1 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. ASTM INTERNATIONAL (ASTM) ASTM D 4637 EPDM Sheet Used in Single-Ply Roof Membrane 1.2 SUBMITTALS Government approval is required for submittals with a G designation. Submit the following in accordance with Section SUBMITTAL PROCEDURES: SD-03 Product Data EPDM (Bearing) Sheet G EPDM Cover Strip G Membrane Cleaner G Primer G Lap Sealant G SD-08 Manufacturer s Instructions EPDM Cover Strip G Membrane Cleaner G Primer G Lap Sealant G Page 1 of 6
2 1.3 DELIVERY, STORAGE, AND HANDLING Delivery Deliver materials in their original, unopened containers or wrappings with labels intact and legible. Where materials are covered by a referenced specification number, the labels must bear the specification number, type, class, and shelf life expiration date where applicable. Deliver materials in sufficient quantity to allow continuity of work Storage Store and protect materials from damage and weather in accordance with manufacturer s printed instructions, except as specified otherwise. Keep materials clean and dry. Store and maintain liquid materials above 60 degrees F. Mark and remove damaged materials from the site. Use pallets to support and canvas tarpaulins to completely cover material stored outdoors. Do not use polyethylene as a covering. Locate materials temporarily stored on the roof in approved areas, and distribute the load to stay within the live load limits of the roof construction. Remove unused materials from the roof at the end of each days work Handling Prevent damage to edges and ends of roll materials. Do not install damaged materials in the work. Select and operate material handling equipment so as not to damage materials or applied roofing. Do not use materials contaminated by exposure or moisture. Remove contaminated materials from the site. When hazardous materials are involved, adhere to the special precautions of the manufacturer. 1.4 ENVIRONMENTAL REQUIREMENTS Do not install EPDM products during high winds or inclement weather, or when there is ice, frost, moisture, or visible dampness on the substrate surface, or when condensation develops on surfaces during application. Unless recommended otherwise by the EPDM sheet manufacturer and approved by the Contracting Officer, do not install EPDM sheet when air temperature is below 40 degrees F or within 5 degrees F of the dewpoint. 1.5 SEQUENCING Coordinate the work with other trades to ensure that cover strips are installed as the work progresses. Unless otherwise approved by the Contracting Officer, only cut as much of the existing EPDM roofing as can be sealed with new cover strips in the same work day. If EPDM membrane cuts are permitted to remain without permanent seals (cover strips) beyond the end of the work day, ensure that temporary protection measures are in place to preclude moisture intrusion or damage to the building or installed materials. Page 2 of 6
3 1.6 EXISTING ROOF AND WARRANTY The existing roofing in the area of the work is a loose laid and ballasted.060 inch thick Johns Manville EPDM membrane roofing system over ½ thick protection board and 3 inch thick (2 layers) of loose laid insulation board on a concrete deck supported by metal decking and sloped steel beams. The roofing system was installed in 1992 and is under warranty until Accordingly, all EPDM roofing work required by this specification and as indicated on the drawings shall be executed in a manner which maintains the current roof warranty. In the case of conflict between the requirements of this specification or the accompanying drawings and the manufacturer s requirements for maintenance of the roof warranty relative to the work to be done under this contract, the manufacturer s requirements shall take precedence. PART 2 PRODUCTS 2.1 MATERIALS EPDM (Bearing) Sheets Ethylene Propylene Diene Terpolymer (EDPM), ASTM D 4637, Type I, non-reinforced, inch nominal thickness. The minimum thickness must not be less than minus 10 percent of the specified thickness value. EPDM membrane thickness specified is exclusive of backing material on the EPDM membrane. Principal polymer used in manufacture of the membrane sheet must be greater than 95 percent EPDM EPDM Cover Strips EPDM Cover Strips shall be the self-adhering type and must be.060 inch minimum total thickness composed of cured EPDM with an integral full pressure sensitive adhesive backing, as recommended by the roof membrane manufacturer Membrane Cleaner Membrane cleaner shall be a type suitable for use on existing, weathered EPDM roofing and as recommended by the EPDM manufacturer Primer Primer shall be a type suitable for use on existing aged EPDM roofing and as recommended by the EPDM manufacturer. Page 3 of 6
