BRIDGEWATER COLLEGE HERITAGE HALL RENOVATIONS

Size: px
Start display at page:

Download "BRIDGEWATER COLLEGE HERITAGE HALL RENOVATIONS 12057.00"

Transcription

1 SECTION COMMUNICATIONS HORIZONTAL CABLING PART 1 - GENERAL 1.1 OVERVIEW A. This section provides the necessary guidelines to install service entrance cables to buildings and information for the termination of cables entering buildings. B. The design for all outside plant voice, data, video cabling, communication conduits and manholes, shall be approved by the BC IT Center prior to installation. 1.2 ENTRANCE CABLE 1. Should the project require the installation of new voice, data or video cabling into existing communication conduit approval should be obtained from the BC IT Center. 2. The BC IT Center or its designee will make all connections between voice, data and video entrance cable and inside wiring. 3. In most cases, entrance cabling is to be installed in a continuous run between buildings leaving no splice cases in communication manholes, tunnels or duct systems. Should splicing be required prior approval must be obtained from the BC IT Center and all trunk cables requiring splicing will be performed in accordance with current industry standards. 4. Beyond the voltage that is on the video entrance cable there shall be no cable or wiring with voltages higher than 90 volts AC in communications duct banks. 5. All twisted pair cables entering a building shall be terminated on protection blocks. Only gas and/or solid state protectors shall be used. See protection specifications in Section Repair or replacement of damaged cable is the responsibility of the party involved causing the damage. This will be done at no cost to the College. The BC IT Center must inspect and approve all repairs to damaged cables. All damages shall be reported immediately to the BC IT Center help desk by calling ( ). B. LABELING 1. All trunk cables installed in BC communication conduits and manholes shall be identified as to the cable type, number of pairs or strands, origination and termination points. The information on the tag shall be in permanent ink encased in a waterproof tag made of plastic or other such material designed to be used in a wet environment. Or, tag may be plastic or aluminum with information stamped or embossed. A tag is required at each end of the cable and at all pull points in between. 2. All abandoned communications cable shall be removed from tunnels, manholes and conduit. If it is not feasible to remove abandoned cable, it shall be clearly tagged as abandoned, with appropriate labeling as described above, and shall be reported to the BC IT Center. C. AERIAL 1. No aerial wiring shall be installed on campus unless approved by the BC IT Center. 1.3 ENTRANCE CONDUIT 1. Conduit sizing and quantities for communications conduits between buildings and manholes shall be determined by BC IT Center. Minimum requirements are outlined in the following paragraphs. 2. All campus buildings shall be connected to the nearest manhole/communications conduit duct bank or new manhole/conduit duct bank. Connection to a manhole is detailed in section Fireproof seals shall be required by code as detailed in Section 7. COMMUNICATIONS HORIZONTAL CABLING

2 3. Prior approval and coordination with BC IT Center, and other concerned parties is necessary when the situation requires any modification to the conduit system. 4. Repair or replacement of damaged conduit is the responsibility of the party involved causing the damage and at no cost to the College. The BC IT Center must review and approve all repairs to damaged communications conduits. All damages shall be reported to BC IT Center and Physical Plant immediately. 5. Entrance conduits should be positioned in such a way as to minimize the distance and bends between the new construction and existing communications infrastructure. B. REQUIREMENTS 1. The minimum size for voice, fiber and video cabling for entrance conduit to a new building shall be a minimum of 1 (4) four inch conduit, in new buildings with more than 50 student beds or 25 offices there shall be 2 (4) four inch conduits. 2. No more than the equivalent of 180 degrees of bends is allowed in a run between the building and the manhole, including offsets. C. UNDERGROUND 1. All communications ducts shall also be a minimum of 12 inches from steam pipes and condensation lines when crossing perpendicular. The minimum depth for buried conduit and ducts is 30 inches below grade or underside of road bed to top of duct/conduit. 2. When communication ducts run parallel to steam lines a minimum of a two (2) foot separation is required to avoid conduction of heat. PVC duct is not allowed in steam tunnels. Only under special extenuating circumstances are communication ducts allowed in the steam tunnels and only after permission from the BC IT center and physical plant is obtained. All other duct separations must comply with the National Electric Code. 3. All underground communications conduit shall be four (4) inches in diameter, minimum. 4. All necessary precautions shall be taken by the contractor during construction to prevent the lodging of dirt and construction debris in all conduit, tubing, flow duct, fittings and boxes. All conduit in floors, concrete or below grade, shall be swabbed free of debris and moisture. All newly installed conduits shall be left with a mule tape or pull string. 5. All used and unused conduits shall be sealed to provide a watertight fit inside and out. D. TUNNELS 1. Conduit installed in steam tunnels must have written approval by BC IT Center and reviewed by Physical Plant. Unless written exception is provided by BC IT Center, all conduit placed in and/or sections crossing steam tunnels shall be rigid and galvanized. E. CONDENSATION 1. Duct banks shall be pitched to drain to manholes and away from building entrances. F. TRAPS 1. All conduit, tubing, raceways, ducts and duct banks shall be installed in such manner to insure against collection of trapped condensation. Raceway runs shall be arranged to be void of traps. 2. When conduit passes through exterior concrete walls of any facility, the penetration shall be watertight. Provide pipe sleeves in the concrete with 1/2-inch minimum entrance seal. G. TYPES OF CONDUIT 1. Schedule 40 PVC conduit should be used in all installations requiring underground installation with the exception of when special permission is given to run communication conduit through an existing steam tunnel. Gas pipe and water pipes shall not be used as conduit under any circumstances. 2. Rigid galvanized steel conduit with threaded fittings shall be used in the event special permission is given to install communication conduit in existing steam tunnels. 3. All conduits must be terminated with bell ends at the manhole, facility or other termination point. 4. A color agent shall be sprinkled on top of the underground communications conduits. The color agent is to comply with industry standards. Marker tape shall be placed 12 inches above the communication ducts. COMMUNICATIONS HORIZONTAL CABLING

3 1.4 MANHOLES 1. Manholes shall not be smaller than 7 feet wide, 7 feet long and 7 feet high. 2. The maximum depth of all manholes shall be ten (10) feet from the manhole cover to bottom of the manhole, unless otherwise approved by BC IT Center. 3. The manhole cover and opening shall be round, 36 inches in diameter and shall be engraved or embossed with the word "Communications." Manhole covers shall not have recessed handles that pull out when needed for removal. Notched type covers shall be used. 4. The maximum distance between manholes in any continuous one run shall not exceed 400 feet. B. INTERIOR 1. All materials used in a manhole shall be resistant to corrosion. All steel shall be galvanized or zinc coated. All racks in manholes shall be galvanized or zinc coated steel. 1.5 EXISTING CONDUITS, MANHOLES AND PULL BOXES 1. The location of existing communication conduits, manholes and pull boxes can be obtained by contacting the BC IT Center. All entrance conduits should be positioned such that they take the shortest logical path from the building to an existing manhole or pull box location. PART 2 - TELECOMMUNICATIONS ROOMS AND CABLE TERMINATION 2.1 GENERAL A. Telecommunication rooms are special-purpose rooms that contain telecommunications equipment and wiring. These rooms have specific requirements due to the nature, size and complexity of the equipment and wiring located in the room. 2.2 REQUIREMENTS 1. All MTR and TER doors will be keyed to the existing BC IT Center data closet key. 2. Locks shall be spring lock (self-locking or store room type locks) and BC Physical Plant will install locks. Only authorized IT technicians and Physical Plant supervisors may carry a key to these rooms. 3. Doorways shall be designed with minimum measurements of 3-0" by 6-8" minimum and shall open outward into the corridor or adjacent space. 4. Floors shall be sealed concrete or tile, carpet is prohibited. 5. MTRs and TERs shall be located above any threat of flooding. Rooms located in basements shall have floor drains with positive drainage, otherwise sump pumps must be provided. When sump pumps are required, they shall be connected to an emergency power supply. 6. Fire rated plywood, 3/4 inch thick, must be mechanically fastened to the walls specified in the project specifications of each MTR and TER. The fire rated plywood must be fastened in a way that is easily removable. The fire rated plywood is to begin at 1 foot AFF (above finished floor) and end at 6 AFF. 7. The recommended ceiling height is minimum Install a minimum of 2 (four) 4 inch sleeves between telecommunications rooms, with sleeves extended 4 (four) inches AFF. B. SPACE REQUIREMENTS 1. There are two different types of telecommunications rooms within a building each supporting critical functions as part of the building voice/data/video wiring and communications systems. In general, each room must be large enough to accommodate the wiring and equipment that will be located within them and reserve space for growth. The two types of rooms are: COMMUNICATIONS HORIZONTAL CABLING

