Developing Work Breakdown Structures
|
|
|
- Cornelius Tate
- 10 years ago
- Views:
Transcription
1 Developing Work Breakdown Structures International Cost Estimating & Analysis Association June 2014 Neil F. Albert MCR, LLC MCR, LLC Distribution prohibited without express written consent of MCR, LLC Outline Background Purpose and Definition Development Process WBS Dictionary Program/Project Integration Requirements WBS/OBS Intersection Summary References 2014 MCR, LLC. All rights reserved. Distribution Limited
2 Background Why Is A WBS Important? Acquisition Environment Changing Provides a consistent and visible framework for programs and contracts Improves communication throughout the acquisition process Assists in planning and the assignment of management and technical responsibilities Provides the foundation for project integration and success Provides Standardization - consistency and commonality for Government and Industry implementation 2014 MCR, LLC. All rights reserved. Distribution Limited.. 3 Background Use of Work Breakdown Structures (WBS) is critical to the success of proper program management WBS defines work and system List of Requirements/Specifications List of Resources List of Tasks Statement of Work Structured Subdivision of Project Elements to be communicated within and outside the program Does Not Drive a Program s Requirements 2014 MCR, LLC. All rights reserved. Distribution Limited.. Rights Reserved 4 2
3 Work Breakdown Structure 1.0 Automobile Program 1.1 Design Engineering 1.2 Manufacturing 1.3 Project Management 1.4 Training Feasibility Analysis Producibility Analysis Preliminary Design Casting & Molding Detailed Design Testing 2014 MCR, LLC. All rights reserved. Distribution Limited Work Breakdown Structure (Product Oriented) 1.0 Automobile Program 1.1 Automobile 1.2 System Engineering 1.3 Project Management 1.4 Training 1.5 System Test and Eval 1.6 Data Engine Interior Controls Chassis IAT&CO 2014 MCR, LLC. All rights reserved. Distribution Limited
4 Work Breakdown Structure Definition A product (deliverable) oriented family tree of hardware, software, services, and data which results from engineering efforts during development and production of a system Displays and defines the product(s) and relates the elements of work to each other and the end product, and completely defines the program Uses the 100% rule: Next level of decomposition of a WBS element (child level) must represent 100% of the work applicable to the next higher level (parent) 2014 MCR, LLC. All rights reserved. Distribution Limited.. 7 Work Breakdown Structure Definition Two types of Work Breakdown Structures: 1) Program Work Breakdown Structure encompasses entire program and consists of at least three levels of the program Used to define the entire program Encompasses all elements and used to develop and extend to lower level WBS element structures Ensures that work elements are defined and related to only one specific work effort so activities are not omitted or duplicated 2014 MCR, LLC. All rights reserved. Distribution Limited.. 8 4
5 Work Breakdown Structure Definition Two types of Work Breakdown Structures (Cont d) 2) Contract Work Breakdown Structure is the WBS for reporting purposes and its discretionary extension by the contractor Includes all the elements for the products which are responsibility of the contractor Contract work statement should provide the reporting requirements 2014 MCR, LLC. All rights reserved. Distribution Limited.. 9 WBS Levels Level 1 Entire System, Program, Study Program Element, Project or Subprogram Level 2 Major Elements of the System, Program, Study Top Level Aggregations of Services or Data Level 3 Subordinate Items to Level 2 Elements Generally Common Across Similar Programs, Systems, or Studies 2014 MCR, LLC. All rights reserved. Distribution Limited
6 Program WBS (Example) LEVEL 1 BICYCLE SYSTEM LEVEL 2 BICYCLE ENGINEERING/ PROGRAM MANAGEMENT TEST AND EVALUATION DATA TRAINING LEVEL 3 FRAME SET CRANK SET WHEELS 2014 MCR, LLC. All rights reserved. Distribution Limited.. 11 Contract WBS (Example) LEVEL 1 (Level 3) FRAME SET SYSTEM LEVEL 2 (Level 4) FRAME SET PROGRAM MANAGEMENT DATA ENGINEERING TEST AND EVALUATION LEVEL 3 (Level 5) FRAME HANDLEBAR FORK SEAT 2014 MCR, LLC. All rights reserved. Distribution Limited
