What is Project Scope Management? Project Scope Management Summary. Project Scope Management Processes
|
|
|
- Stephanie Turner
- 10 years ago
- Views:
Transcription
1 What is Project Scope Management? Chapter 5 Project Scope Management October 27, 2008 Scope refers to all the work involved in creating the products of the project and the processes used to create them A deliverable is a product produced as part of a project, such as hardware or software, planning documents, or meeting minutes Project scope management includes the processes involved in defining and controlling what is or is not included in a project 2 Project Scope Management Processes Project Scope Management Summary Scope planning: deciding how the scope will be defined, verified, and controlled Scope definition: reviewing the project charter and preliminary scope statement and adding more information as requirements are developed and change requests are approved Creating the WBS: subdividing the major project deliverables into smaller, more manageable components Scope verification: formalizing acceptance of the project scope Scope control: controlling changes to project scope 3 4 1
2 Scope Planning and the Scope Management Plan Sample Scope Management Plan The scope management plan is a document that includes descriptions of how the team will prepare the project scope statement, create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope Key inputs include the project charter, preliminary scope statement, and project management plan 5 6 Sample Project Charter Scope Definition and the Project Scope Statement The preliminary scope statement, project charter, organizational process assets, and approved change requests provide a basis for creating the project scope statement As time progresses, the scope of a project should become more clear and specific 7 8 2
3 Creating the Work Breakdown Structure (WBS) Sample Intranet WBS Organized by Product A WBS is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project WBS is a foundation document that provides the basis for planning and managing project schedules, costs, resources, and changes Decomposition is subdividing project deliverables into smaller pieces A work package is a task at the lowest level of the WBS 9 10 Sample Intranet WBS Organized by Phase Intranet WBS in Tabular Form 1.0 Concept 1.1 Evaluate current systems 12D 1.2 Define Requirements Define user requirements Define content requirements Define system requirements Define server owner requirements 1.3 Define specific functionality 1.4 Define risks and risk management approach 1.5 Develop project plan 1.6 Brief Web development team 2.0 Web Site Design 3.0 Web Site Development 4.0 Roll Out 5.0 Support
4 Intranet WBS and Gantt Chart in Microsoft Project Intranet Gantt Chart Organized by Project Management Process Groups Approaches to Developing WBSs Using guidelines: some organizations provide guidelines for preparing WBSs The analogy approach: review WBSs of similar projects and tailor to your project The top-down approach: start with the largest items of the project and break them down The bottom-up approach: start with the specific tasks and roll them up Mind-mapping i approach: mind mapping is a technique hi that uses branches radiating out from a core idea to structure thoughts and ideas Sample Mind-Mapping Approach for Creating a WBS
5 Resulting WBS in Chart Form The WBS Dictionary and Scope Baseline Many WBS tasks are vague and must be explained more so people e know what to do and can estimate how long it will take and what it will cost to do the work A WBS dictionary is a document that describes detailed information about each WBS item The approved project scope statement and its WBS and WBS dictionary form the scope baseline, which is used to measure performance in meeting project scope goals Advice for Creating a WBS and WBS Dictionary* A unit of work should appear at only one place in the WBS The work content of a WBS item is the sum of the WBS items below it A WBS item is the responsibility of only one individual, even though many people may be working on it The WBS must be consistent it twith the way in which h work is actually going to be performed; it should serve the project team first, and other purposes only if practical *Cleland, David I. Project Management: Strategic Design and Implementation, Advice for Creating a WBS and WBS Dictionary (continued)* Project team members should be involved in developing the WBS to ensure consistency and buy-in Each WBS item must be documented in a WBS dictionary to ensure accurate understanding of the scope of work included and not included in that item The WBS must be a flexible tool to accommodate inevitable changes while properly maintaining control of the work content in the project according to the scope statement *Cleland, David I. Project Management: Strategic Design and Implementation,