4 2. The Main Telecommunication Room (MTR), sometimes called the Main Distribution Frame (MDF) will be referred to as the MTR throughout this document. There is normally only one MTR per building. This room will contain data switches, routers, telecom, and video distribution electronic equipment. This room will also serve as the primary location for communication cabling to enter the building. 3. The Telecommunications Equipment Room (TER) also sometimes referred to as the Wiring Closet, Intermediate Distribution Frame (IDF), Intermediate Cross-connect (IC), Horizontal Cross-connect or Telecommunications Closet (TC). TER will be used in this document. Depending on the size of the building the MTR may be ample to service the entire building. In the event that the building is too large for a single MTR then secondary TER s should be placed in the building such as to minimize the number of TER s while at the same time keeping the distance between any voice/data communications outlet and the MTR or TER to less than 275 feet. 4. The minimum size for a MTR is 100 square feet. The preferable dimensions for this room are 10 X10. This room will contain telephone equipment, data network equipment, racks, cabinets and other approved networking equipment. BC IT Center shall be contacted for final dimension approval. 5. The minimum size for a TER is 35 square feet and the preferable dimensions for this room are 5 WX7 D. Only in approved cases shall this room be less than 35 square feet. BC IT Center must be contacted for final dimension approval. This room will contain telephone equipment, data network equipment and voice/data wiring. 6. NOTE: Telecommunications rooms may vary in size according to the square footage of the building, number of floors, tenant characteristics and telecommunications services required. Consideration to the future needs of the facility and the end users is a necessity. The BC IT Center will have final approval on room dimensions. 7. Both the MTR and the TER will have sufficient lighting, HVAC, sprinkler and access control. 8. Approved low voltage wiring contractor is to terminate entrance cables in the MTR and horizontal cables from the MTR to each TER. The BC IT Center will be responsible for installing network equipment and making the final connections to the end points from the MTR and TER. 9. All work shall comply with the National Electrical Code, Local Building Codes, current 568 TIA- EIA standards and the BC IT Center Low Voltage Structured Cabling Guidelines and Standards. 10. Electrical panels are strictly prohibited in telecommunications rooms. Services, which are not telecommunications related, shall also be prohibited in these rooms. This includes, but is not limited to, janitorial services and supplies, zone maintenance storage of supplies, tools and equipment, departmental storage of supplies and equipment. Fire alarm and security panels are not permitted in telecommunication rooms. 11. A 50 percent growth factor shall be built in and provided in each riser unless otherwise specified; consequently any cable or conduit work that pertains to telecommunications must be designed and/or approved by BC IT Center. Project specifications will include this growth factor. 12. To facilitate proper installation, routing and placement of cables, wires, premise equipment and terminal fields, telecommunications rooms shall be located as close as possible to the middle of the building and stacked one above the other, unless otherwise instructed or approved by the BC IT Center. Architects and Engineers must pay special attention to telecommunication room locations to overcome distance limitations relating to data networks. The total distance of the conduit path, from outlet to the TER or MTR, when the MTR also serves as a TER, shall not exceed 275 feet (this allows for patch cables at the outlet and in the MTR/TER). In buildings taller than 2 stories where possible the TER that services the top two floors should be located on the second floor and the MTR/TER that services the bottom two floors shall be located on the 1 st floor (above ground). 13. Every network-attached device must be cabled back to the nearest TER or MTR. The telecommunication room(s) shall house all and only the equipment directly related to the telecommunications systems. C. ENVIRONMENT 1. All telecommunications rooms shall be environmentally controlled to maintain the room environment at a temperature range of 65 to 75 degrees Fahrenheit, with a relative humidity level of 35 to 75 percent non-conducting, 24 hours a day, 7 days a week. Telecommunications rooms shall be conditioned with a fresh air exchange of three (3) air changes per hour. If HVAC must be shut down then COMMUNICATIONS HORIZONTAL CABLING

5 an exhaust connected to emergency power must be provided to remove heat. Generally the system must remove 7,000 BTU per hour. 2. No plumbing, HVAC ducts, or electrical conduit shall pass through or be directly above any telecommunications room. D. ELECTRICAL 1. Lighting shall be 1 (4) foot fluorescent type and provide a minimum of 50 FC at 3 feet above the floor and be connected to the emergency generator when available. 2. A minimum of 2 double duplex AC outlets must be provided to power telephone system components, computer interfaces, network electronics and other telecommunications requirements. Outlets should be within 1 of the floor rack. 3. Each double duplex outlet shall be connected to a dedicated circuit breaker. Each dedicated electrical circuit shall be 20-amp, 110V, 60 HZ type. All circuits must be tied to an emergency generator when available. All outlets shall be labeled with panel and circuit location. 4. All breaker panels are to be labeled and identified to avoid being turned off in error. Breakers servicing the MTR or TER shall be equipped with locking devices to prevent turn off. A minimum of amp circuits are to feed each room. E. GROUNDING 1. All MTRs and TERs shall have a grounding bar, which shall be 1 foot long for the TER and 2 feet long for the MTR. Both shall be 4 inches wide by 1/4 inch thick with pre drilled NEMA bolthole sizing and spacing. This bar shall be attached to the main building grounding system with a wire not smaller than #6 AWG copper. The ground wire shall not share the cable tray with communications cabling. It may be installed in a separate conduit, which may be attached to the outside of the communications cabling cable tray. 2. Each distribution point shall be grounded to the main building ground, NEC and EIA/TIA 607 requirement shall be followed. F. LABELING 1. Communications, computer and CATV conduit is to be clearly identified, at every junction box, via a painted section or by use of conduit stickers indicating each conduit run. 2. All Telecommunication Equipment Room Frames, Main Cross-connect Frames and connecting blocks must be properly identified by destination. 3. All riser cables shall be properly marked with from and to indicators. Marker is to be a flat piece of aluminum or wire tied plastic labels. This marking shall be permanent and indicate: 4. The Origination (Cable it is feeding from MTR #) to 5. The Destination (TER# it is feeding). 6. All pairs of the entrance cable must be terminated on a connecting block and identified. 2.3 CABLE 1. A 50 percent growth factor shall be built in for riser cable and provided for unless otherwise specified; consequently any cable work that pertains to telecommunications must be designed and/or approved by BC IT Center. Project specifications will include this growth factor. 2. All riser cables that extend from the MTR to each TER must be 100 percent terminated in the MTR and in each TER. 3. Plenum or PVC communications cable may be run exposed above ceilings, provided this cabling is supported independently of other utilities, such as conduits, pipes, ceiling support systems, and not laid directly on the ceiling panels. PVC jacketed cable may be used in non-plenum areas if such use meets NFPA and NEC standards and local fire codes. 4. To facilitate future cable installations, a new pull string, tied off at both ends, shall be installed in conduit simultaneously with the pull-in of cable. 5. All installed station communication cables for voice and data shall be 4 pair, 24 AWG UTP, Category 6 (Enhanced), tested to 250 megahertz. COMMUNICATIONS HORIZONTAL CABLING

6 B. VOICE RISER CABLE 1. Voice riser cable shall be copper, 24 AWG UTP, category 3. All station and riser cable shall be run through and held in place with D-Rings and/or by use of wire tray in MTRs and TERs. Terminate on 66 type connecting blocks. These blocks should be mounted at 5 AFF and no lower than 3 AFF. Voice cables should be located on the back wall of the MTR TER directly opposite the entrance door. The MTR should be mounted to the left with 6 clearance from the adjourning wall. The riser cables should be mounted no less than 6 to the right of the last entrance cable and no more than 12 to the right. The 66 blocks should start 5 AFF and be no lower than 3 AFF. Riser cables should be terminated on the far left and far right terminals. This will facilitate station wire being used on the left and right inside terminals for interconnects. C. VOICE ENTRANCE CABLE 1. In some instances the BC IT Center may elect to not install voice entrance cables. It will be made known if this is the case on a project by project basis. In the event voice entrance cable is utilized it should be copper 24 AWG UTP, Cat 3 burial rated cable. Prior to construction the size of the cable will be provided and will depend on the scope of the project. Cable sizes will be between 25 pair and 250 pair depending on the project. In the MTR entrance voice cable should be terminated on 25 pair lighting protection 66 blocks similar to Emerson Network Power model R66P25 and properly grounded. Additional specifications on grounding can be found in Section These blocks should be mounted at 5 AFF and no lower than 3 AFF. Voice terminations should be located on the back wall of the MTR/TER directly opposite the entrance door. The voice entrance cables should be mounted on the left side of the back wall with 6 clearance from the adjourning wall. The BC IT Center will provide a count for the number of analog and digital protection modules that will need to be provided for use in the protection blocks. D. DATA RISER CABLE 1. All data riser cable will be optical fiber cable, of multi-mode and single-mode strands. See section E. FIBER OPTIC RISER 1. Fiber optic riser cable shall consist of a minimum of 1 sub-unit of 6 strands of multi-mode fiber and 1 sub-unit of 6 strands of single-mode fiber in a single sheath. Multimode fiber should be 62.5 micron unless otherwise specified by BC IT Center. 2. Termination in the MTR and TER shall be in standard fiber optic enclosures. All fiber strands are to be terminated on ST type connectors. F. FIBER OPTIC ENTRANCE CABLE 1. Fiber optic entrance cable shall consist of a minimum of 12 strands of multi-mode fiber and 12 strands of single mode fiber in a single sheath. Termination in the MTR shall be in standard fiber optic enclosures. All fiber strands are to be terminated on ST type connectors. 2. Multimode fiber should be 62.5 micron unless otherwise specified by BC IT Center. G. VIDEO RISER CABLE 1. A single conductor.500 rigid aluminum cable (hard-line) is to be installed between the MTR and each TER. The coax cable should be loosely coiled on and secured with wire guides to the right wall as you enter the MTR/TER. The cable should be placed no less than 6 and no more than 12 from the corner of the right wall and the back wall which is used for voice cabling. The BC IT Center will contact our video services provider to terminate the riser. H. VIDEO ENTRANCE CABLE 1. Single conductor.500 coax cable is to be installed into the MTR. The BC IT Center will coordinate prior to construction as to the existing wiring infrastructure that the coax cable will originate from to obtain footage information. The BC IT Center will coordinate with our video services provider to terminate the entrance cable. The entrance cable should be loosely coiled and secured with wire guides to the right side wall of the MTR no less than 6 and no more than 12 from the corner of the right wall and the back wall. COMMUNICATIONS HORIZONTAL CABLING