7 Generic System Work Breakdown Structure LEVEL 1 LEVEL 2 LEVEL 3 Delivered System Prime Mission Product (PMP) Subystem 1..n (Specify Names) PMP Applications Software PMP System Software PMP Integration, Assembly, Test and Checkout Systems Engineering Program Management Test and Evaluation Training Data Development Test and Evaluation Operational Test and Evaluation Mock-ups Test and Evaluation Support Test Facilities Equipment Services Facilities Technical Publications Engineering Data Management Data Support Data Data Depository 2014 MCR, LLC. All rights reserved. Distribution Limited.. 13 Generic System Work Breakdown Structure LEVEL 1 LEVEL 2 LEVEL 3 Support Equipment Test and Measurement Equipment Support and Handling Equipment Site Implementation System Assembly, Installation and Checkout on Site Contractor Technical Support Site Construction Site Conversion 2014 MCR, LLC. All rights reserved. Distribution Limited
8 Software and Software Intensive Systems Increasingly critical in today s acquisition environment Divided into two categories for WBS development Software that operates on specific equipment Software that may be procured separately from the operating equipment or is stand-alone that is developed for specific equipment and then must be identified as a subset of that equipment Enterprise Resource Planning Business Systems Developed Systems 2014 MCR, LLC. All rights reserved. Distribution Limited Visibility into Software Development Processes Due to product-oriented hierarchy Progressive subdivision results in common management or functional tasks (i.e., development processes, etc.) Example: Software widespread throughout the WBS and represent high risk in the contract. Program manager requires specific visibility into software performance. Do not overly complicate the Contract WBS and the contractor s management system Provide detail/visibility of key software development processes (i.e., requirements analysis, design, code and test, etc.) through contractor s management system and WBS Not extending the WBS to excessively low levels or developing a separate WBS for software Aggregate information for reporting 2014 MCR, LLC. All rights reserved. Distribution Limited
9 Generic System WBS Software LEVEL X LEVEL X+1 PMP Subsystem Hardware 1 n (Specify) PMP Subsystem Software Release 1...n (Specify) Software Product Engineering Computer Software Configuration Item (CSCI) 1 n Subsystem Integration, Assembly, Test and checkout Subsystem Integration, Assembly, Test and Checkout 2014 MCR, LLC. All rights reserved. Distribution Limited.. 17 Issues in WBS Development Product WBS based on the various views that constitute the functional and/or physical design Define logical relationship between elements of the program and its natural extension Maintain the integrity of the level of placement Defining to a specific level (typically level 3) of indenture does not constrain ability to define or manage the program or resources Lower level if considered high cost, high risk, high technology (product orientation extension maintained) Historical data important Aids as resource to the future development or similar items The need for data should not distort/hinder program definition and/or contractor s extension or management of the program 2014 MCR, LLC. All rights reserved. Distribution Limited
10 Pre-Systems Acquisition Planning Systems Acquisition Systems Sustainment CEA 03 - Work Breakdown Structure Program Life Cycle PM Integrated Baseline Review Surveillance Cost Schedule Technical EVM Risk Analysis Cost Schedule Technical Performance Measuremen t Baseline Cost Schedule Technical Cost Analysis Life Cycle Cost Estimate Cost Schedule Technical Risk Analysis Cost Schedule Technical Acquisition Cost Estimate Cost Schedule Technical Risk Analysis Cost Schedule Technical Systems Engineering Concept Definitio n Operational/ Functional Concept AoA WBS Requirement s Definition Risk Analysis Cost Schedule Technical Acquisition Plan WBS Risk Analysis Cost Schedule Technical 2014 MCR, LLC. All rights reserved. Distribution Limited.. 19 Defense Acquisition Management System Materiel Solution Analysis Materiel Development Decision AoA A B Technology Development PDR Engineering and Manufacturing Development Post PDR Assessment PDR CDR Post CDR Assessment IOC FRP Decision Review FOC or Pre-Systems Acquisition Systems Acquisition Sustainment C Production & Deployment Operations & Support PDR: Preliminary Design Review CDR: Critical Design Review FRP: Full Rate Production IOC: Initial Operational Capability FOC: Full Operational Capability 2014 MCR, LLC. All rights reserved. Distribution Limited