4 2.1.5 Lap Sealant Edge Treatment Lap sealant shall be as supplied and recommended by the EPDM manufacturer. PART 3 EXECUTION 3.1 PREPARATION FOR ROOFING WORK Perform the following work and ensure the following conditions exist prior to the application of the roofing materials: a. Temporarily remove and store existing stone ballast and roof walkpads. Removals shall be as indicated and as needed to permit the proper application of the new EPDM cover strips and bearing sheets at the locations indicated. Existing stone ballast shall be removed by use of a gravel pusher or push broom. Use of rakes or shovels is not permitted. b. Neatly cut existing EPDM roofing and flashing at the locations indicated and remove and dispose of underlying protection board and roof insulation to the extent needed for installation of new wood sleepers and cants. c. Ensure that new pressure preservative treated wood sleepers and cants are securely fastened in place. Ensure that top surfaces of sleepers are flush with the top surface of the existing protection board on the roof. Ensure that cants are installed at the angle between the roof and concrete curb and that the angle of the cant is 45 degrees and the height of the vertical leg of the cant is not less than 3-1/2 inches or otherwise matches the existing cant. Ensure that warped or split wood has been replaced and that there are no cracks or end joints ¼ inch in width or greater. Ensure that all fasteners through sleepers and cants are properly set and that countersunk holes have been filled. d. Ensure substrate is sloped to provide positive drainage. e. Ensure surfaces to which new roofing materials are to be applied are rigid, clean, dry, smooth and free from cracks, holes and sharp changes in elevation. 3.2 APPLICATION Apply roofing materials as indicated and specified herein unless approved otherwise by the Contracting Officer Special Precautions Page 4 of 6
5 a. Do not dilute liquid materials unless specifically recommended by the materials manufacturer s printed application instructions. Do not thin liquid materials with cleaners used for cleaning EPDM sheet. b. Keep liquids in airtight containers, and keep containers closed except when removing materials c. Use liquid components within their shelf life period. Store at 60 to 80 degrees F prior to use. Mix and use liquid components in accordance with label directions and manufacturer s printed instructions. d. Provide clean, dry cloths or pads for applying membrane cleaners and cleaning of membrane. e. Do not use heat guns or open flame to expedite drying of primers. f. Require workmen and others who walk on the membrane to wear clean, softsoled shoes to avoid damage to roofing materials. g. Do not use equipment with sharp edges which could puncture the EPDM sheet EPDM (Cover Strips and Bearing Sheets) Provide watertight roof membrane strips and sheets free of contaminants and defects that might affect serviceability. Provide uniform, straight, and flat edges. Unroll EPDM membrane in position without stretching membrane. Inspect for holes. Remove sections of EPDM membrane that are damaged. Allow strips and sheets to relax a minimum of 30 minutes before adhering or application of subsequent construction Cover Strips Prior to application of cover strips, clean and prime the underlying existing EPDM roof membrane in accordance with the manufacturer s recommendations and instructions using products specifically designed for use on aged or weathered EPDM membrane. Allow primer to dry or set in accordance with the membrane manufacturer s instructions prior to application of the cover strips. Set EPDM cover strips into position and check for proper overlap and position. Cover strips shall be 12 inches wide as indicated, shall overlap the underlying cuts in the existing EPDM roof membrane by a minimum of 3 inches on all sides, and shall extend to the underside of the existing metal sandwich wall panels at the penthouse concrete curb. Corners of cover strips shall be cut round. Peel off protective release liner from the cover strip and press down the exposed tape adhesive using hand pressure over the entire cover strip, then immediately roll across, not parallel Page 5 of 6
6 to, the cover strip edge with a steel roller in accordance with the manufacturer s instructions. Apply lap sealant to all cover strip edges Bearing Sheets Provide for protection of roof membrane by placing temporary EPDM membrane bearing sheets at all surface bearing support locations (wood sleepers) for the temporary staging platform as indicated. Bearing sheets shall be loose laid over the new cover strips and removed after installation of the substation is completed Roof Walkpads Reinstall walkpads in original locations after removal of temporary staging platforms and EPDM membrane bearing sheets Ballast Reinstall (push back) existing stone ballast to cover all new cover strips after removal of temporary staging platforms and EPDM membrane bearing sheets and reinstallation of walkpads. Use a gravel pusher or broom to move ballast. Use of rakes and shovels is not permitted. --End of Section-- Page 6 of 6
A. This Section includes rubberized asphalt sheet membrane waterproofing systems.
SECTION 07110 SHEET MEMBRANE WATERPROOFING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationPeel & Seal Self-Stick Roofing Solutions
Peel & Seal Self-Stick Roofing Solutions Ideal for Low Slope Applications Waterproof and Weatherproof Energy Efficient Tough and Durable Versatile, Effective Sealing Around Protrusions Perfect for Vents,
More informationROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS
ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS 1. 2. 3. 3.0 Scope 1.1 This application standard shall be used where the authority having jurisdiction has adopted its use, and
More informationResidential Roofing Guide
Residential Roofing Guide TABLE OF CONTENTS Building Detail and Accessories...... 1 Panel Introduction and Handling...... 2 Cutting and Trimming.... 3 Roof Preparation..... 3 Roof Slope..... 3 Re-roofing...
