Low Voltage Asset Management (LVAM) The key to reliable and safe electricity

Size: px
Start display at page:

Download "Low Voltage Asset Management (LVAM) The key to reliable and safe electricity"

Transcription

1 Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Archie Jaykaran Distribution Division Eskom SA

2 Contents Change drivers Scope, Approach, Project status LV Planning and Design LV forecasting Maintenance and Operations Data Conclusion 2

3 Change Drivers Rapid growth in network infrastructure to support economic growth and Universal Access. Currently 4 million- expected increase 1.5m Ageing network infrastructure - growing need for refurbishment and replacement of assets Public Safety - networks are an increasing risk Increasing opex expenditure- to keep the lights burning Regulatory and legislative requirements eg. SANS , NRS 057&048 Overloaded networks Theft, tampering, illegal connections - cancerous A Corrective Maintenance approach on low voltage networks 3

4 Scope of low voltage asset management project LV Overhead Network MV Line LV Overhead Line LV Service Connection LV Installation MV/LV transformer LV Fuses x x LV Line (ABC) Service connection box with 4 x MCBs x n homes x n homes Meter LV pole Asset Management Approach PAS 55 4

5 Project status Completed We are here Assessment Design/Scoping Implementation Implementation Phase I Phase II Phase II Phase II 2009 Y1 (2010) Y1 (2010) Y2 (2011) LV Asset Management assessment and project charter (1yr) Recommendation Solutions for Identified Gaps (2 months) Implement prioritised projects (1yr) Full Rollout / Implementation of Asset Management (1yr) Delivered Project team Project charter Specific findings per life cycle stage (Gap Analysis) Information requirements OD requirements Change Management Identified LV maintenance staffing requirement Scope Define initial design / scoping study Analyse life cycle focus areas and produce plan per issue Define y1 implementation plan Develop Change Management Plan Investigate OD Lifecycle data requirements Prioritise solutions Implement prioritised year one projects Implement prioritised y2 projects Define and set up PMO Define desired end state 5 5

6 LV Planning and Design Challenges / lessons Incoherent Planning and Design policy Inaccurate load forecasting - results in overloading 6

7 Key Deliverable: LV Planning and Design Policy Objective: Define principles to improve LV network planning and design Contents: Specifies the primary principles and assumptions to be used during network planning and design. Defines the responsibilities of the MV/LV project engineering department. Documents the expectations from other stakeholders e.g. MV Network Planning, Electrification Planning, the Technology Group etc., to ensure proper integration and co-ordination. Sets out the principles for the costing and evaluation of electrification projects. 7

8 LV Load Forecasting methodology Objective: More accurate load forecasting for domestic customers Approach: Determine correct measures to estimate energy consumption Living Standards Measure (LSM) more accurate than Household Income to estimate energy consumption Independent surveys by SAARF (South African Advertising Research Foundation) every 2 years no effort on part of utility Based on amongst others, ownership of electric appliances directly related to electricity consumption Established guidelines to estimate LSM based on type of dwellings Develop comprehensive load forecasting methodology based on existing load research (NRS 034), and DT-PET (Distribution Pre- Electrification Tool) easy. 8

9 Overview of new LV load forecasting methodology 9

10 LV Maintenance strategy Corrective Maintenance Approach Conditionbased Maintenance Reliability Centred Maintenance (RCM) Approach No inspections Run to failure approach Time-based inspection intervals Time-based Inspection intervals based on risk Maintenance based on RCM Analysis (FMEA & Maint Logic) 10

11 Inspection frequency based on risk assessment Network type (A) Demographic (B) Network Age (C) High Risk (H) Overhead Open Conductor Medium Risk (M) Insulated Bundled Conductors Low Risk (L) Underground cables Urban Semi Rural Rural >10yrs 5-10 Yrs <5 yrs Risk Range Risk Task Frequency months months months months 11

12 Failure Mode, and Effects Analysis (FMEA) For each LV asset, the component was analysed to determine the impact on the network: Function Functional Failure Failure Mode Failure Effect Maintenance Decision Tree Maintenance tasks (inputs to job plans) New Maintenance program 12

13 Maintenance solutions addresses the following: New maintenance programme established to cover all customers and approx. 300,000 transformers zones New staffing model developed additional 1,000 Technical Officials (TOs) being appointed Increase in vehicles and transport budget New training programme introduced focused on LV LV Planning and Design guidelines to reduce life cycle costs by considering the impact on O & M. 13