11 Work Breakdown Structure Evolution MATERIAL SOLUTION ANALYSIS PROPOSED PROGRAM WBS(s) TECHNOLOGY DEVELOPMENT APPROVED/ PROPOSED PROGRAM WBS ENGINEERING AND MANUFACTURING DEVELOPMENT APPROVED/ UPDATED PROGRAM WBS PRODUCTION AND DEPLOYMENT APPROVED PROGRAM WBS #1 CONTRACT PRELIMINARY WBS #2 CONTRACT PRELIMINARY WBS OTHER CONTRACT(s) IF ANY #1 CONTRACT WBS AND EXTENSION #2 CONTRACT WBS AND EXTENSION OTHER CONTRACT(s) IF ANY #1 CONTRACT WBS AND EXTENSION #2 CONTRACT WBS AND EXTENSION OTHER CONTRACT(s) IF ANY PRE-SYSTEMS ACQUISITION SYSTEMS ACQUISITION 2014 MCR, LLC. All rights reserved. Distribution Limited.. 21 Program Manager Role and Responsibility Leads A Multi-Disciplined Team That Attempts To Balance And Integrate: Technical Performance (Quality) Schedule (Time) WBS provides logical Cost (Resources) framework to manage Risk (Acceptable Level) Communicate the team s Vision/Mission. Promotes Multi-Discipline Communication - All the Time 2014 MCR, LLC. All rights reserved. Distribution Limited
12 Expected Results KILL TANKS MOVE DETECT DESTROY 2014 MCR, LLC. All rights reserved. Distribution Limited.. 23 Pre-Systems Acquisition Phase Materiel Solution Analysis Materiel Development Decision AoA Pre-Systems Acquisition WBS impact Decision point driven by requirements for expected results Analysis of Alternatives Need generic or historical WBS to support AoA 2014 MCR, LLC. All rights reserved. Distribution Limited
13 Pre-Systems Acquisition WBS Definition Preliminary Program WBS Developed Top Level cost, schedule and performance goals for the total systems acquisition effort Specific cost, schedule and performance goals and exit criteria for the development phase Risk Management planning and scheduling defined Materiel Solutions Analysis based on AoA results Rationale for acquisition strategy Appropriate definition on prototypes produced and deployed Performance goals and Exit Criteria to be met prior to proceeding into Technology Development phase and producing prototypes 2014 MCR, LLC. All rights reserved. Distribution Limited.. 25 Pre-Systems Acquisition Materiel Solutions Aircraft SYSTEM Air Vehicle Airframe Propulsion Avionics Armament/ Weapon Fire Control Detect Aim Fire Track 2014 MCR, LLC. All rights reserved. Distribution Limited
14 Pre-Systems Acquisition Technology Development Technology Development PDR Technology Development Enter: PM has technical solution and has developed design and may have developed, or integrated into complete system Activities: System design, development and integration of subsystems and components Reduction of integration risk Exit: Demonstration of prototypes in relevant environment WBS Development Top Level WBS with extension into lower level development. Completed prototypes ready for intended environment Cost, schedule and performance measured (EVM) reporting Risk management planning and scheduling integrated 2014 MCR, LLC. All rights reserved. Distribution Limited.. 27 Detailed WBS Development Aircraft System ~ Air Vehicle Training Program Management ~ ~ Airframe Avionics Propulsion Equipment Services ~ Communication Navigation Fire Control ~ Antenna Receiver Transmitter 2014 MCR, LLC. All rights reserved. Distribution Limited
15 Systems Acquisition Engineering and Manufacturing Development WBS Development PDR Complete WBS linked to major products and systems Fully integrated with Program Management/Cost functions Cost/Schedule Performance (EVM) reporting Risk Planning and Scheduling ongoing Engineering and Manufacturing Development Post PDR Assessment Post CDR Assessment CDR EMD Enter: Prototypes demonstrated in intended environment System matured for production Activities: Complete system design and development Prepare for low-rate initial production Establish full manufacturing capability Exit: Demonstration using engineering development models; meets requirements Operationally effective, suitable and ready for full rate production 2014 MCR, LLC. All rights reserved. Distribution Limited.. 29 Systems Acquisition Production & Deployment Production & Deployment FRP Decision Review Production & Deployment Enter: Demonstrated control of manufacturing process Full-up systems level completed Activities: Low rate initial production Full rate production Deliver system Start sustainment activities Exit: Full operational capability; delivery complete WBS Development Maintenance of WBS Change planning for engineering changes (Major Scope changes) Cost/Schedule Performance tracking in place EVM reporting remains in place 2014 MCR, LLC. All rights reserved. Distribution Limited
