RISK MITIGATION THROUGH STRATEGIC MAINTENANCE AND RELIABILITY

Size: px
Start display at page:

Download "RISK MITIGATION THROUGH STRATEGIC MAINTENANCE AND RELIABILITY"

Transcription

1 RISK MITIGATION THROUGH STRATEGIC MAINTENANCE AND RELIABILITY Manufacturing plants today contain numerous equipment items that require some form of maintenance to help deliver company output and profit. This paper presents a practical case study detailing various methods that can be applied to achieve a structured approach to maintenance and reliability.

2 PAGE 2 INTRODUCTION Manufacturing plants today contain numerous equipment items that require some form of maintenance to help deliver company output and profit. This paper presents a practical case study from the initial Reliability Centered Maintenance concept using a computerised simulation approach, followed by the detailed Root Cause Analysis on some high consequence failure modes. The company had recognised through their internal data management processes that a particular critical equipment item was causing unexpected outages resulting in a loss of business profit. It was therefore decided by the business to embark on a continuous improvement path that would enable them to fully understand the equipment and how to prevent the unexpected losses from reoccurring. The approach taken for the critical equipment item was to initially perform a Reliability Centered Maintenance (RCM) study, in which all the likely and the dominant failure modes are identified. A Failure Mode Effect and Criticality Analysis (FMECA) model was then populated with the consequences of failure using the corporate risk matrix and financial cost of failure. The outputs of the study now gave the company the ability to optimise the choice of maintenance tasks from both a cost and safety perspective. Once the optimum maintenance plan was developed, lifetime simulations using a Monte Carlo simulator were performed to provide a forward maintenance budget prediction and also to assess the effectiveness of the plan in reducing the impact of any critical failures. Where maintenance was not able to reduce the failure effects to acceptable levels, they were subjected to detailed root cause analysis in order for effective solutions to be identified. In conclusion, this paper illustrates how a manufacturing plant developed a fully documented maintenance plan with associated work instructions for implementation through the site maintenance management system. The RCM study addressed a critical item of equipment within the manufacturing facility to develop a plan to ensure safe, reliable and economical use of the plant item throughout its life. 1.1 RELIABILITY CENTERED MAINTENANCE Reliability Centered Maintenance (RCM) is a systematic approach that focuses on preserving function rather than preserving the asset. It addresses only failures that matter using a logical process for making maintenance decisions. During this process, the equipment is broken down to the lowest maintainable item. The failure causes for each maintainable item are then identified and analysed. If reliable failure/ maintenance history is available, then this can be used to establish the failure rate or expected life of each failure cause. However, more often than not this information is not readily available or its accuracy is not very reliable. In such cases this information can be estimated based on technical, operational and maintenance experience on similar machines, as well as general engineering knowledge. The maintenance strategy for each failure cause identified must also be derived. These strategies may be predictive maintenance, preventive maintenance or a run-to-fail strategy. As part of the RCM process, the failure effect or failure consequence is assigned to each failure cause. It is important to identify the failure causes that have a potential impact on the availability of the equipment so that the equipment can be correctly modeled when the data is transferred into a Reliability Block Diagram.

3 PAGE RELIABILITY BLOCK DIAGRAM Reliability Block Diagrams (RBD s) are a tool used to carry out a system availability analysis and produce performance predictions. They are made up of series and parallel relationships that represent equipment redundancy levels. The RBD can predict downtime, number of interruptions and the Mean Time Between Failures (MTBF). The information collated during the RCM process can be utilised to create the Reliability Block Diagram (RBD) model. 1.3 ROOT CAUSE ANALYSIS Root Cause Analysis is a problem solving methodology that is aimed at identifying the root causes of problems or events. If the root causes are identified and effective solutions implemented then it would be fair to say that we should not see the problem reoccur again in the future. 2. CASE STUDY ZINC STRIPPING MACHINE The equipment identified for further improvement by the business was a zinc stripping machine. The stripping machine is not something available off the shelf ; it was designed specifically for the business and is unique in its operation. The stripping machine main function is to strip two 20 kilogram sheets of zinc every 4 seconds with a daily target of 450 tonnes a day. 2.1 THE ANALYSIS The RCM study began by collating as much information as was available, including equipment lists and current maintenance plans. Work order history, and performance data were analysed using Weibull Analysis to determine what failure patterns were occurring across the stripping machine. This information was then used to develop a Desktop Reliability Centered Maintenance (RCM) model using the simulation software package Availability Workbench (AWB) 1. The asset hierarchy was built using AWB based on the current structure within the business SAP Computerised Maintenance Management System (CMMS). This alignment with SAP was required for future use of the AWB SAP portal and the uploading and downloading of maintenance plans. With the asset hierarchy developed the next stage of the process was to define equipment functions, functional failures and failure modes. This was predominately completed using available information and equipment experts located within the business. The first model developed was the current maintenance strategy which used the plans that were being currently performed on the stripping machine. Once the current maintenance plans were implemented the next step was to assign the consequences of failure using the corporate risk matrix. The severity levels within the table were calibrated to the companies risk matrix. See Table 1. With the current practice AWB model complete the business was now in a position to simulate using the Monte Carlo Simulator built within AWB to determine the impact of the maintenance tasks on the lifecycle costs and risk levels. The simulation results provided rapid analysis, and allowed for further optimisation of maintenance plans to take place. Where maintenance was not effective in either preventing or predicting a failure mode then Root Cause Analysis was performed to determine what effective solutions could be implemented to prevent reoccurrence. (Ref 1 - Availability Workbench (AWB) is a Trade Mark owned by Isograph Limited UK)

