Recommendation of preferred option

3 Programming Phase Program Analysis a) Consolidate client s Statement of Need, objectives, goals, space requirements, and operational plan into a program b) Identify elements subject to change and make an assessment of short term and long term requirements. c) Will food service be part of the program (including vending machines). Include Auxiliary Services in the planning of food service space. d) Determine interrelationships of the various functions that will be housed in this facility. e) The Program describes the scope and quality that the facility will accommodate. Develop a Programming report that includes the following: 1) Background 2) Project Process 3) Definition of goals and objectives 4) Square footage 5) Design concepts 6) Technical requirements 7) Utility requirements 8) Schedule 9) Budget Utility Review a) Determine energy and other utility requirements for the facility b) Determine whether campus utility capacity at the project site is sufficient to meet project requirements. Environmental Assessment a) Identify and evaluate existing environmental conditions. b) Review special occupant safety requirements. Code Assessment a) Review existing building conditions and summary of required code improvements b) Review extraordinary or atypical code requirements c) Review project intent with CID d) Assess research functions and types/amounts of chemicals to be used in laboratory facilities in order to determine: *Building code hazard classification * Special exhaust and filtration requirements Preservation Analysis

4 a) Identify, evaluate, and document historic resource preservation status, treatment requirements, and proposed project treatment responses. Budget Categories A) Construction Costs: a) Pre-construction services b) Land Acquisition c) Building acquisition d) General requirements e) Permits/regulatory f) Utility charges g) Site construction-existing conditions h) Concrete i) Masonry j) Metals k) Wood. Plastics, and composites l) Thermal and moisture protection m) Openings n) Keys and keying o) Finishes p) Specialties q) Signage and graphics r) Equipment s) Furnishings t) Conveying systems u) Fire suppression v) Plumbing w) HVAC x) Telecomm and data y) Electrical z) Earthwork aa) Exterior improvements bb) Utilities

5 Budget Categories (cont.) B) Professional Fees a) Pre-design services b) Architect services c) Architect reimbursables d) Engineer services e) Site surveys f) Building assessments g) Geotechnical/subsurface investigation h) Environmental consultants i) Legal j) Construction inspections, testing k) Historic preservation l) Sound and vibration m) Lighting n) Elevator o) Building commissioning p) Public art q) Other consulting services C) Client Costs a) Client-provided furniture, fixture, equipment b) Moving costs c) Swing space d) Advertisement for bids e) Project management fees f) Project contingency g) Hard cost contingency h) Soft cost contingency

6

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1 REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Project Information PS-0748-A Page 1 5/4/2016 Table of Contents Project Budget Worksheet Program Plan Project Location (Site Plan) Scope of Services

More information

Cost Planning. Project Kaleidoscope Drury University 2003. Larry Gleason CPMI

Cost Planning. Project Kaleidoscope Drury University 2003. Larry Gleason CPMI Cost Planning Project Kaleidoscope Drury University 2003 Larry Gleason CPMI Cost Management Cycle Planning & Preliminary Budgeting Post Construction Pre-Design & Programming Design & Construction Timing

More information

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

ST. MONICA FOOD PANTRY HOUSTON, TEXAS PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,

More information

Capital Project Delivery Handbook

Capital Project Delivery Handbook Capital Project Delivery Handbook Volume One Facilities Planning & Construction 1 FACILITIES PLANNING & CONSTRUCTION 3/8/09 2 FACILITIES PLANNING & CONSTRUCTION 1. WELCOME TO FACILITIES PLANNING & CONSTRUCTION...

