Administrative Procedures (AP) for supply contracts and related services
|
|
|
- Ferdinand Warner
- 9 years ago
- Views:
Transcription
1 Administrative Procedures (AP) for supply contracts and related services Department Materials Team Report Administrative Procedures (AP) for supply contracts and related services Due by 24 March 2016 Document FP version 1.doc Date, version 24 March 2016, Our reference FPM Status Final 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 1 of 25
2 Preface The content of this specification was previously spread over multiple documents, such as Master Contracts, annees to Purchase Orders and specifications. Many of Gasunie's administrative requirements on topics such as contract management and standardization of engineering documents have not been documented so far. Gasunie s objective is to provide a comprehensive and transparent overview to Suppliers on all administrative procedures. Gasunie epects this overview to assist Suppliers in understanding "how Gasunie works". This shall accelerate alignment between Gasunie and the Supplier and lead to a first time right delivery N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 2 of 25
3 Contents Preface Scope and application Scope Application References Definitions and abbreviations Definitions Abbreviations Contract Management Requirements Quality Assurance and Control Order processing form Meetings and reporting Performance measurements Securities Changes to the Master Contract Changes at Gasunie's request Changes at the Supplier's request Determining the impact of the change Gasunie's approval Concession Requests Spare parts and support Sub-Suppliers Epediting Requirements Etended manufacturing progress reporting Standard manufacturing progress reporting Engineering Requirements Gasunie Technical Standard (GTS) Standard engineering and operating documents package Inspection Requirements Gasunie client inspection Gasunie's UI ITP Inspection at the Supplier's premises Inspections at Gasunie's premises Transportation Requirements Central warehouse Deventer Other locations Invoicing Requirements Payment N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 3 of 25
4 9.2 Transaction method ANNEX A Pre Production meeting ANNEX B Flow Chart Changes to the Master Contract ANNEX C Change Request ANNEX D Change Impact N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 4 of 25
5 1 Scope and application 1.1 Scope This specification describes the administrative procedures for the Supplier and Gasunie for supply contracts and related services. These administrative procedures are only applicable to articles that have an article number. A number of subclauses from the General Conditions (AV) are elaborated in more detail in this specification. The scope of this specification is the process of contract management, epediting, engineering, inspection, transportation and invoicing. This process starts at signing the Master Contract and/or issuing the Purchase Order. This process ends at payment of the invoice. The scheme below shows the process and the activities. Master Contract / Purchase Order Start Engineering Production By Supplier Inspection Contract Management Epediting Transport Invoicing End 1.2 Application The sections in this specification apply to Master Contracts and/or Purchase Orders. The table below shows which section is relevant for the Master Contract and/or Purchase Order N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 5 of 25
6 Master Contract Purchase Order Fout! Verwijzingsbron niet gevonden. Fout! Verwijzingsbron niet gevonden. Fout! Verwijzingsbron niet gevonden. Fout! Verwijzingsbron niet gevonden N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 6 of 25
7 2 References This specification is subject to the requirements of the Gasunie specifications mentioned in this clause. The applicable version can be found in the Purchase Order. FP_AVI08 GTS_A-116 GTS_A-117 MSA-25-E GTS_RED- GTS_REQ-003 GTS_W-089 General conditions for supply contracts and related services. N.V. Nederlandse Gasunie, with registered office in Groningen. Change Request Change impact Transport, packing and marking Requirements for Documents (RED) Engineering and operating documents transmittal Application form Pressure Equipment Directive 97/23/EC 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 7 of 25
8 3 Definitions and abbreviations 3.1 Definitions In this specification the following definitions are applicable: Change Impact Change Request Concession Request Delivery Master Contract Manufacturing Data Book Lump sum Purchase Order Technical Requirements Supplier s estimate of the impact of the Change Request. A Gasunie countersigned Change Impact form is a change order in accordance with article 5.7 of the AV. See GTS_A-117 for the applicable form. A request to change to the scope and/or method of carrying out the Delivery in accordance with article 5.1 of the AV. Gasunie and Supplier are allowed to submit a Change Request. See GTS_A-116 for the applicable form. Supplier s request to deviate from the Technical Requirements. A Concession Request shall neither be subject to compensation by Gasunie nor a change to the Master Contract and/or Purchase Order. See AV See AV See GTS_RED- A fied amount for which the Delivery is supplied. See AV Drawings, specifications (amongst others GTS) and other binding documents. Note: Technical Requirements are not Purchase Orders, award reports, clarification meeting reports, on-site scoping meeting reports, project conditions, Master Contracts and general conditions. 3.2 Abbreviations In this specification the following abbreviations are applicable: AV CE E&I GTS ITP KIWA MT NCR NDE PED PPM PQR PT PWHT General conditions for supply contracts and related services. N.V. Nederlandse Gasunie, with registered office in Groningen. Conformité Européene (European conformity) Electro & Instrumentation Gasunie Technical Standard Inspection and Test Plan (in various specifications still shown as "Quality Inspection Plan" or "QIP") Keurings Instituut voor Waterleiding Artikelen (Dutch Waterworks Testing and Research Institute) Magnetic particle testing Non-Conformity Report Non-Destructive Eamination Pressure Equipment Directive Pre Production Meeting Procedure Qualification Record Penetrant Testing Post Weld Heat Treatment 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 8 of 25
9 QC RED RT UI UT WPS WTB Quality Control Required Engineering Documents (Requirements for Documents) Radiographic Testing User Inspectorate Ultrasonic Testing Welding Procedure Specification Werktuigbouw (mechanical engineering) 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 9 of 25
10 4 Contract Management Requirements Contract management is performed by Gasunie department "Procurement". All communication shall be sent to the relevant purchaser that is stated on the Master Contract or Purchase Order. The purchaser is Gasunie's authorized representative for all contract management issues. 4.1 Quality Assurance and Control Gasunie has the right to assess whether the Supplier meets the requirements of the Master Contract and/or Purchase Order by either audit, surveillance, inspection or documentation reviews or participation in Supplier-led audits, inspections or surveillance activities. The Supplier is required to cooperate with the above. If the Supplier does not meet the requirements of the Master Contract and/or Purchase Order, the Supplier shall send an improvement plan for approval to Gasunie. The Supplier shall eecute the agreed improvement plan. 4.2 Order processing form When Gasunie performs epediting (see clause 5), the Supplier's order reference shall be submitted. The Supplier shall, within ten working days after receipt of the Purchase Order: complete the order processing form enclosed with the hard-copy Purchase Order; submit the Supplier's order reference by to the purchaser when an electronic Purchase Order is issued. 4.3 Meetings and reporting The Supplier shall provide an adequate facility for Gasunie for audits, inspection visits, business review meetings etc.. At Gasunie's request, the Supplier shall attend interface meetings with third parties. The Supplier shall attend all meetings at no cost to Gasunie. The Supplier shall record minutes of all meetings unless otherwise instructed by Gasunie, and issue these minutes of meetings to Gasunie within five working days after the meeting for review and approval. The Supplier shall maintain an action log of all items arising from meetings and report status on same. 4.4 Performance measurements Gasunie shall conduct performance measurements, such as delivery time and inspection findings to determine the Supplier's performance N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 10 of 25