7 2.4 RACKS AND PANELS 1. Each distribution point on the MTR or TER backboard or rack shall be identified as a building entrance and/or a floor service panel. Junction/pull boxes are to be provided on any conduit run longer than 80 feet. 2. All voice terminations at the MTR will be on 66 type-connecting blocks, mounted on relay rack or backboards. All data terminations at the TER will be terminated on CAT 6 RJ45 jacks and inserted into a modular rack mount patch panel. Where space permits, Floor racks should be installed in the MTR and the TER and all fiber and data terminations should be installed on the racks. These racks should be secured to the floor with bolts. 2.5 WIRE DRESS A. ANALOG VOICE STATION WIRES 1. Drop from the telecommunication cable tray, bundle and route the unshielded voice pair groups through the backside of the 66 block mounting bracket. Organize and label the cables in sequentially numbered order. The labels are to be placed on the small tab to the left side of the 66 block. 2. Individual end station cables should be terminated on 66 blocks to the right of the riser cables no less than 6 from the last riser cable 66 block and no more than 12 away. These blocks should be placed no more than 5 AFF and no lower than 3 AFF. Cables should be connected to the far left and far right terminals such that the interior left and right terminals can be used for making interconnects with station wire. If multiple rows of 66 blocks are to be used allow 4 clearance between the rows. 3. Wire hooks are to be mounted between 5 4 and 5 6 AFF above all the voice terminations. These include the entrance cable, riser cables and station cables. B. DATA STATION WIRES 1. Drop from telecommunications room cable tray, bundle and route through a vertical wire management duct attached to the side of the rack. Organize and label the cables in sequentially numbered order. The labels are to be placed on the modular jack panel in the designation space for each jack. 2. A single sided 1.5-inch horizontal wire management duct is to be mounted above and below each modular jack panel. C. VIDEO STATION WIRES 1. Drop from the video cable tray, bundle and route the RG6 coax in a bundle and then split them into segments of 8. Create as many segments of 8 as needed. On the wall designated for video station wires map out and secure 8 way splitters in such a horizontal row. Each 8 way splitter will be feed from a master splitter which is to be feed directly from the entrance cable or the video riser cable. If more than 8 splitters are needed for the station wires it is acceptable to split the entrance cable or video riser cable once to create two master splitters. All splitters are to be grounded reference section 5 for additional details. Organize and label the cables in sequentially numbered order. The labels are to be clearly written on the RG6 cable or a small plastic or metal tag is to be secured to the cable with cable label clearly printed or embossed. 2. Compression RG6 F-Type ends should be installed on the video station cables. 2.6 DATA RACK AND PATCH PANEL A. To install network distribution panels and associated equipment use the following installation method. 1. In TERs and MTRs serving as TERs containing data terminations, mount one (1) 2post freestanding relay racks in the indicated location. Position the racks to maintain a minimum of three (3) feet clearance from the front of the rack to the front facing room wall and three (3) feet clearance from the rear of the rack to the rear facing room wall. If a row of racks is to be installed in a MTR or TER, maintain a minimum of two (2) foot clearance from the rightmost or leftmost rack to the opposing wall. Anchor racks to the finished floor. Ground the rack to the MTR or TER grounding bus bar with #6 AWG copper wire. COMMUNICATIONS HORIZONTAL CABLING

8 2. When data jacks for multiple floors are serviced out of the same TER or MTR serving as a TER, the modular jack panels shall be laid out and labeled as follows. 3. One or more 24 or 48 port horizontal modular jack panels will be dedicated to each floor. Only under specially approved circumstances shall more than one floor share a 48-port panel section. Panels will be installed with the top floor at the top of the rack and then in descending order by floor. 4. If multiple 48 port modular jack panels are utilized a free space of 4 U will be left between them to provide space for network equipment. 5. Additional racks may be required to satisfy this layout. If so, the top floor will be located in the left rack starting again from the top of the rack and then in descending order. 6. Panel labels shall match the jack labels as described in Section Each 48-port panel section shall be labeled with the floor code letter. B. PUNCH DOWN ON SURFACE MOUNTED BACKBOARDS 1. Lay down all station wire pairs in serially numbered order from lowest serial number at the top left most position to the highest serial number at the bottom right position. Use 66 type connecting blocks. Route all cables to be punched down to these blocks starting on the left most edge down to the base of the backboard then over and up to the block dressing the cable under the mounting legs. Fasten the mounting brackets to the plywood backboard with #10 x 3/4 inch Phillips head screws. 2. ANALOG VOICE 4-Pair -- Use 66 type blocks. Locate the punch blocks on the plywood wiring surface in the area designated as Voice Station Wires. Punch down the four (4) unshielded pairs on the block. Minimum bend radius must meet the cable manufacturer s specifications for category 6 wiring. 3. DATA 4-Pair -- Use rack mounted modular jack patch panels. Punch down the four (4) unshielded pairs on the yellow RJ45 jack, use Orange for WAP locations. PART 3 - COMMUNICATION OUTLETS--INSIDE PLANT WIRING AND RACEWAYS 3.1 GENERAL A. OVERVIEW 1. All telephone, data, and CATV station cabling shall be continuous cabling from the MTR or the TER to the communication outlet. All station cables will be free of kinks, chafes, and tight bends. Any ceiling tiles removed by the contractor for cable installation will be re-installed in good condition. Replacement of damaged tiles is the contractor s responsibility at no cost to the College. 2. The standard jack layout used by the BC IT Center is two Cat-6 RJ-45 jacks terminated for data, 1 Cat-6 RJ-45 jack terminated for voice and 1 RG6 threaded F-type coax jack. The standard faceplate will be four port single gang stainless steel. 3. All voice connections shall terminate on beige RJ-45 eight (8) conductor CAT 6 modular jack assemblies. The voice jack will be placed in the bottom left the wall plate. Wire color-coding and termination shall be per EIA/TIA-568-B.2 specifications. All data connections shall terminate on yellow RJ-45 eight (8) conductor CAT 6 modular jack assemblies. The data jacks will be placed in the upper left and right ports of the wall plate. Wire color-coding and termination shall be per EIA/TIA- 568-B.2 specifications. All video connections shall terminate on beige F-type threaded coax jack. The video jack will be placed in the bottom right of the wall plate. 4. All pairs shall be terminated when connecting to voice and data jacks. Terminate as 568B. 5. The total wire path length from the data outlet to the MTR or TER termination point must not exceed 275 feet. This is important to meet Ethernet requirements of IEEE Please note that in most cases the TER that houses network electronics will service both the voice and data jacks on the floor where it is located. This must be considered when determining adherence to the maximum length for the data outlet wiring. 6. Analog wall phones shall be terminated on stainless steel wall phone jack. B. LABELING 1. Each end of all cables will be labeled at their termination locations. 2. In newly constructed buildings communications outlets will be labeled based on their position in the MTR or TER. The following labeling format should be utilized. Where possible jacks should be la- COMMUNICATIONS HORIZONTAL CABLING

9 beled in such a fashion that the jacks to the left of the entrance door begin at the next available lowest number and as you work your way around the room clock wise the jacks increment up. Labels are to be placed under clear plastic inserts. Note: Special labeling considerations for student housing outlined in 3G. C. VOICE CONNECTIONS 1. For voice connections the jacks will be prefixed with a T and a typical voice jack would be labeled liked T-XX where XX is a number that starts with In the event that there is more than 100 phone lines in a MTR or TER three digits is permitted as long as lower numbers are padded with 0 s. (IE T-001 as an example) D. DATA CONNECTIONS 1. For data connections the jacks will be prefixed with a C and a typical data jack would be labeled like C-Y-XX where Y represents the particular modular patch panel in the MTR or TER that the jack is located. These patch panels will be labeled starting at the top of the rack and working their way down. If multiple racks are used the numbering will continue to the second rack at the top working their way down. The XX then represents the port on the denoted patch panel (01-48). An example of a typical data jack labels would be C-1-24 where this is in the first patch panel in the MTR or TER and jack 24 on that patch panel. E. VIDEO CONNECTIONS 1. For video connections the jacks will be prefixed with a V and a typical video jack would be labeled like V-XX where XX is a number that starts with In the event that there is more than 100 coax cables in a MTR or TER three digits is permitted as long as lower numbers are padded with 0 s. (IE V-001 as an example) F. MULTIPLE MTR AND TER S 1. In the event that there are multiple TER s servicing a floor the following labeling shall be utilized. Prior to labeling the MTR and TER s will be numbered. The number for the particular MTR or TER will then be added to the connection labels as follows. 2. Voice connections when multiple MTR and TER s are used servicing the same floor. T-Z-XX where Z represents the number assigned to the MTR or TER that services this location. For Data connections labels will appear like C-Z-Y-XX again where Z represents the MTR or TER servicing this location and for video connections labels should appear as V-Z-XX where Z represents the MTR and TER servicing this location. G. STUDENT HOUSING LABLING REQUIREMENTS 1. For projects that relate to student housing rather than end point labeling the BC IT Center prefers to have labeling done in the MTR and TER. This will limit the need for BC IT center staff to enter into a student s room to activate or deactivate service. 2. In rooms where voice lines are installed the room number is to be noted on the small tab to the left of the blue, blue/white pair of the 66 block for the end station going to that room. Where possible the voice lines should be terminated in the 66 block so the room numbers increase as they work their way down the left and then right side of the 66 block. 3. For data connections in the room the modular jack patch panel in the MTR and TER s shall be labeled with the room number and in rooms where there are multiple jacks the individual jacks should be denoted with A and B, etc. where jack A is the upper left jack on the face plate in the room and B is the upper right jack. In rooms where there are three or more jacks continue the lettering on the second row with C and D, etc. 4. For video connections mark on the cable clearly or use a plastic or metal tag secured around the cable with the room number clearly printed or embossed. Where possible the video cables should be terminated into the splitters in such a way that the room number increase as the cables work their way left to right. COMMUNICATIONS HORIZONTAL CABLING