4 Table 1 Consequence Table PAGE 4 ID Description Cost Per Hour Cost Per Occurrence Safety Severity Operational Severity S&H1 Report Only No treatment S&H2 First Aid Treatment S&H3 Medical treatment or lost time injury S&H4 Extensive or Permanent Part Disability S&H5 Fatality (s) or permanent serious disability ENV1 No impact or measurable impairment ENV2 Minor effects on biological or physical environment ENV3 Measurable impairment on biological or physical environment ENV4 Serious environmental effects with impairment of eco system ENV5 Very serious environmental effects LEG1 Unlikely to result in adverse regulatory response LEG2 Minor non compliances of breaches or regulations LEG3 Serious breach of regulation LEG4 Major breach of regulation LEG5 May be considered wilful or negligent QS1 Can easily be absorbed through normal activity QS2 Consequences can be absorbed. Minor delivery delays QS3 QS4 QS5 Significant event which can be managed under special circumstances Major event with prioritised and focused management, Customers lost Extreme event with failure to lead to failure of business. Key customers lost STK1 Little or no stakeholder interest STK2 Minor adverse local media attention STK3 STK4 STK5 Attention from local media or heightened concern from local community Significant adverse national media/public attention. Share price may be affected Serious public outcry. International coverage. Share price seriously affected DT1 Downtime Cost Smelter THE RESULTS With the AWB desktop model now complete, we needed to perform a reality check and challenge the model results. This is carried out by first examining the Cost Criticality Pareto chart. The Cost Criticality Pareto ranks the failure modes based on total cost which includes any business costs associated with failure, labour cost, spares cost and equipment cost. See Figure 1. Figure 1 Cost Criticality Pareto Chart Failure Mode Prill Build Up Bench Chain Worn Busbars Dirty Prox Misaligned Broken Switches Brushes Worn Hangers Damaged Air Gap Damaged Flag damage Light Curtain Trip $0 2m 4m 6m 8m 10m 12m Total Cost Contribution

5 PAGE 5 Using the Cost Criticality Pareto Chart, the high cost failure modes were examined in detail by carrying out a validation of the failure mode information. Once validation was complete, the Cost Criticality Pareto identified areas for improvement. The type of recommendations made for improvement included root cause analysis (RCA), equipment redesign and maintenance strategy optimisation. The second method used to challenge the model results was to examine the historical maintenance costs and compare to the budget prediction using AWB. The goal of this was not primarily to ensure the budget prediction matched the historical spend but rather to clearly understand the reasons for any discrepancies in the results. In this case study, the predicted results were within 4% of actual maintenance spending. See Figure 2. Figure 2 Actual Cost v Predicted Cost If any failure modes exceeded this target then a safety risk exposure existed. With the stripping machine, four failure modes exceeded the target and showed safety risk exposure. These failure modes were associated to emergency stop switches and the testing regime for those switches. The comparison between current maintenance and optimised maintenance can be seen with a reduction in safety risk to below the target of 1 following maintenance optimisation. See Figure 3 and Figure 4. Figure 3 Safety Criticality Current Practice Failure Mode Edge Growth Not Removed Emergency Stop Panel Failure Emergency Stop Load Failure Cost $700k $600k $500k $400k $300k Emergency Stop Unload Failure Emergency Stop Switch Failure Safety Criticality - Target = 1 $200k $100k 0 SAP Actual Year 1 SAP Actual Year 2 RCMCost Current RCMCost Optimised Spares $361,520 $404,287 $354,028 $353,121 Resources $214,507 $236,551 $241,344 $238,344 Now failure modes had been addressed from a cost perspective, the next step was to determine if the safety risk associated to the stripping machine was less than the acceptable business exposure threshold. This threshold was calibrated with the business risk matrix to align with a target of 1. Figure 4 Safety Criticality Optimised Failure Mode Edge Growth Not Removed Emergency Stop Panel Failure Emergency Stop Load Failure Emergency Stop Unload Failure Emergency Stop Switch Failure Safety Citicality - Target = 1

6 PAGE 6 Figure 5 Average Annual Cost Strategy Comparisons - Stripping Machine Cost $10m $8m $6m $4m $2m 0 Run to Fail Current Optimised Opt Redesign Effects $22,056,284 $3,289,972 $2,334,326 $759,258 Resources $45,107 $241,344 $238,661 $238,344 Spares $320,654 $354,028 $353,121 $353,121 Figure 6 Average Annual Budget Predictions - Stripping Machine $700k $600k $500k $400k $300k Spares Labour With the model details validated, it was then important to recognise the comparison between the alternative strategies on offer to the business. In this case, run to failure, current practice, optimised and optimised with redesign strategies were compared. See Figure 5. Once optimisation was finalised a maintenance budget prediction was developed to determine spares and resource requirements. Using AWB, the budget prediction could be interrogated at many levels including system, subsystem, individual asset and individual failure mode level. See Figure 6. We were now in a position to determine what impact the optimised maintenance strategy was having on the stripping machine overall availability. This would indicate single points of failure and bottlenecks within the machine and identify further opportunity for improvement. See Figure 7 $200k $100k Figure 7 Predicted Availability Performances - Stripping Machine Availabilty % Predicted Availability: 91.6% Total Downtime: 8.4% Outage due to Planned Maintenance: 4.8% Outage due to Unplanned Maintenance: 3.6% Year