11 The average percentage on time delivery is measured in accordance with: O D T Where: D: Average percentage on time delivery O: Number of line items on time measured in accordance with the Incoterms definition in the Master Contract and/or Purchase Order In case of partial deliveries the last delivery determines the delivery date for the line item T: Total number of line times issues If there is not a Master Contract then the minimum average percentage on time delivery measured over every line item in the Purchase Order is 80 %. Gasunie requires higher delivery reliability for Purchase Orders issued under Master Contracts. The delivery reliability requirements are given in table 1. Table 1: Delivery reliability requirements Purchase Orders under Master Contracts Average % on time delivery (D) measured per contract year First contract year > 80 % Second contract year > 90 % Third and further contract years > 95 % The quality requirements are under development and are to be agreed between the Supplier and Gasunie. 4.5 Securities This paragraph is only applicable when securities are agreed in the Master Contract and/or Purchase Order. The Supplier shall submit signed originals of the securities, such as performances bonds, advance payment bonds, parent company guarantees, within ten workings days of receiving the signed Master Contract and/or Purchase Order. 4.6 Changes to the Master Contract A flow chart of the changes to the Master Contract is in Anne B Changes at Gasunie's request If Gasunie wishes to submit a Change Request, Gasunie shall describe the change to the Delivery on the Change Request form in accordance with GTS_A Changes at the Supplier's request If the Supplier wishes to submit a Change Request, this shall be notified to Gasunie within five working days of occurrence by using the Change Request form in accordance with 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 11 of 25
12 GTS_A-116. If the Supplier fails to notify Gasunie within five days, Gasunie is not obliged to compensate for such events. Gasunie shall inform the Supplier within five working days after receipt of the request on its decision to proceed with the determining the impact of the change. If the Change Request is to be clarified, the Change Request shall be re-submitted in accordance with this subclause Determining the impact of the change Within five workings days of the receipt of Gasunie's Change Request or Gasunie's approval of the Supplier's Change Request, the Supplier shall complete a Change Impact form in accordance with GTS_A-117. The Change Impact form shall be accompanied by clear and complete information supporting: the price and delivery time; any impact on the quality of the Delivery, such as technical changes or performance. Within five workings days after receipt of the Change Impact, Gasunie shall decide if the Supplier shall submit further clarification to the Change Impact. If the Change Impact is to be clarified the Change Impact shall be re-submitted within five working days. If Gasunie considers the Change Impact to be sufficiently elaborated, Gasunie decides within five working days after receiving the Change Impact if the change is to be implemented Gasunie's approval Fied price If the Change Impact form is accepted on the basis of fied price, Gasunie shall countersign the Change Impact form within five working days of receipt of the Change Impact form. Unit price/rates If the Change Impact form is accepted on the basis of unit rates, Gasunie shall issue a maimum price limit to the change. The Supplier shall issue weekly reports on the progress of the implementation of the change stating as a minimum: number of units used and forecasted; actual and forecasted price of the change. If the Supplier eceeds the price limit, Gasunie shall: not compensate any performance that eceed the price limit; if it approves the higher price limit, request the Supplier to submit a revised Change Impact form in accordance with subclause Concession Requests Supplier shall complete a Concession Request to deviate from the Technical Requirements as soon as the Supplier becomes aware of the deviation, but ultimately before final inspection of the Delivery. The Supplier shall use its own document. The Supplier shall submit a Concession Request supported with the required information to Gasunie that addresses as a minimum: Master Contract, Purchase Order, item number, material number, serial number; 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 12 of 25
13 reference to the specification, not only the document but also the subclause of the specification; description of the Concession Request, including reason(s) (with detailed analysis) for deviating from the requirement; actions to improve (if any); any ITP that needs to be revised; any standard engineering and operating documents that need to be revised, and; the Supplier's request for approval of the Concession Request. Gasunie shall within 15 working days of receiving the request for concession: decide if the request for concession is approved; if approved, sign the Concession Request and agree that the Concession Request is implemented. if rejected, return the rejected Concession Request and instruct the Supplier to comply to the Technical Requirements. 4.8 Spare parts and support Gasunie has the right to enter into a contract with the Supplier for the delivery of spare parts and support for a period of 10 years immediately after epiration of the Master Contract. The scope of this contract is the delivery of spare parts, services 1 and software. These spare parts, services and software do not require any modifications to the original delivery under the Master Contract. The Supplier shall deliver these spare parts, services and software under the same terms and conditions, at the same price level and within the same delivery time as the Master Contract. 4.9 Sub-Suppliers If the Supplier relies on sub-suppliers for: manufacturing of pressure containing parts; non-destructive testing; destructive testing; chemical analysis, and/or coating application, the Supplier is not allowed to change this sub-supplier without prior approval of Gasunie. 1 Services that can only be purchased from supplier for technical reasons and/or eclusive rights. Eamples of these services are support and repair services N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 13 of 25
14 5 Epediting Requirements Epediting is carried out by Gasunie department "Procurement; Logistics & Supply". All communication is to be sent to: Gasunie states in the Purchare Order what kind of epediting is applicable, this is: etended manufacturing progress reporting, or standard manufacturing progress reporting. Gasunie has the right to request a PPM to align with the Supplier on the epediting programme. For the agenda of the PPM reference is made to anne A. 5.1 Etended manufacturing progress reporting The Supplier shall submit a manufacturing schedule/plan and progress report detailing the applicable milestones below: 1. engineering documents sent; 2. engineering documents approved; 3. Inspection and Test Plan (ITP) sent; 4. Inspection and Test Plan (ITP) approved; 5. materials ordered; 6. materials received; 7. start assembly/production; 8. inspection; 9. coating; 10. final inspection; 11. shipment of product and documents. The Supplier shall submit the aforementioned progress report every two weeks, starting ten days after receipt of the Purchase Order. Upon agreement between Gasunie and the Supplier, the aforementioned standard progress reporting can be relaed to the following lower frequency if the delivery performance meets the requirements of subclause 4.4: monthly; monthly up to eight weeks before the contract date, afterwards - biweekly. Gasunie retains the right to depute its representative(s) to visit the Supplier for the field epediting of the Purchase Order, and/or to request additional information to verify the progress of manufacturing, and/or to increase the frequency of progress reports to every week. 5.2 Standard manufacturing progress reporting The Supplier shall confirm the delivery date two weeks before the planned delivery date, when standard epediting is applicable. The Supplier is obliged to inform Gasunie of any delay as soon as the Supplier becomes aware of it N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 14 of 25