14 LV Asset Data Objective: Solve the challenge of limited LV network data data is key to AM Approach: Developed a detailed data specification for all major LV assets. Defines all data elements that are required to adequately manage LV assets and to effectively perform tasks such as planning, design, maintenance etc. Identifies the information systems in which the data currently reside Defines the actions to be performed by different stakeholders (e.g. create, read, update and delete) in each system. 14

15 LV Asset Data Extract of the data specification. Asset Group (e.g. Transformer Zone ID) o Assets (e.g. Transformers, LV feeder, Point of Supply, Service Connection) Asset Component (e.g. Earthing, Structure, Surge Arrestor etc) o Data Type (e.g. As built data, maintenance data, procurement data etc) Data Attribute (e.g. Transformer no., kva rating, mounting, primary voltage etc) o Alignment with Common Information Model (CIM) Mandatory (Y/N) Etc. 15

16 Conclusion Eskom is taking a holistic approach to managing LV assets in a way that optimizes life-cycle cost, operational efficiency and balances risk. To date the programme has developed several solutions that will improve the planning, design, commissioning and operations and maintenance of LV networks. The expected end state (18 to 24 months) will result in the following benefits: LV and MV networks are optimally planned and designed to meet customer expectations Correct prioritisation of capital expansion, refurbishment and strengthening of LV networks; Correct commissioning and hand-over of constructed LV assets; A pro-active maintenance approach that optimises resources and which helps to reduce the number of supply interruptions and risk to public safety; Optimised asset life and return on invest; Accurate and easily accessible data on LV assets to enable strategic and operational decisions; Ultimately the LV AM programme will result in an AM system that will ensure more reliable LV electricity networks that facilitate public safety. 16

17 THANK YOU 17

Asset Management Plans

Asset Management Plans November 213 Introduction Table of Contents Page # ACS Buildings & Grounds 2 Purpose and Scope ACS Buildings & Seismic 3 The purpose of these ( Plans ) is to demonstrate how we intend to deliver on the

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office, Adelaide, South Australia 5000 Tel: (08) 8404 7966

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2015 Start Date (first day) 1 April 2015 Templates for Schedules 11a 13 (Asset Management Plan)

More information

Analysis of the Brazilian Data Center Power Supplies Market

Analysis of the Brazilian Data Center Power Supplies Market Analysis of the Brazilian Data Center Power Supplies Market IT Infrastructure Outsourcing Services Compel New Trends for this Growing Market ND27-14 September 2013 Contents Section Slide Numbers Executive

More information

Appendix L Network Management Plan September 2011

Appendix L Network Management Plan September 2011 Appendix L Network Management Plan September 2011 Access Arrangement Information for the period 1 July 2012 to 30 June 2017 (AAI) Access Arrangement Information for the period 1 July 2012 to 30 June 2017

More information

Title of presentation

Title of presentation Title of presentation Edison Makwarela Senior Consultant, Eskom, Gauteng, South Africa Current Situation - The reserve margin is currently 8 10%, against an aspiration of 15% - Increased probability of

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Front cover: A team from Connetics installs 11,000 volt and 400 volt cables into a supply

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen BL20A0501 Electricity distribution technology Introduction Jarmo Partanen Introduction to ED Prof. Jarmo Partanen, D.Sc Jukka Lassila Topics of lectures Introduction to Electricity Distribution, 27.10

More information

NETWORK MANAGEMENT STRATEGY

NETWORK MANAGEMENT STRATEGY ABN 85 082 464 622 NETWORK MANAGEMENT STRATEGY DOCUMENT NUMBER: NW-#30065608-V6 DATE: 12 MAY 2011 NW-#30065608-v6-Network_Management_Strategy.DOC Page 1 of 20 This page is intentionally blank. NW-#30065608-v6-Network_Management_Strategy.DOC

More information

CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN

CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN ABN 85 082 464 622 CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN DOCUMENT NUMBER: NW-#30171121 DATE: MARCH 2011 This page should either be left blank or used for any disclaimers. Page 2 of 19

More information

South African Distribution Code

South African Distribution Code South African Distribution Code Glossary and Definitions Version 6.0 July 2014 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact:

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Assessment Of Whole Life Cost In Electrification. Matt Skinner, Functional Lead Analysis (Acting) 22 nd October 2013