More informationWESTERN COOL ROOF SYSTEMS Sustainable - Energy Efficient FLUID APPLIED REINFORCED ROOF SYSTEM
WESTERN COOL ROOF SYSTEMS Sustainable - Energy Efficient FLUID APPLIED REINFORCED ROOF SYSTEM SPECIFICATION NO. SMAA-2P-8xE UPGRADE SMOOTH SURFACE / CAP SHEET / SINGLE PLY 2 PLY POLYESTER REINFORCED ACRYLIC
More informationSECTION 07540 - THERMOPLASTIC MEMBRANE ROOFING
SECTION 07540 - THERMOPLASTIC MEMBRANE ROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationITEM 599.06060008 THERMOPLASTIC MEMBRANE ROOFING
DESCRIPTION Construct adhered membrane roofing system, roof insulation, and vapor retarder in accordance with these specifications. MATERIALS: General: Provide installed roofing membrane and base flashings
More informationRead and understand all installation instructions and precautions before installing. GENERAL APPLICATION INSTRUCTIONS
AC TOPSEAL SELF-ADHERED, GRANULAR SURFACED, SINGLE PLY, LOW SLOPE ROLLED ROOFING 3 X 33.3 = 100 SQ. FT. 10 YEAR MATERIAL LIMITED WARRANTY For Use on Porches / Sheds / Utility Buildings / Accessory Buildings
More information07 5423-1 THERMOPLASTIC-POLYOLEFIN ROOFING (TPO) Data Center
PART 1 GENERAL 1.01 SECTION INCLUDES SECTION 07 5423 THERMOPLASTIC-POLYOLEFIN ROOFING (TPO) Data Center A. Tear off existing roof system down to wood deck and install new Thermoplastic membrane roofing
More information1. Adhered KEE membrane roofing system. 2. Mechanically fastened KEE membrane roofing system.
SECTION 075416 - PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Adhered KEE membrane roofing system. 2. Mechanically fastened KEE membrane roofing system. 1.2 PERFORMANCE REQUIREMENTS A. Solar Reflectance
More informationSECTION 07530 SINGLE PLY MEMBRANE ROOFING. 4. Minor repair to adjacent clay tile roofing and flashings.
SECTION 07530 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section includes the flowing: 1. Removal of existing roofing membrane. Existing bur roof has one overlay and penetration mastic is asbestos containing.
More informationNRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry
More informationHIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS
BSW HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW is a fully reinforced Pre-Applied system membrane designed for horizontal and vertical external blind-side
More informationTITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09
TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09 PMT GUIDE # 10 Book of Order Section G-10.0102o: "The session is responsible for the mission and government of the particular church. It
More informationSEAMS SEAMING USING SEAM TAPE
SEAMING USING SEAM TAPE SEAMS The membrane should be positioned so that the width of the seam is 3. Remove excess chalk from a chalk line by snapping the line into the air and then chalk a line one-quarter
More informationPlease read the entire document before purchasing and installing any of these products
Please read the entire document before purchasing and installing any of these products USA SBS UNDERLAYMENT ROOFING UNDERLAYMENT SBS Mineral Surfaced MINERAL SURFACE CAP SHEET Ice and Water Protection
More informationSECTION 07560 FLUID APPLIED ROOFING (LIGHT TRAFFIC DECKS OVER CONCRETE)
SECTION 07560 FLUID APPLIED ROOFING (LIGHT TRAFFIC DECKS OVER CONCRETE) PART 1 GENERAL 1.1 DESCRIPTION 1. Fluid applied flexible acrylic waterproofing system over concrete. This work shall include the
More informationThe existing roof angle change terminations and flashings when sound and intact can be reused.