16 Work Breakdown Structure Dictionary WBS Dictionary will serve multiple functions within the program. Defines element in terms of technical, schedule, and performance criteria Includes detailed description of element and how it relates to next higher element, Supports product structure regardless of phase or funding Subcontractor effort detailed where it supports the system Identifies what is not in the elements to ensure clear relationship Supports technical, schedule, and/or cost risk assessment and mitigation 2014 MCR, LLC. All rights reserved. Distribution Limited.. 31 Relationship To Management Plan and Schedule Three (3) Elements of Control Project Control is the first unit of control Integrated Master Plan (IMP) ties work scope with technical plans and goals of the program Time or Schedule is the second unit of control Integrated Master Schedule (IMS) ties work scope to schedule or milestones goals Understanding the duration to go from step one to step two of the work scope the better the plan and the better the control Identifying Resources is the third unit of control Identifying materials, people and tools to the work scope definition will determine how well the project is utilizing resources and how performance is measured 2014 MCR, LLC. All rights reserved. Distribution Limited
17 Test & Eval Management Engineering Manufacturing CEA 03 - Work Breakdown Structure 3 Dimensions Of Project Control Management Plan Management Schedule Resources Work Structure Breakdown 2014 MCR, LLC. All rights reserved. Distribution Limited.. 33 WBS Related Definitions Organizational Breakdown Structure (OBS): Hierarchical representation of the project/program organization elements responsible for control accounts and summary level planning packages (SLPP s) Provides the structure to report performance metrics by organization level Control Account (CA): Lowest WBS/CWBS element assigned to a single management focal point to plan and control scope, schedule, and budget for the purpose of performance measurement Comprised of work packages and planning packages Responsibility Assignment Matrix (RAM): Created from the intersection of the WBS and OBS Identifies responsible organizations and CAM's for the project CA's and SLPP's. Tool for assigning organization responsibilities for elements of the project. May include cost (i.e., dollarized RAM) and schedule baseline information for CA and SLPP MCR, LLC. All rights reserved. Distribution Limited
18 Control Account Intersection CONTROL ACCOUNT ESTABLISHED AT THE INTERSECTION OF THE WBS & OBS WBS THE CAM IS RESPONSIBLE FOR TECHNICAL, SCHEDULE AND COST PERFORMANCE OF ALL WORK (ASSIGNED SCOPE)... ITEM 1 ITEM 1.1 ITEM 1.2 ITEM 2 ITEM 2.1 ITEM 2.2 FUNCTION 1.1 FUNCTION 1 OBS FUNCTION1.2 FUNCTION2.1 FUNCTION 2 FUNCTION MCR, LLC. All rights reserved. Distribution Limited.. 35 Integrated Management Requirements WBS Elements SOW Task System Specification 1000 Air Vehicle 1100 Airframe 1110 Wing 1000 Air Vehicle 1100 Airframe 1110 Wing o o 1189 Landing Gear 3.1 Air Vehicle (WBS 1000) Design, develop, produce and verify, complete air vehicles, defined as airframe propulsion, avionics and other installed equipment. Integrated Master Plan Management Plan 1. Preliminary Design Review PDR Events Accomplishment Criteria 1. A. Duty Cycle Defined b. Preliminary Analysis Complete Integrated Master Schedule Detailed Tasks 20XX 20XY 20XZ Program Events 1. Preliminary Design Complete Duty Cycle Defined PDR CDR 2014 MCR, LLC. All rights reserved. Distribution Limited
19 WBS Integration Program Status Reporting Program Plan Development Work Responsibility Assignment Financial Reporting Work Activity Schedulin g Configuration Management Cost Estimating Management Information System Resource Allocation Risk Analysis The WBS Remains the Definitive Framework for Communication of Technical, Cost and Schedule Elements 2014 MCR, LLC. All rights reserved. Distribution Limited
