Seasonal & Pumped Storage Hydro for Yukon. Alterna>ve Hydro Workshop. Prepared for. John Maissan. Yukon Conserva>on Society. September 30, 2015
|
|
- Penelope Bryan
- 7 years ago
- Views:
Transcription
1 Seasonal & Pumped Storage Hydro for Yukon By John Maissan Prepared for Yukon Conserva>on Society Alterna>ve Hydro Workshop September 30, 2015
2 YCS Disclaimer This study was a desk-top exercise carried out by John Maissan. The poten>al project sites iden>fied in this report have not received any social, environmental, or economic evalua>on. YCS has not endorsed or passed judgment on any of the iden>fied poten>al project sites.
3 Presenta>on Outline Background Methodology Results - general Results A sites Conclusions Ques>ons & Discussion
4 Purpose of study To demonstrate that a fresh look through a different lens can iden>fy poten>al hydro sites not previously considered or discarded too soon Most of past hydro reconnaissance looked for conven>onal and larger hydro sites based on drainage basin size rather than sites where storage could be developed regardless of drainage basin size Study Area Carmacks to Faro corridor along the Robert Campbell Highway and the 138 kv transmission line. This corridor has not previously been studied by the author.
5 Pumped storage concept Background Use surplus renewable energy to pump water to a high reservoir for later use Use water from the high reservoir to generate electricity when most needed Up to 80% recovery of energy used in pumping Seasonal storage concept Store water during spring and summer for use in winter Aishihik a perfect example Benefits from pumped or seasonal storage for Yukon Make use of present summer surplus to meet winter energy and capacity requirements Allows beaer u>liza>on of possible new intermiaent or seasonal genera>on sources such as wind and solar, as well as run of river hydro (e.g. Whitehorse Rapids), making them more cost effec>ve
6 Methodology Step 1: obtain hard copy 1:50,000 topo maps for corridor Step 2: physically study the topography of maps in N-S slices from W to E for poten>al sites Minimum head of 300 feet (about 100 meters) Look for high eleva>on lakes and/or features like narrow canyons where dams could be located to create a reservoir Look for low eleva>on lakes or rivers close to the high eleva>on sites from which water could be pumped and into which water could be discharged For upper sites es>mate drainage basin (km2), es>mate upper lake or reservoir area (km2) Step 3: examine Water Survey of Canada flow data for study corridor to determine appropriate annual flow per km2 of drainage area
7 Methodology Step 4: calcula>ons Annual volume of water available Annual new energy (GWh) Power (MW) if run steady over 6 months (winter) Storage height for steady 5 MW over 6 months Storage height for steady 10 MW over 6 months Based on all of the preceding, rank all poten>al sites from A to D with A being the most promising. Please note: First Na>ons and other land tenure NOT considered in rankings Poten>al environmental impacts NOT considered Cost es>ma>ng was NOT part of the process (need more info) Step 5: develop conclusions and recommenda>ons
8 Results 27 poten>al sites iden>fied in sweep through corridor Drury Lake & Creek, considered by Yukon Energy and rejected, so was not considered further Three other sites known & considered to some degree in past (Bearfeed Creek, Anvil Creek, and Orchay Lakes & River) were retained for considera>on No sites considered to be slam dunks 5 sites judged to be A sites, 3 because they form a close cluster and two others 5 sites judged to be B sites; they will require some field inves>ga>on to determine if they have real poten>al Hydrology informa>on suggests about 240,000 m3 runoff per km2 per year on average for study area
9 Results A sites Claire Lake area (3 sites) 3 sites not previously iden>fied to author s knowledge: Claire Lake and Creek Smaller lake to west referred to as West Claire Lake by author Small lake to north referred to as North Claire Lake by author Loca>on about 45 km east of Carmacks, and about 18 km south of highway and 138 kv line Across Liale Salmon and Yukon River from highway this will be a challenge