6 Scope Verification It is very difficult to create a good scope statement and WBS for a project It is even more difficult to verify project scope and minimize scope changes Scope verification involves formal acceptance of the completed project scope by the stakeholders Acceptance is often achieved by a customer inspection and then sign-off on key deliverables Scope Control Scope control involves controlling changes to the project scope Goals of scope control are to: Influence the factors that cause scope changes Assure changes are processed according to procedures developed as part of integrated change control Manage changes when they occur Variance is the difference between planned and actual performance Best Practices for Avoiding Scope Problems 1. Keep the scope realistic: Don t make projects so large that they can t be completed; break large projects down into a series of smaller ones 2. Involve users in project scope management: Assign key users to the project team and give them ownership of requirements definition and scope verification 3. Use off-the-shelf hardware and software whenever possible: Many IT people enjoy using the latest and greatest technology, but business needs, not technology trends, must take priority 4. Follow good project management processes: As described in this chapter and others, there are well-defined processes for managing project scope and others aspects of projects Suggestions for Improving User Input Develop a good project selection process and insist that sponsors are from the user organization Have users on the project team in important roles Have regular meetings with defined agendas, and have users sign off on key deliverables presented at meetings Deliver something to users and sponsors on a regular basis Don t promise to deliver when you know you can t Co-locate users with developers
7 Suggestions for Reducing Incomplete and Changing Requirements Develop and follow a requirements management process Use techniques such as prototyping, use case modeling, and Joint Application Design (JAD) to get more user involvement Put requirements in writing and keep them current Create a requirements management database for documenting and controlling requirements Suggestions for Reducing Incomplete and Changing Requirements (continued) Provide adequate testing and conduct testing throughout the project life cycle Review changes from a systems perspective Emphasize completion dates to help focus on what s most important Allocate resources specifically for handling change requests/enhancements like NWA did with ResNet Using Software to Assist in Project Scope Management Word-processing software helps create several scoperelated documents Spreadsheets help to perform financial calculations and weighed scoring models, and develop charts and graphs Communication software like and the Web help clarify and communicate scope information Project management software helps in creating a WBS, the basis for tasks on a Gantt chart Specialized software is available to assist in project scope management Chapter Summary Project scope management includes the processes required to ensure that the project addresses all the work required, and only the work required, to complete the project successfully Main processes include: Scope planning Scope definition Creating the WBS Scope verification Scope control
IT/Software Project Management Core Functions
IT/Software Project Management Core Functions By: Prof. Dr. Eng. Ghazy Assassa, CMC-IMC Certified Management Consultant, Institute of Management Consultancy, UK Email: [email protected] Mobile: 0502862400
Chapter 5: Project Scope Management. Information Technology Project Management, Fifth Edition
Chapter 5: Project Scope Management Information Technology Project Management, Fifth Edition What is Project Scope Management? Scope refers to all the work involved in creating the products of the project
Software Project Management I
Software Project Management I Dr. Jong Yih Kuo Dr. Chien-Hung Liu Computer Science and Information Engineering National Taipei University of Technology Course Schedule Time Topic Document 18:10~18:55 (45
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1 Introduction to Project Management Learning Objectives Describe the importance of creating plans to guide project
Introduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Time Management. Herb Pollard III
Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
Project Management Concepts and Strategies
Project Management Concepts and Strategies Contact Hours: 24 Course Description This series provides a detailed examination of project management concepts and strategies. It discusses the seven components
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
SCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
Project Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
PROJECT PLAN FOR. Project Name Here
PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION Robert T. Hans Software Engineering Department, Tshwane University of Technology, Pretoria, South Africa [email protected] ABSTRACT
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
Systems Analysis and Design in a Changing World, Fifth Edition
Systems Analysis and Design in a Changing World, Fifth Edition Learning Objectives Explain the elements of project management and the responsibilities of a project manager Explain project initiation and
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Unit 06 Developing the Work Breakdown Structure
Unit 06 Developing the Work Breakdown Structure April 2007 Project Management Wilhelm F. Neuhäuser IBM Corporation 2007 Agenda Unit 6: Developing the Work Breakdown Structure Objectives Value of the WBS
Technical Project Management Engineers Week 2009
Technical Project Management Engineers Week 2009 Presented by: Denise Jackson, PhD, PE Associate Professor University of Tennessee Space Institute [email protected] 1 Technical Project Management: Outline
INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
Project Planning. Project Scope. Work Breakdown Structure.