15 6 Engineering Requirements Engineering is carried out by Gasunie department "Operations & Projects; Technology". All required engineering and operating documents are specified in the RED form (GTS_RED) that is included in the Master Contract and/or Purchase Order. Gasunie has the right to request a PPM to align with the Supplier on the engineering and operating documents. For the agenda of the PPM reference is made to anne A. 6.1 Gasunie Technical Standard (GTS) When a GTS is applicable, the applicable version can be obtained at [email protected]. 6.2 Standard engineering and operating documents package This subclause is only applicable when Gasunie and Supplier agreed in the Master Contract that a standard engineering and operating documents package is to be supplied. Gasunie shall issue a separate Purchase Order for standardization of these documents under the Master Contract. Gasunie and the Supplier shall agree a delivery and review schedule of the standardized engineering and operating documents as listed in the relevant RED form. As soon as Gasunie approves this standard engineering and operating documents package, the Supplier is released from submitting the engineering and operating documents for each individual Purchase Order that is issued under the Master Contract. After Gasunie's approval of a Change Impact (subclause 4.6.4) that requires a revised standard engineering and operating package, the Supplier is responsible for submitting the revised standard engineering and operating package within ten working days of this approval. After Gasunie's approval of a Concession Request (subclause 4.7) that requires a revised standard engineering and operating documents package, the Supplier is responsible for submitting the revised standard engineering and operating package within ten working days of this approval N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 15 of 25
16 7 Inspection Requirements Inspection is carried out by Gasunie department "HSE; Verification & Inspection" or by a representative acting for and on behalf of Gasunie. All ITPs and inspection invitations are to be sent to: [email protected]. Gasunie has the right to request a PPM to align with the Supplier on the inspection requirements. For the agenda of the PPM reference is made to anne A. 7.1 Gasunie client inspection Gasunie performs client inspections. These client inspections: are performed in accordance with the Technical Requirements; consist of a review of other specified requirements (PED, KIWA, design codes and the like) and additional documents. 7.2 Gasunie's UI If stated in the Technical Requirements, Gasunie performs Notified Body inspections in accordance with PED article 14. When Gasunie acts as a UI, Gasunie shall also perform inspection as a client (subclause 7.1). The Supplier needs to use form GTS_W-089 when the UI shall be specified. The ITP shall have a UI column and a client column. Both roles can have different Hold, Witness and Review points. An inspector acting for and on behalf of Gasunie cannot perform the UI activities. 7.3 ITP The Supplier shall submit an ITP in accordance with the RED form (GTS_RED-) that is included in the Master Contract and/or Purchase Order. Gasunie strives to establish a standard ITP that covers the scope of a Master Contract. As soon as Gasunie approves the ITP for Master Contract materials, the Supplier is released from submitting ITPs for each individual Purchase Order that is issued under the Master Contract. After Gasunie's approval of a Change Impact (subclause 4.6.4) that requires a revised ITP, the Supplier is responsible for submitting the revised ITP within ten working days of this approval. After Gasunie's approval of a Concession Request (subclause 4.7) that requires a revised ITP, the Supplier is responsible for submitting the revised ITP within ten working days of this approval N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 16 of 25
17 7.4 Inspection at the Supplier's premises The Supplier shall invite Gasunie in accordance with the ITP for the inspection at the Supplier's premises in writing at least 5 working days before Suppler's preferred inspection date. Gasunie has the right to request an alternative date. During inspection, the Manufacturing Data Book shall be shown to Gasunie. After witnessing the test in accordance with the ITP and reviewing the documentation, Gasunie shall make an inspection report. The report shall describe the activities the inspector performed with reference to the applicable procedures. The report is for Supplier and Gasunie use. After successful completion of the inspection, Gasunie shall stamp and sign the Manufacturing Data Book. The Supplier shall submit Manufacturing Data Book to Gasunie using: Gasunie shall check the Manufacturing Data Book on completeness within five working days. Gasunie shall issue a release note when the Manufacturing Data Book is received in good order. Note: The Supplier is not allowed to ship materials before the issue of Gasunie's final release note. 7.5 Inspections at Gasunie's premises The Supplier shall submit all required test and inspection documents to Gasunie before shipment of the material to Gasunie. The Supplier shall submit Manufacturing Data Book to Gasunie using: Note: The Supplier is not allowed to ship materials before these documents are submitted to Gasunie. Gasunie shall assess and approve/reject this inspection documentation within five working days. Gasunie's approval shall be notified by issuing a release note N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 17 of 25
18 8 Transportation Requirements The Delivery is received by Gasunie department "Procurement; Logistics & Supply". All communication is to be sent to: The transport, packing and marking requirements are stated in MSA-25-E. The Purchase Order contains the shipment location. This can either be the Central warehouse Deventer or other Gasunie locations. 8.1 Central warehouse Deventer The Supplier shall notify Gasunie about a shipment at least five working days prior to the desired delivery date if the Delivery is: pipe; more than 5 europallets or europallet places; heavier than 5000 kg; to be unloaded by crane; a Delivery that cannot be unloaded by Gasunie's standard unloading methods (see below). Gasunie's standard unloading methods are: A fork-lift truck for loads up to 5000 kg; A crane for loads of more than 5000 kg and/or with specific lifting instructions; A crane with a vacuum system for pipes supplied by open trailer, for pipes with a diameter of up to and including DN 450 and a maimum weight of 2000 kg per pipe. Gasunie's pipe unloading capacity is given in table 2 Table 2: Pipe unloading capacity Pipe diameter (DN) Number of truckloads per half day Unloading of pipe is done in the afternoon. Pipe cannot be unloaded in cold weather conditions, such as snow and frost. The Supplier's shipment notification shall contain as a minimum: name of the Supplier; Purchase Order number and position; Volume of the consignment (# pallets or # kg); Unloading instructions for the articles; Release note (in case "Inspection at the suppliers premises" is applicable); Proposed date of delivery and whether the Delivery shall be in the morning (08:00-12:00 a.m.) or afternoon (13:00-16:00 p.m.) N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 18 of 25
