1 Non-modeling Worksheets: Bridge Replacement in Kind April 12, 2016 Darrin Miller PE Hydraulic Engineer Section Manager (North)

2 Overview Intent - When to use the Worksheet Theory behind the Worksheet Bridges and Culverts Examples

3 Non-Modeling Worksheet When to Use the Worksheet Bridge to Bridge replacement Culvert to Bridge replacement Culvert to Culvert replacement If the length of the culvert is essentially the same And if the proposed culvert is of essentially the same material (roughness coefficient) RAS_4.0_Reference_Manual.pdf (page 6-24) Concrete is typically smoother than corrugated metal, smaller n, less loss, lower surcharge Note: If multiple designs, the applicant should only submit the one with the smallest waterway opening for use in the worksheets April 12, 2016

4 Non-Modeling Worksheet When to Not Use the Worksheet The waterway opening decreases The existing structure remains in place Bridge to Culvert replacement If the New bridge is more than 500 ft from the existing bridge

5 Non-Modeling Worksheet How to Use the Worksheet The worksheet was intended to streamline the majority of replacement in kind projects BUT, it does not capture every possibility Single page Excel with if then statements

6 Non-Modeling Worksheet How to Use the Worksheet The worksheet was intended to streamline the majority of replacement in kind projects BUT, it does not capture every possibility 1) It works for my bridge: submit worksheet 2) It does not work for my bridge: modeling 3) It does not work for my bridge, BUT it should include documentation for DNR review to fill in the missing info not captured by the Excel worksheet

7 Two Part Application Non-Modeling Worksheet Directions for use Minimum Requirements Check Sheets Plan Details Companion Worksheet B Excel Spreadsheet with embedded logic to evaluate entries Yes/No questions with dropdown choices Tables for recording relevant data

8 Minimum Requirements Plan view of construction components Aerial of disturbed area Delineated Floodway through the project Plan views with calculations of waterway opening, top of road profile, and low structure Cross section location map Project location map Site photos

9 Companion Worksheet B Questions are asked in an order so that the applicant will move through the worksheet as quickly as possible while providing as little information as is needed to determine the ability to issue a permit for the project Logic is coded into the spreadsheet so the applicant is only asked for applicable data

10

11

12 Culverts & Bridges Why is it important to consider if it s a bridge or culvert? When modeling in HEC-RAS, bridges and culverts are modeled differently which can give drastically different results Bridges are modeled using the methods selected in the bridge modeling approach editor (Energy, Momentum, Pressure and/or Weir, )

13 Culverts & Bridges Why is it important to consider if it s a bridge or culvert? Culverts also come in many different shapes (box, arch, circular, ellipse, ) Culverts can be made of different materials which have different roughness coefficient Culverts are modeled using inlet or outlet control culvert equations and when applicable weir equations

14 Culverts & Bridges When is it a bridge and not a culvert? Consider bridge methods when the structure has a very large opening relative to the deck thickness Consider culvert methods when the structure has a very deep deck and small relative opening FHWA defines a culvert as a structure with a total span of 20 ft or less (measured along centerline of roadway)

15 Culverts & Bridges FHWA defines a culvert as a structure with a span of 20 ft or less (measured along centerline)

16 Non-Modeling Worksheet So when can I use the worksheet? Theory behind logic is to approve in-kind Would the same equations be used to model both structures?

17

18

19

20

21 Companion Worksheet B Regulatory Flood Elevation (RFE) is needed to evaluate the area available below the RFE At toe of road fill Acceptable sources: a published Flood Study a Letter of Map Revision (LOMR) an approved model(s) from a DNR permit a DNR Floodplain Analysis and Regulatory Assessment (FARA) a new model submitted with the permit application for DNR review

22

23 Supporting Documents Minimum submittal requirements listed on the evaluation worksheet Submit all that is needed to support the calculations and values in the RIK assessment worksheet. If your project is unique, submit the nonmodeling assessment with the supporting documentation and DNR can review.

