SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE
|
|
|
- Maximilian Jefferson
- 10 years ago
- Views:
Transcription
1 SOFTWARE PROJECT SCOPE VERIFICATION THROUGH DELIVERABLE-ORIENTED WORK BREAKDOWN STRUCTURE ABSTRACT Robert T. Hans Tshwane University of Technology, Pretoria, South Africa Software project scope verification is a very important process in project scope management and it needs to be performed properly so as to avoid project rework and to promote better project scope control. Moreover, software scope verification is crucial in the process of delivering exactly what the customer requested and minimizing project scope changes. Well defined software scope eases the process of scope verification and contributes to project success. Furthermore, a deliverable-oriented WBS provides a road map to a well defined software scope of work. It is on the basis of this that this paper extends the use of deliverableoriented WBS to that of scope verification process. This paper argues that a deliverableoriented WBS is a tool for software scope verification KEYWORDS Software scope verification, scope definition, User requirements, WBS, Inspection 1. INTRODUCTION A software project manager s success in managing a project is mainly based on how well he/she manages the project s triple constraint (project scope, cost, and time). User requirements must be collected and be well interpreted in the process of scope definition. The process of ensuring that a project scope is well defined and covers all user requirements aspects has proven to be a challenge for software project managers. Schwalbe (2011) agrees with this assertion and states that one of the critical and difficult aspects of project scope management has been project scope definition. It is important that a project team should have a well defined project scope right from the start of a project in order to: minimize project scope changes, scope creep and thereby aiding in scope control, ensure that products produced by the project meet user requirements and avoid unnecessary project rework. The key question is how best can software project managers produce a project scope that meets all the abovementioned requirements? This is possible through the scope verification process. Schwalbe (2011:198) defines scope verification as a process that: Jan Zizka (Eds) : CCSIT, SIPP, AISC, PDCTA pp , CS & IT-CSCP 2013 DOI : /csit
2 408 Computer Science & Information Technology (CS & IT) involves formal acceptance of the completed project scope by the stakeholders In order to do a thorough job in project scope verification, project team members and users should work closely together throughout the project life cycle. Moreover, Schwalbe (2011:198) states: The main tool for performing scope verification is inspection. The customer, sponsor, or user inspects the work after it is delivered. The field of software engineering has numerous research studies and books that have been written on the subject of scope verification. However, the researcher is not aware of any research study on using work breakdown structure (WBS) to verify software project scope. Therefore, this research paper seeks to close this theoretical void by suggesting the use of WBS as a tool for verifying software project scope. This aim is also strengthened by Rad (2001) who states that a WBS provides a road map to a well defined scope of work. It is on the basis of this that this paper extends the use of WBS to that of scope verification process. 2. LITERATURE REVIEW 2.1 Introduction Software project success is generally measured using the triple constraint ( iron/golden triangle), namely, cost goals, time goals and project performance in terms of project scope completion (Brewer & Dittman, 2010). Therefore, an organization would want to have a software project scope finished within these constrains. Software companies are in constant search for tools and techniques that would assist project managers manage the triple constraint. Project scope management ensures that project stakeholders have the same understanding of what products the project will produce (Schwalbe, 2011). Furthermore, Schwalbe (2011) states that scope definition and scope verification are some of the processes used in project scope management. 2.2 Project Scope Verification In broad terms, verification can be regarded as a process of determining whether a software development phase has been correctly carried out (Schach, 1996). Scope verification is a process that is carried out under specification analysis phase. In this phase client s requirements are analyzed and interpreted in order to produce a specification document which will contain project scope of work. Project scope verification is an important process in ensuring that the project team delivers exactly what the customer requested (Brewer & Dittman, 2010) and also in ensuring that project scope changes are minimal (Schwalbe, 2011). It is the process that formalizes the acceptance of the project scope. Various tools and techniques have been suggested for project scope verification process (Schwalbe, 2011; Schach, 1996) and these include: Inspection the customer or user inspects the work after it is delivered. Prototyping working replica of the planned system. Use case modeling a tool used to model business events in order to gain better understanding of user requirements. Joint application design a technique used to promote greater involvement of key project stakeholders in system development. Walkthrough A document is carefully checked by a team of software professionals.