7 PAGE THE IMPROVEMENT WORKSHOPS With a new maintenance strategy developed for the stripping machine, it was important to recognise that two failure modes that were occurring on the machine could not be prevented or predicted with any form of regular maintenance. See Figure 1 Cost Criticality Pareto. It was therefore decided to conduct a detailed RCA (Root Cause Analysis) workshop on these two failures. Table 2 Failure Modes for RCA EQUIPMENT Monorail DESCRIPTION Light curtains trip COST PER YEAR FREQUENCY $1,107,070 Once/shift for 5 min Side Shifter Flag damage $493,765 Once/week for 30 min The approach was taken to create a common reality and build a cause and effect chart that would address the conditions and the actions surrounding both problems using the Apollo Root Cause Analysis Method 2. The goal of the Apollo Root Cause Analysis Method is to identify not only the cause and effects but identify the effective solutions that will prevent reoccurrence of the problem. The methodology is based on the four elements of cause and effect principle: Cause and effect are the same thing Causes and effects are part of an infinite continuum Every effect has at least two causes in the form of actions and conditions An effect exists only if its causes exist at the same point in time and space. The light curtain trip identified 63 cause and effects and 12 solutions. The flag damage identified 22 cause and effects and 3 solutions. With potential solutions identified a cost benefit analysis was carried out to ensure payback on the cost of solutions. Table 3 Solution Cost Benefit PROBLEM Light Curtain Trip COST/YEAR 2.4 FMECA SUMMARY The Stripping machine FMECA analysed a total of 1798 failure modes (see Table 4). The new optimised maintenance plan produced 51 Maintenance Schedules with a total of 1466 maintenance tasks. The maintenance strategy was categorised into 10% Preventive Work and 90% Inspection Work. Table 4 FMECA Summary OPTIMIZED FMECA SUMMARY Action 2.5 CONTINUOUS IMPROVEMENT COST OF SOLUTION Number of Tasks Use As Is 929 Deleted 0 Extend Interval 54 New Tasks 471 Reduce Interval 0 Run to Failure 344 PAYBACK DAYS $1,107,070 $34, Flag Damage $493,765 $2, With the new maintenance strategies uploaded into the CMMS via the AWB SAP portal, it was recognised that a periodic review would be performed to validate the strategy and update according to new information and data becoming available. This will form part of the business continuous improvement process. (Ref 1 - Availability Workbench (AWB) is a Trade Mark owned by Isograph Limited UK)

8 3. CONCLUSION PAGE 8 The paper has presented a Reliability Centered Maintenance approach to evaluating current maintenance regimes. Once complete, the models can be used to predict budgets, maintenance labour and resource requirements and spares usage. The approach also incorporated Root Cause Analysis on high cost failure modes that could not be prevented through the maintenance regime. The paper shows through the breadth of results available, the benefit in applying an RCM and RCA approach to plant strategy optimisation. The outcomes can help ensure that the throughput goals are achieved at least cost and minimum risk exposure to the business. About ARMS Reliability Since 1995, ARMS Reliability has been at the forefront of proactive asset management strategies for a range of blue chip companies throughout the world. These companies have entrusted us with delivering business goals through effective asset management and improvements in operational productivity. ARMS Reliability is a service, software, and training organisation providing a one stop shop for Reliability Engineering, RAMS, and Maintenance Optimisation for both new and existing projects. If you would like to discuss your situation and what are the essential elements to achieving best practice Asset Management, then give ARMS Reliability a call or Apollo Root Cause Analysis ARMS Reliability are global partners and providers of the Apollo Root Cause Analysis methodology. Please visit our website apollorootcause.com to Learn more or to view our Enquire now worldwide training schedule Share this! [email protected] NORTH / CENTRAL / SOUTH AMERICA P: AUSTRALIA / ASIA / NEW ZEALAND P: EUROPE P: SOUTH AFRICA P: North America Latin America Europe Asia Africa Australia

Directory. Maintenance Engineering

Directory. Maintenance Engineering 2 / 17 INDEX 1.0 INTRODUCTION... 3 2.0 MAINTENANCE POLICY... 4 2.1 MAINTENANCE MISSION... 5 2.2 CRITICAL SUCCESS FACTORS AND KEY RESULT AREAS... 6 2.3 OBJECTIVES... 7 3.0 MAINTENANCE ENGINEERING SERVICES...

