PROJECT PLANNING SCOPE, ROLE, RESPONSIBILITIES
|
|
|
- Gabriel Garrett
- 10 years ago
- Views:
Transcription
1 wwwisipmorg ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma wwwisipmorg PROJECT PLANNING SCOPE, ROLE, RESPONSIBILITIES ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
2 wwwisipmorg Summary What is a WBS? What is a OBS? What is a RAM? ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 3 wwwisipmorg What is a WBS? ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
3 wwwisipmorg What is a WBS? Definition: A WBS is the primary tool used to define what to do in the project in a few words, it describes project scope (ISIPM) A WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables It organizes and defines the total scope of the project (PMI) The planned work is contained within the lowest level WBS components, which are called work packages ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 5 wwwisipmorg WBS the magic tree ICT PROJECT (an example) ICT PROJECT FEASIBILITY REQUIREMENTS ING ROLL-OUT NEEDS MODULES HARDARE MODULE 1 MODULE 2 MOULE N 16 work packages DOC HELP DOCUMENT USER MANUAL TRAINING MANUAL A work package can be scheduled, cost estimated, monitored, and controlled ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
4 wwwisipmorg WBS & Decomposition Criteria (1/4) Decomposition is the subdivision of project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level The work package level is the lowest level in the WBS, and is the point at which the cost and activity durations for the work can be reliably estimated and managed Steps Identifying and analyzing the deliverables and related work Structuring and organizing the WBS Decomposing the upper WBS levels into lower level detailed components (measurable/controllable, assignable to a single resp) Developing and assigning identification codes to the WBS components Verifying that the degree of decomposition of the work is necessary and sufficient ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 7 wwwisipmorg WBS & Decomposition Criteria (2/4) The WBS structure can be created in a number of forms Using phases of the project life cycle as the first level of decomposition, with the product and project deliverables inserted at the second level (see slide 9) Using major deliverables as the first level of decomposition (see slide 10) Using subprojects which may be developed by Organizations outside the project team, such as contracted work As the work is decomposed to greater levels of detail, the ability to plan, manage, and control the work is enhanced The total of the work at the lowest levels must roll up to the higher levels so that nothing is left out and no extra work is completed This is sometimes called the 100% rule ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
5 wwwisipmorg WBS & Decomposition Criteria (3/4) ICT PROJECT FEASIBILITY REQUIREMENTS ING ROLL OUT NEEDS MODULE FUNCTIONAL MODULE FUNCTIONAL FUNCTIONAL HELP USER MANUAL TRAINING MANUAL 19 work packages ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 9 wwwisipmorg WBS & Decomposition Criteria (4/4) ICT PROJECT FEASIBILITY MODULES NEEDS USER MANUAL FUNCTIONAL NODULE 1 TRAINING MANUAL FUNCTIONAL HELP ROLL OUT 19 work packages ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
6 wwwisipmorg WBS a roll-up aggregation ICT PROJECT (62 days) (5 days) (42 days) (6 days) (9 days) FEASIBILITY (3 days) NEEDS (2 days) MODULES (35 days) HELP (4 days) (1 day) ROLL OUT (2 days) (4 days) (1 days) (1 day) (3 days) USER MANUAL (4 days) TRAINING MANUAL (2 days) ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 11 Bottom Up Process wwwisipmorg WBS a drill-down control ICT PROJECT (62 days) Info (5 days) FEASIBILITY (3 days) (42 days) MODULES (35 days) (6 days) (4 days) (9 days) (3 days) Description: Documents Responsibility: Mr Rossi Duration: 9 days Start: End: Budget: 2000 Effort : 15 man/days Resources:2 NEEDS (2 days) HELP (4 days) (1 day) USER MANUAL (4 days) Time Baseline Cost Baseline MARZO 1999 (1 day) (1 day) TRAINING MANUAL (2 days) Attività X Attività Y Attività Z ROLL OUT (2 days) ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