More information

Project Budget & Cost Management

Project Budget & Cost Management 1 Project Budget & Cost Management September 15, 2008 Hamid Omidvar, AIA Chief, Office of Planning & Development Department of General Services Montgomery County Maryland 2 Meet the scope defined for the

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

Think Of Us First! When It s Time to Distribute Your Plans

Think Of Us First! When It s Time to Distribute Your Plans Think Of Us First! When It s Time to Distribute Your Plans CONSTRUCTION NOTEBOOK WILL LIST YOUR PLANS AND SPECS FREE CALL TODAY FOR DETAILS 702-876-8660 Why use Experience We have over 60 years of experience

More information

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series Best Practices : Project Phase Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA members without endorsement

More information

Outline. Owner Perspective CM Definition Working Relationships Why CM? Project Approach Pre-construction Construction. Iowa League of Cities // 2011

Outline. Owner Perspective CM Definition Working Relationships Why CM? Project Approach Pre-construction Construction. Iowa League of Cities // 2011 Building the Case for Construction Management Dick Hierstein, IaCMA and Larry Gleason, CPMI Handouts and presentation are available Iowa League of online Cities // 2011 at www.iowaleague.org Outline Owner

More information

GENERAL AND SPECIFIC OBJECTIVES

GENERAL AND SPECIFIC OBJECTIVES GENERAL AND SPECIFIC OBJECTIVES 2015 LICENSING AUTHORITIES WHICH RECOGNIZE THE EXAC ARE: Alberta Association of Architects [ AAA ] Architectural Institute of British Columbia [ AIBC ] Architect s Association

More information

BUY Matrix. Revised 03/18/15. P-Card/Dept. Card (less than $750) Independent Contractor Form. Direct Pay Form. Business and Travel Expense Report

BUY Matrix. Revised 03/18/15. P-Card/Dept. Card (less than $750) Independent Contractor Form. Direct Pay Form. Business and Travel Expense Report 701500 Departmental Operating Pool 701511 Office Supplies except furniture and technology related items 701512 Library Supplies 701513 Instructional Supplies 701514 Laboratory Supplies 701516 Printer Suppliers

More information

Construction Technologies Career Field Pathways and Course Structure

Construction Technologies Career Field Pathways and Course Structure Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry

More information

NORTHERN ARIZONA UNIVERSITY EXHIBIT A SCOPE OF SERVICES FOR DESIGN PROFESSIONAL TO STANDARD FROM AGREEMENT BETWEEN OWNER AND DESIGN PROFESSIONAL

NORTHERN ARIZONA UNIVERSITY EXHIBIT A SCOPE OF SERVICES FOR DESIGN PROFESSIONAL TO STANDARD FROM AGREEMENT BETWEEN OWNER AND DESIGN PROFESSIONAL NORTHERN ARIZONA UNIVERSITY EXHIBIT A SCOPE OF SERVICES FOR DESIGN PROFESSIONAL TO STANDARD FROM AGREEMENT BETWEEN OWNER AND DESIGN PROFESSIONAL (CM@Risk Edition) June 1, 2015 Edition Exhibit A Scope of

More information

CSTM 102 Spring 2013. Construction Documents to Contract Documents

CSTM 102 Spring 2013. Construction Documents to Contract Documents CSTM 102 Spring 2013 Construction Documents to Contract Documents The Construction Industry THE PROJECT TEAM A Project and a Client A Designer Constructors THE GAME PLAN Risk Management Scope of Work The

More information

ISSUE BRIEF. Understanding the Hospital Planning, Design, and Construction Process. Introduction. Background. Phase 1: Project Definition and Planning

ISSUE BRIEF. Understanding the Hospital Planning, Design, and Construction Process. Introduction. Background. Phase 1: Project Definition and Planning Understanding the Hospital Planning, Design, and Construction Process Introduction California s acute care hospitals are an essential health care resource that serve a wide range of patients during times

More information

T109 Architectural Technology MTCU Code 60600 Program Learning Outcomes

T109 Architectural Technology MTCU Code 60600 Program Learning Outcomes T109 Architectural Technology MTCU Code 60600 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes* The graduate has reliably demonstrated the ability to 1. communicate with clients,

More information

REQUEST FOR ARCHITECTURAL SERVICES (RFS)

REQUEST FOR ARCHITECTURAL SERVICES (RFS) REQUEST FOR ARCHITECTURAL SERVICES (RFS) For the Development of three parcels into affordable housing: Highland Ave Site, 9 Manahan Street in Chelmsford and 173 Carlisle Rd. in Westford CHOICE Inc., an

More information

Planning and Construction Management Services

Planning and Construction Management Services Planning and Construction Management Services Construction Project Management Services New construction, major renovations or improvements to building structures and systems are part of the Department's