More information

The Asset Management Landscape

The Asset Management Landscape The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces

More information

The Lowitja Institute Risk Management Plan

The Lowitja Institute Risk Management Plan The Lowitja Institute Risk Management Plan 1. PURPOSE This Plan provides instructions to management and staff for the implementation of consistent risk management practices throughout the Lowitja Institute

More information

ASSET MANAGEMENT. solutions. smec.com

ASSET MANAGEMENT. solutions. smec.com ASSET MANAGEMENT solutions smec.com About SMEC SMEC is a professional services firm with a global footprint that provides high-quality consultancy services on major infrastructure projects. With over 5,300

More information

SKF Asset Management Services. Your trusted resource for life cycle support and sustainability of physical assets

SKF Asset Management Services. Your trusted resource for life cycle support and sustainability of physical assets SKF Asset Management Services Your trusted resource for life cycle support and sustainability of physical assets SKF Asset Management Services People, processes and technology to optimize asset efficiency

More information

HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT STANDARDS. OCTOBER 2011- ISSUE No 01. Doc No: HSEC MS 001

HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT STANDARDS. OCTOBER 2011- ISSUE No 01. Doc No: HSEC MS 001 HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT S OCTOBER 2011- ISSUE No 01 Doc No: MS 001 Introduction Celtique Energie is in the business of exploring for oil and gas in proven basins in Europe.

More information

The Asset Management Landscape

The Asset Management Landscape The Asset Management Landscape Second Edition ISBN 978-0-9871799-2-0 Published March 2014 www.gfmam.org The Global Forum on Maintenance and Asset Management The Global Forum on Maintenance and Asset Management

More information

Reliability Block Diagram RBD

Reliability Block Diagram RBD Information Technology Solutions Reliability Block Diagram RBD Assess the level of failure tolerance achieved RELIABIL ITY OPTIMIZATION System reliability analysis for sophisticated and large scale systems.

More information

Independent analysis methods for Data Centers

Independent analysis methods for Data Centers Bilfinger HSG Facility Management GmbH Independent analysis methods for Data Centers Max Altmeyer / Marvin Köhler August 19 th, 2015 Agenda 1. Weak point analysis 2. Energy efficiency analysis 3. Combined

More information

Core Infrastructure Risk Management Plan

Core Infrastructure Risk Management Plan SHIRE OF MOUNT MAGNET Roads and Buildings Core Infrastructure Risk Management Plan Version 1 May 2013 AM4SRRC Document Control Asset Management for Small, Rural or Remote Communities Document ID: 59_280_110211

More information

Overview of EAM Services. A Fully Integrated Global EAM Service Provider

Overview of EAM Services. A Fully Integrated Global EAM Service Provider A Fully Integrated Global EAM Service Provider Table of Contents Strategy & Process Services Overview... p. 3 Asset Reliability Services Overview... p. 4 Systems & Technology Services Overview... p. 7

More information

Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy

Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy Section 8 Output monitoring Inputs Customer requirements Safety standards Outputs and funding SRA and Government Policy Network stewardship strategy Asset and operational policies Maintenance & renewal

More information

Clinical Risk Management: Agile Development Implementation Guidance

Clinical Risk Management: Agile Development Implementation Guidance Document filename: Directorate / Programme Document Reference NPFIT-FNT-TO-TOCLNSA-1306.02 CRM Agile Development Implementation Guidance v1.0 Solution Design Standards and Assurance Project Clinical Risk

More information

Driving Transformational Change. Innovative Solutions for Optimising Performance in Quarrying & Mining Fleets

Driving Transformational Change. Innovative Solutions for Optimising Performance in Quarrying & Mining Fleets Driving Transformational Change Innovative Solutions for Optimising Performance in Quarrying & Mining Fleets Babcock International Group: In Brief The UK s leading engineering support services organisation

More information

Drawing up an Asset Management plan that delivers Operational Reliability

Drawing up an Asset Management plan that delivers Operational Reliability Drawing up an Asset Management plan that delivers Operational Reliability John Woodhouse CEO, TWPL Chair of Faculty, IAM 1 Who we are Founded 1995 by 8 senior managers from Shell, Philips, MoD, AEA, Kvaerner

More information

Reliability Modeling Software Defined

Reliability Modeling Software Defined Reliability Modeling Software Defined Using Titan Reliability Modeling Software May 30, 2014 Prepared by: The Fidelis Group 122 West Way, Suite 300 Lake Jackson, TX 77566 Fidelis Group, LLC All Rights

More information

ASSET MANAGEMENT. John Woodhouse. The Woodhouse Partnership Ltd

ASSET MANAGEMENT. John Woodhouse. The Woodhouse Partnership Ltd ASSET MANAGEMENT John Woodhouse The Woodhouse Partnership Ltd 1 What is Asset Management? Another catch-phrase, another management initiative or just re-working of good old common sense? We have certainly

More information

6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy

6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy 6 Reasons Why Outsourcing Equipment Maintenance Is Your Best Hedge In A Down Economy The decision to outsource equipment maintenance during times of economic boom is based on the desire of a company to

More information

RISK MANAGEMENT FOR INFRASTRUCTURE

RISK MANAGEMENT FOR INFRASTRUCTURE RISK MANAGEMENT FOR INFRASTRUCTURE CONTENTS 1.0 PURPOSE & SCOPE 2.0 DEFINITIONS 3.0 FLOWCHART 4.0 PROCEDURAL TEXT 5.0 REFERENCES 6.0 ATTACHMENTS This document is the property of Thiess Infraco and all

More information

Risk Management Policy and Framework

Risk Management Policy and Framework Risk Management Policy and Framework December 2014 phone 1300 360 605 08 89589500 email [email protected] location 1Bagot Street Alice Springs NT 0870 post PO Box 2257 Alice Springs NT 0871

More information

A Risk Management Standard

A Risk Management Standard A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

Risk Management. Policy

Risk Management. Policy Policy Risk Management Endorsed: 26 February 2014 Brief description The GPC Risk Management Policy and its supporting standards and procedures provide a framework to ensure that risks arising from our

More information

The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements.