10 Claire Lake area (1:50,000 topo por>on) Possible dam sites in blue North Claire Lake West Claire Lake Claire Lake
11 West Claire Lake aerial photo Possible dam site
12 Claire Lake aerial photo Possible dam sites
13 North Claire Lake Yukon River Possible dam site
14 Features West Claire Lake 500 feet (152 m) head to Yukon River Lake area 3 km2 Drainage basin 47 km2 3.7 GWh per year new energy O.85 MW 6 months of the year 5 MW for 6 months requires 72 feet (22m) of storage 10 MW for 6 months requires 145 feet (44m) of storage Claire Lake 500 feet (152 m) head to Yukon River Lake area 18 km2 Drainage basin 170 km2 12 to 14 GWh per year new energy 3+ MW 6 months of the year 5 MW for 6 months requires 12 feet (3.7m) of storage 10 MW for 6 months requires 24 feet (7.4m) of storage
15 Features North Claire Lake 700 feet (213 m) head to Yukon River Lake area 0.75 km2 Drainage basin 7 km2 0.8 GWh per year new energy O.2 MW 6 months of the year 5 MW for 6 months requires 200 feet (63m) of storage The challenge for the Claire Lake area will be the river crossings, par>cularly the Yukon River
16 Anvil Creek (4 th site) Tributary of Pelly River Previously known site About 30 km west of the Faro mine mill site (138 kv stepdown substa>on) About 45 km west of Faro community
17 Anvil Creek (1:50,000 topo por>on) Possible dam site Pelly River
18 Anvil Creek aerial photo Possible dam site Pelly River
19 Features 600 feet (183m) head to Pelly River Possible reservoir 6 km2 Drainage basin 832 km2 79 GWh per year new energy 18 MW power for 6 months (9 MW year-round) 5 MW for 6 months requires 30 feet (9.2m) storage on 6 km2 10 MW for 6 months requires 60 feet (18.3m) storage 18 MW for 6 months requires 108 feet (33m) storage on 6 km2 The challenge for this site will likely be the distance to infrastructure
20 Small lake east of Faro (5 th site) Small lake 9 km east of Faro Near exis>ng infrastructure, including roads, power line, and substa>on Headwater of Vangorda Creek but near Blind Creek and Pelly River
21 Faro Small lake near Faro (1:50,000 topo map por>on) Possible dam site
22 Small lake near Faro aerial photo Possible dam site
23 Features 1,400 feet (427m) of head to Pelly River Lake/reservoir area about 0.5 km2 Drainage basin 3 km GWh per year new energy 0.15 MW power for 6 months 5 MW power for 6 months requires 155 feet (47m) of storage The main challenge for this site will likely be its modest size poten>al
24 Other results There were 5 B sites, two previously considered and 3 new ones. The ability to develop storage is the main uncertainty in these sites, 100 foot contour lines leave a fair bit of uncertainty. Conclusions There are poten>al sites for seasonal or pumped storage hydro not previously documented This simple office study iden>fied poten>al sites that merit further inves>ga>on A fresh look for poten>al hydro development in Yukon through a lens of seasonal or pumped storage possibili>es, not much used in the past, is merited
25 Ques>ons? Discussion?
Smart Infrastructure Investment: Evalua2ng Demand Trends & Weighing Risks
Smart Infrastructure Investment: Evalua2ng Demand Trends & Weighing Risks David Marshall, P.E. Engineering Services Director Tarrant Regional Water District 1/23/14 TRWD Overview Formed in 1924 from an
More informationINTRODUCING PUMPED STORAGE IN LEBANON: TOWARDS A PROSPECTIVE NATIONAL MASTER PLAN
INTRODUCING PUMPED STORAGE IN LEBANON: TOWARDS A PROSPECTIVE NATIONAL MASTER PLAN by Adib Geadah Senior Hydraulic Engineer and Consultant, P.O.Box 13-6195, Beirut, 1102-2801, Lebanon International Seminar
More informationNOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand
Journal of Hydrology (NZ) 44 (2): 131-135, 2005 New Zealand Hydrological Society (2005) NOTE Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand W. E. Bardsley Department
More informationAlaska Energy Authority: Renewable Energy Fund and Susitna-Watana Hydro
Photo by: Cassandra Cerny, GVEA Alaska Energy Authority: Renewable Energy Fund and Susitna-Watana Hydro Sara Fisher-Goad, executive director Northwest Power Producers Association Oct. 29, 2015 2 Alaska
More informationLadies and Gentlemen, let me introduce myself and give you some information about my office.