Chapter 5 Project Planning. Project Scope. Work Breakdown Structure. 1 Objectives Acquire a general understanding of the parts of the project management plan Understand the importance of discovering and
Software Project Management
Software Project Management Week 5: Work Breakdown Structures and a Case Study COMP3711 Software Project Management 1 Project Planning: A 12 Step Program 1) Set goal and scope 2) Select lifecycle 3) Set
SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE
SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE ABSTRACT Robert T. Hans Tshwane University of Technology, Pretoria, South Africa [email protected] Software project
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
10 Critical Steps to Create a Project Plan
10 Critical Steps to Create a Project Plan Elizabeth Larson, PMP, CBAP and Richard Larson, PMP, CBAP Principals, Watermark Learning, Inc. Industry Article Watermark Learning 7300 Metro Blvd, Suite 207
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
1 Start a new project
Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify
Managing a Project Using an Agile Approach and the PMBOK Guide
Managing a Project Using an Agile Approach and the PMBOK Guide Kathy Schwalbe, Ph.D. [email protected] Augsburg College Minneapolis, Minnesota September 25, 2012 Abstract This paper includes excerpts
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING 03-23-05 Christine Green, PMI PMBOK and Estimating EDS, Delivery
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>.
Guide to Preparing the SOFTWARE PROJECT MANAGEMENT PLAN R. Buckley CSc 190 Senior Project Department of Computer Science - College of Engineering and Computer Science California State University, Sacramento
Advanced Project Management Training Course
Advanced Project Management Training Course 1-34 Advanced Project Management Crea/ng the Scope Baseline 2-34 Crea/ng the Scope Baseline Module 1 Introduction Module 2 Creating the Project Charter Module
Work Breakdown Structure. http://www.mekonginstitute.org/
Work Breakdown Structure Project Scope Management Includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
IMCPM04 Project Scheduling and Cost Control. Course Outline
IMCPM04 Project Scheduling and Cost Control Course Outline January 2012 Project Scheduling and Cost Control Course Aim Project Scheduling and Cost Control is a five-day (5 day) course which provides participants
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
Release 1. BSBPMG410A Apply project time-management techniques
Release 1 BSBPMG410A Apply project time-management techniques BSBPMG410A Apply project time-management techniques Modification History Release Release 1 Comments This version first released with BSB07
Making project management indispensable for business results. Project Management 101
Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of
VA ICJIS. Program Management Plan
VA ICJIS Program Management Plan 1 08/29/01 Program Management Plan VA Integrated Criminal Justice Information System (ICJIS) Program 1. Introduction. The Commonwealth of Virginia Integrated Criminal Justice
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
PMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
ProjectMinds Quick Guide to Project Management
ProjectMinds Quick Guide to Project Management By Manjeet Singh [email protected] 1 A D I F F E R E N T K I N D O F C O P Y R I G H T No rights reserved. All the parts of this book can be reproduced,
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision 7 - 7 -
Jefferson Science Associates, LLC 200 Organization Project Control System Manual Revision 7-7 - 200 Organization This section of the JSA Project Control System Manual describes the organizational elements
5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter
Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the
MICROSOFT OFFICE PROJECT - SYLLABUS
MICROSOFT OFFICE PROJECT - SYLLABUS Sessions Session 1 Description 1. INTRODUCTION a. Introduction to CADFORUM and PPM b. Project c. Examples of project d. Project Triangle e. Project Management f. Life
Using Your PMO to Drive Successful Organizational Change Management
Using Your PMO to Drive Successful Organizational Change Management Joe Saliunas, Booz Allen Hamilton 11 November 2012 1 Agenda Organizational change management overview Case studies PMBOK Guide processes
SOFTWARE ENGINEERING INTERVIEW QUESTIONS
SOFTWARE ENGINEERING INTERVIEW QUESTIONS http://www.tutorialspoint.com/software_engineering/software_engineering_interview_questions.htm Copyright tutorialspoint.com Dear readers, these Software Engineering