More information

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal. 2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other

More information

School of Veterinary Medicine Second Floor Student Clinical/Instructional Space

School of Veterinary Medicine Second Floor Student Clinical/Instructional Space REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES School of Veterinary Medicine Second Floor Student Clinical/Instructional Space For Enumeration in the 2015-17 Capital Budget March 2014 Project

More information

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass

More information

2.4 Hardcopy submittals shall be provided at adequate size so that all notes are readable.

2.4 Hardcopy submittals shall be provided at adequate size so that all notes are readable. DESIGN EQUIEMENTS POJECT DELIVEABLES CHECKLISTS GENEAL INFOMATION 1.1 The following is a checklist to be used as a guide for the required deliverables for the Schematic Design phase. 1.2 Schematic Design

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services

More information

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS

NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS NECESSITY OF SCHOOL CONSTRUCTION STAGE III DESIGN REVIEWS Rhode Island Department of Education School Building Authority 255 Westminster Street, Providence, RI 02909 Telephone (401)222-4600 Website: www.ride.ri.gov

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

Contents. 1.0 Introduction 3. 2.0 Project definition 5. 3.0 Project brief 10. 4.0 Accommodation guidelines 15. 1.1 Objective 4

Contents. 1.0 Introduction 3. 2.0 Project definition 5. 3.0 Project brief 10. 4.0 Accommodation guidelines 15. 1.1 Objective 4 Contents 1.0 Introduction 3 1.1 Objective 4 1.2 Competencies and resources required 4 1.3 Scope 4 1.4 Related documents 5 2.0 Project definition 5 2.1 Pre-design studies 7 3.0 Project brief 10 4.0 Accommodation

More information

HAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA

HAMILTON SCHOOL. 1401 Brentwood Parkway, N.E., Washington, DC INITIAL YEAR BUILT 1968 BUILDING AREA INITIAL YEAR BUILT 1968 BUILDING AREA 187,700 SF CURRENT PROGRAM CAPACITY N/A ENROLLMENT 2008 129 WARD 5 PROPOSED PROGRAM CAPACITY N/A Site Plan HAMILTON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

KIEWIT CM/GC Enabling/Utilities

KIEWIT CM/GC Enabling/Utilities South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 john.todd@kiewit.com General

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 8 E. DESIGN

More information

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital

Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital June 21, 2007 The Grossmont Healthcare District (GHD) will accept proposals for Architectural and Engineering

More information

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids

More information

Animal Health Center for Reid Park Zoo, Tucson, Arizona

Animal Health Center for Reid Park Zoo, Tucson, Arizona Reid Park Zoological Society Request for Qualifications Professional Architectural and Engineering Services for Animal Health Center for Reid Park Zoo, Tucson, Arizona SUBMITTAL DUE DATE: March 21, 2014

More information

BOROUGH OF HADDONFIELD CAMDEN COUNTY NEW JERSEY ARCHITECTURAL SERVICES RELATED TO THE HADDONFIELD LIBRARY REQUEST FOR PROPOSAL

BOROUGH OF HADDONFIELD CAMDEN COUNTY NEW JERSEY ARCHITECTURAL SERVICES RELATED TO THE HADDONFIELD LIBRARY REQUEST FOR PROPOSAL BOROUGH OF HADDONFIELD CAMDEN COUNTY NEW JERSEY ARCHITECTURAL SERVICES RELATED TO THE HADDONFIELD PUBLIC LIBRARY REQUEST FOR PROPOSAL Project Name: ARCHITECTURAL SERVICES RELATED TO THE HADDONFIELD PUBLIC

More information

Revised Work Scope Dated April 23 rd, 2015

Revised Work Scope Dated April 23 rd, 2015 Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March

More information

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes The graduate has reliably demonstrated the ability to 1. analyze a client's needs

More information

BCN 4612 Estimating II - Semester Course Outline Course Syllabus

BCN 4612 Estimating II - Semester Course Outline Course Syllabus BCN 4612 Estimating II - Semester Course Outline Course Syllabus Prerequisites: BCN 3611, Senior Standing 3 Credits COURSE DESCRIPTION: Analysis of determination of the cost of construction operations

More information

Overview of Land Construction Courses at Kansas State University

Overview of Land Construction Courses at Kansas State University Overview of Land Construction Courses at Kansas State University Developed by Professor Day in the mid 1960 s at KSU, continuing to present time, is a vision of a Land Construction course series that examines

More information

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter.