Assessment Of Whole Life Cost In Electrification. Matt Skinner, Functional Lead Analysis (Acting) 22 nd October 2013 Assessment Of Whole Life Cost In Electrification Matt Skinner, Functional Lead Analysis (Acting) 22 nd October 2013 1 Why consider Whole Life Cost? Internal and external challenge to improve Asset Policy

More information

Phase Attribute Identification using GPS Technology

Phase Attribute Identification using GPS Technology Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits

More information

SP Energy Networks 2015 2023 Business Plan

SP Energy Networks 2015 2023 Business Plan Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from

More information

A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank

A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank 1. Introduction Kisiizi Hospital is a Church of Uganda "Private not-for-profit health care provider

More information

Opportunities of Wireless Broadband

Opportunities of Wireless Broadband Corpus Christi, TX Automated Meter Reading (AMR) System Fixed Network AMR System using WiFi Network Jeffrey King, Northrop Grumman IT Opportunities of Wireless Broadband Ogilvie Gericke Director of Information

More information

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...

More information

The Electrical Safety Regulation (pre and post 1 January 2014)

The Electrical Safety Regulation (pre and post 1 January 2014) The Electrical Safety Regulation (pre and post 1 January 2014) The following table provides an overview comparison between the Electrical Safety Regulation 2002 (the ESR 2002) current as at 1 July 2013

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

SUMMARY - RELATIONSHIP BETWEEN QUALITY OF SERVICE DEMANDED AND TARIFF

SUMMARY - RELATIONSHIP BETWEEN QUALITY OF SERVICE DEMANDED AND TARIFF SUMMARY - RELATIONSHIP BETWEEN QUALITY OF SERVICE DEMANDED AND TARIFF PA Consulting Services SA Authors: C. Guidi / J. Espain - / J. García Argentina Restructuring of Electric Sectors in Latin America

More information

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY Author & Presenter: CG Carter-Brown PhD Eskom, Chief Engineer IARC Co-author: R Stephen

More information

Commission de l énergie de l Ontario. Filing Requirements for Electricity Transmission and Distribution Applications. Chapter 5.

Commission de l énergie de l Ontario. Filing Requirements for Electricity Transmission and Distribution Applications. Chapter 5. Ontario Energy Board Commission de l énergie de l Ontario Ontario Energy Board Filing Requirements for Electricity Transmission and Distribution Applications Chapter 5 Consolidated Distribution System

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

Head of Engineering Job Description

Head of Engineering Job Description Head of Engineering Job Description (Job Code and Level: E006) Definition: Overall responsibility and accountability for the Engineering function across the UK which will include people and budgetary management.

More information

AUCKLAND TRANSPORT ASSET MANAGEMENT FRAMEWORK

AUCKLAND TRANSPORT ASSET MANAGEMENT FRAMEWORK AUCKLAND TRANSPORT ASSET MANAGEMENT FRAMEWORK April 2011 Contents 1 Introduction... 1 The purpose of the Asset Management framework... 1 Overview of the asset management activity... 2 2 Auckland Transport

More information

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission

More information

5 Year Strategic Asset Management Plan

5 Year Strategic Asset Management Plan Westernport Region Water Corporation 30 July 2007 Prepared for Westernport Region Water Corporation Prepared by Maunsell Australia Pty Ltd Level 9, 8 Exhibition Street, Melbourne VIC 3000, Australia T

More information

Network Risk Assessment Guideline

Network Risk Assessment Guideline Network Risk Assessment Guideline Network Risk Assessment Guideline Table of Contents Revision history... ii 1. Purpose and Scope... 1 2. Definitions, Abbreviations and Acronyms... 1 3. References... 2

More information

Asset Management Plan

Asset Management Plan 2013 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2013-2023 Network Asset Management Plan (AMP). The 2013 plan follows on from

More information

Asset Management Plan

Asset Management Plan 2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy City of Stonnington April 2011 Odysseus-imc Pty Ltd APPROVAL FUNCTION NAME DATE Checked by S. Muir 4 Mar 2011 Reviewed by T. Griffin 6 Mar 2011 Approved by S. Muir 4 April 2011

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

Electric Power Distribution

Electric Power Distribution Electric Power Distribution A S Pabla Consulting Engineer and Former Chief Engineer Punjab State Electricity Board McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New