7 wwwisipmorg Work Package Description (1/2) A WP Description is a card which should contain Responsible/Actors who responds? Basic Activities what to do? Requirements/Deliverable what should be produced? Deadine by when? Budget how much? Resources Commitment with whom? Inputs Outputs ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 13 wwwisipmorg Work Package Description (2/2) WP Title: NA Needs Analysis WP Description: Customer Needs & Expectations Analysis Responsible: Budget: 1,000 Inputs: Mr Viola Business Analyst Initial Idea (Concept) Feasibility Analysis/Business Plan Outputs: Deadlines: Requirements Analysis Requirements Traceability Matrix Within 1 week ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
8 wwwisipmorg WBS a Summary Define the boundaries of the scope of project work (the work to be done and what should not be done) Decompose the work in modular elements of small entity more manageable, measurable, controllable Describe project products/services/results (deliverables) Create a rational and rigorous basis for Project Planning & Control in terms of time, cost, quality Identify the project without depending on involved actors Constitute the basic reference for Project Communication Management ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 15 wwwisipmorg What is a OBS? ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
9 wwwisipmorg What is a OBS? Definition: A OBS is the organizational structure of the project it is independent of the Enterprise Organization (ISIPM) A OBS is a hierarchically organized depiction of the project organization arranged so as to relate the work packages to the performing organizational units (PMI) ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 17 OBS an example wwwisipmorg ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
10 wwwisipmorg What is a RAM? ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 19 wwwisipmorg What is a RAM? Definition: A RAM is the tool (matrix chart) used to facilitate the assignment of project responsibilities it is obtained by crossing WBS (what) & OBS (who does) (ISIPM) A RAM is a structure that relates the project organizational breakdown structure to the work breakdown structure to help ensure that each component of the scope of work is assigned to a person/ team (PMI) A particular version of RAM ia a RACI (responsible, accountable, consult, and inform) chart ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
11 Segreteria Siga Salvi Ufficio PR Dssa Paoli Sq uadra Cucina 1 Chef Ufficio S ervizi Sig Ulivi Impresa di Trasporto Squadra Camerieri wwwisipmorg WBS, OBS, RACI an example (1/2) WBS for "Charity Dinner" OBS for "Charity Dinner" Charity Dinner 8,000 Project Manager Mr Verdi 8,000 Organization 1,100 Procurement 5,200 Preparation 1,700 Secretary Mrs Bruni 1,500 PR Mrs Paoli 800 Chef Team Mr Marini 5,000 Service Team Mr Ulivi 700 Invitation 100 Room 700 Menù 100 Food 3,000 Beverage 1,000 Provision 800 Room 200 Kitchen 200 Cooking 1,000 Appetizer 100 First Course 300 Service 300 Appetizer 50 First Course 80 Carriage 100 Waiter 600 Staff 200 Flower/Flowerpot 400 Main Course 500 Main Course 120 WBS - Cost Aggregation Dessert 100 Dessert 50 RACI MATRIX OBS Cost Aggregation WB S - Cena di gala Org anizzazio ne Acq uisti P repar azione Inviti Scelta sala Scelta menù Personale C ibi Bevande V ett ovaglie Fior i Sala Cucina Cottura S er vizio Resp Progetto Dott Galante ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma 21 wwwisipmorg WBS, OBS, RACI an example (2/2) Charity Dinner WBS Organization Procurement Preparation OBS Invitation Room Menù Staff Food Beverage Provision Flower/ Flowerpot Room Kitc hen Cooking Service Project Manager Mr Verdi Secretary Mrs Bruni PR Mrs Paoli Cheaf Team Mr Marini Service Team Mr Ulivi Carriage Waiter A C R I R = Responsible, A = Accountable, C = Consult, I = Inform ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
12 wwwisipmorg Thanks for your attention! ISIPM Istituto Italiano di Project Management Via Vallombrosa, 47/a Roma
Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision 7 - 7 -
Jefferson Science Associates, LLC 200 Organization Project Control System Manual Revision 7-7 - 200 Organization This section of the JSA Project Control System Manual describes the organizational elements
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
Project Management Professional (PMP)
Project Management Professional (PMP) Duration: 5 days Course Objectives: PMI s Project Management Professional (PMP) credential is the most important industry-recognized certification for project managers.
