Net Present Value and Capital Budgeting. What to Discount

Size: px
Start display at page:

Download "Net Present Value and Capital Budgeting. What to Discount"

Transcription

1 Net Present Value and Capital Budgeting (Text reference: Chapter 7) Topics what to discount the CCA system total project cash flow vs. tax shield approach detailed CCA calculations and examples project interactions AFM NPV and Capital Budgeting Slide 1 What to Discount some general principles: 1. Only cash flow is relevant the NPV rule is stated in terms of cash flows cash flow is a simple idea: dollars in - dollars out don t confuse cash flow with accounting income (note that accounting income is needed in some cases to calculate taxes) 2. Always estimate cash flows on an incremental basis incremental cash flows are the additional cash flows generated by the project. To identify them, ask two questions: What is the cash flow if the project is taken? What is the cash flow if the project is not taken? If the answers differ, then the cash flow is incremental. AFM NPV and Capital Budgeting Slide 2

2 some things to watch for: exclude sunk costs: it is incorrect to include costs which have already been incurred and cannot be recovered include opportunity costs: e.g. a firm owns some land worth $25 million which it is considering using as a new factory site. If the firm builds the factory, it is giving up the $25 million it could have received by selling the land. incorporate side effects: it is important to ensure that all effects on the remainder of a firm s operations are taken into account (e.g. a new product line may reduce sales of existing products) AFM NPV and Capital Budgeting Slide 3 include working capital requirements: most projects will require an additional investment in working capital (e.g. due to increased inventories, accounts receivable, etc.); such investments are typically recovered later on allocated overhead costs: ensure that only those charges which are actually due to a project are allocated to it interest expense: ignore this for now AFM NPV and Capital Budgeting Slide 4

3 3. Treat inflation consistently notation: nominal interest rate i inflation rate π real interest rate r recall the Fisher relation 1 + i = (1 + r) (1 + π) r = 1 + i 1 + π 1 example: if i = 10% and π = 3.5%, what is the FV after 2 years of $10,000 in real and nominal terms? (assume the money is invested at i = 10%) AFM NPV and Capital Budgeting Slide 5 consistency requires that nominal cash flows be discounted at a nominal discount rate and real cash flows be discounted at a real discount rate. For example, suppose that i = 8% and π = 3% and that we have the following real cash flows: NPV in real terms: C 0 C 1 C NPV in nominal terms: AFM NPV and Capital Budgeting Slide 6

4 why does this work? Let C 0,C 1,C 2,... be real cash flows, so: PV nominal = C 0 + C 1(1 + π) 1 + i + C 2(1 + π) 2 (1 + i) = C 0 + C 1(1 + π) (1 + r)(1 + π) + C 2(1 + π) 2 (1 + r) 2 (1 + π) it is important to understand how to use both real and nominal discounting since you sometimes have to use both approaches. This is because some cash flow forecasts (e.g. sales revenue) are often made in real terms, whereas others (e.g. depreciation tax shields) are calculated in nominal terms. AFM NPV and Capital Budgeting Slide 7 for a single cash flow received at period n: C nominal = C real (1 + π) n for a series of cash flows, the growth rate must also be changed (e.g. a perpetuity which is constant in nominal terms is actually decreasing in real terms due to inflation). The relationship between real and nominal growth rates is: (1 + g nominal ) = (1 + g real ) (1 + π) e.g. a perpetuity of $1,000 per year (nominal), with r = 10% and π = 3%: AFM NPV and Capital Budgeting Slide 8

5 some examples (assume i = 10% and π = 5%): 1. perpetuity C nominal = $100, 1st payment at t = 1, g nominal = 2% 2. perpetuity C nominal = $100, 1st payment at t = 4, g real = 2% period annuity C real = $500, 1st payment at t = 1, g real = 4% AFM NPV and Capital Budgeting Slide 9 The CCA System depreciation or capital cost allowance (CCA) is not a cash flow, but it has cash flow consequences because it is deductible from taxable income since CCA reduces taxable income, it increases cash flow assets such as land or securities cannot be depreciated. Others are assigned to various classes, with varying depreciation rates. Table 7A.1 (text p. 219) provides some common classes: e.g. manufacturing and processing equipment is in Class 8 with a 20% rate, brick buildings are in Class 1 with a 4% rate. The depreciation rate d reflects the economic life of the asset. note that all assets of a firm within a particular class are treated as if they are a single asset (a pool ) AFM NPV and Capital Budgeting Slide 10

6 how to calculate CCA: CCA is calculated on a declining balance allows for faster depreciation than straight line receive cash flows from CCA tax shield faster increases NPV of investments the half year rule: in the first year of its life, an asset is depreciated at half the normal rate, i.e. d/2 example: a firm purchases some Class 8 (d = 20%) equipment for $150,000. What CCA can be claimed for the first four years? AFM NPV and Capital Budgeting Slide 11 how to calculate PV of CCA tax shield: assume for now that you keep the asset forever, and ignore the half year rule. We have: Year Beginning UCC CCA Ending UCC 1 C Cd C(1 d) 2 C(1 d) Cd(1 d) C(1 d) 2 3 C(1 d) 2 Cd(1 d) 2 C(1 d) n C(1 d) n 1 Cd(1 d) n 1 C(1 d) n the tax shields are just CCA multiplied by the corporate tax rate T c, so (using k as the discount rate): PV = CdT c 1 + k + CdT c(1 d) (1 + k) 2 + CdT c(1 d) 2 (1 + k) 3 + = CdT c k + d AFM NPV and Capital Budgeting Slide 12

7 now incorporate the half year rule. We have two perpetuities, decreasing at rate d, one with first payment after one year, the other after two years: PV = 1 2 CdT c 1 k + d + 2 CdT c k + d k [ ] k [ ] 12 (1 + k) = CdT c k + d = CdT c k + d = CdT c k + d [ 1 + k k 1 + k ] AFM NPV and Capital Budgeting Slide 13 now assume that the asset is sold for an amount S at the end of year n. If the firm has other assets in this CCA class, this might reduce the PV of the CCA tax shield as follows: PV = CdT c k + d [ 1 + k k ] min(c,s)dt c k + d 1 (1 + k) n note that the above formula is only an example: it and the similar equation (7.6) from p. 203 of the text are not always applicable! AFM NPV and Capital Budgeting Slide 14