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. SCHEDULE OF CONSULTANT S SERVICES Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. Project (Insert name and description

More information

Career Path Project Engineer to Project Manager 1

Career Path Project Engineer to Project Manager 1 Career Path Project Engineer to Project Manager 1 The Career Path standards listed below are designed to help a Project Engineer at Samet Corporation understand what skills, knowledge and experience they

More information

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals

More information

Design Development Quality Management Phase Checklist Project Phase Checklist Series

Design Development Quality Management Phase Checklist Project Phase Checklist Series Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA

More information

Architectural and Engineering Basic Services Fee Estimating Guidelines

Architectural and Engineering Basic Services Fee Estimating Guidelines Architectural and Engineering Basic Services Fee Estimating Guidelines Basic Services is the design work customary on a typical project to take an established building program, site, and budget, and then

More information

REQUEST FOR PROPOSAL WAYFINDING AND SIGNAGE CONSULTANT

REQUEST FOR PROPOSAL WAYFINDING AND SIGNAGE CONSULTANT REQUEST FOR PROPOSAL WAYFINDING AND SIGNAGE CONSULTANT Objective 1) The Wayfinding and Signage (W&S) Consultant shall develop a wayfinding and signage solution for the interior of Terminal One (only the

More information

ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015

ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015 ADDENDUM NO. 1 DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015 RECEIPT DATE: March 17, 2015 at 2:30 p.m. OPENING DATE: March 18,

More information

Building and Planning

Building and Planning Description of Services Building and Planning 2012 Danish Association of Consulting Engineers The Danish Association of Consulting Engineers (FRI) and the Danish Association of Architectural Firms (DANSKE

More information

Project Management Manual for Design and Construction Projects. (Revised August 2010)

Project Management Manual for Design and Construction Projects. (Revised August 2010) Project Management Manual for Design and Construction Projects (Revised August 2010) Table of Contents 1. Overview...5 1.1 Introduction... 6 1.2 Design and Construction Process... 7 1.3 Project Delegation

More information

DIABLO VALLEY COLLEGE CATALOG 2015-2016

DIABLO VALLEY COLLEGE CATALOG 2015-2016 CONSTRUCTION CONST Tish Young, Dean Physical Sciences and Engineering Division Physical Sciences Building, Room 263 Possible career opportunities Students completing a certificate in construction are qualified

More information

Industrial Suburban District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations

Industrial Suburban District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations 16.20.110 - Industrial Suburban District ( IS ) Figure REFERENCE Typical Buildings in the IS District Figure REFERENCE Site Plan of a typical development in the IS District Sections: 16.20.110.1 Composition

More information

2012 BIM Guidelines and Standards (Rev. 00) University at Albany

2012 BIM Guidelines and Standards (Rev. 00) University at Albany A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested

More information

Capitalization and Depreciation of Property, Plant, and Equipment

Capitalization and Depreciation of Property, Plant, and Equipment Boston College Office of the Financial Vice President Capitalization and Depreciation of Property, Plant, and Equipment University Policy Overview It is the policy of Boston College (the University) to

More information

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield

More information

SUCF PROJECT COST REPORTING GUIDE

SUCF PROJECT COST REPORTING GUIDE SUCF PROJECT COST REPORTING GUIDE State University Construction Fund 353 Broadway / ALBANY, NY 12246 SUCF 900 / 11 Table of Contents Page A. Preface 1 B. Area Takeoff Methodology 1. General 2 2. Net Assignable

More information

The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs.