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Project Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
How to Craft a World-Class Work Breakdown Structure
How to Craft a World-Class Work Breakdown Structure Laura Miller, PMP [email protected] 1 Copyright Copyright 2012 2012 Hewlett-Packard Development Development Company, Company, L.P. The L.P. information
MGMT 4135 Project Management. Chapter-4. Defining the Project
MGMT 4135 Project Management Chapter-4 Where We Are Now Chapter-4 Steps for Chapter-4 Step-1 Scope Step-2 Establishing Project Priorities Step-3 Creating the Work Breakdown Structure Step-4 Integrating
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Project Planning. Project Planning. Project Planning MGMT 409 PROJECT MANAGEMENT PROJECT PLANNING: WORK BREAKDOWN STRUCTURE (WBS) (SLIDE SET 05)
MGMT 409 PROJECT MANAGEMENT PROJECT PLANNING: WORK BREAKDOWN STRUCTURE (WBS) (SLIDE SET 05) Dr. Ömer Yağız Department of Business Administration EMU Project Planning Plans are only good intentions unless
Time Management. Herb Pollard III
Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
Deciding the work to be Performed (Work Breakdown Structure)
Deciding the work to be Performed (Work Breakdown Structure) Goals of the Unit Understanding the transition from project goals to the project schedule Introducing the Work Breakdown Structure notation
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1 Introduction to Project Management Learning Objectives Describe the importance of creating plans to guide project
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
PMP: Project Management Professional Exam Study Guide. 7th Edition
Brochure More information from http://www.researchandmarkets.com/reports/2505193/ PMP: Project Management Professional Exam Study Guide. 7th Edition Description: The ultimate package for preparing you
SCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
Advanced Project Management Training Course
Advanced Project Management Training Course 1-34 Advanced Project Management Crea/ng the Scope Baseline 2-34 Crea/ng the Scope Baseline Module 1 Introduction Module 2 Creating the Project Charter Module
PMLead. Project Management Professional. edition. Based on PMBOK Guide 4 th. www.pmlead.net
PMLead Project Management Professional Based on PMBOK Guide 4 th edition www.pmlead.net SECTION II Chapter 3 Project Management Processes Chapter 3 Project Process Groups A process is a set of interrelated
Lecture Slides for Managing and Leading Software Projects. Chapter 5: Project Planning Techniques
Lecture Slides for Managing and Leading Software Projects Chapter 5: Project Planning Techniques developed by Richard E. (Dick) Fairley, Ph.D. to accompany the text Managing and Leading Software Projects
pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Microsoft Project Activity
Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge
Adapted from slides by John Musser
Adapted from slides by John Musser 1 What s the difference? Plan Identify activities. No specific start and end dates. Estimate Determine the size and duration of activities. Schedule Add specific start
Developing Work Breakdown Structures
Developing Work Breakdown Structures International Cost Estimating & Analysis Association June 2014 Neil F. Albert MCR, LLC [email protected] 703-506-4600 2014 MCR, LLC Distribution prohibited without express
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Chapter 01. PMP work book answers V3 2012. Exercise 01: Question Answer Question Answer
Chapter 01 Exercise 01: Question Answer Question Answer i. Procurement Management KA ii. Integration Management KA iii. Cost Management KA iv. HR Management KA v. Risk Management KA vi. Quality Management
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING 03-23-05 Christine Green, PMI PMBOK and Estimating EDS, Delivery
Project Management Fundamentals. Office of the Senior Associate Vice President for Finance
Project Management Fundamentals Project Management Institute PMI is an aggregation of best practices from thousands of professional project managers Principles in this training are based on PMI methodologies,
Appeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
Unit 06 Developing the Work Breakdown Structure
Unit 06 Developing the Work Breakdown Structure April 2007 Project Management Wilhelm F. Neuhäuser IBM Corporation 2007 Agenda Unit 6: Developing the Work Breakdown Structure Objectives Value of the WBS
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION Robert T. Hans Software Engineering Department, Tshwane University of Technology, Pretoria, South Africa [email protected] ABSTRACT
Project Management for Everyone
Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group Phone: (202) 994-6867 Cell: (240) 472-2171 Email: [email protected] Objectives Basic understanding
Project Managing to Support Change. Cathryn Stam, PMP Tina Salaris, RN, PMP
Project Managing to Support Change Cathryn Stam, PMP Tina Salaris, RN, PMP Project Managing to Support Change Change is a constant in life People by nature do not like change Whether redesigning processes
Project Plan for <project name>
Note: Text displayed in blue italics is included to provide guidance to the author and should be deleted or hidden before publishing the document. This template can be used at it is, or to complete and
How To Organize A Business
Page 1 of 9 The Organization Breakdown Structure Figure 3-1: Organization Breakdown Structure (OBS) (see next page), shows a representative OBS. At the conclusion of this lesson you will be able to recognize
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
Visit www.pm-prepcast.com for Exam Resources P a g e 16
Module and Lesson Directory No Lesson Title Type Duration Module 00.0 Welcome & Exam Overview 1. L00.00 Welcome Video 28:28 Module 00.1 Student Workbook 2. L00.10 PM PrepCast Student Workbook PDF -- Module
Project Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 7 Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org Credits 2 This slides are largely based on Prof. John Musser class
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems The Work Breakdown Structure (WBS) is the foundation for project planning and control. It is the connecting
What is Project Scope Management? Project Scope Management Summary. Project Scope Management Processes
What is Project Scope Management? Chapter 5 Project Scope Management October 27, 2008 Scope refers to all the work involved in creating the products of the project and the processes used to create them
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
Chapter 5: Project Scope Management. Information Technology Project Management, Fifth Edition
Chapter 5: Project Scope Management Information Technology Project Management, Fifth Edition What is Project Scope Management? Scope refers to all the work involved in creating the products of the project
Introduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
Module 7: Change Management
Module 7: Change Module 7: Change Integrating Project with Change They think by installing this system they will end my services let us see if they will ever manage to get it done What is the purpose of
SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE
SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE ABSTRACT Robert T. Hans Tshwane University of Technology, Pretoria, South Africa [email protected] Software project
Work Breakdown Structure. http://www.mekonginstitute.org/
Work Breakdown Structure Project Scope Management Includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE Head, Office of Project Support Services
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
Project Management Process. Prepared by Jay Knape
Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University
Positive Train Control (PTC) Program Management Plan
Positive Train Control (PTC) Program Management Plan Proposed Framework This document is considered an uncontrolled copy unless it is viewed online in the organization s Program Management Information
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?