January 2, 2015 Summary Specification Re-Skinning an Existing Roof Maintenance and Repair Warranty Upgrade for Up to 30 Years Re-Skinning Over an Existing Roof with a New C-EPDM Membrane Using The Existing
More informationCertainTeed. Self-Adhering Roof Systems for Low Slope Residential Roofs
CertainTeed Self-Adhering Roof Systems for Low Slope Residential Roofs Goes down fast. Stays on strong. Flintlastic SA performs in all the right ways. What s more important to you? Speed of installation,
More informationG VYCOR DECK PROTECTOR
G VYCOR DECK PROTECTOR Self-Adhered Flashing Contractor s Guide DECKS AND DETAIL AREAS For longer lasting decks, install Grace Vycor Deck Protector. FROM THE MAKERS OF G Ice & Water Shield What Self-Adhered
More informationChapter 9: INSTALLING ROOFING
9.1 LEAK BARRIER (ICE AND WATER SHIELD) 9.2 SHINGLE UNDERLAYMENT 9.3 INSTALLING GUTTER APRON AND GABLE D-EDGE 9.4 INSTALLING SHINGLES 9.5 RIDGE VENT AND CAP Tools needed by each volunteer: Hammer (16 oz.
More informationYour guide to home maintenance. Flat Roofs
Your guide to home maintenance Flat Roofs Your guide to home maintenance is a series of information leaflets that gives you all the information you need to keep your home in tiptop condition. Flat Roofs
More informationNEOGARD. Preventive Maintenance Manual
NEOGARD Preventive Maintenance Manual Fluid-Applied Roof Coating Systems December 2014 Notes NEOGARD luid-applied roof coating systems are designed to be long lasting, monolithic membranes which provide
More informationAlthough we do a fair amount of residential roofing, my family s breadand-butter. Installing a. Sealants aren t universal
Installing a Low-Slope Exposed EPDM for roof transition Exposed EPDM for resistance to ice damming Sidewall flashing Done with care, a flat roof can provide 0 years or more of leak-free service Gravel
More informationBuilding Owners Guide to a Duro-Last System!
Building Owners Guide to a Duro-Last System Table of Contents Section 1: Introduction to Duro-Last Roofing Systems Section 2: Benefits of a Duro-Last Roofing System Section 3: Comparing a Duro-Last Roof
More informationSTANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES
ROOFING APPLICATION STANDARD (RAS) No. 117 STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES Scope 1.1.
More information3 Installation. 3. Installation. EPDM Installation
3 Installation The information provided within this chapter may assist the contractor to install the Firestone EPDM Systems in accordance with Firestone s requirements. It may also help him and the designer
More informationAir-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association
Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-
More informationRECOATING AND RENEWING SPF ROOFING SYSTEMS
RECOATING AND RENEWING SPF ROOFING SYSTEMS Procedures, Regional Differences and type of coating systems Bruce Schenke Premium Spray Products REASONS TO RECOAT/RENEW Add a new coating layer to renew the
More informationDurapax Coal Tar BUR Application Guide
400 Old Reading Pike, Suite 304 Pottstown, PA 19464 Tel: 610-579-9075 Fax: 610-323-0115 www.durapax.com Durapax Coal Tar BUR Application Guide DESIGN CONSIDERATIONS The proper specifications of any roof
More informationTable of Contents. Western States Standing Seam SS675 Panel Installation, Flashings & Shop Drawing Detail Guide. Notes to Designer /Installers..