The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements. CAPACITY AND AVAILABILITY MANAGEMENT A Project Management Process Area at Maturity Level 3 Purpose The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision

More information

Over 70,000 RELIABILITY CENTERED MAINTENANCE (RCM2 TM ) TRAINING COURSES

Over 70,000 RELIABILITY CENTERED MAINTENANCE (RCM2 TM ) TRAINING COURSES RELIABILITY CENTERED MAINTENANCE (RCM2 TM ) TRAINING COURSES Comprehensive, progressive and practical training solutions tailored to your organization Over 70,000 people have attended Aladon Training Courses

More information

The 39 Subjects and 6 Subject Groups

The 39 Subjects and 6 Subject Groups The 39 Subjects and 6 Subject Groups Over the last year, the IAM has been working with international partners within the Global Forum for Maintenance and Asset Management (GFMAM) to achieve global consensus

More information

Information Needed for Effective Asset Management

Information Needed for Effective Asset Management Emerson Reliability Consulting White Paper Information Needed for Effective Asset Management Bruce Hawkins, CMRP Director of Technical Excellence, Emerson Reliability Consulting Effective asset management

More information

Master Data Management for Life Sciences Manufacturers

Master Data Management for Life Sciences Manufacturers Master Data Management for Life Sciences Manufacturers Achieving Process Excellence by Michael Stein and Geert Crauwels Successful MDM strategies start with identifying broken processes, not technology.

More information

identify hazards, analyze or evaluate the risk associated with that hazard, and determine appropriate ways to eliminate or control the hazard.

identify hazards, analyze or evaluate the risk associated with that hazard, and determine appropriate ways to eliminate or control the hazard. What is a risk assessment? Risk assessment is the process where you: identify hazards, analyze or evaluate the risk associated with that hazard, and determine appropriate ways to eliminate or control the

More information

IMPLEMENTING A RELIABILITY CENTERED MAINTENANCE PROGRAM AT NASA'S KENNEDY SPACE CENTER

IMPLEMENTING A RELIABILITY CENTERED MAINTENANCE PROGRAM AT NASA'S KENNEDY SPACE CENTER IMPLEMENTING A RELIABILITY CENTERED MAINTENANCE PROGRAM AT NASA'S KENNEDY SPACE CENTER Raymond E. Tuttle and Robert R. Pete EG&G Florida BOC-035 Kennedy Space Center FL 32899 (407) 867-5705!qq, Abstract:

More information

Risk Management Procedure

Risk Management Procedure Purpose of this document Develop and document procedures and work instructions for Risk Management to cover the project Stages set out in the Project Process Map. The purpose of this procedure is to identify

More information

Title: OHS Risk Management Procedure

Title: OHS Risk Management Procedure Issue Date: July 2011 Review Date: July 2013 Page Number: 1 of 9 1. Purpose: To outline the methodology by which Department of Education and Early Childhood Development (DEECD) identifies, assesses, controls

More information

Five steps to a successful material handling CMMS implementation

Five steps to a successful material handling CMMS implementation Five steps to a successful material handling CMMS implementation Upgrade maintenance operations with improved efficiency, quality and reduced overhead automation that delivers Five steps to a successful

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Council policy Approved Manager Organisational Development Risk Management Committee Council DATE ADOPTED:

More information

WATE R O&M S E RV I CE S An asset management perspective

WATE R O&M S E RV I CE S An asset management perspective WATE R O&M S E RV I CE S An asset management perspective Smart asset management solutions create long term value With more than 150 years of water industry experience and responsibility for operations

More information

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations Guidelines for the Application of Asset Management in Railway Infrastructure Organisations INTERNATIONAL UNION OF RAILWAYS (UIC) 16 rue Jean Rey - F-75015 PARIS Tel: +33 (0)1 44 49 20 20 Fax: +33 (0)1

More information

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption.

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption. Page 1 of 24 COMMUNITY AND SERVICES SPECIAL COMMITTEE REPORT 9 DECEMBER 2104 AGENDA ITEM 6.1 ASSET MANAGEMENT POLICY 2014 REVIEW Director: Manager: Ian Butterworth Director Infrastructure and Engineering

More information

Physical Asset Management

Physical Asset Management Nicholas A. J. Hastings Physical Asset Management 4y Springer Table of Figures Outline of this Book xxiii xxix 1 Introduction to Asset Management 1 1.1 Background 2 1.2 What is an Asset? - An Accountant's

More information

Training Pack. Kaizen PDCA ( Plan / Do / Check / Act )

Training Pack. Kaizen PDCA ( Plan / Do / Check / Act ) Training Pack Kaizen PDCA ( Plan / Do / Check / Act ) Introductions Name Department Current knowledge of Plan Do Check Act Aims & Objectives Target Audience : All! Purpose of Module : To train the delegates