The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs. SCHOOL PLANNING/SCHOOL CONSTRUCTION PROGRAMS Effective: August 14, 2014 I. Policy Statement The Board of Education is responsible for providing safe, engaging and supportive educational and work environments

More information

Hard copies should be sent to: The Denver Waldorf School Attn: Lori Pucelik 940 Fillmore St Denver, CO 80206

Hard copies should be sent to: The Denver Waldorf School Attn: Lori Pucelik 940 Fillmore St Denver, CO 80206 April 24, 2013 RE: THE DENVER WALDORF SCHOOL SCHEMATIC DESIGN ARCHITECTURAL SERVICES REQUEST FOR PROPOSAL Dear Contact, Beecher Development Services has been retained by to provide Owners Representation

More information

Guidelines for Determining Architect/Engineer Fees for Public Works Building Projects (effective July 1, 2015)

Guidelines for Determining Architect/Engineer Fees for Public Works Building Projects (effective July 1, 2015) Guidelines for Determining Architect/Engineer Fees for Public Works Building Projects (effective July 1, 2015) When budgeting for state capital projects, the estimated value of the Architectural/Engineering

More information

ADDENDUM NUMBER ONE (1)

ADDENDUM NUMBER ONE (1) Page 1 of 1 MINNESOTA DEPARTMENT OF TRANSPORTATION Office of Maintenance: Building Services Section ADDENDUM NUMBER ONE (1) ADDENDUM DATE: 19 October 2012 Request for Proposals for Designer Selection for

More information

Slavic Village Building Condition Review

Slavic Village Building Condition Review Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities

More information

Submittal Requirements for Development Projects

Submittal Requirements for Development Projects Submittal Requirements for Development Projects 2004 Mission Statement: The Denver Urban Renewal Authority is a full-service redevelopment agency engaged in neighborhood and downtown revitalization, economic

More information

Repair Project for April 7, 2009

Repair Project for April 7, 2009 Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades

More information

Volume II- Project Development Processes

Volume II- Project Development Processes Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required

More information

Post Occupancy Evaluation (POE) Technical Instructions

Post Occupancy Evaluation (POE) Technical Instructions 1.0 Purpose These technical instructions define the typical steps required by HHS personnel in the use of the. The POE consists of a detailed and systematic assessment of a facility that is operational

More information

BUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES

BUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES Department of Health and Human Services, Division of Public Health Occupational and Environmental Epidemiology Branch 1912 Mail Service Center, Raleigh, North Carolina 27699-1912 BUILDING ASSESSMENT QUESTIONNAIRE

More information

DRAPER ELEMENTARY SCHOOL

DRAPER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Design Criteria & Service Goals

Design Criteria & Service Goals 4.1 Design Life of Improvements The design life of a water system component is sometimes referred to as its useful life or service life. The selection of a design life is a matter of judgment based on

More information

APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES

APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES APPENDIX E GUIDELINES FOR PREPARING CAPITAL PROJECT COST ESTIMATES The capital project cost estimate is a tool to assist agencies and institutions in creating a project construction budget. It can also

More information

Appendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria

Appendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria Appendix B 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria 423.25 Public shelter design criteria. 423.25.1 New facilities. New educational facilities for school boards

More information

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone:

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: Choctaw Date Recorded: Permit # RESIDENTIAL - BUILDING Permit APPLICATION Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: YES NO Sec., Township, Range/Subdivision: Acres/Block:

More information

PRINCIPLES OF CONSTRUCTION

PRINCIPLES OF CONSTRUCTION 1 PART PRINCIPLES OF CONSTRUCTION CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5 CHAPTER 6 CHAPTER 7 CHAPTER 8 CHAPTER 9 CHAPTER 10 An Overview of the Building Delivery Process How Buildings Come into

More information

City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For. Construction Management Services for the

City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For. Construction Management Services for the City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For Construction Management Services for the Renovation and Expansion of Portsmouth Middle School INVITATION The City of Portsmouth,

More information

How To Design An Interior Design

How To Design An Interior Design Interior Design Gretchen Addi, Associate AIA, and Jacqueline Lytle, IIDA, Associate AIA Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 Interior design services create

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

Saint Cloud Business Center

Saint Cloud Business Center Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with