19 Gasunie shall confirm the proposed date no later than the net day. Gasunie has the right to request an alternative date. 8.2 Other locations As unloading facilities differ per Gasunie location, the Supplier shall notify the relevant Gasunie shipment location at least five working days prior to the desired delivery date, if the shipment cannot be unloaded manually. The contact details of this location shall be stated in the Purchase Order. The Supplier shall also notify the epediting department at about the shipment. Supplier's shipment notification shall contain as a minimum: name of the Supplier; Purchase Order number and position; release note; volume of the consignment (# pallets or # kg); unloading instructions for the articles; proposed date of delivery and whether the Delivery shall be in the morning (08:00-12:00 a.m.) or afternoon (13:00-16:00 p.m.). Gasunie shall confirm the proposed date no later than the net day. Gasunie has the right to request an alternative date N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 19 of 25
20 9 Invoicing Requirements Invoice handling is carried out by Gasunie's Corporate Service Centre (Accounts Payable Department). All communication is to be sent to: 9.1 Payment Article 7.1 of the General conditions for supply contracts and related services is not applicable and replaced by: After receipt at the shipment location (see clause 8) accompanied with a release note (when inspection is applicable), the Supplier charges the amount stated on the Purchase Order. 9.2 Transaction method The Supplier shall send invoices to: NV Nederlandse Gasunie Attn: Accounts Payable Department P.O. Bo MA Groningen The Netherlands Or per [email protected] After implementation of Ariba, all transactions (from issuing the Purchase Order up to and including invoices) shall run via the Ariba Network. The Supplier shall pay a fee to Ariba to enable this. More information about the fee and the Ariba Network is to be found: N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 20 of 25
21 ANNEX A Pre Production meeting The objective of the PPM is to align on the eecution of the Purchase Order and/or Master Contract. All applicable documents mentioned in the RED form shall be submitted for approval to Gasunie three working days before start of the PPM. During the PPM these documents shall be further clarified. After the PPM the Supplier shall re-submit the documents for approval including changes. A.1 Agenda This agenda is a standard agenda. Some items may not be relevant for the Purchase Order and/or Master Contract. Introduction Introduction of attendees Determination of applicable agenda items Minutes of Meeting to be done by Supplier Workshop tour Master Contract / Purchase Order review Scope of supply Document review (availability, latest revisions, deviations, eclusions) Delivery date/place Performance measurements Status securities Status changes Status Concession Requests Status spare parts and support Engineering status Drawings/data sheets/red Procedures Incoming material Re-stamping Welding/Repair welding NDE (RT, UT, MT, PT) PWHT Hydrostatic/leak test Functional test WTB and or E&I Painting/coating Marking/Shipping/Transport (MSA-25-E) Operating documents Material status (incl. subcontracted work) Subcontracting of work (welding, forming, assembly, PWHT, painting/coating) Inspection suborders 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 21 of 25
22 Inspection Quality Control Department Organisation of QC Lines of communication Contact persons Other: Third party inspection Qualification of personnel Welders' qualifications WPS/PQR Qualification Production test plates (incl. re-tests) Material requirements NDE company / Qualifications Facilities for visiting inspectors RED form CE marking Manufactures Quality System NCR, concession procedure, inspection reports, release notes Manufacturing Data Book (according to RED form) Inspection and Test Plan/Inspection invitations Epediting Reporting requirements Engineering status Fabrication status (production schedule) Transport Any other Business Progress meetings (Periodic) Evaluation of this meeting Summary/actions? 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 22 of 25
23 ANNEX B Flow Chart Changes to the Master Contract Occurrence of a Change GTS A-116 by Gasunie Supplier requests change Supplier determines the impact of change request Supplier determines the impact of change request GTS A-116 by Supplier GTS A-117 by Supplier Gasunie assesses the impact of change Yes Impact to be clarified No Change accepted No GTS A-117 rejected by Gasunie Yes GTS A-117 approved by Gasunie 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 23 of 25
24 ANNEX C Change Request Gasunie Technical Standard Doc. : Version : Change Request Date : Page : 24 of 25 From company: CR ref: contact: Date To company: Master Contract contact: Purchase Order Scope of the Change Request Supplier shall ensure that: Reference of applicable contract document Requested implementation date Epected impact to price Epected impact to delivery date Epected impact to Inspection and Test Plan Status of Change Request submitted approved rejected withdrawn company: contact: date: company: contact date: Signature Signature 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 24 of 25
25 ANNEX D Change Impact Gasunie Technical Standard Doc. : Version : Change Impact Date : Page : 25 of 25 From Supplier: CR ref: contact: Date To Gasunie: CI ref: contact: Date Impact of the Change Request Requested implementation date Confirmed impact to price Lump sum Unit rate Confirmed impact to delivery date Confirmed impact to Inspection and Test Plan Suplier: contact: date: Signature Status of Change Impact submitted approved rejected withdrawn Gasunie: Contact date: Signature Attachments: 2016 N.V. Nederlandse Gasunie, Groningen, kenmerk FPM Page 25 of 25
ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary
Page 1 / 9 ABSTRACT This document is the Section F to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES
1.0 SCOPE CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES This document establishes the minimum quality program requirements for a contractor providing equipment, material, and construction
MEDFORD FABRICATION CSC, INC. Quality System Manual. Date of issue: 03/25/2010 Revision : F
MEDFORD FABRICATION CSC, INC Quality System Manual Date of issue: 03/25/2010 Revision : F Table of Contents System Description 1.0 Introduction 2.0 Company Quality Policy 3.0 Organization Charts 4.0 Quality
Supplier Quality. Assurance Provisions. Manual. SQAP-001 Rev. E
9060 WINNETKA AVENUE NORTHRIDGE, CA 91324 USA Supplier Quality Assurance Provisions Manual SQAP-001 Revision E Page 1 of 14 Table of Contents 1 General Requirements... 4 1.1 Supplier Control... 4 1.2 Supplier
Regulations for the certification of environmental management systems in conformity with UNI EN ISO 14001:2004
Regulations for the certification of environmental management systems in conformity with UNI EN ISO 14001:2004 00 24/04/2013 Annulla e sostituisce il documento Regulations for the certification of environmental
STATEMENT OF WORK (SOW) On-Call Certified Welding Inspections and Nondestructive Testing
1.0 INTRODUCTION Colorado Springs Utilities (UTILITIES) is seeking qualified firms to provide verification welding inspection services, nondestructive testing services, and technical reporting to Colorado
Quality Assurance Manual. QAM-2013-Rev2
QAM-2013-Rev2 President s Policy and Authorization of Quality Control The management system for the Steel Structural Fabrication of Pinnacle Industrial Services entrusted through furnishing high quality
Regulations for certification of quality management systems
Regulations for certification of quality management systems 00 24/04/2013 Annulla e sostituisce il documento Regulations for certification of quality management systems in rev. 14 SG DIR AD Rev. Data Descrizione
Supplier Quality Requirements (SQR) for External Process and/or Product Providers
Supplier Quality Requirements (SQR) for External Process and/or Product Providers Document Revision History Revision No Revision Date Revision Description Approved By Apr 2, 2 Initial Release Joel Sodowsky
Purchase Order Clauses and Conditions
Purchase Order Clauses and Conditions All purchase orders for materials, special processes, machining and fabrication services and end items are subject to the following requirements: General Requirements:
Supplier Quality Assurance Requirements Manual
12716 EAST PINE STREET TULSA, OK 74116 Supplier Quality Assurance Requirements Manual Approved: Mike Collins Quality Assurance Manager Precise Machining & Manufacturing 1 Record of Revisions Revision D
Logistics Agreement. between. SMA Solar Technology AG Sonnenallee 1 34266 Niestetal Germany. hereinafter referred to as SMA. and.