20 References MIL-STD-881C OMB Circular A-11 Part 7 Supplement to A-11, Part 7 Capital Programming Guide Earned Value Management Implementation Guide Practice Standard for Work Breakdown Structures, 2 nd Edition MCR, LLC. All rights reserved. Distribution Limited
THE WORK BREAKDOWN STRUCTURE IN AN ACQUISITION REFORM ENVIRONMENT. Prepared For: COST SCHEDULE PERFORMANCE MANAGEMENT CONFERENCE
THE WORK BREAKDOWN STRUCTURE IN AN ACQUISITION REFORM ENVIRONMENT Prepared For: COST SCHEDULE PERFORMANCE MANAGEMENT CONFERENCE Prepared By: Neil F. Albert 700 Technology Park Drive Billerica, MA 01821
DEPARTMENT OF DEFENSE STANDARD PRACTICE
NOT MEASUREMENT SENSITIVE MIL-STD-881C 3 October 2011 SUPERSEDING MIL-HDBK-881A 30 July 2005 MIL-STD-881B 25 March 1993 DEPARTMENT OF DEFENSE STANDARD PRACTICE WORK BREAKDOWN STRUCTURES FOR DEFENSE MATERIEL
DEPARTMENT OF DEFENSE HANDBOOK
NOT MEASUREMENT SENSITIVE MIL-HDBK-881A 30 JULY 2005 SUPERSEDING MIL-HDBK-881 2 JANUARY 1998 DEPARTMENT OF DEFENSE HANDBOOK WORK BREAKDOWN STRUCTURES FOR DEFENSE MATERIEL ITEMS This handbook is for guidance
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)
Appendix B: Work Breakdown Structure (WBS)
: Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
How To Organize A Business
Page 1 of 9 The Organization Breakdown Structure Figure 3-1: Organization Breakdown Structure (OBS) (see next page), shows a representative OBS. At the conclusion of this lesson you will be able to recognize
WORK BREAKDOWN STRUCTURE HANDBOOK
WORK BREAKDOWN STRUCTURE HANDBOOK U.S. Department of Energy Washington, D.C. 20585 August 16, 2012 AVAILABLE ONLINE AT: URL TBD INITIATED BY: Office of Management FOREWORD This handbook was developed by
WBS Development: Rules, Aberrations, and MIL-STD-881C Implementation Challenges
Development: Rules, Aberrations, and MIL-STD-881C Implementation Challenges M. Michael Metcalf, Technomics Inc. SCEA/ISPA 2012 Sponsor: Mr. Mike Augustus, DCARC Some material was taken from DCARC training
FOREWORD. Page 2 of 88
FOREWORD Earned Value Management (EVM) is one of the DoD s and industry's most powerful program management tools. Government and industry program managers use EVM to assess cost, schedule and technical
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision 7 - 7 -
Jefferson Science Associates, LLC 200 Organization Project Control System Manual Revision 7-7 - 200 Organization This section of the JSA Project Control System Manual describes the organizational elements
Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Management Oversight REVISION: 43 APPROVED BY: TITLE Head, Office of Project Management
NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE Head, Office of Project Support Services
Program/Project Management Series Work Breakdown Structure Reference Guide
Program/Project Management Series Work Breakdown Structure Reference Guide National Aeronautics and Space Administration May 1994 2 Work Breakdown Structure Reference Guide May 1994 Table of Contents Chapter
SCHEDULING GUIDE FOR PROGRAM MANAGERS
SCHEDULING GUIDE FOR PROGRAM MANAGERS October 2001 PUBLISHED BY THE DEFENSE SYSTEMS MANAGEMENT COLLEGE PRESS FORT BELVOIR, VA 22060-5565 For sale by the U.S. Government Printing Office Superintendent of
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
Project Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
WORK BREAKDOWN STRUCTURES FOR DEFENCE MATERIEL PROJECTS
COMMONWEALTH OF AUSTRALIA AUSTRALIAN DEFENCE STANDARD DEF(AUST)5664 Issue A Dated Jun 2004 REPLACING/SUPERSEDING DEF(AUST)5664 Dated Aug 1995 WORK BREAKDOWN STRUCTURES FOR DEFENCE MATERIEL PROJECTS DRAFT
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Demystifying the PMBOK: Project Planning Made Simple" By" Bill Carswell, Ph.D., PMP" Adjunct Professor" Embry Riddle Aeronautical University" "
Demystifying the PMBOK: Project Planning Made Simple" By" Bill Carswell, Ph.D., PMP" Adjunct Professor" Embry Riddle Aeronautical University" " How Complicated Is PM?" walks the reader through the new
Earned Value Management System (EVMS) Manual. System Description and Implementing Procedures
Manual System Description and Implementing Procedures Manual System Description and Implementing Procedures Contact Information This document is maintained, updated, and formally revised electronically
WORK BREAKDOWN STRUCTURE