More information

Attachment G.23. SAPN_IT PPM Business Case. 03 July, 2015

Attachment G.23. SAPN_IT PPM Business Case. 03 July, 2015 Attachment G.23 SAPN_IT PPM Business Case 03 July, 2015 Executive Summary Table of Contents 1. Executive Summary... 4 1.1 Introduction... 4 1.2 Reasons for the Project... 4 1.3 High level scope... 5 1.4

More information

Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management

Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management Project Management for Implementing the Smart Grid By Power System Engineering, Inc. Abstract PM Methodology Using a Repeatable Project Management Approach Project management solutions for the Smart Grid

More information

ESB Networks Ltd Statement of Charges

ESB Networks Ltd Statement of Charges ESB Networks Ltd Statement of Charges Revision Date: 9/2014 Revision No.: 11 Document No: DOC-101209-AXR Issued by: ESB NETWORKS LTD Approved by : CER Effective Date: 01/10/2014 Commercial and Renewable

More information

ASSET MANAGEMENT STRATEGY Approved

ASSET MANAGEMENT STRATEGY Approved Approved Document TP.TG 01.01 30/10/2014 Approved Transpower New Zealand Limited 2014. All rights reserved. Page 1 of 25 C O P Y R I G H T 2014 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A

More information

SUMMARY ASsET MANAGEMENT PLAN

SUMMARY ASsET MANAGEMENT PLAN SUMMARY ASsET MANAGEMENT PLAN INFORmATION DISCLOSURE FOR ELECTRICITY NETWORKS JUNE 2010 2019 ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2010 FY2019 1 contents CHIEF EXECUTIVE S STATEMENT... 2 POWERCO

More information

Asset Specific Plan OH Lines and Pole Hardware. Generated Date: 2014-05-29

Asset Specific Plan OH Lines and Pole Hardware. Generated Date: 2014-05-29 Asset Specific Plan and Pole Hardware Generated Date: 2014-05-29 Table of Contents 1 Purpose... 3 2 Good Practice Alignment... 3 3 Corporate Alignment... 3 4 Scope - Asset Management Activities... 5 5

More information

Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue.

Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue. ASSET MANAGEMENT PLAN 2013 Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue. Powerco however, operates

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Front cover: A team from Independent Line Services removing conductors prior to dismantling

More information

Safety Performance Report on Victorian Electricity Distribution and Transmission Businesses

Safety Performance Report on Victorian Electricity Distribution and Transmission Businesses Safety Performance Report on Victorian Electricity Distribution and Transmission Businesses 2012 JUNE 2013 i Contents Contents... ii PREFACE... 5 Summary... 7 Structure of the report... 19 1 Introduction...

More information

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage

More information

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2015-16 Electricity Network Tariffs and Charges and Future Price Trends July 2015 Power and Water Corporation 1 Table of Contents 1 Business Characteristics 3 2 2014 Network Price Determination

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

ESKITP7145.01 Manage IT service delivery performance metrics

ESKITP7145.01 Manage IT service delivery performance metrics Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Attachment 7-2 Asset management framework and governance Public 30 April 2015 Jemena Electricity

More information

6 June 2014. Cathyrn Blair Stakeholder Engagement 2015 to 2020 Directions and Priorities SA Power Networks GPO Box 77 ADELAIDE SA 5001.

6 June 2014. Cathyrn Blair Stakeholder Engagement 2015 to 2020 Directions and Priorities SA Power Networks GPO Box 77 ADELAIDE SA 5001. ABN 14 725 309 328 136 Greenhill Road Unley SA 5061 Telephone 08 8300 0103 Fax 08 8300 0204 Email customerservice@business-sa.com www.business-sa.com 6 June 2014 Cathyrn Blair Stakeholder Engagement 2015

More information

Transformers Energy efficient transformer solutions European Minimum Energy Performance Standard (MEPS)

Transformers Energy efficient transformer solutions European Minimum Energy Performance Standard (MEPS) Transformers Energy efficient transformer solutions European Minimum Energy Performance Standard (MEPS) 2 European MEPS for transformers The EU MEPS (European Minimum Energy Performance Standard) Transformers

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

#3 LV network monitoring in the Demo2

#3 LV network monitoring in the Demo2 #3 LV network monitoring in the Demo2 Type of solution Equipment / Hardware / Firmware Information system Manufacturer(s) implied (for equipment or hardware) ABB emeter Siemens Schneider Electric LV Innovation

More information

Creating the right environment for your Asset Information System implementation

Creating the right environment for your Asset Information System implementation Creating the right environment for your Asset Information System implementation Asset Information Management It s not the most exciting subject... But it s damn important! Roger Byrne - 2007 Software is