10 3.2 COMMUNICATION OUTLET LOCATION A. LOCATIONS AND QUANTITIES GUIDELINES 1. Unless otherwise specified, a Standard Communications Outlet (SCO) shall consist of a voice jack, two (2) data jack, and a video jack. Other communication outlets may be installed depending on the function for that particular office or room. Quantities listed for the following areas are minimum counts. 2. Faculty and Staff Offices: For offices 10 X10 or smaller one (1) SCOs per office. This should go on one of the two walls perpendicular to the office doorway. For offices larger than 10 X10 then two (2) SCO s to be located on opposite walls perpendicular to the office door. 3. Conference Rooms/Meeting Spaces: Two (2) SCO per room on opposite walls and perpendicular to the entrance of the room. Rooms larger than 200 square feet there should be one (1) SCO per wall. Rooms with more than 500 square feet shall have additional outlets equally spaced on each wall. 4. Classrooms/Lecture Halls/Auditoriums: These spaces will hold the same jack requirements as conference rooms/meeting spaces with the addition of an additional SCO to be located at the predetermined instructor station location. In addition an additional single gang box is to be roughed in with 1 conduit turned out above finished ceiling for the install of audio/video connections to support projector and speakers. 5. Residence Hall Rooms: One (1) data communication jack per occupant or potential occupant of each room. One (1) voice jack in rooms designated as RA rooms. One (1) video outlet per room. The preferred location is on the same wall as the door. The final location will be determined during the design period of the project. Blanks to be installed in the four port faceplate in the event that the room does not utilize a voice jack. 6. Residence Hall Lounges: One (1) CATV outlet per lounge. The quantity and locations will be determined during the design period of the project. 7. Mechanical Rooms: Consult the Department of Physical Plant. Some rooms may require communications outlets for telephones or energy management devices. 8. WAP locations: Two (2) Cat-6 cables terminated with RJ-45 ends (not jacks) we will directly connect one of these cables into the WAP and the other is to be a spare. The cables should be labeled clearly either in writing on the label or metal or plastic tag affixed to the cable. WAP locations are to be terminated in the MTR and TER s with Orange Cat-6 modular jacks. 3.3 COMMUNICATION OUTLET HOUSING INSTALLATION A. MOUNTING 1. Use a single or double gang outlet box, when mounting the outlet box in a steel studded wall, use a back brace. 2. Use single gang plaster rings and they must be level and positioned flush with the finished surface. 3. Outlets are to be mounted at standard industry heights and positions, unless otherwise specified on the plans. Standard heights for communication outlets: 4. SCO 18 inches, AFF. (above finished floor) (Single gang plaster ring) 5. WAP to be ceiling mounted with a minimum of 12 clearance on all sides from any other ceiling mounted hardware including but not limited to light fixtures, sprinkler heads, smoke detectors, and thermostats. (Double gang box with single gang plaster ring) In the event that a WAP location is to exist in an exposed ceiling the double gang box is to be mounted at a height equal to the lighting in the space. 6. Wall mount phone 48 inches, AFF. (Stainless steel phone wall mount) 7. In most cases power should be adjacent to all SCO locations. 3.4 WIRING PATHWAYS 1. To avoid electromagnetic interference (EMI), all pathways should provide clearance of at least: 2. 4 feet (1.2 m) from motors or transformers 3. 1 foot (0.3 m) from conduit and cables used for electrical power distribution COMMUNICATIONS HORIZONTAL CABLING

11 4. 5 in. (12 cm) from fluorescent lighting or power lines over 2kVA and up to 24 inches from any power line over 5kVA. In general, communications cabling is routed separately or several feet away from power cabling. Similarly, communications cabling is routed away from large motors, generators, induction heaters, arc welders, x-ray equipment, and radio frequency, microwave or radar sources. Whenever possible, pathways should cross perpendicular to fluorescent lighting and electrical power cables or conduits. 5. Preplanning should be done to try to minimize the distance voice, data and video cables are run between the end point and the MTR and TER s. 3.5 CONDUIT 1. All conduit work shall meet the requirements of the National Electrical Code. 2. All voice, data and video wiring inside rooms shall be protected by conduit or other means such as wire mold or troughs in the floor. Aluminum is not acceptable in caustic environments. All conduits are to be concealed whenever possible. 3. No more than an equivalent of two (2) 90-degree bends are allowed in a run between junction boxes or pull boxes. 4. The use of plenum cable instead of conduit shall be determined on a case-by-case basis. BC IT Center must be contacted for approval. 5. In major renovation and new construction projects where the MTR and TER(s) are not in alignment, the contract shall include provisions for installation of two (2) riser conduits (4 inches minimum diameter) from the MTR to each TER. A pull string and appropriate junction pull box shall also be provided in each conduit run to facilitate future installation of cable(s). 6. To reduce EMI, all conduits in slab shall be a minimum of 1 1/4 inches galvanized steel with threaded fittings. All exceptions shall be determined during the design stage of the project and shall be subject to the approval of BC IT Center. 7. All sleeves must protrude four (4) inches AFF and below and be capped at both ends. Coordinate with BC IT Center for the number of conduits entering the facility. 8. No horizontal conduit run shall be more than 80 feet between pull boxes. 9. Conduit for telephone or computer outlets shall be terminated in a dual or single gang box with single gang plastic ring. 10. All communications outlets shall be minimum 1-inch conduit, with a minimum of bends, from the outlet to the cable tray, wire way or homerun directly to the MTR or TER. Home run conduit is required when the cable path above the ceiling is not easily accessible. Examples of ceilings where conduit is required include dry wall and interlocking ceiling tiles. Pull boxes must be installed every 180 degrees or 80 feet of the conduit run. 11. All conduits must extend from the station end to the MTR or TER as a home run or to a cable tray that extends to the MTR or TER. Conduits extending to a cable tray shall be mechanically bonded to the tray. 12. All station run conduits shall have a pull string installed. B. CONDUIT CAPACITY 1. Conduit shall be sized using industry standard guidelines for telecommunications distribution methods. Such guidelines can be found in the Building Industry Consulting Service International (BICSI) Telecommunications Distribution Methods Manual. Capacity is typically a 40% fill rate. 3.6 CABLE TRAYS 1. All communications cable trays shall be designed to accommodate all types of communications cabling; consequently any cable work that pertains to telecommunications must be designed and/or approved for use in the trays by BC IT Center. 2. Communications cable trays shall be made of welded steel wire mesh construction commonly known as basket tray. No use of solid surface construction cable tray is allowed except in penetrations COMMUNICATIONS HORIZONTAL CABLING

12 through firewalls. In these cases the entrance and exit of the tray penetrating the wall shall not exceed 6 inches beyond either side. Removable solid surface top covers on the wire mesh tray are allowed. 3. The minimum dimensions for a communications cable tray shall be 12 inches wide and 4 inches deep. In certain instances where a smaller tray may be required due to space constraints, the BC IT Center shall have final design approval. 4. Contract documents shall show cross section of the communication wire way or cable tray. The drawing must show reference to other installed utilities in the building. 5. All conduits terminating at a cable tray must be easily accessible. Avoid ending conduits at tray in locations that are not accessible by removable ceiling tile or ceiling access panel. No conduit shall extend into the wire way area of the tray. All conduits used for communications cabling are to be bonded to the communications cable tray. 6. Consideration may be given for installation of other types of cables in a cable tray to prevent interference on unshielded cables. BC IT Center shall approve location of such installation. 7. The communications cable tray is to be supported with thread rods in a trapeze form. Supports for cable trays larger than 12 inches in width are to be installed according to the manufacturer s specifications. Supports for cable trays 12 inches or less may be farther apart but must meet the manufacturer s installation requirements. A single support is not acceptable. All supports are to be fastened to the building structure above. 8. BC IT Center or its designee will not install any cable or perform any work until all communications cable tray installations are in compliance with specifications listed above. B. MOUNTING 1. Cable trays must maintain a minimum of six (6) inch clearance from obstructions above the tray and a minimum of eight (8) feet (6) inches AFF to bottom of tray. Trays are to provide access via the most direct path to all communications outlets on the floor. 2. Install sweeping 90s for all turns. Use end-of tray terminations where wire drops down to walls to prevent abrasions and cuts from metal edges. Use a trapeze cable tray mounting method suspended by manufacturer recommended size threaded rods. Fasten threaded rods to ceiling anchors, allowing no bends in rods. Support the cable tray in this manner at every section-to-section junction and at five (5) feet to six (6) feet intervals (mid span) between joints. Whenever possible, the tray should be no closer than six (6) inches from the structural ceiling, ducts or pipes, considering all other possible obstructions. A minimum of 5 inches distance from lighting, especially fluorescent lighting, is required. 3.7 OPEN TOP CABLE SUPPORTS AND RINGS 1. All open top cable supports (J-supports) and cable rings must be suspended from or attached to the structural ceiling or walls with hardware or other installation aids specifically designed to support their weight. When used, J-supports or cable rings shall be located on 24 to 36 inch centers to adequately support and distribute the weight of cables. These types of supports may typically hold up to fifty 0.25-inch diameter cables. 2. For larger quantities of cables that convene at the MTR or TEC, provide cable trays or other special supports that are specifically designed to support the required cable weight and volume. 3.8 UNDERFLOOR DUCT SYSTEM 1. This type of raceway is to be used minimally at all costs. Care must be taken to design a system that will consider electrical and communications requirements. Adequate electricity must be available at all locations. With proper planning, an adequate system can be installed but it is discouraged. PART 4 ACCESS CONTROL DOOR AND CABLING 4.1 OVERVIEW COMMUNICATIONS HORIZONTAL CABLING