More information

REDUCING THE COST OF PREVENTIVE MAINTENANCE

REDUCING THE COST OF PREVENTIVE MAINTENANCE REDUCING THE COST OF PREVENTIVE MAINTENANCE Deryk Anderson Business Analyst - Maintenance Oniqua Enterprise Analytics [email protected] T: +61 7 3859 9523 SUMMARY: Lean Manufacturing and Lean Maintenance

More information

ESKISP6055.01 Manage security testing

ESKISP6055.01 Manage security testing Overview This standard covers the competencies concerning with managing security testing activities. Including managing resources activities and deliverables. This includes planning, conducting and reporting

More information

Asset Management Plan Overview

Asset Management Plan Overview Council Strategy Asset Management Plan Overview City of Albany 2013 File Ref: CM.STD.6 Synergy Ref: NMP1331749 102 North Road, Yakamia WA 6330 Version: 25/06/2013 PO Box 484, ALBANY WA 6331 Tel: (08) 9841

More information

An Introduction to Continuous Controls Monitoring

An Introduction to Continuous Controls Monitoring An Introduction to Continuous Controls Monitoring Reduce compliance costs, strengthen the control environment and lessen the risk of unintentional errors and fraud Richard Hunt, Managing Director Marc

More information

Audit & Inspection Management. Enterprise Cloud Audit & Inspection Management Solution

Audit & Inspection Management. Enterprise Cloud Audit & Inspection Management Solution Enterprise Cloud Solution is an end-to-end solution for the planning, execution and reporting of corporate external and internal audit and inspections across enterprise risk, safety, security and sustainability.

More information

Predictive Asset Maintenance

Predictive Asset Maintenance Predictive Asset Maintenance Role of Business Analytics Intelligence Framework ASSET INTELLIGENCE Optimisation What is the best that could happen? Business Maturity & Value DCS Historian Vibration Data

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

Efficient Operations for Maintenance

Efficient Operations for Maintenance Efficient Operations for Maintenance Business challenges Through Absoft s unrivalled experience of optimising operations and maintenance processes for operators, drilling and oilfield service companies,

More information

Master Data Management For Life Sciences Manufacturers

Master Data Management For Life Sciences Manufacturers Master Data Management For Life Sciences Manufacturers Achieving Process Excellence by Michael Stein, Geert Crauwels, Martin Schiesser and Colin Bryant Successful MDM strategies starts with identifying

More information

2016 Asset Management & Maintenance Priorities Survey

2016 Asset Management & Maintenance Priorities Survey 2016 Asset Management & Maintenance Priorities Survey An Original Study from 2016 Asset Management & Maintenance Priorities Survey Copyright 2016 Assetivity Pty Ltd. All Rights Reserved. Published by Assetivity

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office, Adelaide, South Australia 5000 Tel: (08) 8404 7966

More information

Title: Rio Tinto management system

Title: Rio Tinto management system Standard Rio Tinto management system December 2014 Group Title: Rio Tinto management system Document No: HSEC-B-01 Standard Function: Health, Safety, Environment and Communities (HSEC) No. of pages: 23

More information

Risk Management Policy

Risk Management Policy Risk Management Policy Responsible Officer Author Ben Bennett, Business Planning & Resources Director Julian Lewis, Governance Manager Date effective from December 2008 Date last amended December 2012

More information

GFMAM Competency Specification for an ISO 55001 Asset Management System Auditor/Assessor First Edition, Version 2

GFMAM Competency Specification for an ISO 55001 Asset Management System Auditor/Assessor First Edition, Version 2 GFMAM Competency Specification for an ISO 55001 Asset Management System Auditor/Assessor First Edition, Version 2 English Version PDF format only ISBN 978-0-9871799-5-1 Published April 2014 www.gfmam.org

More information

Mining & Construction Transforming your fleet performance

Mining & Construction Transforming your fleet performance Mining & Construction Transforming your fleet performance Giving you greater focus on your business Today s difficult economy challenges organisations within the mining and construction sector to deliver

More information

Rail Asset Management. Rail

Rail Asset Management. Rail Rail Asset Management Rail Rail Asset Management Calibre Global understands the key drivers facing rail owners and operators are both financial and operational performance. The end objective for any company

More information

Master Data Management for Life Science Manufacturers

Master Data Management for Life Science Manufacturers Master Data Management for Life Science Manufacturers by Infosys Lodestone Successful MDM strategies start with identifying broken processes, not technology. Table of Contents Master Data Management is

More information

Analyzing Risks in Healthcare. February 12, 2014

Analyzing Risks in Healthcare. February 12, 2014 Analyzing s in Healthcare February 12, 2014 1 Content What is Enterprise Management (ERM) ERM Benefits ERM Standards / ISO 31000:2009 ERM Process Register ERM Governance Model s Q&A 2 What is Enterprise

More information

Quality Manual ISO 9001:2015 Quality Management System

Quality Manual ISO 9001:2015 Quality Management System Quality management input comprises the standard requirements from ISO 9001:2015 which are deployed by our organization to achieve customer satisfaction through process control. Quality Manual ISO 9001:2015

More information

Capacity Plan. Template. Version X.x October 11, 2012

Capacity Plan. Template. Version X.x October 11, 2012 Template Version X.x October 11, 2012 This is an integral part of infrastructure and deployment planning. It supports the goal of optimum provisioning of resources and services by aligning them to business