24 Examples Bridge deck improvements result in thicker deck. The low chord of the proposed bridge (red line) has a lower elevation than existing. Does it qualify? Existing Proposed 1% BFE

25 Examples Yes. The area of the waterway opening beneath the structure is decreasing. But since the BFE is known, it can be shown that the area below the BFE is NOT changed. Existing Proposed 1% BFE

26 Examples The proposed road profile is raised and minimum top of road remains unchanged. Does it qualify? Proposed road profile 1% BFE Minimum top of road

27 Examples No, the worksheet captures the high structure elevation, and the minimum top of road. But additional road fill may block road overflow. Proposed road profile 1% BFE Minimum top of road

28 Examples The proposed road profile will be raised above the existing minimum top of road. Does it qualify? Proposed road profile 1% BFE Minimum top of road

29 Examples Yes, the worksheet captures the high structure elevation, and the minimum top of road. Both are above the BFE. Proposed road profile 1% BFE Minimum top of road

2011 HYDRAULICS MANUAL

2011 HYDRAULICS MANUAL STATE OF LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT P.O. Box 94245 Baton Rouge, Louisiana 70804-9245 http://www.dotd.la.gov/ HYDRAULICS MANUAL Hydraulics (225) 379-1306 PREFACE The following

More information

Using GIS Data With HEC-RAS

Using GIS Data With HEC-RAS C H A P T E R 14 Using GIS Data With HEC-RAS HEC-RAS has the ability to import three-dimensional (3D) river schematic and cross section data created in a GIS or CADD system. While the HEC- RAS software

More information

Appendix 4-C. Open Channel Theory

Appendix 4-C. Open Channel Theory 4-C-1 Appendix 4-C Open Channel Theory 4-C-2 Appendix 4.C - Table of Contents 4.C.1 Open Channel Flow Theory 4-C-3 4.C.2 Concepts 4-C-3 4.C.2.1 Specific Energy 4-C-3 4.C.2.2 Velocity Distribution Coefficient

More information

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow CHAPTER 9 CHANNELS APPENDIX A Hydraulic Design Equations for Open Channel Flow SEPTEMBER 2009 CHAPTER 9 APPENDIX A Hydraulic Design Equations for Open Channel Flow Introduction The Equations presented

More information

CHAPTER 4 STORM DRAINAGE SYSTEMS

CHAPTER 4 STORM DRAINAGE SYSTEMS CHAPTER 4 STORM DRAINAGE SYSTEMS 4.1 Overview... 4-1 4.1.1 Introduction... 4-1 4.1.2 Inlet Definition... 4-1 4.1.3 Criteria... 4-1 4.2 Pavement Drainage... 4-2 4.2.1 Introduction... 4-2 4.2.2 Storm Drain

More information

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal Lecture 21 Culvert Design & Analysis Much of the following is based on the USBR publication: Design of Small Canal Structures (1978) I. Cross-Drainage Structures Cross-drainage is required when a canal

More information

CHAPTER 3 STORM DRAINAGE SYSTEMS

CHAPTER 3 STORM DRAINAGE SYSTEMS CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next

More information

CHAPTER 9 CULVERTS TABLE OF CONTENTS. CDOT Drainage Design Manual

CHAPTER 9 CULVERTS TABLE OF CONTENTS. CDOT Drainage Design Manual CHAPTER 9 CULVERTS TABLE OF CONTENTS 9.1 INTRODUCTION...4 9.1.1 Definition...4 9.1.2 Purpose of Use...5 9.1.3 Concepts and Definitions...5 9.1.4 Symbols...8 9.1.5 Classification...10 9.1.6 Geometry...10

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Mehmet Secilmis, GISP Environmental Engineer/GIS Specialist Dewberry Parsippany, NJ msecilmis@dewberry.com

Mehmet Secilmis, GISP Environmental Engineer/GIS Specialist Dewberry Parsippany, NJ msecilmis@dewberry.com Bridge Inventory Using GIS City of New Haven, CT Mehmet Secilmis, GISP Environmental Engineer/GIS Specialist Dewberry Parsippany, NJ msecilmis@dewberry.com (973) 576-9640 Introduction City of New Haven

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

DRAINAGE CRITERIA MANUAL (V. 2) CULVERTS CONTENTS

DRAINAGE CRITERIA MANUAL (V. 2) CULVERTS CONTENTS DRAINAGE CRITERIA MANUAL (V. 2) CONTENTS Section Page CU 1.0 INTRODUCTION AND OVERVIEW... 1 1.1 Required Design Information... 3 1.1.1 Discharge... 4 1.1.2 Headwater... 4 1.1.3 Tailwater... 5 1.1.4 Outlet