More information

Revised July 2001 CAPITALIZATION OF TENANT IMPROVEMENTS

Revised July 2001 CAPITALIZATION OF TENANT IMPROVEMENTS Revised July 2001 CAPITALIZATION OF TENANT IMPROVEMENTS Capitalization of Tenant Improvements 1.0 What is a Tenant Improvement (TI)?... 3 2.0 Capitalization Guidelines... 3 3.0 Approval Levels... 4 4.0

More information

Civil Engineering and Architecture (CEA) Detailed Outline

Civil Engineering and Architecture (CEA) Detailed Outline Civil Engineering and Architecture (CEA) Detailed Outline Unit 1: Overview of Civil Engineering and Architecture (23 days) Lesson 1.1: History of Civil Engineering and Architecture 1. Many features of

More information

Historic Preservation Principles and Approaches

Historic Preservation Principles and Approaches Section 4: Historic Preservation Principles & Approaches four section Historic Preservation Principles and Approaches Before any preservation project is begun, a number of fundamental decisions need to

More information

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES

NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES NATIONAL INSTITUTE OF GOVERNMENT PURCHASING (NIGP) DESIGN AND CONSTRUCTION CODES All searches and notifications on Bid4Michigan are based on National Institute of Government Purchasing (NIGP) codes. It

More information

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS

EXHIBIT A RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF ARCHITECT TABLE OF CONTENTS A. SCOPE OF PROJECT... 1 B. BASIC SERVICES... 1 C. PRE-DESIGN AND START-UP SERVICES... 4 D. SCHEMATIC DESIGN PHASE... 7 E. DESIGN

More information

Application for Tax Abatement for Rehabilitation of Property in a Local Historic District

Application for Tax Abatement for Rehabilitation of Property in a Local Historic District Application for Tax Abatement for Rehabilitation of Property in a Local Historic District Historic Preservation Office Austin, Texas 512-974-2727 Adopted December 2012 To encourage preservation and maintenance

More information

City of Portland Job Code: 30000313. CLASS SPECIFICATION Landscape Architect

City of Portland Job Code: 30000313. CLASS SPECIFICATION Landscape Architect City of Portland Job Code: 30000313 CLASS SPECIFICATION Landscape Architect FLSA Status: Union Representation: Exempt City of Portland Professional Employees Association (COPPEA) GENERAL PURPOSE Under

More information

This request for qualifications seeks the following type of service providers:

This request for qualifications seeks the following type of service providers: ANNOUNCEMENT REQUEST FOR STATEMENT OF QUALIFICATIONS NOTICE SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN AND CONSTRUCTION ARCHITECTURAL SERVICES The San Francisco Unified School District Facilities,

More information

ENGINEERING DEPARTMENT CHANDIGARH ADMINISTRATION NOTICE INVITING EXPRESSION OF INTEREST (EOI)

ENGINEERING DEPARTMENT CHANDIGARH ADMINISTRATION NOTICE INVITING EXPRESSION OF INTEREST (EOI) ENGINEERING DEPARTMENT CHANDIGARH ADMINISTRATION NOTICE INVITING EXPRESSION OF INTEREST (EOI) The online Expression of Interest (EOI) is invited from reputed consulting/ professional firms/urban Designer/Architect/Consortia(Consortium

More information

The following terms should be understood prior to review of the Services Policy:

The following terms should be understood prior to review of the Services Policy: 1.0 BACKGROUND AND PURPOSE The Department of Facilities Management (FM) at the Colorado School of Mines has developed a Services policy to define for the campus community the types of services provided

More information

REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES. The Battery Conservancy

REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES. The Battery Conservancy REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES The Battery Conservancy Issue Date: March 23, 2012 Responses Due: April 20, 2012 Introduction The Battery Conservancy ( TBC ) is a 501(c)(3) not-for-profit

More information

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY HOWARD COUNTY MARYLAND ARCHITECTURAL DESIGN ACADEMY Architectural Design 1 Introduction / Overview of Course This course will introduce the basic principles

More information

OHLONE COMMUNITY COLLEGE BOND MEASURE G

OHLONE COMMUNITY COLLEGE BOND MEASURE G Monthly Report OHLONE COMMUNITY COLLEGE BOND MEASURE G Fremont, California June 2014 TABLE OF CONTENTS 1. Executive Summary 2. Safety Status 3. Schedule Status 4. Design Progress 5. Construction Progress

More information

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage University of Missouri Hospitals and Clinics Structural Repair and Protection of Post-tensioned Parking Garage 1 University of Missouri Project The University of Missouri Health Care Patient and Visitor

More information

Exceptional... Everytime!