More information

Appendix B: Capital expenditure forecasts for Standard Control Services

Appendix B: Capital expenditure forecasts for Standard Control Services Appendix B: Capital expenditure forecasts for Standard Control Services Introduction Our capital expenditure forecasts are focused on continuing to give our customers a safe, dependable service, and increasingly

More information

A Systems Engineering Approach to Risk-based Asset Management

A Systems Engineering Approach to Risk-based Asset Management A Systems Engineering Approach to Risk-based Asset Management Michael Salvato, Executive Program Manager NYCT Enterprise Asset Management Program Office Office of the President Email: michael.salvato@nyct.com

More information

Cost Allocation Method

Cost Allocation Method Cost Allocation Method Ergon Energy Corporation Limited Document Summary Version: 4.0 Status: AER Approved Version History and Date of Issue Version Date Issued Summary of Changes 1.0 March 2009 Initial

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Advanced Metering Infrastructure Deployment at Energa-Operator. 8 December 2010

Advanced Metering Infrastructure Deployment at Energa-Operator. 8 December 2010 Advanced Metering Infrastructure Deployment at Energa-Operator Agenda AMI deployment purpose and scope Project status Standardization and interoperability Key business aspects Next steps AMI Deployment

More information

Business Area Distribution

Business Area Distribution Business Area Distribution David Ringmar Director Network Strategy and Development Vattenfall Capital Markets Day, Solna, 27 May 2015 Facts and figures Business Area Distribution Vattenfall s total lenght

More information

Finnish Energy Industries draft answer to CEER public consultation The future role of DSOs

Finnish Energy Industries draft answer to CEER public consultation The future role of DSOs Finnish Energy Industries draft answer to CEER public consultation The future role of DSOs Respondents information Name Ina Lehto Name of organisation Finnish Energy Industries Type of organisation Other

More information

A Strategic Approach to Housing Asset Management

A Strategic Approach to Housing Asset Management Housing A Strategic Approach to Housing Asset Management www.milton-keynes.gov.uk/housing-mkc 0 A Strategic Approach to Housing Asset Management Contents Page 1. Introduction 1 2. Developing a New Set

More information

High Voltage. Hazards

High Voltage. Hazards High Voltage Hazards HV Hazards Substations, Overhead Lines, Cables Safety Incidents Requirements for Designers, Constructors Construction Regs 2013 and other Legislation Codes of Practice Other Guidance

More information

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI 1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed

More information

RIN Response. Part C. Operating and maintenance expenditure

RIN Response. Part C. Operating and maintenance expenditure RIN Response Part C Operating and maintenance expenditure Aurora Energy Pty Ltd ABN 85 082 464 622 Level 2 / 21 Kirksway Place Hobart TAS 7000 www.auroraenergy.com.au Enquiries regarding this RIN Response

More information

5. The applicable test instruments are selected and testing carried out according to specific task requirements. ASSESSMENT CRITERION NOTES

5. The applicable test instruments are selected and testing carried out according to specific task requirements. ASSESSMENT CRITERION NOTES STAATSKOERANT, 19 DESEMBER 2003 No. 25853 473 ASSESSMENT CWITERlON I 1, Conditions are assessed and safety measures implemented according to safe work procedures. ASSESSMENT CRjTERION NOTES ASSESSMENT

More information

Condition Monitoring of equipment to improve quality of supply to customers by averting failures

Condition Monitoring of equipment to improve quality of supply to customers by averting failures Condition Monitoring of equipment to improve quality of supply to customers by averting failures Author & presenter: Patrick O Halloran BTECH Manager Technology Services at City Power Johannesburg Abstract

More information

Ladies and Gentlemen,

Ladies and Gentlemen, Ladies and Gentlemen, I would like to begin my speech by thanking deeply the Maniatakeion Foundation and especially the Chairman, Mr. Dimitris Maniatakis for his invitation and to congratulate him for

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

Network Monitoring and Smart meters

Network Monitoring and Smart meters Network Monitoring and Smart meters Author: Chris Halliday - Electrical Consulting and Training Pty Ltd Email: chris@elect.com.au Mr Dave Urquhart Energex Email: daveurquhart@energex.com.au This paper

More information

A study into approaches to minimise the impact of electricity price increases on the poor