3 Computer Science & Information Technology (CS & IT) 409 Any of these tools and techniques may be applied in the process of project scope verification. In order for project scope verification to proceed smoothly, scope definition has to be done thoroughly. A well defined project scope is a pre-cursor for successful project scope control, project success and customer satisfaction. The next section discusses work breakdown structure which plays an important role in defining a project scope. 2.3 Work Breakdown Structure (WBS) According to Schwalbe (2011:186) a work breakdown structure is: a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. In essence, a WBS is a decomposition of a large project into smaller manageable parts. The decomposition can proceed until the desired level of detail, lowest-level discrete deliverables, is reached (Fuller et al., 2008; Rad & Cioffi, 2004). A WBS defines the total project scope (Schwalbe, 2011; Brewer & Dittman, 2010; Malone, 2012). Therefore, a work breakdown structure is important to the success delivery of any software project (Fuller, Valacich and George, 2008) because it defines in detail the work necessary to accomplish a project s objectives. The successful delivery of the software project is in terms of cost and schedule (Zhao, 2006) performance a WBS provides a foundation for better cost and schedule estimation. Chua and Godinot (2006) agree with this assertion and state that a WBS is widely regarded as powerful tool for better performance control. Furthermore, a typical WBS reflects user and/or system requirements (Fuller et al., 2008) as well as providing a basis for identifying resources and tasks for developing a project cost estimate. A well developed WBS also serves as a communication tool among stakeholders (U.S.A Government Accountability Office, 2006). Rad (2001) agrees with this assertion and states that a good WBS reduces the possibility of omitting key project elements. Software project managers use various tools and techniques in developing a WBS. The next section briefly discusses different approaches used in WBS development. 2.4 Approaches in developing WBS The primary technique in creating a WBS is the decomposition process (Fuller et al., 2008; Schwalbe, 2011). A WBS can be presented in two forms, namely, hierarchical and tabular form (Fuller et al., 2008). According to Schwalbe (2011) there are various approaches that can be used in developing a WBS and these include: Using guidelines organizational guidelines that are to be followed in developing work breakdown structures in the organization. An analogy approach the use of a similar project s WBS in developing a WBS of the new project. The Top-down approach one starts with largest items of the project and break them down into their subordinate items. The Bottom-up approach one identifies specific related project tasks and organize them into summary activities (aggregate tasks). Mind mapping approach one starts with a core idea and then link related ideas to the core idea.
4 410 Computer Science & Information Technology (CS & IT) There is no single best approach in developing a WBS and therefore it is possible to use a combination of approaches in a WBS development (Schwalbe, 2011). According to Cadle and Yeates (2008), in recent years experts have considered another approach to project planning and have suggested the use of product breakdown structure (PBS) or a deliverable-oriented WBS (Rad, 2001) in creating a WBS. The advantage of this approach is that the project s focus is on what is to be achieved rather than how, in other words the focus is on the ends instead of the means (Cadle and Yeates, 2008). The creation of a PBS uses the similar principles as in the creation of a WBS progressively decomposing the project products into smaller products until a sensible, unitary product level is reached. The aim is to create a WBS which highlights a logical organization of products, parts and modules (Rad, 2001). The next section discusses the role that a deliverable-oriented WBS can play in scope verification. 2.5 The importance of deliverable-oriented WBS in scope verification Covey (1994) emphasizes the importance of having the end results in mind right from the beginning of a project. The deliverable-oriented approach in creating a WBS enforces this the end result is project deliverables. According to Rad (2001) a deliverable-oriented WBS provides a road map to the definition of scope of work. It also provides a clear picture of what needs to be accomplished (U.S.A Government Accountability Office, 2006:65). Furthermore, deliverables serve as a basis for creating a WBS (Rad, 2001). Moreover, a deliverable-oriented WBS facilitates the sharing of information and serves as a tool for communication and project scope control (Rad & Cioffi, 2004). The process of scope verification involves establishing as to whether the developed scope does conform to the user requirements (Schach, 1996) verifying scope against user requirements, as indicated by Figure 1 below. That is, verifying that the scope addresses all user requirements. Therefore, scope verification encompasses, in a way, requirements analysis. In the process of clarifying the project scope and establishing its completeness with the users, one would be able to find out if the product(s) that will be produced through the completion of project scope would meet user requirements (Rouse, 2012). Project Scope Verify scope against user requirements using deliverableoriented WBS User Requirements Verify product against project scope Verify product against user requirements Final Product Figure 1