8 in general, the following steps apply when a firm sells a CCA eligible asset: 1. The UCC in the asset class is reduced by the lesser of the sale price or the initial cost. 2. If step 1 leaves a negative balance, this amount is added to taxable income (recaptured depreciation), and the UCC of the asset class is reset to zero. 3. If step 1 leaves a positive balance and there are no other assets in the asset class, this amount is deducted from taxable income (terminal loss), and the UCC of the asset class is reset to zero. 4. If step 1 leaves a positive balance and there are assets left in the class, the balance becomes the new UCC for the class. 5. If the asset is sold for more than its initial cost, the difference is a capital gain (50% inclusion rate). 6. Suppose there is a new acquisition in the same year as an asset is sold. Define net acquisitions as acquisitions less disposals. If net acquisitions are > 0, apply the half year rule to net acquisitions; if net acquisitions are < 0, do not apply the half year rule. AFM NPV and Capital Budgeting Slide 15 example: Atlantic Trucking Co. is starting up business and has just purchased its first truck for $25,000. The truck is in Class 10 with a CCA rate of 30%. Calculate applicable CCA for years 1, 2, and 3: Year Beginning UCC CCA Ending UCC now suppose that the firm buys a second truck for $35,000 in year 2 and that it sells the first truck for $7,000 in year 3: AFM NPV and Capital Budgeting Slide 16

9 Year Beginning UCC CCA Ending UCC 1 12,500 3,750 8, instead suppose that the firm buys a second truck for $35,000 in year 2 and that it sells the first truck for $7,000 in year 2: Year Beginning UCC CCA Ending UCC 1 12,500 3,750 8, AFM NPV and Capital Budgeting Slide 17 to illustrate some asset disposition cases, consider the following four scenarios. Here a firm purchased a number of assets in a single class some time ago for $117,000, and at the beginning of the current year, this pool of assets had a UCC of $82,500. Scenario Beginning UCC $82,500 $82,500 $82,500 $82,500 Capital cost of assets sold $35,000 $117,000 $85,000 $117,000 Sale proceeds $12,000 $100,000 $90,000 $50,000 Capital gains UCC after sale Terminal loss Recapture Ending UCC AFM NPV and Capital Budgeting Slide 18

10 Total Project Cash Flow vs. Tax Shield Approach to illustrate, we will consider in detail the MMCC example from the text (pp , ). The information provided includes: Expected life of machine 8 years Costs of test marketing $250,000 Current market value of factory site $0 Cost of machine $800,000 Salvage value after 8 years $150,000 Production in thousands of units (by year) 6, 9, 12, 13, 12, 10, 8, 6 Unit price in first year $100 Growth rate in unit price after first year 2% Unit production costs in first year $64 Growth rate in production costs after first year 5% Corporate tax rate 40% Working capital: initial $40,000 Working capital: end $0 Working capital: during 15% of sales Inflation: 5% Fixed costs: $50,000 per year AFM NPV and Capital Budgeting Slide 19 the total project cash flow approach: the basic idea is to determine the project cash flows year by year, add them up, and discount to obtain NPV some notes: in general, cannot use convenient PV formulas (annuities, perpetuities) requires that all cash flows (for a given year) must be either in real terms or in nominal terms requires that all cash flows be discounted at the same rate must use this approach if we want to calculate IRR, payback, or AAR see spreadsheet handouts for MMCC example AFM NPV and Capital Budgeting Slide 20

11 the tax shield approach: a divide and conquer method recall that after tax operating cash flow = revenues - expenses - taxes since taxable income = revenues - expenses - CCA, we have taxes = T c ( revenues expenses CCA ) this implies after tax operating cash flow = revenues (1 T c ) expenses (1 T c ) + T c CCA see spreadsheet handout for MMCC example AFM NPV and Capital Budgeting Slide 21 Detailed CCA Calculations and Examples assume that salvage takes place at the end of year n, and consider the following formula for the PV of CCA tax shields: PV of CCA = CdT c k + d [ ] 1 + k 2 UCCdT c (1 + k) n 1 + k k + d UCC depends on circumstances. Let the undepreciated capital cost of the asset class just before the asset is disposed of be UCC n. if the firm only ever has one asset in the class, then UCC n = C(1 d/2)(1 d) n 1 AFM NPV and Capital Budgeting Slide 22

12 Calculate the value X = UCC n min(c,s). Then: 1. If X < 0 recaptured depreciation add X to taxable income in year n: PV of recapture = set UCC of asset class to zero (so UCC = UCC n ): PV of CCA = CdT c k + d XT c (1 + k) n [ ] 1 + k 2 UCC ndt c (1 + k) n 1 + k k + d AFM NPV and Capital Budgeting Slide If X > 0 and there are no other assets in the class terminal loss subtract X from taxable income in year n: PV of terminal loss = XT c (1 + k) n set UCC of asset class to zero (so UCC = UCC n ): [ ] PV of CCA = CdT c 1 + k 2 UCC ndt c k + d 1 + k k + d (1 + k) n AFM NPV and Capital Budgeting Slide 24

13 3. If X > 0 and there are other assets in the class X becomes the new UCC of the asset class (so UCC = min(c,s)): PV of CCA = CdT c k + d [ 1 + k k three further points: 1. If S > C, there is a capital gain: ] min(c,s)dt c k + d (1 + k) n PV of tax liability = (S C)T c /2 (1 + k) n 2. Formulas for CCA tax shields are always given in nominal terms. AFM NPV and Capital Budgeting Slide The formulas given on the preceding slides have a half year rule adjustment applied to the first term but not the second term. This may not always be the case: the half year rule may instead be applied to both terms, neither term, or the second term but not the first, depending on circumstances. In particular, the net acquisitions rule works as follows. Recall that all assets of a given firm within a single CCA class are treated as part of a common pool. In practice, firms often buy and sell many assets in a single class within a year. Define net acquisitions for an asset class as the total capital cost of all acquisitions (in a year) less the total adjusted cost of all disposals within that class and in that year. If net acquisitions is positive, apply the half year rule. If net acquisitions is negative, there is no adjustment for the half year rule. AFM NPV and Capital Budgeting Slide 26

14 illustrative problem: you are considering whether to undertake a project that will generate revenues of $50,000 per year for 8 years and expenses of $20,000 per year for 8 years. The project requires an investment of $150,000 today in class 8 machinery (d = 25%). Assume k = 12%, T c = 40%, and all cash flows are nominal, and calculate project NPV under the following scenarios: 1. You always have many other class 8 assets and a positive UCC in that class and you can salvage the machinery at the end of the 9th year for (i) $10,000; and (ii) $200,000. (Assume there are no other acquisitions or disposals of class 8 assets in either the current year or in the 9th year.) 2. The machinery will always be in its own class and it can be salvaged in 9 years for (i) $10,000; (ii) $20,000; and (iii) $200, From this point on, the machinery will be in its own class and it can be salvaged in 9 years for $10,000. However, you purchased one other class 8 asset 5 years ago for $200,000 which you have just sold for (i) $100,000; and (ii) $175,000. AFM NPV and Capital Budgeting Slide (i) Cost of machine: -$150, PV after-tax operating revenues: $149, PV after-tax operating expenses: -$59, PV salvage: $3, PV perpetual tax shield on $150,000: $38, PV lost tax shield: -$ NPV: -$19, AFM NPV and Capital Budgeting Slide 28

15 1. (ii) Cost of machine: -$150, PV after-tax operating revenues: $149, PV after-tax operating expenses: -$59, PV salvage: $72, PV capital gain tax: -$3, PV perpetual tax shield on $150,000: $38, PV lost tax shield: -$14, NPV: $31, AFM NPV and Capital Budgeting Slide (i) Cost of machine: -$150, PV after-tax operating revenues: $149, PV after-tax operating expenses: -$59, PV salvage: $3, PV perpetual tax shield on $150,000: $38, PV lost tax shield: -$1, PV terminal loss: $ NPV: -$19, AFM NPV and Capital Budgeting Slide 30

16 2. (ii) Cost of machine: -$150, PV after-tax operating revenues: $149, PV after-tax operating expenses: -$59, PV salvage: $7, PV perpetual tax shield on $150,000: $38, PV lost tax shield: -$1, PV recapture: -$ NPV: -$17, AFM NPV and Capital Budgeting Slide (iii) Cost of machine: -$150, PV after-tax operating revenues: $149, PV after-tax operating expenses: -$59, PV salvage: $72, PV capital gain tax: -$3, PV perpetual tax shield on $150,000: $38, PV lost tax shield: -$1, PV recapture: -$19, NPV: $25, AFM NPV and Capital Budgeting Slide 32

17 3. (i) Cost of machine: -$150, PV after-tax operating revenues: $149, PV after-tax operating expenses: -$59, PV salvage: $3, PV perpetual tax shield on $50,000: $12, PV continuing tax shield on $55, $14, PV lost tax shield: -$ PV recapture (year 9): -$ PV avoided recapture today: $17, NPV: -$12, AFM NPV and Capital Budgeting Slide (ii) Cost of machine: -$150, PV after-tax operating revenues: $149, PV after-tax operating expenses: -$59, PV salvage: $3, PV perpetual tax shield on $30,371.09: $8, PV lost tax shield: -$ PV recapture (year 9): -$1, PV avoided recapture today: $47, NPV: -$2, AFM NPV and Capital Budgeting Slide 34

18 Project Interactions many projects have effects on others, e.g. it is important to incorporate effects on other aspects of a firm s business in capital budgeting analysis (including opportunity costs), and CCA pooling of assets can lead to other interactions between projects another aspect of this is choosing between investments of unequal lives. Suppose that two machines produce the same output but have the following after-tax operating costs per year: Machine C 0 C 1 C 2 C 3 A -1, B -2, At a 10% discount rate, which is cheaper to operate? AFM NPV and Capital Budgeting Slide 35 the replacement chain: why not just use NPV and choose the machine with lower discounted costs? assume that machines are needed forever the matching cycle approach: run the example for 6 years. A has 3 complete cycles, B has 2: PV of costs over 6 years: AFM NPV and Capital Budgeting Slide 36

19 the equivalent annual cost (EAC) approach: idea is to convert PV of costs for machine into an appropriate annuity: firm is indifferent between PV of costs and EAC since the project is assumed to continue forever, the EAC lasts forever, so choose the machine with lower EAC AFM NPV and Capital Budgeting Slide 37 when to replace an old machine? 1. Calculate EAC for new machine (EAC new ) 2. Calculate cost of operating old machine for 1 more year (C old ) 3. Replace just before C old > EAC new example: a firm has an existing machine, which could be salvaged for $2,800 today, $2,100 after one year, $1,200 after two years, or zero after 3 years (at which point it would have to be replaced). Maintenance costs on this old machine are $1,175 after one year, $1,600 after two years, and $1,800 after three years. A new machine is available which costs $5,000 and can be salvaged after four years for $1,800. Its maintenance costs are $1,000 after one year, $1,250 after two years, $1,500 after three years, and $2,000 after four years. The new machine produces the same output as the old machine. When should the firm replace the old machine? Assume a discount rate of 10%. AFM NPV and Capital Budgeting Slide 38

20 the EAC for the new machine is: should the existing machine be replaced now? AFM NPV and Capital Budgeting Slide 39 what about replacing it after one year? note that these types of decisions can easily get far more complicated (e.g. different output levels for the machines, different numbers of machines required, anticipated new technology, etc.) AFM NPV and Capital Budgeting Slide 40

Cash Flow, Taxes, and Project Evaluation. Remember Income versus Cashflow

Cash Flow, Taxes, and Project Evaluation. Remember Income versus Cashflow Cash Flow, Taxes, and Project Evaluation Of the four steps in calculating NPV, the most difficult is the first: Forecasting cash flows. We now focus on this problem, with special attention to What is cash

More information

Capital Budgeting Further Considerations

Capital Budgeting Further Considerations Capital Budgeting Further Considerations For 9.220, Term 1, 2002/03 02_Lecture10.ppt Lecture Outline Introduction The input for evaluating projects relevant cash flows Inflation: real vs. nominal analysis

More information

CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS

CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS Answers to Concepts Review and Critical Thinking Questions 1. In this context, an opportunity cost refers to the value of an asset or other input that will

More information

Strategy and Analysis in Using NPV. How Positive NPV Arises

Strategy and Analysis in Using NPV. How Positive NPV Arises Strategy and Analysis in Using NPV (Text reference: Chapter 8) Topics how positive NPV arises decision trees sensitivity analysis scenario analysis break-even analysis investment options AFM 271 - Strategy

More information

Chapter 9 Cash Flow and Capital Budgeting

Chapter 9 Cash Flow and Capital Budgeting Chapter 9 Cash Flow and Capital Budgeting MULTIPLE CHOICE 1. Gamma Electronics is considering the purchase of testing equipment that will cost $500,000. The equipment has a 5-year lifetime with no salvage

More information

Capital Budgeting Cash Flows

Capital Budgeting Cash Flows Learning Objectives 1-1 Capital Budgeting Cash Flows 1 Corporate Financial Management 3e Emery Finnerty Stowe 1-2 Calculate incremental after-tax cash flows for a capital budgeting project. Explain the

More information

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Basic 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After two years, the

More information

Chapter 10: Making Capital Investment Decisions

Chapter 10: Making Capital Investment Decisions Chapter 10: Making Capital Investment Decisions Faculty of Business Administration Lakehead University Spring 2003 May 21, 2003 Outline 10.1 Project Cash Flows: A First Look 10.2 Incremental Cash Flows

More information

Oklahoma State University Spears School of Business. Capital Investments

Oklahoma State University Spears School of Business. Capital Investments Oklahoma State University Spears School of Business Capital Investments Slide 2 Incremental Cash Flows Cash flows matter not accounting earnings. Sunk costs do not matter. Incremental cash flows matter.

More information

CHAPTER 7: NPV AND CAPITAL BUDGETING

CHAPTER 7: NPV AND CAPITAL BUDGETING CHAPTER 7: NPV AND CAPITAL BUDGETING I. Introduction Assigned problems are 3, 7, 34, 36, and 41. Read Appendix A. The key to analyzing a new project is to think incrementally. We calculate the incremental

More information

DUKE UNIVERSITY Fuqua School of Business. FINANCE 351 - CORPORATE FINANCE Problem Set #1 Prof. Simon Gervais Fall 2011 Term 2.

DUKE UNIVERSITY Fuqua School of Business. FINANCE 351 - CORPORATE FINANCE Problem Set #1 Prof. Simon Gervais Fall 2011 Term 2. DUKE UNIVERSITY Fuqua School of Business FINANCE 351 - CORPORATE FINANCE Problem Set #1 Prof. Simon Gervais Fall 2011 Term 2 Questions 1. Two years ago, you put $20,000 dollars in a savings account earning

More information

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After three years, the project

More information

Which projects should the corporation undertake

Which projects should the corporation undertake Which projects should the corporation undertake Investment criteria 1. Investment into a new project generates a flow of cash and, therefore, a standard DPV rule should be the first choice under consideration.

More information

How To Calculate Discounted Cash Flow

How To Calculate Discounted Cash Flow Chapter 1 The Overall Process Capital Expenditures Whenever we make an expenditure that generates a cash flow benefit for more than one year, this is a capital expenditure. Examples include the purchase

More information

Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6. Part One. Multiple Choice Questions.

Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6. Part One. Multiple Choice Questions. Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6 Part One. Multiple Choice Questions. 1. Similar to the example given in class, assume that a corporation has $500 of cash revenue and $300

More information

( ) ( )( ) ( ) 2 ( ) 3. n n = 100 000 1+ 0.10 = 100 000 1.331 = 133100

( ) ( )( ) ( ) 2 ( ) 3. n n = 100 000 1+ 0.10 = 100 000 1.331 = 133100 Mariusz Próchniak Chair of Economics II Warsaw School of Economics CAPITAL BUDGETING Managerial Economics 1 2 1 Future value (FV) r annual interest rate B the amount of money held today Interest is compounded

More information

Chapter 09 - Using Discounted Cash-Flow Analysis to Make Investment Decisions

Chapter 09 - Using Discounted Cash-Flow Analysis to Make Investment Decisions Solutions to Chapter 9 Using Discounted Cash-Flow Analysis to Make Investment Decisions 1. Net income = ($74 $42 $10) [0.35 ($74 $42 $10)] = $22 $7.7 = $14.3 million Revenues cash expenses taxes paid =

More information

Course 3: Capital Budgeting Analysis

Course 3: Capital Budgeting Analysis Excellence in Financial Management Course 3: Capital Budgeting Analysis Prepared by: Matt H. Evans, CPA, CMA, CFM This course provides a concise overview of capital budgeting analysis. This course is recommended

More information

Chapter 6. 1. Your firm is considering two investment projects with the following patterns of expected future net aftertax cash flows:

Chapter 6. 1. Your firm is considering two investment projects with the following patterns of expected future net aftertax cash flows: Chapter 6 1. Your firm is considering two investment projects with the following patterns of expected future net aftertax cash flows: Year Project A Project B 1 $1 million $5 million 2 2 million 4 million

More information

Chapter 9. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60 $12.36 $1.00 $2.06 $5.18 $3.11

Chapter 9. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60 $12.36 $1.00 $2.06 $5.18 $3.11 Chapter 9 9-1 We assume that revenues and selling & administrative expenses will increase at the rate of inflation. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60

More information

Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows

Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows Chapter 7: 1,5,7,8,27,32 Chapter 8: 1,3,5,8,13 (clarification for problem 13b:

More information

Chapter 7 Fundamentals of Capital Budgeting

Chapter 7 Fundamentals of Capital Budgeting Chapter 7 Fundamentals of Capital Budgeting 7-1. Pisa Pizza, a seller of frozen pizza, is considering introducing a healthier version of its pizza that will be low in cholesterol and contain no trans fats.

More information

Net Present Value and Other Investment Criteria

Net Present Value and Other Investment Criteria Net Present Value and Other Investment Criteria Topics Covered Net Present Value Other Investment Criteria Mutually Exclusive Projects Capital Rationing Net Present Value Net Present Value - Present value

More information

Part 7. Capital Budgeting

Part 7. Capital Budgeting Part 7. Capital Budgeting What is Capital Budgeting? Nancy Garcia and Digital Solutions Digital Solutions, a software development house, is considering a number of new projects, including a joint venture

More information

CAPITAL BUDGETING. Definition. Time Value of Money [TVM] TVM is the reward for postponement of consumption of money.

CAPITAL BUDGETING. Definition. Time Value of Money [TVM] TVM is the reward for postponement of consumption of money. 11 CAPITAL BUDGETING 1LO 1: Time Value of Money Definition Time Value of Money [TVM] TVM is the reward for postponement of consumption of money. Principle Rs.100 received today is greater than Rs. 100

More information

DEPRECIATION AND INCOME TAX

DEPRECIATION AND INCOME TAX Dr. Hassan, Y. 91.380 1 DEPRECIATIO AD ICOME TAX General Depreciation is a decrease in worth Production equipment gradually becomes less valuable though wear Instead of charging the full purchase price

More information

1.1 Introduction. Chapter 1: Feasibility Studies: An Overview

1.1 Introduction. Chapter 1: Feasibility Studies: An Overview Chapter 1: Introduction 1.1 Introduction Every long term decision the firm makes is a capital budgeting decision whenever it changes the company s cash flows. Consider launching a new product. This involves

More information

5. Time value of money

5. Time value of money 1 Simple interest 2 5. Time value of money With simple interest, the amount earned each period is always the same: i = rp o We will review some tools for discounting cash flows. where i = interest earned

More information

Capital Budgeting Formula

Capital Budgeting Formula apital Budgeting Formula Not in the book. Wei s summary If salvage value S is less than U n : If salvage value S is greater than U n : Note: IF t : incremental cash flows (could be negative) )(NW): change

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Financial Evaluation

More information

CHAPTER 5. Interest Rates. Chapter Synopsis

CHAPTER 5. Interest Rates. Chapter Synopsis CHAPTER 5 Interest Rates Chapter Synopsis 5.1 Interest Rate Quotes and Adjustments Interest rates can compound more than once per year, such as monthly or semiannually. An annual percentage rate (APR)

More information

Using Discounted Cash- Flow Analysis to Make Investment Decisions

Using Discounted Cash- Flow Analysis to Make Investment Decisions Chapter 7 Using Discounted Cash- Flow Analysis to Make Investment Decisions 7.1 Discount Cash Flows, Not Profits 7.2 Discount Incremental Cash Flows 7.3 Discount Nominal Cash Flows by the Nominal Cost

More information

Chapter 5 Capital Budgeting

Chapter 5 Capital Budgeting Chapter 5 Capital Budgeting Road Map Part A Introduction to finance. Part B Valuation of assets, given discount rates. Fixed-Income securities. Common stocks. Real assets (capital budgeting). Part C Determination

More information

Capital Investment Analysis and Project Assessment

Capital Investment Analysis and Project Assessment PURDUE EXTENSION EC-731 Capital Investment Analysis and Project Assessment Michael Boehlje and Cole Ehmke Department of Agricultural Economics Capital investment decisions that involve the purchase of

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

EXAM 2 OVERVIEW. Binay Adhikari

EXAM 2 OVERVIEW. Binay Adhikari EXAM 2 OVERVIEW Binay Adhikari FEDERAL RESERVE & MARKET ACTIVITY (BS38) Definition 4.1 Discount Rate The discount rate is the periodic percentage return subtracted from the future cash flow for computing

More information

Chapter 14 Demonstration Problem Solutions Page 1

Chapter 14 Demonstration Problem Solutions Page 1 Chapter 14 Demonstration Problem Solutions Page 1 Demo 14-1 ANSWER a. First, we need to calculate the tax bill: Year (A) (B) (CA-B) (D.4C) Cash Flow Depreciation Taxable Inc Tx Rate Taxes 1 $ 100,000 -

More information

The Time Value of Money

The Time Value of Money The Time Value of Money Future Value - Amount to which an investment will grow after earning interest. Compound Interest - Interest earned on interest. Simple Interest - Interest earned only on the original

More information

CHAPTER 14 COST OF CAPITAL

CHAPTER 14 COST OF CAPITAL CHAPTER 14 COST OF CAPITAL Answers to Concepts Review and Critical Thinking Questions 1. It is the minimum rate of return the firm must earn overall on its existing assets. If it earns more than this,

More information

Real Estate. Refinancing

Real Estate. Refinancing Introduction This Solutions Handbook has been designed to supplement the HP-2C Owner's Handbook by providing a variety of applications in the financial area. Programs and/or step-by-step keystroke procedures

More information

MBA 8130 FOUNDATIONS OF CORPORATION FINANCE FINAL EXAM VERSION A

MBA 8130 FOUNDATIONS OF CORPORATION FINANCE FINAL EXAM VERSION A MBA 8130 FOUNDATIONS OF CORPORATION FINANCE FINAL EXAM VERSION A Fall Semester 2004 Name: Class: Day/Time/Instructor:. Read the following directions very carefully. Failure to follow these directions will

More information

ADVANCED INVESTMENT APPRAISAL

ADVANCED INVESTMENT APPRAISAL RELEVANT TO ACCA QUALIFICATION PAPER F9 Studying Paper F9? Performance objectives 15 and 16 are relevant to this exam Investment appraisal is one of the eight core topics within Paper F9, Financial Management

More information

What is the net present value of the project (to the nearest thousand dollars)?

What is the net present value of the project (to the nearest thousand dollars)? corporate finance, final exam practice questions, NPV *Question 1.1: Net Present Value A firm invests $200,000 in machinery that yields net after-tax cash flows of $90,000 at the end of each of the next

More information

Chapter 7: Net Present Value and Capital Budgeting

Chapter 7: Net Present Value and Capital Budgeting Chapter 7: Net Present Value and Capital Budgeting 7.1 a. Yes, the reduction in the sales of the company s other products, referred to as erosion, should be treated as an incremental cash flow. These lost

More information

(Relevant to AAT Examination Paper 4 Business Economics and Financial Mathematics)

(Relevant to AAT Examination Paper 4 Business Economics and Financial Mathematics) Capital Budgeting: Net Present Value vs Internal Rate of Return (Relevant to AAT Examination Paper 4 Business Economics and Financial Mathematics) Y O Lam Capital budgeting assists decision makers in a

More information

Chapter 20 Lease Financing ANSWERS TO END-OF-CHAPTER QUESTIONS

Chapter 20 Lease Financing ANSWERS TO END-OF-CHAPTER QUESTIONS Chapter 20 Lease Financing ANSWERS TO END-OF-CHAPTER QUESTIONS 20-1 a. The lessee is the party leasing the property. The party receiving the payments from the lease (that is, the owner of the property)

More information

$1,300 + 1,500 + 1,900 = $4,700. in cash flows. The project still needs to create another: $5,500 4,700 = $800

$1,300 + 1,500 + 1,900 = $4,700. in cash flows. The project still needs to create another: $5,500 4,700 = $800 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After three years, the project has created: $1,300 + 1,500 + 1,900 = $4,700 in cash flows.

More information

3. Time value of money. We will review some tools for discounting cash flows.

3. Time value of money. We will review some tools for discounting cash flows. 1 3. Time value of money We will review some tools for discounting cash flows. Simple interest 2 With simple interest, the amount earned each period is always the same: i = rp o where i = interest earned

More information

Capital Budgeting Final Analysis

Capital Budgeting Final Analysis Capital Budgeting Final Analysis For 9.220 Students, Term 1, 2002/03 02_Lecture11.ppt Lecture Outline Introduction CCA Detailed Calculations Capital Gains Taxes Summary of Capital Budgeting Items and Tax

More information

CHAPTER 9 Time Value Analysis

CHAPTER 9 Time Value Analysis Copyright 2008 by the Foundation of the American College of Healthcare Executives 6/11/07 Version 9-1 CHAPTER 9 Time Value Analysis Future and present values Lump sums Annuities Uneven cash flow streams

More information

Solutions to Chapter 8. Net Present Value and Other Investment Criteria

Solutions to Chapter 8. Net Present Value and Other Investment Criteria Solutions to Chapter 8 Net Present Value and Other Investment Criteria. NPV A = $00 + [$80 annuity factor (%, periods)] = $00 $80 $8. 0 0. 0. (.) NPV B = $00 + [$00 annuity factor (%, periods)] = $00 $00

More information

Chapter 7. Net Present Value and Other Investment Criteria

Chapter 7. Net Present Value and Other Investment Criteria Chapter 7 Net Present Value and Other Investment Criteria 7-2 Topics Covered Net Present Value Other Investment Criteria Mutually Exclusive Projects Capital Rationing 7-3 Net Present Value Net Present

More information

Week- 1: Solutions to HW Problems

Week- 1: Solutions to HW Problems Week- 1: Solutions to HW Problems 10-1 a. Payback A (cash flows in thousands): Annual Period Cash Flows Cumulative 0 ($5,000) ($5,000) 1 5,000 (0,000) 10,000 (10,000) 3 15,000 5,000 4 0,000 5,000 Payback

More information

Chapter 9 Making Capital Investment Decisions Introduction

Chapter 9 Making Capital Investment Decisions Introduction Chapter 9 Making Capital Investment Decisions Introduction The cash flows that should be included in a capital budgeting analysis are those that will only occur if the project is accepted These cash flows

More information

Final Examination, BUS312, D1+ E1. SFU Student number:

Final Examination, BUS312, D1+ E1. SFU Student number: Final Examination, BUS312, D1+ E1 NAME: SFU Student number: Instructions: For qualitative questions, point form is not an acceptable answer. For quantitative questions, an indication of how you arrived

More information

The table for the present value of annuities (Appendix A, Table 4) shows: 10 periods at 14% = 5.216. = 3.93 years

The table for the present value of annuities (Appendix A, Table 4) shows: 10 periods at 14% = 5.216. = 3.93 years 21-18 Capital budgeting methods, no income taxes. The table for the present value of annuities (Appendix A, Table 4) shows: 10 periods at 14% 5.216 1a. Net present value $28,000 (5.216) $146,048 $36,048

More information

Chapter Review and Self-Test Problems

Chapter Review and Self-Test Problems 340 PART FOUR Capital Budgeting costs and cash revenues and costs. We also went over the calculation of depreciation expense under current tax law. 4. Some special cases encountered in using discounted

More information

How To Calculate A Profit From A Machine Shop

How To Calculate A Profit From A Machine Shop CHAPTER 21 CAPITAL BUDGETING AND COST ANALYSIS 21-20 Capital budgeting with uneven cash flows, no income taxes. 1. Present value of savings in cash operating costs: $10,000 0.862 $ 8,620 8,000 0.743 5,944

More information

Chapter 8: Using DCF Analysis to Make Investment Decisions

Chapter 8: Using DCF Analysis to Make Investment Decisions FIN 301 Class Notes Chapter 8: Using DCF Analysis to Make Investment Decisions Capital Budgeting: is the process of planning for capital expenditures (long term investment). Planning process involves 1-

More information

Time Value of Money (TVM)

Time Value of Money (TVM) BUSI Financial Management Time Value of Money 1 Time Value of Money (TVM) Present value and future value how much is $1 now worth in the future? how much is $1 in the future worth now? Business planning

More information

FIN 614 Cash Flow Forecasting. Professor Robert B.H. Hauswald Kogod School of Business, AU. Vitamin C. Cash flows matter: focus on economics

FIN 614 Cash Flow Forecasting. Professor Robert B.H. Hauswald Kogod School of Business, AU. Vitamin C. Cash flows matter: focus on economics FIN 64 Cash Flow Forecasting Professor Robert B.H. Hauswald Kogod School of Business, AU Vitamin C Cash flows matter: focus on economics not earnings or other accounting measures Continue our focus on

More information

University of Rio Grande Fall 2010

University of Rio Grande Fall 2010 University of Rio Grande Fall 2010 Financial Management (Fin 20403) Practice Questions for Midterm 1 Answers the questions. (Or Identify the letter of the choice that best completes the statement if there

More information

Time Value of Money. Background

Time Value of Money. Background Time Value of Money (Text reference: Chapter 4) Topics Background One period case - single cash flow Multi-period case - single cash flow Multi-period case - compounding periods Multi-period case - multiple

More information

Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS

Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS 11-1 a. Cash flow, which is the relevant financial variable, represents the actual flow of cash. Accounting

More information

Chapter 6. Learning Objectives Principles Used in This Chapter 1. Annuities 2. Perpetuities 3. Complex Cash Flow Streams

Chapter 6. Learning Objectives Principles Used in This Chapter 1. Annuities 2. Perpetuities 3. Complex Cash Flow Streams Chapter 6 Learning Objectives Principles Used in This Chapter 1. Annuities 2. Perpetuities 3. Complex Cash Flow Streams 1. Distinguish between an ordinary annuity and an annuity due, and calculate present

More information

Performing Net Present Value (NPV) Calculations

Performing Net Present Value (NPV) Calculations Strategies and Mechanisms For Promoting Cleaner Production Investments In Developing Countries Profiting From Cleaner Production Performing Net Present Value (NPV) Calculations Cleaner Production Profiting

More information

Project Evaluation Roadmap. Capital Budgeting Process. Capital Expenditure. Major Cash Flow Components. Cash Flows... COMM2501 Financial Management

Project Evaluation Roadmap. Capital Budgeting Process. Capital Expenditure. Major Cash Flow Components. Cash Flows... COMM2501 Financial Management COMM501 Financial Manageent Project Evaluation 1 (Capital Budgeting) Project Evaluation Roadap COMM501 Financial Manageent Week 7 Week 7 Project dependencies Net present value ethod Relevant cash flows

More information

Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14

Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14 Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14 I. Additional Issues in Capital Budgeting. A. Capital rationing: Use profitability index

More information

10.SHORT-TERM DECISIONS & CAPITAL INVESTMENT APPRAISAL

10.SHORT-TERM DECISIONS & CAPITAL INVESTMENT APPRAISAL INDUSTRIAL UNIVERSITY OF HO CHI MINH CITY AUDITING ACCOUNTING FACULTY 10.SHORT-TERM DECISIONS & CAPITAL INVESTMENT APPRAISAL 4 Topic List INDUSTRIAL UNIVERSITY OF HO CHI MINH CITY AUDITING ACCOUNTING FACULTY

More information

Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS

Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS 13-3 Since the cost of capital includes a premium for expected inflation, failure to adjust cash

More information

Management Accounting Financial Strategy

Management Accounting Financial Strategy PAPER P9 Management Accounting Financial Strategy The Examiner provides a short study guide, for all candidates revising for this paper, to some first principles of finance and financial management Based

More information

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs 385 356 PART FOUR Capital Budgeting a large number of NPV estimates that we summarize by calculating the average value and some measure of how spread out the different possibilities are. For example, it

More information

Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions

Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions Chapter 8 Capital Budgeting Concept Check 8.1 1. What is the difference between independent and mutually

More information

Paper F9. Financial Management. Fundamentals Pilot Paper Skills module. The Association of Chartered Certified Accountants

Paper F9. Financial Management. Fundamentals Pilot Paper Skills module. The Association of Chartered Certified Accountants Fundamentals Pilot Paper Skills module Financial Management Time allowed Reading and planning: Writing: 15 minutes 3 hours ALL FOUR questions are compulsory and MUST be attempted. Do NOT open this paper

More information

Chapter 10. What is capital budgeting? Topics. The Basics of Capital Budgeting: Evaluating Cash Flows

Chapter 10. What is capital budgeting? Topics. The Basics of Capital Budgeting: Evaluating Cash Flows Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows 1 Topics Overview and vocabulary Methods NPV IRR, MIRR Profitability Index Payback, discounted payback Unequal lives Economic life 2 What

More information

Fundamentals Level Skills Module, Paper F9. Section A. Monetary value of return = $3 10 x 1 197 = $3 71 Current share price = $3 71 $0 21 = $3 50

Fundamentals Level Skills Module, Paper F9. Section A. Monetary value of return = $3 10 x 1 197 = $3 71 Current share price = $3 71 $0 21 = $3 50 Answers Fundamentals Level Skills Module, Paper F9 Financial Management December 2014 Answers Section A 1 A Monetary value of return = $3 10 x 1 197 = $3 71 Current share price = $3 71 $0 21 = $3 50 2

More information

Things to do before the first class meeting

Things to do before the first class meeting FINANCE 351 Corporate Finance John Graham Things to do before the first class meeting C Read the Gifford and Brealey and Myers material (see class schedule) C Read over the syllabus and class schedule.

More information

Fundamentals of Capital Budgeting

Fundamentals of Capital Budgeting 8 Fundamentals of Capital Budgeting LEARNING OBJECTIVES Identify the types of cash flows needed in the capital budgeting process Forecast incremental earnings in a pro forma earnings statement for a project

More information

Measuring Investment Returns

Measuring Investment Returns Measuring Investment Returns Aswath Damodaran Stern School of Business Aswath Damodaran 156 First Principles Invest in projects that yield a return greater than the minimum acceptable hurdle rate. The

More information

Introduction to Discounted Cash Flow and Project Appraisal. Charles Ward

Introduction to Discounted Cash Flow and Project Appraisal. Charles Ward Introduction to Discounted Cash Flow and Project Appraisal Charles Ward Company investment decisions How firms makes investment decisions about real projects (not necessarily property) How to decide which

More information

How To Compare The Pros And Cons Of A Combine To A Lease Or Buy

How To Compare The Pros And Cons Of A Combine To A Lease Or Buy Leasing vs. Buying Farm Machinery Department of Agricultural Economics MF-2953 www.agmanager.info Machinery and equipment expense typically represents a major cost in agricultural production. Purchasing

More information

CHAPTER 4 DISCOUNTED CASH FLOW VALUATION

CHAPTER 4 DISCOUNTED CASH FLOW VALUATION CHAPTER 4 DISCOUNTED CASH FLOW VALUATION Solutions to Questions and Problems NOTE: All-end-of chapter problems were solved using a spreadsheet. Many problems require multiple steps. Due to space and readability

More information

CALCULATOR TUTORIAL. Because most students that use Understanding Healthcare Financial Management will be conducting time

CALCULATOR TUTORIAL. Because most students that use Understanding Healthcare Financial Management will be conducting time CALCULATOR TUTORIAL INTRODUCTION Because most students that use Understanding Healthcare Financial Management will be conducting time value analyses on spreadsheets, most of the text discussion focuses

More information

1 (a) Net present value of investment in new machinery Year 1 2 3 4 5 $000 $000 $000 $000 $000 Sales income 6,084 6,327 6,580 6,844

1 (a) Net present value of investment in new machinery Year 1 2 3 4 5 $000 $000 $000 $000 $000 Sales income 6,084 6,327 6,580 6,844 Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2013 Answers 1 (a) Net present value of investment in new machinery Year 1 2 3 4 5 $000 $000 $000 $000 $000 Sales income 6,084

More information

Numbers 101: Taxes, Investment, and Depreciation

Numbers 101: Taxes, Investment, and Depreciation The Anderson School at UCLA POL 2000-20 Numbers 101: Taxes, Investment, and Depreciation Copyright 2002 by Richard P. Rumelt. In the Note on Cost and Value over Time (POL 2000-09), we introduced the basic

More information

5.5 The Opportunity Cost of Capital

5.5 The Opportunity Cost of Capital Problems 161 The correct discount rate for a cash flow is the expected return available in the market on other investments of comparable risk and term. If the interest on an investment is taxed at rate

More information

How To Get A Profit From A Machine

How To Get A Profit From A Machine Vol. 2, Chapter 4 Capital Budgeting Problem 1: Solution Answers found using Excel formulas: 1. Amount invested = $10,000 $21,589.25 Compounding period = annually Number of years = 10 Annual interest rate

More information

CHAPTER 8 INTEREST RATES AND BOND VALUATION

CHAPTER 8 INTEREST RATES AND BOND VALUATION CHAPTER 8 INTEREST RATES AND BOND VALUATION Solutions to Questions and Problems 1. The price of a pure discount (zero coupon) bond is the present value of the par value. Remember, even though there are

More information

$20,000 invoice price 1,500 sales tax 500 freight 200 set-up (contractor) $22,200 total cost

$20,000 invoice price 1,500 sales tax 500 freight 200 set-up (contractor) $22,200 total cost Section 2 DEPRECIATION UNDER GAAP (FOR BOOK PURPOSES) Introduction Most plant and equipment assets wear out or become obsolete over the years. Similarly, although land is not depreciated (because it does

More information

Chapter 8: Fundamentals of Capital Budgeting

Chapter 8: Fundamentals of Capital Budgeting Chapter 8: Fundamentals of Capital Budgeting-1 Chapter 8: Fundamentals of Capital Budgeting Big Picture: To value a project, we must first estimate its cash flows. Note: most managers estimate a project

More information

Net Present Value (NPV)

Net Present Value (NPV) Investment Criteria 208 Net Present Value (NPV) What: NPV is a measure of how much value is created or added today by undertaking an investment (the difference between the investment s market value and

More information

CHAPTER 10. EVALUATING PROPOSED CAPITAL EXPENDITURES Table of Contents

CHAPTER 10. EVALUATING PROPOSED CAPITAL EXPENDITURES Table of Contents CHAPTER 10 EVALUATING PROPOSED CAPITAL EXPENDITURES Table of Contents Section Description Page 1000 INTRODUCTION... 10-1 1001 ANALYZING THE CURRENT SITUATION... 10-2.2 Using a Diagnostic Approach... 10-3.4

More information

Manage Risk with Fixed Assets

Manage Risk with Fixed Assets Manage Risk with Fixed Assets Presented by: V. Lynn Lambert, CPA Lambert Lanoue & Smoker LLC www.lambertcpas.com Outline Analysis of Lease vs Purchase of Fixed Assets New IRS Repair Regulations Capital

More information

CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Answers to Concepts Review and Critical Thinking Questions 1. Assuming conventional cash flows, a payback period less than the project s life means

More information

] (3.3) ] (1 + r)t (3.4)

] (3.3) ] (1 + r)t (3.4) Present value = future value after t periods (3.1) (1 + r) t PV of perpetuity = C = cash payment (3.2) r interest rate Present value of t-year annuity = C [ 1 1 ] (3.3) r r(1 + r) t Future value of annuity

More information

CARNEGIE MELLON UNIVERSITY CIO INSTITUTE

CARNEGIE MELLON UNIVERSITY CIO INSTITUTE CARNEGIE MELLON UNIVERSITY CIO INSTITUTE CAPITAL BUDGETING BASICS Contact Information: Lynne Pastor Email: lp23@andrew.cmu.edu RELATED LEARNGING OBJECTIVES 7.2 LO 3: Compare and contrast the implications

More information

Fundamentals Level Skills Module, Paper F9

Fundamentals Level Skills Module, Paper F9 Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2008 Answers 1 (a) Calculation of weighted average cost of capital (WACC) Cost of equity Cost of equity using capital asset

More information

How To Calculate The Value Of A Project

How To Calculate The Value Of A Project Chapter 02 How to Calculate Present Values Multiple Choice Questions 1. The present value of $100 expected in two years from today at a discount rate of 6% is: A. $116.64 B. $108.00 C. $100.00 D. $89.00

More information

Financial Accounting and Reporting Exam Review. Fixed Assets. Chapter Five. Black CPA Review www.blackcpareview.com Chapter 5

Financial Accounting and Reporting Exam Review. Fixed Assets. Chapter Five. Black CPA Review www.blackcpareview.com Chapter 5 Fixed Assets Chapter Five Black CPA Review www.blackcpareview.com Chapter 5 Objectives: Objective 1: Know which costs associated with the purchase of fixed assets are capitalized Objective 2: Understand

More information