Chapter 9 Work Breakdown Structure CHAPTER 9 WORK BREAKDOWN STRUCTURE 9.1 INTRODUCTION The Work Breakdown Structure (WBS) is a means of organizing system development activities based on system and product
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
AIRCRAFT WORK BREAKDOWN STRUCTURE (WBS) LEVELS (FROM MILITARY SPECIFICATION 881)
Appendix C AIRCRAFT WORK BREAKDOWN STRUCTURE (WBS) LEVELS (FROM MILITARY SPECIFICATION 881) Level 1 Level 2 Level 3 Aircraft System Air Vehicle (AV) System Engineering/ Program Management Airframe Propulsion
IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?
1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,
WORKFORCE COMPOSITION CPR. Verification and Validation Summit 2010
WORKFORCE COMPOSITION CPR PEO IEW&S Organizational Assessment VCSA Brief Date 2010 October 13, 2010 This briefing is UNCLASSIFIED/FOUO PREDECISIONAL LIMITED DISTRIBUTION AS OF: 11 Sep 2010 Verification
MGMT 4135 Project Management. Chapter-4. Defining the Project
MGMT 4135 Project Management Chapter-4 Where We Are Now Chapter-4 Steps for Chapter-4 Step-1 Scope Step-2 Establishing Project Priorities Step-3 Creating the Work Breakdown Structure Step-4 Integrating
Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control
Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
Manufacturing Readiness Level (MRL) Deskbook Version 2.0 May, 2011
Manufacturing Readiness Level (MRL) Deskbook Version 2.0 May, 2011 Prepared by the OSD Manufacturing Technology Program In collaboration with The Joint Service/Industry MRL Working Group This document
Earned Value Management System Description
LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS
How To Write Ansi/Eia Evm System Acceptanceance Guide
National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006
Government Contracting and Earned Value Management (EVM)
Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine
Fixed Work Breakdown Structures in Microsoft Project A Case for a Custom Outline Code Field
Fixed Work Breakdown Structures in Microsoft Project A Case for a Custom Outline Code Field Jim Aksel, PMP, PMI SP ProjectPMO [email protected] (714) 312 3120 Microsoft Project contains Work Breakdown
Appendix E Program Management Plan Template
Appendix E Program Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
Project Management System Description (PMSD)
Project Management System Description (PMSD) Revision 3 Project Management System Description (PMSD) Revision 3 February 2016 Prepared by: Date: Steve Langish Planning & Control Division Approved by: Date:
Earned Value Management Best Practices
Division of Information Technology Investment Management Enterprise Architecture & Strategy Group Office of Information Services Earned Value Management Best Practices Version 2.2 Last Modified: 19 November
FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office
Space Flight Project Work Breakdown Structure
APPENDIX G. (WBS) Space Flight Project Work Breakdown Structure G.1 Introduction G.1.1 The Project Work Breakdown Structure (WBS) is a key element of project management. The purpose of a WBS is to divide
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Technology Readiness Assessment (TRA)
DEPARTMENT OF DEFENSE Technology Readiness Assessment (TRA) Guidance April 2011 Prepared by the Assistant Secretary of Defense for Research and Engineering (ASD(R&E)) revision posted 13 May 2011 Contents
Department of Defense INSTRUCTION
Department of Defense INSTRUCTION NUMBER 5000.02 January 7, 2015 USD(AT&L) SUBJECT: Operation of the Defense Acquisition System References: See References 1. PURPOSE. This instruction: a. In accordance
NODIS Library Program Formulation(7000s) Search
NODIS Library Program Formulation(7000s) Search NASA Procedural Requirements This Document Is Uncontrolled When Printed. Check the NASA Online Directives Information System (NODIS) Library to verify that
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
An Introduction to IMP/IMS
An Introduction to IMP/IMS In 2003 the US Government revised its acquisition policies with a procurement strategy focused on process improvement and acquisition reform implemented by performance-based
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
CalMod Design-Build Electrification Services
SECTION 01800 SYSTEMS INTEGRATION AND INTEGRATOR REQUIREMENTS PART 1 GENERAL DESCRIPTION A. This section specifies the system-wide integration requirements for the Caltrain Electrification system, i.e.