between SMA Solar Technology AG Sonnenallee 1 34266 Niestetal Germany hereinafter referred to as SMA and Supplier hereinafter referred to as Supplier jointly referred to as Parties Version 2 2014-09-18
Quality Assurance Requirements. For. Pratt & Whitney/Space Propulsion, Chemical Systems Division
Quality Assurance Requirements For Pratt & Whitney/Space Propulsion, FORM 06.13.02.02 (REV. 6) Page 1 of 14 Table of Contents SECTION I QUALITY SYSTEMS REQUIREMENTS... 5 1. QUALITY ASSURANCE PROGRAM...
Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015
Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 For PROJECT : Renovation and Repair of Atlanta Jewish Academy
JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management
JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project
ONTIC UK SUPPLIER QUALITY SURVEY
MAIL-IN / ONSITE This report is intended to furnish data relative to the Suppliers capability to control the quality of supplies and services furnished to Ontic UK. Please complete this Survey and return
Product Order Quality Requirements Meggitt (Orange County), Inc.
Product Order Quality Requirements Meggitt (Orange County), Inc. Reference QP8-051, Purchase Order Quality Requirements QP8-055, Review/Control Supplier Documentation PP-401, Quality Assurance Codes 50-2-351,
NON-DESTRUCTIVE TESTING FULL SCOPE OF INTEGRATED NDT SERVICES
NON-DESTRUCTIVE TESTING FULL SCOPE OF INTEGRATED NDT SERVICES RIGHT SERVICE MAXIMUM RETURN Whether it is in fabrication, pipe manufacturing, pipeline, plant construction, chemical, petrochemical plants,
GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059
QUALITY MANUAL GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059 Distribution: Position Location Copy # President / CEO Office 1 Operations Manager Office 2 Quality Assurance Office
Ege Fren Ege Fren San. ve Tic. A.Ş.
Page : 1 / 8 1. Purpose: This manual is formed in order to create a business environment based on a partnership understanding with our suppliers, determine and develop our relationships in this context
New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification
New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification Revision - New Program Quality Requirements for Suppliers Rev.
Quality System Manual
Chalmers & Kubeck, Inc. Quality System Manual ISO 9001:2008 Control #:00 Rev. 4 (02-01-11) Chalmers & Kubeck, Inc. Quality System Manual Scope Chalmers & Kubeck Inc. is a job shop that performs new manufacturing
GARDNER AEROSPACE SUPPLIER QUALITY REQUIREMENTS MANUAL
GARDNER AEROSPACE SUPPLIER QUALITY REQUIREMENTS MANUAL Issue Number: 1 Issue Date: 12/9/14 1 of 19 Contents Revision Summary... 4 1.0 Introduction... 5 2.0 Supplier Quality System Requirements... 6 3.0
DOCUMENT. General Purchase Conditions
1. Scope 1.1 These general purchase conditions (hereinafter the GPC ) shall apply to all kinds of materials, articles, products and services related to them, (hereinafter Products ), offered, sold or supplied
Change Notice Revision 2 adds a definition of NANDTB, and acceptance of the National Aerospace NDT Board of Australia.
Advisory Circular AC43-8 Revision 2 Non-destructive Testing 27 February 2015 General Civil Aviation Authority advisory circulars contain information about standards, practices, and procedures that the
ABTREX INDUSTRIES, INC. QUALITY MANAGEMENT SYSTEM MANUAL
ABTREX INDUSTRIES, INC. QUALITY MANAGEMENT SYSTEM MANUAL Project Quality Management System Status APPROVED Approved by KB Keith Byars, Vice President Owner KC Kevin Couvillion, Operations Manager Author
Annex of the Certificate (Page 1/4) Scope of Accreditation
Annex of the Certificate (Page 1/4) As a "Type A" Inspection Body Accreditation Nr: Address :Centrum İş Merkezi Aydınevler Sanayi Cad. No:3 Küçükyalı - Maltepe 34854 ISTANBUL / TURKEY Phone : +90 216 518
Guidelines for the Acceptance of Manufacturer's Quality Assurance Systems for Welding Consumables
(1987) Guidelines for the Acceptance of Manufacturer's Quality Assurance Systems for Welding Consumables 1. General 1.1 Introduction 1.1.1 The present guidelines are to serve as a supplement to the IACS
Helical Products Co., Inc.
Q01 GENERAL REQUIREMENTS 1. Supplier Responsibilities 1.1. Delivery Certification By delivering products or services on the Contract, the Supplier certifies that such products or services are in compliance
GE Power & Water. Supplier Handbook
GE Power & Water Handbook 1 DISCLAIMER The information in this handbook is provided for convenience of our suppliers and may be subjected to change from time to time without prior intimation. This document
General Rules for the certification of Management Systems
General Rules for the certification of Management Systems Effective from 19/11/2015 RINA Via Corsica 12 16128 Genova - Italy tel. +39 010 53851 fax +39 010 5351000 website : www.rina.org Technical rules
CLARK COUNTY DEPARTMENT OF BUILDING & FIRE PREVENTION 4701 W. Russell Road Las Vegas, NV 89118 (702) 455-3000 Fax (702) 221-0630
CLARK COUNTY DEPARTMENT OF BUILDING & FIRE PREVENTION 4701 W. Russell Road Las Vegas, NV 89118 (702) 455-3000 Fax (702) 221-0630 Ronald L. Lynn, Director/Building & Fire Official Samuel D. Palmer, P.E.,
Engineering Procurement Construction Quality Plan
Engineering Procurement Construction Quality Plan Index 1 Introduction... 4 1.1 Project Background... 4 1.2 Document Purpose... 4 1.3 Change Control... 4 1.4 Contract... 4 1.5 Quality system... 4 1.6 Distribution...