5 Computer Science & Information Technology (CS & IT) 411 A project scope which is contained in the project specification document (Schach, 1996) is a product of user requirements analysis process. Moreover, a deliverable-oriented WBS, which is the total project scope, focuses on what is to be produced in terms of project products. Therefore, such a structuring of work (scope) makes it easier for project managers to verify the scope against user requirements, because he/she knows what deliverables are expected in order to meet user requirements. The primary purpose of scope verification as it was pointed out above, is to establish the completeness of project scope in terms of user requirements. This would entail establishing as to whether all scope deliverables as outlined by the WBS are in fact complete in terms of user specification. This cross checking or reference using a deliverable-oriented WBS would also help detect misinterpretation of user requirements as well as omissions that might have occurred in the process of specification document development. 2.6 Conclusion In the light of avoiding software project scope rework and promotion of better project scope control, project scope verification process is critical. Moreover, software scope verification is an important process in ensuring that the project team delivers exactly what the customer requested and minimizes project scope changes. A deliverable-oriented WBS provides project managers with a scope verification tool to ease the challenge of scope verification (Schwalbe, 2011). This paper has argued this assertion in the preceding sections. 3. LIMITATIONS This paper has only presented a conceptual argument in as far as using a deliverable-oriented WBS for software project scope verification process, and therefore empirical evidence is needed to support the claim. 4. FUTURE RESEARCH The practical usefulness and benefits of using a deliverable-oriented WBS as a software project scope verification tool need to tested and validated. REFERENCES [1] Brewer, J.L., & Dittman, K.C Methods of IT Project Management. USA: Pearson Prentice Hall [2] Chua, D.K.H. & Godinot, M Use of a WBS Matrix to Improve Interface Management in Projects, Journal of Construction Engineering and Management, January [3] Covey, S First Things First. USA: Pearson Prentice Hall. [4] Fuller, M.A., Valacich, J.S. & George, J.F Information Systems Project Management. USA: Pearson Prentice Hall. [5] Malone, B.A Work Breakdown Structure. OPEN MIC. [6] Rad, P.F Advocating a Deliverable-Oriented Work Breakdown Structure, Cost Engineering, 41(12): [7] Rad, P.F. & Cioffi, D.F Work and Resource Breakdown Structures for Formalized Bottom-Up Estimating, Cost Engineering, 46(2): [8] Rouse, M Requirements analysis (requirements engineering) [Online]. Search Software Quality. Available from: [Accessed: 06 September 2012]
6 412 Computer Science & Information Technology (CS & IT) [9] Schach, S.R Classical and Object-Oriented Software Engineering. 3rd ed. USA: Irwin. [10] Schwalbe, K Information Technology Project Management. 6th ed. USA: Thomson Course Technology. [11] U.S.A Government Accountability Office Work Breakdown Structure Chapter 8. [12] Zhao, J.G Significance of WBS in Contigency Modeling, AACE International Transactions. AUTHORS Robert Hans is a lecturer at Tshwane University of Technology (TUT), where he teaches project management as well as systems analysis and design subjects. He has worked for many years in the ICT industry before joining TUT three years ago. Robert has a master s degree in business leadership (MBL) from University of South Africa Graduate School of Business Leadership. He received a distinction for his research paper in his master s degree. He is currently studying for a doctoral degree with the University of South Africa. So far Robert has published two peer-reviewed journal papers and conference proceedings in project management.
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION
WORK BREAKDOWN STRUCTURE: A TOOL FOR SOFTWARE PROJECT SCOPE VERIFICATION Robert T. Hans Software Engineering Department, Tshwane University of Technology, Pretoria, South Africa [email protected] ABSTRACT
IT/Software Project Management Core Functions
IT/Software Project Management Core Functions By: Prof. Dr. Eng. Ghazy Assassa, CMC-IMC Certified Management Consultant, Institute of Management Consultancy, UK Email: [email protected] Mobile: 0502862400
What is Project Scope Management? Project Scope Management Summary. Project Scope Management Processes
What is Project Scope Management? Chapter 5 Project Scope Management October 27, 2008 Scope refers to all the work involved in creating the products of the project and the processes used to create them
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
PROJECT SCOPE MANAGEMENT
5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
SCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
The purpose of this course is to provide practical assistance for defining and managing project scope.
Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step
Project Planning. Project Scope. Work Breakdown Structure.