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
SYSTEMS ENGINEERING FUNDAMENTALS
Introduction Systems Engineering Fundamentals SYSTEMS ENGINEERING FUNDAMENTALS January 2001 SUPPLEMENTARY TEXT PREPARED BY THE DEFENSE ACQUISITION UNIVERSITY PRESS FORT BELVOIR, VIRGINIA 22060-5565 i Systems
Military Handbook 881 Work Breakdown Structure Update
Military Handbook 881 Work Breakdown Structure Update Presented By: Neil Albert 25 August 2004 MCR, LLC 2000 Corporate Ridge, Suite 400 McLean, VA 22102 Update to incorporate DoD changes in Acquisition
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
Project Management Planning
The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information
Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam
Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the
U.S. Department of Defense Extension to:
U.S. Department of Defense Extension to: A Guide to the Project Management Body of Knowledge (PMBOK Guide) First Edition Version 1.0 June 2003 PUBLISHED BY THE DEFENSE ACQUISITION UNIVERSITY PRESS FORT
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
!"#$%&'(%)*$+ :%;$)*%<&%6 4.7&68'9"/6")& 0)1.%$2.3*%./'4"55*)6 ,&+-%$+./ !"#$%&##'()*+&## Figure 1: Five OSP Dimensions
!""#!$%&'(#)$*+,(-*(.&%/# &0*$1!"#$%&'(%)*$+ :%;$)*%
NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook
NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook National Aeronautics and Space Administration NASA Headquarters Washington, D.C. 20546 February 2013 NASA STI Program... in Profile
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
Requirements Management John Hrastar
Requirements Management John Hrastar NASA Project Management Conference March 30-31, 2004 University of Maryland Conference Center Introduction Three aspects of requirements management Requirements in
Information Technology Project Management (ITPM)
FUNCTIONAL AREA 10 Project Management (ITPM) Incumbents in this functional area direct information technology system solution and/or improvement projects for cost, time, scope, risk, and quality. They
Introduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
Program and Project Management Practices in the Federal Civilian Agencies
Progress through partnership National Defense Industry Association, Civilian Agencies Industry Working Group Program and Project Management Practices in the Federal Civilian Agencies White Paper Lawrence
SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
Project Management Standards: A Review of Certifications/Certificates
Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in
Guided Process across Project Management; Preliminary phase: Contract Preparation
Electronics Technology Department FINAL PROJECT Guided Process across Project Management; Preliminary phase: Contract Preparation Author: Mª Pilar Albertos Mesonero Director: Bernardo Delicado Trapero
CAPITAL PROGRAMMING GUIDE
CAPITAL PROGRAMMING GUIDE V 3.0 SUPPLEMENT TO OFFICE OF MANAGEMENT AND BUDGET CIRCULAR A 11: PLANNING, BUDGETING, AND ACQUISITION OF CAPITAL ASSETS CAPITAL PROGRAMMING GUIDE LIST OF ABBREVIATIONS LIST
ENOVIA Aerospace and Defense Accelerator for Program Management
ENOVIA Aerospace and Defense Accelerator for Program Management Through project pipeline dashboards, ENOVIA Aerospace and Defense Accelerator for Program Management provides real-time visibility into a
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Goddard Procedures and Guidelines
Goddard Procedures and Guidelines DIRECTIVE NO. APPROVED BY Signature: Original signed by NAME: A. V. Diaz TITLE: Director Responsible Office: Title: Code 300 / Office of Systems Safety and Mission Assurance,
The Air Force Materiel Command