Sargent Controls & Aerospace 5675 West Burlingame Rd. Tucson AZ 85743 PHONE: (520) 744-1000 FAX: (520) 744-8054
Sargent Controls & Aerospace 5675 West Burlingame Rd. Tucson AZ 85743 PHONE: (520) 744-1000 FAX: (520) 744-8054 SUPPLIER EVALUATION CHECKLIST Date: Vendor: Address: City, State, Zip: Web Site: Prepared
TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION INTERSTATE TRANSPORTATION OF GOODS (FREIGHT) SERVICES PUBLICATION
TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION SPECIFICATION NO. TxDOT 9628622 INTERSTATE TRANSPORTATION OF GOODS (FREIGHT) SERVICES PUBLICATION This specification is a product of the Texas
GLOBAL INSPECTION AND CERTIFICATION
GLOBAL INSPECTION AND CERTIFICATION CONTENTS About us 3 Services 3 Lifting Equipment Inspection & Certification 3 Conventional & Advanced Non Destructive Testing (NDT) 4 Rig Inspection & Commissioning
Technical Notes NDT 001 Specific Requirements for Non- Destructive Testing Laboratories
ACCREDITATION SCHEME FOR LABORATORIES Technical Notes NDT 001 Specific Requirements for Non- Destructive Testing Laboratories Technical Notes NDT 001, Apr 14 The SAC Accreditation Programme is managed
Quality Management System General
Audit Date: Quality Management System General Requirement: 4.1 and 4.2.2-QMS General Verify Scope Comments/Evidence/Findings: Verify the Exclusions is applicable and justified How are the processes in
BASE CONSTRUCTION INC
BASE CONSTRUCTION INC 14252 CULVER DRIVE A-630 IRVINE,CA 92604-0326 OFFICE:949 387-3471 Shop 714 994 9563 CELL:949 735-5292 FAX:949 786-8753 QUALITY ASSURANCE and QUALITY CONTROL MANUAL 1 TABLE OF CONTENTS
Application for Approved (Overseas/Local) Third Party Inspection Agency for Lifting Equipment
Occupational Safety and Health Division 18 Havelock Road #03-02 Singapore 059764 Tel: 64385122 www.mom.gov.sg [email protected] Application for Approved (Overseas/Local) Third Party Inspection Agency
SUPPLIER QUALITY ASSURANCE REQUIREMENTS
SUPPLIER QUALITY ASSURANCE REQUIREMENTS The following supplier quality assurance requirements, referenced by number on the Purchase Order, are an integral part of each order placed by Continental Disc
Bogue Machine Company, Inc. Business Instruction
Bogue Machine Company, Inc. Business Instruction Document Title: Supplier Quality Control Requirements Document Number: Revision: Document Owner: Mark Bogue Backup Owner: Craig Bogue Parent Document: PURP-004,
Pressure Equipment Certification. Ensure the Conformity and Quality of Your Pressure Equipment. Worldwide. www.tuv.com/asme
INDUSTRIAL SERVICES PRESSURE EQUIPMENT CERTIFICATION Pressure Equipment Certification. Ensure the Conformity and Quality of Your Pressure Equipment. Worldwide. www.tuv.com/asme Worldwide Compliance of
New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification
New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification Revision A New Program Quality Requirements for Suppliers Rev.
GLOBAL AEROSPACE PROCEDURE
1 of 13 1. PURPOSE: This procedure establishes the minimum PPG Aerospace requirements for a Supplier's Quality Plan. These requirements pertain to the documentation and inspection/testing necessary to
14620 Henry Road Houston, Texas 77060 PH: 281-447-3980 FX: 281-447-3988. WEB: www.texasinternational.com QUALITY MANUAL
14620 Henry Road Houston, Texas 77060 PH: 281-447-3980 FX: 281-447-3988 WEB: www.texasinternational.com QUALITY MANUAL ISO 9001:2008 API Spec Q1, 9th Edition API Spec 8C 5 Th Edition MANUAL NUMBER: Electronic
Gulfstream Production Certificate Operations
SUPPLIER QUALITY ASSURANCE SYSTEM REQUIREMENTS SQAR 0001 REV D Supplier s Quality System David H. Trucksis Donald A. Strickland R. Christiansen PREPARED BY: REVIEWED BY: APPROVED BY: Robert W. Mullen Jr.
South East Europe (SEE) Implementation Manual
South East Europe (SEE) Implementation Manual Version 5.0 Date of approval (v1.2): 8 th May 2009 1 st amendment (v2.1): 7th July 2009 2 nd amendment (v3.1): 21 st January 2011 3 rd amendment (v3.2): 27
The Prophotonix (UK) Ltd Quality manual
The Prophotonix (UK) Ltd Quality manual Date: March 2014 Revision: D Sparrow lane, Hatfield Broad Oak, Herts, UK, CM22 7BA Tel: +44 (0)1279 717170 Fax: +44 (0)1279 717171 e-mail: [email protected] Page