1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
Applying the Work Breakdown Structure to the Project Management Lifecycle
Applying the Work Breakdown Structure to the Project Management Lifecycle Introduction Shelly A. Brotherton, PMP; Robert T. Fried, PMP; Eric S. Norman, PMP, PgMP Today, Project Managers are more frequently
PROJECT TIME MANAGEMENT
PROJECT TIME MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_time_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
Project Management Professional (PMP) Boot Camp
Project Management Professional (PMP) Boot Camp According to the Project Management Institute, the world's leading association for the project management profession: "PMP Certification is the profession's
Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date: 07-31-2012
Minnesota Health Insurance Exchange Project (MNHI) Deliverable Definition Document (DDD) For Project Plan Date: 07-31-2012 11/9/2012 1:18 PM Page 1 of 8 1. High Level Deliverable Description The Project
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
Lab 1 Introduction to Microsoft Project
Lab 1 Introduction to Microsoft Project Statement Purpose This lab provides students with the knowledge and skills to use Microsoft Project. This course takes students step-by-step through the features
Understanding risk exposure using multiple hierarchies. Introduction
Understanding risk exposure using multiple hierarchies David Hillson PhD PMP FAPM FIRM MCMI FRSA Director, Risk Doctor & Partners Introduction Risk management is recognised as an essential contributor
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to
PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP
TSE015 PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP Course Outline I. Introduction and Course Objectives A. About PMI B. PMP and CAPM
www.aryanengineering.com Email: [email protected]
What is PMP Certification exam? www.aryanengineering.com PMP stands for Project Management Professional certification exam. PMP, is one of the most respected and globally recognized certification is offered
Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study
2011 International Conference on Management and Service Science IPEDR vol.8 (2011) (2011) IACSIT Press, Singapore Application of Earned Value Management System on an Infrastructure Project: A Malaysian
PMP/CAPM Prep course. Anwers to all questions with rationale
2 Fmwk&Int. 1 C PMBOK 2012, 1.2 - What is a project 2 Fmwk&Int. 2 D PMBOK 2012, 3.7 Closing Process Group 2 Fmwk&Int. 3 D PMBOK 2012, 1.4 - Relationships Among Project/Program/Portfolio Mgmt 2 Fmwk&Int.
Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK
Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK Lewis Gray, Ph.D., PMP Abelia Fairfax, Virginia USA www.abelia.com Copyright 2002 by Abelia Corporation. All rights reserved
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
MODULE TWO PROJECT MANAGEMENT BACKGROUND & COMMUNICATION
Syed Quadri, PMP Region 5 RPM MODULE TWO PROJECT MANAGEMENT BACKGROUND & COMMUNICATION 0 Project Management Background Topics to be covered: Benefits of using PM tools PMI and PMBOK Strategic Project Management
2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster
2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster Traditional Classroom / Onsite Course No. 665 Duration: 2 days Credits: 14 PDUs / 1.4 CEUs Prerequisites Twelve hours of
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: [email protected]
Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition 1 Topics for Discussion
PMI Fundamentals PMI Processes Project Organization. Initial documents. Functional, Project, Matrix Orgs. Statement of Work (SOW) Project Charter
PMI Fundamentals PMI Processes Project Organization Functional, Project, Matrix Orgs. Initial documents Statement of Work (SOW) Project Charter Remember the 40-20-40 Rule Specification-Implementation-Test
How To Develop Software
Software Engineering Prof. N.L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture-4 Overview of Phases (Part - II) We studied the problem definition phase, with which
Project Management Office (PMO)
Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project
Family Computer Centre
PMP - Project Professional 35 Contact Hours Comprehensive Training Program Designed on the basis of Project Body of Knowledge (PMBOK Guide) Family Computer Centre Ground Floor, Al Rayyan Complex P. O Box:
Masaryk University Faculty of Economics and Administration MASTER THESIS
Masaryk University Faculty of Economics and Administration MASTER THESIS BA. Isaac Tetteh Brno, 2014 Masaryk University Faculty of Economics and Administration Use of Project Management Methods Master
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Earned Value Management System (EVMS) Manual. System Description and Implementing Procedures
Manual System Description and Implementing Procedures Manual System Description and Implementing Procedures Contact Information This document is maintained, updated, and formally revised electronically
Project Manager and Business Analyst Collaboration
Project Manager and Business Analyst Collaboration Mike Sandberg Director, IT Business Analysis Center of Excellence Novell, Inc. Email: [email protected] LinkedIn: http://www.linkedin.com/in/mdsandberg
Applied Software Project Management
Applied Software Project Management Software Project Planning http://www.stellman-greene.com 1 Who needs software? Most software is built in organizations for people with specific needs. A stakeholder
Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam
Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please