Chapter 5 Project Planning. Project Scope. Work Breakdown Structure. 1 Objectives Acquire a general understanding of the parts of the project management plan Understand the importance of discovering and
Introduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
TOWARDS A FRAMEWORK FOR PROJECT MANAGEMENT INTELLIGENCE (PMInt) Robert Hans PhD Student at University of South Africa Supervised by Prof E Mnkandla
TOWARDS A FRAMEWORK FOR PROJECT MANAGEMENT INTELLIGENCE (PMInt) Robert Hans PhD Student at University of South Africa Supervised by Prof E Mnkandla AGENDA Background Purpose of the study Foundation of
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Advanced Project Management Training Course
Advanced Project Management Training Course 1-34 Advanced Project Management Crea/ng the Scope Baseline 2-34 Crea/ng the Scope Baseline Module 1 Introduction Module 2 Creating the Project Charter Module
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
MGMT 4135 Project Management. Chapter-4. Defining the Project
MGMT 4135 Project Management Chapter-4 Where We Are Now Chapter-4 Steps for Chapter-4 Step-1 Scope Step-2 Establishing Project Priorities Step-3 Creating the Work Breakdown Structure Step-4 Integrating
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Software Engineering CSCI 4490. Lesson 9 Project Management Part 1- Planning & Estimating. February 23, 2015
Lesson 9 Project Management Part 1- Planning & Estimating February 23, 2015 Projects and Project Managers Project a [temporary] sequence of unique, complex, and connected activities having one goal or
DATABASE DEVELOPMENT LIFE CYCLE
DATABASE DEVELOPMENT LIFE CYCLE Pranshu Gupta 1 Ramon A. Mata-Toledo 2 Morgan D. Monger 3 Abstract A software development life cycle model (SDLC) consists of a set of processes (planning, requirements,
Manual on Training Preparation
Project on Improvement of Local Administration in Cambodia Three Steps of Training Preparation Step 1: Work Breakdown Structure Step 2: Schedule Step 3: Budget Table of Contents Three Steps of Training
An Introduction to Project Management
An Introduction to Project Management The purpose of this briefing paper is to introduce key project management terms and concepts to provide a common language for discussion, including what is: A project
Chapter 5: Project Scope Management. Information Technology Project Management, Fifth Edition
Chapter 5: Project Scope Management Information Technology Project Management, Fifth Edition What is Project Scope Management? Scope refers to all the work involved in creating the products of the project
Project Management Institute STANDARD
Project Management Institute STANDARD Project Management Institute Practice Standard for Work Breakdown Structures Project Management Institute Practice Standard for Work Breakdown Structures Project Management
INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
PROJECT MANAGEMENT STUDY GUIDE
PROJECT MANAGEMENT STUDY GUIDE PROGRAMME : MBA Final Year CREDIT POINTS : 20 points NOTIONAL LEARNING : 200 hours over 1 semester Copyright 2013 MANAGEMENT COLLEGE OF SOUTHERN AFRICA All rights reserved,
http://www.io4pm.org IO4PM - International Organization for Project Management
THE ONLY BOOK CAN SIMPLY LEARN PROJECT MANAGEMENT! Page 1 Contents ABOUT THE AUTHOR... 3 WHAT IS PROJECT MANAGEMENT?... 5 ORGANIZATIONAL INFLUENCES AND PROJECT LIFECYCLE... 11 PROJECT MANAGEMENT PROCESSES...