2.2 Stipulations deviating from these conditions must be agreed in writing.
GENERAL PURCHASE CONDITIONS OF THE MEMBERS OF THE NEDERLANDSE VERENIGING VAN ZIEKENHUIZEN [NETHERLANDS ASSOCIATION OF HOSPITALS], ARCARES, GGZ NEDERLAND AND THE VERENIGING GEHANDICAPTENZORG NEDERLAND [ASSOCIATION
Quality Agreement Template
Quality Agreement Template Prepared by Dan O Leary Ombu Enterprises, LLC 3 Forest Ave. Swanzey, NH 03446 603-209-0600 This document is intended to form the basis for a Supplier Agreement. The document
General Description of The CMC- Services
STANDARD FOR CERTIFICATION No.1.1 General Description of The CMC- Services JANUARY 2013 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version The
Indiana Boiler and Pressure Vessel Safety Section Frequently Asked Questions
Indiana Boiler and Pressure Vessel Safety Section Frequently Asked Questions What are the licensing requirements for boiler operators? Answer: Indiana statute (IC 22-15-6) and administrative rules (680
Supplier Quality Requirements and Clauses
Supplier Quality Requirements and Clauses Supplier Quality Requirements General The following Quality Notes (QN01 through QN19) apply to and form a part of all Purchase Orders issued by Advanced Conversion
Guiding Principles for the contents of Particular Materials Appraisals (Version approved at the WGP on 21 November 2006)
PE- 03-28 - rev 5 21 November 2006 Page 1 of 5 Guiding Principles for the contents of Particular Materials Appraisals (Version approved at the WGP on 21 November 2006) Introduction A Particular Material
GUIDELINES FOR FOOD IMPORT CONTROL SYSTEMS
GUIDELINES FOR FOOD IMPORT CONTROL SYSTEMS SECTION 1 SCOPE CAC/GL 47-2003 1. This document provides a framework for the development and operation of an import control system to protect consumers and facilitate
Copies of this document shall be classified either as Controlled or Uncontrolled, and shall be identified as such on the cover sheet.
INTRODUCTION This document describes an inspection system broken down into four separate levels. When Inspection Level IV is invoked, this system meets the requirements of former MIL-I-45208A. The primary
Section 100 Contractor Quality Control Program
7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and
PPI/TZ Standard Quality Requirements for Suppliers -SQRS-
PPI/TZ Standard Quality Requirements for Suppliers -SQRS- AS9100, ISO 13485 and ISO 9001 Revision: November 16, 2015 For questions concerning Standard Quality Requirements for Supplier (SQRS), please contact
GE Power Electronics Business Total Quality Management for Suppliers
GE Power Electronics Business Total Quality Author: Reviewers: Contributors: Alessandro A. Cervone Technical Manager Component & Reliability Engineering Alicia Scott Title Erika Nannis Title Robert Roessler
VENDOR QUALIFICATION APPROVAL FORM
COMPANY INFORMATION: Company Name: Jet Aviation St. Louis, Inc. Address (Street, City, State) Other Property Locations: Website: Repair Station Certificate No. With Class Rating: Date of Last FAA Audit:
Component. Annex I 4.3-97/23 EC. Adopted by WPG: 07/09/2014 Adopted by CLAP: 07/09/2014
Guideline 7/25 CLAP FORM N 1 Version : 9 Keywords : Tube Welding Essential requirements Permanent joint Component Directive references: Annex I 3.1.2-97/23 EC Annex I 3.1.3-97/23 EC Annex I 4.3-97/23 EC
How To Accept A Delivery From A Customer
General Selling, Service, Delivery and Payment Conditions of BORGERS USA Corp., Vance, Alabama ( GSC ) (March 2015) 1. General Provisions These General Selling, Service, Delivery and Payment Conditions
ISO 9001 Quality Systems Manual
ISO 9001 Quality Systems Manual Revision: D Issue Date: March 10, 2004 Introduction Micro Memory Bank, Inc. developed and implemented a Quality Management System in order to document the company s best
Supply Chain Security Audit Tool - Warehousing/Distribution
Supply Chain Security Audit Tool - Warehousing/Distribution This audit tool was developed to assist manufacturer clients with the application of the concepts in the Rx-360 Supply Chain Security White Paper:
SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE
Community Development Permit Services SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE PROJECT NAME PROJECT ADDRESS PERMIT NUMBER CITY RECEIVED STAMP AND INITIALS Instructions: BEFORE
Turbo Resources International Quality Procedure
TURBO RESOURCES INTERNATIONAL QUALITY MANAGEMENT SYSTEM MANUAL APPROVALS: Revision : 46 Page : 1 of 53 TABLE OF CONTENTS INTRODUCTION 3 1. SCOPE 4 1.1 GENERAL 4 1.2 APPLICATION 5 2. NORMATIVE REFERENCE
Pharmaceutical Wholesaler Site Inspection Checklist
Pharmaceutical Wholesaler Site Inspection Checklist Date and time of inspection: Legal business name and plant name: Location (address): Phone number: Fax number: Email address: Web site URL: Contact Person:
Quality Supplier Requirements for Beckwith Electric Co., Inc.
Quality Supplier Requirements for Beckwith Electric Co., Inc. This Page Left Intentionally Blank To Our Valued Suppliers: One of the primary goals of Beckwith Electric is to provide the highest Quality
STEEL fabrication quality SySTEmS guideline
STEEL fabrication quality systems guideline Copyright 2002 by Canadian Institute of Steel Construction All rights reserved. This book or any part therof must not be reproduced in any form without written
Self-Audit Checklist
Page 1 Company Name: Date of audit: Date of last audit performed: Name of person performing self-audit: Signature: Name of person responsible for quality system: Signature: Number of non-compliances: Page
Quality Control Procedures QCP 5.4 Page 1 of 5
Quality Control Procedures QCP 5.4 Page 1 of 5 1.0 PURPOSE 2.0 SCOPE SOURCE INSPECTION To establish a system for Source Inspection of material supplied to Eaton Corporation, FSD, Euclid. This procedure
Quality Management System
LH Sleightholme Ltd, Westfield Works, Helperthorpe, Malton, North Yorkshire YO17 8TQ Quality Management System MANUAL ISO 9001:2008 This Quality Management System Manual has been issued on the authority
FAMI-QS Certification Rules for Operators. Rules for Operators
Rules for Operators TABLE OF CONTENTS 1. Application for certification and FAMI QS associate membership...2 2. Assessment of operators...3 2.1. Audit planning...3 2.2. Frequency of audits and re certification...5
VEHICULAR EQUIPMENT PURCHASE EXHIBIT. This Exhibit modifies the Terms and Conditions for Materials and Related Services:
VEHICULAR EQUIPMENT PURCHASE EXHIBIT This Exhibit modifies the Terms and Conditions for Materials and Related Services: The following definitions are added to DEFINITIONS of the Terms and Conditions. Contract:
KEBA 2014 We reserve the right to make technical modifications. No liability accepted for information provided. All rights reserved.
Supplier Handbook Contact address KEBA AG Headquarters, Gewerbepark Urfahr, A-4041 Linz phone: +43 732 7090-0, fax: +43 732 730910, e-mail: [email protected], www.keba.com KEBA Group worldwide Austria Germany
DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS
WELDING FABRICATOR CERTIFICATION SCHEME DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS 6 th Edition July 2012 Issued under the authority of the Governing Board for Certification All correspondence should
External Quality, Environment, Health & Safety Management Manual with Integrated Welding Engineering Manual
conferdo GmbH & Co. KG External Quality, Environment, Health & Safety Management Manual with Integrated Welding Engineering Manual of the company conferdo GmbH & Co. KG STAHLBAU OHNE GRENZEN STEELWORK
Supplier Requirements Manual M M 0 3
Supplier Requirements Manual M M 0 3 Conformance to this manual is a requirement for all of Merrill Technologies Group and Ranger s suppliers & subcontractors, unless otherwise specified on purchase orders.