A study into approaches to minimise the impact of electricity price increases on the poor TRADE AND INDUSTRY CHAMBER FUND FOR RESEARCH INTO INDUSTRIAL DEVELOPMENT, GROWTH AND EQUITY (FRIDGE) A study into approaches to minimise the impact of electricity price increases on the poor Final Report

More information

Guide to Integrated Strategic Asset Management

Guide to Integrated Strategic Asset Management Guide to Integrated Strategic Asset Management Issue date: 14 November 2011 Acknowledgements This guide is based on the Australasian Procurement and Construction Council Inc. s (APCC) publication, Asset

More information

Rail Asset Management. Rail

Rail Asset Management. Rail Rail Asset Management Rail Rail Asset Management Calibre Global understands the key drivers facing rail owners and operators are both financial and operational performance. The end objective for any company

More information

ASSET MANAGEMENT PROGRAM EVALUATION BEST PRACTICES

ASSET MANAGEMENT PROGRAM EVALUATION BEST PRACTICES 1.0 Corporate Asset Management Program 1.1 Vision and Support 1.2 Resource Management 1.3 Strategic Asset Management Plan 1.4 Communications 2.0 Customer Service and Risk Management 2.1 Levels of Service

More information

Network Asset Management Plan

Network Asset Management Plan Network Asset Management Plan CEOM 8018 2014-2019 Page 1 of 87 TROLLED COPY IF PRINTED UNCON PREPARED BY: CAPITAL WORKS P ROGRAM M ANAGER DOCUMENT NUMBER: AUTHORISED BY: PAUL BRAZIER POSITION TITLE: Manager

More information

ASSET MANAGEMENT STRATEGY

ASSET MANAGEMENT STRATEGY SHIRE OF BODDINGTON ASSET MANAGEMENT STRATEGY Version 1 January 2014 Asset Management Strategy Document Control Rev No Date Revision Details Author Reviewer Approver 1 January 2014 Draft Strategy T McCarthy

More information

Western Power transmission and distribution annual asset management report. prepared by Asset Management Division

Western Power transmission and distribution annual asset management report. prepared by Asset Management Division 2006 Western Power transmission and distribution annual asset management report prepared by Asset Management Division Disclaimer The Asset Management Division of Western Power has published this document

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

Taking the guesswork. management

Taking the guesswork. management Taking the guesswork out of strategic asset management 1 1 2 To replace, repair or maintain: that is the question. Answering it is our speciality. To replace, repair or maintain: that is the question.

More information

Monitoring Underground Power Networks

Monitoring Underground Power Networks Monitoring Underground Power Networks By Mark Stiles Merve Cankaya ABSTRACT Underground electric distribution systems are common in large cities throughout the United States. Power usage for the entire

More information

SURGE PROTECTIVE DEVICES

SURGE PROTECTIVE DEVICES SURGE PROTECTIVE DEVICES 1. INTRODUCTION In order to ensure safety of people, protection of equipment and, to a certain extent, continuity of supply, insulation co-ordination aims at reducing the likelihood

More information

ERGON ENERGY. Fleet. Capital Expenditure Forecast. Fleet Forecast Expenditure Summary 1

ERGON ENERGY. Fleet. Capital Expenditure Forecast. Fleet Forecast Expenditure Summary 1 ERGON ENERGY Fleet Capital Expenditure O i Fleet Expenditure Summary 1 Contents Contents... 2 1. Introduction... 3 1.1 Purpose... 3 1.2 Summary of expenditure... 3 1.3 Customer outcomes... 4 2. Current

More information

This plan forms one part of a suite of Asset Management Plans that have been developed:

This plan forms one part of a suite of Asset Management Plans that have been developed: E: D1: Levee Footpath Bank Asset Management Plan March July 2014 2015 This plan forms one part of a suite of Asset Management Plans that have been developed: A. Bridges B. Buildings C. Drainage D. Footpaths

More information

Producing Safe Drinking Water: Ultra-filtration Membrane for the Removal of Indicator Bacteria

Producing Safe Drinking Water: Ultra-filtration Membrane for the Removal of Indicator Bacteria Producing Safe Drinking Water: Ultra-filtration Membrane for the Removal of Indicator Bacteria South African Vision To provide access to an adequate, safe and affordable supply of potable water to all

More information

How To Develop A Smart Grid In Elenia

How To Develop A Smart Grid In Elenia GEODE Autumn Seminar in Brighton 12 th of November Utilization of Automatic Meter Management in Smart Grid Development Ville Sihvola Head of Marketing and Sales Elenia Oy Elenia Oy Turnover 220 M Employees

More information

We thank you again for your invaluable contribution to the World Bank s work.