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING
PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING PMI PMBOK & ESTIMATING 03-23-05 Christine Green, PMI PMBOK and Estimating EDS, Delivery
Chapter 3 Chapter 3 Service-Oriented Computing and SOA Lecture Note
Chapter 3 Chapter 3 Service-Oriented Computing and SOA Lecture Note Text book of CPET 545 Service-Oriented Architecture and Enterprise Application: SOA Principles of Service Design, by Thomas Erl, ISBN
How To Manage The Health Benefit Exchange At Mhix
Minnesota Health Insurance Exchange (MNHIX) 1.1.2 Project Charter Date: 09/21/2012 11/9/2012 12:10 PM Page 1 of 18 T A B L E O F C O N T E N T S 1. MNHIX Introduction... 3 1.1 MNHIX Scope... 4 1.2 Critical
Software Project Management. Objective. Course Objectives. Introduction to SPM
Software Project Management Lecture 01 Introduction to SPM 1 Objective Course Introduction (learning objectives) Course Contents & Grading Policy Motivation of Studying SPM What is Project What is Project
Expert Reference Series of White Papers. Intersecting Project Management and Business Analysis
Expert Reference Series of White Papers Intersecting Project Management and Business Analysis 1-800-COURSES www.globalknowledge.com Intersecting Project Management and Business Analysis Daniel Stober,
Project Management Concepts and Strategies
Project Management Concepts and Strategies Contact Hours: 24 Course Description This series provides a detailed examination of project management concepts and strategies. It discusses the seven components
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Chapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Defining and measuring project success
Defining and measuring project success Danie van der Westhuizen, Department Information Systems, Faculty of Business, University of Southern Queensland - Wide Bay Campus, Hervey Bay, Queensland, Australia,
PROJECT TIME MANAGEMENT
PROJECT TIME MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_time_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita
Metadata-Based Project Management System. A Case Study at M-Files Corporation Iulia Adomnita University of Tampere School of Information Sciences Computer Science M.Sc. Thesis Supervisors: Timo Poranen,
Answers to Review Questions
Tutorial 2 The Database Design Life Cycle Reference: MONASH UNIVERSITY AUSTRALIA Faculty of Information Technology FIT1004 Database Rob, P. & Coronel, C. Database Systems: Design, Implementation & Management,
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
INFORMATION BROCHURE. Masters and Doctor of Computing. (MComp & DComp) Applications for 2017 academic year
INFORMATION BROCHURE Masters and Doctor of Computing (MComp & DComp) Applications for 2017 academic year Contents INFORMATION BROCHURE... 1 Masters and PhD... 1 MCom and DCom: Informatics (Business Information
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
A Framework for Integrating Software Usability into Software Development Process
A Framework for Integrating Software Usability into Software Development Process Hayat Dino AFRICOM Technologies, Addis Ababa, Ethiopia [email protected] Rahel Bekele School of Information Science, Addis
A Case Study of the Systems Engineering Process in Healthcare Informatics Quality Improvement. Systems Engineering. Ali M. Hodroj
A Case Study of the Systems Engineering Process in Healthcare Informatics Quality Improvement By Ali M. Hodroj Project Report submitted to the Faculty of the Maseeh School of Engineering and Computer Science
Software Project Management I
Software Project Management I Dr. Jong Yih Kuo Dr. Chien-Hung Liu Computer Science and Information Engineering National Taipei University of Technology Course Schedule Time Topic Document 18:10~18:55 (45
Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
DEVELOPING REQUIREMENTS FOR DATA WAREHOUSE SYSTEMS WITH USE CASES
DEVELOPING REQUIREMENTS FOR DATA WAREHOUSE SYSTEMS WITH USE CASES Robert M. Bruckner Vienna University of Technology [email protected] Beate List Vienna University of Technology [email protected]
Applying the Work Breakdown Structure to the Project Management Lifecycle
Applying the Work Breakdown Structure to the Project Management Lifecycle Introduction Shelly A. Brotherton, PMP; Robert T. Fried, PMP; Eric S. Norman, PMP, PgMP Today, Project Managers are more frequently
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
Axiomatic design of software systems
Axiomatic design of software systems N.P. Suh (1), S.H. Do Abstract Software is playing an increasingly important role in manufacturing. Many manufacturing firms have problems with software development.
Project Management Process. Prepared by Jay Knape
Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems
Creating The Work Breakdown Structure By Kim Colenso, Managing Principal, Artemis Management Systems The Work Breakdown Structure (WBS) is the foundation for project planning and control. It is the connecting
IT4202: SOFTWARE PROJECT MANAGEMENT
: SOFTWARE PROJECT MANAGEMENT 1. OUTLINE OF THE SYLLABUS (Compulsory) Topic Minimum number of hours Introduction to Project Management 05 Project Planning 08 Project Scheduling 08 Project Cost Management
A WBS-Based Plan Changeability Measurement Model for Reducing Software Project Change Risk
A WBS-Based Plan Changeability Measurement Model for Reducing Software Project Change Risk Sen-Tarng Lai Abstract In software development process, it is necessary to face challenge for plan changes. In
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
Software Project Management Plan (SPMP)
Software Project Management Plan (SPMP) The basic template to be used is derived from IEEE Std 1058-1998, IEEE Standard for Software Project Management Plans. The following is a template for the SPMP.