Exceptional... Everytime! Oil & Gas Exceptional... Everytime! Oil & Gas Industry With each Team Leader possessing 10 20 Years experience, BAR Engineering not only contributes high level engineering expertise, but also the practical

More information

Suggested Procedures for School Boards

Suggested Procedures for School Boards Suggested Procedures for School Boards The Chronology of a Project: Some of the steps described may not apply to certain types of projects, or might occur concurrently with others. As you confer with the

More information

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community

More information

Certification: Building Plans Examiner. Exam ID: B3

Certification: Building Plans Examiner. Exam ID: B3 Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building

More information

Healthcare 101 Committee Member James E. Sykes, AIA, LEED AP BD+C MorrisSwitzer Environments for Health, LLC JSykes@MorrisSwitzer.

Healthcare 101 Committee Member James E. Sykes, AIA, LEED AP BD+C MorrisSwitzer Environments for Health, LLC JSykes@MorrisSwitzer. Healthcare 101: Master Planning Presenter Eduardo S. Egea, CAAPPR, AIA, NCARB Senior Vice President / Associate Principal Director of Healthcare for the Caribbean and Latin America HKS Architects, Inc.

More information

CITY OF CHICAGO SMALL BUSINESS IMPROVEMENT FUND (SBIF) PROGRAM RULES

CITY OF CHICAGO SMALL BUSINESS IMPROVEMENT FUND (SBIF) PROGRAM RULES CITY OF CHICAGO SMALL BUSINESS IMPROVEMENT FUND (SBIF) PROGRAM RULES The City of Chicago s Small Business Improvement Fund is a Tax Increment Financing (TIF) program, which will reimburse building owners

More information

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system

More information

REQUIREMENTS FOR OBTAINING A THORNBURY TOWNSHIP, DELAWARE COUNTY PERMIT

REQUIREMENTS FOR OBTAINING A THORNBURY TOWNSHIP, DELAWARE COUNTY PERMIT REQUIREMENTS FOR OBTAINING A THORNBURY TOWNSHIP, DELAWARE COUNTY PERMIT ATTACHED ARE THE REQUIREMENTS FOR OBTAINING A BUILDING PERMIT INCOMPLETE SUBMISSIONS WILL BE RETURNED IN THEIR ENTIRETY -- NO EXCEPTIONS!!

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES TO ASSIST WITH AN EDUCATIONAL NEEDS ASSESSMENT OF BEAVER DAM HIGH SCHOOL ~ October 2015 ~ Issuing Agency: Beaver Dam Unified School District Educational

More information

SAMPLE. CONTRACT FOR PROFESSIONAL SERVICES: Lump Sum by Phase. Federal Identification (I.D.) Number

SAMPLE. CONTRACT FOR PROFESSIONAL SERVICES: Lump Sum by Phase. Federal Identification (I.D.) Number Lump Sum A/E R 12/16/13 STATE OF MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET This contract authorizes the professional services contractor to provide professional services. (Authority: 1984

More information

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

D Sample Notices to Property Owners, Sample Affidavits, and Other Material D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully

More information

Request for Qualifications 2015-162

Request for Qualifications 2015-162 Kitsap County Human Services Department Request for Qualifications 2015-162 Architectural and Project Management Services - Kitsap County Work Release Facility Remodel Response Deadline: November 17, 2015

More information

MOBILE HOME LAW. Revised November 2001

MOBILE HOME LAW. Revised November 2001 MOBILE HOME LAW Revised November 2001 TABLE OF CONTENTS: SECTION 1: SECTION 2: SECTION 3: SECTION 4: SECTION 5: SECTION 6: SECTION 7: SECTION 8: SECTION 9: SECTION 10: SECTION 11: SECTION 12: INTENT DEFINITIONS

More information