We thank you again for your invaluable contribution to the World Bank s work. Getting Electricity - www.doingbusiness.org Dear Contributor, We would like to thank you for your cooperation with the Doing Business project. As an expert in the field of electricity distribution, you

More information

The National Development Plan 2030: Implications for Project Managers. 16 September 2013 Dr. Bridgette Gasa

The National Development Plan 2030: Implications for Project Managers. 16 September 2013 Dr. Bridgette Gasa The National Development Plan 2030: Implications for Project Managers 16 September 2013 Dr. Bridgette Gasa NATIONAL DEVELOPMENT PLAN 2030 Our future - make it work Implications of the NDP for Project Managers

More information

Considering UNDERGROUND. tampaelectric.com

Considering UNDERGROUND. tampaelectric.com Considering UNDERGROUND Electric Service? tampaelectric.com INTRODUCTION The majority of Tampa Electric s customers receive their electric service through overhead construction, which is the standard type

More information

Electrical Resistance Resistance (R)

Electrical Resistance Resistance (R) Electrical Resistance Resistance (R) Any device in a circuit which converts electrical energy into some other form impedes the current. The device which converts electrical energy to heat energy is termed

More information

a growing market in an appealing business context with NO local competitors Wire and Cable Manufacturing in Rwanda

a growing market in an appealing business context with NO local competitors Wire and Cable Manufacturing in Rwanda a growing market in an appealing business context with NO local competitors Wire and Cable Manufacturing in Rwanda Construction in Rwanda is Big & Growing Trends in construction & materials: Construction

More information

Enterprise Risk Management & Information Technology

Enterprise Risk Management & Information Technology Enterprise Risk Management & Information Technology Presented by Scott Perry and Gary Ross Slalom Consulting, San Francisco Agenda Introductions Session Objectives Overview of Enterprise Risk Management

More information

VOLUME 1 FINAL. Energex. Distribution Annual Planning Report. 2014 / 2015 to 2018 / 2019. Energex DAPR 2014/15 2018/19 Volume 1

VOLUME 1 FINAL. Energex. Distribution Annual Planning Report. 2014 / 2015 to 2018 / 2019. Energex DAPR 2014/15 2018/19 Volume 1 VOLUME 1 FINAL Energex Distribution Annual Planning Report 2014 / 2015 to 2018 / 2019 Energex DAPR 2014/15 2018/19 Volume 1 Version Control Version Date Description 1.0 30/09/2014 Final version for publication

More information

REPLACEMENT PLANNING STRATEGY TO OPTIMIZE LIFE CYCLE PROFIT. N-7034 Trondheim Willy Hanssen, Trondheim Energiverk Nett AS

REPLACEMENT PLANNING STRATEGY TO OPTIMIZE LIFE CYCLE PROFIT. N-7034 Trondheim Willy Hanssen, Trondheim Energiverk Nett AS REPLACEMENT PLANNING STRATEGY TO OPTIMIZE LIFE CYCLE PROFIT Arnt Ove Eggen, Eivind Solvang Jan A. Foosnæs, Nord-Trøndelag Elektrisitetsverk SINTEF Energy Research Kjell Harald Hansen, Troms Kraft Nett

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

Investor day. November 17, 2010. Energy business Michel Crochon Executive Vice President

Investor day. November 17, 2010. Energy business Michel Crochon Executive Vice President Investor day November 17, 2010 Energy business Michel Crochon Executive Vice President We built a global leadership in medium voltage and grid automation with Areva Distribution MV switchgears & systems

More information

Strategic Plan. New Zealand Fire Service Commission to 2005 2010

Strategic Plan. New Zealand Fire Service Commission to 2005 2010 Strategic Plan New Zealand Fire Service Commission to 2005 2010 Table of contents Forward from the Chairperson...3 Summarises the purpose, content and logic behind the Commission s strategic direction.

More information

Delivering Sustainable Reductions in Infrastructure Costs. An Introduction

Delivering Sustainable Reductions in Infrastructure Costs. An Introduction Delivering Sustainable Reductions in Infrastructure Costs An Introduction Delivering Sustainable Reductions in Infrastructure Costs Contents Introduction to AMCL Overview Our Ethos Our Provenance The Services

More information