Ladies and Gentlemen, let me introduce myself and give you some information about my office. 1 In 2010, I made a doctorate with the title: Storage demand for a power supply with renewable energies. This
More informationSatellite derived Groundwater Storage Es4mates and Opportuni4es for Expanding Research in Arid Environments
Satellite derived Groundwater Storage Es4mates and Opportuni4es for Expanding Research in Arid Environments NASA Ames DEVELOP Program Summer 2011 Amber Kuss, San Francisco State University William Brandt,
More informationCURRENT INITIATIVES AND WHAT IT WILL TAKE TO ACHIEVE THE SOLAR ENERGY GOALS OF THE NATION
CURRENT INITIATIVES AND WHAT IT WILL TAKE TO ACHIEVE THE SOLAR ENERGY GOALS OF THE NATION Solar Qatar Summit 19 November 2013 2 Qatar s annual electric power consumption is more than 3x the global rate
More informationChattichai WAISURASINGHA 1*, Prinya CHINDAPRASIRT 1, Winai SRI-AMPORN 1 and Sinee CHUANGCHAM 2
The Utilization of Geographic Information Systems and Multi-Criteria Decision Making with Local Community Participation for Selection of Site for Micro Hydropower Project: A Case Study of Chi River Basin,
More informationUpper Pitt River Water Power Project Project Description Appendix I - Photographs
Upper Pitt River Water Power Project Project Description Appendix I - Photographs Photo 1. Boise Creek Reach 3 at 1+223 m: typical fish habitat where the diversion reach overlaps with anadromous fish habitat.
More informationBurnt River Black River and Gull River Flood Contingency Plan
Burnt River Black River and Gull River Flood Contingency Plan Objective: The objective of this plan is to preplan and prepare for flooding events in the Burnt River, Black River and Gull River area of
More informationARIZONA DEPARTMENT OF WATER RESOURCES
ARIZONA DEPARTMENT OF WATER RESOURCES WATER MANAGEMENT REQUIREMENTS FOR SOLAR POWER PLANTS IN ARIZONA ADWR CONTACT: Jeff Tannler, Statewide Active Management Area Director Arizona Department of Water Resources
More informationScenarios for Future Internet Business@Energy
Scenarios for Future Internet Business@Energy Global energy challenges Demographic dynamics Scarce resources Climate change Population growth 7.5 bill. in 2020 (+1.1 bill.) Megacities 27 megacities (>10
More informationWelcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community. www.fortisbc.
Welcome to our open house Thanks for coming Please sign in and help yourself to refreshments Integrated System Plan (ISP) Looks ahead 20 years to identify the energy and infrastructure needs of our customers
More informationHydroelectric Power Planning DIRECTIVE WORK PLAN. May 2014 NEXT GENERATION HYDRO. powering our future. Tourism and Culture.
Hydroelectric Power Planning DIRECTIVE WORK PLAN May 2014 NEXT GENERATION HYDRO powering our future Government Tourism and Culture Table of Contents Introduction... 4 Context... 8 Policy overview... 8
More informationBlack Mountain Reservoir Land Rezoning
Black Mountain Reservoir Rezoning Information Meeting Black Mountain Reservoir Rezoning 1.0 Black Mountain Reservoir What the reservoir provides The Black Mountain Reservoir will be a low-elevation raw
More informationFlumill: fra sterke mari(me tradisjoner via olje og gass (l ledende fornybar teknologi
Flumill: fra sterke mari(me tradisjoner via olje og gass (l ledende fornybar teknologi Presenta(on Oppstartkonferransen for VINN Agder 25 september 2014 The Flumill Technology represents a Step Change
More informationDarrel L. Williams 1, Samuel N. Goward 2, and Ta9ana Loboda 2
Darrel L. Williams 1, Samuel N. Goward 2, and Ta9ana Loboda 2 1 Global Science & Technology, Inc., 7855 Walker Drive, Suite 200, Greenbelt, MD 20770 2 U. of Maryland College Park, Department of Geographical
More informationEarth Science. River Systems and Landforms GEOGRAPHY 1710. The Hydrologic Cycle. Introduction. Running Water. Chapter 14.
Earth Science GEOGRAPHY 1710 River Systems and Landforms DAVID R. SALLEE Robert W. Christopherson Charlie Thomsen Chapter 14 Introduction Rivers and streams are dynamic systems that continually adjust
More informationCORUH RIVER DEVELOPMENT PLAN
CORUH RIVER DEVELOPMENT PLAN International Workshop on Transboundary Water Resources Management Tbilisi, Georgia 8-10 December 2009 Ubeyd Sezer Geological Engineer U. Sezer GENERAL DIRECTORATE OF STATE
More informationArktis en kilde til fornybar energi?