COMMUNICATION = SUCCESS F-22 PROGRAM INTEGRATED PRODUCT DEVELOPMENT TEAMS How One Major Aircraft Program Developed Integrated vs. Independent Product Teams Capt. Gary F. Wagner, USAF Capt. Randall L. White,
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1 Introduction to Project Management Learning Objectives Describe the importance of creating plans to guide project
Earned Value Management and Professional Services Automation
Earned Value Management and Professional Services Automation Prepared by: Frances B. Craig Unanet Technologies www.unanet.com 1 of 5 Earned Value Management and Professional Services Automation Earned
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains Mary J. Simpson System Concepts 6400 32 nd Northwest, #9 Seattle, WA 98107 USA Joseph J. Simpson System Concepts
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
How to Craft a World-Class Work Breakdown Structure
How to Craft a World-Class Work Breakdown Structure Laura Miller, PMP [email protected] 1 Copyright Copyright 2012 2012 Hewlett-Packard Development Development Company, Company, L.P. The L.P. information
Work Breakdown Structure
Project Management Practices Rev E, June 23 U.S. Department of Energy Office of Management, Budget and Evaluation Work Breakdown Structure Initiated by: Office of Engineering and Construction Management
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
Criteria for Flight Project Critical Milestone Reviews
Criteria for Flight Project Critical Milestone Reviews GSFC-STD-1001 Baseline Release February 2005 Approved By: Original signed by Date: 2/19/05 Richard M. Day Director, Independent Technical Authority
SCHEDULE AND BUDGETING
PROJECT CONTROLS The right combination of software management tools, proper initial project set-up, timely and accurate data input, continuous tracking of progress, a meaningful reporting structure, strong
Project Management Terms
FDM 2-1 Attachment 1.1 Terms Terms Baseline Term Baseline Budget Baseline Schedule Baseline Scope Budget Budget Change Control Communication Corrective Action Cost-Benefit Analysis Critical Path Decision
DATA REQUIREMENTS DESCRIPTION (DRD)
DATA REQUIREMENTS DESCRIPTION (DRD) 1. DPD NO.: XXX ISSUE: Draft 2. DRD NO.: STD/EDAL 3. DATA TYPE: 3 4. DATE REVISED: 5. PAGE: 1/3 6. TITLE: Engineering Drawings and Associated Lists 7. DESCRIPTION/USE:
AP1000 European 18. Human Factors Engineering Design Control Document
18.2 Human Factors Engineering Program Management The purpose of this section is to describe the goals of the AP1000 human factors engineering program, the technical program to accomplish these goals,
3SL. Requirements Definition and Management Using Cradle
3SL Requirements Definition and Management Using Cradle November 2014 1 1 Introduction This white paper describes Requirements Definition and Management activities for system/product development and modification
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
PROGRAM MANAGEMENT IN DEFENSE SYSTEMS
Seminar s Title : PROGRAM MANAGEMENT IN DEFENSE SYSTEMS Purpose and Background : Program Management is one of the most important aspects of the entire defense acquisition process. It is the application
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Deciding the work to be Performed (Work Breakdown Structure)
Deciding the work to be Performed (Work Breakdown Structure) Goals of the Unit Understanding the transition from project goals to the project schedule Introducing the Work Breakdown Structure notation
SOFTWARE DEVELOPMENT AND DOCUMENTATION
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. NOT MEASUREMENT SENSITIVE MIL-STD-498 5 December 1994 (PDF version) Superseding DOD-STD-2167A 29 February 1988 DOD-STD-7935A
Training Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