More information

An Introduction to Risk Management. For Event Holders in Western Australia. May 2014

An Introduction to Risk Management. For Event Holders in Western Australia. May 2014 An Introduction to Risk Management For Event Holders in Western Australia May 2014 Tourism Western Australia Level 9, 2 Mill Street PERTH WA 6000 GPO Box X2261 PERTH WA 6847 Tel: +61 8 9262 1700 Fax: +61

More information

Module 1 Study Guide

Module 1 Study Guide Module 1 Study Guide Introduction to OSA Welcome to your Study Guide. This document is supplementary to the information available to you online, and should be used in conjunction with the videos, quizzes

More information

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM 13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM This ESIA has identified impacts (both positive and negative) to the physical, natural and socio-economic environments, as well as to community and worker

More information

Enterprise Asset. Public Sector

Enterprise Asset. Public Sector HEADING GOES HERE Enterprise Asset CALIBRI BOLD, Management for the UPPERCASE, 32pt SUB-HEADING GOES HERE CALIBRI BOLD, UPPERCASE, 20pt Public Sector PRESENTER: Ernst Name Swanepoel Goes Here 10 April

More information

IT Professional Standards. Information Security Discipline. Sub-discipline 605 Information Security Testing and Information Assurance Methodologies

IT Professional Standards. Information Security Discipline. Sub-discipline 605 Information Security Testing and Information Assurance Methodologies IT Professional Standards Information Security Discipline Sub-discipline 605 Information Security Testing and Information Assurance Methodologies December 2012 Draft Version 0.6 DOCUMENT REVIEW Document

More information

Incident Reporting & Management

Incident Reporting & Management Rivo Software Solution Layer allows you to report and manage incidents such as injuries, accidents and theft. With powerful capabilities including analytical trending you can make better decisions to reduce

More information

Optimising a LNG supply chain and its assets through performance prediction studies

Optimising a LNG supply chain and its assets through performance prediction studies Optimising a LNG supply chain and its assets through performance prediction studies LNG Summit Barcelona 28 th September 2015 Fabien Treillaud DNV GL 1 SAFER, SMARTER, GREENER Introduction How to assess

More information

Maintenance Strategy 2015 Owner: Kevin Bullimore Head of Infrastructure Next review 2020

Maintenance Strategy 2015 Owner: Kevin Bullimore Head of Infrastructure Next review 2020 Maintenance Strategy 2015 Owner: Kevin Bullimore Head of Infrastructure Next review 2020 Page 1 of 7 Maintenance Strategy Introduction The requirement for maintenance of premises, plant and equipment arises

More information

RCM Success Starts with CMMS

RCM Success Starts with CMMS RCM Success Starts with CMMS Ruth Olszewski, President CMMS data group, inc. 5701 N. Sheridan Road, Suite 17Q Chicago, Illinois 60660 Phone: (773) 275-8846 Fax: (801) 991-6567 [email protected]

More information

Public Training Programs. Master classes in Maintenance Practical Courses in Maintenance Management

Public Training Programs. Master classes in Maintenance Practical Courses in Maintenance Management Public Training Programs Master classes in Maintenance Practical Courses in Maintenance Management Courses Title 1- Advanced Maintenance Management for Maintenance and Operations (5 Days) Workshop 2- Maintenance

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

ASSET MANAGEMENT STRATEGY

ASSET MANAGEMENT STRATEGY ASSET MANAGEMENT STRATEGY Transport and Highways June 2013 Asset Management Strategy (June 2013) Page 1 of 10 CONTENTS INTRODUCTION 3 SECTION 1: WHY ASSET MANAGEMENT 4 1.1 Background 4 1.2 Strategic Framework

More information

Changing data needs from a life cycle perspective in the context of ISO 55000

Changing data needs from a life cycle perspective in the context of ISO 55000 Changing data needs from a life cycle perspective in the context of ISO 55000 Mr. Ed de Vroedt and Mr. Peter Hoving Affiliation: UMS Group Europe; [email protected], +316 1026 6162 ABSTRACT This paper

More information

A Perspective on Draft Embedded Digital RIS. Ron Jarrett Tennessee Valley Authority Embedded Digital Devices Workshop October 9, 2014 NRC

A Perspective on Draft Embedded Digital RIS. Ron Jarrett Tennessee Valley Authority Embedded Digital Devices Workshop October 9, 2014 NRC A Perspective on Draft Embedded Digital RIS Ron Jarrett Tennessee Valley Authority Embedded Digital Devices Workshop October 9, 2014 NRC What does the RIS mean to a Utility? This is an important RIS from

More information

Physical Asset Management: What is it all about and why?

Physical Asset Management: What is it all about and why? Physical Asset Management: What is it all about and why? Lisbon, May 2013 Kari Komonen, EFNMS Asset Management Committee EFNMSvzw 1 Section 1 What is physical asset management? 2 What is Asset (ISO55000

More information

Risk Management: Coordinated activities to direct and control an organisation with regard to risk.