Western States Standing Seam SS675 Panel Installation, Flashings & Shop Drawing Detail Guide Table of Contents Section Page Section Page Notes to Designer /Installers.. 1 Fastener Placement and Selection.2-3
More informationGYPSUM AREA SEPARATION FIREWALLS GA-620-2011
GYPSUM AREA SEPARATION FIREWALLS GA-620-2011 GA-620-2011 Copyright 2011 Gypsum Association All rights reserved. Printed in U.S.A. Characteristics, properties, or performance of materials or systems herein
More informationWATERPROOFING FOR CONCRETE STRUCTURES
MANUAL OF CONTRACT DOCUMENTS FOR ROAD WORKS VOLUME 1 SPECIFICATION FOR ROAD WORKS SERIES 2000 WATERPROOFING FOR CONCRETE STRUCTURES Contents Clause Title Page 2001 General 2 2002 Protection of Bridge Deck
More informationMETAL ROOF RESTORATION SAMPLE DESIGN GUIDELINES
METAL ROOF RESTORATION SAMPLE DESIGN GUIDELINES REFLECTICLEAN ACRYLIC/URETHANE Elastomeric Roofing Systems, Inc 6900 Bleck Dr. Rockford, MN 55373 800.403.7747 -or- 763.565.6900 fax: 763.565.6901 email:
More informationCHAPTER 7: Building Systems ROOFING SYSTEMS
ROOFING SYSTEMS Purpose Examples 1. Shingle roof system 2. Metal roof with blanket insulation 3. Metal roof with rigid insulation 4. Built-up asphalt roof system 5. Single-ply roof system 6. Modified Bitumen
More informationGENERAL RUBBER LINING PRINCIPLES
GENERAL RUBBER LINING PRINCIPLES I. METAL PREREQUISITES Metal to be lined should meet the requirements as stated in section 8 Metal Fabrication and section 12 Blasting and Cementing Procedures. The surface
More informationRESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
More informationMODULAR EPDM ROOFING SYSTEMS
MODULAR EPDM ROOFING SYSTEMS INSPECTION, REPAIR & MAINTENANCE HANDBOOK Now that you ve selected one of the best roofing systems available today, please take the time to read through this handbook carefully
More informationDistributed by: BEST MATERIALS LLC, Phoenix AZ Ph: 800-474-7570, 602-272-8128 Fx: 602-272-8014 www.bestmaterials.com Email: Sales@BestMaterials.
FULLY-ADHERED ROOFING SYSTEM INSTALLATION INSTRUCTIONS Distributed by: BEST MATERIALS LLC, Phoenix AZ Ph: 800-474-7570, 602-272-8128 Fx: 602-272-8014 www.bestmaterials.com Email: Sales@BestMaterials.com
More informationfoot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.
Skylight Installation Instructions This document provides instruction and guidelines for installation of both curb mount (CM) and self flashing (SF) unit skylights on flat, pitched (> or equal to 3/12
More informationMETHOD STATEMENT 006 TORCH APPLIED MEMBRANE TO BASEMENT WALLS
This Document is designed to cover best practice installation procedures for a one layer torch applied sheet membrane system to basement walls. PRELIMINARY WORK Ensure that all surface preparation work,
More informationBLACK JACK ALL WEATHER ROOF COATING
PAGE: 1 of 6 PRINT DATE: 16/09/2004 BLACK JACK ALL WEATHER ROOF COATING DESCRIPTION BLACK JACK ALL WEATHER ROOF COATING is a solvent based, full bodied black brushable compound with added fibres for reinforcement.
More informationDRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H
DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H Soil Drainage Mat with Built-In Protection Layer POLYGUARD DRAINAGE MATS are three-part prefabricated geocomposite drain consisting of a
More informationEPDM System Repair and Cleaning
EPDM single-ply roof systems have represented a third of the volume of the low-sloped commercial market for close to twenty years. The majority of these roofs were installed to receive the manufacturer
More informationA. Roofing Terminology: Definitions in ASTM D 1079 and glossary in NRCA's "The NRCA Roofing and Waterproofing Manual" apply to work of this Section.
SECTION 075419 POLYVINYL CHLORIDE (PVC) ROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
More informationWINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING
WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING IMPORTANT NOTICES AND INFORMATION Read these instructions in their entirety prior to installing windows. Any local building code requirements
More informationSECTION 07 61 13 STANDING SEAM METAL ROOFING
SECTION 07 61 13 STANDING SEAM METAL ROOFING PART 1 GENERAL 1.01 SCOPE OF WORK A. The Work shall include all labor, materials, equipment and supervision required to complete the work of the above referenced
More information3 Installation. 9 Roof Edges... p. 3. 19 10 Wall Terminations... p. 3. 20 11 Membrane Repair... p. 3. 21 12 Miscellaneous... p. 3. 22. 3.
3 Installation The information provided within this chapter may assist the contractor to install the Firestone UltraPly TPO Systems in accordance with Firestone s requirements. It may also help him and
More informationSun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
More informationThe better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................
More informationAsphalt Shingle Application Requirements
Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt
More informationCITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503. Re-Roofing: Asphalt Shingles
CITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503 Re-Roofing: Asphalt Shingles This is a summary of the standard requirements based on the
More informationTHIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150
THIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150 SECTION ONE A. Objective The objective of this guide is to provide Owners and General Contractors/Construction
More informationRoofing Systems. There are many different systems, each with it's own special requirements and benefits. Browse through all the options below.