13 A. This section provides the necessary guidelines for installing access control equipment that will integrate with the existing CBord access control system. 1. The design for all access control equipment, shall be approved by the BC IT Center prior to installation. 4.2 GENERAL INFORMATION A. The access control system presently in place is provided by CBord. The software presently being used is CSGold 6. Each building with access control is outfitted with a Squadron V1000 controller in the MTR and a Squadron V100 is installed in the MTR for every two doors used to provide card access. The CBord MR-5 readers will be used at all new entrance doors. 1. In instances where there are exit only doors Squadron V200 and V300 panels are installed in the MTR to monitor door contacts and trigger alarm horns as needed. One V200/V300 are needed for every 16 exit doors. 4.3 DOOR SPECIFICATIONS A. ENTRANCE DOORS 1. Any exterior door designated as an access control entrance shall include the following features. A single gang box mounted flush outside the building. This box is to be placed at a height of 40 inches above the bottom of the door frame. The card reader will be mounted to this box. The box can be placed either to the left of the door or right of the door depending on the placement of the door handle and swing of the door. The reader would typically be placed opposite of the door hinges, an exception to this would be double swing doors. If the door is equipped with a handicap door opener the exterior handicap button needs to be placed within easy reach of the card reader. If the card reader is to be placed on an exterior wall that is not protected by an overhang or roof a weather resistance shroud is to be installed on the single gang box housing the card reader. A double gang box mounted six inches above the top of the door frame is to be installed inside the doorway on the same side of the door as the external card reader rough-in. A ¾ metal conduit is to be installed from the exterior single gang box to the interior double gang box. A 1 metal conduit is to be installed from the double gang box to the MTR or TER if the MTR is further than 250 feet. A ½ metal conduit is to be installed running from the double gang box to the electronic locking mechanism of the door. For single door entranceways strike locks mounted in the door frame are preferred. HES and Van Duprin brands of strike locks are preferred. For double door entranceways electrified trim is preferred but if electrified trim is not available magnetic locks are required on both doors. Any doorway using a magnetic lock will additionally include boxes and conduit for a request to exit button and an IR motion sensor. Supplied locks must be able to be powered by either a 12 volt or 24 volt power supply located in the MTR/TER where the corresponding CBord control panel is located. Lock power supplies must include battery backups that will continue to power the lock in the event of loss of building power. Strike locks and electrified trim are to be installed in a normally open fail secure configuration. Magnetic locks are to be installed in a normally closed fail safe configuration. COMMUNICATIONS HORIZONTAL CABLING

14 A magnetic contact is to be installed in the door frame to determine the state of the door. This contact will be wired to the CBord control panel. An audible alarm horn is to be installed on the interior double gang box. This horn will be sounded in the event of a door being propped open. The horn will be triggered by the CBord control panel. When installing conduit in a door frame that will be filled with grout all connections must be sealed to prevent the leakage of grout into the conduit. B. EXIT DOORS 1. Any exterior door designated as an exit only door will include the following access control features. A double gang box mounted six inches above the top of the door frame is to be installed inside the doorway. The box should be placed above the door on the side opposite the door hinges. A 1 metal conduit is to be installed from the double gang box to the MTR or TER if the MTR is further than 250 feet. A magnetic contact is to be installed in the door frame to determine the state of the door. This contact will be wired to the CBord control panel. An audible alarm horn is to be installed on the interior double gang box. This horn will be sounded in the event of a door being propped open. The horn will be triggered by the CBord control panel. C. CABLING BETWEEN DOOR AND MTR/TER 1. A composite plenum rated access control cable is to be installed between the interior double gang box and the MTR or TER where the connection is terminated into a CBord control panel. The composite cable is to be comprised of twelve 22 AWG conductors and four 18 AWG conductors. The conductors are to be split into subunits as follows: Four 18 AWG conductors designated for lock power Two 22 AWG conductors designated for door contact Three pairs of 22 AWG conductors designated for card reader Four 22 AWG conductors designated for REX (request to exit)/spare use 2. When installed the composite cable at the doorway enough cables needs to be pulled to reach the exterior card reader without splices. A service loop of 10 feet of cable is to be coiled and secured in the MTR/TER. 4.4 CONTROL PANEL INSTALLATION A. Each MTR or TER that is used to service an entrance or exit doorway must have the following control panels installed. (This equipment as well as the card readers will be provided by the BC IT Center) The BC IT Center or its designee shall make the final connections with respect to the CBord controllers/readers and the installed lock and wiring. A CBord Squadron V1000 controller to control any subpanel located in that MTR/TER. A CBord Squadron V100 controller for every two entrance doors. A CBord Squadron V200 controller for every sixteen exit only door contacts. A CBord Squadron V300 controller for every sixteen exit only alarm horns. 1. The CBord control panels are to be installed on the left wall as you enter the MTR/TER. If fewer than four total panels are to be installed in any given MTR/TER they can be installed directly on the plywood. If more than four total panels are to be installed an appropriately sized enclosure is to be installed. If an enclosure is installed it must be sized to included room for growth of 25%. 2. CBord control panels are to be installed at 54 inches AFF. Power supplies servicing the CBord control panels are to be installed at 36 inches AFF. Power supplies must conform to CBord standards and include batteries that will take over in the event of loss of building power. COMMUNICATIONS HORIZONTAL CABLING

15 PART 5 - PROTECTION, GROUNDING AND BONDING 5.1 LIGHTNING PROTECTION 1. Lightning protection of telecommunications facilities is essential. While federal and state standards must be adhered to, local conditions may require additional investigation and/or modifications to meet site, equipment, environmental or safety requirements. 2. NEC Articles 250 "Grounding" and 800 "Communications Circuits" cover general requirements for grounding, bonding and protecting electrical and communications circuits. NFPA 78 "Lightning Protection" addresses zone protection and other items that are beneficial. 3. All cabling (including grounding to building ground) within the building and entrance facilities shall be installed with protection from lightning and power surges via grounding and bonding. B. MATERIALS 1. The most frequently used lightning protectors on campus for voice lines are listed below. Consult BC IT Center should you wish to make any substitution to the below. 2. Emerson Protection Block -- part number R66P25QCVS. 3. The gas protection module shall be AT&T, 5 pin black for analog phone and red for digital lines. The count of analog to digital shall be provided by the BC IT Center upon request. 5.2 GROUNDING 1. All MTR grounding shall use a single point scheme from the building main transformer. EIA/TIA 607 requirements must be followed. 2. All shields shall be bonded to a common ground. 3. All entrance cables must be properly grounded to the building ground through grounding facilities provided at the MTR. 4. All protector blocks shall be connected to the backboard ground busbar using NEC code 6 AWG copper wire. 5.3 BONDING 1. Bonding is to be durable, strong and of low impedance to assure electrical continuity. EIA/TIA 607 requirements must be followed. 2. All conduits terminating to cable trays and wireways shall be mechanically fastened to the tray clamps or equivalent. The cable tray or wire way shall be grounded to the main building grounding system with a wire not smaller than #6 AWG copper. 3. A resistance of.001 ohm or less indicates a high-quality junction and is required per the Building Industry Consulting Services International (BICSI) Telecommunications Distribution Methods Manual. PART 6 - INSPECTION, TESTING AND DOCUMENTATION 6.1 INSPECTION OF WORK 1. BC IT Center or its designees shall have access to construction sites. 2. To enable BC IT Center to inspect telecommunications facilities work, the contractor must: 3. Provide a progress schedule with the installation of telephone raceways and spaces shown as a separate item. 4. Immediately notify BC IT Center of any change in architectural drawings and/or plans affecting telecommunications and provide as-builts. COMMUNICATIONS HORIZONTAL CABLING

16 5. Provide proper access to facilities for inspections. 6. Notify BC IT Center when any work is ready for inspection. 7. All underground work must be inspected and approved by BC IT Center and/or Physical Plant before the site is covered with dirt or concrete. Failure to have the work inspected shall result in uncovering the area at the contractor' expense. 8. Per contract documents, the contractor shall provide a final checkout certification letter and inspection reports to BC IT Center on all telecommunications work. 6.2 TESTING 1. Testing shall conform to ANSI/TIA/EIA-568-B.1-B.2 and B.3 standards. Where as ANSI/TIA/EIA- 568-B.1 addresses cabling system requirements, ANSI/TIA/EIA-568-B.2 addresses copper components and ANSI/TIA/EIA-568-B.3 addresses fiber components. 2. The contractor shall submit to BC IT Center, a detailed test procedure to be used for the project. All cables shall be tested for length, attenuation, impedance, grounds, shorts, reversals, and continuity of communications conductors and shields. 3. Upon completion, test results shall be submitted in digital form to BC IT Center for final approval and acceptance. The contractor shall guarantee 100 percent continuity on all fiber and copper conductors on all cables. 4. Failure during testing and warranty period will result in re-pulling and terminating cables at the contractor expense. B. STATION CABLES 1. The total cable length from the communications outlet to the telecommunications room must not exceed 275 feet in any case. 6.3 DOCUMENTATION STANDARDS A. CONTRACTOR DOCUMENTATION REQUIREMENTS 1. Upon project completion, the installing contractor shall provide to the BC IT Center a list of voice communication outlet identification labels, data communication outlet identification labels, their corresponding room numbers, location within the room, and punch block or data panel termination points. Voice and data communication outlet identification labels at the jack locations, shall also be placed on the as-built drawings and provided to ITCS. 2. OTDR and/or power meter test results to manufacturer s specifications and UofL standards for all fiber optic cable installed. The documentation must include OTDR or power meter readings, fiber route diagrams, length, and end-to-end attenuation results for multimode and singlemode fiber cable. All fiber OTDR or power meter readings shall be made bi-directionally on all fiber cable. Test results shall be provided in digital form. 3. Station cable tests shall be performed to manufacturer s specifications and UofL standards. Test results shall be provided in digital form. 4. Riser cable tests shall be performed to manufacturer s specifications and UofL standards. Trunk cable tests shall be performed to manufacturer s specifications and UofL standards. Test results shall be provided in digital form. PART 7 - FIRE STOPPING 7.1 GENERAL A. Provide fireproof seals in accordance with the National Fire Protection Association (NFPA) and the National Electric Code (NEC), Article and EIA/TIA 569 Standards. B. Fire stop all penetrations in accordance with the current edition of the National Fire Protection Association (NFPA). COMMUNICATIONS HORIZONTAL CABLING