More information

STORM DRAINS CHAPTER 7

STORM DRAINS CHAPTER 7 CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect

More information

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION GENERAL Rehabilitation of culverts with pipe liners is one of several methods available for extending the life of an existing culvert. It is often cost

More information

Storm Drainage Systems 11.9-1

Storm Drainage Systems 11.9-1 Storm Drainage Systems 11.9-1 11.9 Gutter Flow Calculations 11.9.1 Introduction Gutter flow calculations are necessary in order to relate the quantity of flow (Q) in the curbed channel to the spread of

More information

MAP TYPES FLOOD HAZARD BOUNDARY MAP MAP READING & FLOOD INSURANCE STUDIES. FHBM Flood Hazard Boundary Map. FIRM Flood Insurance Rate Map

MAP TYPES FLOOD HAZARD BOUNDARY MAP MAP READING & FLOOD INSURANCE STUDIES. FHBM Flood Hazard Boundary Map. FIRM Flood Insurance Rate Map FLOODPLAIN MANAGEMENT 101 MAP READING & FLOOD INSURANCE STUDIES MAP TYPES FHBM Flood Hazard Boundary Map FIRM Flood Insurance Rate Map FBFM Flood Boundary and Floodway Map DFIRM Digital Flood Insurance

More information

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness 3 Chapter 3 of Concentration and Travel Time Time of Concentration and Travel Time Travel time ( T t ) is the time it takes water to travel from one location to another in a watershed. T t is a component

More information

Spreadsheet Use for Partially Full Pipe Flow Calculations

Spreadsheet Use for Partially Full Pipe Flow Calculations Spreadsheet Use for Partially Full Pipe Flow Calculations Course No: C02-037 Credit: 2 PDH Harlan H. Bengtson, PhD, P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY

More information

Flood Damage Mitigation And Insurance Costs

Flood Damage Mitigation And Insurance Costs Flood Damage Mitigation And Insurance Costs Friday, September 25, 2015 at 7:00 PM Saturday, September 26, 2015 at 10:00 AM This presentation was prepared by the Town of South Bethany using Federal Funds

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

Quality Assurance Reviews of Hydraulic Models Developed for the Central Valley Floodplain Evaluation and Delineation Program

Quality Assurance Reviews of Hydraulic Models Developed for the Central Valley Floodplain Evaluation and Delineation Program Quality Assurance Reviews of Hydraulic Models Developed for the Central Valley Floodplain Evaluation and Delineation Program Techniques Applied and Lessons Learned Seth Ahrens, P.E., CFM Selena Forman,

More information

CHAPTER 5 STORMWATER DRAINAGE SYSTEM DESIGN. Table of Contents SECTION 5.1 STORMWATER DRAINAGE DESIGN OVERVIEW

CHAPTER 5 STORMWATER DRAINAGE SYSTEM DESIGN. Table of Contents SECTION 5.1 STORMWATER DRAINAGE DESIGN OVERVIEW CHAPTER 5 STORMWATER DRAINAGE SYSTEM DESIGN Table of Contents SECTION 5.1 STORMWATER DRAINAGE DESIGN OVERVIEW 5.1.1 Stormwater Drainage System Design...5-1 5.1.1.1 Introduction...5-1 5.1.1.2 Drainage System

More information

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge

More information

Floodplain Hydraulics! Hydrology and Floodplain Analysis Dr. Philip Bedient

Floodplain Hydraulics! Hydrology and Floodplain Analysis Dr. Philip Bedient Floodplain Hydraulics! Hydrology and Floodplain Analysis Dr. Philip Bedient Open Channel Flow 1. Uniform flow - Manning s Eqn in a prismatic channel - Q, V, y, A, P, B, S and roughness are all constant

More information

City of West Linn Public Works Design Standards 2010. Table of Contents

City of West Linn Public Works Design Standards 2010. Table of Contents City of West Linn Public Works Design Standards Table of Contents SECTION TWO STORM DRAIN REQUIREMENTS... 1 2.0000 STORM DRAINS... 1 2.0010 General Design Requirements...1 2.0011 Site Drainage Plans...2

More information

CONDITIONAL LETTER OF MAP REVISION US-34A and US-34D PERMANENT FLOOD REPAIRS

CONDITIONAL LETTER OF MAP REVISION US-34A and US-34D PERMANENT FLOOD REPAIRS CONDITIONAL LETTER OF MAP REVISION US-34A and US-34D PERMANENT FLOOD REPAIRS June 25, 2014 REVISED 8/26/2014 Prepared for: Colorado Department of Transportation, Region 4 20068, PR 0342-057 Submitted to:

More information

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 This page intentionally left blank. PAGE 34 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN ASSET INVENTORY

More information

How To Fix A Flood Control System In South Lakewood

How To Fix A Flood Control System In South Lakewood Cedar and South Street Area Flood Remediation Project Upstream Watersheds 1 Cross Section Locations HEC-RAS Model Cross Sections 25-year Flood Limits 10-year and 25-year event between 1 or 2 year event

More information

What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation)

What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation) OPEN CHANNEL FLOW 1 3 Question What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation) Typical open channel shapes Figure

More information

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND

ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND The Rose Creek Watershed (RCW) consists of three planning

More information

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow 2F-2 Open Channel Flow A. Introduction The beginning of any channel design or modification is to understand the hydraulics of the stream. The

More information

Chapter 4 Hydraulic Design of Open Channels, Culverts, Bridges, and Detention Structures

Chapter 4 Hydraulic Design of Open Channels, Culverts, Bridges, and Detention Structures Table of Contents CHAPTER 4 Chapter 4 Hydraulic Design of Open Channels, Culverts, Bridges, and Detention Structures 4.1 Storm Water Open Channels, Culverts, Bridges, and Detention Structure Design Overview

More information

Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M.

Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Fort Dodge Stormwater Master Planning Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Project Location Project Background Flooding History Localized flooding and storm sewer

More information

Lower Breton Sound Sediment Diversion Conceptual Engineering Design Presentation

Lower Breton Sound Sediment Diversion Conceptual Engineering Design Presentation EXPERT PANEL ON DIVERSION PLANNING AND IMPLEMENTATION Lower Breton Sound Sediment Diversion Conceptual Engineering Design Presentation February 12, 2015 Topics I. Introduction II. Geotechnical Study III.

More information

Bridge Type Selection

Bridge Type Selection Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when

More information

Experiment (13): Flow channel

Experiment (13): Flow channel Introduction: An open channel is a duct in which the liquid flows with a free surface exposed to atmospheric pressure. Along the length of the duct, the pressure at the surface is therefore constant and

More information

Procedures for No-Rise Certification For Proposed Developments in the Regulatory Floodway

Procedures for No-Rise Certification For Proposed Developments in the Regulatory Floodway US Department of Homeland Security Region X 130 228 th Street, SW Bothell, WA 98021 Procedures for No-Rise Certification For Proposed Developments in the Regulatory Floodway Section 60.3 (d) (3) of the

More information

CHAPTER 5. Storm Sewer

CHAPTER 5. Storm Sewer CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water

More information

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section: . Introduction Presented in this chapter are the criteria and methodology for design and evaluation of storm sewer inlets located in Town of Castle Rock. The review of all planning submittals will be based

More information

ESI Consultants, Ltd. PROJECT EXPERIENCE

ESI Consultants, Ltd. PROJECT EXPERIENCE CRAWFORD COUNTY, ILLINOIS NBIS Program Manager and Bridge Inspection services provided for 123 structures throughout Crawford County. Routine Maintenance/Safety Inspection of existing bridges was performed

More information

Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE

Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE Frequently-Asked Questions about Floodplains and Flood Insurance What is a floodplain? The floodplain is any area covered by water during normal water flows, and which could be inundated as a result of

More information

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used:

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used: Lecture 24 Flumes & Channel Transitions I. General Characteristics of Flumes Flumes are often used: 1. Along contours of steep slopes where minimal excavation is desired 2. On flat terrain where it is

More information

CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL SECTION 800 STORM SEWER SYSTEMS TABLE OF CONTENTS

CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL SECTION 800 STORM SEWER SYSTEMS TABLE OF CONTENTS CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL SECTION 800 STORM SEWER SYSTEMS TABLE OF CONTENTS 801 INTRODUCTION 803 802 DESIGN PARAMETERS 804 802.1 - Allowable

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

ALAN BRUBAKER, P.E., P.S. SUMMIT COUNTY ENGINEER

ALAN BRUBAKER, P.E., P.S. SUMMIT COUNTY ENGINEER ALAN BRUBAKER, P.E., P.S. SUMMIT COUNTY ENGINEER STORMWATER DRAINAGE MANUAL Revised March 6, 2013 Revised February 7, 2013 Performance Requirements Part 1 Summit County Engineer Stormwater Drainage Manual

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

University of MT Helena College of Technology Helena, MT July 21, 2010. Image Courtesy Watershed Sciences, Inc.

University of MT Helena College of Technology Helena, MT July 21, 2010. Image Courtesy Watershed Sciences, Inc. University of MT Helena College of Technology Helena, MT July 21, 2010 Image Courtesy Watershed Sciences, Inc. WELCOME INTRODUCTIONS Image Courtesy Watershed Sciences, Inc. Target Audience: Engineers,

More information

Using Hydraflow Storm Sewers Extension with AutoCAD Civil 3D 2008: A Recommended Workflow

Using Hydraflow Storm Sewers Extension with AutoCAD Civil 3D 2008: A Recommended Workflow AutoCAD Civil 3D 2008 Using Hydraflow Storm Sewers Extension with AutoCAD Civil 3D 2008: A Recommended Workflow The ability to perform storm water hydrology and hydraulic (H&H) tasks is crucial to civil

More information

Federal Emergency Management Agency Region IV 3003 Chamblee-Tucker Road Atlanta, GA 30341

Federal Emergency Management Agency Region IV 3003 Chamblee-Tucker Road Atlanta, GA 30341 Federal Emergency Management Agency Region IV 3003 Chamblee-Tucker Road Atlanta, GA 30341 GUIDANCE FOR "NO-RISE / NO-IMPACT" CERTIFICATION FOR PROPOSED DEVELOPMENTS IN REGULATORY FLOODWAYS The National

More information

Lincoln County Floodplain Development Permit Application

Lincoln County Floodplain Development Permit Application Lincoln County Floodplain Development Permit Application Application # FP Use Permit Variance Appeal Date SECTION I: GENERAL PROVISIONS (APPLICANT to read and sign) 1. No work of any kind may start until

More information

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

TENNESSEE GAS PIPELINE COMPANY, L.L.C. TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC & HYDRAULIC CALCULATIONS FOR WATERBODIES CROSSED BY CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,

More information

CITY OF COLTON PUBLIC WORKS/ENGINEERING DEPARTMENT STORM DRAIN PLAN REVIEW CHECKLIST (PROVIDE SEPARATE ON-SITE & OFF-SITE STORM DRAIN PLAN SETS)

CITY OF COLTON PUBLIC WORKS/ENGINEERING DEPARTMENT STORM DRAIN PLAN REVIEW CHECKLIST (PROVIDE SEPARATE ON-SITE & OFF-SITE STORM DRAIN PLAN SETS) CITY OF COLTON PUBLIC WORKS/ENGINEERING DEPARTMENT STORM DRAIN PLAN REVIEW LIST (PROVIDE SEPARATE ON-SITE & OFF-SITE STORM DRAIN PLAN SETS) PROJECT NAME: TRACT, PARCEL MAP OR PROJECT ID NO. PLAN ED BY:

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Policy: This policy will replace all previous policies regarding the selection of pipe material for cross drains, drive pipe, drop pipe, storm

More information

Criteria for Appeals of Flood Insurance Rate Maps

Criteria for Appeals of Flood Insurance Rate Maps Criteria for Appeals of Flood Insurance Rate Maps November 30, 2011 This document outlines the criteria for appealing proposed changes in flood hazard information on Flood Insurance Rate Maps (FIRMs)

More information

Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978)

Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978) Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978) I. An Example Culvert Design Design a concrete culvert using the

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

CHAPTER 860 OPEN CHANNELS

CHAPTER 860 OPEN CHANNELS HIGHWAY DESIGN MANUAL 860-1 CHAPTER 860 OPEN CHANNELS Topic 861 - General Index 861.1 - Introduction An open channel is a conveyance in which water flows with a free surface. Although closed conduits such

More information

INTEROFFICE MEMORANDUM DATE: October 15, 1997. Special Provisions for Construction in Special Flood Hazard Areas

INTEROFFICE MEMORANDUM DATE: October 15, 1997. Special Provisions for Construction in Special Flood Hazard Areas INTEROFFICE MEMORANDUM DATE: October 15, 1997 TO: FROM: SUBJECT: Staff Design Engineers, Roadway Design Division Brooks Booher, Staff Hydraulic Engineer Special Provisions for Construction in Special Flood

More information

Drainage DR-701. Materials Field Sampling. Purpose of the Guidance Manual. General DR 701-1

Drainage DR-701. Materials Field Sampling. Purpose of the Guidance Manual. General DR 701-1 DR-701 Chapter Materials Field Sampling Drainage Subject INLETS INTRODUCTION & STORM SEWERS General Purpose of the Guidance Manual DR 701-1 STORM SEWER DEFINITION KYTC defines a storm sewer as two or more

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

2D Modeling of Urban Flood Vulnerable Areas

2D Modeling of Urban Flood Vulnerable Areas 2D Modeling of Urban Flood Vulnerable Areas Sameer Dhalla, P.Eng. Dilnesaw Chekol, Ph.D. A.D. Latornell Conservation Symposium November 22, 2013 Outline 1. Toronto and Region 2. Evolution of Flood Management

More information

STORMWATER MANAGEMENT CHECKLIST

STORMWATER MANAGEMENT CHECKLIST STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative

More information

City of La Quinta Public Works Department - Storm Drain Plan Review Checklist

City of La Quinta Public Works Department - Storm Drain Plan Review Checklist Tract or Parcel Project Name PCN Checked By Date City of La Quinta Public Works Department - Storm Drain Plan Review Checklist SUBMITTAL REQUIREMENTS Approved Tentative Tract Map Conditions of Approval

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within

More information

TABLE OF CONTENTS. Section / Article Page

TABLE OF CONTENTS. Section / Article Page TABLE OF CONTENTS Section / Article Page 1. INTRODUCTION 1.1 Purpose................ 6 1.2 Definitions................ 6 1.3 Guidelines and References............ 7 2. AGREEMENTS 2.1 Applicant and Contractor

More information

LIMITED SCOPE CONCEPT DEVELOPMENT REPORT

LIMITED SCOPE CONCEPT DEVELOPMENT REPORT LIMITED SCOPE CONCEPT DEVELOPMENT REPORT Route 33 Resurfacing Project Eastbound: Milepost 24.2 to Milepost 28.9 Westbound: Milepost 24.3 to Milepost 28.9 Manalapan & Freehold Townships, Monmouth County

More information

PRECAST CONCRETE BOX CULVERTS

PRECAST CONCRETE BOX CULVERTS PRECAST CONCRETE BOX CULVERTS OUTLINE Introduction Applications Manufacturing Methods Design Procedures & Joints Installation Quality Summary INTRODUCTION Four-sided culverts are typically referred to

More information

HEC-RAS. River Analysis System. Applications Guide. Version 4.1 January 2010. US Army Corps of Engineers Hydrologic Engineering Center CPD-70

HEC-RAS. River Analysis System. Applications Guide. Version 4.1 January 2010. US Army Corps of Engineers Hydrologic Engineering Center CPD-70 US Army Corps of Engineers Hydrologic Engineering Center HEC-RAS HEC-RAS River Analysis System Applications Guide Version 4.1 January 2010 Approved for Public Release. Distribution Unlimited CPD-70 REPORT

More information

Drainage Design and Stormwater Pollution Prevention Manual

Drainage Design and Stormwater Pollution Prevention Manual , Texas Drainage Design and Stormwater Pollution Prevention Manual 2001 Teague Nall and Perkins, Inc. Engineers Consultants Fort Worth Irving Denton CITY OF DESOTO DRAINAGE DESIGN AND STORM WATER POLLUTION

More information

5.14 Floodplains and Drainage/Hydrology

5.14 Floodplains and Drainage/Hydrology I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important

More information

Section 3. HYDRAULIC DESIGN A. Weirs and Orifices

Section 3. HYDRAULIC DESIGN A. Weirs and Orifices Section 3. HYDRAULIC DESIGN A. Weirs and Orifices NOTE: Some of the graphs contained in this section are copied from the Los Angeles Hydraulics Manual and we wish to give them credit for their efforts.

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

National Bridge Inspection Standards (NBIS) Metrics

National Bridge Inspection Standards (NBIS) Metrics Table of Contents National Bridge Inspection Standards (NBIS) Metrics NATIONAL BRIDGE INSPECTION STANDARDS (NBIS) METRICS TABLE OF CONTENTS...1 Metric #1: 23 CFR 650.307 Bridge inspection organization...2

More information

UNION COUNTY, FLORIDA AND INCORPORATED AREAS

UNION COUNTY, FLORIDA AND INCORPORATED AREAS UNION COUNTY, FLORIDA AND INCORPORATED AREAS COMMUNITY NAME COMMUNITY NUMBER LAKE BUTLER, CITY OF 120595 RAIFORD, TOWN OF 120593 UNION COUNTY 120422 (UNINCORPORATED AREAS) WORTHINGTON SPRINGS, CITY OF

More information

Guide To Bridge Planning Tools

Guide To Bridge Planning Tools Guide To Bridge Planning Tools The following bridge planning and hydrotechnical analysis tools (Excel spreadsheets, some with associated databases and VBA code), and GIS data-sets are available from the

More information

Shooks Run Drainage Study Basic Terminology

Shooks Run Drainage Study Basic Terminology Shooks Run Drainage Study Basic Terminology PREPARED FOR: PREPARED BY: City of Colorado Springs CH2M DATE: April 9, 2015 Introduction This document is intended to provide an introduction to Colorado Springs

More information

Quality Control and Quality Assurance Guide

Quality Control and Quality Assurance Guide Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...

More information

COMPUTATIONAL FLOW MODEL OF WESTFALL'S 4000 OPEN CHANNEL MIXER 411527-1R1. By Kimbal A. Hall, PE. Submitted to: WESTFALL MANUFACTURING COMPANY

COMPUTATIONAL FLOW MODEL OF WESTFALL'S 4000 OPEN CHANNEL MIXER 411527-1R1. By Kimbal A. Hall, PE. Submitted to: WESTFALL MANUFACTURING COMPANY COMPUTATIONAL FLOW MODEL OF WESTFALL'S 4000 OPEN CHANNEL MIXER 411527-1R1 By Kimbal A. Hall, PE Submitted to: WESTFALL MANUFACTURING COMPANY FEBRUARY 2012 ALDEN RESEARCH LABORATORY, INC. 30 Shrewsbury

More information

Scour and Scour Protection

Scour and Scour Protection Design of Maritime Structures Scour and Scour Protection Steven A. Hughes, PhD, PE Coastal and Hydraulics Laboratory US Army Engineer Research and Development Center Waterways Experiment Station 3909 Halls

More information

SECTION 5 DRAFTING STANDARDS

SECTION 5 DRAFTING STANDARDS SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.

More information

Design Charts for Open-Channel Flow HDS 3 August 1961

Design Charts for Open-Channel Flow HDS 3 August 1961 Design Charts for Open-Channel Flow HDS 3 August 1961 Welcome to HDS 3-Design Charts for Open-Channel Flow Table of Contents Preface DISCLAIMER: During the editing of this manual for conversion to an electronic

More information

Chapter 9. Steady Flow in Open channels

Chapter 9. Steady Flow in Open channels Chapter 9 Steady Flow in Open channels Objectives Be able to define uniform open channel flow Solve uniform open channel flow using the Manning Equation 9.1 Uniform Flow in Open Channel Open-channel flows

More information

STORMWATER DESIGN CRITERIA MANUAL

STORMWATER DESIGN CRITERIA MANUAL STORMWATER DESIGN CRITERIA MANUAL SEPTEMBER 2007 COMMUNITY DEVELOPMENT DEPARTMENT City of Weatherford, Texas TABLE OF CONTENTS Foreword.... 3 Storm Water Management Policy.... 4 Definitions.... 5 1. Preliminary

More information

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)

More information

M6a: Open Channel Flow (Manning s Equation, Partially Flowing Pipes, and Specific Energy)

M6a: Open Channel Flow (Manning s Equation, Partially Flowing Pipes, and Specific Energy) M6a: Open Channel Flow (, Partially Flowing Pipes, and Specific Energy) Steady Non-Uniform Flow in an Open Channel Robert Pitt University of Alabama and Shirley Clark Penn State - Harrisburg Continuity

More information

Section 5 Floodplain Management Tools

Section 5 Floodplain Management Tools 5.1 Floodprone Areas One of the major elements of the Master Plan is the updated 100-year floodplain and floodway boundary maps. This information provided the most up-to-date tools to protect homes and

More information

Town of Hingham. Changes to Flood Insurance Rate Maps and Flood Insurance Costs Frequently Asked Questions

Town of Hingham. Changes to Flood Insurance Rate Maps and Flood Insurance Costs Frequently Asked Questions Town of Hingham 1. What is a floodplain? Changes to Flood Insurance Rate Maps and Flood Insurance Costs Frequently Asked Questions A floodplain is an area of land where water collects, pools and flows

More information

SECTION 5 - STORM DRAINS

SECTION 5 - STORM DRAINS Drainage Criteria Manual SECTION 5 - STORM DRAINS 5.1.0 GENERAL This The purpose of this section discusses briefly is to consider the hydraulic aspects of storm drains and their appurtenances in a storm

More information

FEMA Flood Zone Designations

FEMA Flood Zone Designations Note: SFHA "Special Flood Hazard Area" FEMA Flood Zone Designations Zone VE Zone A Zone AE Zone X Zone X500 UNDES along coasts subject to inundation by the 100-year flood with additional hazards due to

More information

Sharp-Crested Weirs for Open Channel Flow Measurement, Course #506. Presented by:

Sharp-Crested Weirs for Open Channel Flow Measurement, Course #506. Presented by: Sharp-Crested Weirs for Open Channel Flow Measurement, Course #506 Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.com A weir is basically an obstruction in an open channel

More information

ITD Pipe Materials Selection & Specification Procedures. July 2011

ITD Pipe Materials Selection & Specification Procedures. July 2011 ITD Pipe Materials Selection & Specification Procedures July 2011 INTRODUCTION: This technical memorandum is written as a guide to the selection of compliant pipe materials and the elimination of non-compliant

More information

CHAPTER 7 ROAD STORM DRAINAGE SYSTEMS

CHAPTER 7 ROAD STORM DRAINAGE SYSTEMS CHAPTER 7 ROAD STORM DRAINAGE SYSTEMS Note: All questions and comments should be directed to the Hydraulics Unit Supervisor, Environmental Services Section. Revised November 2015 Road Storm Drainage Systems

More information

Montgomery County Government. Drainage Design Criteria. Department of Transportation. November 2013 Rockville, Maryland

Montgomery County Government. Drainage Design Criteria. Department of Transportation. November 2013 Rockville, Maryland Government Drainage Design Criteria November 2013 Rockville, Maryland Revised Final TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 PURPOSE OF THE DRAINAGE DESIGN CRITERIA... 1 1.2 LAWS ORDINANCES AND POLICIES...

More information

OHIO ENGINEERING JOB APPROVAL AUTHORITY ETHICS STATEMENT

OHIO ENGINEERING JOB APPROVAL AUTHORITY ETHICS STATEMENT Sheet 1 of 9 NAME TITLE GRADE LOCATION DELEGATED BY (Responsible Engineer) TITLE DATE 210-NEM-501-A, Third Ed., Amend. OH1, February 2015 CONCURRED BY (Line Supervisor) (non-nrcs) TITLE DATE TITLE ETHICS

More information

Appendix F Benefit-Cost Analysis of Flood Protection Measures

Appendix F Benefit-Cost Analysis of Flood Protection Measures Appendix F Benefit-Cost Analysis of Flood Protection Measures Acronyms used in Appendix F: AA B AA C AA D BC BFE EAD FEMA NED O&M PV RED USACE Average Annual Benefits Average Annual Cost Average Annual

More information

River Analysis System HEC-RAS

River Analysis System HEC-RAS Hydrologic Engineering Center River Analysis System HEC-RAS Release Notes Version 4.1 January 2010 Approved for Public Release Distribution Unlimited 1 Introduction Version 4.1 of the River Analysis System

More information

Topic 8: Open Channel Flow

Topic 8: Open Channel Flow 3.1 Course Number: CE 365K Course Title: Hydraulic Engineering Design Course Instructor: R.J. Charbeneau Subject: Open Channel Hydraulics Topics Covered: 8. Open Channel Flow and Manning Equation 9. Energy,