Roofing Systems There are many different systems, each with it's own special requirements and benefits. Browse through all the options below. BUR (Built-Up Roofing) Built-Up-Roofing, BUR is a roof that
More informationPREMIUM LAMINATED ASPHALT SHINGLES Dallas, TX Tuscaloosa, AL Phillipsburg, KS
Application Instructions for THESE ARE THE MANUFACTURER S APPLICATION INSTRUCTIONS FOR THE ROOFING CONDITIONS DESCRIBED. TAMKO BUILDING PRODUCTS, INC. ASSUMES NO RESPONSIBILITY FOR LEAKS OR OTHER ROOFING
More informationRoof Inspection. Summary Report
Phone: (561) 866 9956 www.real-estate-inspections.com Roof Inspection Summary Report Subject Property File Number: 05-15-RF-002 Inspector: Craig Milliken, PE CPM Real Estate Inspections, Inc. Date of Inspection:
More informationINSTALLATION INSPECTION GUIDE FOR 3RD PARTY INSPECTORS FOR PAREX USA EXTERIOR INSULATION AND FINISH SYSTEMS
INSTALLATION INSPECTION GUIDE FOR 3RD PARTY INSPECTORS FOR PAREX USA EXTERIOR INSULATION AND FINISH SYSTEMS Introduction This inspection guide is organized to follow the EIF System's Installation Guide.
More informationROOF INSPECTION & MAINTENANCE
Physical Plant Administration Facilities Maintenance Department ROOF INSPECTION & MAINTENANCE All roofs require periodic inspection and maintenance in order to perform as designed and to provide a long
More informationCommercial Roof Management
Disclaimer: This material is designed and intended for general informational purposes only, and is not intended, nor shall it be construed or relied upon, as specific legal advice. Roof damage is a leading
More informationWarranty Information TABLE OF CONTENTS PROCEDURES FOR WARRANTY 2
Warranty Information TABLE OF CONTENTS PROCEDURES FOR WARRANTY 2 PROTECTING YOUR DURO-LAST ROOFING 3 Safety Measures 3 Inspection 3 Maintenance Program 4 Sealants 4 Drainage 4 Parapets Walls 4 Building
More informationRoof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building
Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building Prepared For: Ms Marilyn Bittenbender Colliers International 805 New Hampshire St Lawrence Kansas, 66046 Prepared
More informationConstruction. SikaProof A-08 Edge, A-12 Edge. Fully bonded FPO sheet membrane in L-shape for the SikaProof A waterproofing system. Product Description
Product Data Sheet Edition 15/10/2014 Identification no: 02 07 04 10 300 0 000002 SikaProof A Edge SikaProof A-08 Edge, A-12 Edge Fully bonded FPO sheet membrane in L-shape for the SikaProof A waterproofing
More informationEpdm Flat Roofing Systems
Epdm Flat Roofing Systems EDPM can be fully bonded, loose laid and ballasted or mechanically attached depending on the existing roof and its proposed usage. This applies to roofs to be refurbished and
More informationSPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 16 BRIDGE DECK WATERPROOFING. 16.1 General...16-1. 16.2 Materials...16-1. 16.3 Equipment...
SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 16 BRIDGE DECK WATERPROOFING TABLE OF CONTENTS 16.1 General...16-1 16.2 Materials...16-1 16.3 Equipment...16-1 16.4 Installation...16-2 16.4.1 Traffic Restrictions...16-2
More informationCOMPARATIVE PERFORMANCE OF EPDM RUBBER ROOFING MEMBRANE AS PROTECTION AGAINST HAIL DAMAGE
www.epdmroofs.org COMPARATIVE PERFORMANCE OF EPDM RUBBER ROOFING MEMBRANE AS PROTECTION AGAINST HAIL DAMAGE By Ric Vitiello President Forensic Roof Consulting and Hail Damage Assessment Training www.benchmark-services.com
More informationLow-slope reroofing guidelines
Low-slope reroofing guidelines by Thomas Bollnow and Joan P. Crowe, AIA The NRCA Roofing and Waterproofing Manual, Fifth Edition, contains reroofing guidelines for steep- and low-slope roofing. The August
More informationWATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 87 88 GOOD INDUSTRY PRACTICES 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12.1 BACKGROUND Most roofs in Singapore are constructed using reinforced
More informationHERITAGE WOODGATE LAMINATED ASPHALT SHINGLES Dallas, TX
Application Instructions for THESE ARE THE MANUFACTURER S APPLICATION INSTRUCTIONS FOR THE ROOFING CONDITIONS DESCRIBED. TAMKO BUILDING PRODUCTS, INC. ASSUMES NO RESPONSIBILITY FOR LEAKS OR OTHER ROOFING
More informationSECTION 07550 - MODIFIED BITUMINOUS MEMBRANE ROOFING. A. Vapor barrier (base ply); cover board at existing roof deck.