17 C. Do not use concrete for fire stopping on cable trays, wireways or conduit. Contractors who use this method will be required to replace and test all cables adversely affected. PART 8 LOW VOLTAGE STRUCTURED CABLE TECHNOLOGY 8.1 OVERVIEW A. Cabling technology at the College is comprised in three mediums; fiber optic, UTP and coaxial. All cabling used for horizontal installations shall be rated for use in a plenum type ceiling. Cabling for use in building risers should be rated as specified for the application. B. GENERAL 1. BC IT Center shall approve all low voltage structured cable planning, installation and specifications. The BC IT Center or its designee will make all the final interconnects to join new construction into our existing communications network. 8.2 FIBER OPTIC CABLE 1. Multi-mode and single-mode fibers are both utilized at the College. In all cases of multi-mode-fiber installation, 62.5/125MM will be used. 2. Direct burial of fiber optic cable is not allowed. 3. When installing fiber optic cable in ductwork and manholes between buildings, there shall be a minimum of one complete loop; minimum of 30 feet in length, in the manhole and it shall be pulled in a protective liner inside the manhole to prevent damage to the cable. 4. All fiber optic cables shall be terminated with LC type connector and properly connected to the fiber enclosure. Fiber cable metallic sheath if attached shall be properly grounded. 5. When placed in a cable tray or on a runway where there is the possibility of someone standing, walking or sitting on the cable, it shall be placed inside a protective liner. When floor duct is utilized one chamber will be used exclusively for the fiber. 6. All cable placed along runways, relay racks and distribution shelves shall comply with the manufacturer s minimum bend radius requirements for that particular type cable. Cable is to be secured by Velcro so as not to be pulled tight at any point that causes the cable jacket to be crushed flat or indented. 7. Use vertical and horizontal wire management on relay racks to accommodate the fiber cable to be dressed into the fiber terminating enclosures. 8. Fiber optic patch cords are to be used to connect different fibers together for continuation of service. Do not wrap a jumper completely around a routing guide or other type bracket. When using routing guides on a relay rack always use the rear portion of the guides to hold vertical jumper runs and the front portion of the guides to hold horizontal jumpers. Always use the front routing guide to enter or leave a housing. 9. There should be a minimum 30 ft. service loop left in a TER, mounted in a circular configuration on fire rated plywood (3/4 in.) or left in the wiring tray. 10. All fiber strands shall be terminated in accordance with industry standards and layed out in order of industry color codes. 11. Label all fiber cable and each fiber strand at termination locations. BC IT Center will provide fiber cable nomenclature. 12. Test all strands using an optical time domain reflectometer (OTDR) and/or optical loss test sets (OLTS). Fiber cable runs less than 100 meters in length shall be tested with an approved light meter. Provide hardcopy test results of each fiber strand to BC IT Center. See Section 6 for additional testing information. 8.3 UTP A. All four pair UTP cable installed at the College will be at a minimum CAT6 and rated at least 250Megahertz. COMMUNICATIONS HORIZONTAL CABLING

18 B. All UTP riser cable installed at the College will be CAT3 rated and 25 pairs minimum. 8.4 COAXIAL A. All coaxial cable installed at the College for the intended purpose of cable TV distribution will be RG6 quadshield. B. Riser cable for cable TV distribution may be.500 hard line coaxial. PART 9 - CODES, STANDARDS AND REGULATIONS 9.1 GENERAL A. To design facilities for an effective telecommunications system, the designer and installer must be familiar with national and local regulations. Both the designer and the contractor must be familiar with and adhere to the standards of the telecommunications and building industries. B. EXTREMELY IMPORTANT: 1. The installing contractor and/or its designee must be a current BICSI certified installer. This is a mandatory requirement in order for the College to ensure the installation of its communication infrastructure is current with industry standards. NO exceptions will be permitted on this requirement. 9.2 AGENCIES A. The following agencies and their codes, standards and regulations shall govern all telecommunications work performed at Bridgewater College. ANSI American National Standards Institute BICSI Building Industry Consulting Service International Telecommunications Distribution Methods Manual (current edition) Building Officials and Code BOCA Administrators (Standard Building Code) EIA Electronic Industries Association FCC Federal Communications Commission International Conference of ICBO Building Officials (Uniform Building Code) IEEE Institute of Electrical and Electronic Engineers, Inc. NBC National Building Code NFPA National Fire Protection Association NEC National Electrical Code TIA Telecommunications Industry Association UL Underwriters Laboratories Bridgewater College IT Center Wiring Standards PART 10 - COMMUNICATION SERVICES INFORMATION COMMUNICATIONS HORIZONTAL CABLING

19 10.1 CONTACTS A. A list of contacts and addresses is provided for your convenience. BC IT CENTER Director Kristy Rhea [email protected] Manager of IT Operations Aaron Klein [email protected] Network Administrator & IT Security Officer Joe Meslovich [email protected] Help Desk [email protected] COMMUNICATIONS HORIZONTAL CABLING

20

21 Addendum: Information specific to Heritage Hall renovation. The MTR in Heritage is on the 1 st floor in room 108 on the renovation plans. Part of the Heritage renovation project will be to move the entry cables from this location to the new MTR which will be in room 133. There should be ample entry cable within the building to allow for this move. The following cables will need to be moved and re-terminated. From Bowman Hall to Heritage Hall 150 pair burial voice cabling.750 coax cable (we will coordinate with our video provider to reconnect) 12 Strands single mode and 6 Strands multimode Fiber In addition to the cables that feed Heritage Hall another building is also feed from Heritage and those cables are listed below. They will need to be relocated to the new MTR as well. From Heritage Hall to 313 Dinkle Ave 50 pair burial voice cable.500 coax cable (we will coordinate with our video provider to reconnect) 6 Strands multimode Fiber RA designated rooms: These rooms are to have in addition to the 2 Cat-6 data jacks and 1 Coax video jack a Cat-6 voice jack installed. RA Rooms = 17,110,205,220,305,320 RA apartment = 114 and 115 Double gang ceiling box s are to be installed in each room. In rooms not marked to have a WAP installed a blank cover is to be installed that matches the celling paint color. In rooms with a WAP

Presenters Brett Weiss, Gabe Martinez, Brian Kroeger.

Presenters Brett Weiss, Gabe Martinez, Brian Kroeger. 1 Presenters Brett Weiss, Gabe Martinez, Brian Kroeger. Topics to be covered: Cable identification Purpose of the various cable types Installation techniques Building Infrastructure Overview of networking

More information

Building Telecommunications Infrastructure Requirements

Building Telecommunications Infrastructure Requirements Building Telecommunications Infrastructure Requirements This page identifies specific requirements for the design of telecommunications infrastructure for buildings at Clemson University. (Revised October,

More information

800 Communications Circuits

800 Communications Circuits ARTICLE 800 Communications Circuits INTRODUCTION TO ARTICLE 800 COMMUNICATIONS CIRCUITS This article has its roots in telephone technology. Consequently, it addresses telephone and related systems that

More information

COMMUNICATIONS STANDARDS

COMMUNICATIONS STANDARDS UNIVERSITY OF CINCINNATI OFFICE OF INFORMATION TECHNOLOGIES COMMUNICATIONS STANDARDS REVISION DATE: June 01, 2013 TABLE OF CONTENTS Section 1. Section 2. Section 3. Section 4. Section 5. Section 6. Section

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

ATTACHMENT F 050R6800016 - CABLE AND WIRING SERVICES FUNCTIONAL AREA I PRICE PROPOSAL FORM Amendment 6

ATTACHMENT F 050R6800016 - CABLE AND WIRING SERVICES FUNCTIONAL AREA I PRICE PROPOSAL FORM Amendment 6 050R6800016 CABLE AND WIRING SERVICES (Column A) (Column B) (Column C) (Column D) (Column E) (Column F) (Column G) (B+C+D+E)*F= G Item Description PER 100' RUN PER 150' RUN PER 200' RUN PER 300' RUN QUANTITY

More information

TELECOMMUNICATIONS STRUCTURED CABLING GUIDELINES AND SPECIFICATIONS. University of Chicago IT Services Infrastructure Services October 2011

TELECOMMUNICATIONS STRUCTURED CABLING GUIDELINES AND SPECIFICATIONS. University of Chicago IT Services Infrastructure Services October 2011 TELECOMMUNICATIONS STRUCTURED CABLING GUIDELINES AND SPECIFICATIONS IT Services Infrastructure Services October 2011 Table of Contents 1 Introduction... 4 1.1 Planning and Design... 4 1.2.1 Roles and Responsibilities...