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
STARTING A PROJECT. Sergey V. Nesterov MD, PhD, PMP
STARTING A PROJECT Sergey V. Nesterov MD, PhD, PMP QUESTIONS to ask at the start 1. What is the situation? 2. What do you need to do? 3. Why do you need to do it? 4. What will you do? 5. How will you do
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1
Chapter 4: Planning Projects, Part I (Integration, Scope, Time, and Cost Management) Slide 1 Introduction to Project Management Learning Objectives Describe the importance of creating plans to guide project
Project Management Office (PMO)
Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project
Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.
Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.5 hours Program Description The Advance Project Management Knowledge, Skills
7 Conclusions and suggestions for further research
7 Conclusions and suggestions for further research This research has devised an approach to analyzing system-level coordination from the point of view of product architecture. The analysis was conducted
Project Scheduling & Tracking
Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the
Making project management indispensable for business results. Project Management 101
Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of
ATTACHMENT B PROGRAM MANAGEMENT SERVICES BEXAR COUNTY FY 2007 - FY 2017 FLOOD CONTROL PROJECTS
ATTACHMENT B PROGRAM MANAGEMENT SERVICES BEXAR COUNTY FY 2007 - FY 2017 FLOOD CONTROL PROJECTS The following scope of services for program management is an effort to provide an encompassing but not all
WVU. PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members. Robert C. Byrd Health Sciences Center Chancellor s Office
WVU Robert C. Byrd Health Sciences Center Chancellor s Office PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members Fostering a culture of high purpose, accountability & accomplishment
Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision 7 - 7 -
Jefferson Science Associates, LLC 200 Organization Project Control System Manual Revision 7-7 - 200 Organization This section of the JSA Project Control System Manual describes the organizational elements
PROJECT AUDIT METHODOLOGY
PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC. Abstract. About PRINCE2
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC Abstract PMBOK is the recognized (de facto) standard of project management knowledge. In the UK and Europe, PRINCE2
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Classical Software Life Cycle Models
Classical Software Life Cycle Models SWEN 301 Trimester 1, 2015 Lecturer: Dr Hui Ma Engineering and Computer Science Lecture slides make use of material provided on the textbook's companion website Motivation
ICT Project Management. Software Project Planning By J. Ogutu
ICT Project Management Software Project Planning By J. Ogutu Overview Step Wise project planning framework Preparation of a software project plan Planning and scheduling the activities in software project
MIS 460 Project Management
Ursuline College Accelerated Program CRITICAL INFORMATION! DO NOT SKIP THIS LINK BELOW... BEFORE PROCEEDING TO READ THE UCAP MODULE, YOU ARE EXPECTED TO READ AND ADHERE TO ALL UCAP POLICY INFORMATION CONTAINED
Certificate In Project Management (CIPM)
Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Certificate In Project Management (CIPM) Course Overview The Certificate
The Key to a Successful KM Project
Introduction An integrated PKM methodology enables organizations to maximize their investments by ensuring initiatives are on time and within budget, while sharing project challenges and successes that
Java Programming (10155)
Java Programming (10155) Rationale Statement: The world is full of problems that need to be solved or that need a program to solve them faster. In computer, programming students will learn how to solve
Software Development Process by a Logical Approach to Quantify the Throughput by Balancing Time and Cost
IOSR Journal of Computer Engineering (IOSR-JCE) e-issn: 2278-0661,p-ISSN: 2278-8727, Volume 16, Issue 5, Ver. V (Sep Oct. 2014), PP 43-47 Software Development Process by a Logical Approach to Quantify
Project Management Planning
Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing
D6 INFORMATION SYSTEMS DEVELOPMENT. SOLUTIONS & MARKING SCHEME. June 2013
D6 INFORMATION SYSTEMS DEVELOPMENT. SOLUTIONS & MARKING SCHEME. June 2013 The purpose of these questions is to establish that the students understand the basic ideas that underpin the course. The answers
SOFTWARE PROJECT MANAGEMENT
SOFTWARE PROJECT MANAGEMENT http://www.tutorialspoint.com/software_engineering/software_project_management.htm Copyright tutorialspoint.com The job pattern of an IT company engaged in software development
Project Roles and Responsibilities Template
Purpose The purpose of this document is to provide a summary of the primary roles in the X project and the responsibilities associated with each role. A roles and responsibilities spreadsheet also maps
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
PROJECT PLAN FOR. Project Name Here
PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project
APM web briefing - Use of Product Breakdown Structures and Work Breakdown Structures
APM web briefing - Use of Product Breakdown Structures and Work Breakdown Structures Introduction Product Breakdown Structures and Work Breakdown Structures look very similar and both have important roles