Risk Management: Coordinated activities to direct and control an organisation with regard to risk. POLICY CG01 RISK MANAGEMENT Document Control Statement This Policy is maintained by the Governance and Organisational Strategy. Any printed copy may not be up to date and you are advised to check the electronic

More information

Compliance Management Framework. Managing Compliance at the University

Compliance Management Framework. Managing Compliance at the University Compliance Management Framework Managing Compliance at the University Risk and Compliance Office Effective from 07-10-2014 Contents 1 Compliance Management Framework... 2 1.1 Purpose of the Compliance

More information

SOUTHERN RURAL WATER POLICY RISK MANAGEMENT POLICY

SOUTHERN RURAL WATER POLICY RISK MANAGEMENT POLICY SOUTHERN RURAL WATER POLICY RISK MANAGEMENT POLICY 1. POLICY STATEMENT Having regard to AS/NZS ISO 31000 Risk Management, it shall be the Policy of SRW to manage risk to protect public safety, quality

More information

ITIL Introducing service operation

ITIL Introducing service operation ITIL Introducing service operation This document is designed to answer many of the questions about IT service management and the ITIL framework, specifically the service operation lifecycle phase. It is

More information

2012 Americas School of Mines

2012 Americas School of Mines www.pwc.com 2012 Americas School of Mines Maximizing Asset Management From Work Plan to Financial Performance Doug Stretton, Paul Ingram May 17, 2012 Presentation Summary Maximizing mining assets is often

More information

of The New England Water Works Association

of The New England Water Works Association Journal Our 132nd Year of The New England Water Works Association Volume 127 No. 2 June 2013 PUTNAM WATER TREATMENT PLANT AQUARION WATER COMPANY OF CONNECTICUT GREENWICH, CONNECTICUT New England Water

More information

Quality Risk Management Understanding and Control the Risk in Pharmaceutical Manufacturing Industry

Quality Risk Management Understanding and Control the Risk in Pharmaceutical Manufacturing Industry International Journal of Pharmaceutical Science Invention ISSN (Online): 2319 6718, ISSN (Print): 2319 670X Volume 4 Issue 1 January 2015 PP.29-41 Quality Risk Management Understanding and Control the

More information

Risk & Hazard Management

Risk & Hazard Management Rivo Software Solution Layer provides a rapidly deployable complete set of hazard and risk management functionality from any device, accessible from anywhere through our highly secure cloud platform. Identify,

More information

Increase Equipment Uptime Through Robust Enterprise Asset Management. For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry

Increase Equipment Uptime Through Robust Enterprise Asset Management. For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry Increase Equipment Uptime Through Robust Enterprise Asset Management For the Upstream, Midstream & Downstream Sectors of the Oil & Gas Industry The Oil & Gas industry is challenged with effectively maximizing

More information

Hazard Identification, Risk Assessment and Management Procedure. Documentation Control

Hazard Identification, Risk Assessment and Management Procedure. Documentation Control Hazard Identification, Risk Assessment and Management Procedure Reference: Date approved: Approving Body: Implementation Date: Version: 3 Documentation Control GG/CM/007 Trust Board Supersedes: Version

More information

ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS. Paper prepared for the REAAA Conference in Japan, 4 9 September 2000

ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS. Paper prepared for the REAAA Conference in Japan, 4 9 September 2000 ROAD NETWORK ASSET MANAGEMENT AS A BUSINESS PROCESS Paper prepared for the REAAA Conference in Japan, 4 9 September 2000 Florentina Mihai, BEng, GDipMgt, MIEAust Main Roads Western Australia Neville Binning,

More information

ASSET MANAGEMENT STRATEGY

ASSET MANAGEMENT STRATEGY ASSET MANAGEMENT STRATEGY Page 1 of 15 TABLE OF CONTENTS 1. INTRODUCTION...3 2. THE ASSET LIFECYCLE...3 2.1 Asset Planning...5 2.2 Asset Creation / Acquisition...6 2.3 Asset Operations...7 2.4 Asset Maintenance...7

More information

NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT

NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT NORWEGIAN PROJECT MANAGEMENT PRINCIPLES APPLIED IN THE JURONG ROCK CAVERN PROJECT FINN FAGERVIK 1, PETTER PLASSBAK 1 and TEO TIONG YONG 2 1 Sintef-Tritech-Multiconsult (STM) Consortium, Singapore E-mail:[email protected]

More information

COST EFFECTIVE APPROACHES FOR PRESCRIBED DAM ASSET MANAGEMENT

COST EFFECTIVE APPROACHES FOR PRESCRIBED DAM ASSET MANAGEMENT COST EFFECTIVE APPROACHES FOR PRESCRIBED DAM ASSET MANAGEMENT Haris Pinidiya Sydney Water, NSW, Australia ABSTRACT Dams need to be dewatered in an emergency, typically by operating scour valves. Operating

More information

ENERGY EFFICIENCY IN BUSINESS PLANNING ENERGY EFFICIENCY FACT SHEET

ENERGY EFFICIENCY IN BUSINESS PLANNING ENERGY EFFICIENCY FACT SHEET ENERGY EFFICIENCY IN BUSINESS PLANNING ENERGY EFFICIENCY FACT SHEET as part of the Energy Efficiency Information Grants Program Managing energy effectively within your business will decrease your energy

More information

Health and Safety Management Standards

Health and Safety Management Standards Health and Safety Management Standards Health and Safety Curtin University APR 2012 PAGE LEFT INTENTIONALLY BLANK Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Health and Safety Documents...

More information