More information

TCTC Cabling Specifications

TCTC Cabling Specifications TCTC Cabling Specifications Purpose: To provide a standard specification that will be used for all Tri County Technical College (TCTC) facilities requiring structured cabling installation. Product specifications,

More information

Standards. www.nordx.com 5 ANSI/TIA/EIA-569-A (CSA T530)

Standards. www.nordx.com 5 ANSI/TIA/EIA-569-A (CSA T530) The primary focus of this standard is to provide design specifications and guidance for all building facilities relating to telecommunications cabling systems and components. This standard identifies and

More information

1. Furnish and install faceplate and modular jacks at each single gang outlet as described below:

1. Furnish and install faceplate and modular jacks at each single gang outlet as described below: Washington University in St. Louis Building: Communication Specification: Research Voice/Network/Typical 1. Furnish and install faceplate and modular jacks at each single gang outlet as described below:

More information

DIVISION 27 COMMUNICATIONS. A. System design shall be completed by a Registered Communications Distribution Designer (RCDD).

DIVISION 27 COMMUNICATIONS. A. System design shall be completed by a Registered Communications Distribution Designer (RCDD). DIVISION 27 COMMUNICATIONS 27 00 00 COMMUNICATIONS A. System design shall be completed by a Registered Communications Distribution Designer (RCDD). B. Comply with American National Standards Institute

More information

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION 17650 SECURITY SYSTEMS

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION 17650 SECURITY SYSTEMS PART 0 DESIGN STANDARDS 0.01 GENERAL DESIGN GUIDELINES A. Inspections and observations by the Owner do not relieve the A/E of contract responsibilities. B. Chain of command 1. The DPS Project Manager is

More information

DIVISION 26 - ELECTRICAL SECTION 26 05 20 CABLES FOR INSTRUMENTATION

DIVISION 26 - ELECTRICAL SECTION 26 05 20 CABLES FOR INSTRUMENTATION DIVISION 26 - ELECTRICAL PART 1 - GENERAL 1.01 SUMMARY A. Section Includes 1. Instrumentation Cables 1.02 SUBMITTALS A. Submit in accordance with requirements of Section 01 33 00. B. Product Data: Submit

More information

SECTION 25110 TELECOMMUNICATION ROOMS

SECTION 25110 TELECOMMUNICATION ROOMS PART 1 - GENERAL 1.1 SUMMARY A. SCOPE SECTION 25110 TELECOMMUNICATION ROOMS 1. This section includes the minimum installation requirements for equipment and cabling infrastructure in Telecommunication

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-27 05 14.00 10 (April 2006) -------------------------------- Preparing Activity: USACE Superseding UFGS-27 05 14.00 10 (April 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Specifications for Communication Cabling Distribution Systems

Specifications for Communication Cabling Distribution Systems Washington University in St. Louis Specifications for Communication Cabling Distribution Systems General Overview Listed below are the separate sub-systems of Washington University s structured cabling

More information

UT Southwestern Medical Center Information Resources Cable Installation Standard

UT Southwestern Medical Center Information Resources Cable Installation Standard UT Southwestern Medical Center Information Resources Cable Installation Standard PART 1- GENERAL 1.01 SUMMARY A. Furnish and install wire, cable, devices, equipment, and accessories for a complete system

More information

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264 BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

Electrical. This section applies to the design and installation of building power distribution systems.

Electrical. This section applies to the design and installation of building power distribution systems. Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions

More information

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12

HOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12 SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes grounding and bonding products, design requirements and installation for communications

More information

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to

More information

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding A Guide for California Developers of Com m ercial Property This guide consists of

More information

DESIGN GUIDELINES. Local Area Network

DESIGN GUIDELINES. Local Area Network DESIGN GUIDELINES Local Area Network The total oversight and management responsibilities for information assurance (IA) and protection of DoDEA s critical infrastructure fall under the purview of the DoDEA

More information

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval. Polk School District Specifications for the New Fire Alarm in the Existing Building Eastside Elementary School FIRE ALARM SYSTEM 1.01 SUBMITTALS A. Shop drawings shall be submitted as follows: 1. Manufacturer's

More information

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables The National Armored Cable Manufacturers Association Presents Installation Standard for Types AC and MC Cables An ANSI Standard Original document jointly produced by NECA and NACMA as Standard for Installing

More information

Minimum Standards for Data/Voice Infrastructure in New Building Construction

Minimum Standards for Data/Voice Infrastructure in New Building Construction UNIVERSITY OF WATERLOO Minimum Standards for Data/Voice Infrastructure in New Building Construction 12/17/2012 Offices 1. Two Work Area Outlets (WAO) on opposite walls, each with 2 jacks 2. Each WAO shall

More information

SYSTIMAX SCS PowerSum and GigaSPEED XL Cabling Installation Guidelines

SYSTIMAX SCS PowerSum and GigaSPEED XL Cabling Installation Guidelines SYSTIMAX SCS PowerSum and GigaSPEED XL Cabling Installation Guidelines This document contains critical information regarding the installation of a certified SYSTIMAX SCS that meets or exceeds performance

More information

1 Campus Cabling Systems Introduction

1 Campus Cabling Systems Introduction 1 Campus Cabling Systems Introduction This document represents the campus cable and infrastructure standards adopted and supported by the XXXX. All new construction and renovation should conform to these

More information

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION SPECIFICATION EO-5023 REVISION 3 MARCH 2003 REQUIREMENTS FOR

More information

ELECTRIC METERING COMMERCIAL & INDUSTRIAL

ELECTRIC METERING COMMERCIAL & INDUSTRIAL ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS

More information

TIA 569 Standards Update Pathways & Spaces. Ignacio Diaz, RCDD April 25, 2012

TIA 569 Standards Update Pathways & Spaces. Ignacio Diaz, RCDD April 25, 2012 TIA 569 Standards Update Pathways & Spaces Ignacio Diaz, RCDD April 25, 2012 The purpose of this Standard is to standardize specific pathway and space design and construction practices in support of telecommunications

More information

SECTION 17400 ACCESS CONTROL SYSTEM. CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section.

SECTION 17400 ACCESS CONTROL SYSTEM. CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section. SECTION 17400 ACCESS CONTROL SYSTEM CONDITIONS OF THE CONTRACT AND DIVISION 1, as applicable, apply to this Section. PART 1 - GENERAL 1.1 RELATED WORK A. 16060 Grounding and Bonding B. 16070 Electrical

More information

GENERAL ELECTRICAL REQUIREMENTS

GENERAL ELECTRICAL REQUIREMENTS GENERAL ELECTRICAL REQUIREMENTS RECEPTACLE SPACING Within 6-feet of the edge of any door HABITABLE Not more than 12-feet apart along wall ROOMS: At all wall spaces 24 or more wide Within 24 of edge of

More information

SECTION 22 LIGHTNING PROTECTION SYSTEM

SECTION 22 LIGHTNING PROTECTION SYSTEM SECTION 22 LIGHTNING PROTECTION SYSTEM 22.01 SCOPE: A. These Specifications shall form a part of the Contract Documents and shall govern construction work for all buildings to be built or modified for

More information

March 2007. 27 08 00 Commissioning of Communications. See Appendix E3. 27 08 00-1

March 2007. 27 08 00 Commissioning of Communications. See Appendix E3. 27 08 00-1 March 2007 27 08 00 Commissioning of Communications See Appendix E3. 27 08 00-1 27 11 00 Communications Equipment Room Fittings 1.0 General TELEPHONE RISERS: A. All copper telephone riser cables must be

More information

Fire Alarm System Plans Review Checklist Property location Date of Review

Fire Alarm System Plans Review Checklist Property location Date of Review Fire Alarm System Plans Review Checklist Property location Date of Review 1. Is application completed in entirety? 2. Are the plans review fee submitted with the application? 3. Does floor plan include

More information

The Telecommunications Closet and Building Services

The Telecommunications Closet and Building Services APPENDIX G Telecommunications Building & Network Standards 1. Expectations...2 2. Definitions...2 3. Contractor Requirements...2 4. Design Elements...3 4.1. Spaces...3 4.1.1. Building Service Entrance...3

More information

SECTION 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY

SECTION 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY SECTION 28 05 00 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specifications Sections, apply

More information

1.1 SYSTEM DESCRIPTION.1 Data system includes data outlets and wiring for office and school applications.

1.1 SYSTEM DESCRIPTION.1 Data system includes data outlets and wiring for office and school applications. Issued 2005/06/01 Section 16743 Data System Page 1 of 7 PART 1 GENERAL 1.1 SYSTEM DESCRIPTION.1 Data system includes data outlets and wiring for office and school applications..2 Data system equipment

More information

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included

More information

Electrical Service Guidelines

Electrical Service Guidelines Electrical Service Guidelines Middle Tennessee Electric Membership Corporation Revised: May 23, 2013 MTEMC's Electrical Guidelines TABLE OF CONTENTS Right-of-Way Clearance Guide 3 MTEMC Requirements 4

More information

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS:

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: Signed completed Electrical Permit application form. Minnesota law requires all electrical work is to be performed by licensed,

More information

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements 16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications

More information

TELECOMMUNICATIONS NETWORK STANDARDS AND GUIDELINES FOR THE NEW ADMINISTRATION BULDING

TELECOMMUNICATIONS NETWORK STANDARDS AND GUIDELINES FOR THE NEW ADMINISTRATION BULDING TELECOMMUNICATIONS NETWORK STANDARDS AND GUIDELINES FOR THE NEW ADMINISTRATION BULDING October 1998 Table of Contents SECTION I: New Construction Programming 1.0 New Construction 1.1 Design Elements..................................