ID Task Name Time Pred
0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive
Information Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
Project Scheduling & Tracking
Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the
Project Management Process. Prepared by Jay Knape
Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
MIS 460 Project Management
Ursuline College Accelerated Program CRITICAL INFORMATION! DO NOT SKIP THIS LINK BELOW... BEFORE PROCEEDING TO READ THE UCAP MODULE, YOU ARE EXPECTED TO READ AND ADHERE TO ALL UCAP POLICY INFORMATION CONTAINED
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
Project Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生
專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生 講 師 介 紹 > 學 歷 台 灣 大 學 學 士 台 灣 大 學 碩 士 美 國 德 州 大 學 奧 斯 汀 校 區 工 程 專 案 管 理 博 士 中 華 民 國 土 木 工 程 大 地 工 程 水 土 保 持 工 程 專 門 技 術 人 員 高
Project Management Plan. Project Management Plan Guide. Strategic Capital, Infrastructure and Projects
Project Management Plan Guide A guide to completing the Project Management Plan Strategic Capital, Infrastructure and Projects Prepared by: Andrew Segrott / Strategic Capital, Infrastructure and Projects
PMP/CAPM Prep course. Anwers to all questions with rationale
2 Fmwk&Int. 1 C PMBOK 2012, 1.2 - What is a project 2 Fmwk&Int. 2 D PMBOK 2012, 3.7 Closing Process Group 2 Fmwk&Int. 3 D PMBOK 2012, 1.4 - Relationships Among Project/Program/Portfolio Mgmt 2 Fmwk&Int.
The PMP Application Process
The PMP Application Process The purpose of this document is to explain the PMP application process and provide helpful links and tools for submitting your application. Reference: The reference for the
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Project Management Planning
The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK
Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK Lewis Gray, Ph.D., PMP Abelia Fairfax, Virginia USA www.abelia.com Copyright 2002 by Abelia Corporation. All rights reserved
In this chapter we explore a concept and a practice that has grown
11 Chapter Project Management In this chapter we explore a concept and a practice that has grown in importance as organizations have become more complex and are continuously evolving and implementing new
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
MGMT 4135 Project Management. Chapter-4. Defining the Project
MGMT 4135 Project Management Chapter-4 Where We Are Now Chapter-4 Steps for Chapter-4 Step-1 Scope Step-2 Establishing Project Priorities Step-3 Creating the Work Breakdown Structure Step-4 Integrating
CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 7 Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org Credits 2 This slides are largely based on Prof. John Musser class
Guidelines. Project Management Methodology. & Step-by-Step Guide to Managing Successful Projects
Project Management Methodology Guidelines Project Management Methodology & Step-by-Step Guide to Managing Successful Projects Table of Contents Table of Contents 1. Project Management Overview...1 1.1.
Project Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
Project Management for Scientists
Project Management for Scientists Cost & Schedule Estimates Christoph U. Keller, [email protected] Sterrekundig Instituut Utrecht Utrecht University www.astro.uu.nl/~keller Outline Resource Assignments
The Secret Mix of Successful GIS Project Management
2014 WAURISA Conference The Secret Mix of Successful GIS Project Management Presented By: Geoff Almvig, Skagit County GIS Don Burdick, Salish Coast Sciences, LLC What Is A Project? Definition: A project
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
Introduction and Overview
Introduction and Overview Definitions. The general design process. A context for design: the waterfall model; reviews and documents. Some size factors. Quality and productivity factors. Material from:
Certified Project Management Professional VS-1079
Certified Project Management Professional VS-1079 Certified Project Management Professional Certification Code VS-1079 Vskills certification for Project Management Professional assesses the candidate for
A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition
A Guide To The Project Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition Major Changes The adoption of the verb-noun format for process names Amplification as to Enterprise
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems The Work Breakdown Structure (WBS) is the foundation for project planning and control. It is the connecting