Raad voor Accreditatie (Dutch Accreditation Council RvA) Assessment of Conformity Assessment Schemes
Raad voor Accreditatie (Dutch Accreditation Council RvA) Assessment of Conformity Assessment Schemes Document code: RvA-T033-UK Version 3, 28 februari 2014 A Rv A-Explanatory note describes the policy
QUALITY ASSURANCE MANUAL JPM OF MISSISSIPPI, INC.
QUALITY ASSURANCE MANUAL JPM OF MISSISSIPPI, INC. Hattiesburg, MS Revision E 01/19/11 Revised to ISO 9001:2008 on July 9, 2009 JPM OF MISSISSIPPI, INC. MANAGEMENT QUALITY POLICY It is the goal of JPM of
Quality Manual PA3-01-001
Rev 01C February 2008 2008, PhaseLink Corporation PhaseLink is the trademark of PhaseLink Corporation, www.phaselink.com CONTENTS 1. Purpose and scope:...3 1.1. Purpose:...3 1.2. Scope:...3 2. Introduction
Doc Edition Section Question Answer Q1 9th 3.1.6 / 5.6.1.1
Doc Edition Section Question Answer Q1 9th 3.1.6 / 5.6.1.1 In a recent API Q1 audit, my auditor interpreted API Spec Q1, Section 3.1.6 to mean that the distributor supplying plastic shrink wrap material
NABL NATIONAL ACCREDITATION
NABL 160 NABL NATIONAL ACCREDITATION BOARD FOR TESTING AND CALIBRATION LABORATORIES GUIDE for PREPARING A QUALITY MANUAL ISSUE NO. : 05 AMENDMENT NO : 00 ISSUE DATE: 27.06.2012 AMENDMENT DATE: -- Amendment
RG 7 Accreditation for Inspection Bodies Performing Non-Destructive Testing
This publication contains policy, recommendations and guidance applicable to UKAS accredited inspection bodies RG 7 Accreditation for Inspection Bodies Performing Non-Destructive Testing Contents Section
Supplier Quality Assurance
Supplier Quality Assurance Preface We strive to continually improve our process performance by meeting quality objectives. It is imperative that our suppliers operate under the zero defects and 100% on
GE Oil & Gas Quality Management System Sourcing Supplier Quality Requirements ARSB-O&G-001 Rev: 2.0
Approved By: Type name or written signature Arun Tv Global Quality Leader Livio Loschiavo Global QMS Leader Luca Palatiello Global Quality Operations & Process Leader Orlando Dean Supplier Quality Manager
Smart Meters Programme Schedule 2.5. (Security Management Plan) (CSP South version)
Smart Meters Programme Schedule 2.5 (Security Management Plan) (CSP South version) Schedule 2.5 (Security Management Plan) (CSP South version) Amendment History Version Date Author Status v.1 Signature
Surgi Manufacturing Quality Manual
Surgi Manufacturing Page 1 of 18 Approvals: QA: Eng. Mgt. : A Date: 18Aug98 1. Introduction... 4 1.1 Scope... 4 1.2 Purpose... 4 1.3 Authority... 4 1.4 Issue of the Manual... 4 1.5 Amendments... 4 1.6
ADMINISTRATIVE PROCEDURES
ADMINISTRATIVE PROCEDURES FOR SMALL BUSINESS CONSTRUCTION CONTRACTS HARRISBURG, PENNSYLVANIA MAY 2014 EDITION DEPARTMENT OF GENERAL SERVICES BUREAU OF CONSTRUCTION ADMINISTRATIVE PROCEDURES TABLE OF CONTENTS
Standard Practice for Quality Control Systems for Nondestructive Testing Agencies 1
Designation: E 1212 99 AMERICAN SOCIETY FOR TESTING AND MATERIALS 100 Barr Harbor Dr., West Conshohocken, PA 19428 Reprinted from the Annual Book of ASTM Standards. Copyright ASTM Standard Practice for
QUALITY POLICY MANUAL Document: 01-090000 Revision: E Effective Date: January 15, 2010
Section i INTRODUCTION QUALITY POLICY STATEMENT: The purpose of our business is to provide continuity of electrical power to keep businesses in business. We do this by helping clients solve their power
SQM-H. This Handbook is a summary of the processes and documents of the supplier quality management 1/13
SQM-H Supplier Quality Management Handbook MAHLE Behr - global This Handbook is a summary of the processes and documents of the supplier quality management 1/13 Scope of Application The Supplier Quality
Worship Facility Matching Grant Program 2010 Program Manual
Worship Facility Matching Grant Program 2010 Program Manual Chapter 1 Introduction TABLE OF CONTENTS 1 1 INTRODUCTION 4 1.1 DEFINITIONS... 4 1.2 PROGRAM GOALS... 4 1.3 PROGRAM PARTICIPANTS... 5 1.3.1 PROGRAM
QT-2 QUALITY MANUAL Written to the requirements of ASME NQA-1-2008 & 09a and 10 CFR Part 21. Revision: 14
QT-2 QUALITY MANUAL Written to the requirements of ASME NQA-1-2008 & 09a and 10 CFR Part 21 Revision: 14 SPRINGS FABRICATION, INC. ADVANCED TECHNOLOGY GROUP 2685 Industrial Lane Broomfield, CO 80020 Controlled
MSC Group Chain of Custody (CoC) Guidance for Non-Reduced Risk Groups
MSC Group Chain of Custody (CoC) Guidance for Non-Reduced Risk Groups 1. About this document This document is a non-normative guidance document intended to help companies understand CoC requirements. The
Supplier Quality Requirements F16 Program
ISRAEL AEROSPACE INDUSTRIES LTD. MILITARY AIRCRAFT GROUP, LAHAV DIVISION DOCUMENT IDENTIFIER : WF16Z/150901 Supplier Quality Requirements F16 Program RESTRICTION ON USE, DUPLICATION, OR DISCLOSURE OF PROPRIETARY
4.0 Receiving Process
4.0 Receiving Process Delivery of requested products or services marks a transition in the Purchase-to-Pay process from a purchasing activity to a payables activity. All purchases must be received to release