SECTION 07550 - PART I GENERAL 1.01 SECTION INCLUDES A. Vapor barrier (base ply); cover board at existing roof deck. B. Roof insulation at new roof deck. C. Modified bitumen membrane. D. Fluid applied
More informationCOMMERCIAL BUILDING APPLICATIONS
EXPANDED POLYSTYRENE FOR COMMERCIAL BUILDING APPLICATIONS www.falconfoam.com Commercial Building Ap Expanded Polystyrene Insulation Falcon Foam leads the commercial building industry with products that
More informationEPDM. Roofing systems
Roofing systems Our Promise Through ongoing interchange of experiences with contractors, Mule-Hide keeps on top of the latest roofing requirements and solutions Trusted in roofing since 1906, Mule-Hide
More informationAvoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
More informationA. Work on this project shall consist of, but is not limited to, the following:
PART 1 - GENERAL CLEANING AND RESTORATION OF SECTION 05900-1 1.1 SUMMARY A. Work on this project shall consist of, but is not limited to, the following: 1. Clean and treat all exposed anodized architectural
More informationCERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011
CERTIFICATE NAME OF PRODUCT No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011 H-CONTROL REFLEX+ reflective insulating vapour control layer for roof and wall applications MANUFACTURER ACTIS
More informationGUIDELINE SPECIFICATIONS
GUIDELINE SPECIFICATIONS GORDON SOFFIT-SHIELD - An Exterior Metal Soffit System DIVISION 05 5800 or DIVISION 07 7700 Note To Specifier: SOFFIT-SHIELD should be installed by tradesmen that are experienced
More informationThe Perfect Fit For Metal Retrofit
D u r o - S h i e l d M e t a l R e t r o f i t R o o f i n g S y s t e m The Perfect Fit For Metal Retrofit Lock out leaks. Lock in your investment. Has time caught up with your metal roof? There are
More informationHHS J.W. Peavy Center Exterior Walls Waterproofing and Roof Replacement Project WBS # H-000018-0006-4 SECTION 07610 STANDING SEAM METAL ROOFING
PART 1 - GENERAL 1.01 DESCRIPTION SECTION 07610 A. Furnish and install a weather and watertight prefabricated standing seam roof system complete, in place, as shown on the drawings and as specified herein.
More informationINSTALLATION GUIDE. americanwick.com 800.242.WICK (9425)
INSTALLATION GUIDE americanwick.com 800.242.WICK (9425) American Wick Drain SITEDRAIN prefabricated drainage products may be installed in a variety of civil construction applications including: retaining
More informationWISCONSIN HOUSING AND ECONOMIC DEVELOPMENT AUTHORITY
WISCONSIN HOUSING AND ECONOMIC DEVELOPMENT AUTHORITY EPDM - SINGLE PLY MEMBRANE ROOFING REPLACEMENT SPECIFICATION Section 07500 - June 97 - Revised TO: Owners/Project Managers/Contractors RE: All WHEDA
More informationTable of Contents. Western States RustWall Wall and Soffit Panels Installation, Flashings & Shop Drawing Detail Guide
Western States RustWall Wall and Soffit Panels Installation, Flashings & Shop Drawing Detail Guide Table of Contents Section Page Section Page Notes to Designer /Installers.. 1 Fastener Placement and Selection.2-3
More informationRe-Cover Board-3. Insulation for Above the Deck ROOF WALL SPECIALTY
Insulation for Above the Deck WALL SPECIALTY PRODUCT DESCRIPTION Rmax Re-Cover Board-3 is an energy-efficient thermal insulation board composed of a closed-cell polyisocyanurate (polyiso) foam core bonded
More informationShingle Installation Guide
Shingle Installation Guide Getting Started Dedicated to improving the environment, NewTech manufactures roofing tiles that are composed of up to 90% recycled post-industrial plastic. The manufacture of
More informationFirestone RubberGard The EPDM reference
Firestone RubberGard The EPDM reference EPDM Roofing Systems 1.000.000.000 m 2 of proven performance The Firestone heritage of success and quality is extended to the construction industry through the Firestone
More informationSECTION 07400 STANDING SEAM METAL ROOF
SECTION 07400 STANDING SEAM METAL ROOF PART 1 - GENERAL 1.01 SECTION INCLUDES A. Work described in this section includes pre-formed standing seam metal roofing system complete with clips, perimeter and