More information

SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME)

SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME) SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME) Construction Criteria The unit costs for ADP Mainframe space types are based on the construction quality and design features in the following

More information

Electrical Code Regulation

Electrical Code Regulation Electrical Code Regulation St. Clair County has adopted the 2005 National Electrical Code in its entirety for the unincorporated areas of the county and all communities that have contracted with the county

More information

SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY

SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY Construction Criteria The unit costs for (Wet) space types are based on the construction quality and design features in the following table. This

More information

PUBLIC RESTROOMS, DESIGN INTENT

PUBLIC RESTROOMS, DESIGN INTENT PUBLIC RESTROOMS, DESIGN INTENT 1.01 STRUCTURAL A. Where feasible, metal stud partitions will be constructed on a 6 high concrete curb. 1.02 MECHANICAL A. Restrooms will have a minimum of 15 air changes

More information

IRRIGATION PUMPING Table of Contents - Section 900

IRRIGATION PUMPING Table of Contents - Section 900 IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS

More information

ANSI/TIA/EIA - 568-A, Commercial Building Telecommunications Cabling Standard.

ANSI/TIA/EIA - 568-A, Commercial Building Telecommunications Cabling Standard. WIRING STANDARD INTRODUCTION This standard defines a telecommunications wiring system for North Dakota State Agencies, offices or buildings that will support a multi-product environment. The purpose of

More information

Fibre Optic Wiring Guide for Multiple Dwelling Units (MDUs)

Fibre Optic Wiring Guide for Multiple Dwelling Units (MDUs) Fibre Optic Wiring Guide for Multiple Dwelling Units (MDUs) Greenfield/Brownfield Renovations Table of Contents Future-Proof your Building... 1 MTS Fibre Optics Installation Guidelines... 2 MTS Fibre Optics

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

SECTION 27 13 24 COMMUNICATIONS OPTICAL FIBER OSP CABLING

SECTION 27 13 24 COMMUNICATIONS OPTICAL FIBER OSP CABLING SECTION 27 13 24 COMMUNICATIONS OPTICAL FIBER OSP CABLING PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete

More information

Network Design. Yiannos Mylonas

Network Design. Yiannos Mylonas Network Design Yiannos Mylonas Physical Topologies There are two parts to the topology definition: the physical topology, which is the actual layout of the wire (media), and the logical topology, which

More information

READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY!

READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! The main power to any existing system must be disconnected prior to the

More information

Element D Services Heating, Ventilating, and Air Conditioning

Element D Services Heating, Ventilating, and Air Conditioning PART 1 - GENERAL 1.01 OVERVIEW A. This section supplements Design Guideline Element D3041 on air handling distribution with specific criteria for projects involving design of a Data Center spaces B. Refer

More information

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D 12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section

More information

A. Shop Drawing submittals shall include, but not be limited to, the following:

A. Shop Drawing submittals shall include, but not be limited to, the following: SECTION 26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Divisions 0 and 1 and Section 26 00 01, Electrical

More information

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances. Basement Finishing Guide Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

Electrical Wiring Technical Bulletin

Electrical Wiring Technical Bulletin Electrical Wiring Technical Bulletin Overview In general, SIP construction is easier and more cost effective when things are planned and thought out before the panels are manufactured. This process will

More information

Engineers Edge, LLC PDH & Professional Training

Engineers Edge, LLC PDH & Professional Training 510 N. Crosslane Rd. Monroe, Georgia 30656 (770) 266-6915 fax (678) 643-1758 Engineers Edge, LLC PDH & Professional Training Copyright, All Rights Reserved Engineers Edge, LLC An Introduction to Communication

More information

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada Whitepaper Modular Substation Cable Termination Design Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada Abstract The methods for cable penetrations into modular industrial substations are

More information

REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING

REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3

More information

BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE

BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877

More information

Cable Installation Project

Cable Installation Project Cable Installation Project 1. Intent. It is the intent of the U.S. Court of Appeals to install Category 6 (CAT6) data cabling in the Robert F. Peckham Federal Building and United States Courthouse, 280

More information

How To Plan Out An Array Of Solar Panels

How To Plan Out An Array Of Solar Panels CITY OF DOWNEY COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 11111 Brookshire Avenue Downey, CA 90241 562.904.7142 (www.downeyca.org) B SECTION 01/01/2011 EFFECTIVE DATE PHOTOVOLTAIC 032 FORM NUMBER 2013

More information

Packaged Terminal Air Conditioner Wall Sleeve Installation

Packaged Terminal Air Conditioner Wall Sleeve Installation Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation

More information

SECTION 18370 SIGNAL WIRE AND CABLE

SECTION 18370 SIGNAL WIRE AND CABLE SECTION 18370 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for all cable and wire required for signal and signal power system wiring to wayside shelters, junction boxes, and factory

More information

TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE

TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE The University of Arizona has implemented a Keyless Access and Security System program to provide a cost effective, efficient, and maintainable means

More information

Installation Manual For Support Call 01704 807114 or email [email protected]

Installation Manual For Support Call 01704 807114 or email info@hipentertainment.co.uk Installation Manual Hip Smart Hub (Standard BT and BT FTTP Sites) The Home Network Hub houses the Home Owner s Broadband Router and connects the hardwired network ports on that Router to three network

More information

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor

More information

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2

More information

March 14, 2007. Installation of Bay, Bow and Garden Windows

March 14, 2007. Installation of Bay, Bow and Garden Windows March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed

More information

ADDENDUM NO. 2 TO PROJECT NO. 43153

ADDENDUM NO. 2 TO PROJECT NO. 43153 ADDENDUM NO. 2 TO PROJECT NO. 43153 CONSTRUCTION WORK, MECHANICAL WORK, PLUMBING WORK, ELECTRICAL WORK PROVIDE VISITOR CENTER BUILDING AND SITE IMPROVEMENTS FIVE RIVERS ENVIRONMENTAL EDUCTION CENTER 56

More information

Requirements for the Attachment of Communication Cable Facilities on PPL Poles

Requirements for the Attachment of Communication Cable Facilities on PPL Poles Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication

More information

SECTION 16720 - FIRE AND SMOKE ALARM SYSTEM. City of San Diego, CWP Guidelines

SECTION 16720 - FIRE AND SMOKE ALARM SYSTEM. City of San Diego, CWP Guidelines PART 1 -- GENERAL 1.1 WORK OF THIS SECTION SECTION 16720 - City of San Diego, CWP Guidelines A. The WORK of this Section includes providing manual and automatic fire alarm and smoke detection systems meeting

More information

4 Installation Requirements

4 Installation Requirements 4 Installation Requirements 9 4.1 Code Reference The authority having jurisdiction should be referenced to determine what law, ordinance or code shall apply in the use of flexible duct. Ducts conforming

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

NC State University Design and Construction Guidelines Division 26 Fire Alarm Systems

NC State University Design and Construction Guidelines Division 26 Fire Alarm Systems NC State University Design and Construction Guidelines Division 26 Fire Alarm Systems 1.0 Purpose A. The following guideline provides the minimum standards and requirements for fire alarm systems. 2.0

More information

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

Specifying an IT Cabling System

Specifying an IT Cabling System Specifying an IT Cabling System This guide will help you produce a specification for an IT cabling system that meets your organisation s needs and gives you value for money. You will be able to give your

More information

SECTION 16721 FIRE ALARM AND DETECTION SYSTEMS

SECTION 16721 FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 FIRE ALARM AND DETECTION SYSTEMS The equipment requirements of this section apply to the IUB Campus. The IUPUI Campus has a preferred vendor agreement for fire alarm systems. Contact Pat

More information

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

IT&T Infrastructure Standards

IT&T Infrastructure Standards Technology Services IT&T Infrastructure Standards Version 1.5 17 th April 2015 Page 1 Table of contents 1 CHANGE HISTORY... 3 1.1 DOCUMENT HISTORY... 3 1.2 REVIEWERS... 3 1.3 APPROVALS... 3 2 INTRODUCTION...

More information

2301.1 Scope: Communications and Electronic Systems addressed in this section include:

2301.1 Scope: Communications and Electronic Systems addressed in this section include: Chapter 23 COMMUNICATIONS / ELECTRONIC SYSTEMS SECTION 2301 - GENERAL 2301.1 Scope: Communications and Electronic Systems addressed in this section include: 1. Fire Alarm System 2. Telecommunication and

More information

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings

More information

SECTION 11 78 13 MORTUARY REFRIGERATORS

SECTION 11 78 13 MORTUARY REFRIGERATORS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 11 78 13 MORTUARY REFRIGERATORS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in

More information

Intelligent Cable Management Systems

Intelligent Cable Management Systems Intelligent Cable Management Systems Bringing Practical Application Karen Pearson - Leviton Why Cable Management Matters Performance Cooling and air-handling Maintenance ANSI/TIA 569* Telecommunication

More information

Designing A Communications Cabling System for the Colocation Data Center Larry Smith President, ABR Consulting Group, Inc.

Designing A Communications Cabling System for the Colocation Data Center Larry Smith President, ABR Consulting Group, Inc. Designing A Communications Cabling System for the Colocation Data Center Larry Smith President, ABR Consulting Group, Inc. It is often said that the communications cabling system is the conduit over which

More information