Arktis en kilde til fornybar energi? Ånund Killingtveit 1 1 Norwegian University of Science and Technology Centre for environmental design of renewable energy - CEDREN SRREN was prepared for WG III In
More informationFLOOD FORECASTING PRACTICE IN NORTHERN CALIFORNIA
FLOOD FORECASTING PRACTICE IN NORTHERN CALIFORNIA California Department of Water Resources Post Office Box 219000, Sacramento, California 95821 9000 USA By Maurice Roos, Chief Hydrologist ABSTRACT Although
More informationCambridge International Examinations Cambridge International General Certificate of Secondary Education
Cambridge International Examinations Cambridge International General Certificate of Secondary Education *0123456789* GEOGRAPHY 0460/02 Paper 2 Geographical skills For Examination from 2016 SPECIMEN PAPER
More informationHydroelectric Power Plant - Los Cóndores. Santiago, April 2014
Hydroelectric Power Plant - Los Cóndores Santiago, April 2014 Introduction Los Cóndores, a large hydro project of 150 MW with water flow regulation using the existing water reservoir of the Embalse Laguna
More informationGeneral Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage
Determination Case number: 227307 General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage 4 April 2011 Background 1. The Applicants insured their home contents
More information5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
More informationOntario s Electricity Dilemma - Energy Policy Presentation. This presenta,on can be downloaded at: h4p://www.ospe.on.ca/?
Ontario s Electricity Dilemma - Achieving Low Emissions at Reasonable Electricity Rates Energy Policy Presentation This presenta,on can be downloaded at: h4p://www.ospe.on.ca/?page=pres_lib#peo OSPE Energy
More information23 November 2011. Contact Energy Geothermal update November 2011
Contact Energy Geothermal update November 2011 Disclaimer This presentation may contain projections or forward looking statements regarding a variety of items. Such forward-looking statements are based
More informationQuartz Mining Act Guidelines for Claim Staking. Please use the following document as a guide when staking and recording claims in Yukon.
Quartz Mining Act Guidelines for Claim Staking Please use the following document as a guide when staking and recording claims in Yukon. Before you set out to stake your own Yukon mineral claim, read these
More informationWater Extraction Permitting Policy
Water Extraction Policy 1 Water Extraction Permitting Policy Department of Environment, Labour & Justice January 2013 Water Extraction Policy 2 EXECUTIVE SUMMARY This document establishes a new policy
More informationBackground Information: The Mamquam River Floodplain Restoration Project
Background Information: The Mamquam River Floodplain Restoration Project The Mamquam River Floodplain Restoration project is being undertaken in partnership with the Squamish River Watershed Society, Fisheries
More informationEagle Mountain Pumped Storage Project No. 13123 Final License Application Volume 6 of 6. Exhibit G Project Boundary PUBLIC. Palm Desert, California
PUBLIC Eagle Mountain Pumped Storage Project No. 13123 Final License Application Volume 6 of 6 Exhibit G Project Boundary Palm Desert, California Submitted to: Federal Energy Regulatory Commission Submitted
More informationRuby River Grayling - Gravel Spawning Beds Monitoring Report January 2008
Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008 In partnership with Montana Department of Fish, Wildlife, and Parks (FWP), American Wildlands, and Wildlife Forever, the Madison
More informationClimate Change Resilience Workshop IHA-World Bank meeting. 13 November 2015 Philippe MEUNIER
Climate Change Resilience Workshop IHA-World Bank meeting 13 November 2015 Philippe MEUNIER CONTENTS Chapter 1 ENGIE and hydro production Chapter 2 Adaptation policy Chapter 3 Case studies ENGIE : An hydro
More informationThe River Ribble is one of the longest rivers in the North West of England
River Ribble The River Ribble is one of the longest rivers in the North West of England Did you know? The tidal limit of the Ribble is 11 miles inland (above Preston); The River Ribble is home to a variety
More informationFuture domes+c hea+ng systems and their poten+al role in integra+ng variable renewable energy
Future domes+c hea+ng systems and their poten+al role in integra+ng variable renewable energy Steve Heinen Workshop on ICT Enabling Thermal Energy Flexibility in Integrated Energy Systems KIER, Daejeon,
More informationWHERE DOES THE WATER GO IN THE WATER CYCLE?
WHERE DOES THE WATER GO IN THE WATER CYCLE? OBJECTIVES Identify the water cycle as a system that is a combination of systems Describe each process in the water cycle, including the changes in state (if
More informationAmir Bashirzadeh Tabrizi, Nassir Gifani. TOOSSAB Consulting Engineers Company e-mail: bashirzadeh@hotmail.com, nssrgifani@gmail.com.
International Renewable Energy Congress November 5-7, 2010 Sousse, Tunisia Economical and Environmental Effects of Pressure Reducer Valve Substituting by Small Hydro Power-Plants in Gravity Water Transmission
More informationHYDROMETEOROLOGICAL AND MONITORING SERVICE
Regional Association VI, Forum Hydrology, Koblenz May 8 10, 2012 MINISTRY OF EMERGENCY SITUATIONS OF ARMENIA ARMENIAN STATE HYDROMETEOROLOGICAL AND MONITORING SERVICE Amalya Misakyan THE STRUCTURE OF ARMSTATEHYDROMET
More informationRe: Preliminary Permit Application for the Rose Creek Pumped Storage Project
September 12, 2013 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Preliminary Permit Application for the Dear Ms. Bose, Please find attached
More informationEcoInformatics International Inc.
1 von 10 03.08.2010 14:25 EcoInformatics International Inc. Home Services - solutions Projects Concepts Tools Links Contact EXPLORING BEAVER HABITAT AND DISTRIBUTION WITH GOOGLE EARTH: THE LONGEST BEAVER
More informationCSER & emerge Consor.a EHR Working Group Collabora.on on Display and Storage of Gene.c Informa.on in Electronic Health Records
electronic Medical Records and Genomics CSER & emerge Consor.a EHR Working Group Collabora.on on Display and Storage of Gene.c Informa.on in Electronic Health Records Brian Shirts, MD, PhD University of
More information4 Water supply description
4 Water supply description A description of the drinking-water system is equally applicable to large utilities with piped distribution systems, piped and non-piped community supplies, including handpumps
More informationUntreated (left) and treated (right) Sierra Nevada forests in Amador County, CA. Photos: Sierra Nevada Conservancy
Case Study Mokelumne Watershed, CA and Santa Fe, NM Avoided Costs: The Economics of Watershed Restoration Forested headwaters are the source of much of the West s drinking water. Protecting and restoring
More informationHEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES
HEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES INTRODUCTION The Headwaters Control Structure at Gray's Bay is the outlet of Lake Minnetonka to Minnehaha Creek. It is an adjustable
More informationTheodore Roosevelt Dam WebQuest and Research Report Writing
Theodore Roosevelt Dam WebQuest and Research Report Writing Estimated Time: WebQuest, 60 minutes; report, three to five days depending on writing time needed State Standards for Grades 6 8 Standards Taught
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS LOWER GREAT MIAMI RIVER NUTRIENT MANAGEMENT PROJECT INTRODUCTION On behalf of a partnership of Water Resource Recovery Facilities (WRRFs) WRRFs and other stakeholders with permitted
More informationThin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant
Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant By Ginger Gillin, John Pizzimenti, and Doug Foss, GEI Consultants, Inc., USA, and Jon Jourdonnais, PPL Montana, USA. Abstract The
More informationHow To Manage Water Resources In The Yakima Basin
Yakima Basin Integrated Water Resource Management Plan October 23, 2014 Presented by Derek Sandison, Director Office of Columbia River Photo Courtesy of Tom Ring Basin size: 6,155 sq. miles Population:
More informationThe HIGH SPEED RAIL THREAT to LOS ANGELES DRINKING WATER
The HIGH SPEED RAIL THREAT to LOS ANGELES DRINKING WATER INTRODUCTION On December 2 nd, 2014, the High Speed Rail (HSR) Project released new maps showing recently proposed alternate rail routes that go
More informationWalla Walla Bi state Stream Flow Enhancement Study Interim Progress Report. Department of Ecology Grant No. G1400656.
Walla Walla Bi state Stream Flow Enhancement Study Interim Progress Report Department of Ecology Grant No. G1400656 Submitted by: Walla Walla Watershed Management Partnership Walla Walla, WA Walla Walla
More informationColorado Water Bar December 13, 2012
Colorado Water Bar December 13, 2012 Typical DWR Comments for Water Court Applications Augmentation Plans Applicant must prove that the proposed augmentation plan will be sufficient to prevent injury to
More informationLEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN
1 AUGUST 2011 LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN KEY ELEMENTS OF THE PLAN: 1. Replace the existing unsafe Ragged Mountain dam with a new dam and raise the reservoir pool level initially
More informationWhat are the Benefits?
Micro hydro power system introduction Not everyone is lucky enough to have a source of running water near their homes. But for those with river-side homes or live-on boats, small water generators (micro-hydro
More informationGrid Tracker: Connect using the web link and new phone / passcode information:
Grid Tracker: Connect using the web link and new phone / passcode information: Web link: http://westgov.adobeconnect.com/gridtracker/ Phone: 1-888-850-4523 Passcode: 169969# Workshop August 28, 2013 Grid
More informationWater management and challenges in Norway
Photo: Morten Nicholls Water management and challenges in Norway Geir Stene-Larsen Ministry of Health and Care Services Ministries and directorates involved in freshwater management Ministry of Health
More informationHow To Get A Better Deal On Power From Powerline Power From Pse
ELECTRICITY RATES FOR COMMERCIAL AND INDUSTRIAL CUSTOMERS Rates Effective January 1, 2010 If you would like information about our services, details about your rights and responsibilities, or a copy of
More information10 Steps to Preparedness
10 Steps to Preparedness Key Take- Aways Review basics of disaster recovery and con2nuity of opera2ons. Understand what you can do to prepare your pool and its members for an unplanned interrup2on. Ini2ate
More informationAssessment of hydropower resources
Assessment of hydropower resources Oliver Froend Assessment of hydropower resources Relevance of surveys, data assessment and analyses to the success of the project. Required data and field survey. Key
More informationRecreational Enhancements on the Lehigh River Public Information Workshop February 2013
Recreational Enhancements on the Lehigh River Public Information Workshop February 2013 Cooperating Agencies US Army Corps of Engineers Philadelphia District Pennsylvania Fish & Boat Commission Pennsylvania
More informationAdvanced Project Management Training Course
Advanced Project Management Training Course 1-34 Advanced Project Management Crea/ng the Scope Baseline 2-34 Crea/ng the Scope Baseline Module 1 Introduction Module 2 Creating the Project Charter Module
More informationELECTRICITY SECURITY OF SUPPLY CHALLENGES IN THE ENERGY COMMUNITY
ELECTRICITY SECURITY OF SUPPLY CHALLENGES IN THE ENERGY COMMUNITY - topics for discussion - 17 th PHLG Meeting 30-31 May 2006 Zagreb, Croatia - Prepared by ECS - 1 CONTENTS CONTENTS PURPOSE LEGAL PROVISIONS
More informationGROUNDWATER CONDITIONS
GROUNDWATER CONDITIONS IN THE NORTHERN SACRAMENTO VALLEY LOCAL MANAGEMENT OF WATER RESOURCES IN THE NORTHERN SACRAMENTO VALLEY MEETING DECEMBER 16, 2011 KELLY STATON, SENIOR ENGINEERING GEOLOGIST, GROUNDWATER
More informationCOMMUNITY DEVELOPMENT FUND ANNUAL REPORT
COMMUNITY DEVELOPMENT FUND ANNUAL REPORT April 1, 2012 to March 31, 2013 www.cdf.gov.yk.ca TABLE OF CONTENTS Minister s Message...3 General Program Information...4 Eligibility...4 Assessment...4 Funding
More informationExecutive Summary: PA No. 12 Micro-hydro at Graham Hill Water Treatment Plant
Executive Summary: PA No. 12 Micro-hydro at Graham Hill Water Treatment Plant Description A micro-hydro project at SCWD s Graham Hill Water Treatment Plant (WTP) would replace an exisiting non-operational
More informationNatural Gas as a Transportation Fuel
Natural Gas as a Transportation Fuel Manitoba Hydro! Electric Utility 556,000 electric customers! Responsible for generation, transmission, distribution and retailing of electricity in Manitoba! 5,500
More informationSolar PV panels fitted to roofs. Solar PV panels produce electricity from energy provided by sunlight. 3.5 MWh per system
Solar PV panels fitted to roofs Yearly cost of production Cost per kwh 12.5p Solar PV panels produce electricity from energy provided by sunlight. 3.5 MWh per system 430 per system Solar energy can be
More informationUsing Mobile to Capture In- the- Moment Insights
With the global leader in sampling and data services Using Mobile to Capture In- the- Moment Insights Saran Ganesh Director, Mobile product marke8ng 2015 Survey Sampling Interna6onal 1 During this webcast
More informationGuidelines for Monthly Statistics Data Collection
Guidelines for Monthly Statistics Data Collection Final version Data Expert Group 31 May 2015 1. Table of contents 1. Table of contents... 2 2. Remarks... 3 3. Introduction... 3 4. Geographical perimeter
More informationCrowdfunding for Renewable Energy Projects: European Survey Results (November Release)*
Crowdfunding for Renewable Energy Projects: European Survey Results (November Release)* 2nd Renewable Energy Crowdfunding Conference London, 5 November 2015 *Please cite as Bergmann, A.; Burton, B.; Maidonis,
More informationAn Introduc+on to the College Selec+on Process for College- Bound Student- Athletes. Preparing for College Soccer
An Introduc+on to the College Selec+on Process for College- Bound Student- Athletes Preparing for College Soccer AGENDA Club Resources Selec+ng a College Path to College Success NCAA Rules & Regula+ons
More informationEnvironmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization
Introduction A visual examination of Doolittle Creek in a highly developed suburban county in Georgia yielded telltale signs of a creek whose original streambed had been altered. Examination of official
More informationChina s Small Hydropower in Rural Energy Development
China s Small Hydropower in Rural Energy Development Li Zhiwu National Research Institute for Rural Electrification, China Hangzhou regional (Asia & Pacific) Center for Small Hydropower 2012.8.1 As one
More informationREPORT. Impact on Irrigated Land by the Proposed 765kV Perseus-Hydra Transmission Power line
Rehab Green cc Registration No: 2002/094339/23 PI Steenekamp PO Box 12636 Queenswood 0121 Pretoria Cell: 082 560 0592 Fax: 086 678 1690 E-mail: rehabgreen@ee-sa.com Report No: RG/2007/05/14/1 Date: May
More informationRFP Marke*ng Services
RFP Marke*ng Services RFP Professional Services MAC Adver*sing, Marke*ng Plan and Press for 38 MAC touring Shows 6 Global Flick College Events 2 College Theatre Plays 2 College Music Events 2 College Choral
More informationFlood After Fire Fact Sheet
FACT SHEET Flood After Fire Fact Sheet Risks and Protection Floods are the most common and costly natural hazard in the nation. Whether caused by heavy rain, thunderstorms, or the tropical storms, the
More informationMission Canyon Residential Design Guidelines Workshop. Table Focus: Environmental Issues and Concerns
Mission Canyon Residential Design Guidelines Workshop Table Focus: Environmental Issues and Concerns Grading How is Grading Regulated in Santa Barbara County? The technical aspects of grading are regulated
More informationCouncil Monitoring & Assessment Program Development
Council Monitoring & Assessment Program Development Steve Giordano & Mark Monaco, Na9onal Oceanic & Atmospheric Administra9on Greg Steyer & Mike Lee, U.S. Geological Survey Alyssa Dausman & Jessica Henkel,
More informationWind Cluster Management for Grid Integration of Large Wind Power
1 Wind Cluster Management for Grid Integration of Large Wind Power B. Lange, M. Wolff, R. Mackensen, K. Rohrig German-Egyptian Symposium Wind Energy and Integration Overview 2 Challenges for the Integration
More informationHVDC Transmission Line Project for Moving ERCOT Wind Into SERC
HVDC Transmission Line Project for Moving ERCOT Wind Into SERC ERCOT RPG Meeting August 13, 2010 Agenda Pattern Energy Group SERC and ERCOT Market Drivers Southern Cross Project Overview Project Development
More informationFY 2015-16 Springs Funding Projects
FY 2015-16 Springs Funding Projects Spring Homosassa Springs Project Name and Description Garcia Point Septic Project: Through the connection of 88 residential septic systems to Citrus County s central
More informationUsing LIDAR to monitor beach changes: Goochs Beach, Kennebunk, Maine
Geologic Site of the Month February, 2010 Using LIDAR to monitor beach changes: Goochs Beach, Kennebunk, Maine 43 o 20 51.31 N, 70 o 28 54.18 W Text by Peter Slovinsky, Department of Agriculture, Conservation
More informationCoastal Engineering Indices to Inform Regional Management
Coastal Engineering Indices to Inform Regional Management Lauren Dunkin FSBPA 14 February 2013 Outline Program overview Standard products Coastal Engineering Index Conclusion and future work US Army Corps
More informationMonitoring Riparian Areas With a Camera
Monitoring Riparian Areas With a Camera By Michael DeLasaux 1, Holly George 2, and Philip Mainwaring 3 Riparian areas are next to streams, springs, rivers, ponds and lakes. Physical characteristics that
More informationUniversity of Utah WAN Firewall Presenta6on
University of Utah WAN Firewall Presenta6on Raising Awareness of our WAN Firewall Issues This document is for internal University of Utah use only. 4 Key Internet Firewall Ques6ons Who do we serve and
More informationPreliminary Plan for Expansion of the Regional Network of Floridan and Surficial Aquifer Monitor Wells for Northern Tampa Bay
DRAFT - August 24, 2000 Preliminary Plan for Expansion of the Regional Network of Floridan and Surficial Aquifer Monitor Wells for Northern Tampa Bay Introduction In 1999, the Southwest Florida Water Management
More informationColumbia River Project Water Use Plan. Monitoring Program Terms of Reference
Columbia River Project Water Use Plan Revelstoke Flow Management Plan Monitoring Program Terms of Reference CLBMON-15a Middle Columbia River Physical Habitat Monitoring Revision January 29, 2015 Monitoring
More informationHydropower Projects Portfolio
Business Network Forum 18th Meeting, Iquitos- Peru, 04 March 2008 MINISTRY OF ENERGY AND MINES Hydropower Projects Portfolio By Jorge Aguinaga Diaz General Director for Electricity 1 Content I. GENERAL
More informationWILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10
WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta
More informationUS DOE Misc. Refrigera2on Products Coverage. Presented by Robert Van Buskirk, Ph.D.
US DOE Misc. Refrigera2on Products Coverage Presented by Robert Van Buskirk, Ph.D. Source Material Material is copied from US DOE public mee2ng on February 22, 2012: hgp://www1.eere.energy.gov/buildings/appliance_standards/rulemaking.aspx/ruleid/71
More informationWater Security Agency. Plan for 2015-16. saskatchewan.ca
Water Security Agency Plan for 2015-16 saskatchewan.ca Statement from the Minister I am pleased to present the Water Security Agency s Plan for 2015-16. The Honourable Scott Moe Minister Responsible for
More informationDIVISION D ELECTRICITY, GAS, WATER AND WASTE SERVICES
The Electricity, Gas, Water and Waste Services Division comprises units engaged in the provision of electricity; gas through mains systems; water; drainage; and sewage services. This division also includes
More informationWorkshop 2: Economics and Financing for Commercial/Industrial Solar Projects
Workshop 2: Economics and Financing for Commercial/Industrial Solar Projects Commercial Accelera@on of Solar Energy in Silicon Valley (CASE- SV) Moderator: Eileen Hays, Optony September 23, 2014 2:00-3:00PM
More informationFloodplain Mapping. Vision. Events: 1 in 2 year 1 in 10 year 1 in 20 year 1 in 50 year 1 in 100 year Probable Maximum Flood Climate Change Impacts
Events: 1 in 2 year 1 in 10 year 1 in 20 year 1 in 50 year 1 in 100 year Probable Maximum Flood Climate Change Impacts Floodplain Mapping 28 General Approaches to Reducing Flooding Risks Reducing Upstream
More informationNPLOTH7 GIS Database Development Mission (2619), Bryson (2601), Franklin (2603), Dillsboro (2602) Final Report
NPLOTH7 GIS Database Development Mission (2619), Bryson (2601), Franklin (2603), Dillsboro (2602) Final Report Introduction Duke Power Nantahala Area (Duke) is in the process of relicensing the Mission,
More informationThe Great Lakes Futures Project Assessing what the state of the Great Lakes St. Lawrence River Basin could be in 50 years.
Assessing what the state of the Great Lakes St. Lawrence River Basin could be in 50 years. Our goal is to develop a trans disciplinary understanding of the future of the Great Lakes St. Lawrence River
More informationYukon Development Corporation. Next Generation Hydro Summary of the Hydroelectric Power Planning Directive Work Plan
SUMMARY Yukon Development Corporation Next Generation Hydro Summary of the Hydroelectric Power Planning Directive Work Plan It is time for bold leadership to take charge of our energy future so the next
More informationUTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION
UTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION Joshua A. Israel, Fish Biologist, U.S Bureau of Reclamation, Sacramento, CA. jaisrael@usbr.gov; Paul
More informationLecture 4: Streamflow and Stream Gauging
Lecture 4: Streamflow and Stream Gauging Key Questions 1. What is stream discharge and what controls its magnitude? 2. What is a hydrograph? 3. Where is the velocity highest in a stream? 4. Where is the
More informationGREENSTONE-MARATHON Integrated Regional Resource Plan
GREENSTONE-MARATHON Integrated Regional Resource Plan Local Advisory Committee Meeting #2 November 24-25, 2015 Presentation Outline Recap of LAC meeting #1 Implementation of Near-term Planning Elements
More information156 West End Lane Workshop 7 November 2015. Fortune Green & West Hampstead Neighbourhood Development Forum
156 West End Lane Workshop 7 November 2015 Fortune Green & West Hampstead Neighbourhood Development Forum Camden Council s Site AllocaIons Document Sept 2013 Site 28 The London Plan iden(fies the site
More information