More informationDrexel Metals Inc. DMC 100SS 16oz min. Copper Mechanical Seam Metal Roof System over Plywood
Drexel Metals Inc. DMC 100SS 16oz min. Copper Mechanical Seam Metal Roof System over Plywood Section 07411 Metal Roof Panels Part 1 General 1.1 Summary A. This section includes the following: a. Factory-formed
More informationSTANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS
ROOFING APPLICATION STANDARD (RAS) No. 133 STANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS 1. Scope 1.1 This application standard has been developed to provide consistent information for the
More informationVC 104+ Rigid Grade / Rigid Grade Imagine VC 104 Rigid Grade Commercial Customised
Page 1 of 6 instructions VC 104+ Rigid Grade / VC 104+ Rigid Grade Imagine / (for the rest of this document referred to as VC 104) can be applied to new and used trucks and trailers with painted rigid
More informationRenovating Your Basement
building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Renovating Your Building America Report - 0309 2003 (revised 2007) Building Science Corporation Abstract:
More informationFLAT ROOF REPAIR CUT COST WITHOUT CUTTING CORNERS
FLAT ROOF REPAIR CUT COST WITHOUT CUTTING CORNERS Table of Contents Chapter 1: FLAT ROOF REPAIR - CUT COST WITHOUT CUTTING CORNERS Chapter 2: PVC RECOVER SYSTEM HOW IT WORKS Chapter 3: 8 STRATEGIES TO
More informationHoliday Inn Express & Suites Covington (Newton County) 1. Standing-seam metal roofing, custom fabricated.
PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Standing-seam metal roofing, custom fabricated. 1.2 SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: Show installation
More informationWindow Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
More informationROXUL Board Insulation Section 07 21 13 Master Guide Specification (CAVITYROCK ) Page 1 April 2016
Master Guide Specification (CAVITYROCK ) Page 1 Click on the pilcrow in the MS Word Toolbar to toggle ROXUL GUIDE NOTES on and off. Delete this text before incorporating the section into a Project Manual.
More informationUNIVERSITY OF WASHINGTON Facilities Services Design Guide. Architectural. Roofing. Basis of Design
Basis of Design This section applies to roofing membranes, flashing and accessories. Design Criteria Adhere to the standards and details of the latest editions of the National Contractors Association (NRCA)
More informationWATERPROOFING OF WET ROOMS
WATERPROOFING OF WET ROOMS Waterproofing under tiles For longterm enjoyment of a wetroom area a complete and resistant waterproofing system is an important precondition. Most tiles are by themselves waterproof
More informationMaintenance & repair Solutions
Maintenance & repair Solutions low-slope ROOFING We ve got what you need in the sizes you need them and the options to match the results that building owners want Seal-fast Temporary roof sealer Now you
More informationSECTION 07320 ROOFING TILE
SECTION 07320 ROOFING TILE PART 1 - GENERAL 1.1 SUMMARY: A. Section Includes: 1. Vitrified clay roofing tiles. 2. Tile accessories. 3. Felt underlayment. 4. Self-adhering sheet underlayment. 5. Snow guards.
More informationSECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.
SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,
More informationGreenGuard Housewrap Installation Guide
000768PACBPHW_Flashing Bro 5/23/03 2:52 PM Page 1 For the most current product information, go to www.green-guard.com. Pactiv Building Products believes the information and recommendations herein to be
More informationSika Membran System For Sealing and Waterproofing Construction Gaps in Building Façades
Construction Sika For Sealing and Waterproofing Construction Gaps in Building Façades Waterproof and Airtight Flexible Seal Controlled Vapour Diffusion Bonds to any Building Substrate Prevents Interstitial
More informationDIVISION 23 HEATING, COOLING, AIR CONDITIONING AND VENTILATION
SECTION 230713- ALUMAGUARD ENGINEER SPECIFICATION DIVISION 23 HEATING, COOLING, AIR CONDITIONING AND VENTILATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract,